SlideShare a Scribd company logo
1 of 2
Download to read offline
Project Spotlight
Conwy Tubular Railway Bridge
Kaymac Marine & Civil Engineering Ltd
Client: Birse Rail
Duration: 4 weeks- Completed April 2009
Value: £150,000.00
Conwy Tubular Railway Bridge (Underbridge No. 110), which carries the North Wales coast railway line across the River Conwy between Llandudno
Junction and the town of Conwy, was built by Robert Stephenson in 1848. The superstructure is formed from two wrought iron tubular box girders
which carry the railway lines, with masonry castellated abutments that compliment the adjacent Conwy castle. An assessment in 1899-1900
showed that the tubes were theoretically overstressed under loadings from the heaviest locomotives running at the time, and this entailed the
construction of additional piers at each end of the tubes at points of the span.
Kaymac Marine & Civil Engineering Ltd were commissioned by Birse Rail to carry out works to remove two existing inspection gantries from the
Conwy tubular railway bridge. The gantries were deemed redundant by Network Rail and required removal from both tubes. Conway Tubular
Bridge is a listed structure set within a SSSI area.
Due to access restrictions for plant and equipment on to the top of the tubular spans, it
was decided early in the project to utilise floating plant to systematically dismantle the
inspection gantries. Therefore a modular pontoon system was mobilised to site consisting
of 16 Linkflote units, which when assembled, resulted in a work barge with a deck area of
210m², complete with 2 no. 12m long spud legs and winches. Due to the high rate of tidal
flow below the bridge structure, the support vessel ‘Sabrina’, a converted landing craft
equipped with 600hp engines, was utilised to mobilise the work barge into position below
the structure.
To allow access from the work barge to the gantries, 2 no. Genie Z34/22 articulated boom
MEWP’s were mobilised from the shore to the work barge on board ‘Sabrina’. Each
MEWP had the hydraulic oil replaced with a vegetable based replacement prior to
mobilisation. The MEWP’s were then used to allow IPAF trained personnel to reach the
structures and rig 4 6.5t air hoists at both sides of each tube.
Each air hoist weighed in at 170kg, and was lifted up the outside face of each vertical
section of gantry using chain hoists. With the air hoists in position and securely rigged,
the lower underslung sections of the gantries were flame cut from the vertical elements
working from the MEWP’s. Once separated, the underslung sections were lowered onto
the deck of the work barge on the air hoists for disposal.
Before removing the side sections of the gantries, the trolleys on which they were
originally moved across the tubes were secured to their rails with cam type strops
providing 14t of down force. This was to prevent any overturning moment of the trolleys
during the dismantling process.
Project Spotlight
Conwy Tubular Railway Bridge
Kaymac Marine & Civil Engineering Ltd
Client: Birse Rail
Duration: 4 weeks- Completed April 2009
Value: £150,000.00
The side sections were then rigged to the air hoists and flame cut and lowered down to
the deck of the work barge for disposal. With the MEWP’s having proved successful in
providing access for the removal of the underslung and vertical sections of the gantry,
they were demobilised to allow the removal of the remaining trolley assemblies on the
top of the tubes.
To provide adequate lifting duty and radius from the work barge, a 30t telescopic crawler
crane was mobilised from the shore using ‘Sabrina’. As with the MEWP’s, the hydraulic oil
within the crane was replaced with a vegetable based alternative.
The work barge was then mobilised into position to allow the crane to access the trolley
on the downstream tube. This meant that the crane was now positioned between two
iconic listed structures, Stevenson’s Tubular Bridge and Thomas Telford’s Conwy
Suspension Bridge. Using the full extent of the 28m of crane jib, the 3t trolley was
successfully lifted off the rails, slewed between the 2 bridge structures and lowered
down onto the work barge.
The work barge was then moved upstream of the bridge structure for the final lifting
operation.
On the incoming flood tide, the crane lifted the second gantry trolley clear of the bridge
tube. The gantry section was successfully lowered into the hold of the ‘Sabrina’. The
crane was then demobilised to shore on the next suitable high tide.
The work barge was demobilised 4 days later on a night time high tide to reduce access
problems with local residents.

More Related Content

What's hot

locomotive Haulage presentation
locomotive Haulage  presentationlocomotive Haulage  presentation
locomotive Haulage presentationwaseemanwar31
 
The Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the worldThe Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the worldADARSH _
 
Presentation on chenab bridge by Aamir Khan
Presentation on chenab bridge by Aamir KhanPresentation on chenab bridge by Aamir Khan
Presentation on chenab bridge by Aamir KhanAamir Rajput Khan
 
Mining Machinery Learning Material
Mining Machinery Learning MaterialMining Machinery Learning Material
Mining Machinery Learning MaterialBhaskar Naidu
 
conceptual desig of Chenab bridge
conceptual desig of Chenab bridge conceptual desig of Chenab bridge
conceptual desig of Chenab bridge muzafar farooq
 
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONBhavek Sharma
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaRubnawaz Bhatti
 
Presentation on Suspension Bridge
Presentation on Suspension BridgePresentation on Suspension Bridge
Presentation on Suspension Bridgemantukr4ever
 
Samuel beckett bridge
Samuel beckett bridge Samuel beckett bridge
Samuel beckett bridge Dhruv Seth
 
Mine locomotive ppt (under ground transport system )
Mine locomotive ppt (under ground transport system )Mine locomotive ppt (under ground transport system )
Mine locomotive ppt (under ground transport system )AMIT SAHU
 
Cable suspension bridge pdf
Cable suspension bridge pdfCable suspension bridge pdf
Cable suspension bridge pdfGaurav Rawat
 
Worldhighestrailwaybridge
Worldhighestrailwaybridge Worldhighestrailwaybridge
Worldhighestrailwaybridge Hakkim Shajahan
 
Chenab Bridge, Jammu and Kashmir - Railway Technology
Chenab Bridge, Jammu and Kashmir - Railway TechnologyChenab Bridge, Jammu and Kashmir - Railway Technology
Chenab Bridge, Jammu and Kashmir - Railway TechnologyPradeep Kumar
 

What's hot (20)

locomotive Haulage presentation
locomotive Haulage  presentationlocomotive Haulage  presentation
locomotive Haulage presentation
 
Bridges
BridgesBridges
Bridges
 
The Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the worldThe Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the world
 
Presentation on chenab bridge by Aamir Khan
Presentation on chenab bridge by Aamir KhanPresentation on chenab bridge by Aamir Khan
Presentation on chenab bridge by Aamir Khan
 
Mining Machinery Learning Material
Mining Machinery Learning MaterialMining Machinery Learning Material
Mining Machinery Learning Material
 
conceptual desig of Chenab bridge
conceptual desig of Chenab bridge conceptual desig of Chenab bridge
conceptual desig of Chenab bridge
 
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
 
Chenab Bridge
Chenab BridgeChenab Bridge
Chenab Bridge
 
Presentation on Suspension Bridge
Presentation on Suspension BridgePresentation on Suspension Bridge
Presentation on Suspension Bridge
 
Aerial ropeway
Aerial ropewayAerial ropeway
Aerial ropeway
 
Ppt mine machinery
Ppt mine machineryPpt mine machinery
Ppt mine machinery
 
Samuel beckett bridge
Samuel beckett bridge Samuel beckett bridge
Samuel beckett bridge
 
Mine locomotive ppt (under ground transport system )
Mine locomotive ppt (under ground transport system )Mine locomotive ppt (under ground transport system )
Mine locomotive ppt (under ground transport system )
 
Cable suspension bridge pdf
Cable suspension bridge pdfCable suspension bridge pdf
Cable suspension bridge pdf
 
BRIDGE OVERVIEW
BRIDGE OVERVIEWBRIDGE OVERVIEW
BRIDGE OVERVIEW
 
Worldhighestrailwaybridge
Worldhighestrailwaybridge Worldhighestrailwaybridge
Worldhighestrailwaybridge
 
Chenab Bridge, Jammu and Kashmir - Railway Technology
Chenab Bridge, Jammu and Kashmir - Railway TechnologyChenab Bridge, Jammu and Kashmir - Railway Technology
Chenab Bridge, Jammu and Kashmir - Railway Technology
 
Longwall machinery
Longwall  machineryLongwall  machinery
Longwall machinery
 
Sustainable Bridges
Sustainable BridgesSustainable Bridges
Sustainable Bridges
 

Viewers also liked

ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE & NON DESTRUCTIVE TE...
ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE &  NON DESTRUCTIVE TE...ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE &  NON DESTRUCTIVE TE...
ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE & NON DESTRUCTIVE TE...GLA University
 
Lecture 3: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa Gabr
Lecture 3: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa GabrLecture 3: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa Gabr
Lecture 3: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa GabrHossam Shafiq I
 
General layout of steel structures
General layout of steel structuresGeneral layout of steel structures
General layout of steel structuresMaha Hassan
 
Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)sharda university
 
Bridge
Bridge Bridge
Bridge illpa
 
Lecture 1: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa Gabr
Lecture 1: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa Gabr Lecture 1: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa Gabr
Lecture 1: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa Gabr Hossam Shafiq I
 

Viewers also liked (7)

ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE & NON DESTRUCTIVE TE...
ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE &  NON DESTRUCTIVE TE...ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE &  NON DESTRUCTIVE TE...
ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE & NON DESTRUCTIVE TE...
 
Lecture 3: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa Gabr
Lecture 3: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa GabrLecture 3: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa Gabr
Lecture 3: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa Gabr
 
General layout of steel structures
General layout of steel structuresGeneral layout of steel structures
General layout of steel structures
 
Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Bridge
Bridge Bridge
Bridge
 
Lecture 1: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa Gabr
Lecture 1: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa Gabr Lecture 1: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa Gabr
Lecture 1: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa Gabr
 

Similar to Conwy Tubular Railway Bridge

Millau Bridge (Operations Management)
Millau Bridge (Operations Management)Millau Bridge (Operations Management)
Millau Bridge (Operations Management)Rohan Negi
 
Warsak Hydro Power Plant
Warsak Hydro Power PlantWarsak Hydro Power Plant
Warsak Hydro Power PlantMoiz Rao
 
H & d ppt 06 repair docks
H & d ppt 06 repair docksH & d ppt 06 repair docks
H & d ppt 06 repair docksHasna Hassan
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuVishweshwar Rao Narla
 
Suspension bridge (modern const. tech)
Suspension bridge (modern const. tech)Suspension bridge (modern const. tech)
Suspension bridge (modern const. tech)Vivek Chauhan
 
Millau via duct presentation full analysis
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysisMohammad Ali
 
Shaft sinking.
Shaft sinking.Shaft sinking.
Shaft sinking.Safdar Ali
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMIshant Gautam.
 
Bandra+worli+sea+link
Bandra+worli+sea+linkBandra+worli+sea+link
Bandra+worli+sea+linkASHOK KUMAR
 
Megastructures design pdf
Megastructures design pdfMegastructures design pdf
Megastructures design pdfSaqib Imran
 
Boom Structural Design and Static Finite Element Analysis for a 1000tons Shee...
Boom Structural Design and Static Finite Element Analysis for a 1000tons Shee...Boom Structural Design and Static Finite Element Analysis for a 1000tons Shee...
Boom Structural Design and Static Finite Element Analysis for a 1000tons Shee...IRJET Journal
 
Electriclocomoti00newt
Electriclocomoti00newtElectriclocomoti00newt
Electriclocomoti00newtGore Tavi
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge EngineeringKHUSHBU SHAH
 
Regulating structure for canal flow
Regulating structure for canal flowRegulating structure for canal flow
Regulating structure for canal flowCivil engeeneer
 

Similar to Conwy Tubular Railway Bridge (20)

Millau Bridge (Operations Management)
Millau Bridge (Operations Management)Millau Bridge (Operations Management)
Millau Bridge (Operations Management)
 
Millau viaduct
Millau viaductMillau viaduct
Millau viaduct
 
Millau viaduct
Millau viaductMillau viaduct
Millau viaduct
 
Warsak Hydro Power Plant
Warsak Hydro Power PlantWarsak Hydro Power Plant
Warsak Hydro Power Plant
 
Susppension bridges
Susppension bridges Susppension bridges
Susppension bridges
 
Project report
Project reportProject report
Project report
 
H & d ppt 06 repair docks
H & d ppt 06 repair docksH & d ppt 06 repair docks
H & d ppt 06 repair docks
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara Setu
 
Suspension bridge (modern const. tech)
Suspension bridge (modern const. tech)Suspension bridge (modern const. tech)
Suspension bridge (modern const. tech)
 
Millau via duct presentation full analysis
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysis
 
Bandra worli sealink pdf
Bandra worli sealink pdfBandra worli sealink pdf
Bandra worli sealink pdf
 
Shaft sinking.
Shaft sinking.Shaft sinking.
Shaft sinking.
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
 
Bandra+worli+sea+link
Bandra+worli+sea+linkBandra+worli+sea+link
Bandra+worli+sea+link
 
Megastructures design pdf
Megastructures design pdfMegastructures design pdf
Megastructures design pdf
 
456.pdf
456.pdf456.pdf
456.pdf
 
Boom Structural Design and Static Finite Element Analysis for a 1000tons Shee...
Boom Structural Design and Static Finite Element Analysis for a 1000tons Shee...Boom Structural Design and Static Finite Element Analysis for a 1000tons Shee...
Boom Structural Design and Static Finite Element Analysis for a 1000tons Shee...
 
Electriclocomoti00newt
Electriclocomoti00newtElectriclocomoti00newt
Electriclocomoti00newt
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
 
Regulating structure for canal flow
Regulating structure for canal flowRegulating structure for canal flow
Regulating structure for canal flow
 

Conwy Tubular Railway Bridge

  • 1. Project Spotlight Conwy Tubular Railway Bridge Kaymac Marine & Civil Engineering Ltd Client: Birse Rail Duration: 4 weeks- Completed April 2009 Value: £150,000.00 Conwy Tubular Railway Bridge (Underbridge No. 110), which carries the North Wales coast railway line across the River Conwy between Llandudno Junction and the town of Conwy, was built by Robert Stephenson in 1848. The superstructure is formed from two wrought iron tubular box girders which carry the railway lines, with masonry castellated abutments that compliment the adjacent Conwy castle. An assessment in 1899-1900 showed that the tubes were theoretically overstressed under loadings from the heaviest locomotives running at the time, and this entailed the construction of additional piers at each end of the tubes at points of the span. Kaymac Marine & Civil Engineering Ltd were commissioned by Birse Rail to carry out works to remove two existing inspection gantries from the Conwy tubular railway bridge. The gantries were deemed redundant by Network Rail and required removal from both tubes. Conway Tubular Bridge is a listed structure set within a SSSI area. Due to access restrictions for plant and equipment on to the top of the tubular spans, it was decided early in the project to utilise floating plant to systematically dismantle the inspection gantries. Therefore a modular pontoon system was mobilised to site consisting of 16 Linkflote units, which when assembled, resulted in a work barge with a deck area of 210m², complete with 2 no. 12m long spud legs and winches. Due to the high rate of tidal flow below the bridge structure, the support vessel ‘Sabrina’, a converted landing craft equipped with 600hp engines, was utilised to mobilise the work barge into position below the structure. To allow access from the work barge to the gantries, 2 no. Genie Z34/22 articulated boom MEWP’s were mobilised from the shore to the work barge on board ‘Sabrina’. Each MEWP had the hydraulic oil replaced with a vegetable based replacement prior to mobilisation. The MEWP’s were then used to allow IPAF trained personnel to reach the structures and rig 4 6.5t air hoists at both sides of each tube. Each air hoist weighed in at 170kg, and was lifted up the outside face of each vertical section of gantry using chain hoists. With the air hoists in position and securely rigged, the lower underslung sections of the gantries were flame cut from the vertical elements working from the MEWP’s. Once separated, the underslung sections were lowered onto the deck of the work barge on the air hoists for disposal. Before removing the side sections of the gantries, the trolleys on which they were originally moved across the tubes were secured to their rails with cam type strops providing 14t of down force. This was to prevent any overturning moment of the trolleys during the dismantling process.
  • 2. Project Spotlight Conwy Tubular Railway Bridge Kaymac Marine & Civil Engineering Ltd Client: Birse Rail Duration: 4 weeks- Completed April 2009 Value: £150,000.00 The side sections were then rigged to the air hoists and flame cut and lowered down to the deck of the work barge for disposal. With the MEWP’s having proved successful in providing access for the removal of the underslung and vertical sections of the gantry, they were demobilised to allow the removal of the remaining trolley assemblies on the top of the tubes. To provide adequate lifting duty and radius from the work barge, a 30t telescopic crawler crane was mobilised from the shore using ‘Sabrina’. As with the MEWP’s, the hydraulic oil within the crane was replaced with a vegetable based alternative. The work barge was then mobilised into position to allow the crane to access the trolley on the downstream tube. This meant that the crane was now positioned between two iconic listed structures, Stevenson’s Tubular Bridge and Thomas Telford’s Conwy Suspension Bridge. Using the full extent of the 28m of crane jib, the 3t trolley was successfully lifted off the rails, slewed between the 2 bridge structures and lowered down onto the work barge. The work barge was then moved upstream of the bridge structure for the final lifting operation. On the incoming flood tide, the crane lifted the second gantry trolley clear of the bridge tube. The gantry section was successfully lowered into the hold of the ‘Sabrina’. The crane was then demobilised to shore on the next suitable high tide. The work barge was demobilised 4 days later on a night time high tide to reduce access problems with local residents.