SlideShare a Scribd company logo
1 of 37
Project 17:
Hangar Air Quality and Energy Consumption Analysis
1
Sponsor:
College of Engineering
Faculty Mentor:
Li Song
Company Mentor:
Aruna Abhayagoonawardhana
Group Members:
Sara Bondy
Kyle Mcgee
Bridget Taylor
Tyler Totten
2
Team Duties
3
The Facility
● Hangar Function:
• Secondary
Paint/Stencil facility for Military
Planes
• Painting only done
10% of the time
• 100% outside air
intake
• Heating needed
during winter
• Eight fans run 100%
of the time
• Has a non-painting 4
Deliverables Required
● Determine current energy
consumption
● Calculate potential savings from
reducing number of fans in use
● Find time it takes for the room to
clear of VOC’s within safe range
● Make recommendations to Tinker
on how to implement demand
controlled ventilation
5
Deliverables Required
6
Determine
time for a
return on DCV
investment
Demand
Controlled
Ventilation
(DCV)
Determine
SAFE VOC
levels
Find highest
concentration
location
Prove VOC
level will
remain at a
SAFE level
FEASIBILITY
Determine
potential
savings
SAFETY
Volatile Organic Compounds
● Volatized: released in vapor form
● Negative effect on human health
● 400+ varieties of VOCs
● Emitted from
o paints
o paint strippers
● VOC limits for aerosol are 150 PPM
over a 6 hour period
● Photoionization detector
● 10.6 eV Krypton Lamp
7
Demand Controlled Ventilation
• Standard vent. systems control vent. from
preset “worst-case” scenarios
• Too little vent. breathing in pollutants
• Too much vent. energy waste
• DCV continuously controls ventilation
• VOC sensors will control ventilation mode
inside hangar
8
Strategic Plan
9
Research
Develop
Technical Plan
Analyze Results
Conclusions
Simulation
Analysis
Experimental
Analysis
Schedule
10
Finances
Expenses
Indoor air quality manual $ 66.96
Tripod $ 48.60
Sensor Rental $ 702.00
Total $ 817.56
11
Technical Approach
Objective: Prove the SAFETY and FEASIBILITY of implementing
Simulation Analysis Experimental Analysis
Create CAD Models
Place sensor inside hangar
Run simulation to find VOC
concentration
Record and analyze data
Calculate amount of time that is needed for
the VOC’s to dissipate to a safe level
Make recommendations for demand
controlled ventilation
12
Demand Controlled Ventilation
Create CAD models
for aircraft and the
hangar
Simulation Analysis
Objective: Create a model to analyze the VOC distribution inside the hangar
and to verify results from the experimental portion
13
Calculate amount of
time that is needed for
the VOC’s to dissipate
to a safe level
Calculate VOC
concentration during
paint mode and non-
paint mode
Find the highest VOC
concentration location
Current Conditions
● Four Inlet fans with an airspeed velocity of
40 m/s
● Two outlet vents with two fans in each
operating at 101 Pa
● Each fan operates at 80 HP
● VOC’s are emitted from the center of the
hanger at a velocity of 25 m/s
● Paint guns operate between 689 and 827
kPa
● Between .517 and .3878 grams of VOC are
released per liter of air
14
Building Specs
Dimensions:
Hangar: 63.1m X 50.6m X 18.29m
Inlet Vents: 2m X 2m
Filter: 7.62m X 8.6m
Cross Sectional Area:
Hangar: 1154.1 m2
Vent: 4 * 4 m2 = 16 m2
Filter: 65.5 m2
15
Modeling the Hangar
Plane Types:
KC-10,C-130, C-135, E-5, E-6
16
Assumptions
Option Setting Validation
Bay Doors Closed Confirmed via Tinker
Pressure 1 atm Confirmed via Meter
Room/Fluid
Temperature
18°C Confirmed via Specs
Heat Transfer Model Isothermal Marginal Impact
Pressure Average Whole Outlet Marginal Impact
Wall Roughness Smooth Confirmed via Visit
Filtered Exhaust Ports Both in Operation Dependent
17
Airflow Distribution Settings
Avg. Airflow Rate: 39.97 m/s
Avg. Exhaust: 6.58 m/s
Humidity: 40-80%
ANSYS Simulation Mesh
18
Boundary Conditions
Multiphase - Volume
Phase 1 - Air
Phase 2 - Formaldehyde
Volume Fraction ~ 50%
Inlet Vents: Velocity Inlets ~ 40 m/s
VOC Source: Velocity Inlets ~ 25 m/s
Exhaust: Pressure Outlets ~ 101 Pa
19* Values measured via air flow meter
Air flow Streamline Distribution
Residual Divergence Chart
VOC Emission Particle Pathlines
15 Seconds
● Momentum and Volume Fraction: 2nd Upwind
● Residual Setting : 3 Orders of Magnitude
● Steady State Confirmed by Convergence Reality Check
20
VOC Emission Simulation Timeline
10 Seconds
21
20 Seconds
VOC Emission Simulation Timeline
30 Seconds
22
50 Seconds
VOC Emission Simulation Timeline
70 Seconds
23
80 Seconds 90 Seconds
100 Seconds 110 Seconds 120 Seconds
VOC Diffusion Simulation Timeline
24
3 Minutes and 20 Seconds 5 Minutes
6 Minutes and 40 Seconds
● Time Step: 1 Second
● Intervals: 100
● Time Steps/Interval: 20
● Total Diffusal Time: Approx. 7 Minutes
Purchase Sensor and
Install inside hangar
Experimental analysis
Objective: Install a data logging sensor and analyze the VOC concentration
inside the hangar to verify the installation of demand controlled ventilation.
25
Create cost analysis
for implementation of
demand controlled
ventilation.
Analyze data collected
Collect data during
painting, drying, and
non-paint mode
Barriers in Testing
• Class 1 Div. 1 area: Hazardous locations w/ flammable gases
•Equipment entering the hangar must be explosive proof
•Anything left inside hangar is covered in Paint
•Limited battery life of Portable sensors
•Limited access to hangar facility
26
Refined Test Approach:
ProCheck TIGER
Pros Cons
Class 1 Div. 1 certified Can only rent due to cost
Wireless Battery lasts 16 hours
Built in data logger
VOC Range 1 PPB to
20,000 PPM
27
Experimental Setup
• Sensor was placed against
exhaust fan
• Tripod was used to support
sensor
• Velcro straps used to mount
sensor to tripod
28
Experimental Results
29
Experimental Results
n= Number of Air Exchanges per Hour
Q= Volumetric Flow Rate
V= Volume of air inside Hangar
From this we found that the air inside the hangar
will be exchanged every 24.3 minutes.
30
Experimental Results
31
Potential Impact
32
Ventilation Mode Fan Useage Average Monthly
Costs (Winter)
Savings
(Winter)
Current Energy
Consumption
100% $80,173 $0
Consumption w/
Demand Control
Ventilation
50% $60,130 $20,043.43
Demand Control Ventilation Setup
• 4 fixed RAEGuard II PID Sensors
• Class I, Division 1 (Zone 1) continuous
VOC monitoring for hazardous locations
• 0.01-100 ppm
• $5,000.00 / unit
• HA-40 4 channel Controller
• Transmits VOC level to Honeywell Controls
• Explosion Proof Container
• $2,400.00
33
4 Point Detection DCV System
34
INVESTMENT COST /
RECOVERY
• $20,043.43 (heating) + $5,923.00 (fans) = $25,966.00 Average Winter Monthly Savings
• Hardware Investment cost will be recovered 1 month after DCV installation
* Installation costs not included in estimate
35
Item Cost/Unit Quantity Part Total Cost
RAEGuard II Sensor $5,000.00 4 $20,000.00
HA-40 Controller $2,400.00 1 $2,400.00
Est. TOTAL COST $22,400.00
Acknowledgements
Tinker AFB
(Joseph, Aruna, Zac)
36
Raeco Rents
(John)
Questions?
37

More Related Content

What's hot

Airqual 1 breathing air quality test kit datasheet 0
Airqual 1 breathing air quality test kit datasheet 0Airqual 1 breathing air quality test kit datasheet 0
Airqual 1 breathing air quality test kit datasheet 0
a1-cbiss
 
XVII CONVEGNO EUROPEO P. De Larminat - LOWER GWP FLUIDS FOR AIR CONDITIONING
XVII CONVEGNO EUROPEO P. De Larminat - LOWER GWP FLUIDS FOR AIR CONDITIONINGXVII CONVEGNO EUROPEO P. De Larminat - LOWER GWP FLUIDS FOR AIR CONDITIONING
XVII CONVEGNO EUROPEO P. De Larminat - LOWER GWP FLUIDS FOR AIR CONDITIONING
Centro Studi Galileo
 
VVC AUTO 85.5 - Smog Technician - Level 1 - Nox
VVC AUTO 85.5 - Smog Technician - Level 1 - NoxVVC AUTO 85.5 - Smog Technician - Level 1 - Nox
VVC AUTO 85.5 - Smog Technician - Level 1 - Nox
Justin Gatewood
 

What's hot (20)

Dynamic Simulation of Cooling Water Circuit in Aspen HYSYS
Dynamic Simulation of Cooling Water Circuit in Aspen HYSYSDynamic Simulation of Cooling Water Circuit in Aspen HYSYS
Dynamic Simulation of Cooling Water Circuit in Aspen HYSYS
 
Wetland methane flux chamber
Wetland methane flux chamberWetland methane flux chamber
Wetland methane flux chamber
 
Orsat appatarus
Orsat appatarus Orsat appatarus
Orsat appatarus
 
Ap ms l5
Ap ms l5Ap ms l5
Ap ms l5
 
Clean air sorbent samplers
Clean air sorbent samplersClean air sorbent samplers
Clean air sorbent samplers
 
Sodium Analyzer for Industrial Applications
Sodium Analyzer for Industrial ApplicationsSodium Analyzer for Industrial Applications
Sodium Analyzer for Industrial Applications
 
MLSEV Virtual. Anomalies in Oil Temperature Variations in a TBM
MLSEV Virtual. Anomalies in Oil Temperature Variations in a TBMMLSEV Virtual. Anomalies in Oil Temperature Variations in a TBM
MLSEV Virtual. Anomalies in Oil Temperature Variations in a TBM
 
Airqual 1 breathing air quality test kit datasheet 0
Airqual 1 breathing air quality test kit datasheet 0Airqual 1 breathing air quality test kit datasheet 0
Airqual 1 breathing air quality test kit datasheet 0
 
Instrumentation Interview Questions Download
Instrumentation Interview Questions DownloadInstrumentation Interview Questions Download
Instrumentation Interview Questions Download
 
40 CFR 98 Tier 4 Greenhouse Gas Reporting with Stack Emissions Flow Meter
40 CFR 98 Tier 4 Greenhouse Gas Reporting with Stack Emissions Flow Meter40 CFR 98 Tier 4 Greenhouse Gas Reporting with Stack Emissions Flow Meter
40 CFR 98 Tier 4 Greenhouse Gas Reporting with Stack Emissions Flow Meter
 
Specifications gc
Specifications gcSpecifications gc
Specifications gc
 
Are your gas detectors actually working Tim Wylie
Are your gas detectors actually working   Tim WylieAre your gas detectors actually working   Tim Wylie
Are your gas detectors actually working Tim Wylie
 
Polaris FID
Polaris FIDPolaris FID
Polaris FID
 
XVII CONVEGNO EUROPEO P. De Larminat - LOWER GWP FLUIDS FOR AIR CONDITIONING
XVII CONVEGNO EUROPEO P. De Larminat - LOWER GWP FLUIDS FOR AIR CONDITIONINGXVII CONVEGNO EUROPEO P. De Larminat - LOWER GWP FLUIDS FOR AIR CONDITIONING
XVII CONVEGNO EUROPEO P. De Larminat - LOWER GWP FLUIDS FOR AIR CONDITIONING
 
INNOVATION DRIVES OUR GAS DETECTION
 INNOVATION DRIVES OUR GAS DETECTION INNOVATION DRIVES OUR GAS DETECTION
INNOVATION DRIVES OUR GAS DETECTION
 
Adev triple range hydrogen on analysis hydrogen cooled generators
Adev triple range hydrogen on analysis hydrogen cooled generatorsAdev triple range hydrogen on analysis hydrogen cooled generators
Adev triple range hydrogen on analysis hydrogen cooled generators
 
Oil tankers
Oil tankersOil tankers
Oil tankers
 
Outside Plant Presentation
Outside Plant PresentationOutside Plant Presentation
Outside Plant Presentation
 
Changing Best Practices in Flue Gas Analysis
Changing Best Practices in Flue Gas AnalysisChanging Best Practices in Flue Gas Analysis
Changing Best Practices in Flue Gas Analysis
 
VVC AUTO 85.5 - Smog Technician - Level 1 - Nox
VVC AUTO 85.5 - Smog Technician - Level 1 - NoxVVC AUTO 85.5 - Smog Technician - Level 1 - Nox
VVC AUTO 85.5 - Smog Technician - Level 1 - Nox
 

Viewers also liked

CDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyCDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 Strategy
Robert Doig
 
MUHAMMED MUSA CIVIL ENGG PP
MUHAMMED MUSA CIVIL ENGG PPMUHAMMED MUSA CIVIL ENGG PP
MUHAMMED MUSA CIVIL ENGG PP
Muhammed Musa
 
Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)
Waqas Aslam
 
FINAL Summer Internship REPORT NICMAR
FINAL Summer Internship REPORT NICMARFINAL Summer Internship REPORT NICMAR
FINAL Summer Internship REPORT NICMAR
Kamlesh Chaudhary
 
30 st mary axe the bullet building
30 st mary axe   the bullet building30 st mary axe   the bullet building
30 st mary axe the bullet building
Rohan Maskay
 
Quantity Surveying
Quantity SurveyingQuantity Surveying
Quantity Surveying
geddolan
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
Awanish Shukla
 
Managing Project Execution
Managing Project ExecutionManaging Project Execution
Managing Project Execution
pajames36
 

Viewers also liked (20)

Demand Controlled Ventilation and Energy Savings
Demand Controlled Ventilation and Energy SavingsDemand Controlled Ventilation and Energy Savings
Demand Controlled Ventilation and Energy Savings
 
CDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyCDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 Strategy
 
MUHAMMED MUSA CIVIL ENGG PP
MUHAMMED MUSA CIVIL ENGG PPMUHAMMED MUSA CIVIL ENGG PP
MUHAMMED MUSA CIVIL ENGG PP
 
Quality Systems Presentation Opca Mtg
Quality Systems Presentation   Opca MtgQuality Systems Presentation   Opca Mtg
Quality Systems Presentation Opca Mtg
 
Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)
 
Project Execution
Project ExecutionProject Execution
Project Execution
 
FINAL Summer Internship REPORT NICMAR
FINAL Summer Internship REPORT NICMARFINAL Summer Internship REPORT NICMAR
FINAL Summer Internship REPORT NICMAR
 
Project Execution
Project ExecutionProject Execution
Project Execution
 
30 st mary axe the bullet building
30 st mary axe   the bullet building30 st mary axe   the bullet building
30 st mary axe the bullet building
 
Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentation
 
Project Execution & Control Checklist
Project Execution & Control ChecklistProject Execution & Control Checklist
Project Execution & Control Checklist
 
Quantity Surveying
Quantity SurveyingQuantity Surveying
Quantity Surveying
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
 
Road Construction
Road ConstructionRoad Construction
Road Construction
 
Ppt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction SitePpt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction Site
 
Execution
ExecutionExecution
Execution
 
7 Steps Project Execution Process
7 Steps Project Execution Process7 Steps Project Execution Process
7 Steps Project Execution Process
 
road construction project
road construction projectroad construction project
road construction project
 
Managing Project Execution
Managing Project ExecutionManaging Project Execution
Managing Project Execution
 

Similar to Final Presentation

Technology reqmts-hvac-design-ses-2-aseptic-wkshp-pune-f
Technology reqmts-hvac-design-ses-2-aseptic-wkshp-pune-fTechnology reqmts-hvac-design-ses-2-aseptic-wkshp-pune-f
Technology reqmts-hvac-design-ses-2-aseptic-wkshp-pune-f
sachin kumar
 
USP 797/800 Cleanroom Compliance by Terra Universal
USP 797/800 Cleanroom Compliance by Terra UniversalUSP 797/800 Cleanroom Compliance by Terra Universal
USP 797/800 Cleanroom Compliance by Terra Universal
Terra Universal
 
Assessment of the natural air ventilation of buildings in urban area with the...
Assessment of the natural air ventilation of buildings in urban area with the...Assessment of the natural air ventilation of buildings in urban area with the...
Assessment of the natural air ventilation of buildings in urban area with the...
Stephane Meteodyn
 
Project By Rcdohare& Miss Kakoli Shaw
Project By Rcdohare& Miss Kakoli ShawProject By Rcdohare& Miss Kakoli Shaw
Project By Rcdohare& Miss Kakoli Shaw
BHILAI STEEL PLANT
 

Similar to Final Presentation (20)

final presentation edit.pptx
final presentation edit.pptxfinal presentation edit.pptx
final presentation edit.pptx
 
A case study on Air Pollution in Cement Industry
A case study on Air Pollution in Cement IndustryA case study on Air Pollution in Cement Industry
A case study on Air Pollution in Cement Industry
 
Technology reqmts-hvac-design-ses-2-aseptic-wkshp-pune-f
Technology reqmts-hvac-design-ses-2-aseptic-wkshp-pune-fTechnology reqmts-hvac-design-ses-2-aseptic-wkshp-pune-f
Technology reqmts-hvac-design-ses-2-aseptic-wkshp-pune-f
 
Sampling procedures part-3
Sampling procedures part-3Sampling procedures part-3
Sampling procedures part-3
 
CIBSE Yorkshire 2014 - Public Pool CPD by Menerga
CIBSE Yorkshire 2014 - Public Pool CPD by MenergaCIBSE Yorkshire 2014 - Public Pool CPD by Menerga
CIBSE Yorkshire 2014 - Public Pool CPD by Menerga
 
Steam Blow out
Steam Blow outSteam Blow out
Steam Blow out
 
USP 797/800 Cleanroom Compliance by Terra Universal
USP 797/800 Cleanroom Compliance by Terra UniversalUSP 797/800 Cleanroom Compliance by Terra Universal
USP 797/800 Cleanroom Compliance by Terra Universal
 
parenteral
parenteralparenteral
parenteral
 
Assessment of the natural air ventilation of buildings in urban area with the...
Assessment of the natural air ventilation of buildings in urban area with the...Assessment of the natural air ventilation of buildings in urban area with the...
Assessment of the natural air ventilation of buildings in urban area with the...
 
Anhydrous Ammonia Measurement for oil and water
Anhydrous Ammonia Measurement for oil and waterAnhydrous Ammonia Measurement for oil and water
Anhydrous Ammonia Measurement for oil and water
 
HVAC SYSTEM by Pratik
HVAC SYSTEM by PratikHVAC SYSTEM by Pratik
HVAC SYSTEM by Pratik
 
Air sampling
Air samplingAir sampling
Air sampling
 
Hvac basics
Hvac basicsHvac basics
Hvac basics
 
hvac_basics
hvac_basicshvac_basics
hvac_basics
 
Project By Rcdohare& Miss Kakoli Shaw
Project By Rcdohare& Miss Kakoli ShawProject By Rcdohare& Miss Kakoli Shaw
Project By Rcdohare& Miss Kakoli Shaw
 
One slider for qualification and validation of depyrogenation and sterilizati...
One slider for qualification and validation of depyrogenation and sterilizati...One slider for qualification and validation of depyrogenation and sterilizati...
One slider for qualification and validation of depyrogenation and sterilizati...
 
Air sampling
Air samplingAir sampling
Air sampling
 
Ppt1
Ppt1Ppt1
Ppt1
 
VALIDATION OF UTILITY ( HVAC , CLEANING VALIDATION,)
VALIDATION OF UTILITY ( HVAC , CLEANING VALIDATION,)VALIDATION OF UTILITY ( HVAC , CLEANING VALIDATION,)
VALIDATION OF UTILITY ( HVAC , CLEANING VALIDATION,)
 
HVAC validation.pdf
HVAC validation.pdfHVAC validation.pdf
HVAC validation.pdf
 

Final Presentation

  • 1. Project 17: Hangar Air Quality and Energy Consumption Analysis 1
  • 2. Sponsor: College of Engineering Faculty Mentor: Li Song Company Mentor: Aruna Abhayagoonawardhana Group Members: Sara Bondy Kyle Mcgee Bridget Taylor Tyler Totten 2
  • 4. The Facility ● Hangar Function: • Secondary Paint/Stencil facility for Military Planes • Painting only done 10% of the time • 100% outside air intake • Heating needed during winter • Eight fans run 100% of the time • Has a non-painting 4
  • 5. Deliverables Required ● Determine current energy consumption ● Calculate potential savings from reducing number of fans in use ● Find time it takes for the room to clear of VOC’s within safe range ● Make recommendations to Tinker on how to implement demand controlled ventilation 5
  • 6. Deliverables Required 6 Determine time for a return on DCV investment Demand Controlled Ventilation (DCV) Determine SAFE VOC levels Find highest concentration location Prove VOC level will remain at a SAFE level FEASIBILITY Determine potential savings SAFETY
  • 7. Volatile Organic Compounds ● Volatized: released in vapor form ● Negative effect on human health ● 400+ varieties of VOCs ● Emitted from o paints o paint strippers ● VOC limits for aerosol are 150 PPM over a 6 hour period ● Photoionization detector ● 10.6 eV Krypton Lamp 7
  • 8. Demand Controlled Ventilation • Standard vent. systems control vent. from preset “worst-case” scenarios • Too little vent. breathing in pollutants • Too much vent. energy waste • DCV continuously controls ventilation • VOC sensors will control ventilation mode inside hangar 8
  • 9. Strategic Plan 9 Research Develop Technical Plan Analyze Results Conclusions Simulation Analysis Experimental Analysis
  • 11. Finances Expenses Indoor air quality manual $ 66.96 Tripod $ 48.60 Sensor Rental $ 702.00 Total $ 817.56 11
  • 12. Technical Approach Objective: Prove the SAFETY and FEASIBILITY of implementing Simulation Analysis Experimental Analysis Create CAD Models Place sensor inside hangar Run simulation to find VOC concentration Record and analyze data Calculate amount of time that is needed for the VOC’s to dissipate to a safe level Make recommendations for demand controlled ventilation 12 Demand Controlled Ventilation
  • 13. Create CAD models for aircraft and the hangar Simulation Analysis Objective: Create a model to analyze the VOC distribution inside the hangar and to verify results from the experimental portion 13 Calculate amount of time that is needed for the VOC’s to dissipate to a safe level Calculate VOC concentration during paint mode and non- paint mode Find the highest VOC concentration location
  • 14. Current Conditions ● Four Inlet fans with an airspeed velocity of 40 m/s ● Two outlet vents with two fans in each operating at 101 Pa ● Each fan operates at 80 HP ● VOC’s are emitted from the center of the hanger at a velocity of 25 m/s ● Paint guns operate between 689 and 827 kPa ● Between .517 and .3878 grams of VOC are released per liter of air 14
  • 15. Building Specs Dimensions: Hangar: 63.1m X 50.6m X 18.29m Inlet Vents: 2m X 2m Filter: 7.62m X 8.6m Cross Sectional Area: Hangar: 1154.1 m2 Vent: 4 * 4 m2 = 16 m2 Filter: 65.5 m2 15
  • 16. Modeling the Hangar Plane Types: KC-10,C-130, C-135, E-5, E-6 16
  • 17. Assumptions Option Setting Validation Bay Doors Closed Confirmed via Tinker Pressure 1 atm Confirmed via Meter Room/Fluid Temperature 18°C Confirmed via Specs Heat Transfer Model Isothermal Marginal Impact Pressure Average Whole Outlet Marginal Impact Wall Roughness Smooth Confirmed via Visit Filtered Exhaust Ports Both in Operation Dependent 17
  • 18. Airflow Distribution Settings Avg. Airflow Rate: 39.97 m/s Avg. Exhaust: 6.58 m/s Humidity: 40-80% ANSYS Simulation Mesh 18
  • 19. Boundary Conditions Multiphase - Volume Phase 1 - Air Phase 2 - Formaldehyde Volume Fraction ~ 50% Inlet Vents: Velocity Inlets ~ 40 m/s VOC Source: Velocity Inlets ~ 25 m/s Exhaust: Pressure Outlets ~ 101 Pa 19* Values measured via air flow meter
  • 20. Air flow Streamline Distribution Residual Divergence Chart VOC Emission Particle Pathlines 15 Seconds ● Momentum and Volume Fraction: 2nd Upwind ● Residual Setting : 3 Orders of Magnitude ● Steady State Confirmed by Convergence Reality Check 20
  • 21. VOC Emission Simulation Timeline 10 Seconds 21 20 Seconds
  • 22. VOC Emission Simulation Timeline 30 Seconds 22 50 Seconds
  • 23. VOC Emission Simulation Timeline 70 Seconds 23 80 Seconds 90 Seconds 100 Seconds 110 Seconds 120 Seconds
  • 24. VOC Diffusion Simulation Timeline 24 3 Minutes and 20 Seconds 5 Minutes 6 Minutes and 40 Seconds ● Time Step: 1 Second ● Intervals: 100 ● Time Steps/Interval: 20 ● Total Diffusal Time: Approx. 7 Minutes
  • 25. Purchase Sensor and Install inside hangar Experimental analysis Objective: Install a data logging sensor and analyze the VOC concentration inside the hangar to verify the installation of demand controlled ventilation. 25 Create cost analysis for implementation of demand controlled ventilation. Analyze data collected Collect data during painting, drying, and non-paint mode
  • 26. Barriers in Testing • Class 1 Div. 1 area: Hazardous locations w/ flammable gases •Equipment entering the hangar must be explosive proof •Anything left inside hangar is covered in Paint •Limited battery life of Portable sensors •Limited access to hangar facility 26
  • 27. Refined Test Approach: ProCheck TIGER Pros Cons Class 1 Div. 1 certified Can only rent due to cost Wireless Battery lasts 16 hours Built in data logger VOC Range 1 PPB to 20,000 PPM 27
  • 28. Experimental Setup • Sensor was placed against exhaust fan • Tripod was used to support sensor • Velcro straps used to mount sensor to tripod 28
  • 30. Experimental Results n= Number of Air Exchanges per Hour Q= Volumetric Flow Rate V= Volume of air inside Hangar From this we found that the air inside the hangar will be exchanged every 24.3 minutes. 30
  • 32. Potential Impact 32 Ventilation Mode Fan Useage Average Monthly Costs (Winter) Savings (Winter) Current Energy Consumption 100% $80,173 $0 Consumption w/ Demand Control Ventilation 50% $60,130 $20,043.43
  • 33. Demand Control Ventilation Setup • 4 fixed RAEGuard II PID Sensors • Class I, Division 1 (Zone 1) continuous VOC monitoring for hazardous locations • 0.01-100 ppm • $5,000.00 / unit • HA-40 4 channel Controller • Transmits VOC level to Honeywell Controls • Explosion Proof Container • $2,400.00 33
  • 34. 4 Point Detection DCV System 34
  • 35. INVESTMENT COST / RECOVERY • $20,043.43 (heating) + $5,923.00 (fans) = $25,966.00 Average Winter Monthly Savings • Hardware Investment cost will be recovered 1 month after DCV installation * Installation costs not included in estimate 35 Item Cost/Unit Quantity Part Total Cost RAEGuard II Sensor $5,000.00 4 $20,000.00 HA-40 Controller $2,400.00 1 $2,400.00 Est. TOTAL COST $22,400.00
  • 36. Acknowledgements Tinker AFB (Joseph, Aruna, Zac) 36 Raeco Rents (John)