SlideShare a Scribd company logo
1 of 31
Download to read offline
LESCO Report
Submitted By:
Syed Muhammad Ali Shah 2012-EE-148
Submitted To:
Miss Masooma
HR LESCO Head Office
Electrical Engineering Department
University of Engineering and Technology Lahore
Overview
Instructor: Miss Masooma
Designation: Deputy Manager Trainee and Man Power Planning
Wapda
The Water and Power Development Authority (WAPDA) is a government-owned public
utility maintaining power and water in Pakistan, although it does not manage thermal power.
WAPDA includes Tarbela and Mangla dams among its resources. Its headquarters are in Lahore.
WAPDA was established in February 1959 to unify the maintenance of infrastructure previously
overseen by provincial agencies. Its Chairmen included outstanding civil servants like Ghulam
Ishaq Khan, Ghulam Faruque Khan and Aftab Ghulam Nabi Kazi who were
subsequently President of Pakistan, Minister for Commerce and Economic Adviser, respectively.
In October 2007, thermal power management was split into the newly formed Pakistan Electric
Power Company (PEPCO).
Debundding
If department is too large than debunding is needed. It provides the following things:
 Competition
 Management
 Service
 Performance
 Price control
Area Electricity Board in 1982, in which these distribution companies were named base on the
areas, like LESCO was known at that time as “Lahore Electricity Area Board”
Company Act
In 1994, according to Company Act, distribution companies were formed.
SECP (Security and Exchange Company)
In 1998, LESCO was registered with SECP
The ultimate goal was to privatize all these distribution companies
PEPCO
It is an independent company. And it has 9 companies under it. Recently another company which
covers tribal areas is came into being known as TESCO. These companies are given below:
 Peshawar
 Islamabad
 Gujranwala
 Lahore LESCO
 Faisalabad FESCO
 Multain MEPCO
 Sakhar
 Hyderabad
 Quetta QESCO
 Trible areas TESCO (tribal electric sully company)
Pepco basically has three different parts
1. GENCO
2. NTDC
3. Distribution companies
GENCO
All generation is under GENCO, which produces electricity and sold it to different
companies for distribution. It includes,
 GENCO 1
 GENCO 2
 GENCO 3
NTDC
National Transmission and Dispatch Company, it basially gets bulk power from GENCO.
In 2008, NTDC further sub divided the system.
500KV and 220KV it kept with itself and 132KV and below this voltage, the system was handed
over to DISCO’s.
LESCO
Lahore supply control
It is a distribution company and almost 100 grid stations are under it.
It has around 3 million users including:
Wapda
GENCO NTDC DISCO'S
 Industrial users
 Residential users
 Domestic users
 agriculture user
Basically there are four regions under LESCO, whose distribution is governed by LESCO
 Lahore region
 Okara region
 Kasoor region
 Sheikhupura region
Mission Statement of LESCO
 Un interrupted power supply
 Quality service
 Customer care
Area of Operation
 Lahore
 Okara
 Kasoor
 Sheikhupura
Types of PD under LESCO
There are three types of PD under LESCO
 PD Construction
 PD Civil
 PD GSC
Organization Structure
 BOD
 CO
 Marketing
 HR
 Customer Service
 Managing Department
 Internal Audit Department
 External Audit Department
Internal Audit Department
It checks whether policies are followed or not.
It also check what are the discrepancies in the system.
On this basis, different reports are generated according to the situation, known as:
 Advanced Para
 Summary Para
 Draft Para
External Audit Department
PAC (Public Account Commission)
Opposition Leader is head of this commission. This commission overlooks the
system and find flaws in it. If there is any discrepancy, a warning is given. And it
give opportunity to solve the issue, which is known as “Advanced Para”
If the issue is not solved than a file is generated and forwarded to high authorities
known as “Draft Para”
Operation Department
This is the most important department and distribution is under it
Offices
There are two main offices
 Head Office
 Circle Office
Circle Office
Circle office is under operation director equivalent to Chief Engineer.
Areas
LESCO is divided into seven areas (Circles)
Lahore is portioned into four circles
 East Circle
 South Circle
 West Circle
 Central Circle
In each circle “Supredendant Engineer” sit over there. Transformer failure, D-issue these all are
under his work.
GSO (Grid System Operation)
GSC (Grid System Construction)
2 MNT (Metering and Testing) Circle
 East side
 West side
SE level
Detection Bill
PMU (Project Management Unit)
This unit was made around seven years back. Its major work is to kkep sight on Environmental
and Social aspects.
LESCO Achievement
 One Window
It provides 24 hour service.
 Circle
 Division
Its encharge is EXION, Deputy Manager.
o Sub Division
Every sub division has SDO (Sub Division Officer)
 RO Office (Revenue Office)
It is in parallel with Divison.
 Call Center
118
 ERP (Enter Pries Resource)
Oracle base, it basically keeps the record of employee. For example let suppose one line
man is transferred from one division to another division.
 Customer Service Center
 Regional Training Center (RTC)
 It provides training to Line man, Line supredandant, Meter reader, Line staff, BPS-
13
 Safety Seminars
 Customer Service Van
It is an automobile with necessary equipments and fascilitate the users immediately
by resolving issues. For example, issue related to bills etc.
 PD Construction Circle
 Power Shutt Down
Project Management Unit (PMU)
Instructor
Head: Chief Engineer Development
 Director / Manager
o Deputy Director
 Assistant Director
 Line supredendant
Purpose
 To identify the development projects through Load Forecasting and Load flow studies
techniques.
 To prepare the plan (feasibility studies), PC-1 (planning commission), get its approval from
the government.
 Prepare the government plan.
 Get it’s approval from Board of Director (BOD).
 Precruitment procedure
 Bidding process / Tending process
 Award of Contex
 Inspection of material
 Delivering of material to the store
 Side selection of grid station
 Prepration of Root Plan of transmission line
 Prepration of Engineering Drawing for Civil and Electrical work
 Engineering estimates
 Approval of estimates
Director
Deputy
Director
Assistant
Director
Line
Supredendant
Construction Activities
 Civil work
 Electrical Equipment installation
 Testing
 Commissioning
 Hand over to the department
Departments
 Planning and Schedule
Head: Director
 PMS unit
 Precruitment
Head: Director
 Finance
Head: Director
 Enviromental unit
Head: Deputy Director
1. Planning and Schedule
PMU
Planning and
Schedule
Precurement Finance Environmental
 Forecasting (Power Market Survey)
 Line forecasting
 Load Forecasting
 Load forecasting can be handled in two ways.
 New grid station
 Old grid station either by Augment or by Extent
 Daily problem
 Issues
 Tender evaluation Committee
Projects are floated and this committee basically checks which companies are responsive
and which are non-responsive
Minimum Area for Grid Station: 18-20 canal
40 to 50 crore is needed approximately, to build grid station
Whenever load increases more than 5MV for single user, than it’s the rule that they are needed to
bulid their own grid station.
Transformer Rating: 13MVA, 26MVA, 40MVA
PMS Unit:
This is basically an important section of Planning and Schedule. Its work include following things:
 Future Load in this area
 Load Flow studies (Software work)
Through this PC-1 report is generated.PMU do only this. PC-2,PC-3, PC-4 these reports
are generated on later stages.
 Cost
 Cost Benefit ratio
 Payback period
 Approval
 Head Quarter (Chief executive)
 BOD
 Ministry
 Secretary of Water and Power resources
2. Precruitment
Whenever public money is involved, there is a process known as “Precurement”.
There are some rules introduced by PPRA, that must be obeyed during procurement.
Precurement has severeal advantages that are listed below:
 Competitive environment
 Transparency
 Accountability
In procurement “Brands (company names)” are not specified, only specification of
the things are mentioned.
It includes,
 Number of transformers
 Number of lines or conductors
 Towers
There are basically two resoures:
 LESCO own resources
 World Bank, Asian Development (ADP) resources
The process is followed as:
 Tender float
 If equipment is in store, no need to tender
 Whenever company is selected by the process of tendring, equipment is supervised
 Buy equipment
 “Contract Document” of every project
3. Finance
This department basically deals with loan.
 Initially 10% pay
 Two types of projects
 LESCO own revenue
These project are supervised by PDGSE (Project Director GSE)
 Loan from World Bank(head office in New York), Asian Development (ADP)
(head office in Monala)
These projects are supervised by LESCO and also by ADP
ADP gave loan in installations known as Tranch 1, Tranch 2, Tranch 3, Tranch4
Own Revenue Ways:
 Ascar account (Billing)
 Deposit work
 Capital contribution e.g. Meter cost
Types of Payments by LESCO
A. Direct payment
Like payment to PEL. The steps for this payment are as followed:
 Withdrawal application
 Bill copy
 Inspection Certificate
 Performance Guarantee
 GRN
 Nonpayment certificate
 Tax deduction
In this payment there is usually a guarantee of 18 months or 24 months
B. Payment through LC (Letter of Credit)
The steps for this payment are as followed:
 Firm invoice (Bank Alfalah, Sindh Bank, Standard Charter Bank)
 PU copy
 ADP gives to bank and Bank gives to Firm
C. Payment through Advance (Empress)
We get money in advance. But this method has the disadvantage of “Interest”.
Although money is not spend on project and still is present in Bank, the interest is
going to start from the first day on the total amount that is took in advance.
D. Disbursement through Re-imbursement
Use money our self
Quantity Rate Liquid and
Damages
FBR Net amount A/C
due to late
(LD)
LD can be maximum 10% of the total.
Famous Contractors of LESCO
 PEL
 Siemens
 HEC
 NEW AGE
 Fast Cable
 Universal Cable
 NSI
 Sadique Son’s (incoming outgoing panels)
4. Environmental unit
The important factors that must be considered and should be controlled are:
 Air noise
 Water testing
Environment Impact Analysis (EIA)
Initial Environment Examination (IEE)
 After study the report is sent to Ministry of Environment (EPD)
 PC1 (5 years) is generated, for this actually EIA is compulsory
 This is sent to Ministry of Environment, which issues the NOC (set of clauses), which
need to be implement.
 Binding document is prepared
 Environment Monitory Plan is prepared
 Set of conditions
 Contractor follow and represent monthly report
Working
Environmental unit make sure the following things:
 Training
 Safety hazards
 Complain reports (Check list)
 Compensation (Crop compensation)
 Land acquisition settlement plan
 3 payment
 Erection
 Stringing
 Compact Fluorescent lamp (CFL) project
This is an energy conservation project, in which 2 CFL are given to each user.
 Carbon Credits
If emission of Carbon is reduced than UNO gives credit and millions of dollars are
rewarded
MO (Central) Circle
Instructor: Muhammad Hafeez
Designation: Deputy Director (TECH)
Area Distribution
Divisions:
Each circle has five divisions.
The officer which controls the division is "Exion".
It mean, each circle has 5 exions.
Central Circle Divisions:
The name of central circle divisions are given below,
1. Township division
2. Riwind division
3. Allama-Iqbal Town division
4. Samna Bad division
5. Civil Line division
Circle
Division
Sub
Division
Sub Divisions
Each division is further divided into different number of Sub Divisions,
1.Township division
This divisions has seven sub divisions, also two more sub divisions get included from 1st of July.
Names are given below:
i. Johar town sub division
ii. Wapda town sub division
iii. Green town sub division
iv. Township sub division
v. College road sub division
vi. Liaqat'a'bad sub division
vii. Air line sub division
viii.Engineer town sub division
ix. Behar Colony sub division
2.Riwind division
This divisions has four sub divisions.
Names are given below:
i. Ali Raza Abid sub division (near Thokar)
ii. Jea Bhaga sub division
iii. Riwind sub division
iv. Manga sub division
v.
3.Allama-Iqbal Town division
This divisions has six sub divisions, also three more sub divisions get included from 1st of July.
Names are given below:
i. Iqbal Town sub division
ii. Multain Road sub division
iii. Canal Road sub division
iv. Niaz Baig sub division
v. Choong sub division
vi. Awan Town sub division
vii. Rana Town sub division
viii.Mustafa Tow sub division
ix. Shahpur (Kanjra) sub division
4.Samna Bad division
This divisions has five sub divisions.
Names are given below:
i. Islam Pura sub division (near MAO)
ii. Prame Nagar sub division
iii. Samana Bad sub division
iv. Itahaad Colony sub division
v. Said Pur sub division
5.Civil Line division
This divisions has four sub divisions.
Names are given below:
i. Ichra sub division
ii. Government Officer Residence (GOR) sub division
iii. Mazang sub division
iv. Islamia Park sub division
Hierarchy
 SDO / Assistant Manager
 Grade 17 officer
 Two courses are needed for it,
1. Sector Specific (Junior Management Course) which covers the period of 6 week. Its classes
are arranged in Wapda Engineering Acadmy.
2. WASC (Wapda Administrative Staff College) which covers the duration of 9 weeks. Its
classes are arranged in Islamabad.
 Additional EXION
If there is no promotion of SDO and ten year pass than, there is a promotion on next grade
and given the designation of "Additional Exion", but he will continue the same work.
 Pre Promotion exam from SDO oblique junior engineer to Exion oblique Senior
engineer, is needed to clear.
 EXION / Deputy Manager
 Grade 18 officer.
 A test is needed for it, known as MMN (Middle Management Course) which covers the
period of nine to ten weeks.
 Additional SE (Supredendant Engineer)
 If twenty year (SDO + Exion) pass and there is no promotion from exion to SE than, there
is a promotion on next grade and given the designation of "Additional SE", but he will
continue the same work.
 SE (Supredendant Engineer) / Manager
 Grade 19 officer
 Chief Engineer
 Grade 20 officer
 In LESCO there are four Chief Engineers
i. Chief of Operation and maintainence (1st chief engineers). 4 circles are controlled by
one chief engineer.
ii. Chief of Operation and maintainence (2nd chief engineers).3 circles are controlled by
second chief engineer.
iii. Chief of Material Management (3rd chief engineers)
iv. Chief of Engineer Planning (4th chief engineers)
 GM
 Grade 20 officer
 No further grade for Engineers in this section
Rank Hierarchy
Connection Authority
 SDO 8-10KW Commercial connections
GM
Chief Engineer
Supredendant
Engineer
Exion
Sub Division
Officer
 EXION 70KW industry
 SE 70-500KW
 Chief Engineer Planning (LESCO Head Quarter B3) Above 500KW
Types of Meters on basis of phases
 Single phase meter
 Three phase meter
 MDA (Maximum Demand Indicator)
Types of Meters on basis of Load
A1 (01) Domestic
A2 (04) Commercial
B1 (07) Industry 25KW
B2 (10) Above 500KW
B3 Above 500KW/ Bulk supply (They have to develop their own grid)
B4
DIVISION
Instructor: Tariq Mehmood Butter
Designation: Exion
What is segregation?
This is due to block billing which implies different tariff rates. If unis exceed from specified limit
than tariff changes and different rates are charged as per unit.
Bifurcate means “Divide into branches”
1) Computerized meters
 Measurement of consumed energy
 Measurement of consumed units
 Control of supply
2) Smart meters
 Self-monitoring
 Analysis
 Reporting
3) AMR meters(Automatic Meter Reading)
 GSM based, work on Radio Frequency (RF)
Exion Competency
Basically, he permits the new connections
 Meters
 New Transformers
 LT Feeders
 Electrifying new colony
 Matters of Accounts
 Proposal things
 Employee salary
 Capital contribution
This includes cost instead of billing like cost of Poles and Wires.
 Security
Rupees per KWh, this is related to RO
 Meter price
Exion office
Financial Power
Designation Range of Money Range of Extension
SDO Upto 25,000 3 days
Exion 25000 to 1 lac 3 days
SE 1 lac to 2,3 lac 4 days
Chief Engineer Above 2,3 lac
Standard Operating Procedure (SOP)
Power Dispatch Centre (PDC)
This is our purpose, so we want to shut down.
Fault in our lines.
Permit to work (PTW).
SUB DIVISION
Instructor: Engr Kamran Naveed
Designation: Sub Division Officer (SDO)
The main and the most important working of SDO office and its labor is the “Continuity of
Supply”
SUBDIVISION SECTIONS
First of all there is an “Admin section”, which basically overheads the four sections in SDO office.
Any activity from these four sections or external matters are first passed through admin section.
The above mentioned four sections are:
 Complain section
 MCO/ DCO section (Meter connection or disconnection section)
 Reading section
 Maintenance section
Admin section
 There are two Sub Division Clerks (SDC)
 There are four or six Lower Division Clerks (LDC).
Complain section
Instructor: Mr.Saleem
Designation: Line Supredendant
This is a section with twenty four hours service, there are three shifts in this section.
 6am to 2pm
 2pm to 10pm
 10pm to 6am
There is a complain register, with code e.g. wxyz
w represents Region
x represents Circle
y represents Division
z represents Sub division
SDO
Admin
section
Complain
section
MCO/DCO
Section
Reading
section
Maintenance
section
Complain register looks like
Serial
Number
Time Complain
number
Address Complain Line
man
name
Time of
departure
Time
of
arrival
Remarks
MCO/DCO section
Instructor: Ghulam Hussain Naqvi
Designation: Line Supredendant
The following registers are used in the whole process.
 Store requisition
 CA 21
Entrance of new meters
 CA 22
Entrance of old meters
 MCO Book
Meter Change Order Book. In this register details of old meters and also the details
of new meters are present
 Challan Form
 Material return order
Meters are returned to the store
Reading section
The hierarchy of this section is as:
 MRSS (Meter Reading Section Supervisor)
 MS1 (Meter inspector 1)
 MS2 (Meter inspector 2)
Working
CP11 Book
This book is allotted to one person which is enrolled in CP20
Meter reading list
This list has all the readings and is send to computer man in RO office, which enters the data
There are also two more registrers named as:
o Received Register
o Sold register
BATCHES
Batch
Number
Load type Load Meter type Read by
1 to 18 Domestic/
Commercial
19 Tube wells (Govt)
20 Industry 0-5 KW B1
45 Tube well (Private)
46 Industry 5-40 KW
24 Industry 500 KW B2 SDO
24 Industry 500-5000KW B3 Exion
24 132 kv (grid) Above 5000 KW B4 Exion
Green town sub division
This sub division has 14 feeders. In which there are:
 Ten are “Distributed feeders”
 Four are “Independent feeders”
Distributed feeders
Constructed on LESCO’s cost. Anyone can take connections from feeders.
Independent feeders
Dedicated to B3 connections (When load is beyond 1000KW). These feeders are owned
by the user (industry) and no other user can take connection from it.
SUBDIVISION ACTIVITIES
 Prime activity
Accountability of received units from Grid
 Continuity of supply
Maintenance, complains
 New connections
 Rehabilitation of electric system
Up gradation of system e.g. LT , HT
 Redressal of complains
Meters
Meters can also be characterized as:
 Direct meter
 Indirect meter
CT control, max limit is 5A
Types of faults
Basically there are two types of faults
 Phase to phase fault
 Phase to neutral fault
PDC (Power Dispatch Center)
NPCC (National Power Control Center)
GRID STATION
Generation is usually at 11.5KV
Parts of Grid Station
 Transformer (Tap changer)
 On load transformer
 Off load transformer
 Bushing
Point where we have terminals for connection
 Lightning arrestor
 PT
 CT
 Line insulator
 Insulator
 Circuit breaker (SF6 breaker)
Quenching medium is Sulphur Hex Fluoride Gas
 Bus bar insulator
 Capacitor bank (2KV)
 Overhead ground wire
 11KV vacuum breaker
PD Construction
This department has the following three type of work
 Rehabilitation
 Government work ( Poles and lines shifting due to LDA work)
 Private work
There are 7 circles in LESCO but these circles are controlled by 6 exions of PD
Construction.
Working
Design is produced in Head Office under the supervisory of “Chief Engineer Development”
Types of conductors
Three types of conductors are commonly used in field
 Osprey
Used for HT lines. It has 18 aluminum strands and one steel strand in the middle.
 Rabbit
Used for LT lines. It has 7 aluminum strands and one steel (consist of six thin fibers
of steel) strand in the middle
 Dog
Used for LT lines. It has 7 aluminum strands and one steel strand in the middle.
Pole Distance
Types of Conductor on pole Distance between two poles
Osprey 135
Rabbit 160
Dog 180
Components of Pole
Now a days, “Steel Structure” poles are used. Its components are given below:
 Steel cross arm
 11KV brace
 11KV pin insulator
 11KV steel pin
 Bolts
2 * 5/8 bolt
Double arming (DA) bolt
 Stray rod (Rod + Elbow)
This is buried in ground to support the ending pole
Types of Insulators
 Disc insulator
 School insulator
Assemblies on pole’s top
Two types of assemblies are:
 1L assembly
Used in running lines
 7L assembly
Used when there is ending point in the structure
LESCO_report

More Related Content

What's hot

PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substationIshank Ranjan
 
REPORT ON SOLAR TRACKING SYSTEM
REPORT ON SOLAR TRACKING SYSTEMREPORT ON SOLAR TRACKING SYSTEM
REPORT ON SOLAR TRACKING SYSTEMBhautik Sanandiya
 
Renewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectRenewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectPartha Deb
 
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONPPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONSwatantra SwAt
 
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...Jobin Abraham
 
Power System Planning
Power System PlanningPower System Planning
Power System Planninglinsstalex
 
Powergrid Corporation of India Limited.
Powergrid Corporation of India Limited. Powergrid Corporation of India Limited.
Powergrid Corporation of India Limited. Sai Chaithanya Sharma
 
AC Distribution System - Generation Distribution and Transmission
AC Distribution System - Generation Distribution and TransmissionAC Distribution System - Generation Distribution and Transmission
AC Distribution System - Generation Distribution and TransmissionGowtham Cr
 
Power sector in India
Power sector in IndiaPower sector in India
Power sector in IndiaDaya Kherwar
 
Academic Council Meet PPT- 19
Academic Council Meet PPT- 19Academic Council Meet PPT- 19
Academic Council Meet PPT- 19Md Irshad Ahmad
 
Smart under and over voltage protection system for
Smart under and over voltage protection system forSmart under and over voltage protection system for
Smart under and over voltage protection system forShuvadip das
 
EE6004 FACTS
EE6004 FACTSEE6004 FACTS
EE6004 FACTSrmkceteee
 
substation internship report
substation internship report substation internship report
substation internship report Arun Thapa
 

What's hot (20)

PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
 
REPORT ON SOLAR TRACKING SYSTEM
REPORT ON SOLAR TRACKING SYSTEMREPORT ON SOLAR TRACKING SYSTEM
REPORT ON SOLAR TRACKING SYSTEM
 
Renewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectRenewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot Project
 
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONPPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
 
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
 
Power System Planning
Power System PlanningPower System Planning
Power System Planning
 
Internship report
Internship report Internship report
Internship report
 
132 33kv substation
132 33kv substation132 33kv substation
132 33kv substation
 
Powergrid Corporation of India Limited.
Powergrid Corporation of India Limited. Powergrid Corporation of India Limited.
Powergrid Corporation of India Limited.
 
RLC Circuit
RLC CircuitRLC Circuit
RLC Circuit
 
Facts controllers
Facts controllersFacts controllers
Facts controllers
 
Ehv ac transmission line
Ehv ac transmission lineEhv ac transmission line
Ehv ac transmission line
 
AC Distribution System - Generation Distribution and Transmission
AC Distribution System - Generation Distribution and TransmissionAC Distribution System - Generation Distribution and Transmission
AC Distribution System - Generation Distribution and Transmission
 
Power sector in India
Power sector in IndiaPower sector in India
Power sector in India
 
Solar power plant
Solar power plantSolar power plant
Solar power plant
 
Academic Council Meet PPT- 19
Academic Council Meet PPT- 19Academic Council Meet PPT- 19
Academic Council Meet PPT- 19
 
Smart under and over voltage protection system for
Smart under and over voltage protection system forSmart under and over voltage protection system for
Smart under and over voltage protection system for
 
“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”
“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”
“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”
 
EE6004 FACTS
EE6004 FACTSEE6004 FACTS
EE6004 FACTS
 
substation internship report
substation internship report substation internship report
substation internship report
 

Viewers also liked

Lesco internship by muhammad talha
Lesco internship by muhammad talhaLesco internship by muhammad talha
Lesco internship by muhammad talhaMuhammad Talha
 
KMD_sikkerhedbrochure
KMD_sikkerhedbrochureKMD_sikkerhedbrochure
KMD_sikkerhedbrochureClaus Lavdal
 
Presentation - Sluys International NV's Colourant
Presentation - Sluys International NV's ColourantPresentation - Sluys International NV's Colourant
Presentation - Sluys International NV's ColourantSluys International NV
 
Situation Response Analysis final report- Summary
Situation Response Analysis final report- SummarySituation Response Analysis final report- Summary
Situation Response Analysis final report- SummaryMaryam Hemed
 
Seo preparation guide
Seo preparation guideSeo preparation guide
Seo preparation guideHarish Vadla
 
Corporate Presentation - Sluys International NV (FLAVOUR)
Corporate Presentation - Sluys International NV (FLAVOUR)Corporate Presentation - Sluys International NV (FLAVOUR)
Corporate Presentation - Sluys International NV (FLAVOUR)Sluys International NV
 
Learning Commons
Learning Commons Learning Commons
Learning Commons Jody Wilson
 
Mukesh Sharma - CV update (2) (6) (1) (1) (1)
Mukesh Sharma - CV update (2) (6) (1) (1) (1)Mukesh Sharma - CV update (2) (6) (1) (1) (1)
Mukesh Sharma - CV update (2) (6) (1) (1) (1)Mukesh Kumar Sharma
 
Sluys International NV where Smell, Taste, Sight are Balanced
Sluys International NV where Smell, Taste, Sight are BalancedSluys International NV where Smell, Taste, Sight are Balanced
Sluys International NV where Smell, Taste, Sight are BalancedSluys International NV
 

Viewers also liked (17)

Lesco internship by muhammad talha
Lesco internship by muhammad talhaLesco internship by muhammad talha
Lesco internship by muhammad talha
 
KMD_sikkerhedbrochure
KMD_sikkerhedbrochureKMD_sikkerhedbrochure
KMD_sikkerhedbrochure
 
Presentation - Sluys International NV's Colourant
Presentation - Sluys International NV's ColourantPresentation - Sluys International NV's Colourant
Presentation - Sluys International NV's Colourant
 
Belgium: The Small Wonderland
Belgium: The Small WonderlandBelgium: The Small Wonderland
Belgium: The Small Wonderland
 
Situation Response Analysis final report- Summary
Situation Response Analysis final report- SummarySituation Response Analysis final report- Summary
Situation Response Analysis final report- Summary
 
Raj Kumar Rurhi-Resume
Raj Kumar Rurhi-ResumeRaj Kumar Rurhi-Resume
Raj Kumar Rurhi-Resume
 
Seo preparation guide
Seo preparation guideSeo preparation guide
Seo preparation guide
 
Drink Concept: Craft Soda
Drink Concept: Craft SodaDrink Concept: Craft Soda
Drink Concept: Craft Soda
 
Corporate Presentation - Sluys International NV (FLAVOUR)
Corporate Presentation - Sluys International NV (FLAVOUR)Corporate Presentation - Sluys International NV (FLAVOUR)
Corporate Presentation - Sluys International NV (FLAVOUR)
 
RAJ-RURHI-RESUME
RAJ-RURHI-RESUMERAJ-RURHI-RESUME
RAJ-RURHI-RESUME
 
Learning Commons
Learning Commons Learning Commons
Learning Commons
 
Infographic: VR Taste Test
Infographic: VR Taste TestInfographic: VR Taste Test
Infographic: VR Taste Test
 
Trafalgar2016.5
Trafalgar2016.5Trafalgar2016.5
Trafalgar2016.5
 
Power Plant
Power PlantPower Plant
Power Plant
 
Raj Kumar Rurhi-Resume
Raj Kumar Rurhi-ResumeRaj Kumar Rurhi-Resume
Raj Kumar Rurhi-Resume
 
Mukesh Sharma - CV update (2) (6) (1) (1) (1)
Mukesh Sharma - CV update (2) (6) (1) (1) (1)Mukesh Sharma - CV update (2) (6) (1) (1) (1)
Mukesh Sharma - CV update (2) (6) (1) (1) (1)
 
Sluys International NV where Smell, Taste, Sight are Balanced
Sluys International NV where Smell, Taste, Sight are BalancedSluys International NV where Smell, Taste, Sight are Balanced
Sluys International NV where Smell, Taste, Sight are Balanced
 

Similar to LESCO_report

RESUME_MJU_04.07.2016
RESUME_MJU_04.07.2016RESUME_MJU_04.07.2016
RESUME_MJU_04.07.2016Jashim Pd-2
 
Resume_MJU_04.07.2016
Resume_MJU_04.07.2016Resume_MJU_04.07.2016
Resume_MJU_04.07.2016Jashim Pd-2
 
Resume mju 03.10.2016
Resume mju 03.10.2016Resume mju 03.10.2016
Resume mju 03.10.2016Jashim Pd-2
 
IRJET- Sanctioned Load Monitoring & Controlling by using PLC
IRJET- Sanctioned Load Monitoring & Controlling by using PLCIRJET- Sanctioned Load Monitoring & Controlling by using PLC
IRJET- Sanctioned Load Monitoring & Controlling by using PLCIRJET Journal
 
QUALITY MANAGEMENT PRACTICES USED BY TELECOM ORGANIZATIONS,quality in telecom...
QUALITY MANAGEMENT PRACTICES USED BY TELECOM ORGANIZATIONS,quality in telecom...QUALITY MANAGEMENT PRACTICES USED BY TELECOM ORGANIZATIONS,quality in telecom...
QUALITY MANAGEMENT PRACTICES USED BY TELECOM ORGANIZATIONS,quality in telecom...Micky Lyf
 
Power Distribution Overview
Power Distribution OverviewPower Distribution Overview
Power Distribution OverviewHIMADRI BANERJI
 
Software Eng. for Critical Systems - Traffic Controller
Software Eng. for Critical Systems - Traffic ControllerSoftware Eng. for Critical Systems - Traffic Controller
Software Eng. for Critical Systems - Traffic ControllerZiya Ilkem Erogul
 
160615 cs2680551
160615 cs2680551160615 cs2680551
160615 cs2680551Tahir Khan
 
160615CS2680551
160615CS2680551160615CS2680551
160615CS2680551Tahir Khan
 
Terminal Automation - Evolution & challenges
Terminal Automation - Evolution & challengesTerminal Automation - Evolution & challenges
Terminal Automation - Evolution & challengesNaimish Raval
 
Sayan-CV 2015
Sayan-CV 2015Sayan-CV 2015
Sayan-CV 2015Sayan Ml
 
Design of management dashboard (smart electric grids)
Design of management dashboard (smart electric grids)Design of management dashboard (smart electric grids)
Design of management dashboard (smart electric grids)Jatin Pherwani
 

Similar to LESCO_report (20)

Material Procurement and Management
Material Procurement and ManagementMaterial Procurement and Management
Material Procurement and Management
 
CV OF droni
CV OF droniCV OF droni
CV OF droni
 
CV DRONI
CV DRONICV DRONI
CV DRONI
 
RESUME_MJU_04.07.2016
RESUME_MJU_04.07.2016RESUME_MJU_04.07.2016
RESUME_MJU_04.07.2016
 
Resume_MJU_04.07.2016
Resume_MJU_04.07.2016Resume_MJU_04.07.2016
Resume_MJU_04.07.2016
 
Resume mju 03.10.2016
Resume mju 03.10.2016Resume mju 03.10.2016
Resume mju 03.10.2016
 
IRJET- Sanctioned Load Monitoring & Controlling by using PLC
IRJET- Sanctioned Load Monitoring & Controlling by using PLCIRJET- Sanctioned Load Monitoring & Controlling by using PLC
IRJET- Sanctioned Load Monitoring & Controlling by using PLC
 
QUALITY MANAGEMENT PRACTICES USED BY TELECOM ORGANIZATIONS,quality in telecom...
QUALITY MANAGEMENT PRACTICES USED BY TELECOM ORGANIZATIONS,quality in telecom...QUALITY MANAGEMENT PRACTICES USED BY TELECOM ORGANIZATIONS,quality in telecom...
QUALITY MANAGEMENT PRACTICES USED BY TELECOM ORGANIZATIONS,quality in telecom...
 
Power Distribution Overview
Power Distribution OverviewPower Distribution Overview
Power Distribution Overview
 
Deputy Manager Electrical
Deputy Manager ElectricalDeputy Manager Electrical
Deputy Manager Electrical
 
Software Eng. for Critical Systems - Traffic Controller
Software Eng. for Critical Systems - Traffic ControllerSoftware Eng. for Critical Systems - Traffic Controller
Software Eng. for Critical Systems - Traffic Controller
 
160615 cs2680551
160615 cs2680551160615 cs2680551
160615 cs2680551
 
160615CS2680551
160615CS2680551160615CS2680551
160615CS2680551
 
Terminal Automation - Evolution & challenges
Terminal Automation - Evolution & challengesTerminal Automation - Evolution & challenges
Terminal Automation - Evolution & challenges
 
Final Report
Final ReportFinal Report
Final Report
 
Sayan-CV 2015
Sayan-CV 2015Sayan-CV 2015
Sayan-CV 2015
 
RESUME_Sumeet
RESUME_SumeetRESUME_Sumeet
RESUME_Sumeet
 
Dr.pptx1
Dr.pptx1Dr.pptx1
Dr.pptx1
 
Design of management dashboard (smart electric grids)
Design of management dashboard (smart electric grids)Design of management dashboard (smart electric grids)
Design of management dashboard (smart electric grids)
 
Malikjan Resume New
Malikjan Resume NewMalikjan Resume New
Malikjan Resume New
 

LESCO_report

  • 1. LESCO Report Submitted By: Syed Muhammad Ali Shah 2012-EE-148 Submitted To: Miss Masooma HR LESCO Head Office Electrical Engineering Department University of Engineering and Technology Lahore
  • 2. Overview Instructor: Miss Masooma Designation: Deputy Manager Trainee and Man Power Planning Wapda The Water and Power Development Authority (WAPDA) is a government-owned public utility maintaining power and water in Pakistan, although it does not manage thermal power. WAPDA includes Tarbela and Mangla dams among its resources. Its headquarters are in Lahore. WAPDA was established in February 1959 to unify the maintenance of infrastructure previously overseen by provincial agencies. Its Chairmen included outstanding civil servants like Ghulam Ishaq Khan, Ghulam Faruque Khan and Aftab Ghulam Nabi Kazi who were subsequently President of Pakistan, Minister for Commerce and Economic Adviser, respectively. In October 2007, thermal power management was split into the newly formed Pakistan Electric Power Company (PEPCO). Debundding If department is too large than debunding is needed. It provides the following things:  Competition  Management  Service  Performance  Price control Area Electricity Board in 1982, in which these distribution companies were named base on the areas, like LESCO was known at that time as “Lahore Electricity Area Board” Company Act In 1994, according to Company Act, distribution companies were formed. SECP (Security and Exchange Company) In 1998, LESCO was registered with SECP
  • 3. The ultimate goal was to privatize all these distribution companies PEPCO It is an independent company. And it has 9 companies under it. Recently another company which covers tribal areas is came into being known as TESCO. These companies are given below:  Peshawar  Islamabad  Gujranwala  Lahore LESCO  Faisalabad FESCO  Multain MEPCO  Sakhar  Hyderabad  Quetta QESCO  Trible areas TESCO (tribal electric sully company) Pepco basically has three different parts 1. GENCO 2. NTDC 3. Distribution companies
  • 4. GENCO All generation is under GENCO, which produces electricity and sold it to different companies for distribution. It includes,  GENCO 1  GENCO 2  GENCO 3 NTDC National Transmission and Dispatch Company, it basially gets bulk power from GENCO. In 2008, NTDC further sub divided the system. 500KV and 220KV it kept with itself and 132KV and below this voltage, the system was handed over to DISCO’s. LESCO Lahore supply control It is a distribution company and almost 100 grid stations are under it. It has around 3 million users including: Wapda GENCO NTDC DISCO'S
  • 5.  Industrial users  Residential users  Domestic users  agriculture user Basically there are four regions under LESCO, whose distribution is governed by LESCO  Lahore region  Okara region  Kasoor region  Sheikhupura region Mission Statement of LESCO  Un interrupted power supply  Quality service  Customer care Area of Operation  Lahore  Okara  Kasoor  Sheikhupura Types of PD under LESCO There are three types of PD under LESCO  PD Construction  PD Civil  PD GSC Organization Structure  BOD  CO  Marketing  HR  Customer Service
  • 6.  Managing Department  Internal Audit Department  External Audit Department Internal Audit Department It checks whether policies are followed or not. It also check what are the discrepancies in the system. On this basis, different reports are generated according to the situation, known as:  Advanced Para  Summary Para  Draft Para External Audit Department PAC (Public Account Commission) Opposition Leader is head of this commission. This commission overlooks the system and find flaws in it. If there is any discrepancy, a warning is given. And it give opportunity to solve the issue, which is known as “Advanced Para” If the issue is not solved than a file is generated and forwarded to high authorities known as “Draft Para” Operation Department This is the most important department and distribution is under it Offices There are two main offices  Head Office  Circle Office Circle Office Circle office is under operation director equivalent to Chief Engineer.
  • 7. Areas LESCO is divided into seven areas (Circles) Lahore is portioned into four circles  East Circle  South Circle  West Circle  Central Circle In each circle “Supredendant Engineer” sit over there. Transformer failure, D-issue these all are under his work. GSO (Grid System Operation) GSC (Grid System Construction) 2 MNT (Metering and Testing) Circle  East side  West side SE level Detection Bill PMU (Project Management Unit) This unit was made around seven years back. Its major work is to kkep sight on Environmental and Social aspects. LESCO Achievement  One Window It provides 24 hour service.  Circle  Division Its encharge is EXION, Deputy Manager.
  • 8. o Sub Division Every sub division has SDO (Sub Division Officer)  RO Office (Revenue Office) It is in parallel with Divison.  Call Center 118  ERP (Enter Pries Resource) Oracle base, it basically keeps the record of employee. For example let suppose one line man is transferred from one division to another division.  Customer Service Center  Regional Training Center (RTC)  It provides training to Line man, Line supredandant, Meter reader, Line staff, BPS- 13  Safety Seminars  Customer Service Van It is an automobile with necessary equipments and fascilitate the users immediately by resolving issues. For example, issue related to bills etc.  PD Construction Circle  Power Shutt Down Project Management Unit (PMU) Instructor Head: Chief Engineer Development  Director / Manager o Deputy Director  Assistant Director  Line supredendant
  • 9. Purpose  To identify the development projects through Load Forecasting and Load flow studies techniques.  To prepare the plan (feasibility studies), PC-1 (planning commission), get its approval from the government.  Prepare the government plan.  Get it’s approval from Board of Director (BOD).  Precruitment procedure  Bidding process / Tending process  Award of Contex  Inspection of material  Delivering of material to the store  Side selection of grid station  Prepration of Root Plan of transmission line  Prepration of Engineering Drawing for Civil and Electrical work  Engineering estimates  Approval of estimates Director Deputy Director Assistant Director Line Supredendant
  • 10. Construction Activities  Civil work  Electrical Equipment installation  Testing  Commissioning  Hand over to the department Departments  Planning and Schedule Head: Director  PMS unit  Precruitment Head: Director  Finance Head: Director  Enviromental unit Head: Deputy Director 1. Planning and Schedule PMU Planning and Schedule Precurement Finance Environmental
  • 11.  Forecasting (Power Market Survey)  Line forecasting  Load Forecasting  Load forecasting can be handled in two ways.  New grid station  Old grid station either by Augment or by Extent  Daily problem  Issues  Tender evaluation Committee Projects are floated and this committee basically checks which companies are responsive and which are non-responsive Minimum Area for Grid Station: 18-20 canal 40 to 50 crore is needed approximately, to build grid station Whenever load increases more than 5MV for single user, than it’s the rule that they are needed to bulid their own grid station. Transformer Rating: 13MVA, 26MVA, 40MVA PMS Unit: This is basically an important section of Planning and Schedule. Its work include following things:  Future Load in this area  Load Flow studies (Software work) Through this PC-1 report is generated.PMU do only this. PC-2,PC-3, PC-4 these reports are generated on later stages.  Cost  Cost Benefit ratio  Payback period  Approval  Head Quarter (Chief executive)  BOD  Ministry  Secretary of Water and Power resources
  • 12. 2. Precruitment Whenever public money is involved, there is a process known as “Precurement”. There are some rules introduced by PPRA, that must be obeyed during procurement. Precurement has severeal advantages that are listed below:  Competitive environment  Transparency  Accountability In procurement “Brands (company names)” are not specified, only specification of the things are mentioned. It includes,  Number of transformers  Number of lines or conductors  Towers There are basically two resoures:  LESCO own resources  World Bank, Asian Development (ADP) resources The process is followed as:  Tender float  If equipment is in store, no need to tender  Whenever company is selected by the process of tendring, equipment is supervised  Buy equipment  “Contract Document” of every project 3. Finance This department basically deals with loan.  Initially 10% pay  Two types of projects  LESCO own revenue These project are supervised by PDGSE (Project Director GSE)  Loan from World Bank(head office in New York), Asian Development (ADP) (head office in Monala) These projects are supervised by LESCO and also by ADP ADP gave loan in installations known as Tranch 1, Tranch 2, Tranch 3, Tranch4
  • 13. Own Revenue Ways:  Ascar account (Billing)  Deposit work  Capital contribution e.g. Meter cost Types of Payments by LESCO A. Direct payment Like payment to PEL. The steps for this payment are as followed:  Withdrawal application  Bill copy  Inspection Certificate  Performance Guarantee  GRN  Nonpayment certificate  Tax deduction In this payment there is usually a guarantee of 18 months or 24 months B. Payment through LC (Letter of Credit) The steps for this payment are as followed:  Firm invoice (Bank Alfalah, Sindh Bank, Standard Charter Bank)  PU copy  ADP gives to bank and Bank gives to Firm C. Payment through Advance (Empress) We get money in advance. But this method has the disadvantage of “Interest”. Although money is not spend on project and still is present in Bank, the interest is going to start from the first day on the total amount that is took in advance. D. Disbursement through Re-imbursement Use money our self Quantity Rate Liquid and Damages FBR Net amount A/C
  • 14. due to late (LD) LD can be maximum 10% of the total. Famous Contractors of LESCO  PEL  Siemens  HEC  NEW AGE  Fast Cable  Universal Cable  NSI  Sadique Son’s (incoming outgoing panels) 4. Environmental unit The important factors that must be considered and should be controlled are:  Air noise  Water testing Environment Impact Analysis (EIA) Initial Environment Examination (IEE)  After study the report is sent to Ministry of Environment (EPD)  PC1 (5 years) is generated, for this actually EIA is compulsory  This is sent to Ministry of Environment, which issues the NOC (set of clauses), which need to be implement.  Binding document is prepared  Environment Monitory Plan is prepared  Set of conditions
  • 15.  Contractor follow and represent monthly report Working Environmental unit make sure the following things:  Training  Safety hazards  Complain reports (Check list)  Compensation (Crop compensation)  Land acquisition settlement plan  3 payment  Erection  Stringing  Compact Fluorescent lamp (CFL) project This is an energy conservation project, in which 2 CFL are given to each user.  Carbon Credits If emission of Carbon is reduced than UNO gives credit and millions of dollars are rewarded MO (Central) Circle Instructor: Muhammad Hafeez Designation: Deputy Director (TECH) Area Distribution
  • 16. Divisions: Each circle has five divisions. The officer which controls the division is "Exion". It mean, each circle has 5 exions. Central Circle Divisions: The name of central circle divisions are given below, 1. Township division 2. Riwind division 3. Allama-Iqbal Town division 4. Samna Bad division 5. Civil Line division Circle Division Sub Division
  • 17. Sub Divisions Each division is further divided into different number of Sub Divisions, 1.Township division This divisions has seven sub divisions, also two more sub divisions get included from 1st of July. Names are given below: i. Johar town sub division ii. Wapda town sub division iii. Green town sub division iv. Township sub division v. College road sub division vi. Liaqat'a'bad sub division vii. Air line sub division viii.Engineer town sub division ix. Behar Colony sub division 2.Riwind division This divisions has four sub divisions. Names are given below: i. Ali Raza Abid sub division (near Thokar) ii. Jea Bhaga sub division iii. Riwind sub division iv. Manga sub division v.
  • 18. 3.Allama-Iqbal Town division This divisions has six sub divisions, also three more sub divisions get included from 1st of July. Names are given below: i. Iqbal Town sub division ii. Multain Road sub division iii. Canal Road sub division iv. Niaz Baig sub division v. Choong sub division vi. Awan Town sub division vii. Rana Town sub division viii.Mustafa Tow sub division ix. Shahpur (Kanjra) sub division 4.Samna Bad division This divisions has five sub divisions. Names are given below: i. Islam Pura sub division (near MAO) ii. Prame Nagar sub division iii. Samana Bad sub division iv. Itahaad Colony sub division v. Said Pur sub division 5.Civil Line division This divisions has four sub divisions.
  • 19. Names are given below: i. Ichra sub division ii. Government Officer Residence (GOR) sub division iii. Mazang sub division iv. Islamia Park sub division Hierarchy  SDO / Assistant Manager  Grade 17 officer  Two courses are needed for it, 1. Sector Specific (Junior Management Course) which covers the period of 6 week. Its classes are arranged in Wapda Engineering Acadmy. 2. WASC (Wapda Administrative Staff College) which covers the duration of 9 weeks. Its classes are arranged in Islamabad.  Additional EXION If there is no promotion of SDO and ten year pass than, there is a promotion on next grade and given the designation of "Additional Exion", but he will continue the same work.  Pre Promotion exam from SDO oblique junior engineer to Exion oblique Senior engineer, is needed to clear.  EXION / Deputy Manager  Grade 18 officer.  A test is needed for it, known as MMN (Middle Management Course) which covers the period of nine to ten weeks.  Additional SE (Supredendant Engineer)  If twenty year (SDO + Exion) pass and there is no promotion from exion to SE than, there is a promotion on next grade and given the designation of "Additional SE", but he will
  • 20. continue the same work.  SE (Supredendant Engineer) / Manager  Grade 19 officer  Chief Engineer  Grade 20 officer  In LESCO there are four Chief Engineers i. Chief of Operation and maintainence (1st chief engineers). 4 circles are controlled by one chief engineer. ii. Chief of Operation and maintainence (2nd chief engineers).3 circles are controlled by second chief engineer. iii. Chief of Material Management (3rd chief engineers) iv. Chief of Engineer Planning (4th chief engineers)  GM  Grade 20 officer  No further grade for Engineers in this section Rank Hierarchy
  • 21. Connection Authority  SDO 8-10KW Commercial connections GM Chief Engineer Supredendant Engineer Exion Sub Division Officer
  • 22.  EXION 70KW industry  SE 70-500KW  Chief Engineer Planning (LESCO Head Quarter B3) Above 500KW Types of Meters on basis of phases  Single phase meter  Three phase meter  MDA (Maximum Demand Indicator) Types of Meters on basis of Load A1 (01) Domestic A2 (04) Commercial B1 (07) Industry 25KW B2 (10) Above 500KW B3 Above 500KW/ Bulk supply (They have to develop their own grid) B4 DIVISION Instructor: Tariq Mehmood Butter Designation: Exion What is segregation? This is due to block billing which implies different tariff rates. If unis exceed from specified limit than tariff changes and different rates are charged as per unit.
  • 23. Bifurcate means “Divide into branches” 1) Computerized meters  Measurement of consumed energy  Measurement of consumed units  Control of supply 2) Smart meters  Self-monitoring  Analysis  Reporting 3) AMR meters(Automatic Meter Reading)  GSM based, work on Radio Frequency (RF) Exion Competency Basically, he permits the new connections  Meters  New Transformers  LT Feeders  Electrifying new colony  Matters of Accounts  Proposal things  Employee salary  Capital contribution This includes cost instead of billing like cost of Poles and Wires.  Security Rupees per KWh, this is related to RO  Meter price Exion office Financial Power Designation Range of Money Range of Extension SDO Upto 25,000 3 days
  • 24. Exion 25000 to 1 lac 3 days SE 1 lac to 2,3 lac 4 days Chief Engineer Above 2,3 lac Standard Operating Procedure (SOP) Power Dispatch Centre (PDC) This is our purpose, so we want to shut down. Fault in our lines. Permit to work (PTW). SUB DIVISION Instructor: Engr Kamran Naveed Designation: Sub Division Officer (SDO) The main and the most important working of SDO office and its labor is the “Continuity of Supply” SUBDIVISION SECTIONS First of all there is an “Admin section”, which basically overheads the four sections in SDO office. Any activity from these four sections or external matters are first passed through admin section. The above mentioned four sections are:  Complain section  MCO/ DCO section (Meter connection or disconnection section)  Reading section  Maintenance section
  • 25. Admin section  There are two Sub Division Clerks (SDC)  There are four or six Lower Division Clerks (LDC). Complain section Instructor: Mr.Saleem Designation: Line Supredendant This is a section with twenty four hours service, there are three shifts in this section.  6am to 2pm  2pm to 10pm  10pm to 6am There is a complain register, with code e.g. wxyz w represents Region x represents Circle y represents Division z represents Sub division SDO Admin section Complain section MCO/DCO Section Reading section Maintenance section
  • 26. Complain register looks like Serial Number Time Complain number Address Complain Line man name Time of departure Time of arrival Remarks MCO/DCO section Instructor: Ghulam Hussain Naqvi Designation: Line Supredendant The following registers are used in the whole process.  Store requisition  CA 21 Entrance of new meters  CA 22 Entrance of old meters  MCO Book Meter Change Order Book. In this register details of old meters and also the details of new meters are present  Challan Form  Material return order Meters are returned to the store Reading section The hierarchy of this section is as:  MRSS (Meter Reading Section Supervisor)  MS1 (Meter inspector 1)  MS2 (Meter inspector 2) Working CP11 Book This book is allotted to one person which is enrolled in CP20
  • 27. Meter reading list This list has all the readings and is send to computer man in RO office, which enters the data There are also two more registrers named as: o Received Register o Sold register BATCHES Batch Number Load type Load Meter type Read by 1 to 18 Domestic/ Commercial 19 Tube wells (Govt) 20 Industry 0-5 KW B1 45 Tube well (Private) 46 Industry 5-40 KW 24 Industry 500 KW B2 SDO 24 Industry 500-5000KW B3 Exion 24 132 kv (grid) Above 5000 KW B4 Exion Green town sub division This sub division has 14 feeders. In which there are:  Ten are “Distributed feeders”  Four are “Independent feeders” Distributed feeders Constructed on LESCO’s cost. Anyone can take connections from feeders. Independent feeders Dedicated to B3 connections (When load is beyond 1000KW). These feeders are owned by the user (industry) and no other user can take connection from it. SUBDIVISION ACTIVITIES
  • 28.  Prime activity Accountability of received units from Grid  Continuity of supply Maintenance, complains  New connections  Rehabilitation of electric system Up gradation of system e.g. LT , HT  Redressal of complains Meters Meters can also be characterized as:  Direct meter  Indirect meter CT control, max limit is 5A Types of faults Basically there are two types of faults  Phase to phase fault  Phase to neutral fault PDC (Power Dispatch Center) NPCC (National Power Control Center) GRID STATION Generation is usually at 11.5KV Parts of Grid Station  Transformer (Tap changer)  On load transformer  Off load transformer
  • 29.  Bushing Point where we have terminals for connection  Lightning arrestor  PT  CT  Line insulator  Insulator  Circuit breaker (SF6 breaker) Quenching medium is Sulphur Hex Fluoride Gas  Bus bar insulator  Capacitor bank (2KV)  Overhead ground wire  11KV vacuum breaker PD Construction This department has the following three type of work  Rehabilitation  Government work ( Poles and lines shifting due to LDA work)  Private work There are 7 circles in LESCO but these circles are controlled by 6 exions of PD Construction. Working Design is produced in Head Office under the supervisory of “Chief Engineer Development” Types of conductors Three types of conductors are commonly used in field  Osprey Used for HT lines. It has 18 aluminum strands and one steel strand in the middle.  Rabbit Used for LT lines. It has 7 aluminum strands and one steel (consist of six thin fibers of steel) strand in the middle
  • 30.  Dog Used for LT lines. It has 7 aluminum strands and one steel strand in the middle. Pole Distance Types of Conductor on pole Distance between two poles Osprey 135 Rabbit 160 Dog 180 Components of Pole Now a days, “Steel Structure” poles are used. Its components are given below:  Steel cross arm  11KV brace  11KV pin insulator  11KV steel pin  Bolts 2 * 5/8 bolt Double arming (DA) bolt  Stray rod (Rod + Elbow) This is buried in ground to support the ending pole Types of Insulators  Disc insulator  School insulator Assemblies on pole’s top Two types of assemblies are:  1L assembly Used in running lines  7L assembly Used when there is ending point in the structure