SlideShare a Scribd company logo
1 of 34
Download to read offline
Unknowns, Systemic Risks and
Risk Prioritization
in Schedule Risk Analysis
Presented to APM
Value of Quantitative Risk Analysis (QRA)
Conference
London February 2016
David T. Hulett, Ph.D., FAACE
(c) 2016 Hulett & Associates, LLC 1
Secretary Rumsfeld’s use of
“Unknown Unknowns”
In February 2002 DOD Secretary Donald Rumsfeld stated:
“Reports that say that something hasn't happened are always
interesting to me, because as we know:
There are known knowns; there are things we know we know.
We also know there are known unknowns; that is to say we
know there are some things we do not know.
But there are also unknown unknowns -- the ones we don't
know we don't know.
And if one looks throughout the history of our country and other
free countries, it is the latter category that tend to be the
difficult ones.”
(source: http://en.wikipedia.org/wiki/There_are_known_knowns cited January 26,
2015)
2(c) 2016 Hulett & Associates, LLC
Uncertainty including Inherent Variability,
Estimating Error, Estimating Bias
• Inherent variability in project activities that arise
because people and organizations cannot do things
reliably on plan
• Estimating error – attaches to all types of estimates
• Estimating bias – estimates may be slanted, usually
toward shorter durations, to make desired project
results
“There are No Facts About the Future”
3(c) 2016 Hulett & Associates, LLC
Lincoln Moses, Statistician and Administrator of Energy Information in the
US DOE 1977 Annual Report to Congress)
Uncertainty
• Uncertainty in schedule duration is similar to “common cause”
variation related to six sigma management, concepts developed
by Walter Shewhart and championed by Edwards Demming
• “Common cause variability is a source of variation caused by
unknown factors that result in a steady but random distribution
of output around the average of the data …. Common cause
variation is also called random variation, noise, non-controllable
variation … ” (http://www.isixsigma.com/dictionary/common-
cause-variation/ )
• Hence application of uncertainty alone establishes the earliest
date that risk mitigation can achieve even if individual risks were
fully mitigated
4
Example Schedule: Offshore Gas
Production Platform Project
(c) 2016 Hulett & Associates, LLC 5
Case Study On Application of
Uncertainty and Risk
6(c) 2016 Hulett & Associates, LLC
Offshore Gas Production Platform Construction project, 3+ years and $1.7 billion.
Using Polaris© from Booz Allen Hamilton
Correcting for Inherent Variability,
Estimating Error and Bias
• Schedule uncertainty exhibiting inherent variation, estimating
uncertainty and bias with ranges of .9, 1.05 and 1.3
• To replicate the estimated overall project ranges by using these
parameters for individual activities we need to correlate the
uncertainty
7(c) 2016 Hulett & Associates, LLC
Correlated durations
Uncorrelated durations
Without Correlation
P-80 duration is
113% of planned
With Correlation at
1.0 the P-80
duration is 116% of
planned
Variation Caused by Known Unknowns
• Project-specific risks are:
– Characterized by probability of occurring that is
usually less than 100%
– Represent “root causes” of variation in durations
– May be reducible by risk mitigation actions
• These are specified during risk interviews and
implemented with:
– Estimated probabilities
– Impact ranges (3-point estimates of multiplicative
factors called Risk Drivers”) if they occur
– The activities or cost elements they influence
8(c) 2016 Hulett & Associates, LLC
Project-Specific Risks, Pre-Mitigated
• Risk is similar to “special causes” in six sigma
• “… special cause variation is caused by known factors that
result in a non-random distribution of output…Special cause
variation is a shift in output caused by a specific factor such as
environmental conditions or process input parameters. It can
be accounted for directly and potentially removed...”
(http://www.isixsigma.com/dictionary/variation-special-
cause/)
• Hence, pre-mitigated risks are the subject of risk mitigation
workshops. The improvement from risk mitigation is limited
by the date determined by uncertainty alone
9
Applying Known Unknowns: Project-Specific
Risk Drivers to the Offshore Platform
10(c) 2016 Hulett & Associates, LLC
There are 8 project-specific Risk Drivers including one Organizational Risk Driver assigned to
all activities. Probability and impact multiplier ranges are specified, risks are assigned to
activities. A risk can affect many activities, and an activity can be affected by several risks.
Adding Project Specific Risk Drivers
(c) 2016 Hulett & Associates, LLC 11
Adding Project
Specific Risk Drivers
Uncertainty
correlated 1.0
Uncertainty not
correlated
Adding Project-Specific Risk Drivers increases
P-80 Duration to 125% of planned
Unknown Unknowns
May Not be Unknowable
• Interviews or workshops on risk often focus on
risks and uncertainties that are close-in or
actually happening now
– This myopia leads to insufficient consideration of
future risks
• It is arguable that some unknown unknowns are
not truly unknowable but just have not been
thought of yet
• Extra effort to focus on down-stream risks during
the risk interviews could improve our
understanding of risks, including making some of
these “Unknown Unknowns” known
12(c) 2016 Hulett & Associates, LLC
Add a Fourth Category
of “Unknown Knowns”
• Psychoanalytic philosopher Slavoj Zizek says that
beyond these three categories there is a fourth, the
unknown known, that which we intentionally refuse
to acknowledge that we know
• German sociologists Daase and Kessler (2007) agree
with a basic point of Rumsfeld in stating that the
cognitive frame for political practice may be
determined by the relationship between what we
know, what we do not know, what we cannot know,
but Rumsfeld having left out what we do not like to
know
13(c) 2016 Hulett & Associates, LLC
http://en.wikipedia.org/wiki/There_are_known_knowns, Cited 12/26/2015)
Risk Interviews vs. Risk Workshops (1)
• Risk Interviews provide a safe environment to discuss
both Unknown Unknowns and Unknown Knowns
• Specifically, Unknown Knowns
– We find that the Risk Register is always incomplete
– Many of the risk events found to be most important in
determining the schedule risk results are not in the Risk
Register at all
– These can be safely discussed in one-on-one interviews
where confidentiality is promised
• In these interviews new risks are discussed, whether
they are hurtful to the project or embarrassing or not
– Responding to open-ended questions, interviewees are
encouraged to talk about “the good, the bad and the ugly”
14(c) 2016 Hulett & Associates, LLC
Risk Interviews vs. Risk Workshops (2)
• We need to avoid the ostrich approach to risk management.
Identify, talk about and quantify the Unknown Knowns, the
“elephant in the room,” and tell unbiased results
• Risk interviews provide a confidential environment where
individuals can talk in depth without being afraid of being
embarrassed, pressured or subjected to “shoot the
messenger”
• Conversely, Risk Workshops often are places where social
pressures or group dynamics limit debate
– Groupthink – prefer unanimity, discourage dissent
– “Moses factor” – adopting influential person’s ideas
– Cultural Conformity – decisions match the group’s norms
15(c) 2016 Hulett & Associates, LLC
David Hillson and Ruth Murray-Webster, Understanding and Managing Risk Attitude 2005
Considering Systemic Risks
(c) 2016 Hulett & Associates, LLC 16
Compare what Risk Analysis Typically
Predicts vs. What Actually Happens
(c) 2016 Hulett & Associates, LLC 17
Source: John K. Hollmann, PE, “Reliable Risk Quantification for Project Cost and
Schedule”, AACE International webinar December 15, 2015
Incorporate Systemic Risks
into the Monte Carlo Simulation (MCS)
• Systemic Risks that include:
– Technical complexity, new technology challenging
– Scope not fully known
– Process definition not complete
– Megaproject complexity, size / duration, participants
– Project organization, e.g., joint venture, multiple EPCs
– Project management, scheduling and estimating
process, bias
• Some argue that these factors can be measured
and their impact on project success estimated
using parametric techniques
(c) 2016 Hulett & Associates, LLC 18
Inserting 3 Megaproject Systemic Risks
with Original Uncertainty
• Identifying the systemic risks and inserting them
with appropriately-large impacts allows us to:
– Specify the probability of occurrence
– Identify the risks for risk mitigation
• In this case study, these megaproject risks:
– May have interdependency issues between project
elements
– May have complex offshoring of supply chain and
even EPC contractors
– May have excessive schedule pressure “I want it
sooner”
(c) 2016 Hulett & Associates, LLC 19
Megaproject Systemic Risk Example
(c) 2016 Hulett & Associates, LLC 20
Individual Systemic Risks with Regular
Uncertainty Approximates Hollmann
(c) 2016 Hulett & Associates, LLC 21
Regular Uncertainty,
Project-specific Risks
Hollmann
Benchmarking
Uncertainty
Regular Uncertainty,
Project-specific and
Megaproject
Systemic Risks
Parameters for specific Megaproject Systemic Risks are challenging, need to be selected
based on historical data
We need to be sure to include the systemic risks with the right probability and impact ranges
based on data into the Monte Carlo simulation
Results for
Total Project Duration from MCS
(c) 2016 Hulett & Associates, LLC 22
Some suggest that
megaprojects that
come in at 25% or less
(cost) over the
sanction budget are
considered successful.
This curve shows that
about 50% do so.
The P-80 duration is
1,913 days about 61%
overrun of schedule
Results are Similar to those for Cost
Provided by IPA
(c) 2016 Hulett & Associates, LLC 23
“Quantifying Estimate Accuracy and Precision for the Process Industries: A Review of Industry
Data” Alexander Ogilvie, Robert A. Brown, Jr., Fredrick P. Biery and Paul Barshop from IPA.
IPA’s Front End Loading (FEL) 2 is “Scoping Facility Planning,” comparable to AACE International
Class 4 estimates which gets a high range of +30% to +50%. This is not high enough
+35 to +50%
Risk Prioritization Method
Illustrated
(c) 2016 Hulett & Associates, LLC 24
Problems with Typical Risk
Prioritization Approaches
• Risk prioritization usually involves presenting:
– Standard tornado diagrams based on correlation between
activities and finish date
– Risk tornado diagrams, based on correlation between risks and
finish date
• Correlation-based tornados have problems with risks that may or may
not occur
– Risk criticality based on activities’ being on the critical path
• None of these methods give management what they need
to assess mitigations
– Risks prioritized at the P-80, not means as in correlation
– Risks measured in days saved if mitigated, not correlation
coefficients
– Risks have to be the arguments driving MCS to do this
(c) 2016 Hulett & Associates, LLC 25
Prioritizing Risks using MCS
Selected by their Days Saved at P-80
26
Iterative Approach to Prioritizing Risks (Based on Days Saved at P-80)
Risk # 1 2 3 4 5 6 7 8
Priority Level
(Iteration #)
Abusive
Bids
Offshore
design
firm
Suppliers
Busy
Fab
productivity
Geology
unknown
Coordinati
on during
Installation
Problems
at HUC
Resources
may go to
other
projects
1 X X X X X X X 1
2 X X X 2 X X X
3 X 3 X X X X
4 X X X X 4
5 X 5 X X
6 X X 6
7 7 X
8 8
© 2015 Hulett & Associates
Risk Prioritization for Mitigation
(c) 2016 Hulett & Associates, LLC 27
Megaproject Systemic Risks
Risk Prioritization Results for
Risk Mitigation Workshop
(c) 2016 Hulett & Associates, LLC 28
Risk Prioritization at P-80 with Days Saved
Name Days Saved
Megaproject may have interdependency problems 245
Megaproject may have excessive schedule pressure 128
The organization has other priority projects so personnel and funding
may be unavailable 54
Megaproject may have coordination problems offshore sourcing 46
Fabrication yards may experience lower Productivity than planned 25
Engineering may be complicated by using offshore design firm 12
Suppliers of installed equipment may be busy 13
Fabrication and installation problems may be revealed during HUC 9
Bids may be Abusive leading to delayed approval 1
Installation may be delayed due to coordination problems 1
The subsea geological conditions may be different than expected 0
Days Saved from Project Specific and Systemic Risks 534
Days Contributed by Uncertainty alone 189
Total Days contingency at P-80 723
Summary (1)
• Unknown Unknowns are unknown today, but
some may become known during confidential
interviews
• A new category of “Unknown Knowns,” or
those risks which are known to exist but are
not talked about, is addressed
29(c) 2016 Hulett & Associates, LLC
Summary (2)
• Confidential interviews allow interviewees to identify
“unknown unknowns” and to discuss “unknown
knowns”
• Interviewees introduce risks not included in the current
Risk Register
– Open ended questions often reveal important,
embarrassing or potentially dangerous risks that are not
talked about
– Once introduced, other team members seem to be able to
contribute to quantifying those “unspoken risks”
– These “interview risks” are often more impactful than the
risks in the Risk Register
30(c) 2016 Hulett & Associates, LLC
Summary (3)
• Monte Carlo simulation methods have been
challenged to address systemic risks
– Some say that systemic risks are best captured by
parametric analysis
• We show how systemic risks, often identified
with megaprojects, can be handled in MCS,
compared to simple expanding the uncertainty
ranges
• Project results databases need to be created or
mined if they exist to determine the impact
multipliers for systemic risks.
(c) 2016 Hulett & Associates, LLC 31
Summary (4)
• Risk mitigation decisions are greatly helped with
prioritized risks
• Risks need to be prioritized at the target level of
certainty, e.g., P-80
• Risks prioritization needs to supply some metric
that management can use in a benefit / cost
analysis, e.g., “days saved” even if assuming
perfect mitigation
• These tables have been useful in mitigation
workshops
(c) 2016 Hulett & Associates, LLC 32
Unknowns, Systemic Risks and
Risk Prioritization
in Schedule Risk Analysis
Presented to APM
Value of Quantitative Risk Analysis (QRA)
Conference
London February 2016
David T. Hulett, Ph.D., FAACE
(c) 2016 Hulett & Associates, LLC 33
This presentation was delivered
at an APM event
To find out more about
upcoming events please visit our
website www.apm.org.uk/events

More Related Content

What's hot

“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”Ary Jamil
 
Applying risk factors in the strategic selection of portfolio projects, prese...
Applying risk factors in the strategic selection of portfolio projects, prese...Applying risk factors in the strategic selection of portfolio projects, prese...
Applying risk factors in the strategic selection of portfolio projects, prese...Association for Project Management
 
Technical Risk Management
Technical Risk ManagementTechnical Risk Management
Technical Risk ManagementGlen Alleman
 
Agile IS Risk Management - Agile 2014 - Antifragile
Agile IS Risk Management - Agile 2014 - AntifragileAgile IS Risk Management - Agile 2014 - Antifragile
Agile IS Risk Management - Agile 2014 - AntifragileKen Rubin
 
A world in which all projects succeed - but not without risk management, pres...
A world in which all projects succeed - but not without risk management, pres...A world in which all projects succeed - but not without risk management, pres...
A world in which all projects succeed - but not without risk management, pres...Association for Project Management
 
Probabilistic Cost, Schedule, and Risk management
Probabilistic Cost, Schedule, and Risk managementProbabilistic Cost, Schedule, and Risk management
Probabilistic Cost, Schedule, and Risk managementGlen Alleman
 
Applying risk radar (v2)
Applying risk radar (v2)Applying risk radar (v2)
Applying risk radar (v2)Glen Alleman
 
Risk assesment template
Risk assesment templateRisk assesment template
Risk assesment templateGlen Alleman
 
Cost and schedule risk modelling - Range analysis
Cost and schedule risk modelling - Range analysisCost and schedule risk modelling - Range analysis
Cost and schedule risk modelling - Range analysisStephen Grey
 
NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5Future Managers
 
Project examples for sampling and the law of large numbers
Project examples for sampling and the law of large numbersProject examples for sampling and the law of large numbers
Project examples for sampling and the law of large numbersJohn Goodpasture
 
Risk analysis, priority setting team building and strategic insight
Risk analysis, priority setting team building and strategic insightRisk analysis, priority setting team building and strategic insight
Risk analysis, priority setting team building and strategic insightStephen Grey
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMIMudassir Iqbal
 
Project Risk Management
Project  Risk ManagementProject  Risk Management
Project Risk ManagementKelvin Fredson
 
Increasing the Probability of Success with Continuous Risk Management
Increasing the Probability of Success with Continuous Risk ManagementIncreasing the Probability of Success with Continuous Risk Management
Increasing the Probability of Success with Continuous Risk ManagementGlen Alleman
 

What's hot (20)

“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”
 
Applying risk factors in the strategic selection of portfolio projects, prese...
Applying risk factors in the strategic selection of portfolio projects, prese...Applying risk factors in the strategic selection of portfolio projects, prese...
Applying risk factors in the strategic selection of portfolio projects, prese...
 
Risk management case study
Risk management case studyRisk management case study
Risk management case study
 
Technical Risk Management
Technical Risk ManagementTechnical Risk Management
Technical Risk Management
 
Agile IS Risk Management - Agile 2014 - Antifragile
Agile IS Risk Management - Agile 2014 - AntifragileAgile IS Risk Management - Agile 2014 - Antifragile
Agile IS Risk Management - Agile 2014 - Antifragile
 
A world in which all projects succeed - but not without risk management, pres...
A world in which all projects succeed - but not without risk management, pres...A world in which all projects succeed - but not without risk management, pres...
A world in which all projects succeed - but not without risk management, pres...
 
Probabilistic Cost, Schedule, and Risk management
Probabilistic Cost, Schedule, and Risk managementProbabilistic Cost, Schedule, and Risk management
Probabilistic Cost, Schedule, and Risk management
 
Applying risk radar (v2)
Applying risk radar (v2)Applying risk radar (v2)
Applying risk radar (v2)
 
Risk assesment template
Risk assesment templateRisk assesment template
Risk assesment template
 
Cost and schedule risk modelling - Range analysis
Cost and schedule risk modelling - Range analysisCost and schedule risk modelling - Range analysis
Cost and schedule risk modelling - Range analysis
 
NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5
 
Project examples for sampling and the law of large numbers
Project examples for sampling and the law of large numbersProject examples for sampling and the law of large numbers
Project examples for sampling and the law of large numbers
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Risk analysis, priority setting team building and strategic insight
Risk analysis, priority setting team building and strategic insightRisk analysis, priority setting team building and strategic insight
Risk analysis, priority setting team building and strategic insight
 
Risk Management by Roger Pressman
Risk Management by Roger PressmanRisk Management by Roger Pressman
Risk Management by Roger Pressman
 
Enterprise risk management presentation to APM SWWE branch
Enterprise risk management presentation to APM SWWE branchEnterprise risk management presentation to APM SWWE branch
Enterprise risk management presentation to APM SWWE branch
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMI
 
Project Risk Management
Project  Risk ManagementProject  Risk Management
Project Risk Management
 
Project Management 08
Project Management 08Project Management 08
Project Management 08
 
Increasing the Probability of Success with Continuous Risk Management
Increasing the Probability of Success with Continuous Risk ManagementIncreasing the Probability of Success with Continuous Risk Management
Increasing the Probability of Success with Continuous Risk Management
 

Similar to Unknowns systemic risks and prioritization - David Hulett

Sheet1RISK RESPONSE MATRIXRisk EventReduce ProbabilityReduce Impac.docx
Sheet1RISK RESPONSE MATRIXRisk EventReduce ProbabilityReduce Impac.docxSheet1RISK RESPONSE MATRIXRisk EventReduce ProbabilityReduce Impac.docx
Sheet1RISK RESPONSE MATRIXRisk EventReduce ProbabilityReduce Impac.docxlesleyryder69361
 
How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownAcumen
 
Risk Criteria | Where the answer lies
Risk Criteria | Where the answer liesRisk Criteria | Where the answer lies
Risk Criteria | Where the answer liesAdvisian
 
Space Shuttle Columbia Group Case StudyAssuming the perspective .docx
Space Shuttle Columbia Group Case StudyAssuming the perspective .docxSpace Shuttle Columbia Group Case StudyAssuming the perspective .docx
Space Shuttle Columbia Group Case StudyAssuming the perspective .docxwilliame8
 
What legacy will your project leave
What legacy will your project leaveWhat legacy will your project leave
What legacy will your project leaveGreg Hyde
 
اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222nashaat algrara
 
Public Sector Enterprise Risk Management
Public Sector Enterprise Risk ManagementPublic Sector Enterprise Risk Management
Public Sector Enterprise Risk ManagementDr David Hancock
 
strategic risk management.pdf
strategic risk management.pdfstrategic risk management.pdf
strategic risk management.pdfHany Farouk
 
Risk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docxRisk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docxjoellemurphey
 
CHAPTER 34Turning Crisis into OpportunityBuilding an ERM.docx
CHAPTER 34Turning Crisis into OpportunityBuilding an ERM.docxCHAPTER 34Turning Crisis into OpportunityBuilding an ERM.docx
CHAPTER 34Turning Crisis into OpportunityBuilding an ERM.docxketurahhazelhurst
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docxaryan532920
 
5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them TooSHAZEBALIKHAN1
 
Project Risk Management - Introduction 2011
Project Risk Management - Introduction 2011Project Risk Management - Introduction 2011
Project Risk Management - Introduction 2011Sasha Lazarevic
 
PECB Webinar: Dealing with Project Risks
PECB Webinar: Dealing with Project Risks PECB Webinar: Dealing with Project Risks
PECB Webinar: Dealing with Project Risks PECB
 
Table of ContentsIntroduction3P.docx
Table of ContentsIntroduction3P.docxTable of ContentsIntroduction3P.docx
Table of ContentsIntroduction3P.docxmattinsonjanel
 

Similar to Unknowns systemic risks and prioritization - David Hulett (20)

Sheet1RISK RESPONSE MATRIXRisk EventReduce ProbabilityReduce Impac.docx
Sheet1RISK RESPONSE MATRIXRisk EventReduce ProbabilityReduce Impac.docxSheet1RISK RESPONSE MATRIXRisk EventReduce ProbabilityReduce Impac.docx
Sheet1RISK RESPONSE MATRIXRisk EventReduce ProbabilityReduce Impac.docx
 
How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us Down
 
Cipfa Workshops Scotland
Cipfa Workshops ScotlandCipfa Workshops Scotland
Cipfa Workshops Scotland
 
Risk Criteria | Where the answer lies
Risk Criteria | Where the answer liesRisk Criteria | Where the answer lies
Risk Criteria | Where the answer lies
 
Stephen cresswell risk are we missing a trick - 25th june
Stephen cresswell   risk are we missing a trick - 25th juneStephen cresswell   risk are we missing a trick - 25th june
Stephen cresswell risk are we missing a trick - 25th june
 
Space Shuttle Columbia Group Case StudyAssuming the perspective .docx
Space Shuttle Columbia Group Case StudyAssuming the perspective .docxSpace Shuttle Columbia Group Case StudyAssuming the perspective .docx
Space Shuttle Columbia Group Case StudyAssuming the perspective .docx
 
What legacy will your project leave
What legacy will your project leaveWhat legacy will your project leave
What legacy will your project leave
 
اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222
 
18 .docx
18                                  .docx18                                  .docx
18 .docx
 
Public Sector Enterprise Risk Management
Public Sector Enterprise Risk ManagementPublic Sector Enterprise Risk Management
Public Sector Enterprise Risk Management
 
9 .docx
9                                   .docx9                                   .docx
9 .docx
 
strategic risk management.pdf
strategic risk management.pdfstrategic risk management.pdf
strategic risk management.pdf
 
Test management
Test managementTest management
Test management
 
Risk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docxRisk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docx
 
CHAPTER 34Turning Crisis into OpportunityBuilding an ERM.docx
CHAPTER 34Turning Crisis into OpportunityBuilding an ERM.docxCHAPTER 34Turning Crisis into OpportunityBuilding an ERM.docx
CHAPTER 34Turning Crisis into OpportunityBuilding an ERM.docx
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 
5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too
 
Project Risk Management - Introduction 2011
Project Risk Management - Introduction 2011Project Risk Management - Introduction 2011
Project Risk Management - Introduction 2011
 
PECB Webinar: Dealing with Project Risks
PECB Webinar: Dealing with Project Risks PECB Webinar: Dealing with Project Risks
PECB Webinar: Dealing with Project Risks
 
Table of ContentsIntroduction3P.docx
Table of ContentsIntroduction3P.docxTable of ContentsIntroduction3P.docx
Table of ContentsIntroduction3P.docx
 

More from Association for Project Management

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Association for Project Management
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...Association for Project Management
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Association for Project Management
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...Association for Project Management
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Association for Project Management
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Association for Project Management
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Association for Project Management
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Association for Project Management
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...Association for Project Management
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024Association for Project Management
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Association for Project Management
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...Association for Project Management
 

More from Association for Project Management (20)

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 

Recently uploaded

Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1kcpayne
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...amitlee9823
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableSeo
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noidadlhescort
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentationuneakwhite
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfAmzadHosen3
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...lizamodels9
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 

Recently uploaded (20)

Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 

Unknowns systemic risks and prioritization - David Hulett

  • 1. Unknowns, Systemic Risks and Risk Prioritization in Schedule Risk Analysis Presented to APM Value of Quantitative Risk Analysis (QRA) Conference London February 2016 David T. Hulett, Ph.D., FAACE (c) 2016 Hulett & Associates, LLC 1
  • 2. Secretary Rumsfeld’s use of “Unknown Unknowns” In February 2002 DOD Secretary Donald Rumsfeld stated: “Reports that say that something hasn't happened are always interesting to me, because as we know: There are known knowns; there are things we know we know. We also know there are known unknowns; that is to say we know there are some things we do not know. But there are also unknown unknowns -- the ones we don't know we don't know. And if one looks throughout the history of our country and other free countries, it is the latter category that tend to be the difficult ones.” (source: http://en.wikipedia.org/wiki/There_are_known_knowns cited January 26, 2015) 2(c) 2016 Hulett & Associates, LLC
  • 3. Uncertainty including Inherent Variability, Estimating Error, Estimating Bias • Inherent variability in project activities that arise because people and organizations cannot do things reliably on plan • Estimating error – attaches to all types of estimates • Estimating bias – estimates may be slanted, usually toward shorter durations, to make desired project results “There are No Facts About the Future” 3(c) 2016 Hulett & Associates, LLC Lincoln Moses, Statistician and Administrator of Energy Information in the US DOE 1977 Annual Report to Congress)
  • 4. Uncertainty • Uncertainty in schedule duration is similar to “common cause” variation related to six sigma management, concepts developed by Walter Shewhart and championed by Edwards Demming • “Common cause variability is a source of variation caused by unknown factors that result in a steady but random distribution of output around the average of the data …. Common cause variation is also called random variation, noise, non-controllable variation … ” (http://www.isixsigma.com/dictionary/common- cause-variation/ ) • Hence application of uncertainty alone establishes the earliest date that risk mitigation can achieve even if individual risks were fully mitigated 4
  • 5. Example Schedule: Offshore Gas Production Platform Project (c) 2016 Hulett & Associates, LLC 5
  • 6. Case Study On Application of Uncertainty and Risk 6(c) 2016 Hulett & Associates, LLC Offshore Gas Production Platform Construction project, 3+ years and $1.7 billion. Using Polaris© from Booz Allen Hamilton
  • 7. Correcting for Inherent Variability, Estimating Error and Bias • Schedule uncertainty exhibiting inherent variation, estimating uncertainty and bias with ranges of .9, 1.05 and 1.3 • To replicate the estimated overall project ranges by using these parameters for individual activities we need to correlate the uncertainty 7(c) 2016 Hulett & Associates, LLC Correlated durations Uncorrelated durations Without Correlation P-80 duration is 113% of planned With Correlation at 1.0 the P-80 duration is 116% of planned
  • 8. Variation Caused by Known Unknowns • Project-specific risks are: – Characterized by probability of occurring that is usually less than 100% – Represent “root causes” of variation in durations – May be reducible by risk mitigation actions • These are specified during risk interviews and implemented with: – Estimated probabilities – Impact ranges (3-point estimates of multiplicative factors called Risk Drivers”) if they occur – The activities or cost elements they influence 8(c) 2016 Hulett & Associates, LLC
  • 9. Project-Specific Risks, Pre-Mitigated • Risk is similar to “special causes” in six sigma • “… special cause variation is caused by known factors that result in a non-random distribution of output…Special cause variation is a shift in output caused by a specific factor such as environmental conditions or process input parameters. It can be accounted for directly and potentially removed...” (http://www.isixsigma.com/dictionary/variation-special- cause/) • Hence, pre-mitigated risks are the subject of risk mitigation workshops. The improvement from risk mitigation is limited by the date determined by uncertainty alone 9
  • 10. Applying Known Unknowns: Project-Specific Risk Drivers to the Offshore Platform 10(c) 2016 Hulett & Associates, LLC There are 8 project-specific Risk Drivers including one Organizational Risk Driver assigned to all activities. Probability and impact multiplier ranges are specified, risks are assigned to activities. A risk can affect many activities, and an activity can be affected by several risks.
  • 11. Adding Project Specific Risk Drivers (c) 2016 Hulett & Associates, LLC 11 Adding Project Specific Risk Drivers Uncertainty correlated 1.0 Uncertainty not correlated Adding Project-Specific Risk Drivers increases P-80 Duration to 125% of planned
  • 12. Unknown Unknowns May Not be Unknowable • Interviews or workshops on risk often focus on risks and uncertainties that are close-in or actually happening now – This myopia leads to insufficient consideration of future risks • It is arguable that some unknown unknowns are not truly unknowable but just have not been thought of yet • Extra effort to focus on down-stream risks during the risk interviews could improve our understanding of risks, including making some of these “Unknown Unknowns” known 12(c) 2016 Hulett & Associates, LLC
  • 13. Add a Fourth Category of “Unknown Knowns” • Psychoanalytic philosopher Slavoj Zizek says that beyond these three categories there is a fourth, the unknown known, that which we intentionally refuse to acknowledge that we know • German sociologists Daase and Kessler (2007) agree with a basic point of Rumsfeld in stating that the cognitive frame for political practice may be determined by the relationship between what we know, what we do not know, what we cannot know, but Rumsfeld having left out what we do not like to know 13(c) 2016 Hulett & Associates, LLC http://en.wikipedia.org/wiki/There_are_known_knowns, Cited 12/26/2015)
  • 14. Risk Interviews vs. Risk Workshops (1) • Risk Interviews provide a safe environment to discuss both Unknown Unknowns and Unknown Knowns • Specifically, Unknown Knowns – We find that the Risk Register is always incomplete – Many of the risk events found to be most important in determining the schedule risk results are not in the Risk Register at all – These can be safely discussed in one-on-one interviews where confidentiality is promised • In these interviews new risks are discussed, whether they are hurtful to the project or embarrassing or not – Responding to open-ended questions, interviewees are encouraged to talk about “the good, the bad and the ugly” 14(c) 2016 Hulett & Associates, LLC
  • 15. Risk Interviews vs. Risk Workshops (2) • We need to avoid the ostrich approach to risk management. Identify, talk about and quantify the Unknown Knowns, the “elephant in the room,” and tell unbiased results • Risk interviews provide a confidential environment where individuals can talk in depth without being afraid of being embarrassed, pressured or subjected to “shoot the messenger” • Conversely, Risk Workshops often are places where social pressures or group dynamics limit debate – Groupthink – prefer unanimity, discourage dissent – “Moses factor” – adopting influential person’s ideas – Cultural Conformity – decisions match the group’s norms 15(c) 2016 Hulett & Associates, LLC David Hillson and Ruth Murray-Webster, Understanding and Managing Risk Attitude 2005
  • 16. Considering Systemic Risks (c) 2016 Hulett & Associates, LLC 16
  • 17. Compare what Risk Analysis Typically Predicts vs. What Actually Happens (c) 2016 Hulett & Associates, LLC 17 Source: John K. Hollmann, PE, “Reliable Risk Quantification for Project Cost and Schedule”, AACE International webinar December 15, 2015
  • 18. Incorporate Systemic Risks into the Monte Carlo Simulation (MCS) • Systemic Risks that include: – Technical complexity, new technology challenging – Scope not fully known – Process definition not complete – Megaproject complexity, size / duration, participants – Project organization, e.g., joint venture, multiple EPCs – Project management, scheduling and estimating process, bias • Some argue that these factors can be measured and their impact on project success estimated using parametric techniques (c) 2016 Hulett & Associates, LLC 18
  • 19. Inserting 3 Megaproject Systemic Risks with Original Uncertainty • Identifying the systemic risks and inserting them with appropriately-large impacts allows us to: – Specify the probability of occurrence – Identify the risks for risk mitigation • In this case study, these megaproject risks: – May have interdependency issues between project elements – May have complex offshoring of supply chain and even EPC contractors – May have excessive schedule pressure “I want it sooner” (c) 2016 Hulett & Associates, LLC 19
  • 20. Megaproject Systemic Risk Example (c) 2016 Hulett & Associates, LLC 20
  • 21. Individual Systemic Risks with Regular Uncertainty Approximates Hollmann (c) 2016 Hulett & Associates, LLC 21 Regular Uncertainty, Project-specific Risks Hollmann Benchmarking Uncertainty Regular Uncertainty, Project-specific and Megaproject Systemic Risks Parameters for specific Megaproject Systemic Risks are challenging, need to be selected based on historical data We need to be sure to include the systemic risks with the right probability and impact ranges based on data into the Monte Carlo simulation
  • 22. Results for Total Project Duration from MCS (c) 2016 Hulett & Associates, LLC 22 Some suggest that megaprojects that come in at 25% or less (cost) over the sanction budget are considered successful. This curve shows that about 50% do so. The P-80 duration is 1,913 days about 61% overrun of schedule
  • 23. Results are Similar to those for Cost Provided by IPA (c) 2016 Hulett & Associates, LLC 23 “Quantifying Estimate Accuracy and Precision for the Process Industries: A Review of Industry Data” Alexander Ogilvie, Robert A. Brown, Jr., Fredrick P. Biery and Paul Barshop from IPA. IPA’s Front End Loading (FEL) 2 is “Scoping Facility Planning,” comparable to AACE International Class 4 estimates which gets a high range of +30% to +50%. This is not high enough +35 to +50%
  • 24. Risk Prioritization Method Illustrated (c) 2016 Hulett & Associates, LLC 24
  • 25. Problems with Typical Risk Prioritization Approaches • Risk prioritization usually involves presenting: – Standard tornado diagrams based on correlation between activities and finish date – Risk tornado diagrams, based on correlation between risks and finish date • Correlation-based tornados have problems with risks that may or may not occur – Risk criticality based on activities’ being on the critical path • None of these methods give management what they need to assess mitigations – Risks prioritized at the P-80, not means as in correlation – Risks measured in days saved if mitigated, not correlation coefficients – Risks have to be the arguments driving MCS to do this (c) 2016 Hulett & Associates, LLC 25
  • 26. Prioritizing Risks using MCS Selected by their Days Saved at P-80 26 Iterative Approach to Prioritizing Risks (Based on Days Saved at P-80) Risk # 1 2 3 4 5 6 7 8 Priority Level (Iteration #) Abusive Bids Offshore design firm Suppliers Busy Fab productivity Geology unknown Coordinati on during Installation Problems at HUC Resources may go to other projects 1 X X X X X X X 1 2 X X X 2 X X X 3 X 3 X X X X 4 X X X X 4 5 X 5 X X 6 X X 6 7 7 X 8 8 © 2015 Hulett & Associates
  • 27. Risk Prioritization for Mitigation (c) 2016 Hulett & Associates, LLC 27 Megaproject Systemic Risks
  • 28. Risk Prioritization Results for Risk Mitigation Workshop (c) 2016 Hulett & Associates, LLC 28 Risk Prioritization at P-80 with Days Saved Name Days Saved Megaproject may have interdependency problems 245 Megaproject may have excessive schedule pressure 128 The organization has other priority projects so personnel and funding may be unavailable 54 Megaproject may have coordination problems offshore sourcing 46 Fabrication yards may experience lower Productivity than planned 25 Engineering may be complicated by using offshore design firm 12 Suppliers of installed equipment may be busy 13 Fabrication and installation problems may be revealed during HUC 9 Bids may be Abusive leading to delayed approval 1 Installation may be delayed due to coordination problems 1 The subsea geological conditions may be different than expected 0 Days Saved from Project Specific and Systemic Risks 534 Days Contributed by Uncertainty alone 189 Total Days contingency at P-80 723
  • 29. Summary (1) • Unknown Unknowns are unknown today, but some may become known during confidential interviews • A new category of “Unknown Knowns,” or those risks which are known to exist but are not talked about, is addressed 29(c) 2016 Hulett & Associates, LLC
  • 30. Summary (2) • Confidential interviews allow interviewees to identify “unknown unknowns” and to discuss “unknown knowns” • Interviewees introduce risks not included in the current Risk Register – Open ended questions often reveal important, embarrassing or potentially dangerous risks that are not talked about – Once introduced, other team members seem to be able to contribute to quantifying those “unspoken risks” – These “interview risks” are often more impactful than the risks in the Risk Register 30(c) 2016 Hulett & Associates, LLC
  • 31. Summary (3) • Monte Carlo simulation methods have been challenged to address systemic risks – Some say that systemic risks are best captured by parametric analysis • We show how systemic risks, often identified with megaprojects, can be handled in MCS, compared to simple expanding the uncertainty ranges • Project results databases need to be created or mined if they exist to determine the impact multipliers for systemic risks. (c) 2016 Hulett & Associates, LLC 31
  • 32. Summary (4) • Risk mitigation decisions are greatly helped with prioritized risks • Risks need to be prioritized at the target level of certainty, e.g., P-80 • Risks prioritization needs to supply some metric that management can use in a benefit / cost analysis, e.g., “days saved” even if assuming perfect mitigation • These tables have been useful in mitigation workshops (c) 2016 Hulett & Associates, LLC 32
  • 33. Unknowns, Systemic Risks and Risk Prioritization in Schedule Risk Analysis Presented to APM Value of Quantitative Risk Analysis (QRA) Conference London February 2016 David T. Hulett, Ph.D., FAACE (c) 2016 Hulett & Associates, LLC 33
  • 34. This presentation was delivered at an APM event To find out more about upcoming events please visit our website www.apm.org.uk/events