SlideShare a Scribd company logo
1 of 12
1.0INTRODUCTION
PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION
PROJECTS FUNDED BY THE PRIVATE SECTOR
16TH
OCTOBER 2002
TONY LATIENDA – MPM CAPITA
1.0 Introduction
1.1 The first part of this document analyses the case where the Government
needs Private Finance Initiatives in order to meet the needs and finance for
Infrastructure Works and Transportation Works and implementing the term
‘Transportation Projects’.
1.2 The organisational system and structure which allows collaboration between
the Public Sector and Private Sector for a Development Project is carried out
by the Nominated Consortium which integrates the following component
parts:
• Government / Client / Sponsor
• Finance
• Project
• Construction
• Operational Concessionaire
The relationship between such diverse parties as a voice: the Project
Finance Team, the Design Team, the Contractors and finally the Operators
should be contained in an Agreement which defines their roles,
responsibilities and obligations in each particular case.
The idea or the opportunity can be originated by any member of the Team.
MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 1
1.0INTRODUCTION
PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION
PROJECTS FUNDED BY THE PRIVATE SECTOR
16TH
OCTOBER 2002
TONY LATIENDA – MPM CAPITA
1.0 Introduction (continued)
1.3 The complexity of this Agreement implies and explains the need to have an
Independent Group of Specialists whose mission is to achieve the following:
• The integration of all the parts of the Agreement, in order to ensure these
comply with the objectives of both the Client and the Operator
• The co-ordination of the Project and the Construction Activities in order to
ensure these comply with the planned objectives
• The direction of the project, in order to guarantee, costs, programme and
quality are met within the specified limits
The functions of this independent Group of Specialists are known as the
Project Management Team
1.4 It is important that a Total Process is implemented – The Process controls
the development of the initial idea through to final delivery and operation.
Responsibility for delivering the benefits is also integrated with the
responsibility for controlling the delivery of the physical Project Components.
(This shows a High Level Project Framework Process.)
1.5 It is critical to have this Project Framework Process underpinned by a
Process Map as a Matrix of Stages and Principles that are linked through a
series of gates which ensure overall objectives are maintained.
(This shows the Process Map Project Stages across the top and the
Business Activities at the side.)
MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 2
1.0INTRODUCTION
PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION
PROJECTS FUNDED BY THE PRIVATE SECTOR
16TH
OCTOBER 2002
TONY LATIENDA – MPM CAPITA
1.0 Introduction (continued)
1.6 The Project Management Team will be appointed to cover and manage the
following items:
• Stakeholder Management
• Risk Management
• Revenue Benefit Forecast
• Supply Chain Management
• Initial Business Case
• Establish Work Breakdown Structure
• Feasibility Studies
• Quality Plan
• Assemble and Brief the Study Team
• Cost Management (including Life Cycle Costs)
• Change Management
• Establish Reporting Systems
• Value Management
• Planning / Programming
• Analysis and Co-ordination of the Project
• Operational Analysis
• Health & Safety Issues
• Environmental Issues
1.7 The Project Management Team can act on behalf of the Government, Client,
or Consortium, working in each case, based on similar directives.
MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 3
1.0INTRODUCTION
PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION
PROJECTS FUNDED BY THE PRIVATE SECTOR
16TH
OCTOBER 2002
TONY LATIENDA – MPM CAPITA
1.0 Introduction (continued)
1.8 The Project Management Team will give the Client, through its extensive
network of people, experts in finance, management and planning - highly
qualified inter-disciplined Specialist Professionals, the complete comfort that
the Project will meet its planned objectives and that this will be carried out
within the planned time and costs limits, guaranteeing a permanent and
systematic control of process and procedures throughout its evolution.
MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 4
2.0TRANSPORTATIONPROJECTS
PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION
PROJECTS FUNDED BY THE PRIVATE SECTOR
16TH
OCTOBER 2002
TONY LATIENDA – MPM CAPITA
2.0 Transportation Projects
2.1 The financial elements for the project construction and operation for a
development project require solid documentation co-ordinated to the
Contract which can be used during periods of conflict and ambiguity but with
the criteria available established will these meet the strict perimeters of cost
and programme. Therefore the documentation should be strong, clear and
unambiguous and the Project Management Team can assess all these
aspects in which it actively participates.
2.2 There are different sections in the Contract which are described in detail,
there should be for example, in order to compliment both the financial and
operational activities the preparation of regulated legal documentation in
order to protect the instructions of the Client and meet the needs of the
Operators on the project all within the determined programme and costs
established. The Project Management Team are appointed in order to
ensure both the technical and financial expectations of each party are
satisfied and ensure these are integrated properly.
2.3 The stages of design and construction can be the periods of major risk to the
programme, given the significant number of key players and the influence
this can cause on a number of factors, therefore it is especially important to
review the following critical points:
• A rigorous analysis on the capability of all the proposed objectives
• A check on income and cost cash flows
• The implementation of a process, procedures and controls to cover time
and cost during the life cycle of the project
MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 5
2.0TRANSPORTATIONPROJECTS
PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION
PROJECTS FUNDED BY THE PRIVATE SECTOR
16TH
OCTOBER 2002
TONY LATIENDA – MPM CAPITA
2.0 Transportation Projects (continued)
The Project Management Team will be responsible for the co-ordination of
the Project, notice any changes to the established objectives, checking at
each stage that the global strategy satisfies those same objectives and
proposing any necessary changes in each case
2.4 A clear understanding of the Operational Requirements between the
Government and the End User (if there is one) or Operator is as important as
any particular instructions on the Project.
These requirements should be reflected in infinite detail in the Agreement
between all the interested parties and should be interpreted correctly, that is
to say that the project should satisfy all their requirements. The Project
Management Team is appointed to translate, interpret, manage and check
the full compliment of all these Operational Requirements across the
functional spectrum.
2.5 The Government as well as the Consortium are interested in the compliance
of the Project within the established objectives (cost, quality, and time). The
role of the Project Management Team is to achieve these objectives, through
the use of permanent processes and controls which generate a climate of
confidence and a clear perspective of the Transportation Project at all times.
MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 6
3.0PROJECTMANAGEMENTONPUBLICSECTORTRANSPORTATIONPROJECTSFUNDEDBYTHEPRIVATESECTOR
PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION
PROJECTS FUNDED BY THE PRIVATE SECTOR
16TH
OCTOBER 2002
TONY LATIENDA – MPM CAPITA
3.0 Project Management on Public Sector Transportation Projects funded by the
Private Sector
3.1 The principle role of the Project Management Team consists in establishing
a climate of confidence between all the key players using a set of
management tools and techniques appropriate to each phase and stage of
the development process adding authenticity to its functional independence.
3.2 During the Initial Investigation and Feasibility & Definition Stage – the Project
Management Team will focus and actively participate in the preparation of
the following items:
• Initial Risk Assessment
• Initial Business Case
• Feasibility Study
• Procedures Manual and Information Flow (Reports / Change Management,
etc.)
• Development Programme and Objectives
• Conditions of Contract(s) – Key Issues
• Cost Plan
• Income Cash Flow
• Full Business Case
• Selection of Consultants, Designers etc.
• Selection of Contractors
• Bid Documents – Key Criteria for the Receipt of Bids (Procurement Plan)
MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 7
3.0PROJECTMANAGEMENTONPUBLICSECTORTRANSPORTATIONPROJECTSFUNDEDBYTHEPRIVATESECTOR
PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION
PROJECTS FUNDED BY THE PRIVATE SECTOR
16TH
OCTOBER 2002
TONY LATIENDA – MPM CAPITA
3.0 Project Management on Public Sector Transportation Projects funded by the
Private Sector (continued)
During the receipt of any Bids – The issue receipt and analysis of Bids and
the selection will be determined by the best value for money which
guarantees the compliance of the objectives stated (economic, technical,
programme).
3.3 During the Development Stage – Exercising the important mission of co-
ordination of all the multi-disciplinary teams and establishing:
• Client Decision Programmes
• Construction Development Programmes (including Phases)
• Cash Flow Programme – Costs
• Cash Flow Programme – Income
• Acquisition / Expropriation and Appointment Programme
• Information Flow on the Project.
3.4 During the Implementation Stage – Acting as the principle control mechanism
and co-ordinating generally through the following list of actions:
•The establishment of a System which covers the receipt, communication
and distribution of information and relative data through the life cycle of
the project
•The preparation, including method statements and analysis of planned
informed programmes covering the two inter-related items of time and
cost
•Informative Analysis of Income Flow
MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 8
3.0PROJECTMANAGEMENTONPUBLICSECTORTRANSPORTATIONPROJECTSFUNDEDBYTHEPRIVATESECTOR
PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION
PROJECTS FUNDED BY THE PRIVATE SECTOR
16TH
OCTOBER 2002
TONY LATIENDA – MPM CAPITA
•Periodic Progress Reports with analysis on delays, their causes and
consequences, including the recommendation of corrective measures
of the appropriate type for implementation
3.0 Project Management on Public Sector Transportation Projects funded by the
Private Sector (continued)
3.5 During the Validation of the Project:
• Co-ordination of Testing and Commissioning, including quality control
• Complete Analysis of Results
• Agreement on all Final Accounts
• Control during Guarantee Period
• Full Completion of the Works including Certificates / Validations
MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 9
4.0THEMANAGEMENTOFEXISTINGTRANSPORTATIONPROJECTS
PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION
PROJECTS FUNDED BY THE PRIVATE SECTOR
16TH
OCTOBER 2002
TONY LATIENDA – MPM CAPITA
4.0 The Management of Existing Transportation Projects
4.1 Up to the present, we have focused on the Project Management Team at the
start of the projects.
4.2 However there is a full role for the Project Management Team to work on
both existing projects and other types of projects, where for example the
Government is having problems with the Consortium or whom whoever they
are associated with.
4.3 In these cases, the Project Management Team can be appointed by the
Client or the Consortium in order to carry out an audit on the project in
relationship to the particular terms of reference, for example to study the
costs, review the project and construction against the programme, equally
the actual position in connection with planned income, and any other aspect
the Government, The Consortium or the Project Management Team deem
appropriate.
4.4 The results of this investigation will not only reflect on the difficulties
encountered but will also indicate the best way to minimise the impact of the
problems faced and conclude with a systematic and controlled solution which
will ultimately achieve success on the project.
4.5 The ongoing role of the Project Management Team, who can enter at any
stage of the Project, is to prepare, comply and follow all the contractual
points of the Contract, ensuring the objectives of their investigation are fully
complied.
MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 10
5.0CONCLUSION
PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION
PROJECTS FUNDED BY THE PRIVATE SECTOR
16TH
OCTOBER 2002
TONY LATIENDA – MPM CAPITA
5.0 Conclusion
5.1 The present document has thoroughly explained the essential role of the
Project Management Team in achieving total success in transportation
projects funded by the private sector in terms of design, cost, programme
and in accordance with the specific instructions of the public sector. Their
professional and independent services can equally be used on private sector
projects with the same objectives on the project, of cost, time and quality.
5.2 The role of the Project Management Team is independent and can vary in
accordance with the structure of the Contract between the Government and
the Private Sector, and equally meeting the precise and exact requirements
of all the parties to the Contract.
5.3 However, the parameters for the appointment of individual professionals in
the Independent Project Management Team can also vary on each project,
dependant on their specific roles, obligations and responsibilities, each
professional / member having an essential role to play in the finalisation of
the scheme.
5.4 Using the proposed Consortium for a Transportation Project, the Client can
have trust on the responsibilities of all the parties to the Contract, including
the Project Management Team and other Professionals who have the
guarantee of Professional Indemnity to recover for commercial losses
suffered by the Government or Client.
5.5 The importance of having such real guarantees that a project completed can
achieve the planned objectives of cost, time and quality are extraordinary.
Using the professional services provided by the Project Management Team,
it is possible to obtain control guarantee real results and achieve success.
MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 11
5.0CONCLUSION
PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION
PROJECTS FUNDED BY THE PRIVATE SECTOR
16TH
OCTOBER 2002
TONY LATIENDA – MPM CAPITA
Tony Latienda
Senior Project Manager
MPM CAPITA
26A Albemarle Street
London
W1S 4HY
Telephone: 44 120 7499 1122
Facsimile: 44 120 7499 6611
E-mail: tony.latienda@mpmcapita.co.uk
MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 12

More Related Content

Viewers also liked

T&j no.108
T&j no.108T&j no.108
T&j no.108washidc
 
2015 DiB QLD Event Fyers (6)
2015 DiB QLD Event Fyers (6)2015 DiB QLD Event Fyers (6)
2015 DiB QLD Event Fyers (6)Blake Barrett CSC
 
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri05
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri052eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri05
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri05Vcoi Vit
 
UPDATED PROFILE(FOR GREAT MEN AND WOMEN OF SCIENCE CAMBRIDGE).
UPDATED PROFILE(FOR GREAT MEN AND WOMEN OF SCIENCE CAMBRIDGE).UPDATED PROFILE(FOR GREAT MEN AND WOMEN OF SCIENCE CAMBRIDGE).
UPDATED PROFILE(FOR GREAT MEN AND WOMEN OF SCIENCE CAMBRIDGE).PAUL IGBOJI
 
Gco for-29 evaluamos-en_primer_periodo_2016
Gco for-29 evaluamos-en_primer_periodo_2016Gco for-29 evaluamos-en_primer_periodo_2016
Gco for-29 evaluamos-en_primer_periodo_2016Paulo Delgado Ordóñez
 
Filiala 20 Ovidius
Filiala 20 OvidiusFiliala 20 Ovidius
Filiala 20 Ovidiusdalex4c
 
Interview schedule
Interview scheduleInterview schedule
Interview schedulea2media15d
 

Viewers also liked (13)

Model dk 9 parpol
Model dk 9 parpolModel dk 9 parpol
Model dk 9 parpol
 
Curso de moodle
Curso de moodleCurso de moodle
Curso de moodle
 
T&j no.108
T&j no.108T&j no.108
T&j no.108
 
FBAwithSmartBeta2
FBAwithSmartBeta2FBAwithSmartBeta2
FBAwithSmartBeta2
 
2015 DiB QLD Event Fyers (6)
2015 DiB QLD Event Fyers (6)2015 DiB QLD Event Fyers (6)
2015 DiB QLD Event Fyers (6)
 
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri05
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri052eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri05
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri05
 
UPDATED PROFILE(FOR GREAT MEN AND WOMEN OF SCIENCE CAMBRIDGE).
UPDATED PROFILE(FOR GREAT MEN AND WOMEN OF SCIENCE CAMBRIDGE).UPDATED PROFILE(FOR GREAT MEN AND WOMEN OF SCIENCE CAMBRIDGE).
UPDATED PROFILE(FOR GREAT MEN AND WOMEN OF SCIENCE CAMBRIDGE).
 
Gco for-29 evaluamos-en_primer_periodo_2016
Gco for-29 evaluamos-en_primer_periodo_2016Gco for-29 evaluamos-en_primer_periodo_2016
Gco for-29 evaluamos-en_primer_periodo_2016
 
Bridges
BridgesBridges
Bridges
 
Filiala 20 Ovidius
Filiala 20 OvidiusFiliala 20 Ovidius
Filiala 20 Ovidius
 
Interview schedule
Interview scheduleInterview schedule
Interview schedule
 
Custumes
CustumesCustumes
Custumes
 
Consejos
ConsejosConsejos
Consejos
 

Similar to 02101103tjb TL (Presentation)(1)

Step4all guide 3 How to apply and how to manage successful European projects
Step4all guide 3 How to apply and how to manage successful European projectsStep4all guide 3 How to apply and how to manage successful European projects
Step4all guide 3 How to apply and how to manage successful European projectsGIANLUCA COPPOLA
 
Building construction manual btc nov_2013_en
Building construction manual btc nov_2013_enBuilding construction manual btc nov_2013_en
Building construction manual btc nov_2013_enAYM1979
 
6_Link LFA to Full application
6_Link LFA to Full application6_Link LFA to Full application
6_Link LFA to Full applicationcsdialogue
 
Presentation-Project Management_1.pdf
Presentation-Project Management_1.pdfPresentation-Project Management_1.pdf
Presentation-Project Management_1.pdfAustinKharkongor
 
Presentation-Project Management_1.pdf
Presentation-Project Management_1.pdfPresentation-Project Management_1.pdf
Presentation-Project Management_1.pdfPranith roy
 
Presentation-Project Management_1.pdf
Presentation-Project Management_1.pdfPresentation-Project Management_1.pdf
Presentation-Project Management_1.pdfssuserbbd2c1
 
Business Plan for a CEN Workshop on eInvoicing phase 3
Business Plan for a CEN Workshop on eInvoicing phase 3Business Plan for a CEN Workshop on eInvoicing phase 3
Business Plan for a CEN Workshop on eInvoicing phase 3Friso de Jong
 
Project 27663255255255781771777166162666
Project 27663255255255781771777166162666Project 27663255255255781771777166162666
Project 27663255255255781771777166162666MilkiasMuse
 
T2 - T2S Consolidation | How to be compliant in time?
T2 - T2S Consolidation | How to be compliant in time?T2 - T2S Consolidation | How to be compliant in time?
T2 - T2S Consolidation | How to be compliant in time?PwC Italy
 
Toronto Pearson Airport - Procurement Strategy Study
Toronto Pearson Airport - Procurement Strategy StudyToronto Pearson Airport - Procurement Strategy Study
Toronto Pearson Airport - Procurement Strategy StudyAhmed Mahmoud
 
Fostering solar technology in the Mediterranean area - Communication Plan
Fostering solar technology in the Mediterranean area - Communication PlanFostering solar technology in the Mediterranean area - Communication Plan
Fostering solar technology in the Mediterranean area - Communication PlanFOSTEr in MED
 
Chapter 4 Construction Project Management. Lec 4.ppt
Chapter 4 Construction Project Management. Lec 4.pptChapter 4 Construction Project Management. Lec 4.ppt
Chapter 4 Construction Project Management. Lec 4.pptssuserb4074f
 
FTA Construction Management Handbook - 2012
FTA Construction Management Handbook - 2012FTA Construction Management Handbook - 2012
FTA Construction Management Handbook - 2012Yusuf Yıldız
 
SLOPE intro we have a new project!
SLOPE intro we have a new project!SLOPE intro we have a new project!
SLOPE intro we have a new project!SLOPE Project
 

Similar to 02101103tjb TL (Presentation)(1) (20)

Step4all guide 3 How to apply and how to manage successful European projects
Step4all guide 3 How to apply and how to manage successful European projectsStep4all guide 3 How to apply and how to manage successful European projects
Step4all guide 3 How to apply and how to manage successful European projects
 
Building construction manual btc nov_2013_en
Building construction manual btc nov_2013_enBuilding construction manual btc nov_2013_en
Building construction manual btc nov_2013_en
 
6_Link LFA to Full application
6_Link LFA to Full application6_Link LFA to Full application
6_Link LFA to Full application
 
Management projet international
Management projet internationalManagement projet international
Management projet international
 
Presentation-Project Management_1.pdf
Presentation-Project Management_1.pdfPresentation-Project Management_1.pdf
Presentation-Project Management_1.pdf
 
Presentation-Project Management_1.pdf
Presentation-Project Management_1.pdfPresentation-Project Management_1.pdf
Presentation-Project Management_1.pdf
 
Presentation-Project Management_1.pdf
Presentation-Project Management_1.pdfPresentation-Project Management_1.pdf
Presentation-Project Management_1.pdf
 
Business Plan for a CEN Workshop on eInvoicing phase 3
Business Plan for a CEN Workshop on eInvoicing phase 3Business Plan for a CEN Workshop on eInvoicing phase 3
Business Plan for a CEN Workshop on eInvoicing phase 3
 
Project 27663255255255781771777166162666
Project 27663255255255781771777166162666Project 27663255255255781771777166162666
Project 27663255255255781771777166162666
 
T2 - T2S Consolidation | How to be compliant in time?
T2 - T2S Consolidation | How to be compliant in time?T2 - T2S Consolidation | How to be compliant in time?
T2 - T2S Consolidation | How to be compliant in time?
 
Project starting report iktimed 2 nov
Project starting report iktimed 2  novProject starting report iktimed 2  nov
Project starting report iktimed 2 nov
 
Toronto Pearson Airport - Procurement Strategy Study
Toronto Pearson Airport - Procurement Strategy StudyToronto Pearson Airport - Procurement Strategy Study
Toronto Pearson Airport - Procurement Strategy Study
 
M Simpson coursework
M Simpson courseworkM Simpson coursework
M Simpson coursework
 
Fostering solar technology in the Mediterranean area - Communication Plan
Fostering solar technology in the Mediterranean area - Communication PlanFostering solar technology in the Mediterranean area - Communication Plan
Fostering solar technology in the Mediterranean area - Communication Plan
 
CATS Contract of Objectives presentation
CATS Contract of Objectives presentationCATS Contract of Objectives presentation
CATS Contract of Objectives presentation
 
Chapter 4 Construction Project Management. Lec 4.ppt
Chapter 4 Construction Project Management. Lec 4.pptChapter 4 Construction Project Management. Lec 4.ppt
Chapter 4 Construction Project Management. Lec 4.ppt
 
Group Presentation MSMS
Group Presentation MSMSGroup Presentation MSMS
Group Presentation MSMS
 
Iktimed final presentation Marche Reg.
Iktimed final presentation Marche Reg. Iktimed final presentation Marche Reg.
Iktimed final presentation Marche Reg.
 
FTA Construction Management Handbook - 2012
FTA Construction Management Handbook - 2012FTA Construction Management Handbook - 2012
FTA Construction Management Handbook - 2012
 
SLOPE intro we have a new project!
SLOPE intro we have a new project!SLOPE intro we have a new project!
SLOPE intro we have a new project!
 

02101103tjb TL (Presentation)(1)

  • 1. 1.0INTRODUCTION PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION PROJECTS FUNDED BY THE PRIVATE SECTOR 16TH OCTOBER 2002 TONY LATIENDA – MPM CAPITA 1.0 Introduction 1.1 The first part of this document analyses the case where the Government needs Private Finance Initiatives in order to meet the needs and finance for Infrastructure Works and Transportation Works and implementing the term ‘Transportation Projects’. 1.2 The organisational system and structure which allows collaboration between the Public Sector and Private Sector for a Development Project is carried out by the Nominated Consortium which integrates the following component parts: • Government / Client / Sponsor • Finance • Project • Construction • Operational Concessionaire The relationship between such diverse parties as a voice: the Project Finance Team, the Design Team, the Contractors and finally the Operators should be contained in an Agreement which defines their roles, responsibilities and obligations in each particular case. The idea or the opportunity can be originated by any member of the Team. MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 1
  • 2. 1.0INTRODUCTION PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION PROJECTS FUNDED BY THE PRIVATE SECTOR 16TH OCTOBER 2002 TONY LATIENDA – MPM CAPITA 1.0 Introduction (continued) 1.3 The complexity of this Agreement implies and explains the need to have an Independent Group of Specialists whose mission is to achieve the following: • The integration of all the parts of the Agreement, in order to ensure these comply with the objectives of both the Client and the Operator • The co-ordination of the Project and the Construction Activities in order to ensure these comply with the planned objectives • The direction of the project, in order to guarantee, costs, programme and quality are met within the specified limits The functions of this independent Group of Specialists are known as the Project Management Team 1.4 It is important that a Total Process is implemented – The Process controls the development of the initial idea through to final delivery and operation. Responsibility for delivering the benefits is also integrated with the responsibility for controlling the delivery of the physical Project Components. (This shows a High Level Project Framework Process.) 1.5 It is critical to have this Project Framework Process underpinned by a Process Map as a Matrix of Stages and Principles that are linked through a series of gates which ensure overall objectives are maintained. (This shows the Process Map Project Stages across the top and the Business Activities at the side.) MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 2
  • 3. 1.0INTRODUCTION PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION PROJECTS FUNDED BY THE PRIVATE SECTOR 16TH OCTOBER 2002 TONY LATIENDA – MPM CAPITA 1.0 Introduction (continued) 1.6 The Project Management Team will be appointed to cover and manage the following items: • Stakeholder Management • Risk Management • Revenue Benefit Forecast • Supply Chain Management • Initial Business Case • Establish Work Breakdown Structure • Feasibility Studies • Quality Plan • Assemble and Brief the Study Team • Cost Management (including Life Cycle Costs) • Change Management • Establish Reporting Systems • Value Management • Planning / Programming • Analysis and Co-ordination of the Project • Operational Analysis • Health & Safety Issues • Environmental Issues 1.7 The Project Management Team can act on behalf of the Government, Client, or Consortium, working in each case, based on similar directives. MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 3
  • 4. 1.0INTRODUCTION PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION PROJECTS FUNDED BY THE PRIVATE SECTOR 16TH OCTOBER 2002 TONY LATIENDA – MPM CAPITA 1.0 Introduction (continued) 1.8 The Project Management Team will give the Client, through its extensive network of people, experts in finance, management and planning - highly qualified inter-disciplined Specialist Professionals, the complete comfort that the Project will meet its planned objectives and that this will be carried out within the planned time and costs limits, guaranteeing a permanent and systematic control of process and procedures throughout its evolution. MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 4
  • 5. 2.0TRANSPORTATIONPROJECTS PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION PROJECTS FUNDED BY THE PRIVATE SECTOR 16TH OCTOBER 2002 TONY LATIENDA – MPM CAPITA 2.0 Transportation Projects 2.1 The financial elements for the project construction and operation for a development project require solid documentation co-ordinated to the Contract which can be used during periods of conflict and ambiguity but with the criteria available established will these meet the strict perimeters of cost and programme. Therefore the documentation should be strong, clear and unambiguous and the Project Management Team can assess all these aspects in which it actively participates. 2.2 There are different sections in the Contract which are described in detail, there should be for example, in order to compliment both the financial and operational activities the preparation of regulated legal documentation in order to protect the instructions of the Client and meet the needs of the Operators on the project all within the determined programme and costs established. The Project Management Team are appointed in order to ensure both the technical and financial expectations of each party are satisfied and ensure these are integrated properly. 2.3 The stages of design and construction can be the periods of major risk to the programme, given the significant number of key players and the influence this can cause on a number of factors, therefore it is especially important to review the following critical points: • A rigorous analysis on the capability of all the proposed objectives • A check on income and cost cash flows • The implementation of a process, procedures and controls to cover time and cost during the life cycle of the project MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 5
  • 6. 2.0TRANSPORTATIONPROJECTS PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION PROJECTS FUNDED BY THE PRIVATE SECTOR 16TH OCTOBER 2002 TONY LATIENDA – MPM CAPITA 2.0 Transportation Projects (continued) The Project Management Team will be responsible for the co-ordination of the Project, notice any changes to the established objectives, checking at each stage that the global strategy satisfies those same objectives and proposing any necessary changes in each case 2.4 A clear understanding of the Operational Requirements between the Government and the End User (if there is one) or Operator is as important as any particular instructions on the Project. These requirements should be reflected in infinite detail in the Agreement between all the interested parties and should be interpreted correctly, that is to say that the project should satisfy all their requirements. The Project Management Team is appointed to translate, interpret, manage and check the full compliment of all these Operational Requirements across the functional spectrum. 2.5 The Government as well as the Consortium are interested in the compliance of the Project within the established objectives (cost, quality, and time). The role of the Project Management Team is to achieve these objectives, through the use of permanent processes and controls which generate a climate of confidence and a clear perspective of the Transportation Project at all times. MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 6
  • 7. 3.0PROJECTMANAGEMENTONPUBLICSECTORTRANSPORTATIONPROJECTSFUNDEDBYTHEPRIVATESECTOR PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION PROJECTS FUNDED BY THE PRIVATE SECTOR 16TH OCTOBER 2002 TONY LATIENDA – MPM CAPITA 3.0 Project Management on Public Sector Transportation Projects funded by the Private Sector 3.1 The principle role of the Project Management Team consists in establishing a climate of confidence between all the key players using a set of management tools and techniques appropriate to each phase and stage of the development process adding authenticity to its functional independence. 3.2 During the Initial Investigation and Feasibility & Definition Stage – the Project Management Team will focus and actively participate in the preparation of the following items: • Initial Risk Assessment • Initial Business Case • Feasibility Study • Procedures Manual and Information Flow (Reports / Change Management, etc.) • Development Programme and Objectives • Conditions of Contract(s) – Key Issues • Cost Plan • Income Cash Flow • Full Business Case • Selection of Consultants, Designers etc. • Selection of Contractors • Bid Documents – Key Criteria for the Receipt of Bids (Procurement Plan) MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 7
  • 8. 3.0PROJECTMANAGEMENTONPUBLICSECTORTRANSPORTATIONPROJECTSFUNDEDBYTHEPRIVATESECTOR PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION PROJECTS FUNDED BY THE PRIVATE SECTOR 16TH OCTOBER 2002 TONY LATIENDA – MPM CAPITA 3.0 Project Management on Public Sector Transportation Projects funded by the Private Sector (continued) During the receipt of any Bids – The issue receipt and analysis of Bids and the selection will be determined by the best value for money which guarantees the compliance of the objectives stated (economic, technical, programme). 3.3 During the Development Stage – Exercising the important mission of co- ordination of all the multi-disciplinary teams and establishing: • Client Decision Programmes • Construction Development Programmes (including Phases) • Cash Flow Programme – Costs • Cash Flow Programme – Income • Acquisition / Expropriation and Appointment Programme • Information Flow on the Project. 3.4 During the Implementation Stage – Acting as the principle control mechanism and co-ordinating generally through the following list of actions: •The establishment of a System which covers the receipt, communication and distribution of information and relative data through the life cycle of the project •The preparation, including method statements and analysis of planned informed programmes covering the two inter-related items of time and cost •Informative Analysis of Income Flow MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 8
  • 9. 3.0PROJECTMANAGEMENTONPUBLICSECTORTRANSPORTATIONPROJECTSFUNDEDBYTHEPRIVATESECTOR PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION PROJECTS FUNDED BY THE PRIVATE SECTOR 16TH OCTOBER 2002 TONY LATIENDA – MPM CAPITA •Periodic Progress Reports with analysis on delays, their causes and consequences, including the recommendation of corrective measures of the appropriate type for implementation 3.0 Project Management on Public Sector Transportation Projects funded by the Private Sector (continued) 3.5 During the Validation of the Project: • Co-ordination of Testing and Commissioning, including quality control • Complete Analysis of Results • Agreement on all Final Accounts • Control during Guarantee Period • Full Completion of the Works including Certificates / Validations MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 9
  • 10. 4.0THEMANAGEMENTOFEXISTINGTRANSPORTATIONPROJECTS PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION PROJECTS FUNDED BY THE PRIVATE SECTOR 16TH OCTOBER 2002 TONY LATIENDA – MPM CAPITA 4.0 The Management of Existing Transportation Projects 4.1 Up to the present, we have focused on the Project Management Team at the start of the projects. 4.2 However there is a full role for the Project Management Team to work on both existing projects and other types of projects, where for example the Government is having problems with the Consortium or whom whoever they are associated with. 4.3 In these cases, the Project Management Team can be appointed by the Client or the Consortium in order to carry out an audit on the project in relationship to the particular terms of reference, for example to study the costs, review the project and construction against the programme, equally the actual position in connection with planned income, and any other aspect the Government, The Consortium or the Project Management Team deem appropriate. 4.4 The results of this investigation will not only reflect on the difficulties encountered but will also indicate the best way to minimise the impact of the problems faced and conclude with a systematic and controlled solution which will ultimately achieve success on the project. 4.5 The ongoing role of the Project Management Team, who can enter at any stage of the Project, is to prepare, comply and follow all the contractual points of the Contract, ensuring the objectives of their investigation are fully complied. MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 10
  • 11. 5.0CONCLUSION PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION PROJECTS FUNDED BY THE PRIVATE SECTOR 16TH OCTOBER 2002 TONY LATIENDA – MPM CAPITA 5.0 Conclusion 5.1 The present document has thoroughly explained the essential role of the Project Management Team in achieving total success in transportation projects funded by the private sector in terms of design, cost, programme and in accordance with the specific instructions of the public sector. Their professional and independent services can equally be used on private sector projects with the same objectives on the project, of cost, time and quality. 5.2 The role of the Project Management Team is independent and can vary in accordance with the structure of the Contract between the Government and the Private Sector, and equally meeting the precise and exact requirements of all the parties to the Contract. 5.3 However, the parameters for the appointment of individual professionals in the Independent Project Management Team can also vary on each project, dependant on their specific roles, obligations and responsibilities, each professional / member having an essential role to play in the finalisation of the scheme. 5.4 Using the proposed Consortium for a Transportation Project, the Client can have trust on the responsibilities of all the parties to the Contract, including the Project Management Team and other Professionals who have the guarantee of Professional Indemnity to recover for commercial losses suffered by the Government or Client. 5.5 The importance of having such real guarantees that a project completed can achieve the planned objectives of cost, time and quality are extraordinary. Using the professional services provided by the Project Management Team, it is possible to obtain control guarantee real results and achieve success. MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 11
  • 12. 5.0CONCLUSION PROJECT MANAGEMENT ON PUBLIC SECTOR TRANSPORTATION PROJECTS FUNDED BY THE PRIVATE SECTOR 16TH OCTOBER 2002 TONY LATIENDA – MPM CAPITA Tony Latienda Senior Project Manager MPM CAPITA 26A Albemarle Street London W1S 4HY Telephone: 44 120 7499 1122 Facsimile: 44 120 7499 6611 E-mail: tony.latienda@mpmcapita.co.uk MPM/l3239/BARCELONA/PRESENTATION/02101103/TL/vCi/tjb Page 12