7. Component A
A-1: DDM renovate ERCC & NDMRTI
A-2: DNCC renovate City Corp & FSCD
A-3: Supply ECT equipment
A-4: Supply SAR equipment
A-5: Provide TED assistance
8. DDM – A1 & A5
A1: DDM renovate ERCC & NDMRTI
Waiting for….design
Contract not signed yet
A5: TED Assistance Program
Waiting for NOL from WB
Pending approval from MoDMR
Verification by M&E Team pending
9. DNCC- A2, A3 & A4
A2: Renovate City Corp & FSCD facilities
Substantial progress made on most KAAs
Construction of 11/12 warehouse done (FSCD)
Construction of 8/8 warehouse done (DNCC & DSCC)
A3: Supply ECT equipment
Frequency allocation of ECT equipment for DNCC done.
FA of ECT yet to be done for DSCC, DNCC and SCC.
Delivery FSCD ECT equipment (G-1-1) expected by November
TER yet to finalized for DNCC ECT equipment (G1-2) by August
A4: Provide SAR equipment
Substantial progress made in procuring equipment
All steps in Procuring equipment (G-2-1~G-2-11 & G-3) done.
10. Component B - RAJUK
B1: Vulnerability Assessment (VA)
NOL not received yet for VA service contract (S-4).
Evaluation not done yet for Earthquake & Seismic equipment
for VA goods contract (G-9).
B2: Risk Sensitive Land use Plan (RSLUP)
Bank decision pending for RSLUP service contract (S-5)
Re-tendering is yet to start for Earthquake & Seismic
equipment for RSLUP goods contract (G-10)
11. Component C - RAJUK
C1: Establish URU in RAJUK
Most KAAs undertaken for foundational & institutional infrastructure.
Mixed progress (2/8 KAAs completed)
C2: e-permit system for construction
Signing contract for S-7 not done, expected by August 2018.
C3: Professional Accreditation Program
Re-RPF for S-8 not done, expected by September 2018.
C4: Improve Building Code enforcement
CCGP approval for S-9 not received, expected by August 30, 2018.
16. Project Development Objective
…to strengthen the capacity of Government of
Bangladesh agencies to respond to emergency
events and
to strengthen systems to reduce the vulnerability
of future building construction to disasters in
Dhaka and Sylhet.
17. Background to the urp
Component A Reinforcing the Country’s
Emergency Management Response Capacity
Component B Vulnerability Assessment of Critical
and Essential Facilities
Component C Improved Construction, Urban
Planning and Development
Component D Project Coordination, Monitoring
and Evaluation
Component E: Contingent Emergency Response