SlideShare a Scribd company logo
1 of 26
Download to read offline
NEW YORK-NEW JERSEY
HARBOR AND TRIBUTARIES
COASTAL STORM RISK
MANAGEMENT STUDY
Briefing to Jamaica Bay Task Force
November 17, 2022
6:30-8:30 PM, ET
New York District
2
DRAFT REPORT
Found at https://www.nan.usace.army.mil/NYNJHATS
3
NON-FEDERAL PARTNERS
4
NEW YORK-NEW JERSEY HARBOR AND TRIBUTARIES
COASTAL STORM RISK MANAGEMENT FEASIBILITY STUDY
STUDY AREA
• The largest and most densely populated of the 9 NACCS Focus Areas
• Area covers 2,150+ square miles and 900+ miles of affected shoreline
• 25 counties in New York & New Jersey
• Affected population of roughly 16 million people, including New York City and the six most
populated cities in New Jersey
COASTAL STORM RISKS & DAMAGES
• Significant Life/Safety Risk and over 275,000 Structures in Potential Impact Area
• Incorporates Dozens of Other Ongoing and Planned CSRM Projects in Study Area
• Present Value Damages for 100-Year Storm Range from $100+B for Intermediate Sea Level
Rise to over $350B for High Sea Level Rise Projection
STUDY SCOPE
• Study Cost: $19.4M, cost-shared 50/50 with NYSDEC and NJDEP thru July 2022, and
100% federal thereafter.
• Study Schedule: Assistant Secretary of the Army for Civil Works Approved (7 Apr 21)
Second Exemption for Study Extension to 2024 Completion
• Funding: Federal funding ($1.45M) resumed in October 2021 following lapses in fiscal years
2020 and 2021. Study also received $6,724,000 of DRSAA funds.
• Study Scope: WRDA 2020 includes study specific language
STUDY SCHEDULE
• Draft Feasibility Report and integrated Tier 1 Environmental Impact Statement Released for
extended public day review with meetings planned throughout area (comment closing date
January 6, 2023). Virtual meetings starting October 24th, 27th and November 5th.
• See WWW.NAN.USACE.ARMY.MIL/NYNJHATS for dates, times and locations of public in-
person meetings in November and December.
• Final Chief of Engineers Report Approved to be Completed in June 2024
5
ALTERNATIVE PLANS – PROS & CONS WITH EACH
Alternative 1: No action
Alternative 2: Harbor-wide storm surge barrier + shore-based
measures
Alternative 3A: Multi-basin storm surge barriers + shore-based
measures
Alternative 3B: Multi-basin storm surge barriers + shore-based
measures
Alternative 4: Single-basin storm surge barriers + shore-based
measures
Alternative 5: Shore-based measures only
• Alternatives span spectrum from large in-water storm surge gates to
numerous shoreline-based structures. Alternatives also have (or will
have) complementary non-structural and natural and nature-based
features (where feasible).
• Best Solution Appears to Involve Multiple, Layered Features
• Possible Phased Implementation:
1) Short-term: Construct Actionable Features,
2) Mid-Term: Further Evaluate, Design and possibly Construct
Complex Features,
3) Long-Term: Adapt and expand features due to further sea level rise
and climate change
6
FUTURE WITHOUT-PROJECT (FWOP) CONDITION
Assumptions
• Investments in coastal storm risk
management / resiliency projects will
continue
– Federal, state, local government
investment
– Private investment
• Relative sea level rise over time
– Used USACE intermediate projection
for comparing plans in Draft Report
– Considering ALL USACE sea level
rise projections in future study plan
formulation
1% flood extent (with intermediate RSLC)
7
OTHER CONSTRUCTED AND ONGOING PROJECTS (BLUE) ASSUMED AS PART
OF FUTURE BASELINE CONDITION
8
USACE RELATIVE SEA LEVEL CHANGE AT BATTERY
COMPARED TO STATES AND CITY PROJECTIONS
Economic Period
of Analysis
Planning Horizon
Base
Year
2044
Study
Authorization
and
Design
Construction
Operation, Maintenance and Adaptation (if/as warranted)
9
COMPOSITE: ALTERNATIVE PLANS SHOWING STORM SURGE
BARRIER LOCATIONS CONSIDERED
Alternative 2
Alternative 3B
Alternative 3A
Alternative 4
• All alternative plans will
include nonstructural
measures, as feasible, for
areas with unaddressed
coastal storm risk
• All alternative plans will
include natural and nature-
based features where
applicable and feasible
Alternative 5 (shore-based
measures only) not shown in
figure
10
PROJECT COSTS (INTERMEDIATE RSLC)
Alternative
Construction
Duration
(years)
Years of
Full
Benefits*
First Costs
(not including
contingency)
Contingency
OMRR&R and
IDC (PV)
Total
(Present
Value)**
2 32 32 $70.6B $41.7B $37.3B $150.2B
3A 24 40 $48.9B $28.0B $18.7B $95.7B
3B 14 50 $35.6B $17.1B $23.5B $76.2B
4 14 50 $28.8B $14.2B $19.4B $62.5B
5 5 50 $10.1B $5.9B $9.8B $25.8B
* - USACE policy only allows a maximum of 50 years of benefits in the economic evaluation, but the alternatives and
measures are planned for permanent implementation with an at least one-hundred-year planning horizon
** - Adaptation costs for higher sea level rise projections are under refinement and have not been included in the
total cost estimates at this time
11
PROJECT BENEFITS & COSTS – ON AN AVERAGE
ANNUAL BASIS (INTERMEDIATE RSLC)
Alternative
Average
Annual Cost
Average
Annual Benefits*
Net Benefits* Benefit to Cost Ratio
2 $5.0B $4.6B -$0.5B 0.91
3A $3.2B $6.4B $3.2B 1.99
3B $2.6B $6.3B $3.7B 2.45
4 $2.1B $5.0B $2.9B 2.39
5 $0.9B $1.9B $1.0B 2.21
* Benefits currently based on estimated damages avoided to structures in study area. Critical infrastructure and
other possible benefits under refinement and have not been included in the net benefit calculations at this time.
12
ALTERNATIVE 3B – THE TENTATIVELY SELECTED PLAN
62.75% Study Area at
Direct Risk Benefited
Alternative 3B includes:
• Jamaica Bay and Southern
Brooklyn Storm Surge Gate
and Shoreline-based Measures
• Kill Van Kull and Arthur Kill
Storm Surge Gates with
Shoreline-based tie-ins
• Storm Surge Gates and
Shoreline-based tie-ins for
Gowanus, Newtown and
Flushing Creeks
• Shoreline-based measures
for Lower Manhattan, East
Harlem, and Jersey City
• Numerous other
complementary structural, non-
structural, and NNBFs (not
shown here) to complement
measures listed above and
better manage remaining
residual
risk (many under
development & evaluation)
13
ADDITIONAL CONSIDERATIONS WITH STORM-SURGE BARRIERS – RISK
REDUCTION FEATURES AND INDUCED FLOODING-MITIGATION FEATURES
Risk Reduction
Features BEHIND the
Storm Surge Barriers
Induced Flooding-
Mitigation Features (as
applicable) OUTSIDE the
Storm Surge Barriers
14
TENTATIVELY SELECTED PLAN FEATURE IN DETAIL
Note
Induced
Flooding-
Mitigation
Features
Outside of
Storm Surge
Barrier
Note Risk
Reduction
Features behind
Storm Surge
Barrier
South Brooklyn and Jamaica Bay Area
15
Jamaica Bay Storm Surge Barrier:
2 – 200 foot wide Sector Gates
15 Auxiliary Lift Gates
Total Length in Water: 3,800 feet
Crest elevation*: 18 feet (NAVD88)
Sheepshead Bay Storm Surge Barrier:
100 foot wide Sector Gate
2 Auxiliary Lift Gates
Total Length in Water: 800 feet
Crest elevation*: 17 feet (NAVD88)
Gerritsen Creek Storm Surge Barrier:
115 foot wide Vertical Lift Gate
2 Auxiliary Lift Gates
Total Length in Water: 400 feet
Crest elevation*: 17 feet (NAVD88)
Shoreline-Based Tie-In’s:
Total Length: 116,000+ feet
Measures include: Floodwalls, levees, reinforced
dunes, pedestrian and vehicle gates, elevated
promenades, seawalls, and tide gates
SOUTH BROOKLYN SHORELINE-BASED MEASURES AND JAMAICA
BAY STORM SURGE BARRIER
* - For currently selected design storm event
16
• Layout and measures are conceptual and
preliminary.
• Risk reduction features are designed to address
more frequent coastal flooding in red shaded
areas to complement shoreline-based
measures and storm surge barriers in southern
Brooklyn and Queens encompassing Jamaica
Bay that address more severe coastal flooding
for broader green shaded area.
• Elevation of risk reduction features currently
targeted for +10 ft. NAVD88, with assumed +7
ft. NAVD88 closure criteria for the main Jamaica
Bay storm surge barriers (all elevations
correlated to water elevation predictions at the
Battery – for commonality), but this may change
in terms of elevation, layout, and measures from
further evaluation and optimization of main
storm surge closure gate operation criteria.
RISK REDUCTION FEATURE DETAILS
17
RISK REDUCTION FEATURE DETAIL – FRESH CREEK BASIN
• Shoreline-based features only –
floodwalls (along E 108th St)
and revetments at select
shoreline areas
18
OLD HOWARD BEACH & HAMILTON
BEACH RISK REDUCTION FEATURES
• Currently comprised of berms,
floodwalls and navigable gates
• The gate structures have not been
selected or designed – they could be
sector gates, vertical lift gates or
other type of navigable structural
measure.
• They would need further considerable
environmental and engineering
evaluation.
19
RISK REDUCTION FEATURES – BROAD CHANNEL AREA
• Currently comprised of berms,
bulkheads and road raisings
• They would need further considerable
environmental and engineering
evaluation.
20
RISK REDUCTION FEATURES – HEAD OF BAY
• Currently comprised of
berms, bulkheads,
deployable flood
barriers, floodwalls and
navigable gates.
• The gate structures
have not been selected
or designed – they
could be sector gates,
vertical lift gates or
other type of navigable
structural measure.
• They would need
further considerable
environmental and
engineering evaluation.
21
DRAFT TIER 1 EIS: REPORT ORGANIZATION
Review Aid: StoryMap https://hats-cenan.hub.arcgis.com/
ENVIRONMENTAL CONSEQUENCES
Potential for Adverse Impacts by Measure
Type
Chapter 6
• Defining Tier 1 Scope of Direct, Indirect, and
Cumulative Impacts - BROADLY
• Estimating Beneficial Environmental Effects
(“+”)
• Estimating In-Kind Mitigated Impacts
• Identifying Out-Of-Kind Mitigated Impacts
• Incorporating Cooperating Agency and
Stakeholder Input
ENVIRONMENTAL CONSEQUENCES
Applied Scoring Methodology
Chapter 6
EXISTING CONDITIONS
Chapter 2
- 50 environmental resources assessed
- Organized by Planning Region - Draft Tier 1 assesses Structural Measures only
- Final Tier 1 will also assess ringwalls, nonstructural, and Natural and Nature-Based Features
22
WANT TO LEARN MORE?
Start Here
CONNECT WITH THE STUDY TEAM
Email: NYNJHarbor.TribStudy@usace.army.mil
Mail: Mr. Bryce W. Wisemiller, Project Manager Ms. Cheryl R. Alkemeyer, NEPA Lead
U.S. Army Corps of Engineers New York District U.S. Army Corps of Engineers New York District
Jacob K. Javits Federal Building, Room 17-401 Jacob K. Javits Federal Building, Room 17-420
c/o PSC Mail Center c/o PSC Mail Center
26 Federal Plaza 26 Federal Plaza
New York, New York 10278 New York, New York 10278
WWW.NAN.USACE.ARMY.MIL/NYNJHATS
23
SCHEDULE
Action/Milestone Date
Execute Feasibility Cost-Sharing Agreement (study start) ✅ 15 July 2016
Release Interim Report ✅ 19 February 2019
Public Meetings for Interim Report ✅ March - October 2019
Delay due to lack of Federal funding ✅ February 2020 – September 2021
Federal funding resumption ✅ October 2021
FCSA Amendment Execution ✅ 28 June 2022
Tentatively Selected Plan Milestone ✅ 26 July 2022
Release Draft Integrated Feasibility Report and Tier 1 EIS ✅ Late September 2022 (90+ day
review period)
Public Meetings for Draft Report
October – December 2022 (In-person and
additional virtual public meetings in
November-December. Locations TBD.)
Public Comment Closing Date January 6, 2023
Agency Decision Milestone April 2023
Submit Final Integrated Feasibility Report and Tier 1 EIS January 2024*
Chief of Engineer’s Report Approval (study end) June 2024*
* Schedule may be revised due to actual federal funding resumption shift in 2022
24
• The Tentatively Selected Plan (Alternative 3B) is preliminary and conceptual
– Considerable work remains to be done
– Future work will be informed by and focus on issues raised by the public and agencies
• There are many resources on the study website https://www.nan.usace.army.mil/NYNJHATS
– Draft Integrated Feasibility Report and integrated Tier 1 Environmental Impact Statement
– Readers Guide
– StoryMap Hub
• This is one of a series of public meetings
– There will be in-person and additional virtual public meetings
– Meeting information will be posted to the study website and shared via email
• Your feedback is an important part of the study process
IN SUMMARY
25
YOUR FEEDBACK IS IMPORTANT
The Study Team is here today to answer your questions and hear your feedback
Written Comments
• Send all written comments for the record via email or mail
• The public comment period closes January 6, 2023
Mr. Bryce W. Wisemiller, Project Manager
U.S. Army Corps of Engineers New York District
Jacob K. Javits Federal Building, Room 17-401
c/o PSC Mail Center
26 Federal Plaza
New York, New York 10278
917-790-8307
nynjharbor.tribstudy@usace.army.mil
More Opportunities to Provide Feedback
• There will be in-person and additional virtual public meetings
• Meeting information will be posted to the study website and shared via email
Ms. Cheryl R. Alkemeyer, NEPA Lead
U.S. Army Corps of Engineers New York District
Jacob K. Javits Federal Building, Room 17-420
c/o PSC Mail Center
26 Federal Plaza
New York, New York 10278
917-790-8723
nynjharbor.tribstudy@usace.army.mil
26
QUESTIONS?

More Related Content

Similar to NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf

Jamaica Bay Task Force2- 10May22.pdf
Jamaica Bay Task Force2- 10May22.pdfJamaica Bay Task Force2- 10May22.pdf
Jamaica Bay Task Force2- 10May22.pdfecowatchers
 
Sea Level Rise and Storm Surge Plans
Sea Level Rise and Storm Surge Plans Sea Level Rise and Storm Surge Plans
Sea Level Rise and Storm Surge Plans Bill Kovarik
 
Municipal Adaptations to Create Resilient Beach Communities
Municipal Adaptations to Create Resilient Beach CommunitiesMunicipal Adaptations to Create Resilient Beach Communities
Municipal Adaptations to Create Resilient Beach CommunitiesSMRPC
 
Mitigation symposium - Andre Corbould
Mitigation symposium - Andre CorbouldMitigation symposium - Andre Corbould
Mitigation symposium - Andre CorbouldYourAlberta
 
Staff Presentation 080311 Gtg
Staff Presentation 080311 GtgStaff Presentation 080311 Gtg
Staff Presentation 080311 GtgGreg Gearheart
 
SMP_FinalPublicMeeting_FINAL_083022.pptx
SMP_FinalPublicMeeting_FINAL_083022.pptxSMP_FinalPublicMeeting_FINAL_083022.pptx
SMP_FinalPublicMeeting_FINAL_083022.pptxJohnathanSHill
 
SMP_FinalPublicMeeting_FINAL_083022.pptx
SMP_FinalPublicMeeting_FINAL_083022.pptxSMP_FinalPublicMeeting_FINAL_083022.pptx
SMP_FinalPublicMeeting_FINAL_083022.pptxJohnathanSHill
 
LCW Restoration Plan & EIR- Public Workshop #2
LCW Restoration Plan & EIR- Public Workshop #2LCW Restoration Plan & EIR- Public Workshop #2
LCW Restoration Plan & EIR- Public Workshop #2TidalInlfluence
 
Key aspects of reservoir evaluation for deep water reservoirs
Key aspects of reservoir evaluation for deep water reservoirsKey aspects of reservoir evaluation for deep water reservoirs
Key aspects of reservoir evaluation for deep water reservoirsM.T.H Group
 
ACOE Reformulation study for Jamaica Bay
ACOE Reformulation study for Jamaica BayACOE Reformulation study for Jamaica Bay
ACOE Reformulation study for Jamaica Bayecowatchers
 
Greg Cademartori Great Marsh Symposium
Greg Cademartori Great Marsh SymposiumGreg Cademartori Great Marsh Symposium
Greg Cademartori Great Marsh Symposiumgreenbelt82
 
Baron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdfBaron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdfecowatchers
 
Cademartori great marshsymposium-1
Cademartori great marshsymposium-1Cademartori great marshsymposium-1
Cademartori great marshsymposium-1greenbelt82
 
Urban Runoff - Storm Water 101
Urban Runoff - Storm Water 101Urban Runoff - Storm Water 101
Urban Runoff - Storm Water 101Greg Gearheart
 
Hurricane Impact Preparedness and Resilient by Nature Recovery
Hurricane Impact Preparedness and Resilient by Nature RecoveryHurricane Impact Preparedness and Resilient by Nature Recovery
Hurricane Impact Preparedness and Resilient by Nature RecoveryMarco Pluijm
 

Similar to NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf (20)

7436 2
7436 27436 2
7436 2
 
Jamaica Bay Task Force2- 10May22.pdf
Jamaica Bay Task Force2- 10May22.pdfJamaica Bay Task Force2- 10May22.pdf
Jamaica Bay Task Force2- 10May22.pdf
 
Sea Level Rise and Storm Surge Plans
Sea Level Rise and Storm Surge Plans Sea Level Rise and Storm Surge Plans
Sea Level Rise and Storm Surge Plans
 
Municipal Adaptations to Create Resilient Beach Communities
Municipal Adaptations to Create Resilient Beach CommunitiesMunicipal Adaptations to Create Resilient Beach Communities
Municipal Adaptations to Create Resilient Beach Communities
 
Mitigation symposium - Andre Corbould
Mitigation symposium - Andre CorbouldMitigation symposium - Andre Corbould
Mitigation symposium - Andre Corbould
 
MB_SLR Studio 8
MB_SLR Studio 8MB_SLR Studio 8
MB_SLR Studio 8
 
Staff Presentation 080311 Gtg
Staff Presentation 080311 GtgStaff Presentation 080311 Gtg
Staff Presentation 080311 Gtg
 
SMP_FinalPublicMeeting_FINAL_083022.pptx
SMP_FinalPublicMeeting_FINAL_083022.pptxSMP_FinalPublicMeeting_FINAL_083022.pptx
SMP_FinalPublicMeeting_FINAL_083022.pptx
 
SMP_FinalPublicMeeting_FINAL_083022.pptx
SMP_FinalPublicMeeting_FINAL_083022.pptxSMP_FinalPublicMeeting_FINAL_083022.pptx
SMP_FinalPublicMeeting_FINAL_083022.pptx
 
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
 
LCW Restoration Plan & EIR- Public Workshop #2
LCW Restoration Plan & EIR- Public Workshop #2LCW Restoration Plan & EIR- Public Workshop #2
LCW Restoration Plan & EIR- Public Workshop #2
 
Key aspects of reservoir evaluation for deep water reservoirs
Key aspects of reservoir evaluation for deep water reservoirsKey aspects of reservoir evaluation for deep water reservoirs
Key aspects of reservoir evaluation for deep water reservoirs
 
ACOE Reformulation study for Jamaica Bay
ACOE Reformulation study for Jamaica BayACOE Reformulation study for Jamaica Bay
ACOE Reformulation study for Jamaica Bay
 
Greg Cademartori Great Marsh Symposium
Greg Cademartori Great Marsh SymposiumGreg Cademartori Great Marsh Symposium
Greg Cademartori Great Marsh Symposium
 
Baron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdfBaron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdf
 
Green infrastructure as a foundation for climate resilience and sustainabilit...
Green infrastructure as a foundation for climate resilience and sustainabilit...Green infrastructure as a foundation for climate resilience and sustainabilit...
Green infrastructure as a foundation for climate resilience and sustainabilit...
 
project presentation
project presentationproject presentation
project presentation
 
Cademartori great marshsymposium-1
Cademartori great marshsymposium-1Cademartori great marshsymposium-1
Cademartori great marshsymposium-1
 
Urban Runoff - Storm Water 101
Urban Runoff - Storm Water 101Urban Runoff - Storm Water 101
Urban Runoff - Storm Water 101
 
Hurricane Impact Preparedness and Resilient by Nature Recovery
Hurricane Impact Preparedness and Resilient by Nature RecoveryHurricane Impact Preparedness and Resilient by Nature Recovery
Hurricane Impact Preparedness and Resilient by Nature Recovery
 

More from ecowatchers

JBTF Nov2023 - JBRPC West Pond Living Shoreline.pdf
JBTF Nov2023 - JBRPC West Pond Living Shoreline.pdfJBTF Nov2023 - JBRPC West Pond Living Shoreline.pdf
JBTF Nov2023 - JBRPC West Pond Living Shoreline.pdfecowatchers
 
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptx
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptxNYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptx
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptxecowatchers
 
Baron - Jamaica Bay Task Force Meeting 2 - 30Nov23.pdf
Baron - Jamaica Bay Task Force Meeting 2 - 30Nov23.pdfBaron - Jamaica Bay Task Force Meeting 2 - 30Nov23.pdf
Baron - Jamaica Bay Task Force Meeting 2 - 30Nov23.pdfecowatchers
 
Fall 2023 JBTF presentation on Additional HRE project areas. .pptx
Fall 2023 JBTF presentation on Additional HRE project areas. .pptxFall 2023 JBTF presentation on Additional HRE project areas. .pptx
Fall 2023 JBTF presentation on Additional HRE project areas. .pptxecowatchers
 
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdfNPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdfecowatchers
 
November 17 2022 Jam Bay Task Force.pdf
November 17 2022 Jam Bay Task Force.pdfNovember 17 2022 Jam Bay Task Force.pdf
November 17 2022 Jam Bay Task Force.pdfecowatchers
 
Jamaica Bay Task Force_May 2022.pdf
Jamaica Bay Task Force_May 2022.pdfJamaica Bay Task Force_May 2022.pdf
Jamaica Bay Task Force_May 2022.pdfecowatchers
 
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...ecowatchers
 
Ribbed Mussel Study Status JBTF.pdf
Ribbed Mussel Study Status JBTF.pdfRibbed Mussel Study Status JBTF.pdf
Ribbed Mussel Study Status JBTF.pdfecowatchers
 
Weppler jam bay task force 3 nov 21
Weppler jam bay task force  3 nov 21Weppler jam bay task force  3 nov 21
Weppler jam bay task force 3 nov 21ecowatchers
 
Jb task force 2021 1103
Jb task force 2021 1103Jb task force 2021 1103
Jb task force 2021 1103ecowatchers
 
201130 west pond reduced
201130 west pond reduced201130 west pond reduced
201130 west pond reducedecowatchers
 
Jamaica bay ecowatchers task force presentation 12.9.2020
Jamaica bay ecowatchers task force presentation   12.9.2020Jamaica bay ecowatchers task force presentation   12.9.2020
Jamaica bay ecowatchers task force presentation 12.9.2020ecowatchers
 
Nyc parks marine debris removal
Nyc parks marine debris removalNyc parks marine debris removal
Nyc parks marine debris removalecowatchers
 
Raptor mgmt presentation12 09-2020
Raptor mgmt presentation12 09-2020Raptor mgmt presentation12 09-2020
Raptor mgmt presentation12 09-2020ecowatchers
 
20191113 jbfs presentation final
20191113 jbfs presentation final20191113 jbfs presentation final
20191113 jbfs presentation finalecowatchers
 
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...ecowatchers
 
Ribbed Mussel ability to remove Nitrogen from water bodies.
Ribbed Mussel ability to remove Nitrogen from water bodies.Ribbed Mussel ability to remove Nitrogen from water bodies.
Ribbed Mussel ability to remove Nitrogen from water bodies.ecowatchers
 
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodiesNYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodiesecowatchers
 
Shirley Chisholm State Park-Brooklyn Update on phase two work
Shirley Chisholm State Park-Brooklyn Update on phase two workShirley Chisholm State Park-Brooklyn Update on phase two work
Shirley Chisholm State Park-Brooklyn Update on phase two workecowatchers
 

More from ecowatchers (20)

JBTF Nov2023 - JBRPC West Pond Living Shoreline.pdf
JBTF Nov2023 - JBRPC West Pond Living Shoreline.pdfJBTF Nov2023 - JBRPC West Pond Living Shoreline.pdf
JBTF Nov2023 - JBRPC West Pond Living Shoreline.pdf
 
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptx
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptxNYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptx
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptx
 
Baron - Jamaica Bay Task Force Meeting 2 - 30Nov23.pdf
Baron - Jamaica Bay Task Force Meeting 2 - 30Nov23.pdfBaron - Jamaica Bay Task Force Meeting 2 - 30Nov23.pdf
Baron - Jamaica Bay Task Force Meeting 2 - 30Nov23.pdf
 
Fall 2023 JBTF presentation on Additional HRE project areas. .pptx
Fall 2023 JBTF presentation on Additional HRE project areas. .pptxFall 2023 JBTF presentation on Additional HRE project areas. .pptx
Fall 2023 JBTF presentation on Additional HRE project areas. .pptx
 
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdfNPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
 
November 17 2022 Jam Bay Task Force.pdf
November 17 2022 Jam Bay Task Force.pdfNovember 17 2022 Jam Bay Task Force.pdf
November 17 2022 Jam Bay Task Force.pdf
 
Jamaica Bay Task Force_May 2022.pdf
Jamaica Bay Task Force_May 2022.pdfJamaica Bay Task Force_May 2022.pdf
Jamaica Bay Task Force_May 2022.pdf
 
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
 
Ribbed Mussel Study Status JBTF.pdf
Ribbed Mussel Study Status JBTF.pdfRibbed Mussel Study Status JBTF.pdf
Ribbed Mussel Study Status JBTF.pdf
 
Weppler jam bay task force 3 nov 21
Weppler jam bay task force  3 nov 21Weppler jam bay task force  3 nov 21
Weppler jam bay task force 3 nov 21
 
Jb task force 2021 1103
Jb task force 2021 1103Jb task force 2021 1103
Jb task force 2021 1103
 
201130 west pond reduced
201130 west pond reduced201130 west pond reduced
201130 west pond reduced
 
Jamaica bay ecowatchers task force presentation 12.9.2020
Jamaica bay ecowatchers task force presentation   12.9.2020Jamaica bay ecowatchers task force presentation   12.9.2020
Jamaica bay ecowatchers task force presentation 12.9.2020
 
Nyc parks marine debris removal
Nyc parks marine debris removalNyc parks marine debris removal
Nyc parks marine debris removal
 
Raptor mgmt presentation12 09-2020
Raptor mgmt presentation12 09-2020Raptor mgmt presentation12 09-2020
Raptor mgmt presentation12 09-2020
 
20191113 jbfs presentation final
20191113 jbfs presentation final20191113 jbfs presentation final
20191113 jbfs presentation final
 
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
 
Ribbed Mussel ability to remove Nitrogen from water bodies.
Ribbed Mussel ability to remove Nitrogen from water bodies.Ribbed Mussel ability to remove Nitrogen from water bodies.
Ribbed Mussel ability to remove Nitrogen from water bodies.
 
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodiesNYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
 
Shirley Chisholm State Park-Brooklyn Update on phase two work
Shirley Chisholm State Park-Brooklyn Update on phase two workShirley Chisholm State Park-Brooklyn Update on phase two work
Shirley Chisholm State Park-Brooklyn Update on phase two work
 

Recently uploaded

办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一F dds
 
Dwarka Call Girls 9643097474 Phone Number 24x7 Best Services
Dwarka Call Girls 9643097474 Phone Number 24x7 Best ServicesDwarka Call Girls 9643097474 Phone Number 24x7 Best Services
Dwarka Call Girls 9643097474 Phone Number 24x7 Best Servicesnajka9823
 
Call Girls Abids 7001305949 all area service COD available Any Time
Call Girls Abids 7001305949 all area service COD available Any TimeCall Girls Abids 7001305949 all area service COD available Any Time
Call Girls Abids 7001305949 all area service COD available Any Timedelhimodelshub1
 
办理(Victoria毕业证书)维多利亚大学毕业证成绩单原版一比一
办理(Victoria毕业证书)维多利亚大学毕业证成绩单原版一比一办理(Victoria毕业证书)维多利亚大学毕业证成绩单原版一比一
办理(Victoria毕业证书)维多利亚大学毕业证成绩单原版一比一z xss
 
earthquake drill seminar for schools.pptx
earthquake drill  seminar for schools.pptxearthquake drill  seminar for schools.pptx
earthquake drill seminar for schools.pptxBfpSiniloanFSLaguna
 
Along the Lakefront, "Menacing Unknown"s
Along the Lakefront, "Menacing Unknown"sAlong the Lakefront, "Menacing Unknown"s
Along the Lakefront, "Menacing Unknown"syalehistoricalreview
 
Making a Difference: Understanding the Upcycling and Recycling Difference
Making a Difference: Understanding the Upcycling and Recycling DifferenceMaking a Difference: Understanding the Upcycling and Recycling Difference
Making a Difference: Understanding the Upcycling and Recycling DifferenceSwag Cycle
 
AI and Ecology - The H4rmony Project.pptx
AI and Ecology - The H4rmony Project.pptxAI and Ecology - The H4rmony Project.pptx
AI and Ecology - The H4rmony Project.pptxNeoV2
 
Species composition, diversity and community structure of mangroves in Barang...
Species composition, diversity and community structure of mangroves in Barang...Species composition, diversity and community structure of mangroves in Barang...
Species composition, diversity and community structure of mangroves in Barang...Open Access Research Paper
 
办理英属哥伦比亚大学毕业证成绩单|购买加拿大UBC文凭证书
办理英属哥伦比亚大学毕业证成绩单|购买加拿大UBC文凭证书办理英属哥伦比亚大学毕业证成绩单|购买加拿大UBC文凭证书
办理英属哥伦比亚大学毕业证成绩单|购买加拿大UBC文凭证书zdzoqco
 
原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证
原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证
原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证jdkhjh
 
Abu Dhabi Sea Beach Visitor Community pp
Abu Dhabi Sea Beach Visitor Community ppAbu Dhabi Sea Beach Visitor Community pp
Abu Dhabi Sea Beach Visitor Community pp202215407
 
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhidelih Escorts
 
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full NightCall Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
Water Conservation.pptxfgggggggggggggggggggggggggggggggggggggg
Water Conservation.pptxfggggggggggggggggggggggggggggggggggggggWater Conservation.pptxfgggggggggggggggggggggggggggggggggggggg
Water Conservation.pptxfggggggggggggggggggggggggggggggggggggggkhulekanimkhize2
 
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...Delhi Escorts
 
Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...Open Access Research Paper
 
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdfsrivastavaakshat51
 

Recently uploaded (20)

办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
 
Dwarka Call Girls 9643097474 Phone Number 24x7 Best Services
Dwarka Call Girls 9643097474 Phone Number 24x7 Best ServicesDwarka Call Girls 9643097474 Phone Number 24x7 Best Services
Dwarka Call Girls 9643097474 Phone Number 24x7 Best Services
 
Call Girls Abids 7001305949 all area service COD available Any Time
Call Girls Abids 7001305949 all area service COD available Any TimeCall Girls Abids 7001305949 all area service COD available Any Time
Call Girls Abids 7001305949 all area service COD available Any Time
 
办理(Victoria毕业证书)维多利亚大学毕业证成绩单原版一比一
办理(Victoria毕业证书)维多利亚大学毕业证成绩单原版一比一办理(Victoria毕业证书)维多利亚大学毕业证成绩单原版一比一
办理(Victoria毕业证书)维多利亚大学毕业证成绩单原版一比一
 
earthquake drill seminar for schools.pptx
earthquake drill  seminar for schools.pptxearthquake drill  seminar for schools.pptx
earthquake drill seminar for schools.pptx
 
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
 
Along the Lakefront, "Menacing Unknown"s
Along the Lakefront, "Menacing Unknown"sAlong the Lakefront, "Menacing Unknown"s
Along the Lakefront, "Menacing Unknown"s
 
Making a Difference: Understanding the Upcycling and Recycling Difference
Making a Difference: Understanding the Upcycling and Recycling DifferenceMaking a Difference: Understanding the Upcycling and Recycling Difference
Making a Difference: Understanding the Upcycling and Recycling Difference
 
young call girls in Janakpuri🔝 9953056974 🔝 escort Service
young call girls in Janakpuri🔝 9953056974 🔝 escort Serviceyoung call girls in Janakpuri🔝 9953056974 🔝 escort Service
young call girls in Janakpuri🔝 9953056974 🔝 escort Service
 
AI and Ecology - The H4rmony Project.pptx
AI and Ecology - The H4rmony Project.pptxAI and Ecology - The H4rmony Project.pptx
AI and Ecology - The H4rmony Project.pptx
 
Species composition, diversity and community structure of mangroves in Barang...
Species composition, diversity and community structure of mangroves in Barang...Species composition, diversity and community structure of mangroves in Barang...
Species composition, diversity and community structure of mangroves in Barang...
 
办理英属哥伦比亚大学毕业证成绩单|购买加拿大UBC文凭证书
办理英属哥伦比亚大学毕业证成绩单|购买加拿大UBC文凭证书办理英属哥伦比亚大学毕业证成绩单|购买加拿大UBC文凭证书
办理英属哥伦比亚大学毕业证成绩单|购买加拿大UBC文凭证书
 
原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证
原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证
原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证
 
Abu Dhabi Sea Beach Visitor Community pp
Abu Dhabi Sea Beach Visitor Community ppAbu Dhabi Sea Beach Visitor Community pp
Abu Dhabi Sea Beach Visitor Community pp
 
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
 
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full NightCall Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
 
Water Conservation.pptxfgggggggggggggggggggggggggggggggggggggg
Water Conservation.pptxfggggggggggggggggggggggggggggggggggggggWater Conservation.pptxfgggggggggggggggggggggggggggggggggggggg
Water Conservation.pptxfgggggggggggggggggggggggggggggggggggggg
 
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
 
Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...
 
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
 

NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf

  • 1. NEW YORK-NEW JERSEY HARBOR AND TRIBUTARIES COASTAL STORM RISK MANAGEMENT STUDY Briefing to Jamaica Bay Task Force November 17, 2022 6:30-8:30 PM, ET New York District
  • 2. 2 DRAFT REPORT Found at https://www.nan.usace.army.mil/NYNJHATS
  • 4. 4 NEW YORK-NEW JERSEY HARBOR AND TRIBUTARIES COASTAL STORM RISK MANAGEMENT FEASIBILITY STUDY STUDY AREA • The largest and most densely populated of the 9 NACCS Focus Areas • Area covers 2,150+ square miles and 900+ miles of affected shoreline • 25 counties in New York & New Jersey • Affected population of roughly 16 million people, including New York City and the six most populated cities in New Jersey COASTAL STORM RISKS & DAMAGES • Significant Life/Safety Risk and over 275,000 Structures in Potential Impact Area • Incorporates Dozens of Other Ongoing and Planned CSRM Projects in Study Area • Present Value Damages for 100-Year Storm Range from $100+B for Intermediate Sea Level Rise to over $350B for High Sea Level Rise Projection STUDY SCOPE • Study Cost: $19.4M, cost-shared 50/50 with NYSDEC and NJDEP thru July 2022, and 100% federal thereafter. • Study Schedule: Assistant Secretary of the Army for Civil Works Approved (7 Apr 21) Second Exemption for Study Extension to 2024 Completion • Funding: Federal funding ($1.45M) resumed in October 2021 following lapses in fiscal years 2020 and 2021. Study also received $6,724,000 of DRSAA funds. • Study Scope: WRDA 2020 includes study specific language STUDY SCHEDULE • Draft Feasibility Report and integrated Tier 1 Environmental Impact Statement Released for extended public day review with meetings planned throughout area (comment closing date January 6, 2023). Virtual meetings starting October 24th, 27th and November 5th. • See WWW.NAN.USACE.ARMY.MIL/NYNJHATS for dates, times and locations of public in- person meetings in November and December. • Final Chief of Engineers Report Approved to be Completed in June 2024
  • 5. 5 ALTERNATIVE PLANS – PROS & CONS WITH EACH Alternative 1: No action Alternative 2: Harbor-wide storm surge barrier + shore-based measures Alternative 3A: Multi-basin storm surge barriers + shore-based measures Alternative 3B: Multi-basin storm surge barriers + shore-based measures Alternative 4: Single-basin storm surge barriers + shore-based measures Alternative 5: Shore-based measures only • Alternatives span spectrum from large in-water storm surge gates to numerous shoreline-based structures. Alternatives also have (or will have) complementary non-structural and natural and nature-based features (where feasible). • Best Solution Appears to Involve Multiple, Layered Features • Possible Phased Implementation: 1) Short-term: Construct Actionable Features, 2) Mid-Term: Further Evaluate, Design and possibly Construct Complex Features, 3) Long-Term: Adapt and expand features due to further sea level rise and climate change
  • 6. 6 FUTURE WITHOUT-PROJECT (FWOP) CONDITION Assumptions • Investments in coastal storm risk management / resiliency projects will continue – Federal, state, local government investment – Private investment • Relative sea level rise over time – Used USACE intermediate projection for comparing plans in Draft Report – Considering ALL USACE sea level rise projections in future study plan formulation 1% flood extent (with intermediate RSLC)
  • 7. 7 OTHER CONSTRUCTED AND ONGOING PROJECTS (BLUE) ASSUMED AS PART OF FUTURE BASELINE CONDITION
  • 8. 8 USACE RELATIVE SEA LEVEL CHANGE AT BATTERY COMPARED TO STATES AND CITY PROJECTIONS Economic Period of Analysis Planning Horizon Base Year 2044 Study Authorization and Design Construction Operation, Maintenance and Adaptation (if/as warranted)
  • 9. 9 COMPOSITE: ALTERNATIVE PLANS SHOWING STORM SURGE BARRIER LOCATIONS CONSIDERED Alternative 2 Alternative 3B Alternative 3A Alternative 4 • All alternative plans will include nonstructural measures, as feasible, for areas with unaddressed coastal storm risk • All alternative plans will include natural and nature- based features where applicable and feasible Alternative 5 (shore-based measures only) not shown in figure
  • 10. 10 PROJECT COSTS (INTERMEDIATE RSLC) Alternative Construction Duration (years) Years of Full Benefits* First Costs (not including contingency) Contingency OMRR&R and IDC (PV) Total (Present Value)** 2 32 32 $70.6B $41.7B $37.3B $150.2B 3A 24 40 $48.9B $28.0B $18.7B $95.7B 3B 14 50 $35.6B $17.1B $23.5B $76.2B 4 14 50 $28.8B $14.2B $19.4B $62.5B 5 5 50 $10.1B $5.9B $9.8B $25.8B * - USACE policy only allows a maximum of 50 years of benefits in the economic evaluation, but the alternatives and measures are planned for permanent implementation with an at least one-hundred-year planning horizon ** - Adaptation costs for higher sea level rise projections are under refinement and have not been included in the total cost estimates at this time
  • 11. 11 PROJECT BENEFITS & COSTS – ON AN AVERAGE ANNUAL BASIS (INTERMEDIATE RSLC) Alternative Average Annual Cost Average Annual Benefits* Net Benefits* Benefit to Cost Ratio 2 $5.0B $4.6B -$0.5B 0.91 3A $3.2B $6.4B $3.2B 1.99 3B $2.6B $6.3B $3.7B 2.45 4 $2.1B $5.0B $2.9B 2.39 5 $0.9B $1.9B $1.0B 2.21 * Benefits currently based on estimated damages avoided to structures in study area. Critical infrastructure and other possible benefits under refinement and have not been included in the net benefit calculations at this time.
  • 12. 12 ALTERNATIVE 3B – THE TENTATIVELY SELECTED PLAN 62.75% Study Area at Direct Risk Benefited Alternative 3B includes: • Jamaica Bay and Southern Brooklyn Storm Surge Gate and Shoreline-based Measures • Kill Van Kull and Arthur Kill Storm Surge Gates with Shoreline-based tie-ins • Storm Surge Gates and Shoreline-based tie-ins for Gowanus, Newtown and Flushing Creeks • Shoreline-based measures for Lower Manhattan, East Harlem, and Jersey City • Numerous other complementary structural, non- structural, and NNBFs (not shown here) to complement measures listed above and better manage remaining residual risk (many under development & evaluation)
  • 13. 13 ADDITIONAL CONSIDERATIONS WITH STORM-SURGE BARRIERS – RISK REDUCTION FEATURES AND INDUCED FLOODING-MITIGATION FEATURES Risk Reduction Features BEHIND the Storm Surge Barriers Induced Flooding- Mitigation Features (as applicable) OUTSIDE the Storm Surge Barriers
  • 14. 14 TENTATIVELY SELECTED PLAN FEATURE IN DETAIL Note Induced Flooding- Mitigation Features Outside of Storm Surge Barrier Note Risk Reduction Features behind Storm Surge Barrier South Brooklyn and Jamaica Bay Area
  • 15. 15 Jamaica Bay Storm Surge Barrier: 2 – 200 foot wide Sector Gates 15 Auxiliary Lift Gates Total Length in Water: 3,800 feet Crest elevation*: 18 feet (NAVD88) Sheepshead Bay Storm Surge Barrier: 100 foot wide Sector Gate 2 Auxiliary Lift Gates Total Length in Water: 800 feet Crest elevation*: 17 feet (NAVD88) Gerritsen Creek Storm Surge Barrier: 115 foot wide Vertical Lift Gate 2 Auxiliary Lift Gates Total Length in Water: 400 feet Crest elevation*: 17 feet (NAVD88) Shoreline-Based Tie-In’s: Total Length: 116,000+ feet Measures include: Floodwalls, levees, reinforced dunes, pedestrian and vehicle gates, elevated promenades, seawalls, and tide gates SOUTH BROOKLYN SHORELINE-BASED MEASURES AND JAMAICA BAY STORM SURGE BARRIER * - For currently selected design storm event
  • 16. 16 • Layout and measures are conceptual and preliminary. • Risk reduction features are designed to address more frequent coastal flooding in red shaded areas to complement shoreline-based measures and storm surge barriers in southern Brooklyn and Queens encompassing Jamaica Bay that address more severe coastal flooding for broader green shaded area. • Elevation of risk reduction features currently targeted for +10 ft. NAVD88, with assumed +7 ft. NAVD88 closure criteria for the main Jamaica Bay storm surge barriers (all elevations correlated to water elevation predictions at the Battery – for commonality), but this may change in terms of elevation, layout, and measures from further evaluation and optimization of main storm surge closure gate operation criteria. RISK REDUCTION FEATURE DETAILS
  • 17. 17 RISK REDUCTION FEATURE DETAIL – FRESH CREEK BASIN • Shoreline-based features only – floodwalls (along E 108th St) and revetments at select shoreline areas
  • 18. 18 OLD HOWARD BEACH & HAMILTON BEACH RISK REDUCTION FEATURES • Currently comprised of berms, floodwalls and navigable gates • The gate structures have not been selected or designed – they could be sector gates, vertical lift gates or other type of navigable structural measure. • They would need further considerable environmental and engineering evaluation.
  • 19. 19 RISK REDUCTION FEATURES – BROAD CHANNEL AREA • Currently comprised of berms, bulkheads and road raisings • They would need further considerable environmental and engineering evaluation.
  • 20. 20 RISK REDUCTION FEATURES – HEAD OF BAY • Currently comprised of berms, bulkheads, deployable flood barriers, floodwalls and navigable gates. • The gate structures have not been selected or designed – they could be sector gates, vertical lift gates or other type of navigable structural measure. • They would need further considerable environmental and engineering evaluation.
  • 21. 21 DRAFT TIER 1 EIS: REPORT ORGANIZATION Review Aid: StoryMap https://hats-cenan.hub.arcgis.com/ ENVIRONMENTAL CONSEQUENCES Potential for Adverse Impacts by Measure Type Chapter 6 • Defining Tier 1 Scope of Direct, Indirect, and Cumulative Impacts - BROADLY • Estimating Beneficial Environmental Effects (“+”) • Estimating In-Kind Mitigated Impacts • Identifying Out-Of-Kind Mitigated Impacts • Incorporating Cooperating Agency and Stakeholder Input ENVIRONMENTAL CONSEQUENCES Applied Scoring Methodology Chapter 6 EXISTING CONDITIONS Chapter 2 - 50 environmental resources assessed - Organized by Planning Region - Draft Tier 1 assesses Structural Measures only - Final Tier 1 will also assess ringwalls, nonstructural, and Natural and Nature-Based Features
  • 22. 22 WANT TO LEARN MORE? Start Here CONNECT WITH THE STUDY TEAM Email: NYNJHarbor.TribStudy@usace.army.mil Mail: Mr. Bryce W. Wisemiller, Project Manager Ms. Cheryl R. Alkemeyer, NEPA Lead U.S. Army Corps of Engineers New York District U.S. Army Corps of Engineers New York District Jacob K. Javits Federal Building, Room 17-401 Jacob K. Javits Federal Building, Room 17-420 c/o PSC Mail Center c/o PSC Mail Center 26 Federal Plaza 26 Federal Plaza New York, New York 10278 New York, New York 10278 WWW.NAN.USACE.ARMY.MIL/NYNJHATS
  • 23. 23 SCHEDULE Action/Milestone Date Execute Feasibility Cost-Sharing Agreement (study start) ✅ 15 July 2016 Release Interim Report ✅ 19 February 2019 Public Meetings for Interim Report ✅ March - October 2019 Delay due to lack of Federal funding ✅ February 2020 – September 2021 Federal funding resumption ✅ October 2021 FCSA Amendment Execution ✅ 28 June 2022 Tentatively Selected Plan Milestone ✅ 26 July 2022 Release Draft Integrated Feasibility Report and Tier 1 EIS ✅ Late September 2022 (90+ day review period) Public Meetings for Draft Report October – December 2022 (In-person and additional virtual public meetings in November-December. Locations TBD.) Public Comment Closing Date January 6, 2023 Agency Decision Milestone April 2023 Submit Final Integrated Feasibility Report and Tier 1 EIS January 2024* Chief of Engineer’s Report Approval (study end) June 2024* * Schedule may be revised due to actual federal funding resumption shift in 2022
  • 24. 24 • The Tentatively Selected Plan (Alternative 3B) is preliminary and conceptual – Considerable work remains to be done – Future work will be informed by and focus on issues raised by the public and agencies • There are many resources on the study website https://www.nan.usace.army.mil/NYNJHATS – Draft Integrated Feasibility Report and integrated Tier 1 Environmental Impact Statement – Readers Guide – StoryMap Hub • This is one of a series of public meetings – There will be in-person and additional virtual public meetings – Meeting information will be posted to the study website and shared via email • Your feedback is an important part of the study process IN SUMMARY
  • 25. 25 YOUR FEEDBACK IS IMPORTANT The Study Team is here today to answer your questions and hear your feedback Written Comments • Send all written comments for the record via email or mail • The public comment period closes January 6, 2023 Mr. Bryce W. Wisemiller, Project Manager U.S. Army Corps of Engineers New York District Jacob K. Javits Federal Building, Room 17-401 c/o PSC Mail Center 26 Federal Plaza New York, New York 10278 917-790-8307 nynjharbor.tribstudy@usace.army.mil More Opportunities to Provide Feedback • There will be in-person and additional virtual public meetings • Meeting information will be posted to the study website and shared via email Ms. Cheryl R. Alkemeyer, NEPA Lead U.S. Army Corps of Engineers New York District Jacob K. Javits Federal Building, Room 17-420 c/o PSC Mail Center 26 Federal Plaza New York, New York 10278 917-790-8723 nynjharbor.tribstudy@usace.army.mil