SlideShare a Scribd company logo
1 of 1
Optimization of an Electrostatic Bumper Painting Process
Presented by Brian Anichowski, Yucheng Guo, Steph Keller, John Menke, and Miles Reagans
Advised by Dr. Jose Castro, Dr. Rachmat Mulyana, Robert Rhoads, Dr. Cliff Whitfield, and Jake Allenstein
Multidisciplinary Capstone, Department of Engineering Education, The Ohio State University
Introduction
Objectives
Process Introduction
Baseline Testing Experimental Testing
Future Work or Acknowledgements??
• Typical painting processes involve spraying paint particles at the target,
and often allows for significant amount of overspray (the paint goes past
the part and doesn’t adhere to the intended surface).
• One method to reduce the overspray
is by electrostatically charging the
part and the paint. By negatively
charging the paint particles, and
grounding the part, the paint is
actively drawn to the surface of the
part.
• Negatively charging the paint is easy, however substantial difficulties exist
when attempting to ground the part. In particular, bumpers prove to be
extremely difficult because they are plastic, and therefore non-conductive.
• Ensure a consistent, proper grounding of the bumper.
• Ensure a consistent, proper checking of the grounding of the bumper
• Experimentally highlight key areas of focus within the grounding process.
• The bumper has a conductive primer
applied using conventional (non-
electrostatic) methods.
• Bumpers are loaded onto a metal carrier
which runs along a grounded carrier track
through the painting process.
• The bumpers are electrically connected to
the carrier through the use of clips (fixed
to the carrier) and conductive foil tape.
• Performed testing to isolate the problem areas of the process.
• Focused on...
1. Internal Carrier Resistance(s)
2. Paint Buildup
3. Ground Check System Accuracy
• The bumper is then ran through a
insulation checker to measure the
resistance to ground.
• If the bumper passes the resistance
check, it is sent through the paint
and clearcoat process before being
installed into the vehicle.
• First, the team measured the resistance
between the carrier and ground (see right)
with clean clips, to remove the impact of
paint buildup.
• Second, the team measured the same
resistance, but did NOT clean the clips.
• Internal carrier resistance was found to be negligible with respect to the
same tests with dirty clips ( ).
• The team then looked at the accuracy of the ground check system by
manually duplicating measurements with an ohmmeter.
carrier paintR R
• These tests showed the team that the ground check system was not working
as intended and was not accurately measuring the resistance to ground.
Experimental Testing
• From baseline testing, along with other areas of interest from the team, it
was decided to focus on four main topics:
1. Redesigned Carrier Clip
2. Circuit Verification
3. Flat Plate Primer Thickness Testing
4. Surface Contour Testing
Clip Redesign
• Team wanted to focus on mitigating paint
buildup
• One side of the carrier had an uncovered clip,
one side had a covered clip.
• (Qualitative) Results showed a decrease in the
paint on the contact surface with the covered
clip through 200 cycles.
Circuit Verification
• Testing was performed by introducing known resistance values (resistors)
into the circuit and recording the output from the check circuit system.
• The new configuration shows a 1:1 correlation between the actual and
measured resistance and a marked improvement from the original results.
Flat Plate Testing
• The team wanted to correlate primer thickness to paint thickness, so
different plates from the bumper material were primed them at different
thicknesses, then ran them through the bumper paint line.
• Little correlation can be seen here as primer thickness differed, although
the team believes more testing is required to validate results.
Contour Testing
• The team wanted to investigate the impact the surface profile of the
bumper had on primer thickness. Since primer thickness has been shown
to have an affect on resistance, it was assumed to be true here.
• As can be seen, distance from the grounding locations (red x’s) increases
the surface resistance. As well, adding a third grounding location reduced
the peak surface resistance by almost 60%.

More Related Content

What's hot

Testing of hardened concrete
Testing of hardened concreteTesting of hardened concrete
Testing of hardened concreteJ C
 
Condition Survey, Evaluation & Damage Assessment
Condition Survey, Evaluation & Damage AssessmentCondition Survey, Evaluation & Damage Assessment
Condition Survey, Evaluation & Damage Assessmentwasim shaikh
 
(19 02-13)--ndt tests & their importance
(19 02-13)--ndt tests & their importance(19 02-13)--ndt tests & their importance
(19 02-13)--ndt tests & their importanceRajesh Sharma
 
Ppt on test certificate-Amit Payal
Ppt on test certificate-Amit PayalPpt on test certificate-Amit Payal
Ppt on test certificate-Amit PayalAMIT PAYAL
 
Quality tests for aggregates and concrete mix design
Quality tests for aggregates and concrete mix designQuality tests for aggregates and concrete mix design
Quality tests for aggregates and concrete mix designAyaz khan
 
Penetration of bituminous materials
Penetration of bituminous materialsPenetration of bituminous materials
Penetration of bituminous materialsNUR
 
How to determine compressive strength of cement?
How to determine compressive strength of cement?How to determine compressive strength of cement?
How to determine compressive strength of cement?Civil Insider
 
Shape tests of aggregate
Shape tests of aggregateShape tests of aggregate
Shape tests of aggregateJacob shah
 
Rebound hammer test (non destructive test
Rebound hammer test (non destructive testRebound hammer test (non destructive test
Rebound hammer test (non destructive testAyaz khan
 
Non Destructive Testing -NDT
Non Destructive Testing -NDTNon Destructive Testing -NDT
Non Destructive Testing -NDTMANNU KUMAR
 
CE244 LAB RAPORU
CE244 LAB RAPORUCE244 LAB RAPORU
CE244 LAB RAPORU2001211020
 
Consistency test,Initial & Final setting time of Hydraulic Cement specimen
Consistency test,Initial & Final setting time of Hydraulic Cement specimenConsistency test,Initial & Final setting time of Hydraulic Cement specimen
Consistency test,Initial & Final setting time of Hydraulic Cement specimenMUST,Mirpur AJK,Pakistan
 
Sieve analysis test report
Sieve analysis test reportSieve analysis test report
Sieve analysis test reportPavitrah Segaran
 
Non destructive testing of structures
Non destructive testing of structuresNon destructive testing of structures
Non destructive testing of structuressanjanam9
 
Cube test for compressive strength of concrete
Cube test for compressive strength of concreteCube test for compressive strength of concrete
Cube test for compressive strength of concreteAyaz khan
 

What's hot (20)

Testing of hardened concrete
Testing of hardened concreteTesting of hardened concrete
Testing of hardened concrete
 
Compaction Factor Test
Compaction Factor TestCompaction Factor Test
Compaction Factor Test
 
Condition Survey, Evaluation & Damage Assessment
Condition Survey, Evaluation & Damage AssessmentCondition Survey, Evaluation & Damage Assessment
Condition Survey, Evaluation & Damage Assessment
 
Unit1 l3-rvr
Unit1 l3-rvrUnit1 l3-rvr
Unit1 l3-rvr
 
(19 02-13)--ndt tests & their importance
(19 02-13)--ndt tests & their importance(19 02-13)--ndt tests & their importance
(19 02-13)--ndt tests & their importance
 
Ppt on test certificate-Amit Payal
Ppt on test certificate-Amit PayalPpt on test certificate-Amit Payal
Ppt on test certificate-Amit Payal
 
Quality tests for aggregates and concrete mix design
Quality tests for aggregates and concrete mix designQuality tests for aggregates and concrete mix design
Quality tests for aggregates and concrete mix design
 
Penetration of bituminous materials
Penetration of bituminous materialsPenetration of bituminous materials
Penetration of bituminous materials
 
How to determine compressive strength of cement?
How to determine compressive strength of cement?How to determine compressive strength of cement?
How to determine compressive strength of cement?
 
Cement tests
Cement testsCement tests
Cement tests
 
Shape tests of aggregate
Shape tests of aggregateShape tests of aggregate
Shape tests of aggregate
 
Rebound hammer test (non destructive test
Rebound hammer test (non destructive testRebound hammer test (non destructive test
Rebound hammer test (non destructive test
 
Non Destructive Testing -NDT
Non Destructive Testing -NDTNon Destructive Testing -NDT
Non Destructive Testing -NDT
 
2 standard consistency of cement
2 standard consistency of cement2 standard consistency of cement
2 standard consistency of cement
 
4 soundness of cement.
4 soundness of cement.4 soundness of cement.
4 soundness of cement.
 
CE244 LAB RAPORU
CE244 LAB RAPORUCE244 LAB RAPORU
CE244 LAB RAPORU
 
Consistency test,Initial & Final setting time of Hydraulic Cement specimen
Consistency test,Initial & Final setting time of Hydraulic Cement specimenConsistency test,Initial & Final setting time of Hydraulic Cement specimen
Consistency test,Initial & Final setting time of Hydraulic Cement specimen
 
Sieve analysis test report
Sieve analysis test reportSieve analysis test report
Sieve analysis test report
 
Non destructive testing of structures
Non destructive testing of structuresNon destructive testing of structures
Non destructive testing of structures
 
Cube test for compressive strength of concrete
Cube test for compressive strength of concreteCube test for compressive strength of concrete
Cube test for compressive strength of concrete
 

Viewers also liked

BSHS 345 tutor Real Education / bshs345tutor.com
BSHS 345 tutor Real Education / bshs345tutor.comBSHS 345 tutor Real Education / bshs345tutor.com
BSHS 345 tutor Real Education / bshs345tutor.communnaq2
 
2010 New Year Presentation
2010 New Year Presentation2010 New Year Presentation
2010 New Year Presentationchaguang
 
сабитова айнагуль+английская школа+идея
сабитова айнагуль+английская школа+идеясабитова айнагуль+английская школа+идея
сабитова айнагуль+английская школа+идеяАйнагуль Сабитова
 
BAJU KAOS ISLAMI ANAK
BAJU KAOS ISLAMI ANAKBAJU KAOS ISLAMI ANAK
BAJU KAOS ISLAMI ANAKkaos islami
 
Page 5 terry zick-david kiesz
Page 5  terry zick-david kieszPage 5  terry zick-david kiesz
Page 5 terry zick-david kieszsacpros
 
Irish Museum of Modern Art - Aoife Flynn, Head of Audience and Development
Irish Museum of Modern Art - Aoife Flynn, Head of Audience and DevelopmentIrish Museum of Modern Art - Aoife Flynn, Head of Audience and Development
Irish Museum of Modern Art - Aoife Flynn, Head of Audience and DevelopmentMuseumNext
 
Low anion gap
Low anion gapLow anion gap
Low anion gapJoel Topf
 
Introduction To Chinese Language Characters 華語文簡介 Yamila
Introduction To Chinese Language   Characters 華語文簡介 YamilaIntroduction To Chinese Language   Characters 華語文簡介 Yamila
Introduction To Chinese Language Characters 華語文簡介 YamilaYamila Cheng
 
Needs Analysis Wait or Buy calculator
Needs Analysis Wait or Buy calculatorNeeds Analysis Wait or Buy calculator
Needs Analysis Wait or Buy calculatorHousehuntvictoria
 

Viewers also liked (15)

BSHS 345 tutor Real Education / bshs345tutor.com
BSHS 345 tutor Real Education / bshs345tutor.comBSHS 345 tutor Real Education / bshs345tutor.com
BSHS 345 tutor Real Education / bshs345tutor.com
 
Library personnel productivity
Library personnel productivityLibrary personnel productivity
Library personnel productivity
 
The verb to have
The verb to haveThe verb to have
The verb to have
 
fmtest
fmtestfmtest
fmtest
 
2010 New Year Presentation
2010 New Year Presentation2010 New Year Presentation
2010 New Year Presentation
 
Actividad17 144870
Actividad17 144870Actividad17 144870
Actividad17 144870
 
сабитова айнагуль+английская школа+идея
сабитова айнагуль+английская школа+идеясабитова айнагуль+английская школа+идея
сабитова айнагуль+английская школа+идея
 
BAJU KAOS ISLAMI ANAK
BAJU KAOS ISLAMI ANAKBAJU KAOS ISLAMI ANAK
BAJU KAOS ISLAMI ANAK
 
Page 5 terry zick-david kiesz
Page 5  terry zick-david kieszPage 5  terry zick-david kiesz
Page 5 terry zick-david kiesz
 
Irish Museum of Modern Art - Aoife Flynn, Head of Audience and Development
Irish Museum of Modern Art - Aoife Flynn, Head of Audience and DevelopmentIrish Museum of Modern Art - Aoife Flynn, Head of Audience and Development
Irish Museum of Modern Art - Aoife Flynn, Head of Audience and Development
 
Faltadeinversiontexto
FaltadeinversiontextoFaltadeinversiontexto
Faltadeinversiontexto
 
Low anion gap
Low anion gapLow anion gap
Low anion gap
 
Introduction To Chinese Language Characters 華語文簡介 Yamila
Introduction To Chinese Language   Characters 華語文簡介 YamilaIntroduction To Chinese Language   Characters 華語文簡介 Yamila
Introduction To Chinese Language Characters 華語文簡介 Yamila
 
Needs Analysis Wait or Buy calculator
Needs Analysis Wait or Buy calculatorNeeds Analysis Wait or Buy calculator
Needs Analysis Wait or Buy calculator
 
Beauty
BeautyBeauty
Beauty
 

Similar to BumperPoster

Adhesion test- Pull off adhesion testings.ppt
Adhesion test- Pull off adhesion testings.pptAdhesion test- Pull off adhesion testings.ppt
Adhesion test- Pull off adhesion testings.pptSwaminathanBoopathi
 
Material Testing, Machines And Equipment Requirements
Material Testing, Machines And Equipment RequirementsMaterial Testing, Machines And Equipment Requirements
Material Testing, Machines And Equipment Requirementsamrutaware2
 
MATERIAL TESTING,EQUIPMENTS.pptx
MATERIAL TESTING,EQUIPMENTS.pptxMATERIAL TESTING,EQUIPMENTS.pptx
MATERIAL TESTING,EQUIPMENTS.pptxPranotiHunungare
 
Non Destructive Test
Non Destructive TestNon Destructive Test
Non Destructive TestParth Desani
 
0_Project sample (1).pdsmzmcmzmczxmczcptx
0_Project sample (1).pdsmzmcmzmczxmczcptx0_Project sample (1).pdsmzmcmzmczxmczcptx
0_Project sample (1).pdsmzmcmzmczxmczcptxsmanjunarayana
 
Condition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteCondition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteAvinash Kumar Gupta
 
Condition survey and nde
Condition survey and ndeCondition survey and nde
Condition survey and ndeJay Bhavsar
 
Non destructive testing (Civil Engineering )
Non destructive testing (Civil Engineering )Non destructive testing (Civil Engineering )
Non destructive testing (Civil Engineering )AkashBhardwaj103
 
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restoration
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / RestorationNon-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restoration
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restorationpandian18
 
MATERIAL_TESTING_UOE final.pptx
MATERIAL_TESTING_UOE final.pptxMATERIAL_TESTING_UOE final.pptx
MATERIAL_TESTING_UOE final.pptxShashiShash2
 
1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptxJanak82
 
Non destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptxNon destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptxReigerRoyal
 
Non destructive test in CIVIL ENGINEERING Construction
Non destructive test in CIVIL ENGINEERING Construction Non destructive test in CIVIL ENGINEERING Construction
Non destructive test in CIVIL ENGINEERING Construction SAURABH GUPTA
 
Journal Club Presentationn 3 Cement.pptx
Journal Club Presentationn 3 Cement.pptxJournal Club Presentationn 3 Cement.pptx
Journal Club Presentationn 3 Cement.pptxHafizAli86
 
Insitu and lab tests
Insitu and lab testsInsitu and lab tests
Insitu and lab testsShah Naseer
 
Insitu and lab test
Insitu and lab testInsitu and lab test
Insitu and lab testShah Naseer
 
ESA Module 5 Part-A ME832. by Dr. Mohammed Imran
ESA Module 5 Part-A ME832. by Dr. Mohammed ImranESA Module 5 Part-A ME832. by Dr. Mohammed Imran
ESA Module 5 Part-A ME832. by Dr. Mohammed ImranMohammed Imran
 

Similar to BumperPoster (20)

Adhesion test- Pull off adhesion testings.ppt
Adhesion test- Pull off adhesion testings.pptAdhesion test- Pull off adhesion testings.ppt
Adhesion test- Pull off adhesion testings.ppt
 
UNIT 4.ppt
UNIT 4.pptUNIT 4.ppt
UNIT 4.ppt
 
Material Testing, Machines And Equipment Requirements
Material Testing, Machines And Equipment RequirementsMaterial Testing, Machines And Equipment Requirements
Material Testing, Machines And Equipment Requirements
 
MATERIAL TESTING,EQUIPMENTS.pptx
MATERIAL TESTING,EQUIPMENTS.pptxMATERIAL TESTING,EQUIPMENTS.pptx
MATERIAL TESTING,EQUIPMENTS.pptx
 
Non Destructive Test
Non Destructive TestNon Destructive Test
Non Destructive Test
 
0_Project sample (1).pdsmzmcmzmczxmczcptx
0_Project sample (1).pdsmzmcmzmczxmczcptx0_Project sample (1).pdsmzmcmzmczxmczcptx
0_Project sample (1).pdsmzmcmzmczxmczcptx
 
Condition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteCondition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concrete
 
Condition survey and nde
Condition survey and ndeCondition survey and nde
Condition survey and nde
 
Non destructive testing (Civil Engineering )
Non destructive testing (Civil Engineering )Non destructive testing (Civil Engineering )
Non destructive testing (Civil Engineering )
 
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restoration
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / RestorationNon-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restoration
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restoration
 
MATERIAL_TESTING_UOE final.pptx
MATERIAL_TESTING_UOE final.pptxMATERIAL_TESTING_UOE final.pptx
MATERIAL_TESTING_UOE final.pptx
 
1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx
 
Non destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptxNon destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptx
 
Non destructive test in CIVIL ENGINEERING Construction
Non destructive test in CIVIL ENGINEERING Construction Non destructive test in CIVIL ENGINEERING Construction
Non destructive test in CIVIL ENGINEERING Construction
 
Journal Club Presentationn 3 Cement.pptx
Journal Club Presentationn 3 Cement.pptxJournal Club Presentationn 3 Cement.pptx
Journal Club Presentationn 3 Cement.pptx
 
Introduction to linings
Introduction to liningsIntroduction to linings
Introduction to linings
 
Insitu and lab tests
Insitu and lab testsInsitu and lab tests
Insitu and lab tests
 
Insitu and lab test
Insitu and lab testInsitu and lab test
Insitu and lab test
 
Fresh and harden properties of concrete
Fresh and harden properties of concreteFresh and harden properties of concrete
Fresh and harden properties of concrete
 
ESA Module 5 Part-A ME832. by Dr. Mohammed Imran
ESA Module 5 Part-A ME832. by Dr. Mohammed ImranESA Module 5 Part-A ME832. by Dr. Mohammed Imran
ESA Module 5 Part-A ME832. by Dr. Mohammed Imran
 

BumperPoster

  • 1. Optimization of an Electrostatic Bumper Painting Process Presented by Brian Anichowski, Yucheng Guo, Steph Keller, John Menke, and Miles Reagans Advised by Dr. Jose Castro, Dr. Rachmat Mulyana, Robert Rhoads, Dr. Cliff Whitfield, and Jake Allenstein Multidisciplinary Capstone, Department of Engineering Education, The Ohio State University Introduction Objectives Process Introduction Baseline Testing Experimental Testing Future Work or Acknowledgements?? • Typical painting processes involve spraying paint particles at the target, and often allows for significant amount of overspray (the paint goes past the part and doesn’t adhere to the intended surface). • One method to reduce the overspray is by electrostatically charging the part and the paint. By negatively charging the paint particles, and grounding the part, the paint is actively drawn to the surface of the part. • Negatively charging the paint is easy, however substantial difficulties exist when attempting to ground the part. In particular, bumpers prove to be extremely difficult because they are plastic, and therefore non-conductive. • Ensure a consistent, proper grounding of the bumper. • Ensure a consistent, proper checking of the grounding of the bumper • Experimentally highlight key areas of focus within the grounding process. • The bumper has a conductive primer applied using conventional (non- electrostatic) methods. • Bumpers are loaded onto a metal carrier which runs along a grounded carrier track through the painting process. • The bumpers are electrically connected to the carrier through the use of clips (fixed to the carrier) and conductive foil tape. • Performed testing to isolate the problem areas of the process. • Focused on... 1. Internal Carrier Resistance(s) 2. Paint Buildup 3. Ground Check System Accuracy • The bumper is then ran through a insulation checker to measure the resistance to ground. • If the bumper passes the resistance check, it is sent through the paint and clearcoat process before being installed into the vehicle. • First, the team measured the resistance between the carrier and ground (see right) with clean clips, to remove the impact of paint buildup. • Second, the team measured the same resistance, but did NOT clean the clips. • Internal carrier resistance was found to be negligible with respect to the same tests with dirty clips ( ). • The team then looked at the accuracy of the ground check system by manually duplicating measurements with an ohmmeter. carrier paintR R • These tests showed the team that the ground check system was not working as intended and was not accurately measuring the resistance to ground. Experimental Testing • From baseline testing, along with other areas of interest from the team, it was decided to focus on four main topics: 1. Redesigned Carrier Clip 2. Circuit Verification 3. Flat Plate Primer Thickness Testing 4. Surface Contour Testing Clip Redesign • Team wanted to focus on mitigating paint buildup • One side of the carrier had an uncovered clip, one side had a covered clip. • (Qualitative) Results showed a decrease in the paint on the contact surface with the covered clip through 200 cycles. Circuit Verification • Testing was performed by introducing known resistance values (resistors) into the circuit and recording the output from the check circuit system. • The new configuration shows a 1:1 correlation between the actual and measured resistance and a marked improvement from the original results. Flat Plate Testing • The team wanted to correlate primer thickness to paint thickness, so different plates from the bumper material were primed them at different thicknesses, then ran them through the bumper paint line. • Little correlation can be seen here as primer thickness differed, although the team believes more testing is required to validate results. Contour Testing • The team wanted to investigate the impact the surface profile of the bumper had on primer thickness. Since primer thickness has been shown to have an affect on resistance, it was assumed to be true here. • As can be seen, distance from the grounding locations (red x’s) increases the surface resistance. As well, adding a third grounding location reduced the peak surface resistance by almost 60%.