SlideShare a Scribd company logo
1 of 79
Unit-IIIUnit-III
Sub-stations Layout
• Abhishek Srivastava
• Electrical Engineering Department
• Subject: : POWER STATION PRACTICE
• (NEE /NEN–702)
ContentsContents
• UNIT- III: Sub-stations Layout
• Types of substations,
• Bus-bar arrangements, typical layout of substation.
• Power Plant Economics and Tariffs
• Load curve, load duration curve, different factors
related to plants and consumers, Cost of electrical
energy, depreciation, generation cost, effect of Load
factor on unit cost.
• Fixed and operating cost of different plants, role of
load diversity in power system economy. Objectives
and forms of Tariff; Causes and effects of low power
factor, advantages of power factor improvement,
different methods for power factor improvements.
33
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
THE TRANSFORMER BAY 3
What is a
substation?
An electrical substation takes electricity from a
very high voltage and lowers it to the voltage we
use in our homes & businesses
44
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 INTRODUCTION
The present electrical power system is a
complex interconnection of Generating
stations-Transmission systems- Receiving
stations- Distribution systems and Load
points.
In all the above phases of power flow, the
transfer of electrical energy takes place in
the electric sub stations.
4
55
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 Basically an electrical sub station consists
of a number of incoming circuits and out
going circuits connected to common bus
bar systems.
 Bus bars are conducting bars to which a
number of incoming or out going circuits
are connected.
5
66
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 INTRODUCTION
Each circuit connected to the bus bar will have
certain electrical component such as circuit
breakers, isolators, earth switches, current
transformers and voltage transformers.
These components are connected in a definite
sequence such that a circuit can be switched off
during normal operation by manual command
and also automatically during abnormal
conditions such as short circuits.
6
77
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
A sub station receives electrical power from
generating station through incoming
transmission lines and delivers electrical
power through the out going transmission
lines.
Sub station is an integral part of a power
system and is an important link between
the generating stations, transmission
systems, distribution systems and load
points.
7
88
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 DESIGN CONSIDERATIONS
 The sub station is designed with an
objective to provide maximum
reliability, flexibility, continuity of
service and to meet these objectives
with the lowest investment costs that
satisfy system requirement.
8
99
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 DESIGN CONSIDERATIONS
9
System requirements include the selection of
optimum voltage levels depending on the load
requirements and the transmission distances
involved. Generally, the generating source will be
far away from the load centers. The advantage of
capitalizing on low site costs, availability of ample
cooling water supply, economical fuel supply and
less stringent environmental considerations
compel construction of generating source far away
from load centers, there by, increasing
transmission distances.
1010
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 DESIGN CONSIDERATIONS
 Hence, to transmit power over long distances the
transmission voltage is to be increased and in our
country 400 kV is becoming common and higher
voltages for transmission is being explored. Many
factors such as voltage level, load capacity, site space
limitations, transmission line right of way requirement
and environmental considerations influence the design
of sub stations.
 The system requirement must be met with minimum
costs as the cost of equipment, labor, land and site
treatment is increasing every day.
10
1111
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 BUS LAYOUT AND SWITCHING ARRANGEMENT
 Since the major sub station costs are reflected in the power
transformers, circuit breakers and disconnecting switches,
the bus layout and switching arrangement selected will
determine the number of switches and power circuit breakers
required.
 A number of factors must be considered in the selection of
bus layouts and switching arrangements for a sub station to
meet system and station requirements.
 A sub station must be reliable, economical, safe, and as
simple in design as possible.
11
1212
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 SUB STATION LAYOUT AND BUS BAR SCHEMES
 The term layout denotes the physical
arrangement of various components in
the sub station relative to one another.
The layout is significant as it influences
the operation, maintenance, cost and
protection of the sub station. These
aspects are considered while designing
the sub station layout.
12
1313
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 SUB STATION LAYOUT AND BUS BAR SCHEMES
With the given number of incoming lines, out
going lines, transformers, etc., the sub station
can be designed in several alternative ways.
 The physical arrangement of the equipment is
called the layout of the sub station. The layout is
illustrated by means of single line diagrams.
 The design of sub station layout need careful
consideration of several aspects such as: 13
1414
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 SUB STATION LAYOUT AND BUS BAR SCHEMES
 Switching requirement for normal operation.
 Switching requirement during abnormal
conditions like short circuits and overloads.
 Degree of flexibility in operations, simplicity.
 Freedom from total shutdowns.
 Maintenance requirements, space for
approaching various equipment for
maintenance.
 Road/ rail for transporting main and auxiliary
equipment.
14
1515
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 SUB STATION LAYOUT AND BUS BAR SCHEMES
 Safety of personnel.
 Protective zones for main and back up
protection.
 Provision for bye pass facilities and for
extensions, space requirements.
 Technical requirements such as ratings,
clearances, earth system, lightning protection.
 Requirement for SCADA and communication.
 Compatibility for local and ambient condition.
15
1616
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 SUB STATION LAYOUT AND BUS BAR SCHEMES
 The choice of bus bar schemes for ac yards
depend upon several factors mentioned above.
The important bus bar schemes are:
 Single bus bar
 Double bus bar with one breaker per circuit
 Double bus bar with two breaker per circuit
 Main and transfer bus
 Ring bus or Mesh scheme
 Breaker and a half(1 1/2 breaker) arrangement
16
1717
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 SUB STATION LAYOUT AND BUS BAR SCHEMES
The various schemes are generally compared to
emphasize their advantage and limitations.
 The basis of comparison is generally the
degree of reliability & economic justification.
 The degree of reliability is evaluated by
determining continuity of service under
anticipated operating conditions and possible
faults. 17
1818
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION VARIOUS BUS BAR SCHEMES
 SINGLE BUS BAR SCHEME
BUS
ISOLATOR
BREAKER
CURRENT TRANSFORMER
POWER TRANSFORMER
18
1919
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 SINGLE BUS BAR SCHEME
 Advantage –Lowest cost
 Disadvantage:
Maintenance without interruption of supply is not possible.
Sub station can not be extended without completely de-
energizing the sub station
Can be used only where loads can be interrupted or have other
supply arrangements. Least flexibility. 19
2020
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 VARIOUS BUS BAR SCHEMES
 SINGLE BUS BAR SCHEME WITH BUS
SECTIONALISER
BUS SECTION-2
ISOLATOR
BREAKER
CURRENT TRANSFORMER
POWER TRANSFORMER
BUS SECTION-1
SECTIONALISER
20
2121
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 SINGLE BUS BAR SCHEME WITH BUS SECTIONALISER
Sectionalizing the single bus improves slightly the reliability if
the incoming and out going circuits are distributed evenly on
both the sections.
 Where double feed is provided for any single load it is
preferable to have one circuit from each section.
 In this arrangement each section behaves as a separate bus
bar and any outage can be confined to one section of the bus
bar.
 Only the faulty section will be tripped by bus differential
protection.
21
2222
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 DOUBLE BUS BAR WITH ONE BREAKER PER CIRCUIT
BUS-1
BUS-2
BUS COUPLER
BREAKER
POWER TRANSFORMER
BREAKER
22
2323
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 DOUBLE BUS BAR WITH ONE BREAKER PER CIRCUIT
 This arrangement has the following advantages:
 Each load may be fed from either bus.
 Operational flexibility may be increased by grouping the
incoming and out going feeders in separate groups.
 Either bus bar can be taken out for maintenance.
 Bus coupler helps in ‘on load change over ‘from one bus to
the other.
 Adopted where load and continuity justify additional cost.
 A major disadvantage is that the breaker can not be taken out
for maintenance without interrupting supply to the concerned
circuit.
23
2424
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 DOUBLE BUS BAR WITH ONE BREAKER PER
CIRCUIT
 Bus protection scheme may cause loss of sub
station when it operates if all circuits are
connected to that bus.
 High exposure to bus faults.
 Line breaker failure takes all circuits connected
to that bus out of service.
 Bus tie breaker failure takes the entire sub
station out of service.
24
2525
DOUBLE MAIN BUS & CB BYPASS ISOLATOR SYSTEMDOUBLE MAIN BUS & CB BYPASS ISOLATOR SYSTEM
FEEDER1
BUS-2BUS-2
BUS-1BUS-1
T/F-1
BUSCOUPLER
FEEDER2
T/F-2
FEEDER3 FEEDER4
BAY1 BAY2
BAY3
BAY4
BAY5
BAY6 BAY7
FOR ANY CB PROBLEM OR FOR
PREVENTIVE MAINTANENCE, SUCH
FEEDER CAN BE SHIFTED TO
ANOTHER BUS AND THE BYPASS
ISOLATOR IS CLOSED, THEN
PROTECTION IS TRANSFERRED TO
BUS COUPLER AND THE FAULTY CB
CAN BE ISOLATED.
2626
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 MAIN AND TRANSFER BUS
MAIN BUS
TRANSFER BUS
BREAKERTIE BREAKER
LINE LINE
26
2727
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 MAIN AND TRANSFER BUS
 This is an alternative to double bus single
breaker arrangement which provided for change
over to either bus for carrying out maintenance
on other bus. But it provided no facility for
breaker maintenance without interrupting power
supply to the concerned circuit.
 The main and transfer bus works the other way
round.
 This arrangement provides facility for carrying
out breaker maintenance but does not permit
bus maintenance.
27
2828
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 MAIN AND TRANSFER BUS
 Any breaker can be taken out of service for maintenance.
 Wherever maintenance is required on any breaker, the circuit is changed
over to the transfer bus and controlled through the bus coupler breaker.
 Potential devices may be used on the main bus for relaying.
 The cost is increased due to use of an extra isolator for each circuit and
providing interlock for bus coupler and circuit isolators.
 Relaying sensitivity decreases as the same bus coupler is used to
energize the concerned circuit for all the circuit breakers whenever they
are taken out for maintenance.
 Failure of bus or any circuit breaker results in shut down of entire sub
station. 28
2929
DOUBLE MAIN BUS & TRANSFER BUS SYSTEMDOUBLE MAIN BUS & TRANSFER BUS SYSTEM
FEEDER1
BUS-2BUS-2
BUS-1BUS-1
FEEDER2
TRANSFERBUS
COUPLER
T/F-1 T/F-2
BUSCOUPLER
TRANSFER BUSTRANSFER BUS
FEEDER3 FEEDER4
BAY1 BAY2
BAY3 BAY4 BAY5
BAY6 BAY7 BAY8
3030
BUS BAR ARRANGEMENTSBUS BAR ARRANGEMENTS
• Double Bus Bar Arrangement with
Transfer Bus.
This arrangement provides more
additional flexibility, continuity of Power
Supply, permits periodic maintenance
without total shut down as the two main
buses can be operated independently with
the same redundancy.
3131
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 DOUBLE BUS BAR WITH TWO BREAKER
PER CIRCUIT
BUS-1
BUS-2
BREAKER
LINE LINE
31
3232
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 DOUBLE BUS BAR WITH TWO BREAKER PER
CIRCUIT
 Each circuit has two dedicated breakers.
 Has flexibility in permitting feeder circuits to be
connected to either bus.
 Any breaker can be taken out of service for
maintenance.
 High reliability.
 Most expensive. Used only in large generating
stations where security of connection is paramount.
32
3333
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
• RING BUS OR MESH SCHEME
ISOLATOR
BREAKER
LINE
LINE
POWER TRANSFORMER
33
3434
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 RING BUS OR MESH SCHEME
 In this scheme the breakers are arranged in a ring with
circuits connected between breakers.
 There are the same number of circuits as there are
breakers.
 During normal operation, all breakers are closed. For a
circuit fault, two breakers are tripped, and in the event
one of the breaker fails to operate to clear the fault, an
additional circuit will be tripped by operation of breaker-
failure back up relays.
 During breaker maintenance, the ring is broken, but all
lines remain in service. 34
3535
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
 RING BUS OR MESH SCHEME
 The circuits connected to the ring are arranged so that
sources are alternated with loads.
 For an extended circuit outage, the line isolator may be
opened and the ring can be closed.
 No changes to protective relays are required for any of the
various operating conditions or during maintenance.
 The ring bus scheme is economical in cost, has good
reliability, is safe for operation, is flexible, and is normally
considered suitable for important sub stations up to a limit of
five circuits.
 It is common practice to build major sub stations initially as a
ring bus; for more than five outgoing circuits, the ring bus is
usually developed to the breaker-and-a-half scheme. 35
3636
THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION
• One and a Half Breaker Arrangement.
This arrangement provides three circuit
breakers for every two circuits. It gives
high security against loss of supply but
higher cost is involved. Hence this is
provided for important 400/220 KV Sub
Stations.
Types of LoadsTypes of Loads
Domestic Load
Commercial Load
Industrial Load
Municipal Load
Irrigation Load
Traction Load
Variable load on Power stationVariable load on Power station
The load on a power station varies from time
to time due to uncertain demands of the
consumers and is known as variable load
on the station.
Effects of variable load
Need of additional equipment
Increase in production cost
Load CurveLoad Curve
The curve showing the variation of load on
the power station with respect to time is
known as a load curve
Load duration CurveLoad duration Curve
When the load elements of a load curve are arranged
in the order of descending magnitude ,the curve
thus obtained is called load duration curve.
Important terms and factorsImportant terms and factors
Connected load: It is the sum of continuous
rating of all the equipments connected to
supply system.
Maximum Demand: It is the greatest demand
of load of the power station during a given
period.
Demand factor: it is the ratio of maximum
demand on the power station to its
connected load.
Important terms and factorsImportant terms and factors
Average load: The average of loads occurring
on the power station in a given period (day
or month or year)is known as average load
or average demand.
Load factor: The ratio of average load to the
maximum demand during a period is known
as load factor.
Diversity factor: The ratio of the sum of
individual maximum demands to the
maximum demand on power station
Important terms and factorsImportant terms and factors
Coincidence factor: The coincidence factor is
the reciprocal of the diversity factor
Contribution factor: it is the contribution of
a particular load ,in per unit of the
individual demand ,to the group maximum
demand
Important terms and factorsImportant terms and factors
Plant Capacity factor: it is the ratio of actual
energy produced to the maximum possible
energy that could have been produced
during a given period.
Plant use factor: It is ratio of kWh generated
to the product of plant capacity and the
number of hours for which the plant was
operation.
Plant Utilization factor: it is the ratio of
maximum load to the rated capacity.
TariffTariff
The rate at which electrical energy is supplied
to a consumer is known tariff.
Objectives of tariff
 Recovery of production cost
 Recovery of capital investment cost
 Recovery of operation and maintenance
cost
 A suitable profit
Desirable characteristics of aDesirable characteristics of a
tarifftariff
Proper return
Fairness
Simplicity
Reasonable profit
Attractive
Types of tariffTypes of tariff
Simple tariff
Flat rate tariff
Block rate tariff
Two part tariff
Maximum demand tariff
Power factor tariff
Three part tariff
Simple tariff or uniform rateSimple tariff or uniform rate
tarifftariff
There is a fixed rate per unit of energy consumed.
Advantages:
Simplest tariff method and is readily understood
by the consumers.
Disadvantages:
There is no discrimination between consumers
The cost per unit delivery is high
it does not encourage the use of electricity
Flat rate tariffFlat rate tariff
When different types of consumers are charged
at different uniform per unit rate ,it is called a
flat rate tariff.
Advantanges: it is more fair to different types of
consumers and is quite simple in calculations.
Disadvantages:
 Separate meters are requires for light and
power load.
 A particular class of consumers are charged
at the same rate irrespective of the magnitude
of energy consumed.
Block rate tariffBlock rate tariff
When a given block of energy is charged at a
specified rate and the succeeding blocks of
energy are charged at progressively
reduced rates, it is called a block rate tariff.
Advantages:
Consumer gets an incentive to consume
more energy. It increases the load factor.So
cost of generation reduced.
Disadvantages:
it lacks a measure of consumers demand.
Two part tariffTwo part tariff
When the rate of electrical energy is charged on
the basis of maximum demand of the consumers
and the units consumed ,it is called a two-part
tariff.
In two-part tariff ,the total charges to be made
from the consumer is split in to two
components ,fixed charges and running charges.
The fixed charge depends on the maximum
demand in kW and running cost depends on the
number of units consumed by the consumer in
kWh.
Total charges = b X kW+ c X kWh
Two part tariffTwo part tariff
Advantages:
it is easily understood by the consumers
it recovers the fixed charges which
depend upon the maximum demand
Disadvantages:
The consumer has to pay the fixed
charges irrespective of the fact whether he
has consumed or not.
There is always error in assessing the
maximum demand of the consumer.
Maximum demand tariffMaximum demand tariff
It is similar to two-part tariff with the only
difference that the maximum demand is
actually measured by installing maximum
demand meter in the premises of the
consumer.
Advantages: This removes the objection of two-
part tariff
Disadvantages: Not suitable for small consumers
as a separate maximum demand meter is
required.
Power factor tariffPower factor tariff
The tariff in which power factor of the
consumer’s load taken in to consideration is
known as power factor tariff.
Types of power factor tariff:
1.kVA maximum demand tariff :It is
modification of two part tariff. In this case
fixed charges are made on the basis of
maximum demand kVA and not in kW.
2.Sliding scale tariff : This is also known as
average power factor tariff. In this case, an
average power factor , say 0.8 lagging , is
taken as reference. If the pf of consumer
falls below this factor ,suitable additional
charges are made or if pf of consumer
above the reference ,a discount allowed to
the consumer.
3.kW and kVAR tariff: In this type both kW
and kVAR charged separately.
Power factor tariffPower factor tariff
Three part tariffThree part tariff
When the total charges to be made from the
consumer is split into three parts ,fixed
charge ,semi fixed charge and running charge
,it is known as three part tariff.
Total charge = a + bXkW + cXkWh
a – fixed charge including intrest and
depreciation on the cost of secondary
distribution and labor cost of the collecting
revenues.
b – charge per kW maximum demand
c – charge per kWh of energy consumed.
Power factor and economics ofPower factor and economics of
power factor correctionpower factor correction
Power factor : The cosine of the angle between
voltage and current in an AC circuit is known as
power factor
Disadvantages of low powerDisadvantages of low power
factorfactor
Large kVA rating equipment
kVA = kW/cos ϕ
Greater conductor size
Large copper losses
Poor voltage regulation
Reduced handling capacity of system
Causes of low factorCauses of low factor
AC induction motors
Arc lamps ,electric discharge and
industrial heating furnaces
Varying load on the power system
Power factor improvementPower factor improvement
equipmentequipment
Static Capacitors: The power factor can be improved by
connecting capacitors in parallel with the equipment
operating at lagging power factor.
Advantages:
 They have low losses
 Little maintenance
 Easily installed
 Can work under ordinary atmosphere condition
Disadvantages
 Short service life
 Easily damaged with higher voltage
 Repair uneconomical
Synchronous CondenserSynchronous Condenser
An over-excited synchronous motor running on no
load known as synchronous condenser.
Advantages:
 Power factor can be controlled
 Highly stable
 Faulty can be removed easily
Disadvantages:
 Considerable losses in the motor
 High maintenance cost
 It produces noise
 Not self starting one
Phase advancersPhase advancers
Phase advancers are used to improve the power
factor of induction motors. The low power factor
of an induction motor is due to the fact that its
stator winding draws exciting current which lags
behind the supply voltage by 90 degree. If the
exciting ampere turns can be provided from some
other AC source then the stator wining will be
relieved of exciting current and the power factor
of the motor can be improved.
Advantages: kVAR lagging reduced ,convenient
Disadvantages: Not economical for motors below
200HP
Calculation of Power factorCalculation of Power factor
correctioncorrection
Methods for Power FactorMethods for Power Factor
ImprovementImprovement
• The following devices and equipment are
used for Power Factor Improvement.
• Static Capacitor
• Synchronous Condenser
• Phase Advancer
1. Static Capacitor1. Static Capacitor
• Most of the industries and power system loads are inductive that take lagging current
which decrease the system power factor (See Disadvantages of Low Power factor) .
For Power factor improvement purpose, Static capacitors are connected in parallel
with those devices which work on low power factor.
• Advantages:
• Capacitor bank offers several advantages over other methods of power factor
improvement.
• Losses are low in static capacitors
• There is no moving part, therefore need low maintenance
• It can work in normal conditions (i.e. ordinary atmospheric conditions)
• Do not require a foundation for installation
• They are lightweight so it is can be easy to installed
• Disadvantages:
• The age of static capacitor bank is less (8 – 10 years)
• With changing load, we have to ON or OFF the capacitor bank, which causes
switching surges on the system
• If the rated voltage increases, then it causes damage it
• Once the capacitors spoiled, then repairing is costly
2. Synchronous Condenser
• When a Synchronous motor operates at No-Load and over-exited then it’s called a
synchronous Condenser. Whenever a Synchronous motor is over-exited then it
provides leading current and works like a capacitor.
• When a synchronous condenser is connected across supply voltage (in parallel) then
it draws leading current and partially eliminates the re-active component and this
way, power factor is improved. Generally, synchronous condenser is used to improve
the power factor in large industries.
• Advantages:
• Long life (almost 25 years),High Reliability
• Step-less adjustment of power factor.,No generation of harmonics of maintenance
• The faults can be removed easily
• It’s not affected by harmonics.
• Require Low maintenance (only periodic bearing greasing is necessary)
• Disadvantages:
• It is expensive (maintenance cost is also high) and therefore mostly used by large
power users.
• An auxiliary device has to be used for this operation because synchronous motor has
no self starting torque
• It produces noise
3. Phase Advancer
• Phase advancer is a simple AC exciter which is connected on the main shaft of the
motor and operates with the motor’s rotor circuit for power factor improvement.
Phase advancer is used to improve the power factor of induction motor in industries.
• As the stator windings of induction motor takes lagging current 90° out of phase with
Voltage, therefore the power factor of induction motor is low. If the exciting ampere-
turns are excited by external AC source, then there would be no effect of exciting
current on stator windings. Therefore the power factor of induction motor will be
improved. This process is done by Phase advancer.
• Advantages:
• Lagging kVAR (Reactive component of Power or reactive power) drawn by the motor
is sufficiently reduced because the exciting ampere turns are supplied at slip
frequency (fs).
• The phase advancer can be easily used where the use of synchronous motors is
Unacceptable
• Disadvantage:
• Using Phase advancer is not economical for motors below 200 H.P. (about 150kW)
Load profileLoad profile
• Load profile chart- Load curve
• In electrical engineering, a load profile is a
graph of the variation in the electrical load
versus time. A load profile will vary according to
customer type (typical examples include
residential, commercial and industrial),
temperature and holiday seasons.
Power generationPower generation
• In the electricity generation sector, a load
curve is a chart showing the amount of
electricity customers use over a period of
time.
• Generation companies use this
information to plan how much power they
will need to generate at any given time.
Daily load curveDaily load curve
•
Time Hrs
Load
in
KW
200
700
150
Load curveLoad curve
•
Time Hrs
Load
in
KW
Avarage
Load
Max demand,
peak load
00 24
08 18
Load FactorLoad Factor
• The ratio of the average load supplied during a designated period to
the peak load occurring in that period, in kilowatts.
• Simply, the load factor is the actual amount of kilowatt-hours
delivered on a system in a designated period of time as opposed to
the total possible kilowatt-hours that could be delivered on a system
in a designated period of time.
• Utilities are generally interested in increasing load factors on their
systems.
• A high load factor indicates high usage of the system’s equipment
and is a measure of efficiency. High load factor customers are
normally very desirable from a utility’s point of view.
• Using a year as the designated period, the load factor is calculated
by dividing the kilowatt-hours delivered during the year by the peak
load for the year times the total number or hours during the year.
Load factorLoad factor
• Load factor (electrical) is the average power divided
by the peak power over a period of time.
• in the electricity industry, load factor is a measure
of the output of a power plant.
The two commonest definitions are:
1. the ratio of average load to peak load in a period.
2.the ratio of actual energy produced to The
maximum energy that could have been produced if
the maximum demand stays on for all the time.
A higher load factor is better:
* A power plant may be less efficient at low load
factors.
* A high load factor means fixed costs are spread
over more kWh of output.
Load FactorLoad Factor
Daily LFDaily LF
24_max
__
_
24_max
24_
_
_
_
_
_max
_
_
×
=
×
×
=
=
=
demandimum
producedenergyactual
factorload
demandimum
demandaverage
factorload
demandpeak
demandaverage
factorload
demandimum
demandaverage
factorload
Load FactorsLoad Factors
• Based on the period considered
(Day,Week, Month,or year)
• Daily LF
• Weekly LF
• Monthly LF
• Yearly LF
Diversity factorDiversity factor
• Diversity factor: The ratio of sum of the
individual non-coincident maximum demands
of various subdivisions of the system to the
maximum demand of the complete system.
• The diversity factor is always more than or
equal to 1.
Diversity Factor = ---------------------------------
Sum of Individual max demand
Max demand on Power
station
7979
THANK YOUTHANK YOU

More Related Content

What's hot

A comparative study of cascaded h bridge and reversing voltage multilevel inv...
A comparative study of cascaded h bridge and reversing voltage multilevel inv...A comparative study of cascaded h bridge and reversing voltage multilevel inv...
A comparative study of cascaded h bridge and reversing voltage multilevel inv...IAEME Publication
 
An Improved Single Phase Transformer less Inverter Topology for Cost Effecti...
An Improved Single Phase Transformer less Inverter Topology  for Cost Effecti...An Improved Single Phase Transformer less Inverter Topology  for Cost Effecti...
An Improved Single Phase Transformer less Inverter Topology for Cost Effecti...IJMER
 
PSCAD Final Report
PSCAD Final ReportPSCAD Final Report
PSCAD Final ReportJeff Ge
 
6.[36 45]seven level modified cascaded inverter for induction motor drive app...
6.[36 45]seven level modified cascaded inverter for induction motor drive app...6.[36 45]seven level modified cascaded inverter for induction motor drive app...
6.[36 45]seven level modified cascaded inverter for induction motor drive app...Alexander Decker
 
Analysis and simulation of multilevel inverter using multi carrier based pwm
Analysis and simulation of multilevel  inverter using multi carrier based pwmAnalysis and simulation of multilevel  inverter using multi carrier based pwm
Analysis and simulation of multilevel inverter using multi carrier based pwmIAEME Publication
 
Modified cascaded multilevel inverter with ga to reduce line to line voltage thd
Modified cascaded multilevel inverter with ga to reduce line to line voltage thdModified cascaded multilevel inverter with ga to reduce line to line voltage thd
Modified cascaded multilevel inverter with ga to reduce line to line voltage thdIAEME Publication
 
Single phase h6 transformerless inverter with a simple boost converter for pv...
Single phase h6 transformerless inverter with a simple boost converter for pv...Single phase h6 transformerless inverter with a simple boost converter for pv...
Single phase h6 transformerless inverter with a simple boost converter for pv...eSAT Journals
 
Transmission and distribution system of nepal
Transmission and distribution system of nepalTransmission and distribution system of nepal
Transmission and distribution system of nepalBishal Rimal
 
Design and Simulation of transformer less Single Phase Photovoltaic Inverter ...
Design and Simulation of transformer less Single Phase Photovoltaic Inverter ...Design and Simulation of transformer less Single Phase Photovoltaic Inverter ...
Design and Simulation of transformer less Single Phase Photovoltaic Inverter ...IOSR Journals
 
Tranformerless H6 Grid Tied Inverter For Photovoltaic Generation
Tranformerless H6 Grid Tied Inverter For Photovoltaic GenerationTranformerless H6 Grid Tied Inverter For Photovoltaic Generation
Tranformerless H6 Grid Tied Inverter For Photovoltaic GenerationIJMER
 
Power loss analysis of current-modules based multilevel current-source power ...
Power loss analysis of current-modules based multilevel current-source power ...Power loss analysis of current-modules based multilevel current-source power ...
Power loss analysis of current-modules based multilevel current-source power ...TELKOMNIKA JOURNAL
 
Power System Analysis unit - I
Power System Analysis unit - IPower System Analysis unit - I
Power System Analysis unit - Iarunatshare
 
DESIGNING AND IMPLEMENTATION OF BI - DIRECTIONAL ISOLATED FULL BRIDGE CONVERTER
DESIGNING AND IMPLEMENTATION OF BI - DIRECTIONAL ISOLATED FULL BRIDGE CONVERTERDESIGNING AND IMPLEMENTATION OF BI - DIRECTIONAL ISOLATED FULL BRIDGE CONVERTER
DESIGNING AND IMPLEMENTATION OF BI - DIRECTIONAL ISOLATED FULL BRIDGE CONVERTEREditor IJMTER
 

What's hot (19)

main-project1
main-project1main-project1
main-project1
 
A comparative study of cascaded h bridge and reversing voltage multilevel inv...
A comparative study of cascaded h bridge and reversing voltage multilevel inv...A comparative study of cascaded h bridge and reversing voltage multilevel inv...
A comparative study of cascaded h bridge and reversing voltage multilevel inv...
 
An Improved Single Phase Transformer less Inverter Topology for Cost Effecti...
An Improved Single Phase Transformer less Inverter Topology  for Cost Effecti...An Improved Single Phase Transformer less Inverter Topology  for Cost Effecti...
An Improved Single Phase Transformer less Inverter Topology for Cost Effecti...
 
PSCAD Final Report
PSCAD Final ReportPSCAD Final Report
PSCAD Final Report
 
Pdu 2021 s2
Pdu 2021 s2Pdu 2021 s2
Pdu 2021 s2
 
6.[36 45]seven level modified cascaded inverter for induction motor drive app...
6.[36 45]seven level modified cascaded inverter for induction motor drive app...6.[36 45]seven level modified cascaded inverter for induction motor drive app...
6.[36 45]seven level modified cascaded inverter for induction motor drive app...
 
Analysis and simulation of multilevel inverter using multi carrier based pwm
Analysis and simulation of multilevel  inverter using multi carrier based pwmAnalysis and simulation of multilevel  inverter using multi carrier based pwm
Analysis and simulation of multilevel inverter using multi carrier based pwm
 
Modified cascaded multilevel inverter with ga to reduce line to line voltage thd
Modified cascaded multilevel inverter with ga to reduce line to line voltage thdModified cascaded multilevel inverter with ga to reduce line to line voltage thd
Modified cascaded multilevel inverter with ga to reduce line to line voltage thd
 
Electric09
Electric09Electric09
Electric09
 
Single phase h6 transformerless inverter with a simple boost converter for pv...
Single phase h6 transformerless inverter with a simple boost converter for pv...Single phase h6 transformerless inverter with a simple boost converter for pv...
Single phase h6 transformerless inverter with a simple boost converter for pv...
 
Transmission and distribution system of nepal
Transmission and distribution system of nepalTransmission and distribution system of nepal
Transmission and distribution system of nepal
 
Comparison of Multicarrier PWM Techniques for Cascaded H-Bridge Multilevel In...
Comparison of Multicarrier PWM Techniques for Cascaded H-Bridge Multilevel In...Comparison of Multicarrier PWM Techniques for Cascaded H-Bridge Multilevel In...
Comparison of Multicarrier PWM Techniques for Cascaded H-Bridge Multilevel In...
 
06646829
0664682906646829
06646829
 
Design and Simulation of transformer less Single Phase Photovoltaic Inverter ...
Design and Simulation of transformer less Single Phase Photovoltaic Inverter ...Design and Simulation of transformer less Single Phase Photovoltaic Inverter ...
Design and Simulation of transformer less Single Phase Photovoltaic Inverter ...
 
Structure of power system
Structure of power systemStructure of power system
Structure of power system
 
Tranformerless H6 Grid Tied Inverter For Photovoltaic Generation
Tranformerless H6 Grid Tied Inverter For Photovoltaic GenerationTranformerless H6 Grid Tied Inverter For Photovoltaic Generation
Tranformerless H6 Grid Tied Inverter For Photovoltaic Generation
 
Power loss analysis of current-modules based multilevel current-source power ...
Power loss analysis of current-modules based multilevel current-source power ...Power loss analysis of current-modules based multilevel current-source power ...
Power loss analysis of current-modules based multilevel current-source power ...
 
Power System Analysis unit - I
Power System Analysis unit - IPower System Analysis unit - I
Power System Analysis unit - I
 
DESIGNING AND IMPLEMENTATION OF BI - DIRECTIONAL ISOLATED FULL BRIDGE CONVERTER
DESIGNING AND IMPLEMENTATION OF BI - DIRECTIONAL ISOLATED FULL BRIDGE CONVERTERDESIGNING AND IMPLEMENTATION OF BI - DIRECTIONAL ISOLATED FULL BRIDGE CONVERTER
DESIGNING AND IMPLEMENTATION OF BI - DIRECTIONAL ISOLATED FULL BRIDGE CONVERTER
 

Similar to Psp unit 3

Power station practice (NEE-702) unit-3
Power station practice (NEE-702) unit-3Power station practice (NEE-702) unit-3
Power station practice (NEE-702) unit-3Md Irshad Ahmad
 
power grid design
power grid designpower grid design
power grid designsusanta das
 
NTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship reportNTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship reportAneel-k Suthar
 
Universal Four Leg v4
Universal Four Leg v4Universal Four Leg v4
Universal Four Leg v4AxelDijksman
 
Simulation of different power transmission systems and their capacity of redu...
Simulation of different power transmission systems and their capacity of redu...Simulation of different power transmission systems and their capacity of redu...
Simulation of different power transmission systems and their capacity of redu...eSAT Publishing House
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 7
Principles of Power Systems V.K Mehta Complete Book - Chapter 7Principles of Power Systems V.K Mehta Complete Book - Chapter 7
Principles of Power Systems V.K Mehta Complete Book - Chapter 7Power System Operation
 
Ppt power grid design
Ppt power grid designPpt power grid design
Ppt power grid designsusanta das
 
Design of substation
Design of substationDesign of substation
Design of substationSayanSarkar55
 
POWER QUALITY AND THD MITIGATION IN ELECTRIC VEHICLE CHARGING STATION BY THE ...
POWER QUALITY AND THD MITIGATION IN ELECTRIC VEHICLE CHARGING STATION BY THE ...POWER QUALITY AND THD MITIGATION IN ELECTRIC VEHICLE CHARGING STATION BY THE ...
POWER QUALITY AND THD MITIGATION IN ELECTRIC VEHICLE CHARGING STATION BY THE ...IRJET Journal
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)IJERD Editor
 
IRJET- Inductive Power Transfer System using Digital Controller based Matrix ...
IRJET- Inductive Power Transfer System using Digital Controller based Matrix ...IRJET- Inductive Power Transfer System using Digital Controller based Matrix ...
IRJET- Inductive Power Transfer System using Digital Controller based Matrix ...IRJET Journal
 
A Review on Selection of Proper Busbar Arrangement for Typical Substation (Bu...
A Review on Selection of Proper Busbar Arrangement for Typical Substation (Bu...A Review on Selection of Proper Busbar Arrangement for Typical Substation (Bu...
A Review on Selection of Proper Busbar Arrangement for Typical Substation (Bu...IRJET Journal
 
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdf
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdfHIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdf
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdfEMERSON EDUARDO RODRIGUES
 
Improving power quality in microgrid by means of using
Improving power quality in microgrid by means of usingImproving power quality in microgrid by means of using
Improving power quality in microgrid by means of usingeSAT Publishing House
 
Busduct___Busbar.pptx
Busduct___Busbar.pptxBusduct___Busbar.pptx
Busduct___Busbar.pptxpramod719257
 
Implementation of a grid-tied emergency back-up power supply for medium and l...
Implementation of a grid-tied emergency back-up power supply for medium and l...Implementation of a grid-tied emergency back-up power supply for medium and l...
Implementation of a grid-tied emergency back-up power supply for medium and l...IJECEIAES
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design) SayanSarkar55
 

Similar to Psp unit 3 (20)

Power station practice (NEE-702) unit-3
Power station practice (NEE-702) unit-3Power station practice (NEE-702) unit-3
Power station practice (NEE-702) unit-3
 
power grid design
power grid designpower grid design
power grid design
 
NTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship reportNTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship report
 
Universal Four Leg v4
Universal Four Leg v4Universal Four Leg v4
Universal Four Leg v4
 
Simulation of different power transmission systems and their capacity of redu...
Simulation of different power transmission systems and their capacity of redu...Simulation of different power transmission systems and their capacity of redu...
Simulation of different power transmission systems and their capacity of redu...
 
Substations
SubstationsSubstations
Substations
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 7
Principles of Power Systems V.K Mehta Complete Book - Chapter 7Principles of Power Systems V.K Mehta Complete Book - Chapter 7
Principles of Power Systems V.K Mehta Complete Book - Chapter 7
 
Ppt power grid design
Ppt power grid designPpt power grid design
Ppt power grid design
 
Design of substation
Design of substationDesign of substation
Design of substation
 
POWER QUALITY AND THD MITIGATION IN ELECTRIC VEHICLE CHARGING STATION BY THE ...
POWER QUALITY AND THD MITIGATION IN ELECTRIC VEHICLE CHARGING STATION BY THE ...POWER QUALITY AND THD MITIGATION IN ELECTRIC VEHICLE CHARGING STATION BY THE ...
POWER QUALITY AND THD MITIGATION IN ELECTRIC VEHICLE CHARGING STATION BY THE ...
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
IRJET- Inductive Power Transfer System using Digital Controller based Matrix ...
IRJET- Inductive Power Transfer System using Digital Controller based Matrix ...IRJET- Inductive Power Transfer System using Digital Controller based Matrix ...
IRJET- Inductive Power Transfer System using Digital Controller based Matrix ...
 
A Review on Selection of Proper Busbar Arrangement for Typical Substation (Bu...
A Review on Selection of Proper Busbar Arrangement for Typical Substation (Bu...A Review on Selection of Proper Busbar Arrangement for Typical Substation (Bu...
A Review on Selection of Proper Busbar Arrangement for Typical Substation (Bu...
 
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdf
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdfHIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdf
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdf
 
Improving power quality in microgrid by means of using
Improving power quality in microgrid by means of usingImproving power quality in microgrid by means of using
Improving power quality in microgrid by means of using
 
Busduct___Busbar.pptx
Busduct___Busbar.pptxBusduct___Busbar.pptx
Busduct___Busbar.pptx
 
Shashikdoc
ShashikdocShashikdoc
Shashikdoc
 
Implementation of a grid-tied emergency back-up power supply for medium and l...
Implementation of a grid-tied emergency back-up power supply for medium and l...Implementation of a grid-tied emergency back-up power supply for medium and l...
Implementation of a grid-tied emergency back-up power supply for medium and l...
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design)
 
A 220kV Substation
A 220kV SubstationA 220kV Substation
A 220kV Substation
 

Recently uploaded

Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxJiesonDelaCerna
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentInMediaRes1
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 

Recently uploaded (20)

Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptx
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media Component
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 

Psp unit 3

  • 1. Unit-IIIUnit-III Sub-stations Layout • Abhishek Srivastava • Electrical Engineering Department • Subject: : POWER STATION PRACTICE • (NEE /NEN–702)
  • 2. ContentsContents • UNIT- III: Sub-stations Layout • Types of substations, • Bus-bar arrangements, typical layout of substation. • Power Plant Economics and Tariffs • Load curve, load duration curve, different factors related to plants and consumers, Cost of electrical energy, depreciation, generation cost, effect of Load factor on unit cost. • Fixed and operating cost of different plants, role of load diversity in power system economy. Objectives and forms of Tariff; Causes and effects of low power factor, advantages of power factor improvement, different methods for power factor improvements.
  • 3. 33 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION THE TRANSFORMER BAY 3 What is a substation? An electrical substation takes electricity from a very high voltage and lowers it to the voltage we use in our homes & businesses
  • 4. 44 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  INTRODUCTION The present electrical power system is a complex interconnection of Generating stations-Transmission systems- Receiving stations- Distribution systems and Load points. In all the above phases of power flow, the transfer of electrical energy takes place in the electric sub stations. 4
  • 5. 55 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  Basically an electrical sub station consists of a number of incoming circuits and out going circuits connected to common bus bar systems.  Bus bars are conducting bars to which a number of incoming or out going circuits are connected. 5
  • 6. 66 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  INTRODUCTION Each circuit connected to the bus bar will have certain electrical component such as circuit breakers, isolators, earth switches, current transformers and voltage transformers. These components are connected in a definite sequence such that a circuit can be switched off during normal operation by manual command and also automatically during abnormal conditions such as short circuits. 6
  • 7. 77 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION A sub station receives electrical power from generating station through incoming transmission lines and delivers electrical power through the out going transmission lines. Sub station is an integral part of a power system and is an important link between the generating stations, transmission systems, distribution systems and load points. 7
  • 8. 88 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  DESIGN CONSIDERATIONS  The sub station is designed with an objective to provide maximum reliability, flexibility, continuity of service and to meet these objectives with the lowest investment costs that satisfy system requirement. 8
  • 9. 99 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  DESIGN CONSIDERATIONS 9 System requirements include the selection of optimum voltage levels depending on the load requirements and the transmission distances involved. Generally, the generating source will be far away from the load centers. The advantage of capitalizing on low site costs, availability of ample cooling water supply, economical fuel supply and less stringent environmental considerations compel construction of generating source far away from load centers, there by, increasing transmission distances.
  • 10. 1010 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  DESIGN CONSIDERATIONS  Hence, to transmit power over long distances the transmission voltage is to be increased and in our country 400 kV is becoming common and higher voltages for transmission is being explored. Many factors such as voltage level, load capacity, site space limitations, transmission line right of way requirement and environmental considerations influence the design of sub stations.  The system requirement must be met with minimum costs as the cost of equipment, labor, land and site treatment is increasing every day. 10
  • 11. 1111 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  BUS LAYOUT AND SWITCHING ARRANGEMENT  Since the major sub station costs are reflected in the power transformers, circuit breakers and disconnecting switches, the bus layout and switching arrangement selected will determine the number of switches and power circuit breakers required.  A number of factors must be considered in the selection of bus layouts and switching arrangements for a sub station to meet system and station requirements.  A sub station must be reliable, economical, safe, and as simple in design as possible. 11
  • 12. 1212 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  SUB STATION LAYOUT AND BUS BAR SCHEMES  The term layout denotes the physical arrangement of various components in the sub station relative to one another. The layout is significant as it influences the operation, maintenance, cost and protection of the sub station. These aspects are considered while designing the sub station layout. 12
  • 13. 1313 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  SUB STATION LAYOUT AND BUS BAR SCHEMES With the given number of incoming lines, out going lines, transformers, etc., the sub station can be designed in several alternative ways.  The physical arrangement of the equipment is called the layout of the sub station. The layout is illustrated by means of single line diagrams.  The design of sub station layout need careful consideration of several aspects such as: 13
  • 14. 1414 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  SUB STATION LAYOUT AND BUS BAR SCHEMES  Switching requirement for normal operation.  Switching requirement during abnormal conditions like short circuits and overloads.  Degree of flexibility in operations, simplicity.  Freedom from total shutdowns.  Maintenance requirements, space for approaching various equipment for maintenance.  Road/ rail for transporting main and auxiliary equipment. 14
  • 15. 1515 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  SUB STATION LAYOUT AND BUS BAR SCHEMES  Safety of personnel.  Protective zones for main and back up protection.  Provision for bye pass facilities and for extensions, space requirements.  Technical requirements such as ratings, clearances, earth system, lightning protection.  Requirement for SCADA and communication.  Compatibility for local and ambient condition. 15
  • 16. 1616 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  SUB STATION LAYOUT AND BUS BAR SCHEMES  The choice of bus bar schemes for ac yards depend upon several factors mentioned above. The important bus bar schemes are:  Single bus bar  Double bus bar with one breaker per circuit  Double bus bar with two breaker per circuit  Main and transfer bus  Ring bus or Mesh scheme  Breaker and a half(1 1/2 breaker) arrangement 16
  • 17. 1717 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  SUB STATION LAYOUT AND BUS BAR SCHEMES The various schemes are generally compared to emphasize their advantage and limitations.  The basis of comparison is generally the degree of reliability & economic justification.  The degree of reliability is evaluated by determining continuity of service under anticipated operating conditions and possible faults. 17
  • 18. 1818 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION VARIOUS BUS BAR SCHEMES  SINGLE BUS BAR SCHEME BUS ISOLATOR BREAKER CURRENT TRANSFORMER POWER TRANSFORMER 18
  • 19. 1919 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  SINGLE BUS BAR SCHEME  Advantage –Lowest cost  Disadvantage: Maintenance without interruption of supply is not possible. Sub station can not be extended without completely de- energizing the sub station Can be used only where loads can be interrupted or have other supply arrangements. Least flexibility. 19
  • 20. 2020 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  VARIOUS BUS BAR SCHEMES  SINGLE BUS BAR SCHEME WITH BUS SECTIONALISER BUS SECTION-2 ISOLATOR BREAKER CURRENT TRANSFORMER POWER TRANSFORMER BUS SECTION-1 SECTIONALISER 20
  • 21. 2121 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  SINGLE BUS BAR SCHEME WITH BUS SECTIONALISER Sectionalizing the single bus improves slightly the reliability if the incoming and out going circuits are distributed evenly on both the sections.  Where double feed is provided for any single load it is preferable to have one circuit from each section.  In this arrangement each section behaves as a separate bus bar and any outage can be confined to one section of the bus bar.  Only the faulty section will be tripped by bus differential protection. 21
  • 22. 2222 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  DOUBLE BUS BAR WITH ONE BREAKER PER CIRCUIT BUS-1 BUS-2 BUS COUPLER BREAKER POWER TRANSFORMER BREAKER 22
  • 23. 2323 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  DOUBLE BUS BAR WITH ONE BREAKER PER CIRCUIT  This arrangement has the following advantages:  Each load may be fed from either bus.  Operational flexibility may be increased by grouping the incoming and out going feeders in separate groups.  Either bus bar can be taken out for maintenance.  Bus coupler helps in ‘on load change over ‘from one bus to the other.  Adopted where load and continuity justify additional cost.  A major disadvantage is that the breaker can not be taken out for maintenance without interrupting supply to the concerned circuit. 23
  • 24. 2424 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  DOUBLE BUS BAR WITH ONE BREAKER PER CIRCUIT  Bus protection scheme may cause loss of sub station when it operates if all circuits are connected to that bus.  High exposure to bus faults.  Line breaker failure takes all circuits connected to that bus out of service.  Bus tie breaker failure takes the entire sub station out of service. 24
  • 25. 2525 DOUBLE MAIN BUS & CB BYPASS ISOLATOR SYSTEMDOUBLE MAIN BUS & CB BYPASS ISOLATOR SYSTEM FEEDER1 BUS-2BUS-2 BUS-1BUS-1 T/F-1 BUSCOUPLER FEEDER2 T/F-2 FEEDER3 FEEDER4 BAY1 BAY2 BAY3 BAY4 BAY5 BAY6 BAY7 FOR ANY CB PROBLEM OR FOR PREVENTIVE MAINTANENCE, SUCH FEEDER CAN BE SHIFTED TO ANOTHER BUS AND THE BYPASS ISOLATOR IS CLOSED, THEN PROTECTION IS TRANSFERRED TO BUS COUPLER AND THE FAULTY CB CAN BE ISOLATED.
  • 26. 2626 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  MAIN AND TRANSFER BUS MAIN BUS TRANSFER BUS BREAKERTIE BREAKER LINE LINE 26
  • 27. 2727 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  MAIN AND TRANSFER BUS  This is an alternative to double bus single breaker arrangement which provided for change over to either bus for carrying out maintenance on other bus. But it provided no facility for breaker maintenance without interrupting power supply to the concerned circuit.  The main and transfer bus works the other way round.  This arrangement provides facility for carrying out breaker maintenance but does not permit bus maintenance. 27
  • 28. 2828 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  MAIN AND TRANSFER BUS  Any breaker can be taken out of service for maintenance.  Wherever maintenance is required on any breaker, the circuit is changed over to the transfer bus and controlled through the bus coupler breaker.  Potential devices may be used on the main bus for relaying.  The cost is increased due to use of an extra isolator for each circuit and providing interlock for bus coupler and circuit isolators.  Relaying sensitivity decreases as the same bus coupler is used to energize the concerned circuit for all the circuit breakers whenever they are taken out for maintenance.  Failure of bus or any circuit breaker results in shut down of entire sub station. 28
  • 29. 2929 DOUBLE MAIN BUS & TRANSFER BUS SYSTEMDOUBLE MAIN BUS & TRANSFER BUS SYSTEM FEEDER1 BUS-2BUS-2 BUS-1BUS-1 FEEDER2 TRANSFERBUS COUPLER T/F-1 T/F-2 BUSCOUPLER TRANSFER BUSTRANSFER BUS FEEDER3 FEEDER4 BAY1 BAY2 BAY3 BAY4 BAY5 BAY6 BAY7 BAY8
  • 30. 3030 BUS BAR ARRANGEMENTSBUS BAR ARRANGEMENTS • Double Bus Bar Arrangement with Transfer Bus. This arrangement provides more additional flexibility, continuity of Power Supply, permits periodic maintenance without total shut down as the two main buses can be operated independently with the same redundancy.
  • 31. 3131 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  DOUBLE BUS BAR WITH TWO BREAKER PER CIRCUIT BUS-1 BUS-2 BREAKER LINE LINE 31
  • 32. 3232 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  DOUBLE BUS BAR WITH TWO BREAKER PER CIRCUIT  Each circuit has two dedicated breakers.  Has flexibility in permitting feeder circuits to be connected to either bus.  Any breaker can be taken out of service for maintenance.  High reliability.  Most expensive. Used only in large generating stations where security of connection is paramount. 32
  • 33. 3333 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION • RING BUS OR MESH SCHEME ISOLATOR BREAKER LINE LINE POWER TRANSFORMER 33
  • 34. 3434 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  RING BUS OR MESH SCHEME  In this scheme the breakers are arranged in a ring with circuits connected between breakers.  There are the same number of circuits as there are breakers.  During normal operation, all breakers are closed. For a circuit fault, two breakers are tripped, and in the event one of the breaker fails to operate to clear the fault, an additional circuit will be tripped by operation of breaker- failure back up relays.  During breaker maintenance, the ring is broken, but all lines remain in service. 34
  • 35. 3535 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION  RING BUS OR MESH SCHEME  The circuits connected to the ring are arranged so that sources are alternated with loads.  For an extended circuit outage, the line isolator may be opened and the ring can be closed.  No changes to protective relays are required for any of the various operating conditions or during maintenance.  The ring bus scheme is economical in cost, has good reliability, is safe for operation, is flexible, and is normally considered suitable for important sub stations up to a limit of five circuits.  It is common practice to build major sub stations initially as a ring bus; for more than five outgoing circuits, the ring bus is usually developed to the breaker-and-a-half scheme. 35
  • 36. 3636 THE ELECTRIC SUB STATIONTHE ELECTRIC SUB STATION • One and a Half Breaker Arrangement. This arrangement provides three circuit breakers for every two circuits. It gives high security against loss of supply but higher cost is involved. Hence this is provided for important 400/220 KV Sub Stations.
  • 37.
  • 38. Types of LoadsTypes of Loads Domestic Load Commercial Load Industrial Load Municipal Load Irrigation Load Traction Load
  • 39. Variable load on Power stationVariable load on Power station The load on a power station varies from time to time due to uncertain demands of the consumers and is known as variable load on the station. Effects of variable load Need of additional equipment Increase in production cost
  • 40. Load CurveLoad Curve The curve showing the variation of load on the power station with respect to time is known as a load curve
  • 41.
  • 42. Load duration CurveLoad duration Curve When the load elements of a load curve are arranged in the order of descending magnitude ,the curve thus obtained is called load duration curve.
  • 43. Important terms and factorsImportant terms and factors Connected load: It is the sum of continuous rating of all the equipments connected to supply system. Maximum Demand: It is the greatest demand of load of the power station during a given period. Demand factor: it is the ratio of maximum demand on the power station to its connected load.
  • 44. Important terms and factorsImportant terms and factors Average load: The average of loads occurring on the power station in a given period (day or month or year)is known as average load or average demand. Load factor: The ratio of average load to the maximum demand during a period is known as load factor. Diversity factor: The ratio of the sum of individual maximum demands to the maximum demand on power station
  • 45. Important terms and factorsImportant terms and factors Coincidence factor: The coincidence factor is the reciprocal of the diversity factor Contribution factor: it is the contribution of a particular load ,in per unit of the individual demand ,to the group maximum demand
  • 46. Important terms and factorsImportant terms and factors Plant Capacity factor: it is the ratio of actual energy produced to the maximum possible energy that could have been produced during a given period. Plant use factor: It is ratio of kWh generated to the product of plant capacity and the number of hours for which the plant was operation. Plant Utilization factor: it is the ratio of maximum load to the rated capacity.
  • 47. TariffTariff The rate at which electrical energy is supplied to a consumer is known tariff. Objectives of tariff  Recovery of production cost  Recovery of capital investment cost  Recovery of operation and maintenance cost  A suitable profit
  • 48. Desirable characteristics of aDesirable characteristics of a tarifftariff Proper return Fairness Simplicity Reasonable profit Attractive
  • 49. Types of tariffTypes of tariff Simple tariff Flat rate tariff Block rate tariff Two part tariff Maximum demand tariff Power factor tariff Three part tariff
  • 50. Simple tariff or uniform rateSimple tariff or uniform rate tarifftariff There is a fixed rate per unit of energy consumed. Advantages: Simplest tariff method and is readily understood by the consumers. Disadvantages: There is no discrimination between consumers The cost per unit delivery is high it does not encourage the use of electricity
  • 51. Flat rate tariffFlat rate tariff When different types of consumers are charged at different uniform per unit rate ,it is called a flat rate tariff. Advantanges: it is more fair to different types of consumers and is quite simple in calculations. Disadvantages:  Separate meters are requires for light and power load.  A particular class of consumers are charged at the same rate irrespective of the magnitude of energy consumed.
  • 52. Block rate tariffBlock rate tariff When a given block of energy is charged at a specified rate and the succeeding blocks of energy are charged at progressively reduced rates, it is called a block rate tariff. Advantages: Consumer gets an incentive to consume more energy. It increases the load factor.So cost of generation reduced. Disadvantages: it lacks a measure of consumers demand.
  • 53. Two part tariffTwo part tariff When the rate of electrical energy is charged on the basis of maximum demand of the consumers and the units consumed ,it is called a two-part tariff. In two-part tariff ,the total charges to be made from the consumer is split in to two components ,fixed charges and running charges. The fixed charge depends on the maximum demand in kW and running cost depends on the number of units consumed by the consumer in kWh. Total charges = b X kW+ c X kWh
  • 54. Two part tariffTwo part tariff Advantages: it is easily understood by the consumers it recovers the fixed charges which depend upon the maximum demand Disadvantages: The consumer has to pay the fixed charges irrespective of the fact whether he has consumed or not. There is always error in assessing the maximum demand of the consumer.
  • 55. Maximum demand tariffMaximum demand tariff It is similar to two-part tariff with the only difference that the maximum demand is actually measured by installing maximum demand meter in the premises of the consumer. Advantages: This removes the objection of two- part tariff Disadvantages: Not suitable for small consumers as a separate maximum demand meter is required.
  • 56. Power factor tariffPower factor tariff The tariff in which power factor of the consumer’s load taken in to consideration is known as power factor tariff. Types of power factor tariff: 1.kVA maximum demand tariff :It is modification of two part tariff. In this case fixed charges are made on the basis of maximum demand kVA and not in kW.
  • 57. 2.Sliding scale tariff : This is also known as average power factor tariff. In this case, an average power factor , say 0.8 lagging , is taken as reference. If the pf of consumer falls below this factor ,suitable additional charges are made or if pf of consumer above the reference ,a discount allowed to the consumer. 3.kW and kVAR tariff: In this type both kW and kVAR charged separately. Power factor tariffPower factor tariff
  • 58. Three part tariffThree part tariff When the total charges to be made from the consumer is split into three parts ,fixed charge ,semi fixed charge and running charge ,it is known as three part tariff. Total charge = a + bXkW + cXkWh a – fixed charge including intrest and depreciation on the cost of secondary distribution and labor cost of the collecting revenues. b – charge per kW maximum demand c – charge per kWh of energy consumed.
  • 59. Power factor and economics ofPower factor and economics of power factor correctionpower factor correction Power factor : The cosine of the angle between voltage and current in an AC circuit is known as power factor
  • 60. Disadvantages of low powerDisadvantages of low power factorfactor Large kVA rating equipment kVA = kW/cos ϕ Greater conductor size Large copper losses Poor voltage regulation Reduced handling capacity of system
  • 61. Causes of low factorCauses of low factor AC induction motors Arc lamps ,electric discharge and industrial heating furnaces Varying load on the power system
  • 62. Power factor improvementPower factor improvement equipmentequipment Static Capacitors: The power factor can be improved by connecting capacitors in parallel with the equipment operating at lagging power factor. Advantages:  They have low losses  Little maintenance  Easily installed  Can work under ordinary atmosphere condition Disadvantages  Short service life  Easily damaged with higher voltage  Repair uneconomical
  • 63. Synchronous CondenserSynchronous Condenser An over-excited synchronous motor running on no load known as synchronous condenser. Advantages:  Power factor can be controlled  Highly stable  Faulty can be removed easily Disadvantages:  Considerable losses in the motor  High maintenance cost  It produces noise  Not self starting one
  • 64. Phase advancersPhase advancers Phase advancers are used to improve the power factor of induction motors. The low power factor of an induction motor is due to the fact that its stator winding draws exciting current which lags behind the supply voltage by 90 degree. If the exciting ampere turns can be provided from some other AC source then the stator wining will be relieved of exciting current and the power factor of the motor can be improved. Advantages: kVAR lagging reduced ,convenient Disadvantages: Not economical for motors below 200HP
  • 65. Calculation of Power factorCalculation of Power factor correctioncorrection
  • 66. Methods for Power FactorMethods for Power Factor ImprovementImprovement • The following devices and equipment are used for Power Factor Improvement. • Static Capacitor • Synchronous Condenser • Phase Advancer
  • 67. 1. Static Capacitor1. Static Capacitor • Most of the industries and power system loads are inductive that take lagging current which decrease the system power factor (See Disadvantages of Low Power factor) . For Power factor improvement purpose, Static capacitors are connected in parallel with those devices which work on low power factor. • Advantages: • Capacitor bank offers several advantages over other methods of power factor improvement. • Losses are low in static capacitors • There is no moving part, therefore need low maintenance • It can work in normal conditions (i.e. ordinary atmospheric conditions) • Do not require a foundation for installation • They are lightweight so it is can be easy to installed • Disadvantages: • The age of static capacitor bank is less (8 – 10 years) • With changing load, we have to ON or OFF the capacitor bank, which causes switching surges on the system • If the rated voltage increases, then it causes damage it • Once the capacitors spoiled, then repairing is costly
  • 68. 2. Synchronous Condenser • When a Synchronous motor operates at No-Load and over-exited then it’s called a synchronous Condenser. Whenever a Synchronous motor is over-exited then it provides leading current and works like a capacitor. • When a synchronous condenser is connected across supply voltage (in parallel) then it draws leading current and partially eliminates the re-active component and this way, power factor is improved. Generally, synchronous condenser is used to improve the power factor in large industries. • Advantages: • Long life (almost 25 years),High Reliability • Step-less adjustment of power factor.,No generation of harmonics of maintenance • The faults can be removed easily • It’s not affected by harmonics. • Require Low maintenance (only periodic bearing greasing is necessary) • Disadvantages: • It is expensive (maintenance cost is also high) and therefore mostly used by large power users. • An auxiliary device has to be used for this operation because synchronous motor has no self starting torque • It produces noise
  • 69. 3. Phase Advancer • Phase advancer is a simple AC exciter which is connected on the main shaft of the motor and operates with the motor’s rotor circuit for power factor improvement. Phase advancer is used to improve the power factor of induction motor in industries. • As the stator windings of induction motor takes lagging current 90° out of phase with Voltage, therefore the power factor of induction motor is low. If the exciting ampere- turns are excited by external AC source, then there would be no effect of exciting current on stator windings. Therefore the power factor of induction motor will be improved. This process is done by Phase advancer. • Advantages: • Lagging kVAR (Reactive component of Power or reactive power) drawn by the motor is sufficiently reduced because the exciting ampere turns are supplied at slip frequency (fs). • The phase advancer can be easily used where the use of synchronous motors is Unacceptable • Disadvantage: • Using Phase advancer is not economical for motors below 200 H.P. (about 150kW)
  • 70. Load profileLoad profile • Load profile chart- Load curve • In electrical engineering, a load profile is a graph of the variation in the electrical load versus time. A load profile will vary according to customer type (typical examples include residential, commercial and industrial), temperature and holiday seasons.
  • 71. Power generationPower generation • In the electricity generation sector, a load curve is a chart showing the amount of electricity customers use over a period of time. • Generation companies use this information to plan how much power they will need to generate at any given time.
  • 72. Daily load curveDaily load curve • Time Hrs Load in KW 200 700 150
  • 73. Load curveLoad curve • Time Hrs Load in KW Avarage Load Max demand, peak load 00 24 08 18
  • 74. Load FactorLoad Factor • The ratio of the average load supplied during a designated period to the peak load occurring in that period, in kilowatts. • Simply, the load factor is the actual amount of kilowatt-hours delivered on a system in a designated period of time as opposed to the total possible kilowatt-hours that could be delivered on a system in a designated period of time. • Utilities are generally interested in increasing load factors on their systems. • A high load factor indicates high usage of the system’s equipment and is a measure of efficiency. High load factor customers are normally very desirable from a utility’s point of view. • Using a year as the designated period, the load factor is calculated by dividing the kilowatt-hours delivered during the year by the peak load for the year times the total number or hours during the year.
  • 75. Load factorLoad factor • Load factor (electrical) is the average power divided by the peak power over a period of time. • in the electricity industry, load factor is a measure of the output of a power plant. The two commonest definitions are: 1. the ratio of average load to peak load in a period. 2.the ratio of actual energy produced to The maximum energy that could have been produced if the maximum demand stays on for all the time. A higher load factor is better: * A power plant may be less efficient at low load factors. * A high load factor means fixed costs are spread over more kWh of output.
  • 76. Load FactorLoad Factor Daily LFDaily LF 24_max __ _ 24_max 24_ _ _ _ _ _max _ _ × = × × = = = demandimum producedenergyactual factorload demandimum demandaverage factorload demandpeak demandaverage factorload demandimum demandaverage factorload
  • 77. Load FactorsLoad Factors • Based on the period considered (Day,Week, Month,or year) • Daily LF • Weekly LF • Monthly LF • Yearly LF
  • 78. Diversity factorDiversity factor • Diversity factor: The ratio of sum of the individual non-coincident maximum demands of various subdivisions of the system to the maximum demand of the complete system. • The diversity factor is always more than or equal to 1. Diversity Factor = --------------------------------- Sum of Individual max demand Max demand on Power station