SlideShare a Scribd company logo
1 of 79
Download to read offline
Investigation Report

Power Transformer Tank Rupture and Mitigation
  - Current State of Practice and Knowledge


           by the Task Force of
   IEEE Power Transformer Subcommittee


               March 09, 2010
                Houston, TX.
CONTENT

1.Investigation and Analysis -10 minutes
2.Utility Experience (15 minutes)
3.Manufacturer’s Perspective (25 minutes)
4.PRD (10 minutes)
5.Conclusions (10 minutes )
6.Q&A (5 minutes)
Analysis of Transformer
    Tank Ruptures


Electric Power Research Institute

         Wayne Johnson
       wejohnson@epri.com

         Nick Abi-Samra
       nabisamra@epri.com
Survey On Transformer Rupture



Objectives
• Develop an understanding of the tank rupture process
  associated with internal faults.
• Develop tools, and methods, for evaluating the influence
  of tank designs on rupture characteristics




                            2
Background

• 42 transformer failures (tanks
  ruptured or deformed without
  rupture)
• 22 utilities
• 10-year period (1980-1990)
• 7 transformer manufacturers
• Different voltage levels
• Different designs: (GSU’s, Auto,
  Phase Shifters, etc.)




                               3
Conclusions

• The arc energy is the critical rupture parameter
• Differences in transformer design and application are not major
  discriminators in the tank rupture
• The fault energy capacity of a tank can be increased by increasing
  the tank rupture pressure limit and tank flexibility.
   – The pressure at which tanks rupture can be increased by local
      strengthening of weak points, while the tank flexibility can be
      increased by replacing large beams with a number of smaller
      beams (which permit greater deflection at a given stress level).
• Venting to conservators or to auxiliary tanks was not found to be
  effective for heavy faults (those with arc power greater than 300 MW)




                                   4
Conclusions

• A long arcing time is not
  necessary for rupture:
   – About 75% of the cases
      occurred with arcing times
      less than 4.5 cycles.
• Since arc energy is
  proportional to I2t, where the t
  is duration in seconds, the
  parameter which offers the
  most opportunity for control of
  the risk of rupture is the
  magnitude of the current, and          Graph of Tank Deformation
                                         Rupture as a function of fault
  specifically, the peak crest            current and fault duration.
  value of the first half cycle of
  the fault current (and the
  associated X/R of the circuit).

                                     5
Power Transformer
Tank Rupture
A Utility's Experience

Marc Foata
IEEE Transformers Committee
Houston, March 2010
Presentation
Assessment of the risk
  Statistics
  Arc energy
Prevention of tank rupture
  Venting
  Containment
Specification of a Tank pressure withstand
requirement

                                         2
Assessing the risk - Statistics




                                  3
Assessing the risk - Statistics




                                  4
Assessing the risk - Statistics




                                  5
Arc energy - 4 MJ




                    6
Arc Energy - 8 MJ




                    7
Arc Energy - 12 MJ




                     8
Arc Energy - 14 MJ




                     9
Arc energy vs Damage




                       10
Arc Energy - Calculation

        Earc = 0.9 V I t
I – Arc current: Evaluated from short-circuit level
T – Fault clearing time: Depends mainly on
protection
V – Arc voltage: Very difficult to evaluate
0.9 – Factor introduced for square waveform of V

                                                 11
Arc Energy - Recordings
                     A     100
                                                                                                                          Unité Support et analyses - DESTT




                                                                                                                                   E   BN TT MAIS MICOUA
                                80
                                                                                                                                   E   BN L-7019 MICOUA
                                60                                                                                                 E   BN L-7011 MICOUA
                                                                                                                                   E   BN L-7027 MICOUA
                                40
                                20




                  (kV)
                                 0
                                -20

                                -40
                                -60
                                -80
                                            205       210        215        220        225        230        235         240       245        250         255
                                                                                     (ms rel. à 05:34:32.2870)
                                                  2008-09-12 05:34:32.499 MICOUA       735-02 TENSION RÉSIDUELLE DÉFAUT TRANSFO T8-B

                                12
                                11
                                10
                                 9
                                 8




                    (MJoules)
                                 7
                                 6
                                 5                                                                                 ÉNTERGIE     TOTALE    (TT MAIS)
                                 4                                                                                 ÉNTERGIE     TOTALE    (TTC 7019)
                                 3                                                                                 ÉNTERGIE     TOTALE    (TTC 7011)
                                 2                                                                                 ÉNTERGIE     TOTALE    (TTC 7027)
                                 1
                                 0
                                -1
                                            205       210        215        220        225        230        235         240       245        250         255
                                                                                     (ms rel. à 05:34:32.2870)
                                        2008-09-12 05:34:32.499 MICOUA        735-02 ESTIMÉ DE L'ÉNERGIE TOTALE DANS LE DÉFAUT TRANSFO T8-B

                   20000

                   15000

                   10000

                      5000
            (A)




                                 0

                    -5000

                  -10000
                                                                                                                               COURANTS CÔTÉ 735 kV
                  -15000                                                                                                       COURANTS APROX. CÔTÉ 315 kV

                  -20000
                                      190           200            210             220             230             240             250              260            270
                                                                                     (ms rel. à 05:34:32.2870)
                                                          2008-09-12 05:34:32.499 MICOUA       735-02 COURANTS DE DÉFAUT TRANSFO T8-B


             Lundi 15 Septembre, 2008
                                                                                                                                                       12
                                             VECTEURDONNEESPARTAGE@AUTOMATISMESCOMPORTEMENTRAPPORTRAPP_2008TOSC_ANA20080912_053432499_ENERGIE_T8-B_MICOUA.TOS
Arc Energy - Evaluation of Arc
          Voltage
60-100 V/cm range is often referred
For 40 kV, this means an arc length of
more than 4 m !!




                                         13
Arc Energy - Pressure Effect

        V = 55L P
Constant 55 V/cm
L is arc length (m)
P is absolute pressure (atm)
Pressure in the gas bubble at arc ignition
can reach extremely high values
                                             14
Prevention of tank rupture –
   Venting Simulations




                               15
Prevention of tank rupture –
   Venting Simulations




                               16
Prevention of tank rupture – Vented
     vs Non-vented Example




                                  17
Prevention of tank rupture –
   Conclusions on venting

Pressure reduction from a single 25 cm
aperture is low and becomes negligible
when the arc is more than 1 meter away.
An effective pressure venting strategy
would require either a very large venting
duct or numerous small apertures in the
close vicinity of the arc.

                                            18
Prevention of tank rupture -
      Containment




                               19
Prevention of tank rupture -
       Containment

Present design can contain up to 10 MJ
for the largest tanks (735 kV)
More resistant tank design can be
achieved
Need to implement specifications with
minimum energy requirement to meet.
Energy requirement will be a compromise
between the feasibility and the likelihood.

                                              20
New Specification - Philosophy
Priority is given to the protection of the
workers
Worst energy levels may not always be
containable by the tank
First rupture point must be the cover
Required calculation tools must be
accessible to transformer designers
Must take into account the highly dynamic
phenomena involved
Must be easily verified
                                             21
New specification - Formula

            ⎡               ⎤
   Ps= F
                 1   kE
            ⎢100   +    − 50⎥
            ⎣    4 100C     ⎦

Ps – Calculated tank pressure withstand
F – Dynamic (time & location) amplification
E – Fault energy level to withstand
K – Arc energy conversion factor
C – Tank expansion coefficient
                                         22
New specifications – Dynamic
            factor
        3

       2,5

        2
   F




       1,5

        1
             0   20   40   60    80     100    120    140   160   180   200


                                C/V (x 10 -5 kPa-1)




Time related dynamic factor (pressure and
deformation)
Proximity related dynamic factor
Takes into account tank volume          23
New specification : Hydro-Québec's
Energy Containment Requirements

    Voltage Class   Arc Energy




                                     24
New specification - Implementation


 All transformer suppliers since 1992 have shown
 adequate tank withstand calculation capabilities.
 Since implementing energy level requirements
 (2006), manufacturers have been forced to
 improve their tank design.
 Detailed analysis by a number of manufacturers
 confirmed that all the specified energy
 requirements can be met.

                                                25
Transformer Tanks
- Some Factors Related to Rupture

  A Manufacturers Perspective

    IEEE Transformers Committee
       Houston, March 9, 2010

        by Bill Darovny, P.Eng.
           Siemens Canada
Facts about Liquid Filled Transformer Tanks

• C57.12.00 and C57.12.10 define the operating
  pressures for transformer tanks
  – full vacuum = -101.4 kPa (-14.7 psig)
  – pressure 25% above the normal operating
    pressure


• Transformer tanks are not pressure vessels
  – are not required to be designed to the ASME
    Boiler and Pressure Vessel Code.
     • ASME code is mandatory when operating
       pressure exceeds 2 atmospheres (203 kPa).
Facts about Liquid Filled Transformer Tanks

• C57.12.10 requires a pressure relief device to
  be mounted on the tank cover
  – Typically activate at 34.5 to 69 kPa (5 to 10 psig)


• Most rectangular tanks will sustain internal
  pressures of 140 to 210 kPa (20 to 30 psig)
  before rupture

• A tank on its own cannot be made strong
  enough to resist all magnitudes of internal
  pressure
Transformers have been saved from
rupture by common protection devices

  • Pressure Relief Devices
  • Gas Detector Relays
  • Rapid Pressure Rise Relays
  • Real time Gas Monitors

Provided the alarm signals are quickly
   recognized and the transformer is
             de-energized
Pressure Relief Device in Action
Not Every Tank Rupture Results in a Fire
 Unit gassing, GDR alarmed, long delay in response to alarm,
ambient -30°C, reaction force to rupture shifted unit on the pad.
Some Units Burn After Tank Rupture- 750 MVA 500kV
Same Rating Different Supplier
The Location Where a Tank will Rupture is a
               Function of:

1. the rate of change of the pressure increase
     Slow rate:
     •   Pressure has time to distribute throughout the tank
    Fast rate:
     •   Results in a pressure build-up at the source


2. the co-ordinates of the pressure source
   inside the tank

3. the closest weak spot to those co-ordinates
Slow Rate of Pressure Increase
- Failed at 2 locations on the Cover
- Tensile end reactions tore the welds at the ends of the stiffeners
- Cover end angle rotated and the weld to tank flange cracked
Moderate Rate of Pressure Increase

• Tank failed at
the cover joint
• Some stiffeners
on the tank wall
were permanently
deformed
• There were no
cracks in the oil
containment
welds in the tank
body
Rapid Rate of Pressure Increase

• Co-ordinates of
pressure source was
about 1/3 tank height

• Wall plate fracture
started at the corner
welds and ran almost
full height of the tank


• Tank wall to bottom
weld joint also failed
Rapid Rate of Pressure Increase

• Cover weld did not fail


• Tank failed at the high
stress points in welds at
the tank corners and
wall penetrations then
propagated through the
wall plates


• Unit was returned to
the factory and rebuilt
Weakest Points of a Rectangular Tank

• Main cover to tank wall flange - weld joint

• Tank wall corners - weld joint

• Tank wall to base plate - weld joint

• High stress points at throats and large
  penetrations through the tank plates

• High stress points at ends of stiffeners where the
  end reaction force is transmitted to the tank plate
Main Cover to Tank Wall Flange
     Mode of Weld Failure

              Typical Cover Welded Joint

              Upward and outward forces
              due to internal pressures



              Stress is concentrated at the
              weakest point - the root of
              the weld.

              Weld crack progresses
              outward from the root
Typical Rectangular Tank Corner Joints



                  Stresses are on the face of
                  the weld.


                  The face of the weld is
                  stronger than the root of
                  the weld.


                  Adding corner gussets will
                  reinforce this joint
Cylindrical Tanks are Inherently Stronger
           than Rectangular Tanks

• 110MVAR 735 kV
shunt reactor
• The tank wall is
stressed in hoop
tension
• Typically the
cylinder walls can
sustain pressures
> 350 kPa (50 psig)
• Weakest point is
the cover weld
Design to Help Reduce Tank Rupture

• Design in service systems to detect faults
  early & de-energize quickly

• Use detection & relief accessories
  – Real time gas monitors
  – Gas detector relays - ensure gas collection
    system / piping functions as intended
  – Rapid pressure relays
  – Pressure relief devices
     • To be effective, relief devices must be located close to
       the pressure source
     • Standard size relief devices may not prevent all tank
       ruptures
Design to Help Reduce Tank Rupture

• The best location for a tank to fail is at the welded
  cover joint as this will minimize fluid loss

• Strengthen the tank below the cover joint
   – Reinforce tank corners and wall to bottom joints
     with plates / gussets

   – Distribute stiffener end reaction forces with
     reinforcements or by connecting to stiffeners on
     adjacent walls

   – Reinforce around wall penetrations to reduce the
     high stress points
Transformer Tank Rupture and Mitigation
                 Tutorial
               March 9, 2010


Mitigation Research and Example Techniques
           Presented by Craig Swinderman
       Mitsubishi Electric Power Products, Inc.
Research on Transformer Tank Rupture
                  Mitigation
•   Joint research performed in the mid-1980’s by three large Electric
    Utilities in Japan, Tokyo University, and several transformer
    manufacturers.

•   Goal was to study ways of reducing the risk of transformer tank
    explosion in urban substations/ underground substations.

•   Full scale model testing performed.

•   Arc energies calculated and gas generation rate observed.

•   Pressure rise models developed.

•   Tank construction countermeasures developed.
Summary of Research

Tank Explosion                  Study Process for Internal Fault                     Verification
Process                                                                              Tests
                                 Estimation of Fault Condition
  Internal Fault                                                                    Arc Test in Oil Tank
                                 ① Arc Current ② Arc Voltage ③ Time
   Dissolved Gas
    Generation                    ④ Dissolved Gas Generation Volume



  Internal Pressure                 Pressure Rise Analysis                          Pressure Rise Test
       Increase
                             Dynamic Analysis considering Oil Motion                using Full Scale Tx



Internal Pressure                Comparison between Internal
                                 Pressure and Tank Strength
> Tank Strength

                                         Countermeasure
     Tank
                      ① Tank Strength Improvement ② Protection Relay Improvement
   Explosion
                      ③ System Improvement        ④ Pressure Restrained Structure
Dynamics of Internal Fault (1)
                                                                                                           10000
                Arc Test in Oil Tank
                Arc Test in Oil Tank




                                                                                         Arc Voltage (V)
                                                                                                             1000
                                             Electrode




                                                                                                             100
                                                                        Arc                                         10         100          1000
                                                                                                                          Arc Length (mm)
                                                                       Oil                                                Gas Volume
                                                                                                               1




                                                                                           Gas Volume (m3)
             Arc Current : 1.3 to 40.9 kA
             Time             : 3Cycle (0.05sec)
                                                                                                              0.1
             Arc Energy : 0.11 to 2.64 MJ
             Gap Length : 100 to 300 mm

*Reference – T. KAWAMURA, M. UEDA, K. ANDO, Y. MAEDA, Y. ABIRU, M. WATANABE, K.
MORITSU “Prevention of Tank Rupture Due to Internal Fault of Oil Filled Transformers”,                       0.01
CIGRE, 12-02, 1988.
                                                                                                                 0.1           1            10
                                                                                                                         Arc Energy (MJ)
Dynamics of Internal Fault (2)
Pressure Rise Test using Full Scale model for verifying pressure rise
Pressure Rise Test using Full Scale model for verifying pressure rise
- Pressure rise at internal fault can be simulated by powder combustion, considering nozzle area of
  container and powder amount.
- Dead space (steel tank) was set for simulating internal parts(Core,Coil).in the tested tank.
                                                                                               Measured Results
   Transformer : 275kV 300MVA
                                                                                               Analytical Results
   Arc Energy : 142,000kW、 Time : 80msec




                                                                         Pressure
     (Single Line-Ground Fault at Upper Tank)                                                           Upper Tank



                                                                                                                 Time
                                         Combustion Container
                                                 Φ300,L570                                              Middle Tank




                                                                        Pressure
   Upper Tank
                                   Gas Outlet
                                   (Φ12*72)
                                                                                                                 Time


                                                                                                         Lower Tank




                                                                        Pressure
                                                                                                                  Time
                         Middle Tank                         *Reference – T. KAWAMURA, M. UEDA, K. ANDO, Y. MAEDA, Y.
Lower Tank
                                       Cartridge increment   ABIRU, M. WATANABE, K. MORITSU “Prevention of Tank
                                          (Max.7500g)        Rupture Due to Internal Fault of Oil Filled Transformers”, CIGRE,
                                                             12-02, 1988.
Results of Analysis
•   Decomposed gas generation calculated to be around
    0.5L/kW sec for larger 275 kV class transformers at HV lead.*

•   Dynamic oscillation of fault pressure wave (kinetic energy)
    has a considerable influence on the pressure rise. (Dynamic
    Load Factor approx. 1.3 was recommended)*

•   Tank expansion characteristics and tank strength are
    important in determining the transformer’s capability to
    resist rupture.

•   Reinforcements can be made at the joining flange between
    the tank and cover (or flange between upper and lower tank
    for shell-form) to significantly improve the tank strength
    against rupture.


*Reference – T. KAWAMURA, M. UEDA, K. ANDO, Y. MAEDA, Y. ABIRU, M. WATANABE, K. MORITSU
    “Prevention of Tank Rupture Due to Internal Fault of Oil Filled Transformers”, CIGRE, 12-02, 1988.
Example of Tank Strength Improvement


            Conventional Type                      Improved Type




Connecting Part
                       Alleviation of Stress   Improvement of Connecting Part
                       Concentration           Strength by Tie Reinforcement
Pressure Reducing Space
•   Diaphragm type Conservator Tanks can be used as
    effective pressure reducing space if the connection duct to
    the main tank is short, the cross sectional area of the duct
    is large (approx. 1.4 m dia.), and the air space in the
    conservator diaphragm is adequate

Diaphragm (bladder)                            Conservator Tank

    Connection duct



                       Transformer main tank




      •Tests on 300 MVA, 230 kV units have verified ability to
      withstand 15,000 MVA short circuit capacity without
      rupture of the tank.
      •Still requires operation of protective relays and circuit
      breakers to clear fault within approx. 60 - 80 ms.
Gas Insulated Power Transformers

•Use SF6 Gas as the insulating and cooling medium
instead of insulating oil.

•First units produced in 1967.

•Several thousand units of various sizes now in
service worldwide, several manufacturers.

•Transformer applications: From Distribution class
units up to 400 MVA, 345 kV ratings.

•Primarily used in substations located in urban
areas (including inside buildings, underground) due
to safety benefits.
Features of Gas Insulated Transformers



• Use SF6 Gas as insulating and cooling
  medium, instead of oil.

• Typically use special internal insulation
  materials such as plastics, special paper,
  and pressboard.

• SF6 has excellent dielectric properties, but
  not as good for heat transfer.
Benefit of Gas Insulated Transformers
 SF6 Gas Insulation:                      non-flammable, compressible gas

 Pressure rise during an internal fault is slower than oil-immersed (non-
 compressible fluid), thus SF6 gas reduces the chances of tank explosion
Pressure Rise (%)




                    100
                     100                               Tank Strength
                     80
                      80
                     60
                                Oil-Immersed
                      60
                                Transformer
                     40
                      40                                      Gas Insulated
                     20
                      20
                                                              Transformer
                      00
                           00     0. 22
                                   0.     0. 44
                                           0.         0. 66
                                                       0.        0. 88
                                                                  0.     11
                                                  Fault Time (sec)
Application Example



                             15MVA, Three phase, 50Hz,
                             Continuous Rating,
                             Core-Form,
                             Forced-Gas Natual Air,
                             with On-Load Tap Changer
                             GNAN/GFAN

                             H.V.   64.5kV +10/-10%   Star
                             L.V.    6.6kV            Delta



For underground substation
  beneath office building
A VERY BRIEF HISTORY:

PRESSURE RELIEF DEVICES
(PRDs) AND THEIR USE ON
POWER AND DISTRIBUTION
TRANSFORMERS


          Transformer Tank Rupture and
         Mitigation - March 9, 2010 J.Herz,
                       Qualitrol
BEFORE THERE WERE RE-SEALABLE PRDs…
Rupture Discs

  GOOSENECK CAN ADD TO BACK PRESSURE
  HAD TO BE REPLACED AFTER OPERATION - LEFT
  THE TRANSFORMER OPEN TO ATMOSPHERIC
  MOISTURE IN THE INTERIM
  TYPICALLY WITH NO ALARM

                  More Recently
  THEY HAVE BEEN USED IN MULTIPLE SETS ALONG
  THE TOP AND BOTTOM OF A SINGLE TRANSFORMER
  TO MAXIMIZE THE PRESSURE RELIEF AREA AND TO
  BE LOCATED AS CLOSE AS POSSIBLE TO ANY
  POTENTIAL FAULT LOCATION.
  THEY ARE THE RELIEF MECHANISM FOR
  COMBINATION PRESSURE RELIEF/FIRE
  SUPPRESSION SYSTEMS
THERE WERE SEVERAL DIFFERENT
DESIGN APPROACHES TO RE-SEALING
PRDs MADE BY VARIOUS
MANUFACTURERS

IN THE LATE 1950’s THE INDUSTRY
SETTLED OVERWHELMINGLY ON ONE
DESIGN.
THE DESIGN IS STILL IN FREQUENT
USE TODAY. IT OFFERS SIMPLICITY
AND DURABILITY IN ADDITION TO
RE-SEALABILITY.

REFINEMENTS SINCE HAVE TO DO
WITH IMPROVING THE SEAL,
SHIELDING AND PROTECTION,
SWITCH CAPACITY, CORROSION
RESISTANCE, ETC
WITH OPERATING PRESSURE
WHEN OPERATING PRESSURE   ACTING ON THE LARGER AREA
IS REACHED, TOP SEAL      CIRCUMSCRIBED BY THE SIDE
OPENS WHILE SIDE SEAL     SEAL, THE SPRING IS RAPIDLY
REMAINS BRIEFLY CLOSED    COMPRESSED AND THE VALVE
                          EXHAUSTS QUICKLY
8400 SCFM AT 50% OVERPRESSURE ON A 10 PSI PRD WAS
TYPICAL. NOW THERE ARE DEVICES WHICH GO TO 12,600 SCFM.
Most frequent question: Will it protect?

Most frequent answer is: Depends.


       • location of fault
       • magnitude of fault
       • duration of fault
TEST 1: 1958 AT GE SCHENECTADY


    The test tank was approximately 6 ft in diameter and 4 ft deep, with the
    PRD mounted in the center of the 6 ft. diameter cover.
    The gas space was 10 inches below the cover which resulted in about 700
    gallons of oil and 23 cu. ft. of gas (air).
    Ball nosed copper electrodes (2) were threaded with a small copper wire to
    trigger the arc, the highest of which was 25K amps and 20K volts. Oil,
    smoke, mist, spray blasted out of the relief device over a radius of about 40
    feet.

TEST 2: 1958 AT GE SCHENECTADY

   In tests performed by Jim Barr on a transformer with NO COVER , the fault
   was introduced near the bottom of the tank and the bottom of the tank BLEW
   OUT, at 10K amps and 10K volts.
There are thousands of events where rupture
discs and re-sealable PRDs have successfully
protected transformers:

“Internal arcing, breaker insulation break
down, load tap changer problems, phase
angle regulator problems, and internal
winding problems” are some of the more
common.

                 Transformer Tank Rupture and
                Mitigation - March 9, 2010 J.Herz,
                              Qualitrol
CONCLUSIONS

TTR is a complex problem. The severity is a function of arc location, arc I and T
as well as oil volume and tank expansion characteristics.

It’s possible to reduce the risk of TTR by performing modifications to the tank.

PRDs help to protect the tank against low energy internal arcing faults.

Fluids with high fire point will reduce the consequences of a tank rupture;
however it is not yet proven if these fluids will prevent tank rupture.

GITs will eliminate the risk of tank rupture.

Improved electrical protection and electrical system design can also help
prevent TTR.

The IEEE currently has no standards that provide guidance on TTR mitigation.
IEEE TRANSACTIONS ON POWER DELIVERY
Volume: 24 Issue: 4 Date: Oct. 2009
Page(s): 1959 - 1967


       Power Transformer Tank Rupture and Mitigation
  - A Summary of Current State of Practice and Knowledge
by the Task Force of IEEE Power Transformer Subcommittee
Nick Abi-Samra, Javier Arteaga, Bill Darovny, Marc Foata, Joshua Herz, Terence Lee, Van Nhi Nguyen,
   Guillaume Perigaud, Craig Swinderman, Robert Thompson, Ge (Jim) Zhang, and Peter D. Zhao
Action Next –
Planning to Generate an IEEE Std
   You are all welcome to join
S10 tr-tank rupturetutorial

More Related Content

What's hot

National electrical code.pptx
National electrical code.pptxNational electrical code.pptx
National electrical code.pptxssuser74ea7e
 
CoordinacióN De La Aislacion
CoordinacióN De La AislacionCoordinacióN De La Aislacion
CoordinacióN De La Aislacionacehernan
 
Cable sizing to withstand short circuit current
Cable sizing to withstand short circuit currentCable sizing to withstand short circuit current
Cable sizing to withstand short circuit currentLeonardo ENERGY
 
KUBOTA D1005-E3B DIESEL ENGINE Service Repair Manual
KUBOTA D1005-E3B DIESEL ENGINE Service Repair ManualKUBOTA D1005-E3B DIESEL ENGINE Service Repair Manual
KUBOTA D1005-E3B DIESEL ENGINE Service Repair Manualjksemndmm
 
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...Thorne & Derrick International
 
Manual de practicas_de_electronica_de_potencia
Manual de practicas_de_electronica_de_potenciaManual de practicas_de_electronica_de_potencia
Manual de practicas_de_electronica_de_potenciajvasquez213
 
2011 ARCTIC CAT 550 ATV Service Repair Manual
2011 ARCTIC CAT 550 ATV Service Repair Manual2011 ARCTIC CAT 550 ATV Service Repair Manual
2011 ARCTIC CAT 550 ATV Service Repair Manualjkjskemm rtert
 
Heat Shrink Cable Joints & Cable Terminations LV HV, 6.6kV 11kV 33kV - SPS Ca...
Heat Shrink Cable Joints & Cable Terminations LV HV, 6.6kV 11kV 33kV - SPS Ca...Heat Shrink Cable Joints & Cable Terminations LV HV, 6.6kV 11kV 33kV - SPS Ca...
Heat Shrink Cable Joints & Cable Terminations LV HV, 6.6kV 11kV 33kV - SPS Ca...Thorne & Derrick International
 
Caterpillar cat 930 k wheel loader (prefix frk) service repair manual (frk000...
Caterpillar cat 930 k wheel loader (prefix frk) service repair manual (frk000...Caterpillar cat 930 k wheel loader (prefix frk) service repair manual (frk000...
Caterpillar cat 930 k wheel loader (prefix frk) service repair manual (frk000...ufjjjskkemmd
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission lineFazlur Rahman
 
Cable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - ExampleCable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - ExampleLeonardo ENERGY
 
Megger Electrical Testing Instruments - Cable Fault Locators, High Voltage De...
Megger Electrical Testing Instruments - Cable Fault Locators, High Voltage De...Megger Electrical Testing Instruments - Cable Fault Locators, High Voltage De...
Megger Electrical Testing Instruments - Cable Fault Locators, High Voltage De...Thorne & Derrick International
 
CATERPILLAR CAT DP40K FORKLIFT LIFT TRUCKS CHASSIS AND MAST Service Repair Ma...
CATERPILLAR CAT DP40K FORKLIFT LIFT TRUCKS CHASSIS AND MAST Service Repair Ma...CATERPILLAR CAT DP40K FORKLIFT LIFT TRUCKS CHASSIS AND MAST Service Repair Ma...
CATERPILLAR CAT DP40K FORKLIFT LIFT TRUCKS CHASSIS AND MAST Service Repair Ma...jknsekmdmd
 
Generator protection calculations settings
Generator protection calculations settingsGenerator protection calculations settings
Generator protection calculations settingsmichaeljmack
 
2. Heat Shrink Cable Termination (HV) - 11kV 33kV Single Core XLPE BS6622 Cables
2. Heat Shrink Cable Termination (HV) - 11kV 33kV Single Core XLPE BS6622 Cables2. Heat Shrink Cable Termination (HV) - 11kV 33kV Single Core XLPE BS6622 Cables
2. Heat Shrink Cable Termination (HV) - 11kV 33kV Single Core XLPE BS6622 CablesThorne & Derrick International
 
Distribution Transformer Design (Electrical Machine Design)
Distribution Transformer Design (Electrical Machine Design)Distribution Transformer Design (Electrical Machine Design)
Distribution Transformer Design (Electrical Machine Design)Md. Rayid Hasan Mojumder
 

What's hot (20)

National electrical code.pptx
National electrical code.pptxNational electrical code.pptx
National electrical code.pptx
 
CoordinacióN De La Aislacion
CoordinacióN De La AislacionCoordinacióN De La Aislacion
CoordinacióN De La Aislacion
 
Cable sizing to withstand short circuit current
Cable sizing to withstand short circuit currentCable sizing to withstand short circuit current
Cable sizing to withstand short circuit current
 
KUBOTA D1005-E3B DIESEL ENGINE Service Repair Manual
KUBOTA D1005-E3B DIESEL ENGINE Service Repair ManualKUBOTA D1005-E3B DIESEL ENGINE Service Repair Manual
KUBOTA D1005-E3B DIESEL ENGINE Service Repair Manual
 
Electrical safety
Electrical safetyElectrical safety
Electrical safety
 
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
 
Manual de practicas_de_electronica_de_potencia
Manual de practicas_de_electronica_de_potenciaManual de practicas_de_electronica_de_potencia
Manual de practicas_de_electronica_de_potencia
 
Joints and terminations
Joints and terminationsJoints and terminations
Joints and terminations
 
Rebobinado de un motor eléctrico
Rebobinado de un motor eléctricoRebobinado de un motor eléctrico
Rebobinado de un motor eléctrico
 
2011 ARCTIC CAT 550 ATV Service Repair Manual
2011 ARCTIC CAT 550 ATV Service Repair Manual2011 ARCTIC CAT 550 ATV Service Repair Manual
2011 ARCTIC CAT 550 ATV Service Repair Manual
 
Heat Shrink Cable Joints & Cable Terminations LV HV, 6.6kV 11kV 33kV - SPS Ca...
Heat Shrink Cable Joints & Cable Terminations LV HV, 6.6kV 11kV 33kV - SPS Ca...Heat Shrink Cable Joints & Cable Terminations LV HV, 6.6kV 11kV 33kV - SPS Ca...
Heat Shrink Cable Joints & Cable Terminations LV HV, 6.6kV 11kV 33kV - SPS Ca...
 
Caterpillar cat 930 k wheel loader (prefix frk) service repair manual (frk000...
Caterpillar cat 930 k wheel loader (prefix frk) service repair manual (frk000...Caterpillar cat 930 k wheel loader (prefix frk) service repair manual (frk000...
Caterpillar cat 930 k wheel loader (prefix frk) service repair manual (frk000...
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission line
 
Cable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - ExampleCable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - Example
 
Megger Electrical Testing Instruments - Cable Fault Locators, High Voltage De...
Megger Electrical Testing Instruments - Cable Fault Locators, High Voltage De...Megger Electrical Testing Instruments - Cable Fault Locators, High Voltage De...
Megger Electrical Testing Instruments - Cable Fault Locators, High Voltage De...
 
CATERPILLAR CAT DP40K FORKLIFT LIFT TRUCKS CHASSIS AND MAST Service Repair Ma...
CATERPILLAR CAT DP40K FORKLIFT LIFT TRUCKS CHASSIS AND MAST Service Repair Ma...CATERPILLAR CAT DP40K FORKLIFT LIFT TRUCKS CHASSIS AND MAST Service Repair Ma...
CATERPILLAR CAT DP40K FORKLIFT LIFT TRUCKS CHASSIS AND MAST Service Repair Ma...
 
Generator protection calculations settings
Generator protection calculations settingsGenerator protection calculations settings
Generator protection calculations settings
 
2. Heat Shrink Cable Termination (HV) - 11kV 33kV Single Core XLPE BS6622 Cables
2. Heat Shrink Cable Termination (HV) - 11kV 33kV Single Core XLPE BS6622 Cables2. Heat Shrink Cable Termination (HV) - 11kV 33kV Single Core XLPE BS6622 Cables
2. Heat Shrink Cable Termination (HV) - 11kV 33kV Single Core XLPE BS6622 Cables
 
MITSUBISHI ELECTRIC SPLIT-TYPE
MITSUBISHI ELECTRIC SPLIT-TYPEMITSUBISHI ELECTRIC SPLIT-TYPE
MITSUBISHI ELECTRIC SPLIT-TYPE
 
Distribution Transformer Design (Electrical Machine Design)
Distribution Transformer Design (Electrical Machine Design)Distribution Transformer Design (Electrical Machine Design)
Distribution Transformer Design (Electrical Machine Design)
 

Similar to S10 tr-tank rupturetutorial

SPICE MODEL of RN1902AFS in SPICE PARK
SPICE MODEL of RN1902AFS in SPICE PARKSPICE MODEL of RN1902AFS in SPICE PARK
SPICE MODEL of RN1902AFS in SPICE PARKTsuyoshi Horigome
 
Original Opto PC816 EL816 LTV816 LTV-816 816C 816 DIP-4 New
Original Opto PC816 EL816 LTV816 LTV-816 816C 816 DIP-4 NewOriginal Opto PC816 EL816 LTV816 LTV-816 816C 816 DIP-4 New
Original Opto PC816 EL816 LTV816 LTV-816 816C 816 DIP-4 NewAUTHELECTRONIC
 
SPICE MODEL of GT10Q301 (Professional+FWD+SP PSpice Model) in SPICE PARK
SPICE MODEL of GT10Q301 (Professional+FWD+SP PSpice Model) in SPICE PARKSPICE MODEL of GT10Q301 (Professional+FWD+SP PSpice Model) in SPICE PARK
SPICE MODEL of GT10Q301 (Professional+FWD+SP PSpice Model) in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of GT10Q301 (Professional+FWDS PSpice Model) in SPICE PARK
SPICE MODEL of GT10Q301 (Professional+FWDS PSpice Model) in SPICE PARKSPICE MODEL of GT10Q301 (Professional+FWDS PSpice Model) in SPICE PARK
SPICE MODEL of GT10Q301 (Professional+FWDS PSpice Model) in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of RN1966FS in SPICE PARK
SPICE MODEL of RN1966FS in SPICE PARKSPICE MODEL of RN1966FS in SPICE PARK
SPICE MODEL of RN1966FS in SPICE PARKTsuyoshi Horigome
 
lightning_studies_20160908 (1).pdf
lightning_studies_20160908 (1).pdflightning_studies_20160908 (1).pdf
lightning_studies_20160908 (1).pdffarhan118934
 
SPICE MODEL of RN1963FS in SPICE PARK
SPICE MODEL of RN1963FS in SPICE PARKSPICE MODEL of RN1963FS in SPICE PARK
SPICE MODEL of RN1963FS in SPICE PARKTsuyoshi Horigome
 
Original Opto LTV-354T LTV354T 354T 354 SOP-4 New
Original Opto LTV-354T LTV354T 354T 354 SOP-4 NewOriginal Opto LTV-354T LTV354T 354T 354 SOP-4 New
Original Opto LTV-354T LTV354T 354T 354 SOP-4 NewAUTHELECTRONIC
 
SPICE MODEL of SSM3J314T (Standard+BDS Model) in SPICE PARK
SPICE MODEL of SSM3J314T (Standard+BDS Model) in SPICE PARKSPICE MODEL of SSM3J314T (Standard+BDS Model) in SPICE PARK
SPICE MODEL of SSM3J314T (Standard+BDS Model) in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of SF10LC40 (Standard Model) in SPICE PARK
SPICE MODEL of SF10LC40 (Standard Model) in SPICE PARKSPICE MODEL of SF10LC40 (Standard Model) in SPICE PARK
SPICE MODEL of SF10LC40 (Standard Model) in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of RN1964FS in SPICE PARK
SPICE MODEL of RN1964FS in SPICE PARKSPICE MODEL of RN1964FS in SPICE PARK
SPICE MODEL of RN1964FS in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of RN1905AFS in SPICE PARK
SPICE MODEL of RN1905AFS in SPICE PARKSPICE MODEL of RN1905AFS in SPICE PARK
SPICE MODEL of RN1905AFS in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of RN1906AFS in SPICE PARK
SPICE MODEL of RN1906AFS in SPICE PARKSPICE MODEL of RN1906AFS in SPICE PARK
SPICE MODEL of RN1906AFS in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of RN1903AFS in SPICE PARK
SPICE MODEL of RN1903AFS in SPICE PARKSPICE MODEL of RN1903AFS in SPICE PARK
SPICE MODEL of RN1903AFS in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of RN1904AFS in SPICE PARK
SPICE MODEL of RN1904AFS in SPICE PARKSPICE MODEL of RN1904AFS in SPICE PARK
SPICE MODEL of RN1904AFS in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of RN1961FS in SPICE PARK
SPICE MODEL of RN1961FS in SPICE PARKSPICE MODEL of RN1961FS in SPICE PARK
SPICE MODEL of RN1961FS in SPICE PARKTsuyoshi Horigome
 
Origimal Transistor PNP 2SB649AC B649AC B649 TO-126 120V 1.5A New UNISONIC TE...
Origimal Transistor PNP 2SB649AC B649AC B649 TO-126 120V 1.5A New UNISONIC TE...Origimal Transistor PNP 2SB649AC B649AC B649 TO-126 120V 1.5A New UNISONIC TE...
Origimal Transistor PNP 2SB649AC B649AC B649 TO-126 120V 1.5A New UNISONIC TE...AUTHELECTRONIC
 

Similar to S10 tr-tank rupturetutorial (20)

SPICE MODEL of RN1902AFS in SPICE PARK
SPICE MODEL of RN1902AFS in SPICE PARKSPICE MODEL of RN1902AFS in SPICE PARK
SPICE MODEL of RN1902AFS in SPICE PARK
 
Original Opto PC816 EL816 LTV816 LTV-816 816C 816 DIP-4 New
Original Opto PC816 EL816 LTV816 LTV-816 816C 816 DIP-4 NewOriginal Opto PC816 EL816 LTV816 LTV-816 816C 816 DIP-4 New
Original Opto PC816 EL816 LTV816 LTV-816 816C 816 DIP-4 New
 
SPICE MODEL of GT10Q301 (Professional+FWD+SP PSpice Model) in SPICE PARK
SPICE MODEL of GT10Q301 (Professional+FWD+SP PSpice Model) in SPICE PARKSPICE MODEL of GT10Q301 (Professional+FWD+SP PSpice Model) in SPICE PARK
SPICE MODEL of GT10Q301 (Professional+FWD+SP PSpice Model) in SPICE PARK
 
Day 3
Day 3Day 3
Day 3
 
SPICE MODEL of GT10Q301 (Professional+FWDS PSpice Model) in SPICE PARK
SPICE MODEL of GT10Q301 (Professional+FWDS PSpice Model) in SPICE PARKSPICE MODEL of GT10Q301 (Professional+FWDS PSpice Model) in SPICE PARK
SPICE MODEL of GT10Q301 (Professional+FWDS PSpice Model) in SPICE PARK
 
SPICE MODEL of RN1966FS in SPICE PARK
SPICE MODEL of RN1966FS in SPICE PARKSPICE MODEL of RN1966FS in SPICE PARK
SPICE MODEL of RN1966FS in SPICE PARK
 
lightning_studies_20160908 (1).pdf
lightning_studies_20160908 (1).pdflightning_studies_20160908 (1).pdf
lightning_studies_20160908 (1).pdf
 
SPICE MODEL of RN1963FS in SPICE PARK
SPICE MODEL of RN1963FS in SPICE PARKSPICE MODEL of RN1963FS in SPICE PARK
SPICE MODEL of RN1963FS in SPICE PARK
 
Original Opto LTV-354T LTV354T 354T 354 SOP-4 New
Original Opto LTV-354T LTV354T 354T 354 SOP-4 NewOriginal Opto LTV-354T LTV354T 354T 354 SOP-4 New
Original Opto LTV-354T LTV354T 354T 354 SOP-4 New
 
SPICE MODEL of SSM3J314T (Standard+BDS Model) in SPICE PARK
SPICE MODEL of SSM3J314T (Standard+BDS Model) in SPICE PARKSPICE MODEL of SSM3J314T (Standard+BDS Model) in SPICE PARK
SPICE MODEL of SSM3J314T (Standard+BDS Model) in SPICE PARK
 
SPICE MODEL of SF10LC40 (Standard Model) in SPICE PARK
SPICE MODEL of SF10LC40 (Standard Model) in SPICE PARKSPICE MODEL of SF10LC40 (Standard Model) in SPICE PARK
SPICE MODEL of SF10LC40 (Standard Model) in SPICE PARK
 
SPICE MODEL of RN1964FS in SPICE PARK
SPICE MODEL of RN1964FS in SPICE PARKSPICE MODEL of RN1964FS in SPICE PARK
SPICE MODEL of RN1964FS in SPICE PARK
 
SPICE MODEL of RN1905AFS in SPICE PARK
SPICE MODEL of RN1905AFS in SPICE PARKSPICE MODEL of RN1905AFS in SPICE PARK
SPICE MODEL of RN1905AFS in SPICE PARK
 
SPICE MODEL of RN1906AFS in SPICE PARK
SPICE MODEL of RN1906AFS in SPICE PARKSPICE MODEL of RN1906AFS in SPICE PARK
SPICE MODEL of RN1906AFS in SPICE PARK
 
SPICE MODEL of RN1903AFS in SPICE PARK
SPICE MODEL of RN1903AFS in SPICE PARKSPICE MODEL of RN1903AFS in SPICE PARK
SPICE MODEL of RN1903AFS in SPICE PARK
 
IGBT Modeling in Simplorer
IGBT Modeling in SimplorerIGBT Modeling in Simplorer
IGBT Modeling in Simplorer
 
SPICE MODEL of RN1904AFS in SPICE PARK
SPICE MODEL of RN1904AFS in SPICE PARKSPICE MODEL of RN1904AFS in SPICE PARK
SPICE MODEL of RN1904AFS in SPICE PARK
 
SPICE MODEL of RN1961FS in SPICE PARK
SPICE MODEL of RN1961FS in SPICE PARKSPICE MODEL of RN1961FS in SPICE PARK
SPICE MODEL of RN1961FS in SPICE PARK
 
Origimal Transistor PNP 2SB649AC B649AC B649 TO-126 120V 1.5A New UNISONIC TE...
Origimal Transistor PNP 2SB649AC B649AC B649 TO-126 120V 1.5A New UNISONIC TE...Origimal Transistor PNP 2SB649AC B649AC B649 TO-126 120V 1.5A New UNISONIC TE...
Origimal Transistor PNP 2SB649AC B649AC B649 TO-126 120V 1.5A New UNISONIC TE...
 
Electricmotors6
Electricmotors6Electricmotors6
Electricmotors6
 

Recently uploaded

Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 

Recently uploaded (20)

Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 

S10 tr-tank rupturetutorial

  • 1. Investigation Report Power Transformer Tank Rupture and Mitigation - Current State of Practice and Knowledge by the Task Force of IEEE Power Transformer Subcommittee March 09, 2010 Houston, TX.
  • 2. CONTENT 1.Investigation and Analysis -10 minutes 2.Utility Experience (15 minutes) 3.Manufacturer’s Perspective (25 minutes) 4.PRD (10 minutes) 5.Conclusions (10 minutes ) 6.Q&A (5 minutes)
  • 3. Analysis of Transformer Tank Ruptures Electric Power Research Institute Wayne Johnson wejohnson@epri.com Nick Abi-Samra nabisamra@epri.com
  • 4. Survey On Transformer Rupture Objectives • Develop an understanding of the tank rupture process associated with internal faults. • Develop tools, and methods, for evaluating the influence of tank designs on rupture characteristics 2
  • 5. Background • 42 transformer failures (tanks ruptured or deformed without rupture) • 22 utilities • 10-year period (1980-1990) • 7 transformer manufacturers • Different voltage levels • Different designs: (GSU’s, Auto, Phase Shifters, etc.) 3
  • 6. Conclusions • The arc energy is the critical rupture parameter • Differences in transformer design and application are not major discriminators in the tank rupture • The fault energy capacity of a tank can be increased by increasing the tank rupture pressure limit and tank flexibility. – The pressure at which tanks rupture can be increased by local strengthening of weak points, while the tank flexibility can be increased by replacing large beams with a number of smaller beams (which permit greater deflection at a given stress level). • Venting to conservators or to auxiliary tanks was not found to be effective for heavy faults (those with arc power greater than 300 MW) 4
  • 7. Conclusions • A long arcing time is not necessary for rupture: – About 75% of the cases occurred with arcing times less than 4.5 cycles. • Since arc energy is proportional to I2t, where the t is duration in seconds, the parameter which offers the most opportunity for control of the risk of rupture is the magnitude of the current, and Graph of Tank Deformation Rupture as a function of fault specifically, the peak crest current and fault duration. value of the first half cycle of the fault current (and the associated X/R of the circuit). 5
  • 8. Power Transformer Tank Rupture A Utility's Experience Marc Foata IEEE Transformers Committee Houston, March 2010
  • 9. Presentation Assessment of the risk Statistics Arc energy Prevention of tank rupture Venting Containment Specification of a Tank pressure withstand requirement 2
  • 10. Assessing the risk - Statistics 3
  • 11. Assessing the risk - Statistics 4
  • 12. Assessing the risk - Statistics 5
  • 13. Arc energy - 4 MJ 6
  • 14. Arc Energy - 8 MJ 7
  • 15. Arc Energy - 12 MJ 8
  • 16. Arc Energy - 14 MJ 9
  • 17. Arc energy vs Damage 10
  • 18. Arc Energy - Calculation Earc = 0.9 V I t I – Arc current: Evaluated from short-circuit level T – Fault clearing time: Depends mainly on protection V – Arc voltage: Very difficult to evaluate 0.9 – Factor introduced for square waveform of V 11
  • 19. Arc Energy - Recordings A 100 Unité Support et analyses - DESTT E BN TT MAIS MICOUA 80 E BN L-7019 MICOUA 60 E BN L-7011 MICOUA E BN L-7027 MICOUA 40 20 (kV) 0 -20 -40 -60 -80 205 210 215 220 225 230 235 240 245 250 255 (ms rel. à 05:34:32.2870) 2008-09-12 05:34:32.499 MICOUA 735-02 TENSION RÉSIDUELLE DÉFAUT TRANSFO T8-B 12 11 10 9 8 (MJoules) 7 6 5 ÉNTERGIE TOTALE (TT MAIS) 4 ÉNTERGIE TOTALE (TTC 7019) 3 ÉNTERGIE TOTALE (TTC 7011) 2 ÉNTERGIE TOTALE (TTC 7027) 1 0 -1 205 210 215 220 225 230 235 240 245 250 255 (ms rel. à 05:34:32.2870) 2008-09-12 05:34:32.499 MICOUA 735-02 ESTIMÉ DE L'ÉNERGIE TOTALE DANS LE DÉFAUT TRANSFO T8-B 20000 15000 10000 5000 (A) 0 -5000 -10000 COURANTS CÔTÉ 735 kV -15000 COURANTS APROX. CÔTÉ 315 kV -20000 190 200 210 220 230 240 250 260 270 (ms rel. à 05:34:32.2870) 2008-09-12 05:34:32.499 MICOUA 735-02 COURANTS DE DÉFAUT TRANSFO T8-B Lundi 15 Septembre, 2008 12 VECTEURDONNEESPARTAGE@AUTOMATISMESCOMPORTEMENTRAPPORTRAPP_2008TOSC_ANA20080912_053432499_ENERGIE_T8-B_MICOUA.TOS
  • 20. Arc Energy - Evaluation of Arc Voltage 60-100 V/cm range is often referred For 40 kV, this means an arc length of more than 4 m !! 13
  • 21. Arc Energy - Pressure Effect V = 55L P Constant 55 V/cm L is arc length (m) P is absolute pressure (atm) Pressure in the gas bubble at arc ignition can reach extremely high values 14
  • 22. Prevention of tank rupture – Venting Simulations 15
  • 23. Prevention of tank rupture – Venting Simulations 16
  • 24. Prevention of tank rupture – Vented vs Non-vented Example 17
  • 25. Prevention of tank rupture – Conclusions on venting Pressure reduction from a single 25 cm aperture is low and becomes negligible when the arc is more than 1 meter away. An effective pressure venting strategy would require either a very large venting duct or numerous small apertures in the close vicinity of the arc. 18
  • 26. Prevention of tank rupture - Containment 19
  • 27. Prevention of tank rupture - Containment Present design can contain up to 10 MJ for the largest tanks (735 kV) More resistant tank design can be achieved Need to implement specifications with minimum energy requirement to meet. Energy requirement will be a compromise between the feasibility and the likelihood. 20
  • 28. New Specification - Philosophy Priority is given to the protection of the workers Worst energy levels may not always be containable by the tank First rupture point must be the cover Required calculation tools must be accessible to transformer designers Must take into account the highly dynamic phenomena involved Must be easily verified 21
  • 29. New specification - Formula ⎡ ⎤ Ps= F 1 kE ⎢100 + − 50⎥ ⎣ 4 100C ⎦ Ps – Calculated tank pressure withstand F – Dynamic (time & location) amplification E – Fault energy level to withstand K – Arc energy conversion factor C – Tank expansion coefficient 22
  • 30. New specifications – Dynamic factor 3 2,5 2 F 1,5 1 0 20 40 60 80 100 120 140 160 180 200 C/V (x 10 -5 kPa-1) Time related dynamic factor (pressure and deformation) Proximity related dynamic factor Takes into account tank volume 23
  • 31. New specification : Hydro-Québec's Energy Containment Requirements Voltage Class Arc Energy 24
  • 32. New specification - Implementation All transformer suppliers since 1992 have shown adequate tank withstand calculation capabilities. Since implementing energy level requirements (2006), manufacturers have been forced to improve their tank design. Detailed analysis by a number of manufacturers confirmed that all the specified energy requirements can be met. 25
  • 33. Transformer Tanks - Some Factors Related to Rupture A Manufacturers Perspective IEEE Transformers Committee Houston, March 9, 2010 by Bill Darovny, P.Eng. Siemens Canada
  • 34. Facts about Liquid Filled Transformer Tanks • C57.12.00 and C57.12.10 define the operating pressures for transformer tanks – full vacuum = -101.4 kPa (-14.7 psig) – pressure 25% above the normal operating pressure • Transformer tanks are not pressure vessels – are not required to be designed to the ASME Boiler and Pressure Vessel Code. • ASME code is mandatory when operating pressure exceeds 2 atmospheres (203 kPa).
  • 35. Facts about Liquid Filled Transformer Tanks • C57.12.10 requires a pressure relief device to be mounted on the tank cover – Typically activate at 34.5 to 69 kPa (5 to 10 psig) • Most rectangular tanks will sustain internal pressures of 140 to 210 kPa (20 to 30 psig) before rupture • A tank on its own cannot be made strong enough to resist all magnitudes of internal pressure
  • 36. Transformers have been saved from rupture by common protection devices • Pressure Relief Devices • Gas Detector Relays • Rapid Pressure Rise Relays • Real time Gas Monitors Provided the alarm signals are quickly recognized and the transformer is de-energized
  • 38. Not Every Tank Rupture Results in a Fire Unit gassing, GDR alarmed, long delay in response to alarm, ambient -30°C, reaction force to rupture shifted unit on the pad.
  • 39. Some Units Burn After Tank Rupture- 750 MVA 500kV
  • 41. The Location Where a Tank will Rupture is a Function of: 1. the rate of change of the pressure increase Slow rate: • Pressure has time to distribute throughout the tank Fast rate: • Results in a pressure build-up at the source 2. the co-ordinates of the pressure source inside the tank 3. the closest weak spot to those co-ordinates
  • 42. Slow Rate of Pressure Increase - Failed at 2 locations on the Cover - Tensile end reactions tore the welds at the ends of the stiffeners - Cover end angle rotated and the weld to tank flange cracked
  • 43. Moderate Rate of Pressure Increase • Tank failed at the cover joint • Some stiffeners on the tank wall were permanently deformed • There were no cracks in the oil containment welds in the tank body
  • 44. Rapid Rate of Pressure Increase • Co-ordinates of pressure source was about 1/3 tank height • Wall plate fracture started at the corner welds and ran almost full height of the tank • Tank wall to bottom weld joint also failed
  • 45. Rapid Rate of Pressure Increase • Cover weld did not fail • Tank failed at the high stress points in welds at the tank corners and wall penetrations then propagated through the wall plates • Unit was returned to the factory and rebuilt
  • 46. Weakest Points of a Rectangular Tank • Main cover to tank wall flange - weld joint • Tank wall corners - weld joint • Tank wall to base plate - weld joint • High stress points at throats and large penetrations through the tank plates • High stress points at ends of stiffeners where the end reaction force is transmitted to the tank plate
  • 47. Main Cover to Tank Wall Flange Mode of Weld Failure Typical Cover Welded Joint Upward and outward forces due to internal pressures Stress is concentrated at the weakest point - the root of the weld. Weld crack progresses outward from the root
  • 48. Typical Rectangular Tank Corner Joints Stresses are on the face of the weld. The face of the weld is stronger than the root of the weld. Adding corner gussets will reinforce this joint
  • 49. Cylindrical Tanks are Inherently Stronger than Rectangular Tanks • 110MVAR 735 kV shunt reactor • The tank wall is stressed in hoop tension • Typically the cylinder walls can sustain pressures > 350 kPa (50 psig) • Weakest point is the cover weld
  • 50. Design to Help Reduce Tank Rupture • Design in service systems to detect faults early & de-energize quickly • Use detection & relief accessories – Real time gas monitors – Gas detector relays - ensure gas collection system / piping functions as intended – Rapid pressure relays – Pressure relief devices • To be effective, relief devices must be located close to the pressure source • Standard size relief devices may not prevent all tank ruptures
  • 51. Design to Help Reduce Tank Rupture • The best location for a tank to fail is at the welded cover joint as this will minimize fluid loss • Strengthen the tank below the cover joint – Reinforce tank corners and wall to bottom joints with plates / gussets – Distribute stiffener end reaction forces with reinforcements or by connecting to stiffeners on adjacent walls – Reinforce around wall penetrations to reduce the high stress points
  • 52. Transformer Tank Rupture and Mitigation Tutorial March 9, 2010 Mitigation Research and Example Techniques Presented by Craig Swinderman Mitsubishi Electric Power Products, Inc.
  • 53. Research on Transformer Tank Rupture Mitigation • Joint research performed in the mid-1980’s by three large Electric Utilities in Japan, Tokyo University, and several transformer manufacturers. • Goal was to study ways of reducing the risk of transformer tank explosion in urban substations/ underground substations. • Full scale model testing performed. • Arc energies calculated and gas generation rate observed. • Pressure rise models developed. • Tank construction countermeasures developed.
  • 54. Summary of Research Tank Explosion Study Process for Internal Fault Verification Process Tests Estimation of Fault Condition Internal Fault Arc Test in Oil Tank ① Arc Current ② Arc Voltage ③ Time Dissolved Gas Generation ④ Dissolved Gas Generation Volume Internal Pressure Pressure Rise Analysis Pressure Rise Test Increase Dynamic Analysis considering Oil Motion using Full Scale Tx Internal Pressure Comparison between Internal Pressure and Tank Strength > Tank Strength Countermeasure Tank ① Tank Strength Improvement ② Protection Relay Improvement Explosion ③ System Improvement ④ Pressure Restrained Structure
  • 55. Dynamics of Internal Fault (1) 10000 Arc Test in Oil Tank Arc Test in Oil Tank Arc Voltage (V) 1000 Electrode 100 Arc 10 100 1000 Arc Length (mm) Oil Gas Volume 1 Gas Volume (m3) Arc Current : 1.3 to 40.9 kA Time : 3Cycle (0.05sec) 0.1 Arc Energy : 0.11 to 2.64 MJ Gap Length : 100 to 300 mm *Reference – T. KAWAMURA, M. UEDA, K. ANDO, Y. MAEDA, Y. ABIRU, M. WATANABE, K. MORITSU “Prevention of Tank Rupture Due to Internal Fault of Oil Filled Transformers”, 0.01 CIGRE, 12-02, 1988. 0.1 1 10 Arc Energy (MJ)
  • 56. Dynamics of Internal Fault (2) Pressure Rise Test using Full Scale model for verifying pressure rise Pressure Rise Test using Full Scale model for verifying pressure rise - Pressure rise at internal fault can be simulated by powder combustion, considering nozzle area of container and powder amount. - Dead space (steel tank) was set for simulating internal parts(Core,Coil).in the tested tank. Measured Results Transformer : 275kV 300MVA Analytical Results Arc Energy : 142,000kW、 Time : 80msec Pressure (Single Line-Ground Fault at Upper Tank) Upper Tank Time Combustion Container Φ300,L570 Middle Tank Pressure Upper Tank Gas Outlet (Φ12*72) Time Lower Tank Pressure Time Middle Tank *Reference – T. KAWAMURA, M. UEDA, K. ANDO, Y. MAEDA, Y. Lower Tank Cartridge increment ABIRU, M. WATANABE, K. MORITSU “Prevention of Tank (Max.7500g) Rupture Due to Internal Fault of Oil Filled Transformers”, CIGRE, 12-02, 1988.
  • 57. Results of Analysis • Decomposed gas generation calculated to be around 0.5L/kW sec for larger 275 kV class transformers at HV lead.* • Dynamic oscillation of fault pressure wave (kinetic energy) has a considerable influence on the pressure rise. (Dynamic Load Factor approx. 1.3 was recommended)* • Tank expansion characteristics and tank strength are important in determining the transformer’s capability to resist rupture. • Reinforcements can be made at the joining flange between the tank and cover (or flange between upper and lower tank for shell-form) to significantly improve the tank strength against rupture. *Reference – T. KAWAMURA, M. UEDA, K. ANDO, Y. MAEDA, Y. ABIRU, M. WATANABE, K. MORITSU “Prevention of Tank Rupture Due to Internal Fault of Oil Filled Transformers”, CIGRE, 12-02, 1988.
  • 58. Example of Tank Strength Improvement Conventional Type Improved Type Connecting Part Alleviation of Stress Improvement of Connecting Part Concentration Strength by Tie Reinforcement
  • 59. Pressure Reducing Space • Diaphragm type Conservator Tanks can be used as effective pressure reducing space if the connection duct to the main tank is short, the cross sectional area of the duct is large (approx. 1.4 m dia.), and the air space in the conservator diaphragm is adequate Diaphragm (bladder) Conservator Tank Connection duct Transformer main tank •Tests on 300 MVA, 230 kV units have verified ability to withstand 15,000 MVA short circuit capacity without rupture of the tank. •Still requires operation of protective relays and circuit breakers to clear fault within approx. 60 - 80 ms.
  • 60. Gas Insulated Power Transformers •Use SF6 Gas as the insulating and cooling medium instead of insulating oil. •First units produced in 1967. •Several thousand units of various sizes now in service worldwide, several manufacturers. •Transformer applications: From Distribution class units up to 400 MVA, 345 kV ratings. •Primarily used in substations located in urban areas (including inside buildings, underground) due to safety benefits.
  • 61. Features of Gas Insulated Transformers • Use SF6 Gas as insulating and cooling medium, instead of oil. • Typically use special internal insulation materials such as plastics, special paper, and pressboard. • SF6 has excellent dielectric properties, but not as good for heat transfer.
  • 62. Benefit of Gas Insulated Transformers SF6 Gas Insulation: non-flammable, compressible gas Pressure rise during an internal fault is slower than oil-immersed (non- compressible fluid), thus SF6 gas reduces the chances of tank explosion Pressure Rise (%) 100 100 Tank Strength 80 80 60 Oil-Immersed 60 Transformer 40 40 Gas Insulated 20 20 Transformer 00 00 0. 22 0. 0. 44 0. 0. 66 0. 0. 88 0. 11 Fault Time (sec)
  • 63. Application Example 15MVA, Three phase, 50Hz, Continuous Rating, Core-Form, Forced-Gas Natual Air, with On-Load Tap Changer GNAN/GFAN H.V. 64.5kV +10/-10% Star L.V. 6.6kV Delta For underground substation beneath office building
  • 64. A VERY BRIEF HISTORY: PRESSURE RELIEF DEVICES (PRDs) AND THEIR USE ON POWER AND DISTRIBUTION TRANSFORMERS Transformer Tank Rupture and Mitigation - March 9, 2010 J.Herz, Qualitrol
  • 65. BEFORE THERE WERE RE-SEALABLE PRDs…
  • 66. Rupture Discs GOOSENECK CAN ADD TO BACK PRESSURE HAD TO BE REPLACED AFTER OPERATION - LEFT THE TRANSFORMER OPEN TO ATMOSPHERIC MOISTURE IN THE INTERIM TYPICALLY WITH NO ALARM More Recently THEY HAVE BEEN USED IN MULTIPLE SETS ALONG THE TOP AND BOTTOM OF A SINGLE TRANSFORMER TO MAXIMIZE THE PRESSURE RELIEF AREA AND TO BE LOCATED AS CLOSE AS POSSIBLE TO ANY POTENTIAL FAULT LOCATION. THEY ARE THE RELIEF MECHANISM FOR COMBINATION PRESSURE RELIEF/FIRE SUPPRESSION SYSTEMS
  • 67. THERE WERE SEVERAL DIFFERENT DESIGN APPROACHES TO RE-SEALING PRDs MADE BY VARIOUS MANUFACTURERS IN THE LATE 1950’s THE INDUSTRY SETTLED OVERWHELMINGLY ON ONE DESIGN.
  • 68. THE DESIGN IS STILL IN FREQUENT USE TODAY. IT OFFERS SIMPLICITY AND DURABILITY IN ADDITION TO RE-SEALABILITY. REFINEMENTS SINCE HAVE TO DO WITH IMPROVING THE SEAL, SHIELDING AND PROTECTION, SWITCH CAPACITY, CORROSION RESISTANCE, ETC
  • 69. WITH OPERATING PRESSURE WHEN OPERATING PRESSURE ACTING ON THE LARGER AREA IS REACHED, TOP SEAL CIRCUMSCRIBED BY THE SIDE OPENS WHILE SIDE SEAL SEAL, THE SPRING IS RAPIDLY REMAINS BRIEFLY CLOSED COMPRESSED AND THE VALVE EXHAUSTS QUICKLY
  • 70.
  • 71. 8400 SCFM AT 50% OVERPRESSURE ON A 10 PSI PRD WAS TYPICAL. NOW THERE ARE DEVICES WHICH GO TO 12,600 SCFM.
  • 72.
  • 73. Most frequent question: Will it protect? Most frequent answer is: Depends. • location of fault • magnitude of fault • duration of fault
  • 74. TEST 1: 1958 AT GE SCHENECTADY The test tank was approximately 6 ft in diameter and 4 ft deep, with the PRD mounted in the center of the 6 ft. diameter cover. The gas space was 10 inches below the cover which resulted in about 700 gallons of oil and 23 cu. ft. of gas (air). Ball nosed copper electrodes (2) were threaded with a small copper wire to trigger the arc, the highest of which was 25K amps and 20K volts. Oil, smoke, mist, spray blasted out of the relief device over a radius of about 40 feet. TEST 2: 1958 AT GE SCHENECTADY In tests performed by Jim Barr on a transformer with NO COVER , the fault was introduced near the bottom of the tank and the bottom of the tank BLEW OUT, at 10K amps and 10K volts.
  • 75. There are thousands of events where rupture discs and re-sealable PRDs have successfully protected transformers: “Internal arcing, breaker insulation break down, load tap changer problems, phase angle regulator problems, and internal winding problems” are some of the more common. Transformer Tank Rupture and Mitigation - March 9, 2010 J.Herz, Qualitrol
  • 76. CONCLUSIONS TTR is a complex problem. The severity is a function of arc location, arc I and T as well as oil volume and tank expansion characteristics. It’s possible to reduce the risk of TTR by performing modifications to the tank. PRDs help to protect the tank against low energy internal arcing faults. Fluids with high fire point will reduce the consequences of a tank rupture; however it is not yet proven if these fluids will prevent tank rupture. GITs will eliminate the risk of tank rupture. Improved electrical protection and electrical system design can also help prevent TTR. The IEEE currently has no standards that provide guidance on TTR mitigation.
  • 77. IEEE TRANSACTIONS ON POWER DELIVERY Volume: 24 Issue: 4 Date: Oct. 2009 Page(s): 1959 - 1967 Power Transformer Tank Rupture and Mitigation - A Summary of Current State of Practice and Knowledge by the Task Force of IEEE Power Transformer Subcommittee Nick Abi-Samra, Javier Arteaga, Bill Darovny, Marc Foata, Joshua Herz, Terence Lee, Van Nhi Nguyen, Guillaume Perigaud, Craig Swinderman, Robert Thompson, Ge (Jim) Zhang, and Peter D. Zhao
  • 78. Action Next – Planning to Generate an IEEE Std You are all welcome to join