SlideShare a Scribd company logo
1 of 67
Download to read offline
v
TABLE OF
CONTENTS
CHAPTER TITLE PAGE
NO NO.
iii
iv
viii
ix
1
ACKNOWLEDGEMENT
ABSTRACT
LIST OF TABLES
LIST OF FIGURES
INRODUCTION 1
1.1 INTRODUCTION 1
1.2 OBJECTIVE OF THE PROJECT 1
1.3 PROJECT SCOPE 1
1.4 ORGANIZATION OF PROJECT WORK 1
1.5 ORGANIZATION OF CHAPTERS 2
1.6 CONCLUSION 3
2 LITERATURE REVIEW 4
2.1 INTRODUCTION 4
2.2 MATERIAL HANDLING 4
2.3
MAJOR EQUIPMENTS IN MATERIAL
HANDLING 5
2.4 CONVEYOR SYSTEMS 6
2.4.1
Pneumatic systems for material
inspection 10
vi
2.5 CONCLUSION 11
3. DESIGN CALCULATIONS 12
3.1. INTRODUCTION 12
3.2. REQUIRED CALCULATIONS 12
3.3. CONCLUSION 22
4. ASSEMBLY AND PART DRAWINGS 23
4.1. INTRODUCTION 23
4.2. 2D DIAGRAM 23
4.3. PART DIAGRAMS 24
4.4. ASSEMBLY DRAWING 29
4.4 CONCLUSION 30
5. SYSTEM DESIGN 31
5.1. INTRODUCTION 31
5.2. MODEL OF THE SETUP 31
5.3. CONCLUSION 34
6. PROCESS SHEET 35
6.1. INTRODUCTION 35
6.2. COMPONENT SPECIFICATIONS 35
vii
6.2.1 Project Specification 35
6.2.2 Components of Pneumatic system 36
6.2.3 PLC Specification 38
6.2.4 Programming Logic Controller 39
6.3 PROCESS FLOW CHART 40
6.4 CONCLUSION 41
7 PLC PROGRAMMING 42
7.1 INTRODUCTION 42
7.2 PLC PROGRAMMING 42
7.3 LADDER LOGIC DIAGRAM 43
7.4 CONCLUSION 44
8 COST OF THE PROJECT 45
8.1 INTRODUCTION 45
8.2 COST TABLE 45
8.3 CONCLUSION 46
9 FABRICATION OF THE PROJECT 47
9.1 INTRODUCTION 47
9.2 FABRICATION PHOTOS 47
9.3 CONCLUSION 50
10 CONCLUSION 51
10.1 INTRODUCTION 51
10.2 CONCLUSION 51
REFERENCES 52
APPENDIX 54
viii
LIST OF TABLES
TABLE TITLE PAGE
NO. NO.
6.1 Component specification 35
6.2 PLC specification 38
8.1 Cost estimation 45
ix
LIST OF FIGURES
FIGURE TITLE PAGE NO.
NO.
1.1 2
3.1 17
3.2 18
3.3 20
4.2.1 23
4.3.1 24
4.3.2 25
4.3.3 26
4.3.4 27
4.3.4 28
4.4.1 29
4.5 30
5.2.1 31
5.2.2 32
6.1 40
7.3 44
9.2.1
Organization of chapters
Bending moment of beam 1
and 2
Bending moment of beams 3
and 4
Bending moment of beams 5
and 6
2D Diagram
Bearing
Pneumatic cylinder
Supporting Column
Roller
Conveyor belt
Assembly view
3D View
Circuit Diagram
Working model of PLC
Process flowchart
Ladder logic diagram
Conveyor model 47
9.2.2 Conveyor model 48
9.2.3 Conveyor model 49
9.2.4 Conveyor model 49
ACKNOWLEDGEMENT
At this juncture, we take the opportunity to convey our sincere thanks
and gratitude to the management of the college for providing all the facilities
to us.
ABSTRACT
In this project “Material Inspection and Sorting Conveyor", instead of
using manual inspection here we are introducing the automatic system by
using the pneumatic comparators. The sensors are used to measure the
material dimensions and this signal is given to control Unit. The control unit
gives the appropriate signal to the pneumatic cylinder.
In this type of conveyor sensors are used to measure the dimensions of
parts placed over it and a pneumatic cylinder is placed next to the sensor
which will remove the detective parts.By using this system,we completly
eliminate manual work and reduce inspection time and also increase
production rate.
1
CHAPTER 1
INTRODUCTION
1.1 INTRODUCTION
Material Inspection and Sorting Conveyor uses automatic inspection
instead of the manual system by using the pneumatic comparators. The
sensors are used to measure the material dimensions and this signal is given to
control Unit. The control unit gives the appropriate signal to the pneumatic
cylinder.
1.2 OBJECTIVES OF THE PROJECT
To design and fabricate the material inspection and sorting conveyor
which is capable of inspecting components without human intervention with
the help of pneumatic systems.
1.3 PROJECT SCOPE
Basically ,this project is to achieve the objective.
1.Focus on implementing automation in industrial field.
2.Focus on reducing labours.
3.Focus on making low cost machine for material inspection.
1.4 ORGANIZATION OF PROJECT WORK
This project work is compiled in 7 chapters. The organization of the
chapter is explained in the figure 1.1, Chapter 1 introduces the objective, the
organization and the flow of process in which the project work is executed.
Chapter 2 consists of literature review. Chapter 3 consists of assembly
drawing and part diagrams of the component used and working principle.
Chapter 4 explains the process of the component used and working principle.
Chapter 5 explains the commissioning and Chapter 6 explains the cost
estimation followed by the conclusion and reference.
2
1.5 ORGANISATION OF CHAPTERS
!
Fig 1.1 Organisation of chapters
3
1.6 CONCLUSION
The objective of this project work and the problem statement have
been framed for the “Design and fabrication of automated material inspection
and sorting conveyor” has been organized. Thus, the work from scratch to the
completion of the project is explained in the further chapters.

4
CHAPTER 2
LITERATURE REVIEW
2.1 INTRODUCTION
Before starting this project, it is important to research existing
machines and the technologies used in them. This will help us understand any
existing problems and try to find solutions for these problems in such a way
that it can be implemented in our project. Going through the literature also
helps us understand the practical outcomes of the project and how to attain the
required outcomes.
2.2 MATERIAL HANDLING
In the process or manufacturing industry, raw materials need to be
transported from one manufacturing stage to another. Material handling
equipment are designed such that they facilitate easy, cheap, fast and safe
loading and unloading with least human interference. For instance, belt
conveyor system can be employed for easy handling of materials beyond
human capacity in terms of weight and height.
Different methods such as fork lifting, use of bucket elevators,
conveyors systems, crane, etc. has been identified for lifting or transporting
bulk materials or products from one place to anothern the manufacturing
industries depending on the speed of handling, height of transportation,
nature, quantity, size and weight of materials to be transported.It is easier,
safer, faster, more efficient and cheaper to transport materials from one
processing stage to another with the aid of material handling equipment
devoid of manual handling.
Handling of materials which is an important factor in manufacturing
is an integral part of facilities design and the efficiency of material handling
equipment add to the performance level of a firm. Conveyor systems are
durable and reliable in materials transportation and warehousing. Based on
5
different principles of operation, there are different conveyor systems namely
gravity, belt, screw, bucket, vibrating, pneumatic/hydraulic, chain, spiral,
grain conveyor systems, etc. The choice however depends on the volume to be
transported, speed of transportation, size and weight of materials to be
transported, height or distance of transportation, nature of material, method of
production employed. Material handling equipment ranges from those that are
operated manually to semi- automatic systems. [1]
Material handling involves movement of material in a
manufacturing section. It includes loading, moving and unloading of materials
from one stage of manufacturing process to another. A belt conveyor consists
of an endless and flexible belt of high strength with two end pulleys (driver
and driven) at fixed positions supported by rollers.Pulleys are used for
providing the drive to the belt through a drive unit gear box powered by an
electric motor. It also helps in maintaining the proper tension to the belt. The
drive imparts power to one or more pulleys to move the belt and its loads.
Materials are transported over the required distance as a result of
friction generated between the roller surface and the moving belt set in motion
by a rotating pulley (drive pulley). The other pulley (driven or idler pulley)
acts as a wheel around which the material rotates and returns in a continuous
process. Continuous processes are characterized by non-stop motion of bulk
or unit loads along a path without halt for loading and unloading.
2.3 MAJOR EQUIPMENTS IN MATERIAL HANDLING
Transport Equipment is an equipment used to move material from
one location to another (e.g., between workplaces, between a loading dock
and a storage area, etc.). The major subcategories of transport equipment are
conveyors, cranes, and industrial trucks. Material can also be transported
manually using no equipment.
Positioning Equipment is used to handle material at a single
6
location (e.g., to feed and/or manipulate materials so that are in the correct
position for subsequent handling, machining, transport, or storage). Unlike
transport equipment, positioning equipment is usually used for handling at a
single workplace. Material can also be positioned manually using no
equipment.
Unit Load Formation Equipment is used to restrict materials so that
they maintain their integrity when handled a single load during transport and
for storage. If materials are self-restraining (e.g., a single part or interlocking
parts), then they can be formed into a unit load with no equipment.[2]
Storage Equipment is used for holding or buffering materials over
a period of time. Some storage equipment may include the transport of
materials (e.g., the S/R machines of an AS/RS, or storage carousels). If
materials are block stacked directly on the floor, then no storage equipment is
required.
2.4 CONVEYOR SYSTEMS
Conveyor systems have been used for decades to transport bulk and
unit loads.They have proved their worth everywhere because belt conveyor
installations can be adapted to meet nearly all local conditions.They are work
safe and essential.
The demand for ever increasing capacities and ever longer
conveying lengthshas accelerated the development of the belt conveyor
technique, new materials are being developed, new conveying systems are
being planned and tested especially those having regard to the environment.
A conveyor system is a common piece of mechanical handling
equipment that moves materials from one location to another. Conveyors are
especially useful in applications involving the transportation of heavy or
bulky materials. Conveyor systems allow quick and efficient transportation
for a wide variety of materials, which make them very popular in the material
handling and packaging industries.
They also have popular consumer applications, as they are often
7
found in supermarkets and airports, constituting the final leg of item/ bag
delivery to customers. Many kinds of conveying systems are available and are
used according to the various needs of different industries. There are chain
conveyors (floor and overhead) as well. Chain conveyors consist of enclosed
tracks, I-Beam, towline, power & free, and hand pushed trolleys.
Conveyor systems are commonly used in many industries, including
the Mining, automotive, agricultural, computer, electronic, food processing,
aerospace, pharmaceutical, chemical, bottling and canning, print finishing and
packaging. Although a wide variety of materials can be conveyed, some of the
most common include food items such as beans and nuts, bottles and cans,
automotive components, scrap metal, pills and powders, wood and furniture
and grain and animal feed. [3]
Many factors are important in the accurate selection of a conveyor
system. It is important to know how the conveyor system will be used
beforehand. Some individual areas that are helpful to consider are the required
conveyor operations, such as transportation, accumulation and sorting, the
material sizes, weights and shapes and where the loading and pickup points
need to be.
A conveyor system that is designed properly will last a long time
with proper maintenance. Here are six of the biggest problems to watch for in
overhead type conveyor systems including I-beam monorails, enclosed track
conveyors and power and free conveyors. Overhead conveyor systems have
been used in numerous applications from shop displays, assembly lines to
paint finishing plants and more.
Poor take-up adjustment: this is a simple adjustment on most
systems yet it is often overlooked. The chain take-up device ensures that the
chain is pulled tight as it leaves the drive unit. As wear occurs and the chain
lengthens, the take-up extends under the force of its springs. As they extend,
the spring force becomes less and the take-up has less effect. Simply
compress the take-up springs and your problem goes away. Failure to do this
8
can result in chain surging, jamming, and extreme wear on the track and
chain. Take-up adjustment is also important for any conveyor using belts as a
means to power rollers, or belts themselves being the mover. With poor-take
up on belt-driven rollers, the belt may twist into the drive unit and cause
damage, or at the least a noticeable decrease or complete loss of performance
may occur. In the case of belt conveyors, a poor take-up may cause drive unit
damage or may let the belt slip off of the side of the chassis.Lack of
lubrication: chain bearings require lubrication in order to reduce friction. The
chain pull that the drive experiences can double if the bearings are not
lubricated. This can cause the system to overload by either its mechanical or
electrical overload protection. On conveyors that go through hot ovens,
lubricators can be left on constantly or set to turn on every few cycles.
Contamination like paint, powder, acid or alkaline fluids, abrasives,
glass bead, steel shot, etc. can all lead to rapid deterioration of track and
chain. Ask any bearing company about the leading cause of bearing failure
and they will point to contamination. Once a foreign substance lands on the
raceway of a bearing or on the track, pitting of the surface will occur, and
once the surface is compromised, wear will accelerate. Building shrouds
around your conveyors can help prevent the ingress of contaminants. Or,
pressurize the contained area using a simple fan and duct arrangement.
Contamination can also apply to belts (causing slippage, or in the case of
some materials premature wear), and of the motors themselves. Since the
motors can generate a considerable amount of heat, keeping the surface clean
is an almost-free maintenance procedure that can keep heat from getting
trapped by dust and grime, which may lead to motor burnout.
Product handling in conveyor systems that may be suited for a wide
variety of products, such as those in distribution centers, it is important that
each new product be deemed acceptable for conveying before being run
through the materials handling equipment. Boxes that are too small, too large,
too heavy, too light, or too awkwardly shaped may not convey, or may cause
9
many problems including jams, excess wear on conveying equipment, motor
overloads, belt breakage, or other damage, and may also consume extra man-
hours in terms of picking up cases that slipped between rollers, or damaged
product that was not meant for materials handling. If a product such as this
manages to make it through most of the system, the sortation system will most
likely be the affected, causing jams and failing to properly place items where
they are assigned. It should also be noted that any and all cartons handled on
any conveyor should be in good shape or spills, jams, downtime, and possible
accidents and injuries may result.
Drive train, notwithstanding the above, involving take-up
adjustment, other parts of the drive train should be kept in proper shape.
Broken O-rings on a Lineshaft, pneumatic parts in disrepair, and motor
reducers should also be inspected. Loss of power to even one or a few rollers
on a conveyor can mean the difference between effective and timely delivery,
and repetitive nuances that can continually cost downtime.
Bad belt tracking or timing in a system that uses precisely controlled
belts, such as a sorter system, regular inspections should be made that all belts
are traveling at the proper speeds at all times. While usually a computer
controls this with Pulse Position Indicators, any belt not controlled must be
monitored to ensure accuracy and reduce the likelihood of problems. Timing
is also important for any equipment that is instructed to precisely meter out
items, such as a merge where one box pulls from all lines at one time. If one
were to be mistimed, product would collide and disrupt operation.
Timing is also important wherever a conveyor must "keep track" of
where a box is, or improper operation will result.Since a conveyor system is a
critical link in a company's ability to move its products in a timely fashion,
any disruption of its operation can be costly. Most downtime can be avoided
by taking steps to ensure a system operates at peak performance, including
regular inspections, close monitoring of motors and reducers, keeping key
parts in stock, and proper training of personnel.
10
2.4.1 PNEUMATIC SYSTEMS FOR MATERIAL INSPECTION
Pneumatic systems form the most primitive and distinct class of
mechanical control engineering. They are classified under the term 'Fluid
Power Control', which describes any process or device that converts,
transmits, distributes or controls power through the use of pressurized gas or
liquid. In a pneumatic system, the working fluid is a gas (mostly air) which is
compressed above atmospheric pressure to impart pressure energy to the
molecules. This stored pressure potential is converted to a suitable mechanical
work in an appropriate controlled sequence using control valves and actuators.
Pneumatic systems are well suited for the automation of a simple repetitive
task. The working fluid is abundant in nature and hence the running and
maintenance cost of these systems are exceptionally low. All fluids have the
ability to translate and transfigure and hence pneumatic systems permit
variety of power conversion with minimal mechanical hardware.
The technology of pneumatics deals with study of behavior and
application of compressed air. Today air operated tools and accessories are a
common sight in each every industry, not only in the technologically
advanced countries but even in countries where industrial activities are still at
the stage of sheer infancy. With introduction of pneumatics in the
manufacturing process, the industry is benefited automation which if
judiciously used; many bring down the cost of production to a much lower
level. Nowadays compressed air is used in every walk of industrial life,
starting with pneumatic cranes to the use of air in the brake system of
automobiles, railways coaches, wagons, printing presses, and what not. The
following features are notable for the reason
•Wide availability of air
•Compressibility of air
• Easy transportability of compressed air in pressure vessels
• Fire proof characteristics of the medium
11
• Simple construction of pneumatics elements and easy handling
•High degree of controllability of pressure, speed and force.
•Possibility of easy but reasonably reliable remote controlling
•Easier maintenance
•Explosion proof characteristics of the medium
•Comparatively cheaper in cost than other system.
2.5 CONCLUSION
Thus, research was done regarding this project on various sources of
literature. The many methodologies were studied and this information has
helped to complete the project successfully.
12
CHAPTER 3
DESIGN CALCULATIONS
3.1 INTRODUCTION
This chapter will include the design calculations required for the
automated material inspection and sorting conveyor.
3.2 REQUIRED CALCULATIONS:
WEIGHT:
Mechanical Components:
Roller weight = 850g
Belt weight = 500g
Conveyor platform = 2kg
Supporting columns=1.5kg
Pneumatic cylinder =1kg
Total weight of the mechanical components = 5.85kg
Electrical and electronic components:
Motor weight = 250g
Servo valve = 150g
Servo motor =100g
Regulator unit =150g
Control panel = 650g
Miscellaneous = 200g
Proximity sensor=100g
Weighing sensor=250g
Jam 1,2 =100g
Total weigth of the electrical and electronic components=1.95kg
Total weight of the conveyor= 7.80 kg
Force on the Conveyor = 0.4*9.81
= 3.924 N
13
~ 4 N
Force is maximum when link is in horizontal position
Shaft Diameter of DC motor of above application =12 mm
Radius = 6 mm
Torque required = Force* Radius
= 4*6
= 24 Nmm
= 0.25 kgcm
BELT DIMENSION, CAPACITY AND SPEED:
Belt length is dependent on both the pulley diameters and centre
distances.
V=d×PI(1)
V= Belt speed;
d = diameters of rollers; and
Capacity is the product of speed and belt cross sectional area
Generally, belt capacity (kg/sec) is given as:
B.C = 3.6 × A × 3.14× V
A = belt sectional area (m2);
V = belt speed (m/s) ..(2)
The mass of material Mm (live load) per meter (kg/m) loaded on a belt
conveyor is given as:
Where,
V = belt speed (1.25 m/s).
Mm =0.889 kg.
The magnitude of belt speed V (m/s) can be determined from equations
1, 2, 3 or 6 and can as well be gotten from the catalogue for standard belt.
Belt speed v (m/s) depends
Mm= C/(3.6*v)…(3)
c = Conveyor capacity (4 tones/hr); and
14
V = belt speed (1.25 m/s).
Mm =0.889 kg.
CAPACITY OF THE CONVEYOR:
C = cT*1000*cf*v / 1000…(4)
C = Capacity in tones/hr of a belt conveyor
cT = Capacity of td belts for 3 roll equal le;
cf = Capacity factor (1.08); and
V = Belt speed in m/s (1.25)
= 4 tonnes/hr
ROLLER DIAMETER:
n = (V *1000 *60 )/D*3.14
n = no of revolution per minute;
D = roller diameter (mm); and
V = belt speed (m/s)
From Equation (6), the no of revolution per minute n = 220 rpm
The inclination angle is 100, the conveyor length is 100 m, and the
conveyor height is 10 m.
Belt basic length = 2 × length along conveying route ..(8)
From Equation (8), basic belt length = 2 × 14 = 28 m
The roll diameter for belt is given as,
D = sqrt((d*d)+(0.001273*L*G))
Where,

D = overall diameter (m);
D = core diameter (m);

L = Belt length (m); and
G = Belt Thickness (mm)
The length of a belt on roll is given as:
L = (d+((D-d)/2)*3.14*N)…….(10)
15
Where,

D = outside diameter of the roll (m);
d = diameter of the roll centre (m);
N = no.of.wraps of the belt

BELT POWER AND TENSION:
The power Pp (kW) at drive pulley drum is
Pp = Fu*V /1000
Where,
Fu = Total tangential force at the periphery of the drive pulley (N);
V = Belt speed (1.25 m/sec); and
Fu = Pp*V /1000
Pp = power required for conveyor (kW);
where ,
C = conveyor capacity (4 tones/hr) = (3.9375 kg/sec); and
L = Lift(1.5m)
P = 3.7kW.
Te = Total empty friction + Load friction + load slope tension
= 1.141KN
The belt power (kW) is given as
Pb =Te *V
Te = effective tension (1.141 KN)
V = Belt speed (1.25 m/sec)
Pb = 1.43 kW
σc < σt
Therefore, design is safe.
T = 30 kgcm
= 3 Nm
ρ = (2π*30*3)/260
= 3π
16
= 10 N
“Link material is mild steel”
l = 160 mm
W = 150 g
σc = (0.1)/(16*b)
COLUMN :
Area (A) = (20*20) – (16*16)
= 144 mm2
Length (L) = 240 mm2
= 0.240m
For column both the ends are fixed, so n=4
Critical load (Pc) = (nπ2EI)/(L2)
For mild steel, (E) = 200*109 GPa
Area moment of inertia,I = (a04- ai4)/12
= (204-164)/12
= 7782*10-12 kgcm
Pc = (4*3.142*200*109*7872*10-12)/(0.24)2
Pc = 1077 KN > 26N
Hence design is safe.
l = 250 mm
Area moment of inertia,I = (a14- a24)/12
= (204-164)/12
= 7782 mm4
Sectional area,A = 144 mm2
K1 = √(7872144)
= 7.35
Yield stress,σy/2 = nπ2E/(1/k)2
297/2 = 4*π2*200*1000/(1/k)2
Yield stress of mild steel,σy = 297 Mpa(Design data book)
17
K2 = 0.00433
K1 > K2
So, the screw should be long column.
BENDING MOMENT
Ra = Rb = (5*9.81)/2
= 24.53 N
Mc = Rb*110
= 24.53*110
= 2697.75 Nmm
!
Fig 3.1 Bending Moment of beams 1 and 2

18
RA = RB = 1.23N
Mc = RB*110
= 1.23*110
= 134.89 Nmm
!
Fig 3.2 Bending Moment of beams 3 and 4
19
Weight of Beam 1 = 5.3 Kg
= 51.993 N
~ 52 N
Weight of Beam 2 = 5.3 Kg
= 51.993 N
~ 52 N
Weight of Beam 3 = 0.55 Kg
= 5.395 N
~ 5.4 N
RA + RB = 54.7 N
RA = 54.7 N – RB
MBF = 0
0 = (26*120) – (RB *310) + (26*108) +
(2.7*66) – (RA *26)
26 RA *310 RB = 6760 + 178.2 + 2808
= 9746.2 N
MRB = 0
0 = (26*50) – (26*201) + (2.7*242) – (RA *282)
282 RA = 1300 + 5252 + 653.4
RA = 25.55 N
310 RB = 9081.97 N
RB = 29.29 N
20
!
Fig 3.3 Bending Moment of beams 5 and 6
WELDING CLAMPS :
Area for welding (A) = (50*30) – (40*20)
= 700 mm2
Height of welding = 5 mm
Then Volume of weld (V) = (700*5)/2 = 1750 mm3
Density of alloy carbon steel = 7.86 gm/cm3
Weight of weld steel = v*ρ
= 1750*7.86*103
= 83.16 g
σc = 6*Mb/l*h2
Mb = F*r
= 30*10
21
= 300 Nmm
Length,l = 50 mm
Height,h = 30 mm
σc = 6*300/50*302
= 1.2 N/mm2
σt = 242N/mm2
σc < σt
Therefore, design is safe.
L CLAMP :
Ra = 600*10
= 6000 Nmm2 = 600 kgmm
Area moment of inertia (I) = (b*d3)/12 = (20*103)/12
= 1666.67 mm2
Bending stress,
σ/y = M/I
σ = My/I
= 600*5/1666.67
= 1.8 kg/mm2
For steel yield strength is, 25 kg/mm2 > 1.8 kg/mm2
Hence, design is safe.
For angle from horizontal of 60°
Mass flow % = 25 % ,Sheet metal material is chosen.
σty = 290 N/mm2
σ = 50/32*t
= 29 N/mm2
t = 0.6 to 1 mm
σ = 500/32*8
= 1.95 N/mm2
Critical load,Pcr = (nπ2EI)/(1/K)2
= (4*π2*200*103*144)/(1/7.35)2
22
= 6.136*1010 N
Calculated load,Pcal = 26 N
Pcr > Pcal
Hence, Design is safe.
3.3 CONCLUSION
Thus, the design calculations for the machine were done. These
calculations were done keeping in mind the dimensional restrictions for this
project, along with economic views. The values are well within the limit and
the design is safe and accurate.

23
CHAPTER 4
ASSEMBLY AND PART DRAWINGS
4.1 INTRODUCTION
This chapter consists of assembly drawings and part drawings of the
main components of the automated material inspection and sorting conveyor.
The drawings are designed using Solidworks to generate the 2D and 3D
models of the system and its components.
Based on the design calculations in the previous chapter the
drawings are designed respective of its dimension.
4.2 2D DIAGRAM
Fig 4.2.1 2D Diagram
24
Fig 4.2.1 represents the 2D Dimensional of automated material
inspection and sorting conveyor.
4.3 PART DIAGRAMS
Fig 4.3.1 Bearing
Fig 4.2.1 represents the 2D Dimensional view of bearing used in
automated material inspection and sorting conveyor with the specific
dimensions drawn using Solid works software.
25
Fig 4.3.2 Pneumatic cylinder
Fig 4.3.2 represents the 2D Dimensional view of pneumatic
cylinder used in automated material inspection and sorting conveyor with the
specific dimensions drawn using Solid works software.
26
Fig 4.3.3 Supporting column
Fig 4.3.3 represents the 2D Dimensional view of supporting
column used in automated material inspection and sorting conveyor with the
specific dimensions drawn using Solid works software.
27
Fig 4.3.4 Roller
Fig 4.3.4 represents the 2D Dimensional view of roller used in
automated material inspection and sorting conveyor with the specific
dimensions drawn using Solid works software.
28
Fig 4.3.5 Belt Conveyor
Fig 4.3.3 represents the 2D Dimensional view of belt conveyor
used in automated material inspection and sorting conveyor with the specific
dimensions drawn using Solid works software.
29
4.4 3D SOLID MODEL
Fig 4.4 Assembly View
Fig 4.4 represents the assembly view of automated material
inspection and sorting conveyor with the specific dimensions drawn using
Solid works software.
30
4.5 ASSEMBLY DRAWING
Fig 4.5 Assembly Diagram
4.4 CONCLUSION
Thus the assembly drawings and part drawings of the main
components of the automated material inspection and sorting conveyor were
designed using Solidworks to generate the 2D and 3D models of the system
and its components. Based on the design, the machine is fabricated.

31
CHAPTER 5
SYSTEM DESIGN
5.1 INTRODUCTION
This chapter consists of the complete system architecture of the
electronic components. The system architecture shows the layout of the unit
and the communication cables used for interconnection of various parts of the
system.
5.2 MODEL OF THE SETUP
Fig 5.2.1 Circuit Diagram
32
The circuit diagram consists of three units- sensing units,
controlling units, sorting units.The sensing units consists of ultrasonic level
sensor and an inductive proximity sensor.These are the inputs and the
pneumatic valves are the outputs based on the inputs the PLC processes the
input and HMI controls the outputs based on the logic and the pneumatic
valves are been actuated and the sorting mechanism is been carried out. The
entire mechanism can be visualized at the touch screen HMI panel.
Fig 5.2.2 Working module
33
A programmable logic controller (PLC) or programmable
controller is a digital computer used for automation of electromechanical
processes, such as control of machinery on factory assembly lines,
amusement rides, or lighting fixtures. PLCs are used in many industries and
machines, such as packaging and semiconductor machines. Unlike general-
purpose computer, the PLC is designed for multiple inputs and output
arrangements, extended temperature ranges, immunity to electrical noise, and
resistance to vibration and impact. A very commonly used method of
programming PLC’s is based on the use of ladder diagrams. Writing a
program is the equivalent to drawing a switching circuit. Circuits are
connected as horizontal lines, that is, the rungs of the ladder, between these
two vertical lines. In drawing a ladder diagram, certain conventions are
adopted.
Many types of proximity sensors have been built the simplest
sensors are proximity switches capable of merely detecting the presence or
absence of an object in the sensors proximity. More complex proximity
sensors have the capability of determining continuous three dimensional
positions and other information such as intensity and orientation. Different
proximity sensors employ various media including magnetic field, electric
filed, electric field, air pressure, ultrasonic sound, and light recent advance in
inexpensive electro-optical component also has made optical methods
attractive.
34
5.3 CONCLUSION
Thus the system design has been illustrated by providing the
architecture of electronic process of automated material inspection and sorting
conveyor.
35
CHAPTER 6
PROCESS SHEET
6.1 INTRODUCTION
The prime motive of the ‘PROCESS SHEET’ chapter is to provide
the fine details about the components being used, their material and quantity
of each component involved in the project. It also illustrates the processing
steps to complete the project.
6.2 COMPONENT SPECIFICATIONS
6.2.1 Project Specification
Table 6.1 Component specification
PARAMETER TYPE
SIEMENS PLC S7-200
Pneumatic systems As required
Sensors Weighing sensors and Proximity
Sensors
Connecting wires As required
Valves Servo valves
DC motor 12 volts
36
6.2.2 COMPONENTS OF PNEUMATIC SYSTEM
AIR COMPRESSOR
Though not directly connected to the pneumatic system, the air
compressor plays a vital role in the overall system performance. Various types
of air compressors are used in the industry. But positive displacement
compressors are more popular. The air receiver is important equipment in the
compressor family. For uninterrupted supply of compressed air, receiver with
to optimum size is to be selected.
FRL UNIT
The FRL unit consists of the following separate components, filter,
regulator and lubricator. They are packaged to supply the cleaned lubricated
and regulated air to the actuator.
FILTER
Even very small particle containing in air may be produce wear by
lapping action in the parts. Therefore the air is filtered to remove dirt, rest
particles and other air borne matter in line. The air is filtered before entering
the compressor. However, the passage of the air stream through the distributor
system often contaminates it with oxidation deposits on the sides of the steel
piping.
REGULATOR
Independent pressure control is necessary for air distribution in
pneumat ic circuitry. Pneumatic circuitry uses an outlet side piloted pressure
reducing valve to limit pressure only to desired circuit these specialized
pneumatic pressure reducing valves are known as regulators.
37
LUBRICATOR
Pneumatic systems are not self lubricat ing. Pneumatic
components need lubrication for its smooth functioning. Therefore a
lubricator is used in the FRL unit to add a small amount of oil to the dry air.
PNEUMATIC ACTUATORS
Pneumatic cylinders offer a straight rectilinear motion to
mechanical elements. Cylinders are classified as light, medium, heavy duty
with respect to their application. Selection of materials for cylinder depends
greatly on this factor. Functionally cylinders may be single or double acting.
They may be further classified as diaphragm cylinder, duplex cylinder,
through rod cylinder etc. end position cushioning of cylinder as certain times
may be of almost important.
PNEUMATIC VALVES
The pneumatic energy is regulated and controlled by pneumatic
valves. Functionally the valves are divided into four major groups, viz.
directional control, floe control, pressure control, non return and special type
va lves. As pre construction the valves are sub grouped as seat valves sliding
or spool valves. Both these of constructions are frequently used in pneumatic
valves. However the spool valves are easier to manufacture. Valves are
actuated in various methods, viz. manually, mechanically, electrically,
pneumatically and by various combined mode of actuation. Specially
designed valves like quick exhaust time delay shuttle and twin pressure
valves are used to impart various special functions to pneumatic circuits.
38
PLC SPECIFICATION
Fig 6.2 Table 6.2 S7-200 CPU specification
39
6.2.3 PROGRAMMABLE LOGIC CONTROLLER
A programmable logic controller is a digital computer used for
automation of electromechanical processes. A programmable logic controller
(PLC) or programmable controller is a digital computer used for automation
of electromechanical processes, such as control of machinery on factory
assembly lines, amusement rides, or lighting fixtures. PLCs are used in many
industries and machines, such as packaging and semiconductor machines.
Industrial PLC describes the computing unit of any industrial automation
system and therefore need to meet several challenging requirements such as
high reliability, environmental noise and influence immunity and also
enhanced protection classes (e.g. water-resistant and dust sealed).
PLCs also satisfy the needs of continuous 24 hours/7 days
operation and availability over a wide environmental temperature range as
well as real-time operation capability and security and safety enhancements.
The input/output arrangements may be built into a simple PLC, or the PLC
may have external I/O modules attached to a computer network that plugs into
the PLC. The communications interface is used to receive and transmit data
on communication networks from or to other remote PLCs. [4]
It is concerned with such actions as device verification, data
acquisition, synchronization between user applications and connection
management.Some of the advantages of using PLC include:
• Programming the PLC is easier than wiring the relay control panel
• PLC takes less floor space then relay control panels.
• Maintenance of the PLC is easier, and reliability is greater.
• PLC can be connected to the plant computer systems more easily
than relays.

40
6.3 PROCESS FLOWCHART
Fig 6.1 Process flow chart
Switch on the system
Place the materials on the
conveyor
Sensing using PLC and sensors
Inappropriate materials are
pushed to tray
Correct material follows through
the conveyor
Unloading.components
41
6.4 CONCLUSION
Thus the process sheet has been illustrated by tabulating all the
process took place during the design of automated material inspection and
sorting conveyor. The tables contains the product specification used at this
level of fabrication.
42
CHAPTER 7
PLC PROGRAMMING
7.1 INTRODUCTION
This chapter involves the PLC programming of the material
inspection conveyor by using ladder logic diagram.
7.2 PLC PROGRAMMING
The PLC programming is done by using ladder logic diagram using
ABB control builder plus software.
Ladder logic is widely used to program PLCs, where sequential
control of a process or manufacturing operation is required. Ladder logic is
useful for simple but critical control systems or for reworking old hardwired
relay circuits. As programmable logic controllers became more sophisticated
it has also been used in very complex automation systems. Often the ladder
logic program is used in conjunction with an HMI program operating on a
computer workstation.[5]
Ladder logic can be thought of as a rule-based language rather
than a procedural language. A "rung" in the ladder represents a rule. When
implemented with relays and other electromechanical devices, the various
rules "execute" simultaneously and immediately. When implemented in a
programmable logic controller, the rules are typically executed sequentially
by software, in a continuous loop (scan). By executing the loop fast enough,
typically many times per second, the effect of simultaneous and immediate
execution is achieved, if considering intervals greater than the "scan time"
required to execute all the rungs of the program. Proper use of programmable
controllers requires understanding the limitations of the execution order of
rungs.
43
7.3 LADDER LOGIC
Fig 7.3 Ladder logic diagram
44
7.4 CONCLUSION
Thus the control of the automated material inspection and sorting
conveyor programming is done using PLC programming.
45
CHAPTER 8
COST OF THE PROJECT
8.1 INTRODUCTION
This chapter lists the approximate cost of various components used
in the project.
8.2 COST TABLE
Table 8.1 Cost estimation
Material/material
type
Quantity Cost
1 Roller(mild steel) 5 5600
2 Stand(Iron) 1 3000
3 Pneumatic cylinders 2 6000
4 Servo valve 1 1500
5 Belt 1 4000
6 DC Motor 1 3500
7 Tray(plastic) 3 3000
8 Bearing(roller) 12 18000
9 Air filter unit 1 3500
Total 48100
46
8.3 CONCLUSION
Thus the components were chosen with cost as a parameter to
optimize the development of the system.
47
CHAPTER 9
FABRICATION OF THE PROJECT
9.1 INTRODUCTION
This chapter lists the fabrication photos taken while doing the
fabrication of material inspection and sorting conveyor.
9.2 FABRICATION PHOTOS
Fig 9.2.1 Conveyor model
48
Fig 9.2.2 Conveyor model
50
9.3 CONCLUSION
Thus the material inspection and sorting conveyor which is capable
of inspecting components without human intervention was fabricated
successfully.
51
CHAPTER 10
CONCLUSION
10.1 INTRODUCTION
Thus the material inspection and sorting conveyor which is capable of inspecting
components without human intervention is designed and fabricated with the help of
pneumatic systems.
10.2 FUTURE SCOPE OF THE PROJECT
By producing such system, the scope is in the field of Manufacturing ,identification
of suitable solution, evaluation processes , design the proposal, to build the
prototype .Also we can use such system with some modification for various types of
inspection such as
• Inspection Parameter
• Diameter, hole diameter
• Height
• Thickness
• Surface defect
• Crack, burr
• Roundness
• Minor and major diameter
• Chamfer angle etc.
10.3 CONCLUSION
The project is successfully completed and tested. All the specified
requirements were fulfilled upon completing the project
52
REFERENCES
1. Sambathkumar N. and Siva kumar K,‘‘Design and Fabrication of
Material Inspection Conveyor”,Research paper in International Journal of
Mechanical Engineering and Robotics Research, April 2014
2. Aniket A Jagtap ,“Design of Material Handling Equipment’,Research
paper in International Journal of Mechanical Engineering and Robotics
Research,March 2015
3. Anath K N and Rakesh V, “Design and Selecting Proper Conveyor Belt”,
Int. Journal of Advanced Technology”, Vol. 4, No. 2, pp. 43-49,2015
4. Petruzella, F. D, “Programmable Logic Controllers, McGraw Hill, 2005”.
5. Yang, G., Rasis, Y “Teaching PLC in Automation – A Case Study”, ASEE
Annual Conference &Exposition,June 2005
6.Roberts, A.W., Hayes, J.W. and Scott, 0.J.,"Optimum Design of Continuous
Conveyors". Bulk Solids Handling, Vol. 1, No. 2, 1981.
7. Harrison, A., "Flexural Behaviour of Tensioned Conveyor Belts",
Mech.Eng.Trans. IE (Aust.), Vol. MES (1983), No. 3.
8. Harrison, A. and Roberts, A.W., "Technical Requirements for Operating
Conveyor Belts at High Speed", Bulk Solids Handing, Vol. 4 (1984), No. 1,
pp.99-104.
9. Harrison, A., "Criteria for Minimising Transient Stress in Conveyor Belts",
Mech.Eng.Trans IE(Aust), Vol. ME8 (1983), No. 3, pp. 129-134.
10. Roberts, A.W., Harrison, A. and Hayes, J.W., "Economic Factors Relating
to the Design of Belt Conveyors for Long Distance Transportation of Bulk
53
Solids", Int. Jnl. of Bulk Solids Handling, Vol. 5, No. 6, December 1985 (pp.
1 143-1149).
54
APPENDIX
Fw = Force due to weight
us = Friction coefficient
ur = Rolling friction coefficient
b = Rolling resistance
W = Load or Weight of machine
P = Force required for movement
b = Distance of contact
Ra,Rb = Reactive forces on beams
Mc = Bending moment
Mt = Torsional moment of shaft
d = Diameter of shaft
σ = Stress of link
σc = Calculated stress
σt = Maximum stress that can be withstand
l = Length of link
Pcr = Crippling load for column
Pcal = Applied load for column
E = Young’s Modulus
I = Area moment of Inertia
A = Area of cross section of column
1/k = Slenderness Ratio
h = Height of welding
Ď´ = Angle of inclination
55

More Related Content

What's hot

Design Of Belt Conveyor to Prevent the failure and many other drawbacks from ...
Design Of Belt Conveyor to Prevent the failure and many other drawbacks from ...Design Of Belt Conveyor to Prevent the failure and many other drawbacks from ...
Design Of Belt Conveyor to Prevent the failure and many other drawbacks from ...Vishal Patel
 
Stair climbing trolley
Stair climbing trolleyStair climbing trolley
Stair climbing trolleyHimagiri Silla
 
Design and Model of Bucket Elevator
Design and Model of Bucket ElevatorDesign and Model of Bucket Elevator
Design and Model of Bucket ElevatorUtkarsh Amaravat
 
material handling and its classifications with principles.
material handling and its classifications with principles.material handling and its classifications with principles.
material handling and its classifications with principles.Vaibhav Pathak
 
Conveyors and types
Conveyors and typesConveyors and types
Conveyors and typesAli Murtaza
 
Conveyor system ppt
Conveyor  system pptConveyor  system ppt
Conveyor system pptrohitpateltit
 
Belt conveyor example calculation
Belt conveyor example calculationBelt conveyor example calculation
Belt conveyor example calculationssuser16d252
 
Material handling equipments
Material handling equipmentsMaterial handling equipments
Material handling equipmentsSULAKSHYA GAUR
 
BELT CONVEYORS
BELT CONVEYORSBELT CONVEYORS
BELT CONVEYORSChandana R
 
Final Project_ Design and FEM Analysis of Scissor Jack
Final Project_ Design and FEM Analysis of Scissor JackFinal Project_ Design and FEM Analysis of Scissor Jack
Final Project_ Design and FEM Analysis of Scissor JackMehmet Bariskan
 
Pneumatics: Shuttle, Twin pressure, Quick Exhaust, Time Delay, FRL
Pneumatics: Shuttle, Twin pressure, Quick Exhaust, Time Delay, FRLPneumatics: Shuttle, Twin pressure, Quick Exhaust, Time Delay, FRL
Pneumatics: Shuttle, Twin pressure, Quick Exhaust, Time Delay, FRLAbhishek Patange
 
Vibrating feeder
Vibrating feederVibrating feeder
Vibrating feederJISHNU V
 
Linear motion guideways
Linear motion guidewaysLinear motion guideways
Linear motion guidewaysAkhil Krishnan G
 
Layout of FMS
Layout of FMSLayout of FMS
Layout of FMSsgrsoni45
 
Automated assembly systems
Automated assembly systemsAutomated assembly systems
Automated assembly systemschethan kumar
 
Design and fabrication_automatic_conveyor_ppt
Design and fabrication_automatic_conveyor_pptDesign and fabrication_automatic_conveyor_ppt
Design and fabrication_automatic_conveyor_pptDuraimuruganM27
 
DESIGN & ANALYSIS OF SCREW CONVEYOR
DESIGN & ANALYSIS OF SCREW CONVEYORDESIGN & ANALYSIS OF SCREW CONVEYOR
DESIGN & ANALYSIS OF SCREW CONVEYORVenkatesh Kokala
 

What's hot (20)

Belt conveyor
Belt conveyorBelt conveyor
Belt conveyor
 
Design Of Belt Conveyor to Prevent the failure and many other drawbacks from ...
Design Of Belt Conveyor to Prevent the failure and many other drawbacks from ...Design Of Belt Conveyor to Prevent the failure and many other drawbacks from ...
Design Of Belt Conveyor to Prevent the failure and many other drawbacks from ...
 
Stair climbing trolley
Stair climbing trolleyStair climbing trolley
Stair climbing trolley
 
Design and Model of Bucket Elevator
Design and Model of Bucket ElevatorDesign and Model of Bucket Elevator
Design and Model of Bucket Elevator
 
material handling and its classifications with principles.
material handling and its classifications with principles.material handling and its classifications with principles.
material handling and its classifications with principles.
 
Conveyors and types
Conveyors and typesConveyors and types
Conveyors and types
 
Conveyor system ppt
Conveyor  system pptConveyor  system ppt
Conveyor system ppt
 
Belt conveyor example calculation
Belt conveyor example calculationBelt conveyor example calculation
Belt conveyor example calculation
 
Material handling equipments
Material handling equipmentsMaterial handling equipments
Material handling equipments
 
BELT CONVEYORS
BELT CONVEYORSBELT CONVEYORS
BELT CONVEYORS
 
Final Project_ Design and FEM Analysis of Scissor Jack
Final Project_ Design and FEM Analysis of Scissor JackFinal Project_ Design and FEM Analysis of Scissor Jack
Final Project_ Design and FEM Analysis of Scissor Jack
 
Pneumatics: Shuttle, Twin pressure, Quick Exhaust, Time Delay, FRL
Pneumatics: Shuttle, Twin pressure, Quick Exhaust, Time Delay, FRLPneumatics: Shuttle, Twin pressure, Quick Exhaust, Time Delay, FRL
Pneumatics: Shuttle, Twin pressure, Quick Exhaust, Time Delay, FRL
 
Vibrating feeder
Vibrating feederVibrating feeder
Vibrating feeder
 
Gear train
Gear trainGear train
Gear train
 
Lecture 4 Material Handling Equipment (Conveyors)
Lecture 4 Material Handling Equipment (Conveyors)Lecture 4 Material Handling Equipment (Conveyors)
Lecture 4 Material Handling Equipment (Conveyors)
 
Linear motion guideways
Linear motion guidewaysLinear motion guideways
Linear motion guideways
 
Layout of FMS
Layout of FMSLayout of FMS
Layout of FMS
 
Automated assembly systems
Automated assembly systemsAutomated assembly systems
Automated assembly systems
 
Design and fabrication_automatic_conveyor_ppt
Design and fabrication_automatic_conveyor_pptDesign and fabrication_automatic_conveyor_ppt
Design and fabrication_automatic_conveyor_ppt
 
DESIGN & ANALYSIS OF SCREW CONVEYOR
DESIGN & ANALYSIS OF SCREW CONVEYORDESIGN & ANALYSIS OF SCREW CONVEYOR
DESIGN & ANALYSIS OF SCREW CONVEYOR
 

Similar to Conveyor report

Design of a_material_handling_equipment
Design of a_material_handling_equipmentDesign of a_material_handling_equipment
Design of a_material_handling_equipmentmkpq pasha
 
Development of a Belt Conveyor for Small Scale Industry
Development of a Belt Conveyor for Small Scale IndustryDevelopment of a Belt Conveyor for Small Scale Industry
Development of a Belt Conveyor for Small Scale IndustryScientific Review SR
 
Design and Development of Vertical Material Handling Lift for Reduce Cycl...
Design and Development of Vertical Material Handling Lift for Reduce     Cycl...Design and Development of Vertical Material Handling Lift for Reduce     Cycl...
Design and Development of Vertical Material Handling Lift for Reduce Cycl...IRJET Journal
 
Automation of material_handling_with_buc
Automation of material_handling_with_bucAutomation of material_handling_with_buc
Automation of material_handling_with_bucmkpq pasha
 
IRJET- Design and Development of Conveyor System for Scrap Collection of Tab ...
IRJET- Design and Development of Conveyor System for Scrap Collection of Tab ...IRJET- Design and Development of Conveyor System for Scrap Collection of Tab ...
IRJET- Design and Development of Conveyor System for Scrap Collection of Tab ...IRJET Journal
 
Paper id 41201626
Paper id 41201626Paper id 41201626
Paper id 41201626IJRAT
 
Design and Fabrication of Efficient Material Transport Equipment
Design and Fabrication of Efficient Material Transport EquipmentDesign and Fabrication of Efficient Material Transport Equipment
Design and Fabrication of Efficient Material Transport EquipmentIRJET Journal
 
Development of Bottle Unscramble Machine
Development of Bottle Unscramble MachineDevelopment of Bottle Unscramble Machine
Development of Bottle Unscramble MachineIRJET Journal
 
IRJET- Conceptualization of Pneumatic Uplift Mechanism for Live Roller Conveyor
IRJET- Conceptualization of Pneumatic Uplift Mechanism for Live Roller ConveyorIRJET- Conceptualization of Pneumatic Uplift Mechanism for Live Roller Conveyor
IRJET- Conceptualization of Pneumatic Uplift Mechanism for Live Roller ConveyorIRJET Journal
 
INDUSTRIAL ENGINEERING 2 nd module
INDUSTRIAL ENGINEERING 2 nd moduleINDUSTRIAL ENGINEERING 2 nd module
INDUSTRIAL ENGINEERING 2 nd moduleJim Alex
 
Plc based inspection, packaging, storage and retrieval application
Plc based inspection, packaging, storage and  retrieval applicationPlc based inspection, packaging, storage and  retrieval application
Plc based inspection, packaging, storage and retrieval applicationNilesh parmar
 
IRJET- Design and Development of Sensor Operated Walking Beam Conveyor Sy...
IRJET-  	  Design and Development of Sensor Operated Walking Beam Conveyor Sy...IRJET-  	  Design and Development of Sensor Operated Walking Beam Conveyor Sy...
IRJET- Design and Development of Sensor Operated Walking Beam Conveyor Sy...IRJET Journal
 
DESIGN OF BUCKET ELEVATOR WITH AUTO BELT TENSIONER UNIT
DESIGN OF BUCKET ELEVATOR WITH AUTO BELT TENSIONER UNITDESIGN OF BUCKET ELEVATOR WITH AUTO BELT TENSIONER UNIT
DESIGN OF BUCKET ELEVATOR WITH AUTO BELT TENSIONER UNITSomashekhar Mudalagi
 
Material Handling.pptx
Material Handling.pptxMaterial Handling.pptx
Material Handling.pptxErPoojaHemantSahu
 
Material Handling
Material HandlingMaterial Handling
Material HandlingSagar Savale
 
Design, Simulation & Optimization of Gravity Spiral Roller Conveyer with Auto...
Design, Simulation & Optimization of Gravity Spiral Roller Conveyer with Auto...Design, Simulation & Optimization of Gravity Spiral Roller Conveyer with Auto...
Design, Simulation & Optimization of Gravity Spiral Roller Conveyer with Auto...IRJET Journal
 
Introduction-to-Roller-Conveyors.pptx Material Handling Equipments
Introduction-to-Roller-Conveyors.pptx Material Handling EquipmentsIntroduction-to-Roller-Conveyors.pptx Material Handling Equipments
Introduction-to-Roller-Conveyors.pptx Material Handling EquipmentsRIYAZAHMED125
 
IRJET- Design and Manufacturing of Ladder Roof Lift for Material Lifting
IRJET-  	  Design and Manufacturing of Ladder Roof Lift for Material LiftingIRJET-  	  Design and Manufacturing of Ladder Roof Lift for Material Lifting
IRJET- Design and Manufacturing of Ladder Roof Lift for Material LiftingIRJET Journal
 

Similar to Conveyor report (20)

fpc project
fpc projectfpc project
fpc project
 
Design of a_material_handling_equipment
Design of a_material_handling_equipmentDesign of a_material_handling_equipment
Design of a_material_handling_equipment
 
Development of a Belt Conveyor for Small Scale Industry
Development of a Belt Conveyor for Small Scale IndustryDevelopment of a Belt Conveyor for Small Scale Industry
Development of a Belt Conveyor for Small Scale Industry
 
Design and Development of Vertical Material Handling Lift for Reduce Cycl...
Design and Development of Vertical Material Handling Lift for Reduce     Cycl...Design and Development of Vertical Material Handling Lift for Reduce     Cycl...
Design and Development of Vertical Material Handling Lift for Reduce Cycl...
 
Automation of material_handling_with_buc
Automation of material_handling_with_bucAutomation of material_handling_with_buc
Automation of material_handling_with_buc
 
IRJET- Design and Development of Conveyor System for Scrap Collection of Tab ...
IRJET- Design and Development of Conveyor System for Scrap Collection of Tab ...IRJET- Design and Development of Conveyor System for Scrap Collection of Tab ...
IRJET- Design and Development of Conveyor System for Scrap Collection of Tab ...
 
Paper id 41201626
Paper id 41201626Paper id 41201626
Paper id 41201626
 
Design and Fabrication of Efficient Material Transport Equipment
Design and Fabrication of Efficient Material Transport EquipmentDesign and Fabrication of Efficient Material Transport Equipment
Design and Fabrication of Efficient Material Transport Equipment
 
Development of Bottle Unscramble Machine
Development of Bottle Unscramble MachineDevelopment of Bottle Unscramble Machine
Development of Bottle Unscramble Machine
 
material-handling-prd-430
 material-handling-prd-430 material-handling-prd-430
material-handling-prd-430
 
IRJET- Conceptualization of Pneumatic Uplift Mechanism for Live Roller Conveyor
IRJET- Conceptualization of Pneumatic Uplift Mechanism for Live Roller ConveyorIRJET- Conceptualization of Pneumatic Uplift Mechanism for Live Roller Conveyor
IRJET- Conceptualization of Pneumatic Uplift Mechanism for Live Roller Conveyor
 
INDUSTRIAL ENGINEERING 2 nd module
INDUSTRIAL ENGINEERING 2 nd moduleINDUSTRIAL ENGINEERING 2 nd module
INDUSTRIAL ENGINEERING 2 nd module
 
Plc based inspection, packaging, storage and retrieval application
Plc based inspection, packaging, storage and  retrieval applicationPlc based inspection, packaging, storage and  retrieval application
Plc based inspection, packaging, storage and retrieval application
 
IRJET- Design and Development of Sensor Operated Walking Beam Conveyor Sy...
IRJET-  	  Design and Development of Sensor Operated Walking Beam Conveyor Sy...IRJET-  	  Design and Development of Sensor Operated Walking Beam Conveyor Sy...
IRJET- Design and Development of Sensor Operated Walking Beam Conveyor Sy...
 
DESIGN OF BUCKET ELEVATOR WITH AUTO BELT TENSIONER UNIT
DESIGN OF BUCKET ELEVATOR WITH AUTO BELT TENSIONER UNITDESIGN OF BUCKET ELEVATOR WITH AUTO BELT TENSIONER UNIT
DESIGN OF BUCKET ELEVATOR WITH AUTO BELT TENSIONER UNIT
 
Material Handling.pptx
Material Handling.pptxMaterial Handling.pptx
Material Handling.pptx
 
Material Handling
Material HandlingMaterial Handling
Material Handling
 
Design, Simulation & Optimization of Gravity Spiral Roller Conveyer with Auto...
Design, Simulation & Optimization of Gravity Spiral Roller Conveyer with Auto...Design, Simulation & Optimization of Gravity Spiral Roller Conveyer with Auto...
Design, Simulation & Optimization of Gravity Spiral Roller Conveyer with Auto...
 
Introduction-to-Roller-Conveyors.pptx Material Handling Equipments
Introduction-to-Roller-Conveyors.pptx Material Handling EquipmentsIntroduction-to-Roller-Conveyors.pptx Material Handling Equipments
Introduction-to-Roller-Conveyors.pptx Material Handling Equipments
 
IRJET- Design and Manufacturing of Ladder Roof Lift for Material Lifting
IRJET-  	  Design and Manufacturing of Ladder Roof Lift for Material LiftingIRJET-  	  Design and Manufacturing of Ladder Roof Lift for Material Lifting
IRJET- Design and Manufacturing of Ladder Roof Lift for Material Lifting
 

Recently uploaded

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoĂŁo Esperancinha
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 

Recently uploaded (20)

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 

Conveyor report

  • 1.
  • 2.
  • 3.
  • 4. v TABLE OF CONTENTS CHAPTER TITLE PAGE NO NO. iii iv viii ix 1 ACKNOWLEDGEMENT ABSTRACT LIST OF TABLES LIST OF FIGURES INRODUCTION 1 1.1 INTRODUCTION 1 1.2 OBJECTIVE OF THE PROJECT 1 1.3 PROJECT SCOPE 1 1.4 ORGANIZATION OF PROJECT WORK 1 1.5 ORGANIZATION OF CHAPTERS 2 1.6 CONCLUSION 3 2 LITERATURE REVIEW 4 2.1 INTRODUCTION 4 2.2 MATERIAL HANDLING 4 2.3 MAJOR EQUIPMENTS IN MATERIAL HANDLING 5 2.4 CONVEYOR SYSTEMS 6 2.4.1 Pneumatic systems for material inspection 10
  • 5. vi 2.5 CONCLUSION 11 3. DESIGN CALCULATIONS 12 3.1. INTRODUCTION 12 3.2. REQUIRED CALCULATIONS 12 3.3. CONCLUSION 22 4. ASSEMBLY AND PART DRAWINGS 23 4.1. INTRODUCTION 23 4.2. 2D DIAGRAM 23 4.3. PART DIAGRAMS 24 4.4. ASSEMBLY DRAWING 29 4.4 CONCLUSION 30 5. SYSTEM DESIGN 31 5.1. INTRODUCTION 31 5.2. MODEL OF THE SETUP 31 5.3. CONCLUSION 34 6. PROCESS SHEET 35 6.1. INTRODUCTION 35 6.2. COMPONENT SPECIFICATIONS 35
  • 6. vii 6.2.1 Project Specification 35 6.2.2 Components of Pneumatic system 36 6.2.3 PLC Specification 38 6.2.4 Programming Logic Controller 39 6.3 PROCESS FLOW CHART 40 6.4 CONCLUSION 41 7 PLC PROGRAMMING 42 7.1 INTRODUCTION 42 7.2 PLC PROGRAMMING 42 7.3 LADDER LOGIC DIAGRAM 43 7.4 CONCLUSION 44 8 COST OF THE PROJECT 45 8.1 INTRODUCTION 45 8.2 COST TABLE 45 8.3 CONCLUSION 46 9 FABRICATION OF THE PROJECT 47 9.1 INTRODUCTION 47 9.2 FABRICATION PHOTOS 47 9.3 CONCLUSION 50 10 CONCLUSION 51 10.1 INTRODUCTION 51
  • 8. viii LIST OF TABLES TABLE TITLE PAGE NO. NO. 6.1 Component specification 35 6.2 PLC specification 38 8.1 Cost estimation 45
  • 9. ix LIST OF FIGURES FIGURE TITLE PAGE NO. NO. 1.1 2 3.1 17 3.2 18 3.3 20 4.2.1 23 4.3.1 24 4.3.2 25 4.3.3 26 4.3.4 27 4.3.4 28 4.4.1 29 4.5 30 5.2.1 31 5.2.2 32 6.1 40 7.3 44 9.2.1 Organization of chapters Bending moment of beam 1 and 2 Bending moment of beams 3 and 4 Bending moment of beams 5 and 6 2D Diagram Bearing Pneumatic cylinder Supporting Column Roller Conveyor belt Assembly view 3D View Circuit Diagram Working model of PLC Process flowchart Ladder logic diagram Conveyor model 47
  • 10. 9.2.2 Conveyor model 48 9.2.3 Conveyor model 49 9.2.4 Conveyor model 49
  • 11. ACKNOWLEDGEMENT At this juncture, we take the opportunity to convey our sincere thanks and gratitude to the management of the college for providing all the facilities to us.
  • 12. ABSTRACT In this project “Material Inspection and Sorting Conveyor", instead of using manual inspection here we are introducing the automatic system by using the pneumatic comparators. The sensors are used to measure the material dimensions and this signal is given to control Unit. The control unit gives the appropriate signal to the pneumatic cylinder. In this type of conveyor sensors are used to measure the dimensions of parts placed over it and a pneumatic cylinder is placed next to the sensor which will remove the detective parts.By using this system,we completly eliminate manual work and reduce inspection time and also increase production rate.
  • 13. 1 CHAPTER 1 INTRODUCTION 1.1 INTRODUCTION Material Inspection and Sorting Conveyor uses automatic inspection instead of the manual system by using the pneumatic comparators. The sensors are used to measure the material dimensions and this signal is given to control Unit. The control unit gives the appropriate signal to the pneumatic cylinder. 1.2 OBJECTIVES OF THE PROJECT To design and fabricate the material inspection and sorting conveyor which is capable of inspecting components without human intervention with the help of pneumatic systems. 1.3 PROJECT SCOPE Basically ,this project is to achieve the objective. 1.Focus on implementing automation in industrial field. 2.Focus on reducing labours. 3.Focus on making low cost machine for material inspection. 1.4 ORGANIZATION OF PROJECT WORK This project work is compiled in 7 chapters. The organization of the chapter is explained in the figure 1.1, Chapter 1 introduces the objective, the organization and the flow of process in which the project work is executed. Chapter 2 consists of literature review. Chapter 3 consists of assembly drawing and part diagrams of the component used and working principle. Chapter 4 explains the process of the component used and working principle. Chapter 5 explains the commissioning and Chapter 6 explains the cost estimation followed by the conclusion and reference.
  • 14. 2 1.5 ORGANISATION OF CHAPTERS ! Fig 1.1 Organisation of chapters
  • 15. 3 1.6 CONCLUSION The objective of this project work and the problem statement have been framed for the “Design and fabrication of automated material inspection and sorting conveyor” has been organized. Thus, the work from scratch to the completion of the project is explained in the further chapters.

  • 16. 4 CHAPTER 2 LITERATURE REVIEW 2.1 INTRODUCTION Before starting this project, it is important to research existing machines and the technologies used in them. This will help us understand any existing problems and try to find solutions for these problems in such a way that it can be implemented in our project. Going through the literature also helps us understand the practical outcomes of the project and how to attain the required outcomes. 2.2 MATERIAL HANDLING In the process or manufacturing industry, raw materials need to be transported from one manufacturing stage to another. Material handling equipment are designed such that they facilitate easy, cheap, fast and safe loading and unloading with least human interference. For instance, belt conveyor system can be employed for easy handling of materials beyond human capacity in terms of weight and height. Different methods such as fork lifting, use of bucket elevators, conveyors systems, crane, etc. has been identified for lifting or transporting bulk materials or products from one place to anothern the manufacturing industries depending on the speed of handling, height of transportation, nature, quantity, size and weight of materials to be transported.It is easier, safer, faster, more efficient and cheaper to transport materials from one processing stage to another with the aid of material handling equipment devoid of manual handling. Handling of materials which is an important factor in manufacturing is an integral part of facilities design and the efficiency of material handling equipment add to the performance level of a firm. Conveyor systems are durable and reliable in materials transportation and warehousing. Based on
  • 17. 5 different principles of operation, there are different conveyor systems namely gravity, belt, screw, bucket, vibrating, pneumatic/hydraulic, chain, spiral, grain conveyor systems, etc. The choice however depends on the volume to be transported, speed of transportation, size and weight of materials to be transported, height or distance of transportation, nature of material, method of production employed. Material handling equipment ranges from those that are operated manually to semi- automatic systems. [1] Material handling involves movement of material in a manufacturing section. It includes loading, moving and unloading of materials from one stage of manufacturing process to another. A belt conveyor consists of an endless and flexible belt of high strength with two end pulleys (driver and driven) at fixed positions supported by rollers.Pulleys are used for providing the drive to the belt through a drive unit gear box powered by an electric motor. It also helps in maintaining the proper tension to the belt. The drive imparts power to one or more pulleys to move the belt and its loads. Materials are transported over the required distance as a result of friction generated between the roller surface and the moving belt set in motion by a rotating pulley (drive pulley). The other pulley (driven or idler pulley) acts as a wheel around which the material rotates and returns in a continuous process. Continuous processes are characterized by non-stop motion of bulk or unit loads along a path without halt for loading and unloading. 2.3 MAJOR EQUIPMENTS IN MATERIAL HANDLING Transport Equipment is an equipment used to move material from one location to another (e.g., between workplaces, between a loading dock and a storage area, etc.). The major subcategories of transport equipment are conveyors, cranes, and industrial trucks. Material can also be transported manually using no equipment. Positioning Equipment is used to handle material at a single
  • 18. 6 location (e.g., to feed and/or manipulate materials so that are in the correct position for subsequent handling, machining, transport, or storage). Unlike transport equipment, positioning equipment is usually used for handling at a single workplace. Material can also be positioned manually using no equipment. Unit Load Formation Equipment is used to restrict materials so that they maintain their integrity when handled a single load during transport and for storage. If materials are self-restraining (e.g., a single part or interlocking parts), then they can be formed into a unit load with no equipment.[2] Storage Equipment is used for holding or buffering materials over a period of time. Some storage equipment may include the transport of materials (e.g., the S/R machines of an AS/RS, or storage carousels). If materials are block stacked directly on the floor, then no storage equipment is required. 2.4 CONVEYOR SYSTEMS Conveyor systems have been used for decades to transport bulk and unit loads.They have proved their worth everywhere because belt conveyor installations can be adapted to meet nearly all local conditions.They are work safe and essential. The demand for ever increasing capacities and ever longer conveying lengthshas accelerated the development of the belt conveyor technique, new materials are being developed, new conveying systems are being planned and tested especially those having regard to the environment. A conveyor system is a common piece of mechanical handling equipment that moves materials from one location to another. Conveyors are especially useful in applications involving the transportation of heavy or bulky materials. Conveyor systems allow quick and efficient transportation for a wide variety of materials, which make them very popular in the material handling and packaging industries. They also have popular consumer applications, as they are often
  • 19. 7 found in supermarkets and airports, constituting the final leg of item/ bag delivery to customers. Many kinds of conveying systems are available and are used according to the various needs of different industries. There are chain conveyors (floor and overhead) as well. Chain conveyors consist of enclosed tracks, I-Beam, towline, power & free, and hand pushed trolleys. Conveyor systems are commonly used in many industries, including the Mining, automotive, agricultural, computer, electronic, food processing, aerospace, pharmaceutical, chemical, bottling and canning, print finishing and packaging. Although a wide variety of materials can be conveyed, some of the most common include food items such as beans and nuts, bottles and cans, automotive components, scrap metal, pills and powders, wood and furniture and grain and animal feed. [3] Many factors are important in the accurate selection of a conveyor system. It is important to know how the conveyor system will be used beforehand. Some individual areas that are helpful to consider are the required conveyor operations, such as transportation, accumulation and sorting, the material sizes, weights and shapes and where the loading and pickup points need to be. A conveyor system that is designed properly will last a long time with proper maintenance. Here are six of the biggest problems to watch for in overhead type conveyor systems including I-beam monorails, enclosed track conveyors and power and free conveyors. Overhead conveyor systems have been used in numerous applications from shop displays, assembly lines to paint finishing plants and more. Poor take-up adjustment: this is a simple adjustment on most systems yet it is often overlooked. The chain take-up device ensures that the chain is pulled tight as it leaves the drive unit. As wear occurs and the chain lengthens, the take-up extends under the force of its springs. As they extend, the spring force becomes less and the take-up has less effect. Simply compress the take-up springs and your problem goes away. Failure to do this
  • 20. 8 can result in chain surging, jamming, and extreme wear on the track and chain. Take-up adjustment is also important for any conveyor using belts as a means to power rollers, or belts themselves being the mover. With poor-take up on belt-driven rollers, the belt may twist into the drive unit and cause damage, or at the least a noticeable decrease or complete loss of performance may occur. In the case of belt conveyors, a poor take-up may cause drive unit damage or may let the belt slip off of the side of the chassis.Lack of lubrication: chain bearings require lubrication in order to reduce friction. The chain pull that the drive experiences can double if the bearings are not lubricated. This can cause the system to overload by either its mechanical or electrical overload protection. On conveyors that go through hot ovens, lubricators can be left on constantly or set to turn on every few cycles. Contamination like paint, powder, acid or alkaline fluids, abrasives, glass bead, steel shot, etc. can all lead to rapid deterioration of track and chain. Ask any bearing company about the leading cause of bearing failure and they will point to contamination. Once a foreign substance lands on the raceway of a bearing or on the track, pitting of the surface will occur, and once the surface is compromised, wear will accelerate. Building shrouds around your conveyors can help prevent the ingress of contaminants. Or, pressurize the contained area using a simple fan and duct arrangement. Contamination can also apply to belts (causing slippage, or in the case of some materials premature wear), and of the motors themselves. Since the motors can generate a considerable amount of heat, keeping the surface clean is an almost-free maintenance procedure that can keep heat from getting trapped by dust and grime, which may lead to motor burnout. Product handling in conveyor systems that may be suited for a wide variety of products, such as those in distribution centers, it is important that each new product be deemed acceptable for conveying before being run through the materials handling equipment. Boxes that are too small, too large, too heavy, too light, or too awkwardly shaped may not convey, or may cause
  • 21. 9 many problems including jams, excess wear on conveying equipment, motor overloads, belt breakage, or other damage, and may also consume extra man- hours in terms of picking up cases that slipped between rollers, or damaged product that was not meant for materials handling. If a product such as this manages to make it through most of the system, the sortation system will most likely be the affected, causing jams and failing to properly place items where they are assigned. It should also be noted that any and all cartons handled on any conveyor should be in good shape or spills, jams, downtime, and possible accidents and injuries may result. Drive train, notwithstanding the above, involving take-up adjustment, other parts of the drive train should be kept in proper shape. Broken O-rings on a Lineshaft, pneumatic parts in disrepair, and motor reducers should also be inspected. Loss of power to even one or a few rollers on a conveyor can mean the difference between effective and timely delivery, and repetitive nuances that can continually cost downtime. Bad belt tracking or timing in a system that uses precisely controlled belts, such as a sorter system, regular inspections should be made that all belts are traveling at the proper speeds at all times. While usually a computer controls this with Pulse Position Indicators, any belt not controlled must be monitored to ensure accuracy and reduce the likelihood of problems. Timing is also important for any equipment that is instructed to precisely meter out items, such as a merge where one box pulls from all lines at one time. If one were to be mistimed, product would collide and disrupt operation. Timing is also important wherever a conveyor must "keep track" of where a box is, or improper operation will result.Since a conveyor system is a critical link in a company's ability to move its products in a timely fashion, any disruption of its operation can be costly. Most downtime can be avoided by taking steps to ensure a system operates at peak performance, including regular inspections, close monitoring of motors and reducers, keeping key parts in stock, and proper training of personnel.
  • 22. 10 2.4.1 PNEUMATIC SYSTEMS FOR MATERIAL INSPECTION Pneumatic systems form the most primitive and distinct class of mechanical control engineering. They are classified under the term 'Fluid Power Control', which describes any process or device that converts, transmits, distributes or controls power through the use of pressurized gas or liquid. In a pneumatic system, the working fluid is a gas (mostly air) which is compressed above atmospheric pressure to impart pressure energy to the molecules. This stored pressure potential is converted to a suitable mechanical work in an appropriate controlled sequence using control valves and actuators. Pneumatic systems are well suited for the automation of a simple repetitive task. The working fluid is abundant in nature and hence the running and maintenance cost of these systems are exceptionally low. All fluids have the ability to translate and transfigure and hence pneumatic systems permit variety of power conversion with minimal mechanical hardware. The technology of pneumatics deals with study of behavior and application of compressed air. Today air operated tools and accessories are a common sight in each every industry, not only in the technologically advanced countries but even in countries where industrial activities are still at the stage of sheer infancy. With introduction of pneumatics in the manufacturing process, the industry is benefited automation which if judiciously used; many bring down the cost of production to a much lower level. Nowadays compressed air is used in every walk of industrial life, starting with pneumatic cranes to the use of air in the brake system of automobiles, railways coaches, wagons, printing presses, and what not. The following features are notable for the reason •Wide availability of air •Compressibility of air • Easy transportability of compressed air in pressure vessels • Fire proof characteristics of the medium
  • 23. 11 • Simple construction of pneumatics elements and easy handling •High degree of controllability of pressure, speed and force. •Possibility of easy but reasonably reliable remote controlling •Easier maintenance •Explosion proof characteristics of the medium •Comparatively cheaper in cost than other system. 2.5 CONCLUSION Thus, research was done regarding this project on various sources of literature. The many methodologies were studied and this information has helped to complete the project successfully.
  • 24. 12 CHAPTER 3 DESIGN CALCULATIONS 3.1 INTRODUCTION This chapter will include the design calculations required for the automated material inspection and sorting conveyor. 3.2 REQUIRED CALCULATIONS: WEIGHT: Mechanical Components: Roller weight = 850g Belt weight = 500g Conveyor platform = 2kg Supporting columns=1.5kg Pneumatic cylinder =1kg Total weight of the mechanical components = 5.85kg Electrical and electronic components: Motor weight = 250g Servo valve = 150g Servo motor =100g Regulator unit =150g Control panel = 650g Miscellaneous = 200g Proximity sensor=100g Weighing sensor=250g Jam 1,2 =100g Total weigth of the electrical and electronic components=1.95kg Total weight of the conveyor= 7.80 kg Force on the Conveyor = 0.4*9.81 = 3.924 N
  • 25. 13 ~ 4 N Force is maximum when link is in horizontal position Shaft Diameter of DC motor of above application =12 mm Radius = 6 mm Torque required = Force* Radius = 4*6 = 24 Nmm = 0.25 kgcm BELT DIMENSION, CAPACITY AND SPEED: Belt length is dependent on both the pulley diameters and centre distances. V=d×PI(1) V= Belt speed; d = diameters of rollers; and Capacity is the product of speed and belt cross sectional area Generally, belt capacity (kg/sec) is given as: B.C = 3.6 × A × 3.14× V A = belt sectional area (m2); V = belt speed (m/s) ..(2) The mass of material Mm (live load) per meter (kg/m) loaded on a belt conveyor is given as: Where, V = belt speed (1.25 m/s). Mm =0.889 kg. The magnitude of belt speed V (m/s) can be determined from equations 1, 2, 3 or 6 and can as well be gotten from the catalogue for standard belt. Belt speed v (m/s) depends Mm= C/(3.6*v)…(3) c = Conveyor capacity (4 tones/hr); and
  • 26. 14 V = belt speed (1.25 m/s). Mm =0.889 kg. CAPACITY OF THE CONVEYOR: C = cT*1000*cf*v / 1000…(4) C = Capacity in tones/hr of a belt conveyor cT = Capacity of td belts for 3 roll equal le; cf = Capacity factor (1.08); and V = Belt speed in m/s (1.25) = 4 tonnes/hr ROLLER DIAMETER: n = (V *1000 *60 )/D*3.14 n = no of revolution per minute; D = roller diameter (mm); and V = belt speed (m/s) From Equation (6), the no of revolution per minute n = 220 rpm The inclination angle is 100, the conveyor length is 100 m, and the conveyor height is 10 m. Belt basic length = 2 × length along conveying route ..(8) From Equation (8), basic belt length = 2 × 14 = 28 m The roll diameter for belt is given as, D = sqrt((d*d)+(0.001273*L*G)) Where,
 D = overall diameter (m); D = core diameter (m);
 L = Belt length (m); and G = Belt Thickness (mm) The length of a belt on roll is given as: L = (d+((D-d)/2)*3.14*N)…….(10)
  • 27. 15 Where,
 D = outside diameter of the roll (m); d = diameter of the roll centre (m); N = no.of.wraps of the belt
 BELT POWER AND TENSION: The power Pp (kW) at drive pulley drum is Pp = Fu*V /1000 Where, Fu = Total tangential force at the periphery of the drive pulley (N); V = Belt speed (1.25 m/sec); and Fu = Pp*V /1000 Pp = power required for conveyor (kW); where , C = conveyor capacity (4 tones/hr) = (3.9375 kg/sec); and L = Lift(1.5m) P = 3.7kW. Te = Total empty friction + Load friction + load slope tension = 1.141KN The belt power (kW) is given as Pb =Te *V Te = effective tension (1.141 KN) V = Belt speed (1.25 m/sec) Pb = 1.43 kW σc < σt Therefore, design is safe. T = 30 kgcm = 3 Nm ρ = (2π*30*3)/260 = 3π
  • 28. 16 = 10 N “Link material is mild steel” l = 160 mm W = 150 g σc = (0.1)/(16*b) COLUMN : Area (A) = (20*20) – (16*16) = 144 mm2 Length (L) = 240 mm2 = 0.240m For column both the ends are fixed, so n=4 Critical load (Pc) = (nπ2EI)/(L2) For mild steel, (E) = 200*109 GPa Area moment of inertia,I = (a04- ai4)/12 = (204-164)/12 = 7782*10-12 kgcm Pc = (4*3.142*200*109*7872*10-12)/(0.24)2 Pc = 1077 KN > 26N Hence design is safe. l = 250 mm Area moment of inertia,I = (a14- a24)/12 = (204-164)/12 = 7782 mm4 Sectional area,A = 144 mm2 K1 = √(7872144) = 7.35 Yield stress,σy/2 = nπ2E/(1/k)2 297/2 = 4*π2*200*1000/(1/k)2 Yield stress of mild steel,σy = 297 Mpa(Design data book)
  • 29. 17 K2 = 0.00433 K1 > K2 So, the screw should be long column. BENDING MOMENT Ra = Rb = (5*9.81)/2 = 24.53 N Mc = Rb*110 = 24.53*110 = 2697.75 Nmm ! Fig 3.1 Bending Moment of beams 1 and 2

  • 30. 18 RA = RB = 1.23N Mc = RB*110 = 1.23*110 = 134.89 Nmm ! Fig 3.2 Bending Moment of beams 3 and 4
  • 31. 19 Weight of Beam 1 = 5.3 Kg = 51.993 N ~ 52 N Weight of Beam 2 = 5.3 Kg = 51.993 N ~ 52 N Weight of Beam 3 = 0.55 Kg = 5.395 N ~ 5.4 N RA + RB = 54.7 N RA = 54.7 N – RB MBF = 0 0 = (26*120) – (RB *310) + (26*108) + (2.7*66) – (RA *26) 26 RA *310 RB = 6760 + 178.2 + 2808 = 9746.2 N MRB = 0 0 = (26*50) – (26*201) + (2.7*242) – (RA *282) 282 RA = 1300 + 5252 + 653.4 RA = 25.55 N 310 RB = 9081.97 N RB = 29.29 N
  • 32. 20 ! Fig 3.3 Bending Moment of beams 5 and 6 WELDING CLAMPS : Area for welding (A) = (50*30) – (40*20) = 700 mm2 Height of welding = 5 mm Then Volume of weld (V) = (700*5)/2 = 1750 mm3 Density of alloy carbon steel = 7.86 gm/cm3 Weight of weld steel = v*ρ = 1750*7.86*103 = 83.16 g σc = 6*Mb/l*h2 Mb = F*r = 30*10
  • 33. 21 = 300 Nmm Length,l = 50 mm Height,h = 30 mm σc = 6*300/50*302 = 1.2 N/mm2 σt = 242N/mm2 σc < σt Therefore, design is safe. L CLAMP : Ra = 600*10 = 6000 Nmm2 = 600 kgmm Area moment of inertia (I) = (b*d3)/12 = (20*103)/12 = 1666.67 mm2 Bending stress, σ/y = M/I σ = My/I = 600*5/1666.67 = 1.8 kg/mm2 For steel yield strength is, 25 kg/mm2 > 1.8 kg/mm2 Hence, design is safe. For angle from horizontal of 60° Mass flow % = 25 % ,Sheet metal material is chosen. σty = 290 N/mm2 σ = 50/32*t = 29 N/mm2 t = 0.6 to 1 mm σ = 500/32*8 = 1.95 N/mm2 Critical load,Pcr = (nπ2EI)/(1/K)2 = (4*π2*200*103*144)/(1/7.35)2
  • 34. 22 = 6.136*1010 N Calculated load,Pcal = 26 N Pcr > Pcal Hence, Design is safe. 3.3 CONCLUSION Thus, the design calculations for the machine were done. These calculations were done keeping in mind the dimensional restrictions for this project, along with economic views. The values are well within the limit and the design is safe and accurate.

  • 35. 23 CHAPTER 4 ASSEMBLY AND PART DRAWINGS 4.1 INTRODUCTION This chapter consists of assembly drawings and part drawings of the main components of the automated material inspection and sorting conveyor. The drawings are designed using Solidworks to generate the 2D and 3D models of the system and its components. Based on the design calculations in the previous chapter the drawings are designed respective of its dimension. 4.2 2D DIAGRAM Fig 4.2.1 2D Diagram
  • 36. 24 Fig 4.2.1 represents the 2D Dimensional of automated material inspection and sorting conveyor. 4.3 PART DIAGRAMS Fig 4.3.1 Bearing Fig 4.2.1 represents the 2D Dimensional view of bearing used in automated material inspection and sorting conveyor with the specific dimensions drawn using Solid works software.
  • 37. 25 Fig 4.3.2 Pneumatic cylinder Fig 4.3.2 represents the 2D Dimensional view of pneumatic cylinder used in automated material inspection and sorting conveyor with the specific dimensions drawn using Solid works software.
  • 38. 26 Fig 4.3.3 Supporting column Fig 4.3.3 represents the 2D Dimensional view of supporting column used in automated material inspection and sorting conveyor with the specific dimensions drawn using Solid works software.
  • 39. 27 Fig 4.3.4 Roller Fig 4.3.4 represents the 2D Dimensional view of roller used in automated material inspection and sorting conveyor with the specific dimensions drawn using Solid works software.
  • 40. 28 Fig 4.3.5 Belt Conveyor Fig 4.3.3 represents the 2D Dimensional view of belt conveyor used in automated material inspection and sorting conveyor with the specific dimensions drawn using Solid works software.
  • 41. 29 4.4 3D SOLID MODEL Fig 4.4 Assembly View Fig 4.4 represents the assembly view of automated material inspection and sorting conveyor with the specific dimensions drawn using Solid works software.
  • 42. 30 4.5 ASSEMBLY DRAWING Fig 4.5 Assembly Diagram 4.4 CONCLUSION Thus the assembly drawings and part drawings of the main components of the automated material inspection and sorting conveyor were designed using Solidworks to generate the 2D and 3D models of the system and its components. Based on the design, the machine is fabricated.

  • 43. 31 CHAPTER 5 SYSTEM DESIGN 5.1 INTRODUCTION This chapter consists of the complete system architecture of the electronic components. The system architecture shows the layout of the unit and the communication cables used for interconnection of various parts of the system. 5.2 MODEL OF THE SETUP Fig 5.2.1 Circuit Diagram
  • 44. 32 The circuit diagram consists of three units- sensing units, controlling units, sorting units.The sensing units consists of ultrasonic level sensor and an inductive proximity sensor.These are the inputs and the pneumatic valves are the outputs based on the inputs the PLC processes the input and HMI controls the outputs based on the logic and the pneumatic valves are been actuated and the sorting mechanism is been carried out. The entire mechanism can be visualized at the touch screen HMI panel. Fig 5.2.2 Working module
  • 45. 33 A programmable logic controller (PLC) or programmable controller is a digital computer used for automation of electromechanical processes, such as control of machinery on factory assembly lines, amusement rides, or lighting fixtures. PLCs are used in many industries and machines, such as packaging and semiconductor machines. Unlike general- purpose computer, the PLC is designed for multiple inputs and output arrangements, extended temperature ranges, immunity to electrical noise, and resistance to vibration and impact. A very commonly used method of programming PLC’s is based on the use of ladder diagrams. Writing a program is the equivalent to drawing a switching circuit. Circuits are connected as horizontal lines, that is, the rungs of the ladder, between these two vertical lines. In drawing a ladder diagram, certain conventions are adopted. Many types of proximity sensors have been built the simplest sensors are proximity switches capable of merely detecting the presence or absence of an object in the sensors proximity. More complex proximity sensors have the capability of determining continuous three dimensional positions and other information such as intensity and orientation. Different proximity sensors employ various media including magnetic field, electric filed, electric field, air pressure, ultrasonic sound, and light recent advance in inexpensive electro-optical component also has made optical methods attractive.
  • 46. 34 5.3 CONCLUSION Thus the system design has been illustrated by providing the architecture of electronic process of automated material inspection and sorting conveyor.
  • 47. 35 CHAPTER 6 PROCESS SHEET 6.1 INTRODUCTION The prime motive of the ‘PROCESS SHEET’ chapter is to provide the fine details about the components being used, their material and quantity of each component involved in the project. It also illustrates the processing steps to complete the project. 6.2 COMPONENT SPECIFICATIONS 6.2.1 Project Specification Table 6.1 Component specification PARAMETER TYPE SIEMENS PLC S7-200 Pneumatic systems As required Sensors Weighing sensors and Proximity Sensors Connecting wires As required Valves Servo valves DC motor 12 volts
  • 48. 36 6.2.2 COMPONENTS OF PNEUMATIC SYSTEM AIR COMPRESSOR Though not directly connected to the pneumatic system, the air compressor plays a vital role in the overall system performance. Various types of air compressors are used in the industry. But positive displacement compressors are more popular. The air receiver is important equipment in the compressor family. For uninterrupted supply of compressed air, receiver with to optimum size is to be selected. FRL UNIT The FRL unit consists of the following separate components, filter, regulator and lubricator. They are packaged to supply the cleaned lubricated and regulated air to the actuator. FILTER Even very small particle containing in air may be produce wear by lapping action in the parts. Therefore the air is filtered to remove dirt, rest particles and other air borne matter in line. The air is filtered before entering the compressor. However, the passage of the air stream through the distributor system often contaminates it with oxidation deposits on the sides of the steel piping. REGULATOR Independent pressure control is necessary for air distribution in pneumat ic circuitry. Pneumatic circuitry uses an outlet side piloted pressure reducing valve to limit pressure only to desired circuit these specialized pneumatic pressure reducing valves are known as regulators.
  • 49. 37 LUBRICATOR Pneumatic systems are not self lubricat ing. Pneumatic components need lubrication for its smooth functioning. Therefore a lubricator is used in the FRL unit to add a small amount of oil to the dry air. PNEUMATIC ACTUATORS Pneumatic cylinders offer a straight rectilinear motion to mechanical elements. Cylinders are classified as light, medium, heavy duty with respect to their application. Selection of materials for cylinder depends greatly on this factor. Functionally cylinders may be single or double acting. They may be further classified as diaphragm cylinder, duplex cylinder, through rod cylinder etc. end position cushioning of cylinder as certain times may be of almost important. PNEUMATIC VALVES The pneumatic energy is regulated and controlled by pneumatic valves. Functionally the valves are divided into four major groups, viz. directional control, floe control, pressure control, non return and special type va lves. As pre construction the valves are sub grouped as seat valves sliding or spool valves. Both these of constructions are frequently used in pneumatic valves. However the spool valves are easier to manufacture. Valves are actuated in various methods, viz. manually, mechanically, electrically, pneumatically and by various combined mode of actuation. Specially designed valves like quick exhaust time delay shuttle and twin pressure valves are used to impart various special functions to pneumatic circuits.
  • 50. 38 PLC SPECIFICATION Fig 6.2 Table 6.2 S7-200 CPU specification
  • 51. 39 6.2.3 PROGRAMMABLE LOGIC CONTROLLER A programmable logic controller is a digital computer used for automation of electromechanical processes. A programmable logic controller (PLC) or programmable controller is a digital computer used for automation of electromechanical processes, such as control of machinery on factory assembly lines, amusement rides, or lighting fixtures. PLCs are used in many industries and machines, such as packaging and semiconductor machines. Industrial PLC describes the computing unit of any industrial automation system and therefore need to meet several challenging requirements such as high reliability, environmental noise and influence immunity and also enhanced protection classes (e.g. water-resistant and dust sealed). PLCs also satisfy the needs of continuous 24 hours/7 days operation and availability over a wide environmental temperature range as well as real-time operation capability and security and safety enhancements. The input/output arrangements may be built into a simple PLC, or the PLC may have external I/O modules attached to a computer network that plugs into the PLC. The communications interface is used to receive and transmit data on communication networks from or to other remote PLCs. [4] It is concerned with such actions as device verification, data acquisition, synchronization between user applications and connection management.Some of the advantages of using PLC include: • Programming the PLC is easier than wiring the relay control panel • PLC takes less floor space then relay control panels. • Maintenance of the PLC is easier, and reliability is greater. • PLC can be connected to the plant computer systems more easily than relays.

  • 52. 40 6.3 PROCESS FLOWCHART Fig 6.1 Process flow chart Switch on the system Place the materials on the conveyor Sensing using PLC and sensors Inappropriate materials are pushed to tray Correct material follows through the conveyor Unloading.components
  • 53. 41 6.4 CONCLUSION Thus the process sheet has been illustrated by tabulating all the process took place during the design of automated material inspection and sorting conveyor. The tables contains the product specification used at this level of fabrication.
  • 54. 42 CHAPTER 7 PLC PROGRAMMING 7.1 INTRODUCTION This chapter involves the PLC programming of the material inspection conveyor by using ladder logic diagram. 7.2 PLC PROGRAMMING The PLC programming is done by using ladder logic diagram using ABB control builder plus software. Ladder logic is widely used to program PLCs, where sequential control of a process or manufacturing operation is required. Ladder logic is useful for simple but critical control systems or for reworking old hardwired relay circuits. As programmable logic controllers became more sophisticated it has also been used in very complex automation systems. Often the ladder logic program is used in conjunction with an HMI program operating on a computer workstation.[5] Ladder logic can be thought of as a rule-based language rather than a procedural language. A "rung" in the ladder represents a rule. When implemented with relays and other electromechanical devices, the various rules "execute" simultaneously and immediately. When implemented in a programmable logic controller, the rules are typically executed sequentially by software, in a continuous loop (scan). By executing the loop fast enough, typically many times per second, the effect of simultaneous and immediate execution is achieved, if considering intervals greater than the "scan time" required to execute all the rungs of the program. Proper use of programmable controllers requires understanding the limitations of the execution order of rungs.
  • 55. 43 7.3 LADDER LOGIC Fig 7.3 Ladder logic diagram
  • 56. 44 7.4 CONCLUSION Thus the control of the automated material inspection and sorting conveyor programming is done using PLC programming.
  • 57. 45 CHAPTER 8 COST OF THE PROJECT 8.1 INTRODUCTION This chapter lists the approximate cost of various components used in the project. 8.2 COST TABLE Table 8.1 Cost estimation Material/material type Quantity Cost 1 Roller(mild steel) 5 5600 2 Stand(Iron) 1 3000 3 Pneumatic cylinders 2 6000 4 Servo valve 1 1500 5 Belt 1 4000 6 DC Motor 1 3500 7 Tray(plastic) 3 3000 8 Bearing(roller) 12 18000 9 Air filter unit 1 3500 Total 48100
  • 58. 46 8.3 CONCLUSION Thus the components were chosen with cost as a parameter to optimize the development of the system.
  • 59. 47 CHAPTER 9 FABRICATION OF THE PROJECT 9.1 INTRODUCTION This chapter lists the fabrication photos taken while doing the fabrication of material inspection and sorting conveyor. 9.2 FABRICATION PHOTOS Fig 9.2.1 Conveyor model
  • 61.
  • 62. 50 9.3 CONCLUSION Thus the material inspection and sorting conveyor which is capable of inspecting components without human intervention was fabricated successfully.
  • 63. 51 CHAPTER 10 CONCLUSION 10.1 INTRODUCTION Thus the material inspection and sorting conveyor which is capable of inspecting components without human intervention is designed and fabricated with the help of pneumatic systems. 10.2 FUTURE SCOPE OF THE PROJECT By producing such system, the scope is in the field of Manufacturing ,identification of suitable solution, evaluation processes , design the proposal, to build the prototype .Also we can use such system with some modification for various types of inspection such as • Inspection Parameter • Diameter, hole diameter • Height • Thickness • Surface defect • Crack, burr • Roundness • Minor and major diameter • Chamfer angle etc. 10.3 CONCLUSION The project is successfully completed and tested. All the specified requirements were fulfilled upon completing the project
  • 64. 52 REFERENCES 1. Sambathkumar N. and Siva kumar K,‘‘Design and Fabrication of Material Inspection Conveyor”,Research paper in International Journal of Mechanical Engineering and Robotics Research, April 2014 2. Aniket A Jagtap ,“Design of Material Handling Equipment’,Research paper in International Journal of Mechanical Engineering and Robotics Research,March 2015 3. Anath K N and Rakesh V, “Design and Selecting Proper Conveyor Belt”, Int. Journal of Advanced Technology”, Vol. 4, No. 2, pp. 43-49,2015 4. Petruzella, F. D, “Programmable Logic Controllers, McGraw Hill, 2005”. 5. Yang, G., Rasis, Y “Teaching PLC in Automation – A Case Study”, ASEE Annual Conference &Exposition,June 2005 6.Roberts, A.W., Hayes, J.W. and Scott, 0.J.,"Optimum Design of Continuous Conveyors". Bulk Solids Handling, Vol. 1, No. 2, 1981. 7. Harrison, A., "Flexural Behaviour of Tensioned Conveyor Belts", Mech.Eng.Trans. IE (Aust.), Vol. MES (1983), No. 3. 8. Harrison, A. and Roberts, A.W., "Technical Requirements for Operating Conveyor Belts at High Speed", Bulk Solids Handing, Vol. 4 (1984), No. 1, pp.99-104. 9. Harrison, A., "Criteria for Minimising Transient Stress in Conveyor Belts", Mech.Eng.Trans IE(Aust), Vol. ME8 (1983), No. 3, pp. 129-134. 10. Roberts, A.W., Harrison, A. and Hayes, J.W., "Economic Factors Relating to the Design of Belt Conveyors for Long Distance Transportation of Bulk
  • 65. 53 Solids", Int. Jnl. of Bulk Solids Handling, Vol. 5, No. 6, December 1985 (pp. 1 143-1149).
  • 66. 54 APPENDIX Fw = Force due to weight us = Friction coefficient ur = Rolling friction coefficient b = Rolling resistance W = Load or Weight of machine P = Force required for movement b = Distance of contact Ra,Rb = Reactive forces on beams Mc = Bending moment Mt = Torsional moment of shaft d = Diameter of shaft σ = Stress of link σc = Calculated stress σt = Maximum stress that can be withstand l = Length of link Pcr = Crippling load for column Pcal = Applied load for column E = Young’s Modulus I = Area moment of Inertia A = Area of cross section of column 1/k = Slenderness Ratio h = Height of welding Ď´ = Angle of inclination
  • 67. 55