SlideShare a Scribd company logo
1 of 20
Download to read offline
INDUSTRIAL TRAINING ON CONSTRUCTION IN METRO
UNDER SUPERVISION OF
MR. PRASHANT KUMAR
A.M-CIVIL/TRACK(NMRC)
UNIVERSITY SCHOOL OF ENGINEERING
GAUTAM BUDDHA UNIVERSITY
GREATER NOIDA
PRESENTED BY
AJINKYA RAJ
20/BCE/026
Introduction
A metro station is a railway station for a rapid transit system, which as a whole is usually called a
metro or subway.
A station provides a means for passengers to purchase tickets, board train, and evacuate the
system in the case of an emergency.
Most stations are located underground, with entrances/exits leading up to ground or street
level.
In other cases, a station may be elevated above a road, or at ground level depending on the level
of the train tracks.
Metro Station Construction
Construction of the underground stations would employ the cut-and-cover construction technique
generally begins by opening the ground surface to an adequate depth to permit support of existing
utility lines and to install soldier piles, or other earth retaining structures. The surface opening is then
covered with a temporary street decking so traffic and pedestrian movement can continue overhead
while excavation proceeds beneath the decking.
CUT AND COVER CONSTRUCTION
METHODOLOGY
The cut and cover method is suitable for construction of
station box and cut and cover tunnel in soft for mixed ground
conditions especially for excavation with shallow depth (less
than 30m).
There are two basic cut and cover construction methods,
namely Top down and Bottom up.
Both methods are suitable for station box construction, while
tunnel box structure is usually constructed by bottom up
method.
The system basically comprises of retaining walls and
strutting system.
TOP DOWN CONSTRUCTION METHOD
•In the top-down method, the permanent station structure walls are built
along the excavation boundary from top to bottom.
•The walling system, usually in the form of a diaphragm wall, is first installed
and then excavation is carried out up to roof slab level.
•After casting the roof slab, the excavation is continued up to the next level
of slab. This process is repeated until the excavation reaches the base slab
level.
The retaining walls shall usually be used as part of the permanent station
walls. The strutting system is usually the slabs of station structure
themselves and may occasionally be with some temporary steel struts,
depending upon the site specific requirements.
BOTTOM UP CONSTRUCTION METHODLOGY
•In the bottom up method, the retaining wall is constructed along the station
or tunnel boundary prior to excavation.
•Excavation is carried out to a certain depth and then a strutting system is
installed to support the retaining walls during excavation and construction
of the station.
•After the installation of the strutting system is completed and the final
formation level is reached, the base slab is cast in accordance with normal
procedure.
The wall can either be temporary or part of permanent structure. The
strutting system is removed after casting the slab.
What is Bearing?
The bearings transfer the forces coming from superstructure of a bridge to the
substructure. These also allow necessary movements in the super- structure
which are caused by various reasons like temperature variations.
Functions performed by Bearing
Transfer of vertical loads
Allowing rotation of Girders: The girders deflect under vertical loads which is
maximum in the middle. This causes rotations at the ends near supports.
Bearing facilitate this rotation.
Transfer of Lateral & Longitudinal loads: Loads such as Seismic/ Centrifugal/
wind etc are transferred to the substructure
Allowing certain movements: The girder expands/ contracts under thermal
variations. Bearings allow movements arising due to this thermal variations.
Elastomeric Bearings
• Elastomeric Bearings consist of synthetic rubber layers reinforced with steel layers in
between which provide the sliding as well as rotation capabilities.
• These bearings have no moving parts and require least maintenance.
• There is no arrangement to prevent lateral movements or to provide fixed end in these
bearings. Separate arrangements have to be made if such a requirement is there.
• Bearings are very stiff in resisting volume change but are very flexible when subjected to
shear or pure uni-axial tension.
• They are generally reinforced with a steel plates in alternative layers to reduce bulging.
Design of bearing
As per IRC 83:2015 (part ll)
• Depending upon the plate thickness, the bearing has been classified from type A to I. In our
project, Type B bearing with uniform thickness is used.
• Minimum thickness of top and bottom cover 2.5 mm
• Minimum thickness of side cover 4 mm
• All internal layer shall be of uniform thickness and between range of 8mm to 20mm
• Minimum thickness of steel plate is 3mm
Tendering
The tender is an offer to perform some task or to supply goods at a fixed price.
The contractors will be invited to submit sealed bids for construction or for the
provision of specifically designed services or goods during a particular time
frame in the initial step of this tender process.
Types of Tender
1. Open Tender: An open tender is the principal tender procedure employed by both
the private and government sectors. In the local newspaper, the customer advertises
the tender offer along with the key information of the proposed works and invites
interested contractors.
2. Selective Tender: Selective tendering is an alternative that has been developed to
address the open tender procedure's limitation. This tender aims to increase the quality
of bids received and ensures that contractors with the requisite expertise are given the
opportunity and submit the bids needed.
3. Negotiation Tender: This is widely used in the engineering and construction industry,
which is the subject of pre-contract and post-contract negotiations.
Concrete Mix Design
Concrete is a composite mixture which consists of Cement, Sand and Aggregate. Concrete
mix design is the procedure for finding the right quantities of these materials to achieve the
desired strength. Accurate concrete mix design makes concrete construction
economical. Large constructions such as Bridges, dams requires huge amount of concrete,
using the right quantity of constituents make the structure economical. In order to calculate
or find the right amount of cement, sand and aggregate required in 1m3 of concrete; you
need to know about different grades of concrete.
As per IS456:2000, Different grades of concrete are classified into M5, M7.5, M10, M15 etc.,
whereas M stands for Mix and the number behind M stands for Characteristic Compressive
strength (fck) of the concrete in N/mm2 @28 days when checked with
15cm×15cm×15cm cube in direct compression test.
Mix Design (M) = Cement: Sand :Aggregate
Different grades of concrete
Different grades of concrete has different
Concrete Mix proportions which means
different concrete mix ratios. As
Per IS456:2000, the Concrete mix design has
the following concrete mix proportions :
THANK YOU

More Related Content

Similar to NMRC Civil Construction

Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxsfQyoom
 
Balanced Cantilever Bridge
Balanced Cantilever BridgeBalanced Cantilever Bridge
Balanced Cantilever BridgeJeelkumar Patel
 
Jaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training reportJaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training reportRajendra Jhurawat
 
Construction of prestressed concrete structures
Construction of prestressed concrete structuresConstruction of prestressed concrete structures
Construction of prestressed concrete structuressanmilan
 
national building code
national building codenational building code
national building codeRuhiya Garg
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSOUMYA KHANDELWAL
 
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESREVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESIRJET Journal
 
Type of structural joints
Type of structural joints Type of structural joints
Type of structural joints Hanzlahakhlaq
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 
Slipform construction
Slipform constructionSlipform construction
Slipform constructionErankajKumar
 
Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Prasanth Dasu
 
Building construction report
Building construction  reportBuilding construction  report
Building construction reportAprajeeta Singh
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridgesCivil Engineers
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxJaySinghchib1
 

Similar to NMRC Civil Construction (20)

Ayush
AyushAyush
Ayush
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Balanced Cantilever Bridge
Balanced Cantilever BridgeBalanced Cantilever Bridge
Balanced Cantilever Bridge
 
Jaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training reportJaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training report
 
Construction of prestressed concrete structures
Construction of prestressed concrete structuresConstruction of prestressed concrete structures
Construction of prestressed concrete structures
 
national building code
national building codenational building code
national building code
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALS
 
Metroppt
MetropptMetroppt
Metroppt
 
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESREVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
 
Type of structural joints
Type of structural joints Type of structural joints
Type of structural joints
 
Eurasia tunnel1
Eurasia tunnel1Eurasia tunnel1
Eurasia tunnel1
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3
 
Building construction report
Building construction  reportBuilding construction  report
Building construction report
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridges
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 

Recently uploaded

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 

Recently uploaded (20)

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 

NMRC Civil Construction

  • 1. INDUSTRIAL TRAINING ON CONSTRUCTION IN METRO UNDER SUPERVISION OF MR. PRASHANT KUMAR A.M-CIVIL/TRACK(NMRC) UNIVERSITY SCHOOL OF ENGINEERING GAUTAM BUDDHA UNIVERSITY GREATER NOIDA PRESENTED BY AJINKYA RAJ 20/BCE/026
  • 2. Introduction A metro station is a railway station for a rapid transit system, which as a whole is usually called a metro or subway. A station provides a means for passengers to purchase tickets, board train, and evacuate the system in the case of an emergency. Most stations are located underground, with entrances/exits leading up to ground or street level. In other cases, a station may be elevated above a road, or at ground level depending on the level of the train tracks.
  • 3. Metro Station Construction Construction of the underground stations would employ the cut-and-cover construction technique generally begins by opening the ground surface to an adequate depth to permit support of existing utility lines and to install soldier piles, or other earth retaining structures. The surface opening is then covered with a temporary street decking so traffic and pedestrian movement can continue overhead while excavation proceeds beneath the decking.
  • 4. CUT AND COVER CONSTRUCTION METHODOLOGY The cut and cover method is suitable for construction of station box and cut and cover tunnel in soft for mixed ground conditions especially for excavation with shallow depth (less than 30m). There are two basic cut and cover construction methods, namely Top down and Bottom up. Both methods are suitable for station box construction, while tunnel box structure is usually constructed by bottom up method. The system basically comprises of retaining walls and strutting system.
  • 5. TOP DOWN CONSTRUCTION METHOD •In the top-down method, the permanent station structure walls are built along the excavation boundary from top to bottom. •The walling system, usually in the form of a diaphragm wall, is first installed and then excavation is carried out up to roof slab level. •After casting the roof slab, the excavation is continued up to the next level of slab. This process is repeated until the excavation reaches the base slab level. The retaining walls shall usually be used as part of the permanent station walls. The strutting system is usually the slabs of station structure themselves and may occasionally be with some temporary steel struts, depending upon the site specific requirements.
  • 6.
  • 7.
  • 8. BOTTOM UP CONSTRUCTION METHODLOGY •In the bottom up method, the retaining wall is constructed along the station or tunnel boundary prior to excavation. •Excavation is carried out to a certain depth and then a strutting system is installed to support the retaining walls during excavation and construction of the station. •After the installation of the strutting system is completed and the final formation level is reached, the base slab is cast in accordance with normal procedure. The wall can either be temporary or part of permanent structure. The strutting system is removed after casting the slab.
  • 9.
  • 10.
  • 11.
  • 12. What is Bearing? The bearings transfer the forces coming from superstructure of a bridge to the substructure. These also allow necessary movements in the super- structure which are caused by various reasons like temperature variations.
  • 13. Functions performed by Bearing Transfer of vertical loads Allowing rotation of Girders: The girders deflect under vertical loads which is maximum in the middle. This causes rotations at the ends near supports. Bearing facilitate this rotation. Transfer of Lateral & Longitudinal loads: Loads such as Seismic/ Centrifugal/ wind etc are transferred to the substructure Allowing certain movements: The girder expands/ contracts under thermal variations. Bearings allow movements arising due to this thermal variations.
  • 14. Elastomeric Bearings • Elastomeric Bearings consist of synthetic rubber layers reinforced with steel layers in between which provide the sliding as well as rotation capabilities. • These bearings have no moving parts and require least maintenance. • There is no arrangement to prevent lateral movements or to provide fixed end in these bearings. Separate arrangements have to be made if such a requirement is there. • Bearings are very stiff in resisting volume change but are very flexible when subjected to shear or pure uni-axial tension. • They are generally reinforced with a steel plates in alternative layers to reduce bulging.
  • 15. Design of bearing As per IRC 83:2015 (part ll) • Depending upon the plate thickness, the bearing has been classified from type A to I. In our project, Type B bearing with uniform thickness is used. • Minimum thickness of top and bottom cover 2.5 mm • Minimum thickness of side cover 4 mm • All internal layer shall be of uniform thickness and between range of 8mm to 20mm • Minimum thickness of steel plate is 3mm
  • 16. Tendering The tender is an offer to perform some task or to supply goods at a fixed price. The contractors will be invited to submit sealed bids for construction or for the provision of specifically designed services or goods during a particular time frame in the initial step of this tender process.
  • 17. Types of Tender 1. Open Tender: An open tender is the principal tender procedure employed by both the private and government sectors. In the local newspaper, the customer advertises the tender offer along with the key information of the proposed works and invites interested contractors. 2. Selective Tender: Selective tendering is an alternative that has been developed to address the open tender procedure's limitation. This tender aims to increase the quality of bids received and ensures that contractors with the requisite expertise are given the opportunity and submit the bids needed. 3. Negotiation Tender: This is widely used in the engineering and construction industry, which is the subject of pre-contract and post-contract negotiations.
  • 18. Concrete Mix Design Concrete is a composite mixture which consists of Cement, Sand and Aggregate. Concrete mix design is the procedure for finding the right quantities of these materials to achieve the desired strength. Accurate concrete mix design makes concrete construction economical. Large constructions such as Bridges, dams requires huge amount of concrete, using the right quantity of constituents make the structure economical. In order to calculate or find the right amount of cement, sand and aggregate required in 1m3 of concrete; you need to know about different grades of concrete. As per IS456:2000, Different grades of concrete are classified into M5, M7.5, M10, M15 etc., whereas M stands for Mix and the number behind M stands for Characteristic Compressive strength (fck) of the concrete in N/mm2 @28 days when checked with 15cm×15cm×15cm cube in direct compression test. Mix Design (M) = Cement: Sand :Aggregate
  • 19. Different grades of concrete Different grades of concrete has different Concrete Mix proportions which means different concrete mix ratios. As Per IS456:2000, the Concrete mix design has the following concrete mix proportions :