COLLABORATE. INNOVATE. EDUCATE.
Managing Mobility during Design-
Build Highway Construction –
Successes and Lessons Learned
Duane Milligan, P.E. – TxDOT
Kristopher Pruner – CTR
COLLABORATE. INNOVATE. EDUCATE.
Design-Build Method
• Schematic-level Design
• Two-Step Procurement
• Selected Design-Build Contractor responsible
for final design as well as construction
– Some construction begins while design in other
areas is ongoing
– Contractor develops Traffic Control Plans
COLLABORATE. INNOVATE. EDUCATE.
Dallas Horseshoe Project
Margaret
McDermott
Bridge
• Upgrade Roadway Geometry
• Replace IH 30 and IH 35E
Bridges across Trinity River
• Construct Additional Lanes
• Construct Margaret
McDermott Bridge
COLLABORATE. INNOVATE. EDUCATE.
Horseshoe – Mobility Challenges
• High Volume Interstate Highways
– 460,000 average weekday traffic through project
area
• Constraints involving Houston Viaduct
• Proximity to Downtown Dallas
COLLABORATE. INNOVATE. EDUCATE.
Horseshoe – Successes
• Traffic Control Plan designed in a way that
generally maintained existing access or
provided reasonable alternates
• Contractor structured work to maximize the
usefulness of each closure
• No overnight closures lingered into the
morning peak period
COLLABORATE. INNOVATE. EDUCATE.
Horseshoe – Work during One Night
• Work Completed during one night of full WB IH
30 and full NB IH 35E closure:
– Set 7 Tx62 girders over westbound IH 30 on Bridge 45
– Set 8 Tx62 girders over northbound IH 35E on Bridge
10
– Placed temporary shoring and work platform for
Houston Street arches, decking, and railing
– Removed bridge overhangs for completed Jefferson
Street railing
– Removed existing high mast illumination pole
– Placed 1000 lf of portable concrete barrier
COLLABORATE. INNOVATE. EDUCATE.
Horseshoe – Work during One Night
COLLABORATE. INNOVATE. EDUCATE.
Horseshoe – Work during One Night
COLLABORATE. INNOVATE. EDUCATE.
Horseshoe – Work during One Night
COLLABORATE. INNOVATE. EDUCATE.
Horseshoe – Work during One Night
COLLABORATE. INNOVATE. EDUCATE.
Horseshoe – Work during One Night
COLLABORATE. INNOVATE. EDUCATE.
Lessons Learned
• Collaboration
– Work with the contractor to find reasonable
solutions to difficult situations
• Tracking
– Ongoing and persistent monitoring of lane
closures
COLLABORATE. INNOVATE. EDUCATE.
Tools to Protect Mobility
• Stated Minimum Number of Lanes to be
Maintained
• Designated Allowable Closures
• Liquidated Damages/Lane Rental Fees
– Including an exemption amount (“Bank Balance”)
• Collaborative relationship between TxDOT and
the design-build contractor
COLLABORATE. INNOVATE. EDUCATE.
Minimum Number of Lanes
• Origin-Destination Table defines minimum number of lanes
to be maintained during peak periods
• Developed based on consideration of detours, planning,
comparison of existing and proposed conditions
# Origin Via Destination Minimum Number of Lanes to be
maintained
1 NB IH
35E
NB
IH
35E
NB IH 35E 2 Through Lanes
2 Colorado 1 Lane Exit or Detour
3 Riverfront 1 Lane Exit (2 Lanes for at least 200’
upstream of intersection)
4 Jefferson via HOV 0 (with interim HOV lane end and transition
to main lanes near Louisiana)
5 Reunion 1 Lane Exit
6 EB
IH
30
EB IH 30 2 Through Lanes either to EB IH 30 or EB IH
30 CD (or 1 lane to each) (If 2 Through
Lanes only to EB IH 30, provide slip ramp
east of Hotel Street to EB IH 30 CD)7 EB
IH
30
CD
EB IH 30 CD
8 Lamar/Griffin/Downtown Maintain Routes or Detour
COLLABORATE. INNOVATE. EDUCATE.
Allowable Closures Table
• Provides durations for which closures/detours
may be in place
• Paired with a table specifying liquidated
damages for exceeding allowable durations
# Origin Via Destination Description Allowable
Closure
Duration
(Consecutive
Calendar
Days)
2 NB IH 35E NB IH 35E Colorado NB IH 35E access to
Colorado east of IH
35E
90 Days
8 NB IH 35E EB IH 30
CD
Lamar/Griffin/Downtown NB IH 35E access to
downtown through
the EB IH 30 CD
90 Days
COLLABORATE. INNOVATE. EDUCATE.
Liquidated Damages and Lane
Rental Fees
• Liquidated Damages assessed
for Time Period A closures
• First $1,400,000 in Lane
Rental Fees exempted (Time
Periods B, C, and D)
Northbound IH
35E (South of
Mixmaster)
Time Period A
Liquidated
Damages Per
Hour
Time Period B
Lane Rental
Fees Per Hour
Time Period C
Lane Rental
Fees Per Hour
Time Period
D Lane Rental
Fees Per Hour
One Lane Closed $10,000 $2,000 $100 $50
Two Lanes Closed $20,000 $5,000 $500 $100
Three Lanes
Closed
$50,000 $20,000 $2,000 $500
Four Lanes
Closed (Full Main
Lane Closure)
$100,000 $50,000 $5,000 $2,000
HourDay Sun Mon-
Thu
Fri Sat
… … … … …
4:00 D D D D
5:00 D C C D
6:00 D A A C
7:00 C A A B
8:00 C A A B
9:00 C A A B
10:00 B B B B
11:00 B B B B
12:00 B B B B
13:00 B B B B
14:00 B B B B
… … … … …
COLLABORATE. INNOVATE. EDUCATE.
Collaborative Relationship
• TxDOT and contractor met frequently during
design process
• Difficult areas reviewed jointly to develop
solutions
• Closures scheduled and discussed in advance
• Documentation of actual closure times provided
following each closure
• Periodic, structured review of lane rental hours
and fee calculations to make sure each party
agrees with amounts
COLLABORATE. INNOVATE. EDUCATE.
Keys to Success
• Before/During Procurement
– Evaluate mobility needs near beginning of
procurement
– Give clear direction to proposers in draft contract
documents
– Be open to feedback from proposers and consider
changes
COLLABORATE. INNOVATE. EDUCATE.
Keys to Success
• During Design/Construction
– Work collaboratively with the contractor during
TCP design to make sure public’s needs are being
met
– Stay on top of tracking closures
• Future Projects
– Use lessons learned to improve later projects

Managing Mobility during Design-Build Highway Construction: Successes and Lessons Learned

  • 1.
    COLLABORATE. INNOVATE. EDUCATE. ManagingMobility during Design- Build Highway Construction – Successes and Lessons Learned Duane Milligan, P.E. – TxDOT Kristopher Pruner – CTR
  • 2.
    COLLABORATE. INNOVATE. EDUCATE. Design-BuildMethod • Schematic-level Design • Two-Step Procurement • Selected Design-Build Contractor responsible for final design as well as construction – Some construction begins while design in other areas is ongoing – Contractor develops Traffic Control Plans
  • 3.
    COLLABORATE. INNOVATE. EDUCATE. DallasHorseshoe Project Margaret McDermott Bridge • Upgrade Roadway Geometry • Replace IH 30 and IH 35E Bridges across Trinity River • Construct Additional Lanes • Construct Margaret McDermott Bridge
  • 4.
    COLLABORATE. INNOVATE. EDUCATE. Horseshoe– Mobility Challenges • High Volume Interstate Highways – 460,000 average weekday traffic through project area • Constraints involving Houston Viaduct • Proximity to Downtown Dallas
  • 5.
    COLLABORATE. INNOVATE. EDUCATE. Horseshoe– Successes • Traffic Control Plan designed in a way that generally maintained existing access or provided reasonable alternates • Contractor structured work to maximize the usefulness of each closure • No overnight closures lingered into the morning peak period
  • 6.
    COLLABORATE. INNOVATE. EDUCATE. Horseshoe– Work during One Night • Work Completed during one night of full WB IH 30 and full NB IH 35E closure: – Set 7 Tx62 girders over westbound IH 30 on Bridge 45 – Set 8 Tx62 girders over northbound IH 35E on Bridge 10 – Placed temporary shoring and work platform for Houston Street arches, decking, and railing – Removed bridge overhangs for completed Jefferson Street railing – Removed existing high mast illumination pole – Placed 1000 lf of portable concrete barrier
  • 7.
  • 8.
  • 9.
  • 10.
  • 11.
  • 12.
    COLLABORATE. INNOVATE. EDUCATE. LessonsLearned • Collaboration – Work with the contractor to find reasonable solutions to difficult situations • Tracking – Ongoing and persistent monitoring of lane closures
  • 13.
    COLLABORATE. INNOVATE. EDUCATE. Toolsto Protect Mobility • Stated Minimum Number of Lanes to be Maintained • Designated Allowable Closures • Liquidated Damages/Lane Rental Fees – Including an exemption amount (“Bank Balance”) • Collaborative relationship between TxDOT and the design-build contractor
  • 14.
    COLLABORATE. INNOVATE. EDUCATE. MinimumNumber of Lanes • Origin-Destination Table defines minimum number of lanes to be maintained during peak periods • Developed based on consideration of detours, planning, comparison of existing and proposed conditions # Origin Via Destination Minimum Number of Lanes to be maintained 1 NB IH 35E NB IH 35E NB IH 35E 2 Through Lanes 2 Colorado 1 Lane Exit or Detour 3 Riverfront 1 Lane Exit (2 Lanes for at least 200’ upstream of intersection) 4 Jefferson via HOV 0 (with interim HOV lane end and transition to main lanes near Louisiana) 5 Reunion 1 Lane Exit 6 EB IH 30 EB IH 30 2 Through Lanes either to EB IH 30 or EB IH 30 CD (or 1 lane to each) (If 2 Through Lanes only to EB IH 30, provide slip ramp east of Hotel Street to EB IH 30 CD)7 EB IH 30 CD EB IH 30 CD 8 Lamar/Griffin/Downtown Maintain Routes or Detour
  • 15.
    COLLABORATE. INNOVATE. EDUCATE. AllowableClosures Table • Provides durations for which closures/detours may be in place • Paired with a table specifying liquidated damages for exceeding allowable durations # Origin Via Destination Description Allowable Closure Duration (Consecutive Calendar Days) 2 NB IH 35E NB IH 35E Colorado NB IH 35E access to Colorado east of IH 35E 90 Days 8 NB IH 35E EB IH 30 CD Lamar/Griffin/Downtown NB IH 35E access to downtown through the EB IH 30 CD 90 Days
  • 16.
    COLLABORATE. INNOVATE. EDUCATE. LiquidatedDamages and Lane Rental Fees • Liquidated Damages assessed for Time Period A closures • First $1,400,000 in Lane Rental Fees exempted (Time Periods B, C, and D) Northbound IH 35E (South of Mixmaster) Time Period A Liquidated Damages Per Hour Time Period B Lane Rental Fees Per Hour Time Period C Lane Rental Fees Per Hour Time Period D Lane Rental Fees Per Hour One Lane Closed $10,000 $2,000 $100 $50 Two Lanes Closed $20,000 $5,000 $500 $100 Three Lanes Closed $50,000 $20,000 $2,000 $500 Four Lanes Closed (Full Main Lane Closure) $100,000 $50,000 $5,000 $2,000 HourDay Sun Mon- Thu Fri Sat … … … … … 4:00 D D D D 5:00 D C C D 6:00 D A A C 7:00 C A A B 8:00 C A A B 9:00 C A A B 10:00 B B B B 11:00 B B B B 12:00 B B B B 13:00 B B B B 14:00 B B B B … … … … …
  • 17.
    COLLABORATE. INNOVATE. EDUCATE. CollaborativeRelationship • TxDOT and contractor met frequently during design process • Difficult areas reviewed jointly to develop solutions • Closures scheduled and discussed in advance • Documentation of actual closure times provided following each closure • Periodic, structured review of lane rental hours and fee calculations to make sure each party agrees with amounts
  • 18.
    COLLABORATE. INNOVATE. EDUCATE. Keysto Success • Before/During Procurement – Evaluate mobility needs near beginning of procurement – Give clear direction to proposers in draft contract documents – Be open to feedback from proposers and consider changes
  • 19.
    COLLABORATE. INNOVATE. EDUCATE. Keysto Success • During Design/Construction – Work collaboratively with the contractor during TCP design to make sure public’s needs are being met – Stay on top of tracking closures • Future Projects – Use lessons learned to improve later projects