During May 2016, I gave a long talk as a risk expert at an Asian Power Conference in Singapore about identifying risks and uncertainties for Power Plant developers
2. 2
What is risk?
What is risk management?
Why bother with it?
Different perspectives of Risk
A suggested process
Identify
Quantify (assess)
Response
Avoid (Terminate)
Transfer
Mitigate (Treat)
Accept (Take)
Monitoring and Review
4. ISO 31000
According to ISO 31000:2009, risk is the
“effect of uncertainty on objectives”
and an effect is a positive or negative
deviation from what is expected.
4
13. 13
Identify Risks
What are the uncertainties associated with achieving the objectives?2Step
Assess Risks
Which risks are most significant?4Step
Respond to Risks
What do you choose to do about risks?5Step
Establish the Context: Understand The Business
What is the Business, and the Environment in which it operates?1Step
3Step Analyse Risks
Utilise consistent analytical methods
14. 14
Risk Identification Tools and Techniques
Documentation Reviews
Information Gathering Techniques
Brainstorming
Delphi Technique
Interviewing
Root cause identification
SWOT analysis
Checklist Analysis
Assumptions Analysis
Diagramming Techniques
Cause and Effect (Fishbone) diagrams
System or process flow charts
Influence diagrams
Stakeholder Identification and mapping
16. Risk Identification
When a power plant development project goes wrong
there can be several things to blame, ranging from
inexperience at the hand of the developer, to site
specific problems, technical issues, regulatory
problems and permitting issues, all of which affect
financial and technical viability of the project.
Failure to develop a project can come at a great cost to
the developer, and other stakeholders involved.
16
17. Some Questions?????
Which key risks impact the development of a power plant project?
How do risks vary in practice by energy source, and location?
How do these risks impact development performance?
How do developers manage these risks?
Where along the development process do these risks make impact?
How do risks impact new project investment decision making?
How do risks impact power plant development project selection?
17
18. Power plant development projects
Typically capital intensive
Comprise of a complex network of interconnected risks which can
impact the development's performance.
Failure to develop the power plant to meet the performance
constraints can come at a great cost to the developer and other
stakeholders involved.
It is essential for developers to be able to analyse the risk in
their project opportunities to develop investment strategy plan
based on their risk appetite, and ability to manage the risk.
18
21. Project development categories
Power plant size: The generation output of the
power plant.
Development type: Whether this is a new plant,
expansion or a version thereof.
Site characteristics: Including if this is an
undeveloped site or not.
21
22. Power plant developers
Investor Owned Utilities (IOUs),
Public Owned Utilities (POUs),
Independent Power Producers (IPPs)
In recent years utility mergers, redesigned holding structures, and
establishment of non-regulated subsidiaries that own power plants and
foreign owned utilities, have changed the nature of these boundaries.
22
23. Project Development Process
Development of new power plants is generally
either in the hands of
a regulatory authority (in centralized
regulated systems),
or the energy companies (in liberalized
deregulated systems).
23
24. Phases of development
The power plant lifecycle can be divided into the
following general phases:
1) Planning phase,
2) Construction and commissioning phase,
3) Operation phase, and
4) Decommissioning phase
24
27. Project evaluation
Bottom up process (reactive)
Landowner seeks developers
Referral and word of mouth
Relationships and past customers
Tenders
Top down process (proactive)
The geographic location,
The energy technology,
The ideal site
the project specifics
27
29. Forms of Partnering
Partner's experience
Size of project under development
Risk management
Will they contribute?
Will they pay cash calls?
29
32. The process of identifying risks varies from project to
project.
During pre-selection phase, initial risk identification may
be developed by specialized groups on behalf of the
developer or the developer themselves depending on
in-house knowledge.
Once a project has been selected, effective, ongoing risk
identification requires input from the entire project
team and from others outside it, such as owner's
representatives, contractors, and internal and
external consultants or advisors
32
33. Country attractiveness
Developer's network in that geographic area
Ease of development
Labor resource availability
Stakeholders‘ influence
Political pressure
Prior project commitments
Level of expertise knowledge in that area
Country's power plant portfolio mix and renewable . energy
targets
Government support
Country's future outlook
Climate change strategy
33
40. Risk Classification
1. World system risk
2. World price risk
3. Country risk
4. Institutional and regulatory risk
5. Industry and competitive risk
6. Project risk
40
49. Power plant size
Mega Projects: Mega Projects typically cost
over USD 1 billion and attract public attention
because of their substantial impact on
communities, budgets, and the environment.
Such projects suffer from a high risk of being
derailed or cancelled entirely due to the
difficulties of implementing such large,
complex, and frequently politically as well as
environmentally sensitive projects.
49
52. Hydro
Large (Pelton Turbine,
Francis Turbine,
Propeller Turbine,
Kaplan Turbine),
Small/Mini (Run of river),
Micro,
Hydrokinetic turbines
52
53. Oil and Gas
Reciprocating,
Natural Gas (Shale Gas),
Simple Gas Turbine (Aero-Derivative Gas Turbine,
With Recuperation,
Humid Air Turbine,
Cascaded Humid Air Turbine,
Heavy Frame Gas Turbine),
Combined Cycle,
53