BSBPMG522 Undertake project work
Table of Contents
1.1 – Initiation and scope
...............................................................................................
....1
Project brief
...............................................................................................
....................1
Project scope document
...............................................................................................
2
Stakeholder analysis
...............................................................................................
.....3
Communication plan (example)
...................................................................................4
Roles and responsibilities
............................................................................................5
Project snapshot
...............................................................................................
............6
1.2 – Planning
...............................................................................................
......................7
Work breakdown structure
...........................................................................................7
Project plan
...............................................................................................
....................7
Gantt chart
...............................................................................................
.................. 11
Activities schedule
...............................................................................................
...... 13
Budget
...............................................................................................
......................... 14
Risk register
...............................................................................................
................ 15
Risk assessment form
...............................................................................................
16
1.3 – Implementation
...............................................................................................
....... 17
Change requests
...............................................................................................
......... 17
Issues
log..........................................................................................
.......................... 17
1.4 – Monitoring
...............................................................................................
................ 19
Status update report
...............................................................................................
.. 19
1.5 – Finalising and
review.....................................................................................
......... 20
Budget variation report
..............................................................................................
20
Post-project review meeting
...................................................................................... 21
Handover report
...............................................................................................
.......... 22
Post-project review report
......................................................................................... 23
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 1 of 24
1.1 – Initiation and scope
Project brief
Project purpose and rationale
The justification and validity of the project needs to be
confirmed before the project proceeds. This
document is used to clarify the project purpose and justification
and to gain approval to proceed
to the next phase.
Project title
Working title.
Project purpose
Describe the purpose/need/rationale/feasibility for the project.
Background and strategic context
Explain the background to the project and how it relates to the
key strategic plans.
Priority
Note the importance and/or urgency of the project to the
organisation.
Related projects
Any other projects that have been undertaken in the past, are
currently underway, or planned for
the future that will or may be affected by, or simply connected
to, this project.
Project client/owner
The person who requires the project to be undertaken.
Project sponsor
The person who is providing the funds and has the ultimate
authority over the project.
Project manager
The person who has the responsibility to manage the project on
a day-to-day basis.
Project status
What has already been decided about the project? What
decisions have already been made? What
work has already been done in relation to the project? Any
assumptions or constraints?
Special provisions
Special regulations, ethical or legal considerations, etc.
Project approvals
Add any signatures that are required for approval to proceed to
the next phase.
Project Manager Project Sponsor
Project Client/Owner Other
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 2 of 24
Project scope document
This template is a tool that can be used with key stakeholders to
clearly define the logical
boundaries of the project. Ensure that you note any
requirements that are out of scope to achieve
absolute clarity about what is and is not covered by this project,
and to avoid the potential for
problems later on.
In Scope Out of scope
(exclusions)
Assumptions Constraints
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 3 of 24
Stakeholder analysis
Use this template to identify areas, groups or individuals who
may participate in, or are affected
by, the project. Include everyone who has a vested interest. A
useful question to ask is: ‘What will
make this project a success for you?’
Name Work area Stakeholder type
(client, end-user)
Impact on/by project,
requirements, success
criteria
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 4 of 24
Communication plan (example)
What Who Purpose When/frequency Type/methods
Initiation
meeting
All stakeholders. Gather information
for initiation plan.
FIRST
Before project start
date.
Meeting.
Distribute
project
initiation
plan
All stakeholders. Distribute plan to
alert stakeholders
of project scope
and to gain buy in.
Before kick-off
meeting.
Before project start
date.
Project snapshot
distributed via
hard copy or
electronically.
May be posted on
project website.
Project
kick-off
All stakeholders. Communicate plans
and stakeholder
roles/
responsibilities.
Encourage
communication
among
stakeholders.
At or near project
start date.
Meeting.
Status
reports
All stakeholders
and project office.
Update
stakeholders on
progress of the
project.
Regularly
scheduled.
Weekly is
recommended for
small-medium
projects.
Distribute status
report electronically
and post via
website.
Team
meetings
Entire project team.
Individual meetings
for sub-teams as
appropriate.
To review detailed
plans (tasks,
assignments, and
action items).
Regularly
scheduled.
Weekly is
recommended for
entire team. Weekly
or bi-weekly for
sub-teams as
needed.
Meeting: detailed
plan.
Sponsor
meetings
Sponsor/s and
Project Manager.
Update sponsor/s
on status and
discuss critical
issues.
Seek approval for
changes to project
plan.
Regularly
scheduled.
Recommended
bi-weekly or
monthly and also as
needed when
issues cannot be
resolved or changes
need to be made to
project plan.
Meeting.
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 5 of 24
Roles and responsibilities
It is important to identify who the major players are on the
project. List the major project roles,
responsibilities and the actual people involved. Add in any
additional roles as required.
Role Name/s Responsibilities Signature/s
(if required)
Project client/owner
The person who requires the
project to be undertaken.
Project sponsor/project
director/project board
Senior management of the
project. Accountable for the
success of the project. Has the
authority to commit resources.
Project manager
Person responsible for running
the project on a day-to-day
basis within defined authorities
for cost and schedule as
agreed with the project
sponsor/board.
Manager of the project
manager
The operational/line manager
who the project manager
reports to on a day-to-day
basis.
Project team members
Staff who will be working on
the project.
Steering committee/
working party
To provide advice and
recommendations.
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 6 of 24
Project snapshot
The project snapshot summarises the purpose, deliverables,
stakeholders, resources, risks,
interdependencies and success criteria of the project.
Project snapshot
Name of project:
Project purpose:
What are the goals/objectives of this project? Why are we
undertaking it? What is the
problem/opportunity?
Deliverables with timeframes
What, when, etc.
Stakeholders
Who is the sponsor, project manager,
customers, and other key groups who can
impact, or be impacted by, this project.
Resources
Cash flow, people, equipment, facilities,
software, etc.
Risks
Resource limitations, deadlines, budget,
technology, legal and other constraints, etc.
Interdependencies
With other projects, groups, system
interfaces, etc.
Success criteria
How we know we are successful.
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 7 of 24
1.2 – Planning
Work breakdown structure
A work breakdown structure (WBS) in project management is a
tool used to define and group the
project’s discrete work elements (or tasks) in a way that helps
organise and define the total work
scope of the project. The WBS is a dynamic tool and can be
revised and updated as needed by the
project manager.
Level 1 Level 2 Level 3
Task 1
Sub-task 1.1
Work item 1.1.1
Work item 1.1.2
Work item 1.1.3
Sub-task 1.2
Work item 1.2.1
Work item 1.2.2
Work item 1.2.3
Task 2
Sub-task 2.1
Work item 2.1.1
Work item 2.1.2
Work item 2.1.3
Sub-task 2.2
Work item 2.2.1
Work item 2.2.2
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
Project plan
The project plan is the basis for monitoring and controlling the
project. All project information is
http://en.wikipedia.org/wiki/Project_management
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 8 of 24
consolidated to date, forming the basis for monitoring and
controlling once implementation of the
project commences.
Project title:
Project purpose
From project proposal – update if required.
Background and strategic context
From project proposal – update if required.
Other related projects
From project proposal – update if required.
Project objective
From project proposal – update if required.
Scope including key deliverables
From project proposal – update if required.
In scope.
Out of scope.
Assumptions
Constraints
Deliverables
Governance
From project proposal – update if required. Attach a project
organisation chart and additional
information on responsibilities if required.
Project client/owner
From project proposal.
Project sponsor
Project Manager
Manager of the project manager
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 9 of 24
Project team members
Key stakeholders
From project proposal – update if required. Include a more
detailed stakeholder analysis in the
Appendices, if required.
Schedule
Using the information you generated in the work breakdown
structure, update the schedule.
Include a Gantt chart or additional planning information in the
Appendices.
Item Milestone date Responsibility
Resource and cost plan
Resource planning is where you determine what resources
(people, equipment and materials) and
what quantities of each should be used to perform activities.
Once the resources have been
determined, estimate the project costs. Include a more detailed
resource and cost plan in the
appendices if required.
Deliverable/milestone/phase Resource Cost
Project risk assessment
From project proposal – update if required. Include a more
detailed risk management plan in the
appendices.
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 10 of 24
Risk
Level
(high/medium/low)
Management strategy
Quality management plan
Include a high level quality management plan here. Include a
more detailed quality management
plan in the appendices if required.
Item from WBS Agreed quality standard Recovery procedure
Communications and reporting
Include a high level communications plan here. Include a more
detailed communications
management plan in the appendices if required.
Stakeholder Information required When required Format
Controls
Outline how you are going to track, monitor and report on the
project. For example:
● status reports
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 11 of 24
● exception reports
● issues/risk log
● variance requests.
Appendices
List the appendices that are attached to your project plan, for
example:
● stakeholder needs analysis
● work breakdown structure
● Gantt chart
● activities schedule
● budget/cash flow
● human resource planning schedule
● roles and responsibilities
● procurement schedule
● combined resources and cost schedule
● risk management plan
● quality management plan
● communications management plan.
Future related projects
Project approvals
Add any signatures that are required for approval to proceed to
the next phase.
Project Manager Project Sponsor
Project Client/Owner Other
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
Gantt chart
To use a Gantt chart, list the activities and tasks in column A,
select an appropriate time interval
(days, weeks or months), allocate the dates to columns B
onwards and plot the expected time
duration (total time from start to completion) under the
appropriate column by selecting shading
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 12 of 24
from the cells. When you wish to provide a status report, simply
colour or shade in black those
items that are completed or estimate the percentage complete.
This will give you an immediate
visual representation as to whether or not you are on schedule.
You can add extra columns for
assignment of responsibilities, etc.
For small projects, a Gantt chart can be created as a
spreadsheet.
Activity/task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Legend
If there are many tasks or stages in your project, you can
identify them with a key or legend.
Task 1 Task 5
Task 2 Task 6
Task 3 Task 7
Task 4 Task 8
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 13 of 24
Activities schedule
The activities schedule is a tool used to monitor individual
activities against the project plan. Information recorded on the
schedule can be used when
providing project status updates to stakeholders.
Phases &
activities
Responsibility Resources Effort (hrs) Started Deadline
Actually
completed
Comment/status
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 14 of 24
Budget
The project budget is a prediction of the costs associated with a
particular project. These costs
include labour, materials, and other resources required to
complete the project.
Project Name:
Income Inc. GST Ex. GST
Total income
Expense Inc. GST Ex. GST
Subtotal
Contingency (+10%)
TOTAL
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 15 of 24
Risk register
This template is used to record identified risks associated with
your project, analyse the impact
and determine resultant action to be taken.
Risk
Likelihood
(H/M/L)
Impact
(H/M/L)
Risk response
(contingency
strategies)
Responsible
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 16 of 24
Risk assessment form
Identified risks are logged on a risk form and a copy is
forwarded to the project manager.
Project details
Project Name: Project Name Project name to which the risk
relates.
Project Manager: Name of the project manager responsible for
mitigating the risk.
Risk details
Risk ID: Number allocated to this risk.
Raised by: Name of person who has raised the risk.
Date raised: Date of completion of this form.
Description of risk:
Briefly describe the identified risk and its possible impact on
the project (e.g. scope, resources,
deliverables, timelines and/or budgets).
Likelihood of risk:
Describe and rank the likelihood of the risk
occurring (i.e. low, medium or high).
Impact of risk:
Describe and rank the impact on the project if
the risk occurs (i.e. low, medium or high).
Risk mitigation
Preventative actions recommended:
Briefly describe any action that should be taken to prevent the
risk from occurring.
Contingency actions recommended:
Briefly describe any action that should be taken, should the risk
occur, to minimise its impact
on the project.
Approval details
Supporting documentation:
Details of any supporting documentation used to substantiate
this risk.
Signature: _______________________ Date: ___ /___ /____
PLEASE FORWARD THIS FORM TO THE PROJECT
MANAGER
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 17 of 24
1.3 – Implementation
Change requests
This form is used to assist with recording and management of
changes in scope, time, quality or
budget. The change management procedure must be negotiated
with the key stakeholders prior to
the sign-off of the project plan.
Change request – Project
Issued by
Item affected
Nature of change
requested
Reason for change
Impact on scope
Impact on budget
Impact on schedule
Change authorised: Yes/No Adj. completion date: Adj. final
budget: $
Signed:
Project Manager
Signed
Sponsor
Signed
Client
Signed
Date Date Date Date
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
Issues log
In this template all issues are treated as risks. They should be
recorded when they arise, assigned
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 18 of 24
a number and responsibility, a recovery strategy or alternate
path agreed, acted upon and
recorded when closed.
Item Strategy Date logged Date resolved
Signed:
Project Manager
Signed:
Sponsor
Signed:
Client
Signed:
Date: Date: Date: Date:
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 19 of 24
1.4 – Monitoring
Status update report
This is one example of a status report. The preferred format
should be negotiated with the project sponsor. Attach minutes
of project meetings.
Status report – Project
Item Work completed
to-date
Milestone date Revised/ actual
date
Budgeted cost Revised/ actual
cost
Responsible
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 20 of 24
1.5 – Finalising and review
Budget variation report
The project budget is a prediction of the costs associated with a
particular project. These costs
include labour, materials, and other resources required to
complete the project.
Project name:
Income Budget Actual % Variation
Total income
Expense Budget Actual % Variation
Subtotal
TOTAL
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 21 of 24
Post-project review meeting
This template provides a proposed post-project review meeting
agenda, detailing items to be
discussed when reviewing the overall project.
Post-Project Review Meeting – Agenda
Topic Speaker Time
Brief overview of project:
Purpose of project, major accomplishments, comments.
Project
Manager
5 mins
Review by team:
Goals, objectives, deliverables, schedule, budget, and success
criteria (Were they met, partially met, or missed?).
All 10 mins
What worked/what could have gone better?
Some areas to consider:
● project planning
● project management
● project scheduling and tracking
● project estimating
● communication (with team, other groups/stakeholders,
sponsor)
● risk management
● vendor management
● issues management
● stakeholder management
● resourcing
● users
● development approach:
○ methodology
○ analysis and design
○ development
○ testing
○ implementation
● training, documentation
● technology
● overall approach to project (i.e. vendor package, staged
implementation, etc.)
● production and operation support.
All 20 mins
Lessons learned All 10 mins
Next steps All 5 mins
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 22 of 24
Handover report
This template summarises the project as delivered and any
agreed changes to baseline scope,
quality, costs and schedule.
Handover report
Initial overall objectives
Agreed changes to objectives
Final agreed deliverables
Item Budgeted cost
Final
cost
Schedule
date
Final date
Total
Issues summary
Item Strategy Date logged
Date
resolved
Documents attached
No. Title
____________________
Project Manager
_____________________
Project Sponsor
_____________________
Project Client
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 23 of 24
Post-project review report
This template can be used to guide you through the process of
conducting a post-project review.
This template can be used to document the key learning in terms
of what worked well and what
could have been improved.
Post-Project Review Report
Name of project:
Date and location of meeting:
Names of attendees:
1. Overview by Project Manager:
Brief summary of highlights and achievements, etc.
2. Review by team of goals, objectives/deliverables and
schedule as outlined in project plan
Cut and paste from project plan.
Met Missed Partially
met
Comments
Project goal/s
Objectives/deliverables
Success criteria
Schedule
Budget
BSBPMG522 Undertake project work Project Planning
Templates
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 24 of 24
3. What worked well; what could have gone better?
Worked well Could have gone better
4. Lessons learned
5. Next steps / improvement plans
Project Title: Project Client: Date:
Version:
Project Sponsor: Project Manager:
File Name: Page x of y
Simulated Business
Max Lionel Realty
Table of Contents
Chapter 1 – Business plan (excerpt)
...........................................................................1
Chapter 2 – Organisational chart and management profiles
....................................2
Chapter 3 – Management responsibilities
..................................................................3
Chapter 4 – Budget summary
......................................................................................4
Chapter 5 – Operational plan
......................................................................................5
Chapter 6 – Operational risk register
..........................................................................7
Chapter 7 – Work Health and Safety (WHS) Policy
.....................................................8
Chapter 8 – Anti-discrimination
policy...................................................................... 10
Chapter 9 – Procurement policy and procedures
.................................................... 11
Chapter 10 – Max Lionel Realty current tenants list
............................................... 16
Chapter 11 – List of pre-approved suppliers
........................................................... 17
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 1 of 17
Chapter 1 – Business plan (excerpt)
From Max Lionel Realty business plan FY 2013/14
About Max Lionel Realty
Max Lionel Realty was founded in 2008 by property developer
Max Lionel. The
company currently employs approximately 100 people, 80 of
whom are licensed real
estate agents.
Through its client agents, the organisation manages property
sales and rentals (both
residential and commercial) on behalf of a range of clients. The
organisation also
separately engages in investment activities, such as property
and land development.
Max Lionel Realty has been a member of the Real Estate
Institute of Victoria (REIV)
since 2008 and proudly follows the REIV Code of Conduct.
Mission:
● to achieve the highest returns for our clients and to deliver a
client experience
that is second to none in the industry.
Vision:
● to establish, within five years, the MLR brand — the highest
ethical standards
with best-in-breed performance for clients.
Values:
● integrity
● client-focus
● active encouragement of excellence, innovation and
continuous improvement
● teamwork
● recognition of the diversity and expertise of MLR employees
and agents.
Strategic directions:
The strategic context in which Max Lionel Realty will achieve
its mission and vision is
through:
● engaging with customers and clients
● building goodwill and reputation for integrity
● supporting innovative thinking, management and leadership
skills.
● creating a high-performing, highly profitable organisation.
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 2 of 17
Chapter 2 – Organisational chart and management profiles
Max Lionel Realty organisational chart
Board of Directors
and CEO
Max Lionel
Chief Financial
Officer
Riz Mehra
Operations General
Manager
Kim Sweeney
Human Resources
Manager
Les Goodale
Manager
Residential Realty
(Sales and Rentals)
Sam Lee
Manager
Commercial Realty
(Sales and Rentals)
Pat Mifsud
Manager
Investments
Peter Mitchell
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 3 of 17
Chapter 3 – Management responsibilities
Max Lionel, CEO
Max is responsible for working with the Board of Directors to
oversee the business, set
overall strategic directions, manage risk, and authorise large
financial transactions.
Riz Mehra, Chief Financial Officer
Riz is responsible for preparing quarterly financial statements
and overall budgeting. Riz
Is also responsible for overseeing budgets for cost centres and
individual projects. At the
completion of financial quarters and at the end of projects, Riz
is responsible for viewing
budget variation reports and incorporating information into
financial statements and
financial projections.
Kim Sweeney, Operations General Manager
Kim is responsible for the day-to-day running of the company.
Kim oversees the
coordination, as well as the structural separation, of the
Residential, Commercial, and
Investments centres. Kim is responsible for sponsoring projects
which affect operations
of the organisation as a whole. Kim works with the Human
Resources Manager to
coordinate systems and projects in order to achieve company-
wide synergy.
Les Goodale, Human Resources Manager
Les is responsible for the productive capacity and welfare of
people at MLR. With the
Operations General Manager, Kim works to coordinate projects
and management
systems such as performance management, recruitment, and
induction. Kim will need to
ensure aspects of the recently launched WHS management
system, such as risk
assessment, management, consulting, reporting and continuous
improvement, are
coordinated with all subsequent activities.
Sam Lee, Manager Residential Realty
Sam is responsible for the management of all aspects of
residential realty. Sam manages
the activities of residential agents.
Pat Misfud, Manager Commercial Realty
Pat is responsible for the management of all aspects commercial
realty. Pat manages the
activities of commercial agents.
Peter Mitchell, Manager Investments
Peter is responsible for the management of all aspects
investment realty. Peter manages
the activities of investment agents. Peter works with the
Operations General Manager to
ensure separation of investment from obligations to residential
and commercial clients.
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 4 of 17
Chapter 4 – Budget summary
Max Lionel Realty 2013–2014 budget by activities to be
undertaken
Income:
Commissions, fees from
clients
$2,566,000 Commissions and agents’ fees for the period.
Investment income $1,567,000 Real estate investment income.
COGS $150,413 Cost of provision of services.
Total Income $3,982,587 Gross profit.
Expenses:
Wages, salaries and on
costs
$1,567,890 Wages, salaries, superannuation, work cover
insurance, payroll tax.
Consultancy fees $50,000 Project management: WHS
management
system; AD awareness program.
Communication expenses $42,000 Telephone, ISP costs, IT
support.
Staff travel, transport and
accommodation.
$55,500 Cost of staff travel and associated costs for
sales, etc.
Premises expenses $250,000 Rent, electricity, maintenance,
cleaning.
Capital expenditure $120,000 Purchase of new office equipment
(90%),
vehicles; purchase of properties, land.
Depreciation and
amortisation
$177,569 Computers and capital equipment that is
depreciated.
Office supplies $65,068 Printing and stationery, postage,
amenities.
Professional fees
(consultants, legal and
audit), insurances, taxes and
charges, subscriptions and
memberships.
$62,187 Audit fees, external accounting costs, bank
charges, insurance except workers
compensation.
Total Expenses $2,390,214
Surplus $1,592,373 Net income before tax.
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 5 of 17
Chapter 5 – Operational plan
Max Lionel Realty operational plan (summary) FY 2013 - 2014
Objectives: Performance measures Tasks:
1 Engage with
customers/build
ethical profile:
● raise
organisational
profile by 20%
● improve client
satisfaction
performance by
25%.
● Percentage of brand recognition
in sought-after categories in
periodic customer surveys.
● Percentage of customers with
positive view of organisational
responsiveness, innovation,
quality.
● Number of client/tenant
complaints.
● Project to raise awareness of anti-discrimination, WHS and
other
legislation/codes of conduct among agents, clients, tenants.
● Conduct of quarterly surveys: clients and tenants.
● Training needs analysis and training of agents.
● Ensure agents disclose potential conflict of interest to clients,
tenants.
● Development of ethical charter, including principles all
agents must
follow.
2 Increase revenues by
20% within the third
quarter.
● Total income.
● Agent income.
● Investment income.
● Investigate resourcing needs: number of agents; personnel;
office
equipment, cars, etc.
● Fulfil resourcing needs in accordance with policies and
procedures.
3 Reduce direct and
indirect costs of
operations by 10%.
● General ledger accounts;
financial statements:
○ wages
○ cost of agent services
○ consultancy fees
○ wastage and associated
expenses.
● Renegotiate with suppliers.
● Research potential new suppliers.
● Management engagement with employees to achieve greater
employee support of organisational goals.
● Include explanation of how activities work with
organisational
strategic goals in all communications to internal personnel.
● Greater use by managers of budgets to encourage restraint.
● Greater focus on budget restraint in management of projects.
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 6 of 17
Max Lionel Realty operational plan (summary) FY 2013 - 2014
Objectives: Performance measures Tasks:
4 Engage workers with
strategic goals of
business and
support professional
development in line
with strategic goals.
(Targets to be set by
individual managers.)
● Percentage completion of
performance plans and
performance management
process.
● Numbers of coaching sessions
completed.
● Numbers of operational – related
training programs completed.
● Management engagement with employees to achieve greater
buy in
of organisational goals.
● Include explanation of how activities work with
organisational
strategic goals in all communications to internal personnel.
● Regular coaching.
● Training needs analysis and training.
● Strategic goals included in induction program for estate
agents.
● Employee incentives for performance in all areas relevant to
operational and strategic goals.
5 Improve health of
employees (range of
specific areas).
● Numbers of injuries (Target = 0).
● Numbers of absentees
(Target = <3% of total hours).
● Training need analysis and training on WHS and
implementation of
recently launched MLR WHS management system.
● Research incentives for: safe work achievement and healthy
lifestyle.
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 7 of 17
Chapter 6 – Operational risk register
Max Lionel Realty risk register FY 2012/2013
Identified risk Probability Impact Current controls Future
actions
Failure to recruit qualified real estate
agents due to increased competition.
Medium High ● All office equipment regularly
reviewed and updated as required;
IT security monitored and
maintained.
● Appropriate insurances held and
coverage reviewed annually.
● Managers encouraged and
incentivised to follow performance
management policy.
● Employee performance plans align
with business plan and six-monthly
review process in place.
● Project to raise awareness of anti-
discrimination, WHS and other
legislation/codes of conduct
among agents, clients, tenants
● Appropriate HR policies and
procedures in place.
● WHS management system in
place.
● Industry benchmarking
in all areas of
organisational
performance
● Conduct periodic reviews
of agent performance to
ensure professional
conduct
● Staff trained in use of
technology as needed.
● Keep abreast of changes
in potential liabilities.
● Review and develop HR
related policies where
required.
● Development of ethical
charter, including
principles all agents
must follow
Failure to realise revenue gains due to
recent slump in real estate prices.
High High
Inadequate insurance cover. Low High
Non-compliance on anti-discrimination. Medium High
Perception of discriminatory practice
reducing client and tenant base.
Medium High
Poor organisational culture; low level of
staff engagement and morale.
Medium Medium
Loss of knowledge and capability
through departing staff.
Low High
Failure to meet occupational health and
safety requirements.
Low High
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 8 of 17
Chapter 7 – Work Health and Safety (WHS) Policy
Max Lionel Realty WHS policy
Max Lionel Realty recognises its responsibility to provide a
healthy and safe working
environment for employees, contractors, clients and visitors.
Max Lionel Realty is
committed to the continued wellbeing of its employees and to
ensuring that all employees
are safe from injury and health risks whilst undertaking work-
related duties, including
home-based work.
Purpose The purpose of this policy is to ensure the acquisition
of resources
is carried out consistently, fairly and transparently and in
accordance with organisational requirements.
In order to ensure a healthy and safe working environment, Max
Lionel Realty will (in accordance with the WHS management
system):
● undertake risk assessments and implement procedures to
adequately manage any risks in the working environment
● provide written procedures and instructions for safe working
practices
● ensure compliance with all relevant legislation
● maintain safe systems of work including the work premises
and environment
● provide appropriate support, instruction, training and
supervision to employees to ensure safe working practices.
Scope The scope of this policy covers employees and
contractors of Max
Lionel Realty (MLR).
Resources Specific procedures for the implementation of this
policy are
available below and on the company intranet.
Responsibility Max Lionel Realty management and employees
are ultimately
responsible for ensuring that safe systems of work are
established,
implemented and maintained.
Management is responsible for:
● the effective implementation and regular review of WHS
procedures
● consultation with employees regarding health and safety
issues and changes to legislation and/or working practices
which may affect the health, safety or welfare of employee
● providing and maintaining a safe system of working practices
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 9 of 17
● providing support, training, and supervision to employees to
ensure safe and healthy workplace practices are carried out,
including relevant first aid training where appropriate
● the provision of adequate resources for employees to meet
the WHS commitment, including an up-to-date first aid kit.
Individual employees are responsible for:
● following all WHS policies and procedures
● ensuring they report all potential and actual risks to partners
or managers/supervisors
● taking care to protect their own health and safety and that of
their colleagues at work
● ensuring their own or others health and safety is not
adversely affected by the consumption of drugs or alcohol
● encouraging others to follow healthy and safe working
practices in the workplace.
Policy
Implementation
and Review
This policy has been established and implemented through the
human resource functions of the organisation and will be
reviewed
regularly in consultation with MLR management and employees
to
ensure compliance with legislation, industry standards and
organisational changes.
Relevant
legislation, etc.
● Privacy Act 1988 (Cwlth)
● Estate Agents Act 1980 (Vic)
● Equal Opportunity Act 2010 (Vic)
● Occupational Health and Safety Act 2004
● Dangerous Goods Act 1985 (Vic)
● AS/NZS 4804:2001 Occupational health and safety
management systems – General guidelines on principles,
systems and supporting techniques
Updated/
authorised
10/2013 – Riz Mehra, CFO
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 10 of 17
Chapter 8 – Anti-discrimination policy
Max Lionel Realty Anti-discrimination Policy
Purpose The purpose of this policy is to ensure transactions
with clients,
tenants and other employees is handled fairly and transparently
and in accordance with organisational and legal requirements.
Generally it is unlawful to discriminate on the basis of the
following 16 characteristics:
● sex
● relationship status
● pregnancy
● parental status
● breastfeeding
● age
● race
● impairment
● religious belief or
religious activity
● political belief or activity
● trade union activity
● lawful sexual activity
● gender identity
● sexuality
● family responsibilities
● association with, or
relation to, a person
identified on the basis of
the above.
Scope The scope of this policy covers all employees and
contractors of
Max Lionel Realty (MLR).
Resources Specific procedures for the implementation of this
policy are
available below and on the company intranet.
Responsibility Responsibility for the implementation of this
policy rests with all
employees, contractors and management of Max Lionel Realty.
Relevant
legislation, etc.
● Privacy Act 1988 (Cwlth)
● Equal Opportunity Act 2010 (Vic)
● Age Discrimination Act 2004 (Cwlth)
● Disability Discrimination Act 1992 (Cwlth)
● Racial Discrimination Act 1975 (Cwlth)
● Sex Discrimination Act 1984 (Cwlth)
● Estate Agents Act 1980 (Vic)
Updated/
authorised
10/2013 – Riz Mehra, CFO
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 11 of 17
Chapter 9 – Procurement policy and procedures
Max Lionel Realty procurement policy
Purpose The purpose of this policy is to ensure the acquisition
of
resources is carried out consistently, fairly and transparently
and in accordance with organisational requirements.
Scope The scope of this policy covers the purchasing and
acquisition of
resources by employees and contractors of Max Lionel Realty
(MLR).
Resources Specific procedures for the implementation of this
policy are
available below and on the company intranet.
Responsibility Responsibility for the implementation of this
policy rests with
employees and management of Max Lionel Realty with
responsibility for purchasing resources.
Relevant
legislation etc.
● Privacy Act 1988 (Cwlth)
● Estate Agents Act 1980 (Vic)
● Equal Opportunity Act 2010 (Vic)
● Corporations Act 2001 (Cwlth)
● A New Tax System (Goods and Services Tax) Act 1999
(Cwlth)
● Income Tax Assessment Act 1997 (Cwlth)
● Fair Work Act 2009 (Cwlth)
● Occupational Health and Safety Act 2004 (Vic)
Updated/
authorised
10/2013 – Riz Mehra, CFO
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 12 of 17
14 Principles governing the Max Lionel Realty procurement
process
1. Probity and ethical behaviour
The principle of probity and ethical behaviour governs the
conduct of all procurement
activities. Employees who have authority to procure goods and
services must comply with
the standards of integrity, probity, professional conduct and
ethical behaviour. Employees
or directors must not seek to benefit from supplier practices that
may be dishonest or
unethical.
2. Value for money
Value for money is the core principle underpinning
procurement. Contracted
organisations must be cost effective and efficient in the use of
resources whilst upholding
the highest standards of probity and integrity. In general, a
competitive process carried
out in an open, objective and transparent manner can achieve
the best value for money
in procurement.
3. Non-discrimination
This procurement policy is non-discriminatory. All potential
contracted suppliers should
have the same opportunities to compete for business and must
be treated equitably
based on their suitability for the intended purpose.
4. Risk management
Risk management involves the systematic identification,
analysis, treatment and, where
possible, the implementation of appropriate risk-mitigation
strategies. It is integral to
efficiency and effectiveness to proactively identify, evaluate,
and manage risks arising out
of procurement related activities. The risks associated with
procurement activity must be
managed in accordance with the organisation’s risk management
policy.
5. Responsible financial management
The principle of responsible financial management must be
applied to all procurement
activities. Factors that must be considered include:
● the availability of funds within an existing approved budget
● staff approving the expenditure of funds strictly within their
delegations
● measures to contain costs of the procurement without
compromising any
procurement principles.
6. Procurement planning
In order to achieve value for money, each procurement process
must be well planned and
conducted in accordance with the principles contained in this
document and comply with
all of the organisation’s policies and relevant legal and
regulatory requirements.
When planning appropriate procurement processes consideration
should be given to
adopting an approach that:
● encourages competition
● ensures that rules do not operate to limit competition by
discriminating against
particular suppliers
● recognises any industry regulation and licensing requirements
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 13 of 17
● secures and maintains contractual and related documentation
for the procurement
which best protects the organisation
● complies with the organisation’s delegations policy.
7. Buy Australian Made/support for Australian industry
Employees who are involved in procurement activities must
make a conscious effort to
maximise opportunities for Australian manufacturers and
suppliers to provide products
where there is practicable and economic value. In making a
value for money judgement
between locally-made and overseas-sourced goods, employees
are to take into account:
● whole-of-life costs associated with the good or service
● that the initial purchase price may not be a reliable indicator
of value
● the quality of locally made products
● the record of performance and delivery of local suppliers
● the flexibility, convenience and capacity of local suppliers for
follow on orders
● the scope for improvements to the goods and ‘add-ons’ from
local industry.
8. Pre-registered list of preferred suppliers
Max Lionel Realty shall maintain a pre-registered list of
preferred suppliers, following a
request for expressions of interest and an evaluation of the
submissions. Suppliers can
request to be evaluated for inclusion on the existing pre-register
list at any time.
All purchases under $5,000 may be made from preferred
suppliers without undertaking a
competitive process. Purchases above $5,000 where a preferred
supplier exists should
include a competitive process if practicable.
This list is reviewed at regular intervals with admission of
interested parties on a rolling
basis. Care should be taken to ensure that such lists are used in
an open and
non-discriminatory manner. Max Lionel Realty encourages new
contractors to provide
information on their experience, expertise, capabilities, pricing,
fees, and current
availability. It is in the interest of the organisation that the pool
of potential suppliers is
actively maintained and updated. Employees should be
encouraged to provide reports of
their experiences in working with each contractor/consultant to
assist future decisions
concerning commissioning suitable contractors and consultants.
9. Avoid conflict of interest
Employees and directors are required to be free of interests or
relationships in all aspects
of the procurement process. Employees and directors are not
permitted to personally gain
from any aspect of a procurement process.
Employees and directors shall ensure that to the best of their
knowledge, information and
belief, that at the date of engaging a contractor no conflict of
interest exists or is likely to
arise in the performance of the contractor’s obligations under
their contract.
Should employees or directors become aware of potential
conflicts of interest during the
contract period, they must advise the CEO and the Board of
Directors immediately.
Prior to any situation arising with potential for a conflict of
interest, complete disclosure
shall be made to the CEO and the Board of Directors to allow
sufficient time for a review.
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 14 of 17
10. Report collusive tendering
Employees should be aware of anti-competitive practices such
as collusive tendering. Any
evidence of suspected collusion in tendering should be brought
to the attention of the
CEO and the Board of Directors.
11. Competitive process
It is a basic principle of procurement that a competitive process
should be used unless
there are justifiable circumstances. For purchases under $5,000,
the list of preferred
suppliers may be used. The type of competitive process can vary
depending on the size
and characteristics of the contract to be awarded.
12. Direct invitation (selective or restricted tendering)
A process of direct sourcing to tender may be used. This may
involve:
● an invitation to organisations deemed appropriately qualified
for a particular
product or service (this may be appropriate for specialised
requirements in markets
where there is a limited number of suppliers or service
providers)
● an invitation to tender to organisations on MLR’s pre-
registered list of preferred
suppliers if applicable.
13. Evaluation and contract award
For projects being awarded, consideration will be given not
only to the most economically
advantageous tender, but also to the track record of the tender
respondent and the
degree of confidence that the panel has in the quality if the bid.
It will be the normal
practice to have the evaluation of tenders carried out by a team
with the requisite
competency.
14. Results of tendering process
All tender respondents should be informed in writing of the
result of a tendering process
immediately after a contract has been awarded.
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 15 of 17
Summary of procurement policy delegations
Authority Purchase amount Required number
of quotes
Comment
CEO and one
Director
Authority to sign
contracts for
products and
services over
$75,000.
Two or more
competitive quotes
for contracts over
$75,000.
Detailed services
contract required.
CEO Authority to sign
contracts for
products and
services up to
$75,000.
Two or more
competitive quotes.
Detailed services
contract required for
contracts over
$20,000.
General Managers
Delegated
authority only
through CEO
Authority to sign
contracts for
products and
services under
$30,000.
One or more
competitive quotes
preferred.
Provided they are
within the approved
budget and
consistent with
business/operational
and strategic
planning.
Managers Authority to sign
contracts for
products and
services under
$10,000.
One or more
competitive quotes
preferred.
Follow MLR
purchasing
procedures.
Agents Authority to sign
contracts for
products and
services under
$5,000.
Must use preferred
suppliers list.
Follow MLR
purchasing
procedures.
Contractors and
external
consultants
No authority. One or more
competitive quotes
preferred.
Must use preferred
suppliers list.
Contractors and
external consultants
must follow MLR
purchasing
procedures and must
seek approval for
purchases from
person holding
relevant authority.
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 16 of 17
Chapter 10 – Max Lionel Realty current tenants list
BSBPMG522 Undertake project work Max Lionel Realty
(simulated business)
© 2015 Innovation and Business Industry Skills Council Ltd 1st
edition version: 1
Page 17 of 17
Chapter 11 – List of pre-approved suppliers
Max Lionel Realty
List of preferred suppliers and contractors
● Ace Consultants: Project managers, IT technicians, technical
writers, marketers,
subject matter experts for short or long term human resourcing
needs.
● Innovative Travel: Business travel bookings
● Melbourne Car World: Fleet sales and service
● Ready Office Supplies: Computers, photocopiers, etc.
● Coffeeville: Business function catering
○ Catering menu:
<http://simulations.ibsa.org.au/coffeeville/menu.php>.
# Street Suburb
Property
Type
# Beds # Baths
OS
Parking
LUG
Y/N
BIRs
Y/N
Garden
Floor
Surface
Tenant 1 Name Tenant 2 Name
Tenant 3
Name
Tenant 4 Name
Lease
Commenced
Inspection
Due
Rent
P/W
67 Miller Street Preston House 3 2 2 Y Y Y Carpet Grace
Haines David Haines 6/22/2011 12/22/2013 420.00$
33 Alexandra Avenue Abbotsford House 2 1 1 N Y Y Carpet
Peter Hickman 7/19/2012 7/19/2013 310.00$
789 Carter Road Collingwood House 2 1 1 N N N Polished
Priscilla Schwartz Andrea Lewis 8/12/2012 8/12/2013 297.00$
45 Main Street Epping Townhouse 3 1 1 N Y N Carpet Phong
Lil Michael North Xin Ling 3/5/2012 9/5/2013 207.00$
22b Chestnut Street Northcote Apartment 1 1 0 N Y N Polished
Wendy Stuart 1/7/2012 7/7/2013 159.00$
12/445 Commercial Road South Preston Flat 3 2 1 Y Y N Carpet
Sarah Tatou Sydney Kellett 12/17/2009 12/17/2013 238.00$
72 Hoddle Street Collingwood Apartment 1 1 0 N Y N Carpet
Tom Casper Amanda Casper 6/3/2010 12/3/2013 326.00$
18 Abbotsford Street Westgarth Apartment 2 1 0 N Y N
Polished John Dean Brett Ellis 4/23/2012 10/23/2013 350.00$
3 Rooney Court Fitzroy Townhouse 3 1 2 N Y Y Carpet James
Rothfield Maria Teasdale Ben Dubois 1/15/2011 7/15/2013
389.00$
60 Kaola Street Coburg House 5 2 2 Y N Y Polished Nigel
Cooper Melissa O'Brien Dan Di Donato Elena Charles
2/28/2013 8/28/2013 332.00$
57 Rathdowne Street Thornbury House 4 2 2 Y N Y Carpet
Joanne Evers Craig Avery Kip McNeil Brendan Gorman
2/12/2013 8/12/2013 450.00$
1 Totzetti Court Carlton Flat 1 1 0 N Y Y Polished Tina
Pullman 5/6/2012 11/6/2013 365.00$
22 Darling Street South Preston House 4 2 2 Y N N Carpet
Maggie Stanton Penny Victor 9/9/2012 9/9/2013 298.00$
13 Darebin Road Northcote House 2 1 1 N Y Y Carpet Reece
Swan Sarah Swan 7/27/2012 7/27/2013 284.00$
1/427 Lygon Street Carlton Apartment 2 1 0 N Y N Polished
Anna Lomen Kelly Cheetham 6/27/2012 12/27/2013 363.00$
39 Southill Street Preston Townhouse 3 1 1 Y Y Y Carpet
Louise Appleton Gino Patony Quan Tho 1/27/2013 7/27/2013
256.00$
14/64 Brownes Road Thornbury Apartment 3 2 2 Y Y N
Polished Jack Morgan Sadie Morgan 5/31/2013 12/1/2013
380.00$
58 Johnston Street Northcote Flat 2 1 0 N Y Y Carpet Jim Percy
Paul Percy 1/3/2013 7/3/2013 450.00$
20 St Georges Road Brunswick Apartment 1 1 1 Y Y N Carpet
Owen Smythe 9/8/2012 9/8/2013 446.00$
74 Harrow Street Fitzroy Townhouse 3 2 2 N Y N Polished
David D'Angelo Carla D'Angelo 4/10/2013 10/10/2013 489.00$
502 Wilson Street Preston House 4 2 2 Y N Y Carpet Zita
Nicholson Andy Nicholson 5/11/2013 11/11/2013 465.00$
8 Moore Court Coburg House 3 2 2 Y N Y Carpet Cecelia
Barton Audrey Amber Kate Kingsley 1/22/2013 7/22/2013
310.00$
4 Beattie Crescent Westgarth Townhouse 2 1 0 N Y Y Polished
Julian Milliken Geoff Katz 8/29/2012 8/29/2013 340.00$
39 Hunters Road Preston House 3 2 1 N N N Carpet Minh Chi
Lin Waan Gracie Jiu 1/27/2013 7/27/2013 410.00$
15 Waldron Ave Brunswick House 2 1 0 N Y Y Carpet
Benjamin Drew Bella Salera 11/7/2009 11/7/2013 389.00$
211 Gower Street Thornbury House 3 2 1 N Y N Carpet Tahir
Singh Eashan Tendulkar Tajdar Deuskar 6/14/2010 12/14/2013
350.00$
41/27 Butler Street Collingwood Apartment 1 1 0 N Y N
Polished Helena Swain 2/23/2011 8/23/2013 367.00$
Current Tenants List
Property
Manager
PM Phone #
Susan Hunter 0411-222-333
Dominic Lazaro 0411-222-444
Susan Hunter 0411-222-333
Susan Hunter 0411-222-333
Dominic Lazaro 0411-222-444
Susan Hunter 0411-222-333
Dominic Lazaro 0411-222-444
Susan Hunter 0411-222-333
Susan Hunter 0411-222-333
Dominic Lazaro 0411-222-444
Susan Hunter 0411-222-333
Susan Hunter 0411-222-333
Dominic Lazaro 0411-222-444
Dominic Lazaro 0411-222-444
Susan Hunter 0411-222-333
Susan Hunter 0411-222-333
Susan Hunter 0411-222-333
Susan Hunter 0411-222-333
Dominic Lazaro 0411-222-444
Susan Hunter 0411-222-333
Susan Hunter 0411-222-333
Dominic Lazaro 0411-222-444
Dominic Lazaro 0411-222-444
Susan Hunter 0411-222-333
Susan Hunter 0411-222-333
Dominic Lazaro 0411-222-444
Susan Hunter 0411-222-333
Facilitator Guide Marking Guide
BSBPMG522 Undertake project work 1st edition version: 1
© 2015 Innovation and Business Industry Skills Council Ltd
Marking Guide
Assessment Task 3: Finalise and review project
Candidate’s Name Phone No.
Assessor’s Name Phone No.
Assessment Site
Assessment Date/s Time/s
Outcomes
Did the candidate:
Satisfactory
Yes No
Submit:
● a budget variation report for sign-off
● signed role descriptions for sign-off
● a handover report
● a post-project project review report?
Participate in project team meetings?
Submit all materials within the required timeframe?
Performance indicators
Did the candidate:
Satisfactory
Yes No
Complete financial recordkeeping associated with project and
check for
accuracy?
● Meet with project team to discuss.
● Submit budget variation report for forwarding to Chief
Financial
Officer.
● Report free from errors and showing required numeracy to
complete task.
Facilitator Guide Marking Guide
BSBPMG522 Undertake project work 1st edition version: 1
© 2015 Innovation and Business Industry Skills Council Ltd
Did the candidate:
Satisfactory
Yes No
Assign staff involved in project to new roles or reassign to
previous
roles?
● Meet with project team to assign roles as directed by
Operations
General Manager.
● Complete signed role description forms and submit to
Operations
General Manager.
Complete project documentation and obtain any necessary sign
offs for
concluding project?
● Submit all project documentation and deliverables for sign-off
by
Operations General Manager:
○ budget variation report for sign-off
○ signed role descriptions for sign-off
○ handover report for sign-off
○ post-project review report.
Review project outcomes and processes against the project
scope
and plan?
o review outcomes against objectives, including budgetary
performance
o review team processes
o discuss lessons learned from implementation of project.
Involve team members in the project review?
o review outcomes against objectives, including budgetary
performance
o review team processes
o discuss lessons learned from implementation of project.
Facilitator Guide Marking Guide
BSBPMG522 Undertake project work 1st edition version: 1
© 2015 Innovation and Business Industry Skills Council Ltd
Did the candidate:
Satisfactory
Yes No
Document lessons learned from the project and report within the
organisation?
-project review report to Operations General
Manager
for forwarding to stakeholders.
-project review report should contain:
o a review of outcomes against objectives, including
budgetary performance
o a review of team processes
o discussion of lessons learned from implementation of
project
o discussion of project management tools used, evaluation of
their contribution to the project and recommendations of
future alternatives where applicable.
Comments/feedback to participant
Outcome:
Successful Unsuccessful
Assessor name:
Assessor signature:
Assessment Task 3 BSBPMG522 Undertake project work
© 2015 Innovation and Business Industry Skills Council 1st
edition version: 1
Page 1 of 4
Finalise and review project
Submission details
Candidate’s Name Phone No.
Assessor’s Name Phone No.
Assessment Site
Assessment Date/s Time/s
The assessment task is due on the date specified by your
assessor. Any variations to this
arrangement must be approved in writing by your assessor.
Submit this document with
any required evidence attached. See specifications below for
details.
Performance objective
Candidates will demonstrate knowledge and skills required to
finalise and review
projects.
Assessment description
Following on from Assessment Tasks 1 and 2 and using the
workplace scenario
information provided, you will, drawing on consultation with
your project team, complete
financial record keeping, reassign staff to roles, complete
project documentation for
sign-off and review project outcomes against project scope and
plan. You will then
produce a report on the project for stakeholders.
Procedure
1. Review the simulated business documentation, including
policies and procedures,
in the document ‘Max Lionel Realty.docx’. Review templates
contained in the
document ‘Project planning templates.docx’ for possible use or
adaptation in
completing project requirements.
2. Review the scenario information provided in Appendix 3.
3. In consultation with your project team, complete financial
record-keeping for the
project:
a. compare budgeted spend with actual
b. produce a budget variation report.
Note: You may use or adapt the template provided. Meetings
may be observed by
your assessor. Follow your communication plan or agree to a
time and date.
Assessment Task 3 BSBPMG522 Undertake project work
© 2015 Innovation and Business Industry Skills Council 1st
edition version: 1
Page 2 of 4
4. In consultation with your project team and management,
assign project team
members to roles. Obtain agreement on new roles and
responsibilities. You may
use or adapt the template provided (under initiation and scope)
to record
agreement on new role descriptions.
Note: Meetings may be observed by your assessor. Follow your
communication plan
or agree to a time and date.
5. Produce a handover report for the Project Sponsor (the
assessor) for sign-off. You
may use or adapt the template provided.
6. In consultation with your project team:
a. review the project’s outcomes against objectives, including
budgetary
performance
b. review team processes
c. review the project management tools used, evaluate their
contribution to the
project and discuss possible alternatives
d. discuss lessons learned from implementation of the project.
Note: You may use or adapt the post-project review meeting
agenda template
provided. Meetings may be observed by your assessor. Follow
your
communication plan or agree to a time and date.
7. Produce a post-project review report for all stakeholders,
including the Board of
Directors, containing:
a. a review of project outcomes against objectives, including
budgetary
performance
b. a review of team processes
c. a review of the project management tools used, an evaluation
of their
contribution to the project and any recommendations for
alternative tools for
use in the future
d. a discussion of lessons learned from implementation of the
project
e. recommendations for the implementation of future projects
based on the
lessons learned, ensuring your report takes account of specific
organisational
requirements, e.g. legislative requirements and strategic plans.
Note: You may use or adapt the post-project review report
template provided.
8. Submit documentation as per specifications below.
Specifications
You must:
● participate in project meeting/s
● submit:
○ budget variation report for sign-off
○ signed role descriptions for sign-off
Assessment Task 3 BSBPMG522 Undertake project work
© 2015 Innovation and Business Industry Skills Council 1st
edition version: 1
Page 3 of 4
○ handover report
○ post-project project review report.
Your assessor will be looking for:
● communication and negotiation skills to work with team
members and other
stakeholders to maintain project schedules
● literacy skills to read, write and review a range of
documentation
● planning and organising skills to develop, monitor and
maintain implementation
schedules
● numeracy skills to analyse data and to compare timelines and
promotional costs
against budgets
● culturally appropriate communication skills to relate to
people from diverse
backgrounds and people with diverse abilities
● knowledge of relevant legislation from all levels of
government that may affect
aspects of business operations, such as:
○ anti-discrimination legislation
○ ethical principles
○ codes of practice
○ privacy laws
○ environmental issues
○ WHS
● knowledge of organisational structure, and lines of authority
and communication
within the organisation
● knowledge of how the project relates to organisation’s overall
mission, goals,
objectives and operations.
Adjustment for distance-based learners
● No variation of the task is required.
● A follow-up interview may be required (at the discretion of
the assessor).
● Documentation can be submitted electronically or posted in
the mail
● Meetings may be conducted and observed live or via an
appropriate
teleconferencing tool.
Assessment Task 3 BSBPMG522 Undertake project work
© 2015 Innovation and Business Industry Skills Council 1st
edition version: 1
Page 4 of 4
Appendix – Scenario
Max Lionel Realty
It is now time to review and finalise the project.
Work with your project team to review the outcomes, team
processes and lessons learned
from implementation.
Review the project’s budgetary performance and produce a
budget variation report for the
Chief Financial Officer.
Your Operations General Manager requires you to submit an
implementation report for
the Board of Directors that includes recommendations for the
improvement of
implementation for future projects.
Facilitator Guide Marking Guide
BSBPMG522 Undertake project work 1st edition version: 1
© 2015 Innovation and Business Industry Skills Council Ltd
Marking Guide
Assessment Task 2: Administer and monitor project
Candidate’s Name Phone No.
Assessor’s Name Phone No.
Assessment Site
Assessment Date/s Time/s
Outcomes
Did the candidate:
Satisfactory
Yes No
Submit:
● a written record of agreement with roles and responsibilities
● three status reports as per recordkeeping requirements
● risk management reports (may be change requests or issues
logs)
● project deliverables (drafts and final)?
Provide appropriate form of support: coaching, assistance with
deliverables, etc.?
Participate in project team meetings?
Submit all materials within the required timeframe?
Performance indicators
Did the candidate:
Satisfactory
Yes No
Take action to ensure project team members were clear about
their
responsibilities and the project requirements?
● Candidates should meet with project team to negotiate
responsibilities.
● Candidates should document agreement on templates
provided.
Facilitator Guide Marking Guide
BSBPMG522 Undertake project work 1st edition version: 1
© 2015 Innovation and Business Industry Skills Council Ltd
Did the candidate:
Satisfactory
Yes No
Provide support for project team members, especially with
regard to
specific needs, to ensure that the quality of the expected
outcomes of
the project and documented time lines are met?
● Candidate provides support to team member as per need and
so
that project outcomes can be met at required standard.
● Support should demonstrate (culturally appropriate)
communication and negotiation skills.
● Support needs to adhere to project parameters (cannot cost too
much to provide [each candidate has an hourly rate to
consider]);
cannot take too long to provide; cannot put project at risk.
Establish and maintain required recordkeeping systems
throughout the
project?
● Organisational recordkeeping system requires regular status
reports to record:
○ financial management and budget control.
● Project milestones, for example:
○ quality review completion
○ outcomes and deliverables.
Facilitator Guide Marking Guide
BSBPMG522 Undertake project work 1st edition version: 1
© 2015 Innovation and Business Industry Skills Council Ltd
Did the candidate:
Satisfactory
Yes No
Implement and monitor plans for managing project finances,
resources
(human, physical and technical) and quality?
● Complete status reports, including minutes of team meetings.
● Meet with team to:
○ clarify roles and responsibilities and ensure written record
of agreement, e.g. obtain signatures on roles and
responsibilities template provided
○ determine need for support and inform team members of
your support needs
○ discuss monitoring and recordkeeping systems as required
by the organisation
○ discuss risk processes for identifying risks and risk
management approaches.
Discussions indicate understanding of business documentation
and scenario requirements to demonstrate required literacy
for task.
● Follow project and risk management plans.
● Make required adjustments to plans if required to reflect
changing conditions.
Complete and forward project reports as required to
stakeholders?
● Status reports template competed.
● Status reports submitted to Operations General Manager.
● Status reports demonstrate required numeracy for task.
● Status reports submitted at 25%, 50%, 75% of timeline.
Undertake risk management as required to ensure project
outcomes
are met?
● Each candidate must identify, assess, and treat contingency to
ensure project outcomes.
● Each candidate should coordinate actions with team.
Achieve project deliverables?
● Candidate meets quality specifications outlined in Assessment
Task.
● Project deliverables demonstrate knowledge of organisational
strategic directions.
Facilitator Guide Marking Guide
BSBPMG522 Undertake project work 1st edition version: 1
© 2015 Innovation and Business Industry Skills Council Ltd
Comments/feedback to participant
Outcome:
Successful Unsuccessful
Assessor name:
Assessor signature:
Assessment Task 2 BSBPMG522 Undertake project work
© 2015 Innovation and Business Industry Skills Council 1st
edition version: 1
Page 1 of 4
Administer and monitor project
Submission details
Candidate’s Name Phone No.
Assessor’s Name Phone No.
Assessment Site
Assessment Date/s Time/s
The assessment task is due on the date specified by your
assessor. Any variations to this
arrangement must be approved in writing by your assessor.
Submit this document with
any required evidence attached. See specifications below for
details.
Performance objective
Candidates will demonstrate knowledge and skills required to
administer and monitor
projects.
Assessment description
Using the workplace scenario information provided, you will
work collaboratively with your
project team to administer and monitor a project (initiated,
planned and discussed in
Assessment Task 1) in order to achieve the project deliverables.
Procedure
1. Review the simulated business documentation, including
policies and procedures
in the document ‘Max Lionel Realty.docx’. Review templates
contained in the
document ‘Project planning templates.docx’ for possible use or
adaptation in
completing project requirements.
2. Review the scenario information provided in Appendix 2.
3. Determine monitoring and record-keeping system
requirements from scenario for
project as planned.
4. Determine personal need for support.
5. Meet with the team to:
a. clarify roles and responsibilities and ensure written record of
agreement, e.g.
obtain signatures on roles and responsibilities template provided
b. determine need for support and inform team members of your
support needs
Assessment Task 2 BSBPMG522 Undertake project work
© 2015 Innovation and Business Industry Skills Council 1st
edition version: 1
Page 2 of 4
c. discuss monitoring and record-keeping systems as required by
the
organisation
d. discuss risk processes for identifying risks and risk
management approaches.
Note: Minutes of these meetings should be attached to your
project status reports.
You may need to meet on several occasions. Meetings may be
observed by your
assessor. Follow your communication plan or agree to a time
and date.
6. Plan to support a team member. Arrange suitable time with
team member and
assessor (to observe). You may, for example, provide assistance
with deliverables,
coach, train, etc.
Note: Ensure you adhere to budgetary constraints and timelines.
All resources and
time spent on the project will count towards expenditure.
7. Meet with team member to provide support.
8. Complete the following personal roles and responsibilities:
a. implement monitoring and record-keeping, using or adapting
the template
provided
b. develop project deliverables
c. ensure quality assurance on draft deliverables as required by
your project
plan.
9. Undertake risk management as per your project plan. Provide
risk management
reports (may include change requests and/or issues logs). Use or
adapt the
templates provided.
Note: Your Operations General Manager (the assessor) will
inform your project team
of contingencies that you will need to manage. Coordinate
actions with your project
team members. Each team member will have at least one
contingency to manage.
10. Submit documentation as per specifications below.
Specifications
You must:
● participate in project meeting/s
● provide appropriate support to one team member
● submit:
○ a written record of agreement with roles and responsibilities
○ three status reports as per record-keeping requirements
○ risk management reports: change requests and/or issues logs
○ draft project deliverables for quality assurance
○ final project deliverables.
Assessment Task 2 BSBPMG522 Undertake project work
© 2015 Innovation and Business Industry Skills Council 1st
edition version: 1
Page 3 of 4
Your assessor will be looking for:
● communication and negotiation skills to work with team
members and other
stakeholders to maintain project schedules
● literacy skills to read, write and review a range of
documentation
● planning and organising skills to monitor and maintain
implementation schedules
● numeracy skills to analyse data and compare timelines and
implementation
● culturally appropriate communication skills to relate to
people from diverse
backgrounds and people with diverse abilities
● knowledge of relevant legislation from all levels of
government that may affect
aspects of business operations, such as:
○ anti-discrimination legislation
○ ethical principles
○ codes of practice
○ privacy laws
○ environmental issues
○ WHS
● knowledge of organisational structure and chains of authority
and communication
within the organisation
● knowledge of how the project relates to the organisation’s
overall mission, goals,
objectives and operations.
Adjustment for distance-based learners
● No variation of the task is required.
● A follow-up interview may be required (at the discretion of
the assessor).
● Documentation can be submitted electronically or posted in
the mail.
● Meetings may be conducted and observed live or via an
appropriate
teleconferencing tool.
Assessment Task 2 BSBPMG522 Undertake project work
© 2015 Innovation and Business Industry Skills Council 1st
edition version: 1
Page 4 of 4
Appendix – Scenario
Max Lionel Realty
It is now time to implement the project you initiated, planned
for and negotiated in
Assessment Task 1.
Work with your team to achieve agreed deliverables on time, to
budget, and up to the
required standard. Manage contingencies and renegotiate project
with stakeholders as
required.
As per organisational project management record keeping
system requirements, your
Operations General Manager requires regular status reports to
record:
● financial management and budget control
● project milestones, for example:
○ quality review completion
○ outcomes and deliverables.
Submit three status reports over course of project: at 25%, 50%,
75% of timeframe.
Risk management reports need to be submitted to the project
sponsor for each
contingency managed.
Recall the quality standards for deliverables:
● clearly communicate legal obligations, REIV obligations
● no grammar or spelling errors
● professional but friendly language
● fair and flexible delivery for intended audience
● meet audience requirements and sensitive to information
needs.
Facilitator Guide Marking Guide
BSBPMG522 Undertake project work 1st edition version: 1
© 2015 Innovation and Business Industry Skills Council Ltd
Marking Guide
Assessment Task 1: Define project and develop plan
Candidate’s Name Phone No.
Assessor’s Name Phone No.
Assessment Site
Assessment Date/s Time/s
Outcomes
Did the candidate:
Satisfactory
Yes No
Submit:
● project initiation and scope documents: project brief; project
scope; stakeholder analysis; communication plan; roles and
responsibilities; project snapshot
● a project plan (version 1 and version 2)
● a risk management plan (a risk register and a risk assessment
for each of the four risks) (version 1 and version 2)
● a budget (version 1 and version 2)?
Participate in discussion with the Operations General Manager
(the
assessor)?
Submit all materials within the required timeframe?
Performance indicators
Did the candidate:
Satisfactory
Yes No
Access project scope and other relevant documentation?
● describe project scope as including the development of
communication material for agents as determined by assessor;
exclusions as determined by assessor
● document scope, using template, for example
Facilitator Guide Marking Guide
BSBPMG522 Undertake project work 1st edition version: 1
© 2015 Innovation and Business Industry Skills Council Ltd
Did the candidate:
Satisfactory
Yes No
● describe other relevant documentation determine project and
to
provide content for project deliverables:
○ Max Lionel Realty simulated business documentation,
such as strategic directions, budget, risk management,
policies, etc.
○ REIV Code of Conduct
○ Estate Agents Act 1980 (Vic)
○ Equal Opportunity Act 2010 (Vic)
○ anti-discrimination legislation
○ ethical principles
○ privacy laws.
Define project stakeholders?
● Candidate interprets scenario, organisational chart and
management responsibilities to identify all or most of the
following as potential stakeholders:
○ project team, including technical experts
○ Operations General Manager/Project Sponsor: concerned
with overall success of project and integration with
business strategic objectives, etc.
○ Chief Financial Officer: Will need to review budgets
○ Human Resources Manager: Will be concerned with
coordinating with other HR projects and programs
○ Residential Manager: Will need to be informed of agent
requirements to attend meetings, briefing sessions, etc.
○ Commercial Manager: Will need to be informed of agent
requirements to attend meetings, briefing sessions, etc.
○ Investments Manager: Will need to be informed of agent
requirements to attend meetings, briefing sessions, etc.
○ clients: See Assessment Task 1 for detailed concerns
○ agents: See Assessment Task 1 for detailed concerns
○ tenants: See Assessment Task 1 for detailed concerns.
Seek clarification from delegating authority of any issues
related to the
project and project parameters?
● discuss changes in parameters with Operations General
Manager/Project Sponsor, for example:
○ reduction in budget to $10,000
○ shortened timeline for completion of project (Reduce by
10%).
Facilitator Guide Marking Guide
BSBPMG522 Undertake project work 1st edition version: 1
© 2015 Innovation and Business Industry Skills Council Ltd
Did the candidate:
Satisfactory
Yes No
Identify limits of own responsibility and reporting
requirements?
● As set out in project plan—personal responsibility and
timelines
for deliverables, reporting at 25%, 50%, 75% status, evaluation
reporting
Clarify the relationship of the project to other projects and to
the
organisation’s objectives? For example:
● Performance management: Performance management could
incorporate elements of ethical knowledge into performance
targets.
● Recruitment and induction: Ethics could form integral part of
future inductions.
● WHS management system: management of WHS related
contingencies will need to integrate with system requirements
such as risk assessment, management, consulting, reporting
and continuous improvement.
● Risk management: Project will need to follow risk
management
procedures and account for existing risk as identified in
organisational risk register.
● Financial management: project will need to adhere to
budgetary
constraints and financial objectives for the business as a whole
(See business plan, operational plan, risk register for simulated
business for details).
Determine and access available resources to undertake the
project?
For example:
● human resourcing (as provided by assessor – hourly cost must
be strictly accounted for)
● communication tools (provided and costed by candidates)
● catering at meetings, information briefings, etc. (provided and
or
costed by candidates)
● candidates should refer to use costs specified by preferred
suppliers, otherwise candidates may identify travel costs, etc.
and estimate.
Facilitator Guide Marking Guide
BSBPMG522 Undertake project work 1st edition version: 1
© 2015 Innovation and Business Industry Skills Council Ltd
Did the candidate:
Satisfactory
Yes No
Develop a project plan including timelines, work breakdown
structure,
roles and responsibilities and other details of how the project
will be
managed in relation to the project parameters?
● Candidate should include design, development,
implementation,
and evaluation stages.
● Candidate should include dependencies (may be presented in
Gantt format, for instance).
● Candidate should include periodic monitoring and quality
assurance.
Identify and access appropriate project management tools? For
example:
● software: Microsoft Word, Excel, Project, etc.
● Gantt, critical path method, PERT charts, etc.
● appropriate telecommunication tools, such as Skype,
identified if
required.
Formulate a risk management plan for the project, including
work
health and safety (WHS) considerations?
● Candidate identifies, assesses and suggests treatment of WHS
risk. Candidate should identify consulting, reporting and
continuous improvement requirements in order to work within
organisation’s WHS management system.
● Candidate identifies, assesses and plans treatment of at least
three additional risks, including financial risk. Candidate may
consider already identified risks in risk register.
Develop and approve the project budget?
● Budget accounts for all resources.
● Budget is correct and reflects level of numeracy required to
complete task.
● Resources are costed appropriately as per scenario or
realistically approximated.
Consult team members and take their views into account in
planning
the project?
● Candidate uses (culturally appropriate) communication skills
to
negotiate professionally with project team.
Facilitator Guide Marking Guide
BSBPMG522 Undertake project work 1st edition version: 1
© 2015 Innovation and Business Industry Skills Council Ltd
Did the candidate:
Satisfactory
Yes No
Finalise their project plan and gain any necessary approvals to
commence project according to documented plan?
● Candidate follows scenario to identify lines of authority for
project.
Comments/feedback to participant
Outcome:
Successful Unsuccessful
Assessor name:
Assessor signature:
Assessment Task 1 BSBPMG522 Undertake project work
© 2015 Innovation and Business Industry Skills Council 1st
edition version: 1
Page 1 of 6
Define project and develop plan
Submission details
Candidate’s Name Phone No.
Assessor’s Name Phone No.
Assessment Site
Assessment Date/s Time/s
The assessment task is due on the date specified by your
assessor. Any variations to this
arrangement must be approved in writing by your assessor.
Submit this document with
any required evidence attached. See specifications below for
details.
Performance objective
Candidates will demonstrate knowledge and skills required to
define projects and develop
project plans.
Assessment description
Using the workplace scenario information provided, you will
determine the scope of a
project and develop a portfolio of draft planning documentation
to discuss with your
Operations General Manager (the assessor). You will then
negotiate aspects of the project
with your assigned project team. Finally, you will submit final
planning documentation for
approval.
Procedure
1. Review the simulated business documentation, including
policies and procedures,
in the document ‘Max Lionel Realty.docx’. Review templates
contained in the
document ‘Project planning templates.docx’ for possible use or
adaptation in
completing project requirements.
2. Review the scenario information provided in Appendix 1.
3. Receive details from Operations General Manager (the
assessor) of your project
team, cost, skills, and suggested project deliverables and
timeframes.
4. Determine project scope. Develop appropriate initiation and
scope documents for
discussion with Operations General Manager (the assessor).
5. Determine additional documentation required to determine
project and develop
deliverables.
Assessment Task 1 BSBPMG522 Undertake project work
© 2015 Innovation and Business Industry Skills Council 1st
edition version: 1
Page 2 of 6
6. Define project stakeholders. Determine how you will engage
and manage
stakeholders to achieve project objectives. Develop
communication and
stakeholder management plans for discussion.
Note: Consider scenario information and organisational
structure to determine
stakeholders and stakeholder interests.
7. Identify personal responsibilities and reporting requirements.
8. Determine relationship of project to other projects, systems,
business operations,
strategic aims of organisation, and external legislative
requirements.
9. Determine resources and access to resources. Consult with
Operations General
Manager (the assessor) to clarify if necessary.
10. Determine project management tools, such as software (e.g.
Microsoft Word, MS
Excel, and MS Project) and templates, etc.
Note: You may use software tools or use or adapt the templates
provided.
11. Using an appropriate project management tool, develop your
project plan
(version 1). Include:
a. work breakdown structure: stages of development or of task
completion
(Design, Develop, Implement, Evaluate); opportunities for (peer
and
stakeholder) review and feedback; coordination of roles and
sharing of
responsibility for deliverables; dependencies
b. timelines
c. roles and responsibilities for each team member
d. resourcing requirements.
12. Develop a risk management plan for your project (version 1)
for discussion. Include
consideration of WHS risk management. Identify, assess and
suggest treatment of
at least three additional risks, including financial risk. Record
risks on a risk register
and complete a risk assessment document for each risk.
Note: You may use software tools or use or adapt the templates
provided.
13. Develop a budget (version 1) for the project.
Note: You may use software tools or use or adapt the template
provided.
14. Meet with Operations General Manager (the assessor) to
discuss:
a. project scope
b. additional documentation required to determine project and
develop
deliverables.
c. project stakeholders
d. personal responsibilities
e. relationship of project to other projects, systems, strategic
aims of
organisation
f. resources and access to resources
Assessment Task 1 BSBPMG522 Undertake project work
© 2015 Innovation and Business Industry Skills Council 1st
edition version: 1
Page 3 of 6
g. portfolio of documents:
i. project initiation and scope documents
ii. project plan (version 1)
iii. risk management plan (version 1)
iv. budget (version 1).
15. Ask for feedback from your Operations General Manager
(the assessor) on your
version 1 drafts and ensure understanding of any additional
project issues or
changes to project parameters.
16. Meet with your project team to:
a. negotiate roles and responsibilities
b. Agree on version 2 of documents for approval by Operations
General
Manager (the assessor):
i. project plan (version 2)
ii. risk management plan (version 2)
iii. budget (version 2).
c. Incorporate Operations General Manager (the assessor)
feedback into
planning project:
Note: The meeting will be observed by your assessor. Follow
your
communication plan or agree to a time and date.
When meeting with your team, be:
i. professional
ii. accommodating and conscious of varying skill levels,
interests,
backgrounds
iii. submit documentation as per specifications below.
Specifications
You must:
● meet with Operations General Manager to discuss project
scope and portfolio of
planning documents
● participate in project meeting/s with project team
● submit:
○ project initiation and scope documents, including: a project
brief; a project
scope; a stakeholder analysis; a communication plan; roles and
responsibilities; project snapshot
○ a project plan (version 1 and version 2)
○ a risk management plan (risk register and risk assessment for
each of four
risks) (version 1 and version 2)
○ a budget (version 1 and version 2).
Assessment Task 1 BSBPMG522 Undertake project work
© 2015 Innovation and Business Industry Skills Council 1st
edition version: 1
Page 4 of 6
Your assessor will be looking for:
● communication and negotiation skills to work with team
members and other
stakeholders to maintain project schedules
● literacy skills to read, write and review a range of
documentation
● planning and organising skills to develop project plans
● numeracy skills to analyse data and to compare timelines and
implementation
costs against budgets
● culturally appropriate communication skills to relate to
people from diverse
backgrounds and people with diverse abilities
● knowledge of relevant legislation from all levels of
government that may affect
aspects of business operations, such as:
○ anti-discrimination legislation
○ ethical principles
○ codes of practice
○ privacy laws
○ environmental issues
○ WHS
● knowledge of organisational structure and chains of authority
and communication
within the organisation
● knowledge of how the project relates to the organisation’s
overall mission, goals,
objectives and operations.
Adjustment for distance-based learners
● No variation of the task is required.
● A follow-up interview may be required (at the discretion of
the assessor).
● Documentation can be submitted electronically or posted in
the mail
● Meetings may be conducted and observed live or via an
appropriate
teleconferencing tool.
Assessment Task 1 BSBPMG522 Undertake project work
© 2015 Innovation and Business Industry Skills Council 1st
edition version: 1
Page 5 of 6
Appendix – Scenario
Max Lionel Realty
Max Lionel Realty (MLR), in order to build customer goodwill
and satisfy its legal and
ethical obligations, has decided to implement a program to:
● inform agents of legal and ethical obligations (particularly
with respect to WHS and
anti-discrimination legislation) and any standards or codes of
conduct followed by
the organisation
● promote high standards in professional conduct (see Real
Estate Institute of
Victoria (REIV) Code of Conduct and relevant legislation)
● inform clients, tenants and potential tenants of MLR’s
commitments
● achieve employee and client buy-in for initiative.
You are an external consultant (from Ace Consultants)
contracted to project manage
activities to achieve the objectives above.
Quality standards for deliverables:
● clearly communicate legal obligations and REIV obligations
● contain as content or support company strategic directions
● no grammar or spelling errors
● professional but friendly language
● fair and flexible delivery for intended audience
● meet audience requirements and sensitive to information
needs, cultural diversity.
Previous needs analysis for the project has uncovered
characteristics and requirements
of Residential and Commercial Agents and Clients:
Agents Clients Tenants
● under stress; time poor
● highly trained and
competent in selling
and managing real
estate
● unaware of legal,
ethical requirement.
just want to please
clients
● even if aware, have no
idea how to apply to
daily client practice
● cynical: e.g. ‘why do I
have to pay attention to
MLR’s internal
business? I just want
them to manage my
property.’
● time poor
● not sure of MLR
obligations and
commitment to best-of-
breed client service and
ethical practice, REIV
code of conduct
● sometimes feel
discriminated against
on basis of:
○ lifestyle
○ family status
○ cultural
background
○ income, etc.
Assessment Task 1 BSBPMG522 Undertake project work
© 2015 Innovation and Business Industry Skills Council 1st
edition version: 1
Page 6 of 6
Agents Clients Tenants
● unclear on overall
strategic aims of MLR
● culturally diverse.
● feel it’s the agent’s
obligation to fill
rental/lease properties
according to client
wishes: e.g. ‘I choose
who lives in/leases my
property’
● culturally diverse.
● residential agents have
been rude or insensitive
on occasion: e.g. ‘you
wouldn’t treat your rich
clients or investment
partners this way’
● do not feel they are
adequately consulted
● residential/commercial
agents/clients have let
themselves in without
consultation
● inspections are
sometimes
unannounced.
Project conditions are as follows:
● Six to eight team members (two to four candidates plus four
virtual team members)
who must be utilised and budgeted for. Operations General
Manager (the assessor)
will determine composition of project team.
● The structure of the work should include roles for project
sponsor, technical
experts, quality assurance of deliverables, project manager
(yourself initially and,
after provisional approval, as negotiated with your team), and
roles and
responsibilities for each team member to achieve the
deliverables according to
standards, etc.
● All reasonable resources (e.g. access to a room, computers,
software and
templates) will be provided. Paper and telecommunications
costs, for example, to
be covered by candidates. All resources must be costed and
included in your
budget.
● Budget: $15,000.
● Your Operations General Manager (the assessor) will suggest
Project planning templates

More Related Content

Similar to Project planning templates

ERP/SAP Project Charter
ERP/SAP Project CharterERP/SAP Project Charter
ERP/SAP Project CharterBogdan Gorka
 
Project management-plan
Project management-planProject management-plan
Project management-planTran Tien
 
Project_management_Amit_dubey
Project_management_Amit_dubeyProject_management_Amit_dubey
Project_management_Amit_dubeyAmit Dubey
 
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docx
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docxPROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docx
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docxwkyra78
 
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docx
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docxAssignment 3 Project PerformanceDue Week 8 and worth 150 .docx
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docxbraycarissa250
 
Project Manager Primer
Project Manager PrimerProject Manager Primer
Project Manager PrimerTom Cremins
 
IT-625 The Charter should be based on the attached document. The .docx
IT-625 The Charter should be based on the attached document. The .docxIT-625 The Charter should be based on the attached document. The .docx
IT-625 The Charter should be based on the attached document. The .docxADDY50
 
MBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docxMBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docxAASTHA76
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time ManagementSabrinaScott22
 
Article-How to Write a Project Charter
Article-How to Write a Project CharterArticle-How to Write a Project Charter
Article-How to Write a Project Charterjaydeep chaurasia
 
New projectplandefinition1
New projectplandefinition1New projectplandefinition1
New projectplandefinition1Jonathan Joyce
 
Project Management, Perspective, Planning And Implementation
Project Management, Perspective, Planning And ImplementationProject Management, Perspective, Planning And Implementation
Project Management, Perspective, Planning And ImplementationCamella Taylor
 
Project Charter - Outreach Events for the Company
Project Charter - Outreach Events for the CompanyProject Charter - Outreach Events for the Company
Project Charter - Outreach Events for the CompanyTimothy Cochran
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overviewcford1973
 
Project plan template v3.0 jan 2012
Project plan template v3.0 jan 2012Project plan template v3.0 jan 2012
Project plan template v3.0 jan 2012bm80
 
Assignment 1AgileProjectCharterTemplateExample.pdfC Examp.docx
Assignment 1AgileProjectCharterTemplateExample.pdfC Examp.docxAssignment 1AgileProjectCharterTemplateExample.pdfC Examp.docx
Assignment 1AgileProjectCharterTemplateExample.pdfC Examp.docxtrippettjettie
 
Step by Step Guide to Project Management
Step by Step Guide to Project ManagementStep by Step Guide to Project Management
Step by Step Guide to Project ManagementBrendon Yip
 

Similar to Project planning templates (20)

ERP/SAP Project Charter
ERP/SAP Project CharterERP/SAP Project Charter
ERP/SAP Project Charter
 
Project management-plan
Project management-planProject management-plan
Project management-plan
 
Project_management_Amit_dubey
Project_management_Amit_dubeyProject_management_Amit_dubey
Project_management_Amit_dubey
 
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docx
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docxPROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docx
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docx
 
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docx
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docxAssignment 3 Project PerformanceDue Week 8 and worth 150 .docx
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docx
 
Project Manager Primer
Project Manager PrimerProject Manager Primer
Project Manager Primer
 
Project charter template
Project charter templateProject charter template
Project charter template
 
Charter template 17.01.15
Charter template 17.01.15Charter template 17.01.15
Charter template 17.01.15
 
IT-625 The Charter should be based on the attached document. The .docx
IT-625 The Charter should be based on the attached document. The .docxIT-625 The Charter should be based on the attached document. The .docx
IT-625 The Charter should be based on the attached document. The .docx
 
MBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docxMBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time Management
 
Article-How to Write a Project Charter
Article-How to Write a Project CharterArticle-How to Write a Project Charter
Article-How to Write a Project Charter
 
Project Management Sample
Project Management SampleProject Management Sample
Project Management Sample
 
New projectplandefinition1
New projectplandefinition1New projectplandefinition1
New projectplandefinition1
 
Project Management, Perspective, Planning And Implementation
Project Management, Perspective, Planning And ImplementationProject Management, Perspective, Planning And Implementation
Project Management, Perspective, Planning And Implementation
 
Project Charter - Outreach Events for the Company
Project Charter - Outreach Events for the CompanyProject Charter - Outreach Events for the Company
Project Charter - Outreach Events for the Company
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
 
Project plan template v3.0 jan 2012
Project plan template v3.0 jan 2012Project plan template v3.0 jan 2012
Project plan template v3.0 jan 2012
 
Assignment 1AgileProjectCharterTemplateExample.pdfC Examp.docx
Assignment 1AgileProjectCharterTemplateExample.pdfC Examp.docxAssignment 1AgileProjectCharterTemplateExample.pdfC Examp.docx
Assignment 1AgileProjectCharterTemplateExample.pdfC Examp.docx
 
Step by Step Guide to Project Management
Step by Step Guide to Project ManagementStep by Step Guide to Project Management
Step by Step Guide to Project Management
 

More from danhaley45372

Your initial post should be 2-3 paragraphs in length.Inclu.docx
Your initial post should be 2-3 paragraphs in length.Inclu.docxYour initial post should be 2-3 paragraphs in length.Inclu.docx
Your initial post should be 2-3 paragraphs in length.Inclu.docxdanhaley45372
 
Your initial post should be made during Unit 2,  January 21st at 4.docx
Your initial post should be made during Unit 2,  January 21st at 4.docxYour initial post should be made during Unit 2,  January 21st at 4.docx
Your initial post should be made during Unit 2,  January 21st at 4.docxdanhaley45372
 
Your initial post should be at least 450+ words and in APA forma.docx
Your initial post should be at least 450+ words and in APA forma.docxYour initial post should be at least 450+ words and in APA forma.docx
Your initial post should be at least 450+ words and in APA forma.docxdanhaley45372
 
Your initial post should be made during Unit 2, january 21st at 4.docx
Your initial post should be made during Unit 2, january 21st at 4.docxYour initial post should be made during Unit 2, january 21st at 4.docx
Your initial post should be made during Unit 2, january 21st at 4.docxdanhaley45372
 
Your initial post should be made during, Submissions after this time.docx
Your initial post should be made during, Submissions after this time.docxYour initial post should be made during, Submissions after this time.docx
Your initial post should be made during, Submissions after this time.docxdanhaley45372
 
Your essay should address the following.(a) How  is the biologic.docx
Your essay should address the following.(a) How  is the biologic.docxYour essay should address the following.(a) How  is the biologic.docx
Your essay should address the following.(a) How  is the biologic.docxdanhaley45372
 
Your initial post is due by midnight (1159 PM) on Thursday. You mus.docx
Your initial post is due by midnight (1159 PM) on Thursday. You mus.docxYour initial post is due by midnight (1159 PM) on Thursday. You mus.docx
Your initial post is due by midnight (1159 PM) on Thursday. You mus.docxdanhaley45372
 
Your individual sub-topic written (MIN of 1, MAX 3 pages)You.docx
Your individual sub-topic written (MIN of 1, MAX 3 pages)You.docxYour individual sub-topic written (MIN of 1, MAX 3 pages)You.docx
Your individual sub-topic written (MIN of 1, MAX 3 pages)You.docxdanhaley45372
 
Your HR project to develop a centralized model of deliveri.docx
Your HR project to develop a centralized model of deliveri.docxYour HR project to develop a centralized model of deliveri.docx
Your HR project to develop a centralized model of deliveri.docxdanhaley45372
 
Your Immersion Project for this course is essentially ethnographic r.docx
Your Immersion Project for this course is essentially ethnographic r.docxYour Immersion Project for this course is essentially ethnographic r.docx
Your Immersion Project for this course is essentially ethnographic r.docxdanhaley45372
 
Your country just overthrew its dictator, and you are the newly .docx
Your country just overthrew its dictator, and you are the newly .docxYour country just overthrew its dictator, and you are the newly .docx
Your country just overthrew its dictator, and you are the newly .docxdanhaley45372
 
Your have been contracted by HealthFirst Hospital Foundation (HHF),.docx
Your have been contracted by HealthFirst Hospital Foundation (HHF),.docxYour have been contracted by HealthFirst Hospital Foundation (HHF),.docx
Your have been contracted by HealthFirst Hospital Foundation (HHF),.docxdanhaley45372
 
Your group presentationWhat you need to do.docx
Your group presentationWhat you need to do.docxYour group presentationWhat you need to do.docx
Your group presentationWhat you need to do.docxdanhaley45372
 
Your contribution(s) must add significant information to the dis.docx
Your contribution(s) must add significant information to the dis.docxYour contribution(s) must add significant information to the dis.docx
Your contribution(s) must add significant information to the dis.docxdanhaley45372
 
Your good friends have just adopted a four-year-old child. At th.docx
Your good friends have just adopted a four-year-old child. At th.docxYour good friends have just adopted a four-year-old child. At th.docx
Your good friends have just adopted a four-year-old child. At th.docxdanhaley45372
 
Your good friends have just adopted a four-year-old child. At this p.docx
Your good friends have just adopted a four-year-old child. At this p.docxYour good friends have just adopted a four-year-old child. At this p.docx
Your good friends have just adopted a four-year-old child. At this p.docxdanhaley45372
 
Your goals as the IT architect and IT security specialist are to.docx
Your goals as the IT architect and IT security specialist are to.docxYour goals as the IT architect and IT security specialist are to.docx
Your goals as the IT architect and IT security specialist are to.docxdanhaley45372
 
Your essay should address the following problem.(a) What is .docx
Your essay should address the following problem.(a) What is .docxYour essay should address the following problem.(a) What is .docx
Your essay should address the following problem.(a) What is .docxdanhaley45372
 
Your future financial needs will be based on the income you can reas.docx
Your future financial needs will be based on the income you can reas.docxYour future financial needs will be based on the income you can reas.docx
Your future financial needs will be based on the income you can reas.docxdanhaley45372
 
Your friend Lydia is having difficulty taking in the informati.docx
Your friend Lydia is having difficulty taking in the informati.docxYour friend Lydia is having difficulty taking in the informati.docx
Your friend Lydia is having difficulty taking in the informati.docxdanhaley45372
 

More from danhaley45372 (20)

Your initial post should be 2-3 paragraphs in length.Inclu.docx
Your initial post should be 2-3 paragraphs in length.Inclu.docxYour initial post should be 2-3 paragraphs in length.Inclu.docx
Your initial post should be 2-3 paragraphs in length.Inclu.docx
 
Your initial post should be made during Unit 2,  January 21st at 4.docx
Your initial post should be made during Unit 2,  January 21st at 4.docxYour initial post should be made during Unit 2,  January 21st at 4.docx
Your initial post should be made during Unit 2,  January 21st at 4.docx
 
Your initial post should be at least 450+ words and in APA forma.docx
Your initial post should be at least 450+ words and in APA forma.docxYour initial post should be at least 450+ words and in APA forma.docx
Your initial post should be at least 450+ words and in APA forma.docx
 
Your initial post should be made during Unit 2, january 21st at 4.docx
Your initial post should be made during Unit 2, january 21st at 4.docxYour initial post should be made during Unit 2, january 21st at 4.docx
Your initial post should be made during Unit 2, january 21st at 4.docx
 
Your initial post should be made during, Submissions after this time.docx
Your initial post should be made during, Submissions after this time.docxYour initial post should be made during, Submissions after this time.docx
Your initial post should be made during, Submissions after this time.docx
 
Your essay should address the following.(a) How  is the biologic.docx
Your essay should address the following.(a) How  is the biologic.docxYour essay should address the following.(a) How  is the biologic.docx
Your essay should address the following.(a) How  is the biologic.docx
 
Your initial post is due by midnight (1159 PM) on Thursday. You mus.docx
Your initial post is due by midnight (1159 PM) on Thursday. You mus.docxYour initial post is due by midnight (1159 PM) on Thursday. You mus.docx
Your initial post is due by midnight (1159 PM) on Thursday. You mus.docx
 
Your individual sub-topic written (MIN of 1, MAX 3 pages)You.docx
Your individual sub-topic written (MIN of 1, MAX 3 pages)You.docxYour individual sub-topic written (MIN of 1, MAX 3 pages)You.docx
Your individual sub-topic written (MIN of 1, MAX 3 pages)You.docx
 
Your HR project to develop a centralized model of deliveri.docx
Your HR project to develop a centralized model of deliveri.docxYour HR project to develop a centralized model of deliveri.docx
Your HR project to develop a centralized model of deliveri.docx
 
Your Immersion Project for this course is essentially ethnographic r.docx
Your Immersion Project for this course is essentially ethnographic r.docxYour Immersion Project for this course is essentially ethnographic r.docx
Your Immersion Project for this course is essentially ethnographic r.docx
 
Your country just overthrew its dictator, and you are the newly .docx
Your country just overthrew its dictator, and you are the newly .docxYour country just overthrew its dictator, and you are the newly .docx
Your country just overthrew its dictator, and you are the newly .docx
 
Your have been contracted by HealthFirst Hospital Foundation (HHF),.docx
Your have been contracted by HealthFirst Hospital Foundation (HHF),.docxYour have been contracted by HealthFirst Hospital Foundation (HHF),.docx
Your have been contracted by HealthFirst Hospital Foundation (HHF),.docx
 
Your group presentationWhat you need to do.docx
Your group presentationWhat you need to do.docxYour group presentationWhat you need to do.docx
Your group presentationWhat you need to do.docx
 
Your contribution(s) must add significant information to the dis.docx
Your contribution(s) must add significant information to the dis.docxYour contribution(s) must add significant information to the dis.docx
Your contribution(s) must add significant information to the dis.docx
 
Your good friends have just adopted a four-year-old child. At th.docx
Your good friends have just adopted a four-year-old child. At th.docxYour good friends have just adopted a four-year-old child. At th.docx
Your good friends have just adopted a four-year-old child. At th.docx
 
Your good friends have just adopted a four-year-old child. At this p.docx
Your good friends have just adopted a four-year-old child. At this p.docxYour good friends have just adopted a four-year-old child. At this p.docx
Your good friends have just adopted a four-year-old child. At this p.docx
 
Your goals as the IT architect and IT security specialist are to.docx
Your goals as the IT architect and IT security specialist are to.docxYour goals as the IT architect and IT security specialist are to.docx
Your goals as the IT architect and IT security specialist are to.docx
 
Your essay should address the following problem.(a) What is .docx
Your essay should address the following problem.(a) What is .docxYour essay should address the following problem.(a) What is .docx
Your essay should address the following problem.(a) What is .docx
 
Your future financial needs will be based on the income you can reas.docx
Your future financial needs will be based on the income you can reas.docxYour future financial needs will be based on the income you can reas.docx
Your future financial needs will be based on the income you can reas.docx
 
Your friend Lydia is having difficulty taking in the informati.docx
Your friend Lydia is having difficulty taking in the informati.docxYour friend Lydia is having difficulty taking in the informati.docx
Your friend Lydia is having difficulty taking in the informati.docx
 

Recently uploaded

Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...PsychoTech Services
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 

Recently uploaded (20)

Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 

Project planning templates

  • 1. Part of a suite of support materials for the BSB Business Services Training Package Project Planning Templates BSBPMG522 Undertake project work Table of Contents 1.1 – Initiation and scope ............................................................................................... ....1 Project brief ............................................................................................... ....................1 Project scope document ............................................................................................... 2 Stakeholder analysis ...............................................................................................
  • 2. .....3 Communication plan (example) ...................................................................................4 Roles and responsibilities ............................................................................................5 Project snapshot ............................................................................................... ............6 1.2 – Planning ............................................................................................... ......................7 Work breakdown structure ...........................................................................................7 Project plan ............................................................................................... ....................7 Gantt chart ............................................................................................... .................. 11 Activities schedule ............................................................................................... ...... 13 Budget ............................................................................................... ......................... 14 Risk register
  • 3. ............................................................................................... ................ 15 Risk assessment form ............................................................................................... 16 1.3 – Implementation ............................................................................................... ....... 17 Change requests ............................................................................................... ......... 17 Issues log.......................................................................................... .......................... 17 1.4 – Monitoring ............................................................................................... ................ 19 Status update report ............................................................................................... .. 19 1.5 – Finalising and review..................................................................................... ......... 20 Budget variation report .............................................................................................. 20 Post-project review meeting
  • 4. ...................................................................................... 21 Handover report ............................................................................................... .......... 22 Post-project review report ......................................................................................... 23 BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 1 of 24 1.1 – Initiation and scope Project brief Project purpose and rationale The justification and validity of the project needs to be confirmed before the project proceeds. This document is used to clarify the project purpose and justification and to gain approval to proceed to the next phase. Project title
  • 5. Working title. Project purpose Describe the purpose/need/rationale/feasibility for the project. Background and strategic context Explain the background to the project and how it relates to the key strategic plans. Priority Note the importance and/or urgency of the project to the organisation. Related projects Any other projects that have been undertaken in the past, are currently underway, or planned for the future that will or may be affected by, or simply connected to, this project. Project client/owner The person who requires the project to be undertaken. Project sponsor The person who is providing the funds and has the ultimate authority over the project. Project manager
  • 6. The person who has the responsibility to manage the project on a day-to-day basis. Project status What has already been decided about the project? What decisions have already been made? What work has already been done in relation to the project? Any assumptions or constraints? Special provisions Special regulations, ethical or legal considerations, etc. Project approvals Add any signatures that are required for approval to proceed to the next phase. Project Manager Project Sponsor Project Client/Owner Other Project Title: Project Client: Date: Version: Project Sponsor: Project Manager: File Name: Page x of y
  • 7. BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 2 of 24 Project scope document This template is a tool that can be used with key stakeholders to clearly define the logical boundaries of the project. Ensure that you note any requirements that are out of scope to achieve absolute clarity about what is and is not covered by this project, and to avoid the potential for problems later on. In Scope Out of scope (exclusions) Assumptions Constraints Project Title: Project Client: Date: Version: Project Sponsor: Project Manager:
  • 8. File Name: Page x of y BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 3 of 24 Stakeholder analysis Use this template to identify areas, groups or individuals who may participate in, or are affected by, the project. Include everyone who has a vested interest. A useful question to ask is: ‘What will make this project a success for you?’ Name Work area Stakeholder type (client, end-user) Impact on/by project, requirements, success criteria
  • 9. Project Title: Project Client: Date: Version: Project Sponsor: Project Manager: File Name: Page x of y BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 4 of 24 Communication plan (example) What Who Purpose When/frequency Type/methods Initiation meeting All stakeholders. Gather information for initiation plan.
  • 10. FIRST Before project start date. Meeting. Distribute project initiation plan All stakeholders. Distribute plan to alert stakeholders of project scope and to gain buy in. Before kick-off meeting. Before project start date. Project snapshot distributed via
  • 11. hard copy or electronically. May be posted on project website. Project kick-off All stakeholders. Communicate plans and stakeholder roles/ responsibilities. Encourage communication among stakeholders. At or near project start date. Meeting. Status
  • 12. reports All stakeholders and project office. Update stakeholders on progress of the project. Regularly scheduled. Weekly is recommended for small-medium projects. Distribute status report electronically and post via website. Team
  • 13. meetings Entire project team. Individual meetings for sub-teams as appropriate. To review detailed plans (tasks, assignments, and action items). Regularly scheduled. Weekly is recommended for entire team. Weekly or bi-weekly for sub-teams as needed. Meeting: detailed
  • 14. plan. Sponsor meetings Sponsor/s and Project Manager. Update sponsor/s on status and discuss critical issues. Seek approval for changes to project plan. Regularly scheduled. Recommended bi-weekly or monthly and also as needed when
  • 15. issues cannot be resolved or changes need to be made to project plan. Meeting. Project Title: Project Client: Date: Version: Project Sponsor: Project Manager: File Name: Page x of y BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 5 of 24 Roles and responsibilities It is important to identify who the major players are on the project. List the major project roles, responsibilities and the actual people involved. Add in any additional roles as required.
  • 16. Role Name/s Responsibilities Signature/s (if required) Project client/owner The person who requires the project to be undertaken. Project sponsor/project director/project board Senior management of the project. Accountable for the success of the project. Has the authority to commit resources. Project manager Person responsible for running the project on a day-to-day basis within defined authorities for cost and schedule as agreed with the project
  • 17. sponsor/board. Manager of the project manager The operational/line manager who the project manager reports to on a day-to-day basis. Project team members Staff who will be working on the project. Steering committee/ working party To provide advice and recommendations. Project Title: Project Client: Date: Version:
  • 18. Project Sponsor: Project Manager: File Name: Page x of y BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 6 of 24 Project snapshot The project snapshot summarises the purpose, deliverables, stakeholders, resources, risks, interdependencies and success criteria of the project. Project snapshot Name of project: Project purpose: What are the goals/objectives of this project? Why are we undertaking it? What is the problem/opportunity? Deliverables with timeframes What, when, etc.
  • 19. Stakeholders Who is the sponsor, project manager, customers, and other key groups who can impact, or be impacted by, this project. Resources Cash flow, people, equipment, facilities, software, etc. Risks Resource limitations, deadlines, budget, technology, legal and other constraints, etc. Interdependencies With other projects, groups, system interfaces, etc. Success criteria How we know we are successful. Project Title: Project Client: Date: Version: Project Sponsor: Project Manager:
  • 20. File Name: Page x of y BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 7 of 24 1.2 – Planning Work breakdown structure A work breakdown structure (WBS) in project management is a tool used to define and group the project’s discrete work elements (or tasks) in a way that helps organise and define the total work scope of the project. The WBS is a dynamic tool and can be revised and updated as needed by the project manager. Level 1 Level 2 Level 3 Task 1 Sub-task 1.1 Work item 1.1.1
  • 21. Work item 1.1.2 Work item 1.1.3 Sub-task 1.2 Work item 1.2.1 Work item 1.2.2 Work item 1.2.3 Task 2 Sub-task 2.1 Work item 2.1.1 Work item 2.1.2 Work item 2.1.3 Sub-task 2.2 Work item 2.2.1 Work item 2.2.2 Project Title: Project Client: Date: Version: Project Sponsor: Project Manager: File Name: Page x of y
  • 22. Project plan The project plan is the basis for monitoring and controlling the project. All project information is http://en.wikipedia.org/wiki/Project_management BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 8 of 24 consolidated to date, forming the basis for monitoring and controlling once implementation of the project commences. Project title: Project purpose From project proposal – update if required. Background and strategic context From project proposal – update if required. Other related projects From project proposal – update if required.
  • 23. Project objective From project proposal – update if required. Scope including key deliverables From project proposal – update if required. In scope. Out of scope. Assumptions Constraints Deliverables Governance From project proposal – update if required. Attach a project organisation chart and additional information on responsibilities if required. Project client/owner From project proposal. Project sponsor Project Manager
  • 24. Manager of the project manager BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 9 of 24 Project team members Key stakeholders From project proposal – update if required. Include a more detailed stakeholder analysis in the Appendices, if required. Schedule Using the information you generated in the work breakdown structure, update the schedule. Include a Gantt chart or additional planning information in the Appendices. Item Milestone date Responsibility
  • 25. Resource and cost plan Resource planning is where you determine what resources (people, equipment and materials) and what quantities of each should be used to perform activities. Once the resources have been determined, estimate the project costs. Include a more detailed resource and cost plan in the appendices if required. Deliverable/milestone/phase Resource Cost Project risk assessment From project proposal – update if required. Include a more detailed risk management plan in the appendices.
  • 26. BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 10 of 24 Risk Level (high/medium/low) Management strategy Quality management plan Include a high level quality management plan here. Include a more detailed quality management plan in the appendices if required. Item from WBS Agreed quality standard Recovery procedure Communications and reporting
  • 27. Include a high level communications plan here. Include a more detailed communications management plan in the appendices if required. Stakeholder Information required When required Format Controls Outline how you are going to track, monitor and report on the project. For example: ● status reports BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 11 of 24 ● exception reports ● issues/risk log ● variance requests. Appendices
  • 28. List the appendices that are attached to your project plan, for example: ● stakeholder needs analysis ● work breakdown structure ● Gantt chart ● activities schedule ● budget/cash flow ● human resource planning schedule ● roles and responsibilities ● procurement schedule ● combined resources and cost schedule ● risk management plan ● quality management plan ● communications management plan. Future related projects Project approvals Add any signatures that are required for approval to proceed to
  • 29. the next phase. Project Manager Project Sponsor Project Client/Owner Other Project Title: Project Client: Date: Version: Project Sponsor: Project Manager: File Name: Page x of y Gantt chart To use a Gantt chart, list the activities and tasks in column A, select an appropriate time interval (days, weeks or months), allocate the dates to columns B onwards and plot the expected time duration (total time from start to completion) under the appropriate column by selecting shading BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st
  • 30. edition version: 1 Page 12 of 24 from the cells. When you wish to provide a status report, simply colour or shade in black those items that are completed or estimate the percentage complete. This will give you an immediate visual representation as to whether or not you are on schedule. You can add extra columns for assignment of responsibilities, etc. For small projects, a Gantt chart can be created as a spreadsheet. Activity/task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Legend If there are many tasks or stages in your project, you can identify them with a key or legend.
  • 31. Task 1 Task 5 Task 2 Task 6 Task 3 Task 7 Task 4 Task 8 Project Title: Project Client: Date: Version: Project Sponsor: Project Manager: File Name: Page x of y BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 13 of 24 Activities schedule The activities schedule is a tool used to monitor individual activities against the project plan. Information recorded on the schedule can be used when providing project status updates to stakeholders.
  • 32. Phases & activities Responsibility Resources Effort (hrs) Started Deadline Actually completed Comment/status Project Title: Project Client: Date: Version: Project Sponsor: Project Manager: File Name: Page x of y BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1
  • 33. Page 14 of 24 Budget The project budget is a prediction of the costs associated with a particular project. These costs include labour, materials, and other resources required to complete the project. Project Name: Income Inc. GST Ex. GST Total income Expense Inc. GST Ex. GST Subtotal Contingency (+10%) TOTAL
  • 34. Project Title: Project Client: Date: Version: Project Sponsor: Project Manager: File Name: Page x of y BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 15 of 24 Risk register This template is used to record identified risks associated with your project, analyse the impact and determine resultant action to be taken. Risk Likelihood (H/M/L) Impact (H/M/L) Risk response
  • 35. (contingency strategies) Responsible Project Title: Project Client: Date: Version: Project Sponsor: Project Manager: File Name: Page x of y BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 16 of 24
  • 36. Risk assessment form Identified risks are logged on a risk form and a copy is forwarded to the project manager. Project details Project Name: Project Name Project name to which the risk relates. Project Manager: Name of the project manager responsible for mitigating the risk. Risk details Risk ID: Number allocated to this risk. Raised by: Name of person who has raised the risk. Date raised: Date of completion of this form. Description of risk: Briefly describe the identified risk and its possible impact on the project (e.g. scope, resources, deliverables, timelines and/or budgets). Likelihood of risk: Describe and rank the likelihood of the risk occurring (i.e. low, medium or high).
  • 37. Impact of risk: Describe and rank the impact on the project if the risk occurs (i.e. low, medium or high). Risk mitigation Preventative actions recommended: Briefly describe any action that should be taken to prevent the risk from occurring. Contingency actions recommended: Briefly describe any action that should be taken, should the risk occur, to minimise its impact on the project. Approval details Supporting documentation: Details of any supporting documentation used to substantiate this risk. Signature: _______________________ Date: ___ /___ /____ PLEASE FORWARD THIS FORM TO THE PROJECT MANAGER
  • 38. Project Title: Project Client: Date: Version: Project Sponsor: Project Manager: File Name: Page x of y BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 17 of 24 1.3 – Implementation Change requests This form is used to assist with recording and management of changes in scope, time, quality or budget. The change management procedure must be negotiated with the key stakeholders prior to the sign-off of the project plan. Change request – Project Issued by Item affected
  • 39. Nature of change requested Reason for change Impact on scope Impact on budget Impact on schedule Change authorised: Yes/No Adj. completion date: Adj. final budget: $ Signed: Project Manager Signed Sponsor Signed Client
  • 40. Signed Date Date Date Date Project Title: Project Client: Date: Version: Project Sponsor: Project Manager: File Name: Page x of y Issues log In this template all issues are treated as risks. They should be recorded when they arise, assigned BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 18 of 24 a number and responsibility, a recovery strategy or alternate path agreed, acted upon and recorded when closed. Item Strategy Date logged Date resolved
  • 41. Signed: Project Manager Signed: Sponsor Signed: Client Signed: Date: Date: Date: Date: Project Title: Project Client: Date: Version: Project Sponsor: Project Manager:
  • 42. File Name: Page x of y BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 19 of 24 1.4 – Monitoring Status update report This is one example of a status report. The preferred format should be negotiated with the project sponsor. Attach minutes of project meetings. Status report – Project Item Work completed to-date Milestone date Revised/ actual date Budgeted cost Revised/ actual cost Responsible
  • 43. Project Title: Project Client: Date: Version: Project Sponsor: Project Manager: File Name: Page x of y BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 20 of 24 1.5 – Finalising and review Budget variation report The project budget is a prediction of the costs associated with a particular project. These costs include labour, materials, and other resources required to complete the project.
  • 44. Project name: Income Budget Actual % Variation Total income Expense Budget Actual % Variation Subtotal TOTAL Project Title: Project Client: Date: Version: Project Sponsor: Project Manager: File Name: Page x of y BSBPMG522 Undertake project work Project Planning
  • 45. Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 21 of 24 Post-project review meeting This template provides a proposed post-project review meeting agenda, detailing items to be discussed when reviewing the overall project. Post-Project Review Meeting – Agenda Topic Speaker Time Brief overview of project: Purpose of project, major accomplishments, comments. Project Manager 5 mins Review by team: Goals, objectives, deliverables, schedule, budget, and success criteria (Were they met, partially met, or missed?). All 10 mins What worked/what could have gone better?
  • 46. Some areas to consider: ● project planning ● project management ● project scheduling and tracking ● project estimating ● communication (with team, other groups/stakeholders, sponsor) ● risk management ● vendor management ● issues management ● stakeholder management ● resourcing ● users ● development approach: ○ methodology ○ analysis and design ○ development ○ testing
  • 47. ○ implementation ● training, documentation ● technology ● overall approach to project (i.e. vendor package, staged implementation, etc.) ● production and operation support. All 20 mins Lessons learned All 10 mins Next steps All 5 mins Project Title: Project Client: Date: Version: Project Sponsor: Project Manager: File Name: Page x of y BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 22 of 24
  • 48. Handover report This template summarises the project as delivered and any agreed changes to baseline scope, quality, costs and schedule. Handover report Initial overall objectives Agreed changes to objectives Final agreed deliverables Item Budgeted cost Final cost Schedule date Final date Total Issues summary Item Strategy Date logged Date resolved
  • 49. Documents attached No. Title ____________________ Project Manager _____________________ Project Sponsor _____________________ Project Client Project Title: Project Client: Date: Version: Project Sponsor: Project Manager: File Name: Page x of y
  • 50. BSBPMG522 Undertake project work Project Planning Templates © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 23 of 24 Post-project review report This template can be used to guide you through the process of conducting a post-project review. This template can be used to document the key learning in terms of what worked well and what could have been improved. Post-Project Review Report Name of project: Date and location of meeting: Names of attendees: 1. Overview by Project Manager: Brief summary of highlights and achievements, etc.
  • 51. 2. Review by team of goals, objectives/deliverables and schedule as outlined in project plan Cut and paste from project plan. Met Missed Partially met Comments Project goal/s Objectives/deliverables Success criteria Schedule Budget BSBPMG522 Undertake project work Project Planning Templates
  • 52. © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 24 of 24 3. What worked well; what could have gone better? Worked well Could have gone better 4. Lessons learned 5. Next steps / improvement plans Project Title: Project Client: Date: Version: Project Sponsor: Project Manager: File Name: Page x of y Simulated Business
  • 53. Max Lionel Realty Table of Contents Chapter 1 – Business plan (excerpt) ...........................................................................1 Chapter 2 – Organisational chart and management profiles ....................................2 Chapter 3 – Management responsibilities ..................................................................3 Chapter 4 – Budget summary ......................................................................................4 Chapter 5 – Operational plan ......................................................................................5 Chapter 6 – Operational risk register ..........................................................................7 Chapter 7 – Work Health and Safety (WHS) Policy .....................................................8 Chapter 8 – Anti-discrimination
  • 54. policy...................................................................... 10 Chapter 9 – Procurement policy and procedures .................................................... 11 Chapter 10 – Max Lionel Realty current tenants list ............................................... 16 Chapter 11 – List of pre-approved suppliers ........................................................... 17 BSBPMG522 Undertake project work Max Lionel Realty (simulated business) © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 1 of 17 Chapter 1 – Business plan (excerpt) From Max Lionel Realty business plan FY 2013/14 About Max Lionel Realty Max Lionel Realty was founded in 2008 by property developer Max Lionel. The company currently employs approximately 100 people, 80 of whom are licensed real
  • 55. estate agents. Through its client agents, the organisation manages property sales and rentals (both residential and commercial) on behalf of a range of clients. The organisation also separately engages in investment activities, such as property and land development. Max Lionel Realty has been a member of the Real Estate Institute of Victoria (REIV) since 2008 and proudly follows the REIV Code of Conduct. Mission: ● to achieve the highest returns for our clients and to deliver a client experience that is second to none in the industry. Vision: ● to establish, within five years, the MLR brand — the highest ethical standards with best-in-breed performance for clients. Values: ● integrity ● client-focus
  • 56. ● active encouragement of excellence, innovation and continuous improvement ● teamwork ● recognition of the diversity and expertise of MLR employees and agents. Strategic directions: The strategic context in which Max Lionel Realty will achieve its mission and vision is through: ● engaging with customers and clients ● building goodwill and reputation for integrity ● supporting innovative thinking, management and leadership skills. ● creating a high-performing, highly profitable organisation. BSBPMG522 Undertake project work Max Lionel Realty (simulated business) © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 2 of 17 Chapter 2 – Organisational chart and management profiles
  • 57. Max Lionel Realty organisational chart Board of Directors and CEO Max Lionel Chief Financial Officer Riz Mehra Operations General Manager Kim Sweeney Human Resources Manager Les Goodale Manager Residential Realty (Sales and Rentals) Sam Lee Manager Commercial Realty (Sales and Rentals) Pat Mifsud
  • 58. Manager Investments Peter Mitchell BSBPMG522 Undertake project work Max Lionel Realty (simulated business) © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 3 of 17 Chapter 3 – Management responsibilities Max Lionel, CEO Max is responsible for working with the Board of Directors to oversee the business, set overall strategic directions, manage risk, and authorise large financial transactions. Riz Mehra, Chief Financial Officer Riz is responsible for preparing quarterly financial statements and overall budgeting. Riz Is also responsible for overseeing budgets for cost centres and individual projects. At the completion of financial quarters and at the end of projects, Riz is responsible for viewing
  • 59. budget variation reports and incorporating information into financial statements and financial projections. Kim Sweeney, Operations General Manager Kim is responsible for the day-to-day running of the company. Kim oversees the coordination, as well as the structural separation, of the Residential, Commercial, and Investments centres. Kim is responsible for sponsoring projects which affect operations of the organisation as a whole. Kim works with the Human Resources Manager to coordinate systems and projects in order to achieve company- wide synergy. Les Goodale, Human Resources Manager Les is responsible for the productive capacity and welfare of people at MLR. With the Operations General Manager, Kim works to coordinate projects and management systems such as performance management, recruitment, and induction. Kim will need to ensure aspects of the recently launched WHS management system, such as risk
  • 60. assessment, management, consulting, reporting and continuous improvement, are coordinated with all subsequent activities. Sam Lee, Manager Residential Realty Sam is responsible for the management of all aspects of residential realty. Sam manages the activities of residential agents. Pat Misfud, Manager Commercial Realty Pat is responsible for the management of all aspects commercial realty. Pat manages the activities of commercial agents. Peter Mitchell, Manager Investments Peter is responsible for the management of all aspects investment realty. Peter manages the activities of investment agents. Peter works with the Operations General Manager to ensure separation of investment from obligations to residential and commercial clients. BSBPMG522 Undertake project work Max Lionel Realty (simulated business) © 2015 Innovation and Business Industry Skills Council Ltd 1st
  • 61. edition version: 1 Page 4 of 17 Chapter 4 – Budget summary Max Lionel Realty 2013–2014 budget by activities to be undertaken Income: Commissions, fees from clients $2,566,000 Commissions and agents’ fees for the period. Investment income $1,567,000 Real estate investment income. COGS $150,413 Cost of provision of services. Total Income $3,982,587 Gross profit. Expenses: Wages, salaries and on costs $1,567,890 Wages, salaries, superannuation, work cover insurance, payroll tax.
  • 62. Consultancy fees $50,000 Project management: WHS management system; AD awareness program. Communication expenses $42,000 Telephone, ISP costs, IT support. Staff travel, transport and accommodation. $55,500 Cost of staff travel and associated costs for sales, etc. Premises expenses $250,000 Rent, electricity, maintenance, cleaning. Capital expenditure $120,000 Purchase of new office equipment (90%), vehicles; purchase of properties, land. Depreciation and amortisation $177,569 Computers and capital equipment that is depreciated. Office supplies $65,068 Printing and stationery, postage, amenities.
  • 63. Professional fees (consultants, legal and audit), insurances, taxes and charges, subscriptions and memberships. $62,187 Audit fees, external accounting costs, bank charges, insurance except workers compensation. Total Expenses $2,390,214 Surplus $1,592,373 Net income before tax. BSBPMG522 Undertake project work Max Lionel Realty (simulated business) © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 5 of 17 Chapter 5 – Operational plan Max Lionel Realty operational plan (summary) FY 2013 - 2014 Objectives: Performance measures Tasks:
  • 64. 1 Engage with customers/build ethical profile: ● raise organisational profile by 20% ● improve client satisfaction performance by 25%. ● Percentage of brand recognition in sought-after categories in periodic customer surveys. ● Percentage of customers with positive view of organisational responsiveness, innovation, quality. ● Number of client/tenant
  • 65. complaints. ● Project to raise awareness of anti-discrimination, WHS and other legislation/codes of conduct among agents, clients, tenants. ● Conduct of quarterly surveys: clients and tenants. ● Training needs analysis and training of agents. ● Ensure agents disclose potential conflict of interest to clients, tenants. ● Development of ethical charter, including principles all agents must follow. 2 Increase revenues by 20% within the third quarter. ● Total income. ● Agent income. ● Investment income. ● Investigate resourcing needs: number of agents; personnel; office
  • 66. equipment, cars, etc. ● Fulfil resourcing needs in accordance with policies and procedures. 3 Reduce direct and indirect costs of operations by 10%. ● General ledger accounts; financial statements: ○ wages ○ cost of agent services ○ consultancy fees ○ wastage and associated expenses. ● Renegotiate with suppliers. ● Research potential new suppliers. ● Management engagement with employees to achieve greater employee support of organisational goals. ● Include explanation of how activities work with organisational
  • 67. strategic goals in all communications to internal personnel. ● Greater use by managers of budgets to encourage restraint. ● Greater focus on budget restraint in management of projects. BSBPMG522 Undertake project work Max Lionel Realty (simulated business) © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 6 of 17 Max Lionel Realty operational plan (summary) FY 2013 - 2014 Objectives: Performance measures Tasks: 4 Engage workers with strategic goals of business and support professional development in line with strategic goals. (Targets to be set by individual managers.)
  • 68. ● Percentage completion of performance plans and performance management process. ● Numbers of coaching sessions completed. ● Numbers of operational – related training programs completed. ● Management engagement with employees to achieve greater buy in of organisational goals. ● Include explanation of how activities work with organisational strategic goals in all communications to internal personnel. ● Regular coaching. ● Training needs analysis and training. ● Strategic goals included in induction program for estate agents. ● Employee incentives for performance in all areas relevant to operational and strategic goals.
  • 69. 5 Improve health of employees (range of specific areas). ● Numbers of injuries (Target = 0). ● Numbers of absentees (Target = <3% of total hours). ● Training need analysis and training on WHS and implementation of recently launched MLR WHS management system. ● Research incentives for: safe work achievement and healthy lifestyle. BSBPMG522 Undertake project work Max Lionel Realty (simulated business) © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 7 of 17 Chapter 6 – Operational risk register
  • 70. Max Lionel Realty risk register FY 2012/2013 Identified risk Probability Impact Current controls Future actions Failure to recruit qualified real estate agents due to increased competition. Medium High ● All office equipment regularly reviewed and updated as required; IT security monitored and maintained. ● Appropriate insurances held and coverage reviewed annually. ● Managers encouraged and incentivised to follow performance management policy. ● Employee performance plans align with business plan and six-monthly review process in place. ● Project to raise awareness of anti- discrimination, WHS and other
  • 71. legislation/codes of conduct among agents, clients, tenants ● Appropriate HR policies and procedures in place. ● WHS management system in place. ● Industry benchmarking in all areas of organisational performance ● Conduct periodic reviews of agent performance to ensure professional conduct ● Staff trained in use of technology as needed. ● Keep abreast of changes in potential liabilities.
  • 72. ● Review and develop HR related policies where required. ● Development of ethical charter, including principles all agents must follow Failure to realise revenue gains due to recent slump in real estate prices. High High Inadequate insurance cover. Low High Non-compliance on anti-discrimination. Medium High Perception of discriminatory practice reducing client and tenant base. Medium High Poor organisational culture; low level of staff engagement and morale. Medium Medium
  • 73. Loss of knowledge and capability through departing staff. Low High Failure to meet occupational health and safety requirements. Low High BSBPMG522 Undertake project work Max Lionel Realty (simulated business) © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 8 of 17 Chapter 7 – Work Health and Safety (WHS) Policy Max Lionel Realty WHS policy Max Lionel Realty recognises its responsibility to provide a healthy and safe working environment for employees, contractors, clients and visitors. Max Lionel Realty is committed to the continued wellbeing of its employees and to ensuring that all employees
  • 74. are safe from injury and health risks whilst undertaking work- related duties, including home-based work. Purpose The purpose of this policy is to ensure the acquisition of resources is carried out consistently, fairly and transparently and in accordance with organisational requirements. In order to ensure a healthy and safe working environment, Max Lionel Realty will (in accordance with the WHS management system): ● undertake risk assessments and implement procedures to adequately manage any risks in the working environment ● provide written procedures and instructions for safe working practices ● ensure compliance with all relevant legislation ● maintain safe systems of work including the work premises and environment ● provide appropriate support, instruction, training and supervision to employees to ensure safe working practices.
  • 75. Scope The scope of this policy covers employees and contractors of Max Lionel Realty (MLR). Resources Specific procedures for the implementation of this policy are available below and on the company intranet. Responsibility Max Lionel Realty management and employees are ultimately responsible for ensuring that safe systems of work are established, implemented and maintained. Management is responsible for: ● the effective implementation and regular review of WHS procedures ● consultation with employees regarding health and safety issues and changes to legislation and/or working practices which may affect the health, safety or welfare of employee ● providing and maintaining a safe system of working practices BSBPMG522 Undertake project work Max Lionel Realty (simulated business)
  • 76. © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 9 of 17 ● providing support, training, and supervision to employees to ensure safe and healthy workplace practices are carried out, including relevant first aid training where appropriate ● the provision of adequate resources for employees to meet the WHS commitment, including an up-to-date first aid kit. Individual employees are responsible for: ● following all WHS policies and procedures ● ensuring they report all potential and actual risks to partners or managers/supervisors ● taking care to protect their own health and safety and that of their colleagues at work ● ensuring their own or others health and safety is not adversely affected by the consumption of drugs or alcohol ● encouraging others to follow healthy and safe working practices in the workplace.
  • 77. Policy Implementation and Review This policy has been established and implemented through the human resource functions of the organisation and will be reviewed regularly in consultation with MLR management and employees to ensure compliance with legislation, industry standards and organisational changes. Relevant legislation, etc. ● Privacy Act 1988 (Cwlth) ● Estate Agents Act 1980 (Vic) ● Equal Opportunity Act 2010 (Vic) ● Occupational Health and Safety Act 2004 ● Dangerous Goods Act 1985 (Vic) ● AS/NZS 4804:2001 Occupational health and safety management systems – General guidelines on principles,
  • 78. systems and supporting techniques Updated/ authorised 10/2013 – Riz Mehra, CFO BSBPMG522 Undertake project work Max Lionel Realty (simulated business) © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 10 of 17 Chapter 8 – Anti-discrimination policy Max Lionel Realty Anti-discrimination Policy Purpose The purpose of this policy is to ensure transactions with clients, tenants and other employees is handled fairly and transparently and in accordance with organisational and legal requirements. Generally it is unlawful to discriminate on the basis of the following 16 characteristics: ● sex ● relationship status
  • 79. ● pregnancy ● parental status ● breastfeeding ● age ● race ● impairment ● religious belief or religious activity ● political belief or activity ● trade union activity ● lawful sexual activity ● gender identity ● sexuality ● family responsibilities ● association with, or relation to, a person identified on the basis of the above.
  • 80. Scope The scope of this policy covers all employees and contractors of Max Lionel Realty (MLR). Resources Specific procedures for the implementation of this policy are available below and on the company intranet. Responsibility Responsibility for the implementation of this policy rests with all employees, contractors and management of Max Lionel Realty. Relevant legislation, etc. ● Privacy Act 1988 (Cwlth) ● Equal Opportunity Act 2010 (Vic) ● Age Discrimination Act 2004 (Cwlth) ● Disability Discrimination Act 1992 (Cwlth) ● Racial Discrimination Act 1975 (Cwlth) ● Sex Discrimination Act 1984 (Cwlth) ● Estate Agents Act 1980 (Vic) Updated/
  • 81. authorised 10/2013 – Riz Mehra, CFO BSBPMG522 Undertake project work Max Lionel Realty (simulated business) © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 11 of 17 Chapter 9 – Procurement policy and procedures Max Lionel Realty procurement policy Purpose The purpose of this policy is to ensure the acquisition of resources is carried out consistently, fairly and transparently and in accordance with organisational requirements. Scope The scope of this policy covers the purchasing and acquisition of resources by employees and contractors of Max Lionel Realty (MLR). Resources Specific procedures for the implementation of this policy are available below and on the company intranet.
  • 82. Responsibility Responsibility for the implementation of this policy rests with employees and management of Max Lionel Realty with responsibility for purchasing resources. Relevant legislation etc. ● Privacy Act 1988 (Cwlth) ● Estate Agents Act 1980 (Vic) ● Equal Opportunity Act 2010 (Vic) ● Corporations Act 2001 (Cwlth) ● A New Tax System (Goods and Services Tax) Act 1999 (Cwlth) ● Income Tax Assessment Act 1997 (Cwlth) ● Fair Work Act 2009 (Cwlth) ● Occupational Health and Safety Act 2004 (Vic) Updated/ authorised 10/2013 – Riz Mehra, CFO
  • 83. BSBPMG522 Undertake project work Max Lionel Realty (simulated business) © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 12 of 17 14 Principles governing the Max Lionel Realty procurement process 1. Probity and ethical behaviour The principle of probity and ethical behaviour governs the conduct of all procurement activities. Employees who have authority to procure goods and services must comply with the standards of integrity, probity, professional conduct and ethical behaviour. Employees or directors must not seek to benefit from supplier practices that may be dishonest or unethical. 2. Value for money Value for money is the core principle underpinning procurement. Contracted
  • 84. organisations must be cost effective and efficient in the use of resources whilst upholding the highest standards of probity and integrity. In general, a competitive process carried out in an open, objective and transparent manner can achieve the best value for money in procurement. 3. Non-discrimination This procurement policy is non-discriminatory. All potential contracted suppliers should have the same opportunities to compete for business and must be treated equitably based on their suitability for the intended purpose. 4. Risk management Risk management involves the systematic identification, analysis, treatment and, where possible, the implementation of appropriate risk-mitigation strategies. It is integral to efficiency and effectiveness to proactively identify, evaluate, and manage risks arising out of procurement related activities. The risks associated with procurement activity must be
  • 85. managed in accordance with the organisation’s risk management policy. 5. Responsible financial management The principle of responsible financial management must be applied to all procurement activities. Factors that must be considered include: ● the availability of funds within an existing approved budget ● staff approving the expenditure of funds strictly within their delegations ● measures to contain costs of the procurement without compromising any procurement principles. 6. Procurement planning In order to achieve value for money, each procurement process must be well planned and conducted in accordance with the principles contained in this document and comply with all of the organisation’s policies and relevant legal and regulatory requirements. When planning appropriate procurement processes consideration should be given to adopting an approach that:
  • 86. ● encourages competition ● ensures that rules do not operate to limit competition by discriminating against particular suppliers ● recognises any industry regulation and licensing requirements BSBPMG522 Undertake project work Max Lionel Realty (simulated business) © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 13 of 17 ● secures and maintains contractual and related documentation for the procurement which best protects the organisation ● complies with the organisation’s delegations policy. 7. Buy Australian Made/support for Australian industry Employees who are involved in procurement activities must make a conscious effort to maximise opportunities for Australian manufacturers and suppliers to provide products where there is practicable and economic value. In making a value for money judgement
  • 87. between locally-made and overseas-sourced goods, employees are to take into account: ● whole-of-life costs associated with the good or service ● that the initial purchase price may not be a reliable indicator of value ● the quality of locally made products ● the record of performance and delivery of local suppliers ● the flexibility, convenience and capacity of local suppliers for follow on orders ● the scope for improvements to the goods and ‘add-ons’ from local industry. 8. Pre-registered list of preferred suppliers Max Lionel Realty shall maintain a pre-registered list of preferred suppliers, following a request for expressions of interest and an evaluation of the submissions. Suppliers can request to be evaluated for inclusion on the existing pre-register list at any time. All purchases under $5,000 may be made from preferred suppliers without undertaking a competitive process. Purchases above $5,000 where a preferred supplier exists should
  • 88. include a competitive process if practicable. This list is reviewed at regular intervals with admission of interested parties on a rolling basis. Care should be taken to ensure that such lists are used in an open and non-discriminatory manner. Max Lionel Realty encourages new contractors to provide information on their experience, expertise, capabilities, pricing, fees, and current availability. It is in the interest of the organisation that the pool of potential suppliers is actively maintained and updated. Employees should be encouraged to provide reports of their experiences in working with each contractor/consultant to assist future decisions concerning commissioning suitable contractors and consultants. 9. Avoid conflict of interest Employees and directors are required to be free of interests or relationships in all aspects of the procurement process. Employees and directors are not permitted to personally gain from any aspect of a procurement process. Employees and directors shall ensure that to the best of their
  • 89. knowledge, information and belief, that at the date of engaging a contractor no conflict of interest exists or is likely to arise in the performance of the contractor’s obligations under their contract. Should employees or directors become aware of potential conflicts of interest during the contract period, they must advise the CEO and the Board of Directors immediately. Prior to any situation arising with potential for a conflict of interest, complete disclosure shall be made to the CEO and the Board of Directors to allow sufficient time for a review. BSBPMG522 Undertake project work Max Lionel Realty (simulated business) © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 14 of 17 10. Report collusive tendering Employees should be aware of anti-competitive practices such as collusive tendering. Any evidence of suspected collusion in tendering should be brought
  • 90. to the attention of the CEO and the Board of Directors. 11. Competitive process It is a basic principle of procurement that a competitive process should be used unless there are justifiable circumstances. For purchases under $5,000, the list of preferred suppliers may be used. The type of competitive process can vary depending on the size and characteristics of the contract to be awarded. 12. Direct invitation (selective or restricted tendering) A process of direct sourcing to tender may be used. This may involve: ● an invitation to organisations deemed appropriately qualified for a particular product or service (this may be appropriate for specialised requirements in markets where there is a limited number of suppliers or service providers) ● an invitation to tender to organisations on MLR’s pre- registered list of preferred suppliers if applicable.
  • 91. 13. Evaluation and contract award For projects being awarded, consideration will be given not only to the most economically advantageous tender, but also to the track record of the tender respondent and the degree of confidence that the panel has in the quality if the bid. It will be the normal practice to have the evaluation of tenders carried out by a team with the requisite competency. 14. Results of tendering process All tender respondents should be informed in writing of the result of a tendering process immediately after a contract has been awarded. BSBPMG522 Undertake project work Max Lionel Realty (simulated business) © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 15 of 17 Summary of procurement policy delegations Authority Purchase amount Required number
  • 92. of quotes Comment CEO and one Director Authority to sign contracts for products and services over $75,000. Two or more competitive quotes for contracts over $75,000. Detailed services contract required. CEO Authority to sign contracts for products and
  • 93. services up to $75,000. Two or more competitive quotes. Detailed services contract required for contracts over $20,000. General Managers Delegated authority only through CEO Authority to sign contracts for products and services under $30,000. One or more
  • 94. competitive quotes preferred. Provided they are within the approved budget and consistent with business/operational and strategic planning. Managers Authority to sign contracts for products and services under $10,000. One or more competitive quotes preferred. Follow MLR
  • 95. purchasing procedures. Agents Authority to sign contracts for products and services under $5,000. Must use preferred suppliers list. Follow MLR purchasing procedures. Contractors and external consultants No authority. One or more competitive quotes preferred.
  • 96. Must use preferred suppliers list. Contractors and external consultants must follow MLR purchasing procedures and must seek approval for purchases from person holding relevant authority. BSBPMG522 Undertake project work Max Lionel Realty (simulated business) © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 16 of 17
  • 97. Chapter 10 – Max Lionel Realty current tenants list BSBPMG522 Undertake project work Max Lionel Realty (simulated business) © 2015 Innovation and Business Industry Skills Council Ltd 1st edition version: 1 Page 17 of 17 Chapter 11 – List of pre-approved suppliers Max Lionel Realty List of preferred suppliers and contractors ● Ace Consultants: Project managers, IT technicians, technical writers, marketers, subject matter experts for short or long term human resourcing needs. ● Innovative Travel: Business travel bookings ● Melbourne Car World: Fleet sales and service ● Ready Office Supplies: Computers, photocopiers, etc. ● Coffeeville: Business function catering ○ Catering menu:
  • 98. <http://simulations.ibsa.org.au/coffeeville/menu.php>. # Street Suburb Property Type # Beds # Baths OS Parking LUG Y/N BIRs Y/N Garden Floor Surface Tenant 1 Name Tenant 2 Name Tenant 3 Name Tenant 4 Name Lease
  • 99. Commenced Inspection Due Rent P/W 67 Miller Street Preston House 3 2 2 Y Y Y Carpet Grace Haines David Haines 6/22/2011 12/22/2013 420.00$ 33 Alexandra Avenue Abbotsford House 2 1 1 N Y Y Carpet Peter Hickman 7/19/2012 7/19/2013 310.00$ 789 Carter Road Collingwood House 2 1 1 N N N Polished Priscilla Schwartz Andrea Lewis 8/12/2012 8/12/2013 297.00$ 45 Main Street Epping Townhouse 3 1 1 N Y N Carpet Phong Lil Michael North Xin Ling 3/5/2012 9/5/2013 207.00$ 22b Chestnut Street Northcote Apartment 1 1 0 N Y N Polished Wendy Stuart 1/7/2012 7/7/2013 159.00$ 12/445 Commercial Road South Preston Flat 3 2 1 Y Y N Carpet Sarah Tatou Sydney Kellett 12/17/2009 12/17/2013 238.00$ 72 Hoddle Street Collingwood Apartment 1 1 0 N Y N Carpet Tom Casper Amanda Casper 6/3/2010 12/3/2013 326.00$ 18 Abbotsford Street Westgarth Apartment 2 1 0 N Y N Polished John Dean Brett Ellis 4/23/2012 10/23/2013 350.00$ 3 Rooney Court Fitzroy Townhouse 3 1 2 N Y Y Carpet James Rothfield Maria Teasdale Ben Dubois 1/15/2011 7/15/2013
  • 100. 389.00$ 60 Kaola Street Coburg House 5 2 2 Y N Y Polished Nigel Cooper Melissa O'Brien Dan Di Donato Elena Charles 2/28/2013 8/28/2013 332.00$ 57 Rathdowne Street Thornbury House 4 2 2 Y N Y Carpet Joanne Evers Craig Avery Kip McNeil Brendan Gorman 2/12/2013 8/12/2013 450.00$ 1 Totzetti Court Carlton Flat 1 1 0 N Y Y Polished Tina Pullman 5/6/2012 11/6/2013 365.00$ 22 Darling Street South Preston House 4 2 2 Y N N Carpet Maggie Stanton Penny Victor 9/9/2012 9/9/2013 298.00$ 13 Darebin Road Northcote House 2 1 1 N Y Y Carpet Reece Swan Sarah Swan 7/27/2012 7/27/2013 284.00$ 1/427 Lygon Street Carlton Apartment 2 1 0 N Y N Polished Anna Lomen Kelly Cheetham 6/27/2012 12/27/2013 363.00$ 39 Southill Street Preston Townhouse 3 1 1 Y Y Y Carpet Louise Appleton Gino Patony Quan Tho 1/27/2013 7/27/2013 256.00$ 14/64 Brownes Road Thornbury Apartment 3 2 2 Y Y N Polished Jack Morgan Sadie Morgan 5/31/2013 12/1/2013 380.00$ 58 Johnston Street Northcote Flat 2 1 0 N Y Y Carpet Jim Percy Paul Percy 1/3/2013 7/3/2013 450.00$ 20 St Georges Road Brunswick Apartment 1 1 1 Y Y N Carpet Owen Smythe 9/8/2012 9/8/2013 446.00$
  • 101. 74 Harrow Street Fitzroy Townhouse 3 2 2 N Y N Polished David D'Angelo Carla D'Angelo 4/10/2013 10/10/2013 489.00$ 502 Wilson Street Preston House 4 2 2 Y N Y Carpet Zita Nicholson Andy Nicholson 5/11/2013 11/11/2013 465.00$ 8 Moore Court Coburg House 3 2 2 Y N Y Carpet Cecelia Barton Audrey Amber Kate Kingsley 1/22/2013 7/22/2013 310.00$ 4 Beattie Crescent Westgarth Townhouse 2 1 0 N Y Y Polished Julian Milliken Geoff Katz 8/29/2012 8/29/2013 340.00$ 39 Hunters Road Preston House 3 2 1 N N N Carpet Minh Chi Lin Waan Gracie Jiu 1/27/2013 7/27/2013 410.00$ 15 Waldron Ave Brunswick House 2 1 0 N Y Y Carpet Benjamin Drew Bella Salera 11/7/2009 11/7/2013 389.00$ 211 Gower Street Thornbury House 3 2 1 N Y N Carpet Tahir Singh Eashan Tendulkar Tajdar Deuskar 6/14/2010 12/14/2013 350.00$ 41/27 Butler Street Collingwood Apartment 1 1 0 N Y N Polished Helena Swain 2/23/2011 8/23/2013 367.00$ Current Tenants List Property Manager PM Phone # Susan Hunter 0411-222-333
  • 102. Dominic Lazaro 0411-222-444 Susan Hunter 0411-222-333 Susan Hunter 0411-222-333 Dominic Lazaro 0411-222-444 Susan Hunter 0411-222-333 Dominic Lazaro 0411-222-444 Susan Hunter 0411-222-333 Susan Hunter 0411-222-333 Dominic Lazaro 0411-222-444 Susan Hunter 0411-222-333 Susan Hunter 0411-222-333 Dominic Lazaro 0411-222-444 Dominic Lazaro 0411-222-444 Susan Hunter 0411-222-333 Susan Hunter 0411-222-333 Susan Hunter 0411-222-333 Susan Hunter 0411-222-333 Dominic Lazaro 0411-222-444
  • 103. Susan Hunter 0411-222-333 Susan Hunter 0411-222-333 Dominic Lazaro 0411-222-444 Dominic Lazaro 0411-222-444 Susan Hunter 0411-222-333 Susan Hunter 0411-222-333 Dominic Lazaro 0411-222-444 Susan Hunter 0411-222-333 Facilitator Guide Marking Guide BSBPMG522 Undertake project work 1st edition version: 1 © 2015 Innovation and Business Industry Skills Council Ltd Marking Guide Assessment Task 3: Finalise and review project Candidate’s Name Phone No. Assessor’s Name Phone No. Assessment Site
  • 104. Assessment Date/s Time/s Outcomes Did the candidate: Satisfactory Yes No Submit: ● a budget variation report for sign-off ● signed role descriptions for sign-off ● a handover report ● a post-project project review report? Participate in project team meetings? Submit all materials within the required timeframe? Performance indicators Did the candidate: Satisfactory Yes No Complete financial recordkeeping associated with project and check for
  • 105. accuracy? ● Meet with project team to discuss. ● Submit budget variation report for forwarding to Chief Financial Officer. ● Report free from errors and showing required numeracy to complete task. Facilitator Guide Marking Guide BSBPMG522 Undertake project work 1st edition version: 1 © 2015 Innovation and Business Industry Skills Council Ltd Did the candidate: Satisfactory Yes No Assign staff involved in project to new roles or reassign to previous roles? ● Meet with project team to assign roles as directed by Operations
  • 106. General Manager. ● Complete signed role description forms and submit to Operations General Manager. Complete project documentation and obtain any necessary sign offs for concluding project? ● Submit all project documentation and deliverables for sign-off by Operations General Manager: ○ budget variation report for sign-off ○ signed role descriptions for sign-off ○ handover report for sign-off ○ post-project review report. Review project outcomes and processes against the project scope and plan? o review outcomes against objectives, including budgetary
  • 107. performance o review team processes o discuss lessons learned from implementation of project. Involve team members in the project review? o review outcomes against objectives, including budgetary performance o review team processes o discuss lessons learned from implementation of project. Facilitator Guide Marking Guide BSBPMG522 Undertake project work 1st edition version: 1 © 2015 Innovation and Business Industry Skills Council Ltd Did the candidate: Satisfactory Yes No
  • 108. Document lessons learned from the project and report within the organisation? -project review report to Operations General Manager for forwarding to stakeholders. -project review report should contain: o a review of outcomes against objectives, including budgetary performance o a review of team processes o discussion of lessons learned from implementation of project o discussion of project management tools used, evaluation of their contribution to the project and recommendations of future alternatives where applicable. Comments/feedback to participant Outcome:
  • 109. Successful Unsuccessful Assessor name: Assessor signature: Assessment Task 3 BSBPMG522 Undertake project work © 2015 Innovation and Business Industry Skills Council 1st edition version: 1 Page 1 of 4 Finalise and review project Submission details Candidate’s Name Phone No. Assessor’s Name Phone No. Assessment Site Assessment Date/s Time/s The assessment task is due on the date specified by your assessor. Any variations to this arrangement must be approved in writing by your assessor. Submit this document with
  • 110. any required evidence attached. See specifications below for details. Performance objective Candidates will demonstrate knowledge and skills required to finalise and review projects. Assessment description Following on from Assessment Tasks 1 and 2 and using the workplace scenario information provided, you will, drawing on consultation with your project team, complete financial record keeping, reassign staff to roles, complete project documentation for sign-off and review project outcomes against project scope and plan. You will then produce a report on the project for stakeholders. Procedure 1. Review the simulated business documentation, including policies and procedures, in the document ‘Max Lionel Realty.docx’. Review templates contained in the document ‘Project planning templates.docx’ for possible use or adaptation in
  • 111. completing project requirements. 2. Review the scenario information provided in Appendix 3. 3. In consultation with your project team, complete financial record-keeping for the project: a. compare budgeted spend with actual b. produce a budget variation report. Note: You may use or adapt the template provided. Meetings may be observed by your assessor. Follow your communication plan or agree to a time and date. Assessment Task 3 BSBPMG522 Undertake project work © 2015 Innovation and Business Industry Skills Council 1st edition version: 1 Page 2 of 4 4. In consultation with your project team and management, assign project team members to roles. Obtain agreement on new roles and responsibilities. You may use or adapt the template provided (under initiation and scope)
  • 112. to record agreement on new role descriptions. Note: Meetings may be observed by your assessor. Follow your communication plan or agree to a time and date. 5. Produce a handover report for the Project Sponsor (the assessor) for sign-off. You may use or adapt the template provided. 6. In consultation with your project team: a. review the project’s outcomes against objectives, including budgetary performance b. review team processes c. review the project management tools used, evaluate their contribution to the project and discuss possible alternatives d. discuss lessons learned from implementation of the project. Note: You may use or adapt the post-project review meeting agenda template provided. Meetings may be observed by your assessor. Follow your
  • 113. communication plan or agree to a time and date. 7. Produce a post-project review report for all stakeholders, including the Board of Directors, containing: a. a review of project outcomes against objectives, including budgetary performance b. a review of team processes c. a review of the project management tools used, an evaluation of their contribution to the project and any recommendations for alternative tools for use in the future d. a discussion of lessons learned from implementation of the project e. recommendations for the implementation of future projects based on the lessons learned, ensuring your report takes account of specific organisational requirements, e.g. legislative requirements and strategic plans. Note: You may use or adapt the post-project review report template provided.
  • 114. 8. Submit documentation as per specifications below. Specifications You must: ● participate in project meeting/s ● submit: ○ budget variation report for sign-off ○ signed role descriptions for sign-off Assessment Task 3 BSBPMG522 Undertake project work © 2015 Innovation and Business Industry Skills Council 1st edition version: 1 Page 3 of 4 ○ handover report ○ post-project project review report. Your assessor will be looking for: ● communication and negotiation skills to work with team members and other stakeholders to maintain project schedules ● literacy skills to read, write and review a range of documentation
  • 115. ● planning and organising skills to develop, monitor and maintain implementation schedules ● numeracy skills to analyse data and to compare timelines and promotional costs against budgets ● culturally appropriate communication skills to relate to people from diverse backgrounds and people with diverse abilities ● knowledge of relevant legislation from all levels of government that may affect aspects of business operations, such as: ○ anti-discrimination legislation ○ ethical principles ○ codes of practice ○ privacy laws ○ environmental issues ○ WHS ● knowledge of organisational structure, and lines of authority and communication
  • 116. within the organisation ● knowledge of how the project relates to organisation’s overall mission, goals, objectives and operations. Adjustment for distance-based learners ● No variation of the task is required. ● A follow-up interview may be required (at the discretion of the assessor). ● Documentation can be submitted electronically or posted in the mail ● Meetings may be conducted and observed live or via an appropriate teleconferencing tool. Assessment Task 3 BSBPMG522 Undertake project work © 2015 Innovation and Business Industry Skills Council 1st edition version: 1 Page 4 of 4 Appendix – Scenario Max Lionel Realty It is now time to review and finalise the project.
  • 117. Work with your project team to review the outcomes, team processes and lessons learned from implementation. Review the project’s budgetary performance and produce a budget variation report for the Chief Financial Officer. Your Operations General Manager requires you to submit an implementation report for the Board of Directors that includes recommendations for the improvement of implementation for future projects. Facilitator Guide Marking Guide BSBPMG522 Undertake project work 1st edition version: 1 © 2015 Innovation and Business Industry Skills Council Ltd Marking Guide Assessment Task 2: Administer and monitor project Candidate’s Name Phone No. Assessor’s Name Phone No.
  • 118. Assessment Site Assessment Date/s Time/s Outcomes Did the candidate: Satisfactory Yes No Submit: ● a written record of agreement with roles and responsibilities ● three status reports as per recordkeeping requirements ● risk management reports (may be change requests or issues logs) ● project deliverables (drafts and final)? Provide appropriate form of support: coaching, assistance with deliverables, etc.? Participate in project team meetings? Submit all materials within the required timeframe? Performance indicators Did the candidate:
  • 119. Satisfactory Yes No Take action to ensure project team members were clear about their responsibilities and the project requirements? ● Candidates should meet with project team to negotiate responsibilities. ● Candidates should document agreement on templates provided. Facilitator Guide Marking Guide BSBPMG522 Undertake project work 1st edition version: 1 © 2015 Innovation and Business Industry Skills Council Ltd Did the candidate: Satisfactory Yes No Provide support for project team members, especially with regard to
  • 120. specific needs, to ensure that the quality of the expected outcomes of the project and documented time lines are met? ● Candidate provides support to team member as per need and so that project outcomes can be met at required standard. ● Support should demonstrate (culturally appropriate) communication and negotiation skills. ● Support needs to adhere to project parameters (cannot cost too much to provide [each candidate has an hourly rate to consider]); cannot take too long to provide; cannot put project at risk. Establish and maintain required recordkeeping systems throughout the project? ● Organisational recordkeeping system requires regular status reports to record: ○ financial management and budget control. ● Project milestones, for example: ○ quality review completion
  • 121. ○ outcomes and deliverables. Facilitator Guide Marking Guide BSBPMG522 Undertake project work 1st edition version: 1 © 2015 Innovation and Business Industry Skills Council Ltd Did the candidate: Satisfactory Yes No Implement and monitor plans for managing project finances, resources (human, physical and technical) and quality? ● Complete status reports, including minutes of team meetings. ● Meet with team to: ○ clarify roles and responsibilities and ensure written record of agreement, e.g. obtain signatures on roles and responsibilities template provided ○ determine need for support and inform team members of
  • 122. your support needs ○ discuss monitoring and recordkeeping systems as required by the organisation ○ discuss risk processes for identifying risks and risk management approaches. Discussions indicate understanding of business documentation and scenario requirements to demonstrate required literacy for task. ● Follow project and risk management plans. ● Make required adjustments to plans if required to reflect changing conditions. Complete and forward project reports as required to stakeholders? ● Status reports template competed. ● Status reports submitted to Operations General Manager. ● Status reports demonstrate required numeracy for task. ● Status reports submitted at 25%, 50%, 75% of timeline. Undertake risk management as required to ensure project
  • 123. outcomes are met? ● Each candidate must identify, assess, and treat contingency to ensure project outcomes. ● Each candidate should coordinate actions with team. Achieve project deliverables? ● Candidate meets quality specifications outlined in Assessment Task. ● Project deliverables demonstrate knowledge of organisational strategic directions. Facilitator Guide Marking Guide BSBPMG522 Undertake project work 1st edition version: 1 © 2015 Innovation and Business Industry Skills Council Ltd Comments/feedback to participant
  • 124. Outcome: Successful Unsuccessful Assessor name: Assessor signature: Assessment Task 2 BSBPMG522 Undertake project work © 2015 Innovation and Business Industry Skills Council 1st edition version: 1 Page 1 of 4 Administer and monitor project Submission details Candidate’s Name Phone No. Assessor’s Name Phone No. Assessment Site Assessment Date/s Time/s The assessment task is due on the date specified by your assessor. Any variations to this
  • 125. arrangement must be approved in writing by your assessor. Submit this document with any required evidence attached. See specifications below for details. Performance objective Candidates will demonstrate knowledge and skills required to administer and monitor projects. Assessment description Using the workplace scenario information provided, you will work collaboratively with your project team to administer and monitor a project (initiated, planned and discussed in Assessment Task 1) in order to achieve the project deliverables. Procedure 1. Review the simulated business documentation, including policies and procedures in the document ‘Max Lionel Realty.docx’. Review templates contained in the document ‘Project planning templates.docx’ for possible use or adaptation in completing project requirements.
  • 126. 2. Review the scenario information provided in Appendix 2. 3. Determine monitoring and record-keeping system requirements from scenario for project as planned. 4. Determine personal need for support. 5. Meet with the team to: a. clarify roles and responsibilities and ensure written record of agreement, e.g. obtain signatures on roles and responsibilities template provided b. determine need for support and inform team members of your support needs Assessment Task 2 BSBPMG522 Undertake project work © 2015 Innovation and Business Industry Skills Council 1st edition version: 1 Page 2 of 4 c. discuss monitoring and record-keeping systems as required by the organisation d. discuss risk processes for identifying risks and risk management approaches.
  • 127. Note: Minutes of these meetings should be attached to your project status reports. You may need to meet on several occasions. Meetings may be observed by your assessor. Follow your communication plan or agree to a time and date. 6. Plan to support a team member. Arrange suitable time with team member and assessor (to observe). You may, for example, provide assistance with deliverables, coach, train, etc. Note: Ensure you adhere to budgetary constraints and timelines. All resources and time spent on the project will count towards expenditure. 7. Meet with team member to provide support. 8. Complete the following personal roles and responsibilities: a. implement monitoring and record-keeping, using or adapting the template provided b. develop project deliverables c. ensure quality assurance on draft deliverables as required by your project
  • 128. plan. 9. Undertake risk management as per your project plan. Provide risk management reports (may include change requests and/or issues logs). Use or adapt the templates provided. Note: Your Operations General Manager (the assessor) will inform your project team of contingencies that you will need to manage. Coordinate actions with your project team members. Each team member will have at least one contingency to manage. 10. Submit documentation as per specifications below. Specifications You must: ● participate in project meeting/s ● provide appropriate support to one team member ● submit: ○ a written record of agreement with roles and responsibilities ○ three status reports as per record-keeping requirements ○ risk management reports: change requests and/or issues logs
  • 129. ○ draft project deliverables for quality assurance ○ final project deliverables. Assessment Task 2 BSBPMG522 Undertake project work © 2015 Innovation and Business Industry Skills Council 1st edition version: 1 Page 3 of 4 Your assessor will be looking for: ● communication and negotiation skills to work with team members and other stakeholders to maintain project schedules ● literacy skills to read, write and review a range of documentation ● planning and organising skills to monitor and maintain implementation schedules ● numeracy skills to analyse data and compare timelines and implementation ● culturally appropriate communication skills to relate to people from diverse backgrounds and people with diverse abilities ● knowledge of relevant legislation from all levels of
  • 130. government that may affect aspects of business operations, such as: ○ anti-discrimination legislation ○ ethical principles ○ codes of practice ○ privacy laws ○ environmental issues ○ WHS ● knowledge of organisational structure and chains of authority and communication within the organisation ● knowledge of how the project relates to the organisation’s overall mission, goals, objectives and operations. Adjustment for distance-based learners ● No variation of the task is required. ● A follow-up interview may be required (at the discretion of the assessor). ● Documentation can be submitted electronically or posted in the mail.
  • 131. ● Meetings may be conducted and observed live or via an appropriate teleconferencing tool. Assessment Task 2 BSBPMG522 Undertake project work © 2015 Innovation and Business Industry Skills Council 1st edition version: 1 Page 4 of 4 Appendix – Scenario Max Lionel Realty It is now time to implement the project you initiated, planned for and negotiated in Assessment Task 1. Work with your team to achieve agreed deliverables on time, to budget, and up to the required standard. Manage contingencies and renegotiate project with stakeholders as required. As per organisational project management record keeping system requirements, your Operations General Manager requires regular status reports to record:
  • 132. ● financial management and budget control ● project milestones, for example: ○ quality review completion ○ outcomes and deliverables. Submit three status reports over course of project: at 25%, 50%, 75% of timeframe. Risk management reports need to be submitted to the project sponsor for each contingency managed. Recall the quality standards for deliverables: ● clearly communicate legal obligations, REIV obligations ● no grammar or spelling errors ● professional but friendly language ● fair and flexible delivery for intended audience ● meet audience requirements and sensitive to information needs. Facilitator Guide Marking Guide BSBPMG522 Undertake project work 1st edition version: 1
  • 133. © 2015 Innovation and Business Industry Skills Council Ltd Marking Guide Assessment Task 1: Define project and develop plan Candidate’s Name Phone No. Assessor’s Name Phone No. Assessment Site Assessment Date/s Time/s Outcomes Did the candidate: Satisfactory Yes No Submit: ● project initiation and scope documents: project brief; project scope; stakeholder analysis; communication plan; roles and responsibilities; project snapshot ● a project plan (version 1 and version 2) ● a risk management plan (a risk register and a risk assessment for each of the four risks) (version 1 and version 2)
  • 134. ● a budget (version 1 and version 2)? Participate in discussion with the Operations General Manager (the assessor)? Submit all materials within the required timeframe? Performance indicators Did the candidate: Satisfactory Yes No Access project scope and other relevant documentation? ● describe project scope as including the development of communication material for agents as determined by assessor; exclusions as determined by assessor ● document scope, using template, for example Facilitator Guide Marking Guide
  • 135. BSBPMG522 Undertake project work 1st edition version: 1 © 2015 Innovation and Business Industry Skills Council Ltd Did the candidate: Satisfactory Yes No ● describe other relevant documentation determine project and to provide content for project deliverables: ○ Max Lionel Realty simulated business documentation, such as strategic directions, budget, risk management, policies, etc. ○ REIV Code of Conduct ○ Estate Agents Act 1980 (Vic) ○ Equal Opportunity Act 2010 (Vic) ○ anti-discrimination legislation ○ ethical principles ○ privacy laws. Define project stakeholders?
  • 136. ● Candidate interprets scenario, organisational chart and management responsibilities to identify all or most of the following as potential stakeholders: ○ project team, including technical experts ○ Operations General Manager/Project Sponsor: concerned with overall success of project and integration with business strategic objectives, etc. ○ Chief Financial Officer: Will need to review budgets ○ Human Resources Manager: Will be concerned with coordinating with other HR projects and programs ○ Residential Manager: Will need to be informed of agent requirements to attend meetings, briefing sessions, etc. ○ Commercial Manager: Will need to be informed of agent requirements to attend meetings, briefing sessions, etc. ○ Investments Manager: Will need to be informed of agent requirements to attend meetings, briefing sessions, etc. ○ clients: See Assessment Task 1 for detailed concerns ○ agents: See Assessment Task 1 for detailed concerns
  • 137. ○ tenants: See Assessment Task 1 for detailed concerns. Seek clarification from delegating authority of any issues related to the project and project parameters? ● discuss changes in parameters with Operations General Manager/Project Sponsor, for example: ○ reduction in budget to $10,000 ○ shortened timeline for completion of project (Reduce by 10%). Facilitator Guide Marking Guide BSBPMG522 Undertake project work 1st edition version: 1 © 2015 Innovation and Business Industry Skills Council Ltd Did the candidate: Satisfactory Yes No Identify limits of own responsibility and reporting requirements?
  • 138. ● As set out in project plan—personal responsibility and timelines for deliverables, reporting at 25%, 50%, 75% status, evaluation reporting Clarify the relationship of the project to other projects and to the organisation’s objectives? For example: ● Performance management: Performance management could incorporate elements of ethical knowledge into performance targets. ● Recruitment and induction: Ethics could form integral part of future inductions. ● WHS management system: management of WHS related contingencies will need to integrate with system requirements such as risk assessment, management, consulting, reporting and continuous improvement. ● Risk management: Project will need to follow risk management procedures and account for existing risk as identified in
  • 139. organisational risk register. ● Financial management: project will need to adhere to budgetary constraints and financial objectives for the business as a whole (See business plan, operational plan, risk register for simulated business for details). Determine and access available resources to undertake the project? For example: ● human resourcing (as provided by assessor – hourly cost must be strictly accounted for) ● communication tools (provided and costed by candidates) ● catering at meetings, information briefings, etc. (provided and or costed by candidates) ● candidates should refer to use costs specified by preferred suppliers, otherwise candidates may identify travel costs, etc. and estimate.
  • 140. Facilitator Guide Marking Guide BSBPMG522 Undertake project work 1st edition version: 1 © 2015 Innovation and Business Industry Skills Council Ltd Did the candidate: Satisfactory Yes No Develop a project plan including timelines, work breakdown structure, roles and responsibilities and other details of how the project will be managed in relation to the project parameters? ● Candidate should include design, development, implementation, and evaluation stages. ● Candidate should include dependencies (may be presented in Gantt format, for instance). ● Candidate should include periodic monitoring and quality assurance.
  • 141. Identify and access appropriate project management tools? For example: ● software: Microsoft Word, Excel, Project, etc. ● Gantt, critical path method, PERT charts, etc. ● appropriate telecommunication tools, such as Skype, identified if required. Formulate a risk management plan for the project, including work health and safety (WHS) considerations? ● Candidate identifies, assesses and suggests treatment of WHS risk. Candidate should identify consulting, reporting and continuous improvement requirements in order to work within organisation’s WHS management system. ● Candidate identifies, assesses and plans treatment of at least three additional risks, including financial risk. Candidate may consider already identified risks in risk register. Develop and approve the project budget?
  • 142. ● Budget accounts for all resources. ● Budget is correct and reflects level of numeracy required to complete task. ● Resources are costed appropriately as per scenario or realistically approximated. Consult team members and take their views into account in planning the project? ● Candidate uses (culturally appropriate) communication skills to negotiate professionally with project team. Facilitator Guide Marking Guide BSBPMG522 Undertake project work 1st edition version: 1 © 2015 Innovation and Business Industry Skills Council Ltd Did the candidate: Satisfactory
  • 143. Yes No Finalise their project plan and gain any necessary approvals to commence project according to documented plan? ● Candidate follows scenario to identify lines of authority for project. Comments/feedback to participant Outcome: Successful Unsuccessful Assessor name: Assessor signature: Assessment Task 1 BSBPMG522 Undertake project work © 2015 Innovation and Business Industry Skills Council 1st edition version: 1 Page 1 of 6
  • 144. Define project and develop plan Submission details Candidate’s Name Phone No. Assessor’s Name Phone No. Assessment Site Assessment Date/s Time/s The assessment task is due on the date specified by your assessor. Any variations to this arrangement must be approved in writing by your assessor. Submit this document with any required evidence attached. See specifications below for details. Performance objective Candidates will demonstrate knowledge and skills required to define projects and develop project plans. Assessment description Using the workplace scenario information provided, you will determine the scope of a project and develop a portfolio of draft planning documentation to discuss with your
  • 145. Operations General Manager (the assessor). You will then negotiate aspects of the project with your assigned project team. Finally, you will submit final planning documentation for approval. Procedure 1. Review the simulated business documentation, including policies and procedures, in the document ‘Max Lionel Realty.docx’. Review templates contained in the document ‘Project planning templates.docx’ for possible use or adaptation in completing project requirements. 2. Review the scenario information provided in Appendix 1. 3. Receive details from Operations General Manager (the assessor) of your project team, cost, skills, and suggested project deliverables and timeframes. 4. Determine project scope. Develop appropriate initiation and scope documents for discussion with Operations General Manager (the assessor). 5. Determine additional documentation required to determine
  • 146. project and develop deliverables. Assessment Task 1 BSBPMG522 Undertake project work © 2015 Innovation and Business Industry Skills Council 1st edition version: 1 Page 2 of 6 6. Define project stakeholders. Determine how you will engage and manage stakeholders to achieve project objectives. Develop communication and stakeholder management plans for discussion. Note: Consider scenario information and organisational structure to determine stakeholders and stakeholder interests. 7. Identify personal responsibilities and reporting requirements. 8. Determine relationship of project to other projects, systems, business operations, strategic aims of organisation, and external legislative requirements. 9. Determine resources and access to resources. Consult with Operations General
  • 147. Manager (the assessor) to clarify if necessary. 10. Determine project management tools, such as software (e.g. Microsoft Word, MS Excel, and MS Project) and templates, etc. Note: You may use software tools or use or adapt the templates provided. 11. Using an appropriate project management tool, develop your project plan (version 1). Include: a. work breakdown structure: stages of development or of task completion (Design, Develop, Implement, Evaluate); opportunities for (peer and stakeholder) review and feedback; coordination of roles and sharing of responsibility for deliverables; dependencies b. timelines c. roles and responsibilities for each team member d. resourcing requirements. 12. Develop a risk management plan for your project (version 1) for discussion. Include
  • 148. consideration of WHS risk management. Identify, assess and suggest treatment of at least three additional risks, including financial risk. Record risks on a risk register and complete a risk assessment document for each risk. Note: You may use software tools or use or adapt the templates provided. 13. Develop a budget (version 1) for the project. Note: You may use software tools or use or adapt the template provided. 14. Meet with Operations General Manager (the assessor) to discuss: a. project scope b. additional documentation required to determine project and develop deliverables. c. project stakeholders d. personal responsibilities e. relationship of project to other projects, systems, strategic aims of organisation f. resources and access to resources
  • 149. Assessment Task 1 BSBPMG522 Undertake project work © 2015 Innovation and Business Industry Skills Council 1st edition version: 1 Page 3 of 6 g. portfolio of documents: i. project initiation and scope documents ii. project plan (version 1) iii. risk management plan (version 1) iv. budget (version 1). 15. Ask for feedback from your Operations General Manager (the assessor) on your version 1 drafts and ensure understanding of any additional project issues or changes to project parameters. 16. Meet with your project team to: a. negotiate roles and responsibilities b. Agree on version 2 of documents for approval by Operations General Manager (the assessor):
  • 150. i. project plan (version 2) ii. risk management plan (version 2) iii. budget (version 2). c. Incorporate Operations General Manager (the assessor) feedback into planning project: Note: The meeting will be observed by your assessor. Follow your communication plan or agree to a time and date. When meeting with your team, be: i. professional ii. accommodating and conscious of varying skill levels, interests, backgrounds iii. submit documentation as per specifications below. Specifications You must: ● meet with Operations General Manager to discuss project scope and portfolio of planning documents
  • 151. ● participate in project meeting/s with project team ● submit: ○ project initiation and scope documents, including: a project brief; a project scope; a stakeholder analysis; a communication plan; roles and responsibilities; project snapshot ○ a project plan (version 1 and version 2) ○ a risk management plan (risk register and risk assessment for each of four risks) (version 1 and version 2) ○ a budget (version 1 and version 2). Assessment Task 1 BSBPMG522 Undertake project work © 2015 Innovation and Business Industry Skills Council 1st edition version: 1 Page 4 of 6 Your assessor will be looking for: ● communication and negotiation skills to work with team members and other stakeholders to maintain project schedules
  • 152. ● literacy skills to read, write and review a range of documentation ● planning and organising skills to develop project plans ● numeracy skills to analyse data and to compare timelines and implementation costs against budgets ● culturally appropriate communication skills to relate to people from diverse backgrounds and people with diverse abilities ● knowledge of relevant legislation from all levels of government that may affect aspects of business operations, such as: ○ anti-discrimination legislation ○ ethical principles ○ codes of practice ○ privacy laws ○ environmental issues ○ WHS ● knowledge of organisational structure and chains of authority and communication
  • 153. within the organisation ● knowledge of how the project relates to the organisation’s overall mission, goals, objectives and operations. Adjustment for distance-based learners ● No variation of the task is required. ● A follow-up interview may be required (at the discretion of the assessor). ● Documentation can be submitted electronically or posted in the mail ● Meetings may be conducted and observed live or via an appropriate teleconferencing tool. Assessment Task 1 BSBPMG522 Undertake project work © 2015 Innovation and Business Industry Skills Council 1st edition version: 1 Page 5 of 6 Appendix – Scenario Max Lionel Realty Max Lionel Realty (MLR), in order to build customer goodwill
  • 154. and satisfy its legal and ethical obligations, has decided to implement a program to: ● inform agents of legal and ethical obligations (particularly with respect to WHS and anti-discrimination legislation) and any standards or codes of conduct followed by the organisation ● promote high standards in professional conduct (see Real Estate Institute of Victoria (REIV) Code of Conduct and relevant legislation) ● inform clients, tenants and potential tenants of MLR’s commitments ● achieve employee and client buy-in for initiative. You are an external consultant (from Ace Consultants) contracted to project manage activities to achieve the objectives above. Quality standards for deliverables: ● clearly communicate legal obligations and REIV obligations ● contain as content or support company strategic directions ● no grammar or spelling errors ● professional but friendly language
  • 155. ● fair and flexible delivery for intended audience ● meet audience requirements and sensitive to information needs, cultural diversity. Previous needs analysis for the project has uncovered characteristics and requirements of Residential and Commercial Agents and Clients: Agents Clients Tenants ● under stress; time poor ● highly trained and competent in selling and managing real estate ● unaware of legal, ethical requirement. just want to please clients ● even if aware, have no idea how to apply to daily client practice
  • 156. ● cynical: e.g. ‘why do I have to pay attention to MLR’s internal business? I just want them to manage my property.’ ● time poor ● not sure of MLR obligations and commitment to best-of- breed client service and ethical practice, REIV code of conduct ● sometimes feel discriminated against on basis of: ○ lifestyle ○ family status
  • 157. ○ cultural background ○ income, etc. Assessment Task 1 BSBPMG522 Undertake project work © 2015 Innovation and Business Industry Skills Council 1st edition version: 1 Page 6 of 6 Agents Clients Tenants ● unclear on overall strategic aims of MLR ● culturally diverse. ● feel it’s the agent’s obligation to fill rental/lease properties according to client wishes: e.g. ‘I choose who lives in/leases my
  • 158. property’ ● culturally diverse. ● residential agents have been rude or insensitive on occasion: e.g. ‘you wouldn’t treat your rich clients or investment partners this way’ ● do not feel they are adequately consulted ● residential/commercial agents/clients have let themselves in without consultation ● inspections are sometimes unannounced. Project conditions are as follows:
  • 159. ● Six to eight team members (two to four candidates plus four virtual team members) who must be utilised and budgeted for. Operations General Manager (the assessor) will determine composition of project team. ● The structure of the work should include roles for project sponsor, technical experts, quality assurance of deliverables, project manager (yourself initially and, after provisional approval, as negotiated with your team), and roles and responsibilities for each team member to achieve the deliverables according to standards, etc. ● All reasonable resources (e.g. access to a room, computers, software and templates) will be provided. Paper and telecommunications costs, for example, to be covered by candidates. All resources must be costed and included in your budget. ● Budget: $15,000. ● Your Operations General Manager (the assessor) will suggest