Making Progress in an Uncertain World 
Carolyn Limbert, Principal Planner, Harmonic Ltd, October 2014
Outline 
● The Realities of Delivery 
● The Landscape 
• Socio-Political 
• Structural 
• Emergent 
● Proactive Decision Management 
● 5 things to take away from the webinar
On Paper… 
Adapted from; (Dombkins, 1997) 
Scope: WHAT 
Objectives are to be 
achieved 
Concept 
Mobilisation 
Delivery: HOW 
To implement objectives 
Low 
Uncertainty 
High 
Uncertainty 
Low 
Uncertainty 
Initiation 
Definition 
Closure 
Implementation
The Reality… 
Adapted from; (Dombkins, 1997) 
Scope: WHAT 
Objectives are to be 
achieved 
Delivery: HOW 
To implement objectives 
Low 
Uncertainty 
High 
Mobilisation 
Definition 
Concept 
Uncertainty 
Low 
Uncertainty 
Closure 
Initiation
Complex Projects - Back to Basics 
New view on PM 
Performance 
Time Cost 
Performance 
Time Cost 
Context Financing 
(Strategic Highway Research Program, 2012) 
“The intrinsic complexity of projects, in part, is driven by political, social, 
technological and environmental issues, as well as tight fiscal pressures, end 
user expectations which may change dramatically during the life of a project, 
and government instability.” (ICCPM, 2012)
The Landscape 
Behaviours 
6 
Requirements 
What are the common 
challenges present in a complex 
project landscape? 
Funding / 
Finance 
Uncertainty Culture 
Assumptions Trades 
Change 
Length of Time 
Decision Making 
Optimism 
Unrealistic 
Solutions 
Lack of 
Maturity 
Geography 
Systems of 
Interests 
Regulatory 
Organisational 
Capability 
Ambiguity 
Risk Stakeholders Dependencies 
Utilising concepts from (Maylor, Turner, Murray-Webster, 2013)
Socio-Political Complexity 
Behaviours 
7 
Requirements 
What are the common 
challenges present in a complex 
project landscape? 
Funding / 
Finance 
Uncertainty Culture 
Assumptions Trades 
Change 
Length of Time 
Decision Making 
Optimism 
Unrealistic 
Solutions 
Lack of 
Maturity 
Geography 
Systems of 
Interests 
Regulatory 
Organisational 
Capability 
Ambiguity 
Risk Stakeholders Dependencies 
Utilising concepts from (Maylor, Turner, Murray-Webster, 2013)
Perception
Structural Complexity 
Behaviours 
9 
Requirements 
What are the common 
challenges present in a complex 
project landscape? 
Funding / 
Finance 
Uncertainty Culture 
Assumptions Trades 
Change 
Length of Time 
Decision Making 
Optimism 
Unrealistic 
Solutions 
Lack of 
Maturity 
Geography 
Systems of 
Interests 
Regulatory 
Organisational 
Capability 
Ambiguity 
Risk Stakeholders Dependencies 
Utilising concepts from (Maylor, Turner, Murray-Webster, 2013)
Systems Thinking 
System Engineering 
Enterprise Processes 
Enterprise Environment 
Management 
Investment 
Management 
System Life Cycle 
Process Management 
Resource Management 
Quality Management 
Project Processes 
Planning Assessment Control 
Decision 
Making 
Risk 
Management 
Configuration 
Management 
Information 
Management 
Technical Processes 
Stakeholder 
Requirements 
Definition 
Requirements 
Analysis 
Architectural 
Design 
Implementation Integration 
Verification Transition Validation 
Operation Maintenance 
Disposal 
Agreement Processes 
Enterprise Environment 
Management 
Investment 
Management 
Process 
Guidelines
Systems Thinking 
● You cannot optimise a system by separately optimising its 
components 
● Focus on defining customer needs and required functionality 
early in the development cycle 
● Understand the whole problem before you try to solve it
Requirements Prioritisation 
Agile DSDM – MoSCoW Prioritisation 
Must 
have 
•The Project cannot deliver on the target date without this 
•There is no point deploying the solution without this requirement 
• The solution will not be legal / safe / fit for purpose 
Should 
have 
•The requirement is important but not vital 
•The requirement may be painful to leave out but the solution is still viable 
•The requirement may need some form of workaround 
Could 
have 
•The requirement is wanted or desirable but less important 
• If the requirement is left out, the impact is minimal 
Wont 
have* 
•Project team has agreed it will not deliver this requirement 
•Requirement is not needed for the solution, and is a low priority 
* This time…
Emergent Complexity 
Behaviours 
13 
Requirements 
What are the common 
challenges present in a complex 
project landscape? 
Funding / 
Finance 
Uncertainty Culture 
Assumptions Trades 
Change 
Length of Time 
Decision Making 
Optimism 
Unrealistic 
Solutions 
Lack of 
Maturity 
Geography 
Systems of 
Interests 
Regulatory 
Organisational 
Capability 
Ambiguity 
Risk Stakeholders Dependencies 
Utilising concepts from (Maylor, Turner, Murray-Webster, 2013)
Influence vs. Control 
(INCOSE UK Capability Working Group) 
Influence 
Control 
Uncertainty 
Scope: WHAT 
Objectives are to be 
achieved 
Influence – Control Spectrum 
Implementation 
Delivery: HOW 
To implement objectives 
Closure 
Mobilisation 
Definition 
Concept 
Initiation 
Influence 
Low 
Uncertainty 
Control 
Closure 
Implementation 
Mobilisation 
Definition 
Concept 
Delivery: HOW 
To implement objectives 
Low 
Uncertainty 
Influence 
Control 
Influence 
Low 
High 
Uncertainty 
Initiation 
Scope: WHAT 
Objectives are to be 
achieved 
High 
Uncertainty 
Value Solution 
Purpose 
Focus 
Enterprise Capability Service Product
Now What?
Facilitating Proactive Decisions 
Level of Business Impact 
Skill Levels 
Required 
What 
Happened? 
Why Did it 
Happen? 
What is Likely 
to Happen? 
What Should I 
Do About It? 
Descriptive 
Analytics 
Diagnostic 
Analytics 
Predictive 
Analytics 
Prescriptive 
Analytics 
Forward Looking 
Indicators 
Actuals vs. Forecast 
Actuals vs. Baseline 
Scenario 
Planning
Making Progress
Objective Criteria / Steps 
Issue 
Create & Review Document 
Issue 
Objective Criteria / Steps; 
50% Draft Document Complete 
20% Peer Review Complete 
20% Update Document Complete 
10% Sign-off Loop Complete 
Draft 
Document 
Peer 
Review 
Update 
Document 
Sign-off 
Document 
Issue 
Draft 
Document 
Peer 
Review 
Update 
Document 
Sign-off 
Document 
Issue 
Infeed Infeed 
Suitable for roll-up utilising 
Steps / Objective Criteria 
Unsuitable for roll-up utilising 
Steps / Objective Criteria
Summary 
5 things to do as a result of this webinar… 
● Map your Environment and validate perceptions 
● Understand your priorities 
● Change happens – Influence / Control 
● Do things right and do the right things 
● Subjectively measure progress
Any Questions? 
Carolyn Limbert 
Principal Planner 
Carolyn.limbert@harmonicltd.co.uk
This presentation was delivered at an 
APM event 
To find out more about upcoming 
events please visit our website 
www.apm.org.uk/events

More Related Content

What's hot

Assignment of entrepreneur
Assignment of entrepreneurAssignment of entrepreneur
Assignment of entrepreneur
ibrar shahid
 
Transition & Change Management Presentation
Transition & Change Management PresentationTransition & Change Management Presentation
Transition & Change Management Presentation
Alex Ragan - MBA, PMP
 
ADKAR Change Management Model
ADKAR   Change Management ModelADKAR   Change Management Model
ADKAR Change Management Model
Syed Arh
 

What's hot (20)

Issue Management
Issue ManagementIssue Management
Issue Management
 
Escape Analysis Paralysis
Escape Analysis ParalysisEscape Analysis Paralysis
Escape Analysis Paralysis
 
stopHorseTrading
stopHorseTradingstopHorseTrading
stopHorseTrading
 
Assignment of entrepreneur
Assignment of entrepreneurAssignment of entrepreneur
Assignment of entrepreneur
 
Chap011
Chap011Chap011
Chap011
 
Troubled projects recovery
Troubled projects recoveryTroubled projects recovery
Troubled projects recovery
 
Transition & Change Management Presentation
Transition & Change Management PresentationTransition & Change Management Presentation
Transition & Change Management Presentation
 
The LAST Manifesto
The LAST ManifestoThe LAST Manifesto
The LAST Manifesto
 
Leading and Managing Change in Your Business
Leading and Managing Change in Your BusinessLeading and Managing Change in Your Business
Leading and Managing Change in Your Business
 
Change management case study
Change management   case studyChange management   case study
Change management case study
 
Monitoring & Evaluation - the RAPID approach
Monitoring & Evaluation - the RAPID approachMonitoring & Evaluation - the RAPID approach
Monitoring & Evaluation - the RAPID approach
 
ADKAR Change Management Model
ADKAR   Change Management ModelADKAR   Change Management Model
ADKAR Change Management Model
 
Project Stakeholder Engagement
Project Stakeholder EngagementProject Stakeholder Engagement
Project Stakeholder Engagement
 
Change Management Implementation Checklist PowerPoint Presentation Slides
Change Management Implementation Checklist PowerPoint Presentation SlidesChange Management Implementation Checklist PowerPoint Presentation Slides
Change Management Implementation Checklist PowerPoint Presentation Slides
 
Enterprise Risk Management:from Resistance to Resilience
Enterprise Risk Management:from Resistance to ResilienceEnterprise Risk Management:from Resistance to Resilience
Enterprise Risk Management:from Resistance to Resilience
 
A Performance DNA Leadership Model
A Performance DNA Leadership ModelA Performance DNA Leadership Model
A Performance DNA Leadership Model
 
Issue Management System
Issue Management SystemIssue Management System
Issue Management System
 
Sourcing Lecture 2 Change Management
Sourcing Lecture 2 Change ManagementSourcing Lecture 2 Change Management
Sourcing Lecture 2 Change Management
 
Organizational Change Management
Organizational Change ManagementOrganizational Change Management
Organizational Change Management
 
Stakeholder Engagement: The art & science of winning the SE snakes and ladder...
Stakeholder Engagement: The art & science of winning the SE snakes and ladder...Stakeholder Engagement: The art & science of winning the SE snakes and ladder...
Stakeholder Engagement: The art & science of winning the SE snakes and ladder...
 

Similar to Making progress in an uncertain world 2nd October 14

PCM - Project Cycle Management, Training on Evaluation
PCM - Project Cycle Management, Training on EvaluationPCM - Project Cycle Management, Training on Evaluation
PCM - Project Cycle Management, Training on Evaluation
rexcris
 
Lecture 9 industry studies student
Lecture 9   industry studies studentLecture 9   industry studies student
Lecture 9 industry studies student
moduledesign
 
thechangeaccelerationprocess-140215034525-phpapp01.pptx
thechangeaccelerationprocess-140215034525-phpapp01.pptxthechangeaccelerationprocess-140215034525-phpapp01.pptx
thechangeaccelerationprocess-140215034525-phpapp01.pptx
SamuelLee440194
 

Similar to Making progress in an uncertain world 2nd October 14 (20)

Managing complexity: taking back control, Carolyn Limbert, Wednesday 21st Jan...
Managing complexity: taking back control, Carolyn Limbert, Wednesday 21st Jan...Managing complexity: taking back control, Carolyn Limbert, Wednesday 21st Jan...
Managing complexity: taking back control, Carolyn Limbert, Wednesday 21st Jan...
 
Planning in Management (Principles of management)
Planning in Management (Principles of management)Planning in Management (Principles of management)
Planning in Management (Principles of management)
 
Communicator’s Pivotal Role in Project Management
Communicator’s Pivotal Role in Project ManagementCommunicator’s Pivotal Role in Project Management
Communicator’s Pivotal Role in Project Management
 
Business Plan VS Feasibility study
Business Plan VS Feasibility studyBusiness Plan VS Feasibility study
Business Plan VS Feasibility study
 
planning
planningplanning
planning
 
Identifying and Overcoming Roadblocks to Change
Identifying and Overcoming Roadblocks to ChangeIdentifying and Overcoming Roadblocks to Change
Identifying and Overcoming Roadblocks to Change
 
ISG: TechChange Presentation on M&E MIS Systems
ISG: TechChange Presentation on M&E MIS SystemsISG: TechChange Presentation on M&E MIS Systems
ISG: TechChange Presentation on M&E MIS Systems
 
Evaluation of SME and entreprenuership programme - Jonathan Potter & Stuart T...
Evaluation of SME and entreprenuership programme - Jonathan Potter & Stuart T...Evaluation of SME and entreprenuership programme - Jonathan Potter & Stuart T...
Evaluation of SME and entreprenuership programme - Jonathan Potter & Stuart T...
 
Greencastle readiness assessment webinar 14 aug13
Greencastle readiness assessment webinar 14 aug13Greencastle readiness assessment webinar 14 aug13
Greencastle readiness assessment webinar 14 aug13
 
PCM - Project Cycle Management, Training on Evaluation
PCM - Project Cycle Management, Training on EvaluationPCM - Project Cycle Management, Training on Evaluation
PCM - Project Cycle Management, Training on Evaluation
 
Introducing Policy Implementation and Evaluation.
  Introducing Policy Implementation and Evaluation.  Introducing Policy Implementation and Evaluation.
Introducing Policy Implementation and Evaluation.
 
Identifying and Overcoming Roadblocks to Change
Identifying and Overcoming Roadblocks to ChangeIdentifying and Overcoming Roadblocks to Change
Identifying and Overcoming Roadblocks to Change
 
Applying impact evaluation tools for integrating agricultural sectors in Nati...
Applying impact evaluation tools for integrating agricultural sectors in Nati...Applying impact evaluation tools for integrating agricultural sectors in Nati...
Applying impact evaluation tools for integrating agricultural sectors in Nati...
 
İTÜ İşletme ve Teknoloji Yönetimi - Lojistik & Tedarik Zinciri Yönetimi
İTÜ İşletme ve Teknoloji Yönetimi - Lojistik & Tedarik Zinciri YönetimiİTÜ İşletme ve Teknoloji Yönetimi - Lojistik & Tedarik Zinciri Yönetimi
İTÜ İşletme ve Teknoloji Yönetimi - Lojistik & Tedarik Zinciri Yönetimi
 
Lec 06 planning
Lec 06 planningLec 06 planning
Lec 06 planning
 
Change The Change
Change The ChangeChange The Change
Change The Change
 
Identifying a project in trouble and re-planning
Identifying a project in trouble and re-planningIdentifying a project in trouble and re-planning
Identifying a project in trouble and re-planning
 
Lecture 9 industry studies student
Lecture 9   industry studies studentLecture 9   industry studies student
Lecture 9 industry studies student
 
Create an End User Adoption Strategy
Create an End User Adoption StrategyCreate an End User Adoption Strategy
Create an End User Adoption Strategy
 
thechangeaccelerationprocess-140215034525-phpapp01.pptx
thechangeaccelerationprocess-140215034525-phpapp01.pptxthechangeaccelerationprocess-140215034525-phpapp01.pptx
thechangeaccelerationprocess-140215034525-phpapp01.pptx
 

More from Association for Project Management

Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Association for Project Management
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
Association for Project Management
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Association for Project Management
 

More from Association for Project Management (20)

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 

Recently uploaded

unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
Abortion pills in Kuwait Cytotec pills in Kuwait
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
lizamodels9
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
dlhescort
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
amitlee9823
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
lizamodels9
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 

Recently uploaded (20)

RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 

Making progress in an uncertain world 2nd October 14

  • 1. Making Progress in an Uncertain World Carolyn Limbert, Principal Planner, Harmonic Ltd, October 2014
  • 2. Outline ● The Realities of Delivery ● The Landscape • Socio-Political • Structural • Emergent ● Proactive Decision Management ● 5 things to take away from the webinar
  • 3. On Paper… Adapted from; (Dombkins, 1997) Scope: WHAT Objectives are to be achieved Concept Mobilisation Delivery: HOW To implement objectives Low Uncertainty High Uncertainty Low Uncertainty Initiation Definition Closure Implementation
  • 4. The Reality… Adapted from; (Dombkins, 1997) Scope: WHAT Objectives are to be achieved Delivery: HOW To implement objectives Low Uncertainty High Mobilisation Definition Concept Uncertainty Low Uncertainty Closure Initiation
  • 5. Complex Projects - Back to Basics New view on PM Performance Time Cost Performance Time Cost Context Financing (Strategic Highway Research Program, 2012) “The intrinsic complexity of projects, in part, is driven by political, social, technological and environmental issues, as well as tight fiscal pressures, end user expectations which may change dramatically during the life of a project, and government instability.” (ICCPM, 2012)
  • 6. The Landscape Behaviours 6 Requirements What are the common challenges present in a complex project landscape? Funding / Finance Uncertainty Culture Assumptions Trades Change Length of Time Decision Making Optimism Unrealistic Solutions Lack of Maturity Geography Systems of Interests Regulatory Organisational Capability Ambiguity Risk Stakeholders Dependencies Utilising concepts from (Maylor, Turner, Murray-Webster, 2013)
  • 7. Socio-Political Complexity Behaviours 7 Requirements What are the common challenges present in a complex project landscape? Funding / Finance Uncertainty Culture Assumptions Trades Change Length of Time Decision Making Optimism Unrealistic Solutions Lack of Maturity Geography Systems of Interests Regulatory Organisational Capability Ambiguity Risk Stakeholders Dependencies Utilising concepts from (Maylor, Turner, Murray-Webster, 2013)
  • 9. Structural Complexity Behaviours 9 Requirements What are the common challenges present in a complex project landscape? Funding / Finance Uncertainty Culture Assumptions Trades Change Length of Time Decision Making Optimism Unrealistic Solutions Lack of Maturity Geography Systems of Interests Regulatory Organisational Capability Ambiguity Risk Stakeholders Dependencies Utilising concepts from (Maylor, Turner, Murray-Webster, 2013)
  • 10. Systems Thinking System Engineering Enterprise Processes Enterprise Environment Management Investment Management System Life Cycle Process Management Resource Management Quality Management Project Processes Planning Assessment Control Decision Making Risk Management Configuration Management Information Management Technical Processes Stakeholder Requirements Definition Requirements Analysis Architectural Design Implementation Integration Verification Transition Validation Operation Maintenance Disposal Agreement Processes Enterprise Environment Management Investment Management Process Guidelines
  • 11. Systems Thinking ● You cannot optimise a system by separately optimising its components ● Focus on defining customer needs and required functionality early in the development cycle ● Understand the whole problem before you try to solve it
  • 12. Requirements Prioritisation Agile DSDM – MoSCoW Prioritisation Must have •The Project cannot deliver on the target date without this •There is no point deploying the solution without this requirement • The solution will not be legal / safe / fit for purpose Should have •The requirement is important but not vital •The requirement may be painful to leave out but the solution is still viable •The requirement may need some form of workaround Could have •The requirement is wanted or desirable but less important • If the requirement is left out, the impact is minimal Wont have* •Project team has agreed it will not deliver this requirement •Requirement is not needed for the solution, and is a low priority * This time…
  • 13. Emergent Complexity Behaviours 13 Requirements What are the common challenges present in a complex project landscape? Funding / Finance Uncertainty Culture Assumptions Trades Change Length of Time Decision Making Optimism Unrealistic Solutions Lack of Maturity Geography Systems of Interests Regulatory Organisational Capability Ambiguity Risk Stakeholders Dependencies Utilising concepts from (Maylor, Turner, Murray-Webster, 2013)
  • 14. Influence vs. Control (INCOSE UK Capability Working Group) Influence Control Uncertainty Scope: WHAT Objectives are to be achieved Influence – Control Spectrum Implementation Delivery: HOW To implement objectives Closure Mobilisation Definition Concept Initiation Influence Low Uncertainty Control Closure Implementation Mobilisation Definition Concept Delivery: HOW To implement objectives Low Uncertainty Influence Control Influence Low High Uncertainty Initiation Scope: WHAT Objectives are to be achieved High Uncertainty Value Solution Purpose Focus Enterprise Capability Service Product
  • 16. Facilitating Proactive Decisions Level of Business Impact Skill Levels Required What Happened? Why Did it Happen? What is Likely to Happen? What Should I Do About It? Descriptive Analytics Diagnostic Analytics Predictive Analytics Prescriptive Analytics Forward Looking Indicators Actuals vs. Forecast Actuals vs. Baseline Scenario Planning
  • 18. Objective Criteria / Steps Issue Create & Review Document Issue Objective Criteria / Steps; 50% Draft Document Complete 20% Peer Review Complete 20% Update Document Complete 10% Sign-off Loop Complete Draft Document Peer Review Update Document Sign-off Document Issue Draft Document Peer Review Update Document Sign-off Document Issue Infeed Infeed Suitable for roll-up utilising Steps / Objective Criteria Unsuitable for roll-up utilising Steps / Objective Criteria
  • 19. Summary 5 things to do as a result of this webinar… ● Map your Environment and validate perceptions ● Understand your priorities ● Change happens – Influence / Control ● Do things right and do the right things ● Subjectively measure progress
  • 20. Any Questions? Carolyn Limbert Principal Planner Carolyn.limbert@harmonicltd.co.uk
  • 21. This presentation was delivered at an APM event To find out more about upcoming events please visit our website www.apm.org.uk/events