A Lean Model Based Outlook on
Cost and Quality Optimization
in Software Projects
STC 2009
Kalyanam Kannan
www.sonata-software.com Page No. 2
Abstract
A large quantum of effort and research is being invested to address the Cost and
Quality factors in software projects. Though the solutions, models and methodologies
are well established through experimented processes, adoption and optimization of the
required parameters for a specific project to obtain predictable and acceptable quality
with minimum costs has always remained a challenge.
This paper discusses the Lean process in detail with the help of project data and
demonstrates that simple, affordable and adoptable processes are more economical
and focused on quality. Also, it is observed that the Lean Model enables a project to
be well monitored and controlled by focusing on critical elements, thereby reducing
overheads of bulky documentation and irrelevant processes. The above findings are
statistically analyzed using the coefficient of variation, which strikes a direct correlation
with the predictable quality in a project.
Page No. 3
Lean Model – An Overview
The quality and cost of software are two important areas under constant vigil during
the process of software development and delivery. The quality of software bears a
direct correlation with the thought process and steps followed to achieve the expected
output. The costs involved in executing a streamlined work process and repeatable
steps for software development are considered to be significant overheads in the
industry.
Several teams and groups have been continuously working on a model to achieve high
quality with minimum investments of effort and costs. The Lean process takes a simple
approach to address this business challenge by eliminating unwanted steps in a project
or product development, which translates into ample and required benefits, to remove
overheads.
A Lean Model focuses on eliminating activities that do not add any value to the project
and fatty processes in a lifecycle. The model also offers multiple advantages by
allocating more time and effort for product critical areas and thus minimizing effort for
a particular process activity, which would normally be less significant for the entire
application.
In other words, elimination of wasteful activities from the quality control processes in
a lifecycle helps tailor a process, which is more efficient and can be easily adhered to.
The Lean Model implementation is a combined change in the strategic and operational
processes. (Not too sure about controls)There are several tools and working models
that need to be altered and optimized to remove or minimize wasteful activities to
attain efficiency and optimization.
The generic Lean principles of software development are well established and the same
is presented below for reference:
1. Eliminate waste: Eliminate any process activity that is not adding value to
the project delivery
2. Amplify learning: A sustainable model to manage knowledge and repeatable
process to replicate the knowledge sharing across the projects.
(Tools: Feedback, iterations, synchronization and set-based development)
3. Decide as late as possible: Decision to incorporate the required processes
for effective delivery so that the cost and effort involved for change canbe
avoided.
Tools: Options thinking, the last responsible moment and decision-making.
4. Deliver as fast as possible: Faster delivery resulting in optimized cost and
better productivity.
Tools: Pull systems, Queuing Theory and cost of delay.
Page No. 4
5. Empower the team: Encourage people to take responsibility, get motivated
and work as a team, and responsibility for the outcome and authority to make
it happen.
Tools: Self-determination, motivation, leadership and expertise.
6. Build integrity: Customer’s experience with the delivery, whereas conceptual
integrity is how well the architecture and system components work together to
bring about the perceived integrity. Obviously, testing-unit and integration
testing, is a major part of integrity.
Tools: Perceived integrity, conceptual integrity, refactoring and testing.
7. See the whole: Holiostic and end-to-end approach for projects so the end
point implementation and business value is thought through during the initial
stage of the project and risks identified and mitigated.
8.
Tools: Measurement and contracts.
This White Paper extensively follows Lean principles in the areas of quality control and
quality management by eliminating unwanted processes, and improving team
integration and integrity. It also discusses the outcomes of the observations in detail.
An attempt has been made to analyze data from various projects and the effort
expended in each of the processes and operational activities. The percentage effort
from these activities is mapped to the Lean Model of working and the reduction in
effort in the respective activity areas is predicted. The quality of the deliverables is
measured using defect detection efficiency and coefficient of variation, which is a
measure of risk. Finally, the said parameters and observations are compared between
the Lean and Normal Models.
Sample Study – Data Analysis and Prediction
The aforementioned Lean Model was applied to a sample of projects from Travel
domain, which consisted of Web applications, BI systems, data warehouses, staging
area database and mainframe systems. The finite data on effort spent on each of the
project activities, listed below for quality control, were obtained from ABTS (Activity-
Based Tracking System) and the release data, such as coverage, test cases, defect
leakage, were obtained from the test and project management tools.
The sample data from the above mentioned projects were studied in detail by breaking
them into Planning, Analysis, Development and Testing phases, as done in any other
development model, and all standard processes were monitored throughout this study.
The activity parameters given below were incorporated into the Lean Model and
redistribution of the probable effort was carried out with the help of coefficient of
variation for the mentioned activities. In all these cases, the risk parameter was
maintained at less than 3% for projected Lean activity percentages. The results of the
Lean Model were compared with those of the Standard Process Model. The results
Page No. 5
found were encouraging and highlighted a substantial amount of efficiency, thereby
reducing and eliminating processes and activities that did not value add.
The sample consisted of application development projects of the Travel domain. The
activities studied, using the Standard Process Model, are given below. The parameters
related to quality control are also discussed in this section with their appropriate
weightings in percentages.
Table 1: Effort Distribution on Process Activity Parameters
________________________________________________________
Phase Activity Parameters % Effort
________________________________________________________
Analysis
Requirement Analysis 5
Requirement Clarifications 5
Technology Feasibility Analysis 3
Quality Strategy 5
Effort Estimation 4
Design
Test Strategy 3
High Level Test Scenarios 3
Test Reviews 5
RTM 5
Development
Test Plan Development 5
Test Case Development 18
Test Review 5
Design-Test Case Updation 5
Testing
Test Execution 15
Defect Logging 5
Defect Analysis 2
Test Documentation 5
Test Signoff 2
__________________________________________________________
The table above provides effort distribution across various activities to achieve a
controlled and monitored quality process for predictable software releases.
The data in the table and the proportion of efforts are correlated with the quality of
projects, which is measured using defect detection efficiency as one of the key
parameters, while quality index was measured using Test Maturity Model-based
indices. The available reports based on data and overall risk, derived from quality
index, are represented in the graphs below:
Page No. 6
Figure 1 : Quality Index, DDE and Risk Trend (Normal Model) Figure 2 : Quality Index, DDE and
Risk Trend (Lean Model)
Figure 3 : Quality Index Comparision for Normal and Lean Samples
The graphs above provide details of the sample projects in terms of Quality Index (QI),
Defect Detection Efficiency (DDE) and Coefficient of Variation (CoV).
Figure 1 provides details of those trends in the projects, which followed standard
processes based on the Capability Maturity Model (CMM) and it is observed that the
average quality index, DDE and CoV were around 7, 85% and 30 respectively.
Figure 2 provides simulated data for Lean Model and it is observed that the average
quality index, DDE and CoV were around 8, 90% and 25, in that order.
The improvement in quality from an overall perspective is discussed in detail in the
sections below.
The aforesaid sample projects were fitted into the framework of Lean Development
Model, in which the non-value add processes were minimized by using efficient tools
and thinner documentation processes.
The proven seven stages of the Lean Model were applied in each and every stage, and
the benefits were compounded in each of these areas and the overall efficiency was
observed. The overall Lean Process implementation was provided in a tabular format.
0
1
2
3
4
5
6
7
8
9
0
20
40
60
80
100
120
sample 1 sample 2 sample 3 sample 4 sample 5 sample 6 sample 7 sample 8 sample 9 sample 10
COV DDE QI
0
1
2
3
4
5
6
7
8
9
0
20
40
60
80
100
120
sample 1 sample 2 sample 3 sample 4 sample 5 sample 6 sample 7 sample 8 sample 9 sample 10
COV DDE QI
0
1
2
3
4
5
6
7
8
9
sample 1 sample 2 sample 3 sample 4 sample 5 sample 6 sample 7 sample 8 sample 9 sample 10
QI(NPM) QI (LPM)
Page No. 7
The reduction in effort due to usage of the Lean Model was based on iterations, where
the CoV (risk) did not exceed a value of 30. Also, it should be noted that the below
mentioned effort distribution is prone to change if the absolute value of CoV is altered.
In general, higher the risk coefficient, more is the effort reduction using the Lean
Model. This also provides a wide range of scope for Risk-Based Testing (RBT) and is a
promising area for further analysis and research.
Figure 3 depicts the difference between the Normal Process-based approach and Lean
Process-based approach for quality index values. Although both the models use the
same set of activities towards delivery, the percentage and amount of focus provided
for each of the activity is better managed in the Lean Process, which is likely to yield
better quality behavior as displayed above.
Lean Model Analysis and Discussions
It is observed by means of this hypothesis that around 29% of effort in quality control
can be saved and utilized for various other purposes. The Lean Model gains importance
because the effort saved can be used in the areas of coverage and reviews, which
enhance the quality and predictability of software. The reduction in effort has direct
impact on cost savings, and the processes can be fine-tuned to achieve cost and effort
optimization.
The findings on quality of the projects taken as sample provide the following indicators
and help us identify the areas of importance to achieve quality and cost reduction.
Table 2: Percentage effort distribution in normal and lean process models
% Effort
Distributi
on
Estim
ate
Waste
Effecti
ve
learni
ng
Decide
Late
Delive
r Fast
Empo
wer
Team
Integrity
Holistic
View
Lean
Distribu
tion
Requirement
Analysis
5 5 5 3 3 4 3 2 6.0
Requirement
Clarifications
5 1 3 5 5 2 2 2 2.9
Technology
Feasibility
Analysis
3 2 2 3 3 3 3 3 3.0
Quality
Strategy
5 3 3 5 4 3 3 3 4.0
Effort
Estimation
4 1 3 1 5 3 3 5 3.0
Test Strategy 3 3 1 3 3 3 3 3 2.7
High Level Test
Scenarios
3 3 2 2 3 3 3 3 3.0
Test Reviews 5 2 2 3 5 3 5 5 2.1
RTM 5 1 5 3 5 5 5 5 4.1
Test Plan
Development
5 5 3 5 5 5 5 2 4.3
Test Case
Development
18 20 15 20 20 20 20 10 14.3
Test Review 5 1 2 5 5 5 5 2 3.6
Design-Test
Case Up
gradation
5 1 1 1 1 1 1 1 1.0
Test execution 15 15 15 10 15 15 15 10 10.6
Page No. 8
% Effort
Distributi
on
Estim
ate
Waste
Effecti
ve
learni
ng
Decide
Late
Delive
r Fast
Empo
wer
Team
Integrity
Holistic
View
Lean
Distribu
tion
Defect Logging 5 2 2 2 2 2 2 2 2.0
Defect Analysis 2 2 2 2 2 2 2 2 1.0
Test
Documentation
5 1 1 1 1 1 1 1 1.0
Test Signoff 2 2 2 2 2 2 2 2 2.0
Overall View 100 70.6
Figure 4: Percentage effort distribution in normal and lean process models
The figure above provides an insight into effort distribution in a Quality Control Model.
It is obvious from the graph that the critical steps or processes were accorded more
importance and weightings as compared to the Standard Model. This helps address
the issues of quality and cost in an effective manner. A greater amount of effort for
requirement analysis, quality strategy and effort estimation considerably decreased
the test case development and test execution efforts. A holistic approach and
understanding business criticality of the application or project under development
resulted in decreased effort during the testing phase and minimized the wastages on
clarifications.
Elimination of Waste
Elimination of waste in the sample projects discussed above was based on the
following:
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
20%
Requirement
Analysis
Requirement
Clarifications
Technology
FeasibilityAnalysis
Quality
Strategy
Effort
Estimation
TestStrategy
HighLevel
TestScenarios
TestReviews
RTM
TestPlan
Development
TestCase
Development
TestReview
Design-Test
CaseUpdation
Testexecution
DefectLogging
DefectAnalysis
TestDocumentation
TestSignoff
Effort Distribution Lean Distribution
Page No. 9
 Development of a software / code and a test case, which were waiting to be
tested or integrated
 Incapability to test the code due to non-availability of any other components
 Development of irrelevant test cases, which were not to be used immediately
 Wait for clarifications and defect details
 Excess documentation or effort duplication in terms of reporting
In other words, as per Lean thinking, anything not adding any value to the project was
considered to be waste. This included:
 unnecessary test cases and excessive unwanted coverage
 Unclear requirements and unnecessary documentation
 Complex communication procedures and non-agreed upon engagement models
In order to be able to eliminate waste, one should be able to recognize it. For example:
 If some activity could be bypassed or the result could be achieved without it, it
is waste.
 Any quality control activity that is not completed and needs to be repeated is
also a waste.
 Extra processes and features not often used by project teams are waste.
 Waiting for other activities and teams for integration of code and related
processes is also considered as waste.
 Defects of lower quality are waste. Managerial overheads not generating real
value are waste.
In the sample projects, a value stream mapping was carried out and waste was
minimized, as reflected in Table 2.
Most of the waste was eliminated during phases of requirements understanding and
requirement mapping to the test cases, ultimately saving more effort for test
development and execution. A better understanding of the overall project and realistic
effort estimates also proved helpful in elimination of wastages from the project.
As per an analysis, reduction of 30% waste -- in terms of effort due to requirement
understanding, proper effort estimation and overall business understanding of the
project -- helped trim the process activity efforts. The quality of the deliverables,
measured in terms of defect leakage and risk (CoV), also showed satisfactory quality
levels.
Page No. 10
Amplify learning – Feedback mechanism
The best approach to improve quality and amplify learning within the teams is to get
timely feedback from the testing and quality teams. Most of the defects should be
prevented by running tests as soon as the code is written and delivered. Instead of
adding more documentation or making detailed plans, different ideas should be
experimented with by writing code. The process of user requirements gathering should
also be simplified by presenting screens to the end-users and asking them for inputs
through a simple, workable process.
This specific Lean activity plays a major role in Lean quality control. The high-impact
area or the major beneficiary of this activity is the development team. A considerable
amount of effort can be saved by getting feedback from the testing team immediately
after the software release. More the knowledge of the testing and quality teams, higher
are the benefits of integration and business-based acceptance of the software with
minimum defects.
The sample study predicted that improving the business knowledge of the testing and
quality teams benefited the project by:
 Providing faster feedback to the development teams
 Providing end-to-end test scenarios for integration of code
 Reducing the effort in the development of unwanted test conditions for a
specific release
 Reducing the time delay in release process during production
The simulations based on the above-mentioned benefits predicted a 15% reduction in
cycle time due to integrated and appropriate learning and sharing mechanisms. This
also involved setting up a centralized knowledge management system and planned
meetings during the project period.
The findings were in line with the definition of learning given below:
“The learning process is sped up by usage of short iteration cycles – each one coupled
with refactoring and integration testing. Increasing feedback via short feedback
sessions with customers helps when determining the current phase of development
and adjusting efforts for future improvements. During those short sessions, both
customer representatives and the development team learn more about the domain
problem and figure out possible solutions for further development.
Thus, the customers better understand their needs, based on the existing results of
development efforts, and the developers learn how to better satisfy those needs.
Another idea in the communication and learning process with a customer is set-based
development – this concentrates on communicating the constraints of the future
solution and not the possible solutions, thus, promoting the birth of the solution via
dialog with the customer.”
Page No. 11
Decide as late as possible – Minimize assumptions and
predictions
There are several aspects to be taken care of in a complex software development
environment. The approach of deciding the change as late as possible, will help reduce
assumptions and predictions during the course of the project and get real requirements
and clarifications based on a simple and effective process. This prevents A lot of rework
in the later stages. The iterative approach promotes a simple principle – the ability to
adapt to changes and correct mistakes -- which might be very costly if discovered after
the release of the software.
In a nutshell, this approach prescribes efforts only on a complete and clear
understanding of requirements, and advises against investment of any efforts in
assumptions and predictions, which may need re-work (end up in re-work?????) during
the final stages of the project.
The sample study and simulated data concluded that around 10% of excess effort was
being wasted due to commencement of project activities without a clear understanding
of the requirements. The same is also reiterated in the Agile Development Model
Deliver as fast as possible – Decrease iteration time
The sample projects developed using Agile Development Model responded well to the
dynamic customer needs and demands in a shorter period of time.
Caution should be exercised in communicating and following integrated team approach
during development and testing, so there are no discrepancies between the perceived
product / project and the actual product / project developed.
Business requirements have become more dynamic due to compelling needs of the
industry, and therefore, the processes and methodologies should be adaptable, flexible
and effective, to facilitate faster delivery. The Lean Model exactly falls in line with the
business needs and helps the customers decide what they really need.
Empower the team – Decisive team and proper engagement
Team engagement and working agreement between business owners, development
teams and quality teams play a very critical role in the success and quality of delivery.
It is important to agree on a simple process, through which requirements and changes
will be communicated and clarifications will be addressed. The decisiveness of the
identified members of the team adds value and proves to be the central success factor
for the Lean Model.
Defect management and acceptance of the project heavily depends on the
engagement model as it influences the cycle time and creates a chain effect throughout
the lifecycle.
The sample project data revealed the delay and ambiguity during development, testing
and acceptance due to lack of decisions at various stages, which resulted in a
Page No. 12
cumulative effect leading to delay and shortening of testing cycles. This resulted in
lesser test coverage and delays in delivery.
Building integrity – Deliver business value
Integrity of software is rated on the basis of various factors like flexibility,
maintainability, efficiency and responsiveness. This is normally achieved through face
to face discussions and finally delivers a project full of potential that yields the
expected outcome and addresses the business requirements with minimum possible
efforts. The process of building integrity also proves that understanding of business
requirements is critical to test a project or product for its long-term usability and its
ability to cater to the changing market needs.
See the whole – Holistic approach
Software quality should not be restricted to testing; it should also cover and
encompass the entire software development lifecycle. It is interesting to note that all
activities in the lifecycle are interdependent. A holistic approach to the entire
development model, with minimum processes and small repeatable activities, is the
key differentiator of the Lean Model.
The sample study demonstrated that there was a considerable reduction in effort, with
faster releases, when quality was controlled through a managed model, brought about
by interaction among various project stakeholders. This established the effectiveness
of various small processes -- like stand-up meetings, status updates, triage priorities,
daily feedback mechanism, etc. -- in a day-to-day working environment.
Conclusion
The sample projects provided some vital data, which evidenced that efficiency could
be enhanced and processes could be improved by using the Lean Model:
 The cost to quality and subsequently, the effort is likely to be reduced by
30% by using the Lean Model. Focusing on vital tasks like requirement
understanding and making strategies also leads to effort reduction in the test
case development and execution phases.
 The predicted reduction in effort and increase in productivity is attributed to
elimination of wastes like waiting period for clarifications, and planning the
test cases and activities in the right sequence, so testing was not affected due
to non-availability of integration and systems. At the time of writing this
paper, the team was working at around 80-85% productivity and going Lean
was expected to enhance this to around 95%.
 It is expected that the cycle time will be reduced by 30% owing to effective
feedback from testing, automated build and deployment practices.
The Lean Model seems to be the future of software quality control as it falls in line with
the industry slogan “Enhanced Quality and Reduced Cost.” Optimization of this model
and its customization for specific projects would lead to benefits as it recommends
execution of only those activities that bring value add to the project and thereby,
provide more time for and focus more on the critical success factors in a project.
Page No. 13
It is also very vital to note that suitable and capable resources are a pre-condition to
adopt the Lean Model for a project.
References:
1. Mary Poppendieck, Tom Poppendieck Lean Software Development: An Agile
Toolkit for Software Development Managers
2. Lean Software Institute - Testing in Lean Software Development
3. Jeffrey k. Liker , The Toyota Way: 14 Management Principles from the World's
Greatest Manufacturer

More Related Content

What's hot

Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality ManagementGiO Friginal
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Managementasim78
 
Ensuring Project Quality Powerpoint Presentation Slides
Ensuring Project Quality Powerpoint Presentation SlidesEnsuring Project Quality Powerpoint Presentation Slides
Ensuring Project Quality Powerpoint Presentation SlidesSlideTeam
 
PMP : Webinar on Quality Planning
PMP : Webinar  on Quality PlanningPMP : Webinar  on Quality Planning
PMP : Webinar on Quality PlanningSaket Bansal
 
Quality management strategy template
Quality management strategy templateQuality management strategy template
Quality management strategy templateselinasimpson2701
 
Quality management strategy example
Quality management strategy exampleQuality management strategy example
Quality management strategy exampleselinasimpson1201
 
Quality planning
Quality planningQuality planning
Quality planningRahul Hada
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality managementejlp12
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality ManagementSerdar Temiz
 
Quality in project management
Quality in project management Quality in project management
Quality in project management Zeeshan Azhar
 
Project Quality Planning and KickOff
Project Quality Planning and KickOffProject Quality Planning and KickOff
Project Quality Planning and KickOffkaushikanirudh
 
Quality management assurance
Quality management assuranceQuality management assurance
Quality management assuranceselinasimpson2701
 

What's hot (20)

Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Management
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Management
 
Project quality management
Project quality managementProject quality management
Project quality management
 
Ensuring Project Quality Powerpoint Presentation Slides
Ensuring Project Quality Powerpoint Presentation SlidesEnsuring Project Quality Powerpoint Presentation Slides
Ensuring Project Quality Powerpoint Presentation Slides
 
PMP : Webinar on Quality Planning
PMP : Webinar  on Quality PlanningPMP : Webinar  on Quality Planning
PMP : Webinar on Quality Planning
 
csc 510 Project
csc 510 Projectcsc 510 Project
csc 510 Project
 
Quality management strategy template
Quality management strategy templateQuality management strategy template
Quality management strategy template
 
Quality management strategy example
Quality management strategy exampleQuality management strategy example
Quality management strategy example
 
Quality planning
Quality planningQuality planning
Quality planning
 
My MBA Course on Project Quality Management
My MBA Course on Project Quality ManagementMy MBA Course on Project Quality Management
My MBA Course on Project Quality Management
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality management
 
8 quality PMBOK
8 quality PMBOK8 quality PMBOK
8 quality PMBOK
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality Management
 
Quality in project management
Quality in project management Quality in project management
Quality in project management
 
Pmb
PmbPmb
Pmb
 
Ch28
Ch28Ch28
Ch28
 
Project Quality Planning and KickOff
Project Quality Planning and KickOffProject Quality Planning and KickOff
Project Quality Planning and KickOff
 
Risk and quality management
Risk and quality managementRisk and quality management
Risk and quality management
 
Project Metrics & Measures
Project Metrics & MeasuresProject Metrics & Measures
Project Metrics & Measures
 
Quality management assurance
Quality management assuranceQuality management assurance
Quality management assurance
 

Viewers also liked

Software process models
Software process modelsSoftware process models
Software process modelsJomel Penalba
 
MODELS USED IN SOFTWARE DEVELOPMENT
MODELS USED IN SOFTWARE DEVELOPMENTMODELS USED IN SOFTWARE DEVELOPMENT
MODELS USED IN SOFTWARE DEVELOPMENTPaYal Umraliya
 
Software development processes
Software development processesSoftware development processes
Software development processesguest45d037
 
Lecture 05 Software Quality Management
Lecture 05 Software Quality ManagementLecture 05 Software Quality Management
Lecture 05 Software Quality ManagementAchmad Solichin
 
Lecture 02 Software Process Model
Lecture 02 Software Process ModelLecture 02 Software Process Model
Lecture 02 Software Process ModelAchmad Solichin
 
Dss vs expert system
Dss vs expert systemDss vs expert system
Dss vs expert systemAnita Johri
 
Vendor Evaluation by configuring Vendor Ratings and Vendor Scorecard:
Vendor Evaluation by configuring Vendor Ratings and Vendor Scorecard:Vendor Evaluation by configuring Vendor Ratings and Vendor Scorecard:
Vendor Evaluation by configuring Vendor Ratings and Vendor Scorecard:Sonata Software
 
Str8ts Weekly Extreme #45 - Solution
Str8ts Weekly Extreme #45 - SolutionStr8ts Weekly Extreme #45 - Solution
Str8ts Weekly Extreme #45 - SolutionSlowThinker
 
МультиТендер - почему наша реклама действительно работает
МультиТендер - почему наша реклама действительно работаетМультиТендер - почему наша реклама действительно работает
МультиТендер - почему наша реклама действительно работаетtelekomkonsalting
 
Evaluation q1 presentation
Evaluation q1 presentationEvaluation q1 presentation
Evaluation q1 presentationAharkness2512
 
Question 1 - Conventions
Question 1 - ConventionsQuestion 1 - Conventions
Question 1 - ConventionsPBirkettchs
 
2 May 2012 1HBCT Weekly News Update
2 May 2012 1HBCT Weekly News Update2 May 2012 1HBCT Weekly News Update
2 May 2012 1HBCT Weekly News UpdateNoel Waterman
 
Pedro García-Noblejas, en Forbes (octubre 2013)
Pedro García-Noblejas, en Forbes (octubre 2013)Pedro García-Noblejas, en Forbes (octubre 2013)
Pedro García-Noblejas, en Forbes (octubre 2013)Interbrand Madrid
 
Malaysian Pestiside Board Registration Certicifate
Malaysian Pestiside Board Registration CerticifateMalaysian Pestiside Board Registration Certicifate
Malaysian Pestiside Board Registration Certicifateentogenex
 

Viewers also liked (20)

Software process models
Software process modelsSoftware process models
Software process models
 
Assesment process model
Assesment process modelAssesment process model
Assesment process model
 
MODELS USED IN SOFTWARE DEVELOPMENT
MODELS USED IN SOFTWARE DEVELOPMENTMODELS USED IN SOFTWARE DEVELOPMENT
MODELS USED IN SOFTWARE DEVELOPMENT
 
Software development processes
Software development processesSoftware development processes
Software development processes
 
Lecture 05 Software Quality Management
Lecture 05 Software Quality ManagementLecture 05 Software Quality Management
Lecture 05 Software Quality Management
 
Software process model
Software process modelSoftware process model
Software process model
 
Lecture 02 Software Process Model
Lecture 02 Software Process ModelLecture 02 Software Process Model
Lecture 02 Software Process Model
 
Agile methodology
Agile methodologyAgile methodology
Agile methodology
 
Dss vs expert system
Dss vs expert systemDss vs expert system
Dss vs expert system
 
Vendor Evaluation by configuring Vendor Ratings and Vendor Scorecard:
Vendor Evaluation by configuring Vendor Ratings and Vendor Scorecard:Vendor Evaluation by configuring Vendor Ratings and Vendor Scorecard:
Vendor Evaluation by configuring Vendor Ratings and Vendor Scorecard:
 
Str8ts Weekly Extreme #45 - Solution
Str8ts Weekly Extreme #45 - SolutionStr8ts Weekly Extreme #45 - Solution
Str8ts Weekly Extreme #45 - Solution
 
МультиТендер - почему наша реклама действительно работает
МультиТендер - почему наша реклама действительно работаетМультиТендер - почему наша реклама действительно работает
МультиТендер - почему наша реклама действительно работает
 
Evaluation q1 presentation
Evaluation q1 presentationEvaluation q1 presentation
Evaluation q1 presentation
 
Question 1 - Conventions
Question 1 - ConventionsQuestion 1 - Conventions
Question 1 - Conventions
 
2 May 2012 1HBCT Weekly News Update
2 May 2012 1HBCT Weekly News Update2 May 2012 1HBCT Weekly News Update
2 May 2012 1HBCT Weekly News Update
 
Investing in South Africa - IAR Multicultural Summit
Investing in South Africa - IAR Multicultural SummitInvesting in South Africa - IAR Multicultural Summit
Investing in South Africa - IAR Multicultural Summit
 
Pedro García-Noblejas, en Forbes (octubre 2013)
Pedro García-Noblejas, en Forbes (octubre 2013)Pedro García-Noblejas, en Forbes (octubre 2013)
Pedro García-Noblejas, en Forbes (octubre 2013)
 
Survey
SurveySurvey
Survey
 
Malaysian Pestiside Board Registration Certicifate
Malaysian Pestiside Board Registration CerticifateMalaysian Pestiside Board Registration Certicifate
Malaysian Pestiside Board Registration Certicifate
 
Mis aparatos
Mis aparatos Mis aparatos
Mis aparatos
 

Similar to A lean model based outlook on cost & quality optimization in software projects

Pmbok 5th planning process group part three
Pmbok 5th planning process group part threePmbok 5th planning process group part three
Pmbok 5th planning process group part threeHossam Maghrabi
 
L07 quality management
L07 quality managementL07 quality management
L07 quality managementAsa Chan
 
Next Generation Testing
Next Generation TestingNext Generation Testing
Next Generation TestingBen Cook
 
Jurnal an example of using key performance indicators for software development
Jurnal   an example of using key performance indicators for software developmentJurnal   an example of using key performance indicators for software development
Jurnal an example of using key performance indicators for software developmentRatzman III
 
Quality management system process
Quality management system processQuality management system process
Quality management system processselinasimpson331
 
Quality management in projects
Quality management in projectsQuality management in projects
Quality management in projectsselinasimpson311
 
Improving the roi of software quality assurance activities
Improving the roi of software quality assurance activitiesImproving the roi of software quality assurance activities
Improving the roi of software quality assurance activitieskhush bakhat
 
Ch 7 integrating quality activities in the projectlife cycle
Ch 7 integrating quality activities in the projectlife cycleCh 7 integrating quality activities in the projectlife cycle
Ch 7 integrating quality activities in the projectlife cycleKittitouch Suteeca
 
Software Productivity Framework
Software Productivity Framework Software Productivity Framework
Software Productivity Framework Zinnov
 
Ipc india newsletter feb19_article_ms_seema sabikhi
Ipc india newsletter feb19_article_ms_seema sabikhiIpc india newsletter feb19_article_ms_seema sabikhi
Ipc india newsletter feb19_article_ms_seema sabikhiSuresh Kr. Rana
 
Presentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajanPresentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajanPMI_IREP_TP
 
Lightweight Processes: A Definition
Lightweight Processes: A DefinitionLightweight Processes: A Definition
Lightweight Processes: A DefinitionGlen Alleman
 
Applying Lean Sigma Into Validation
Applying Lean Sigma Into ValidationApplying Lean Sigma Into Validation
Applying Lean Sigma Into Validationtjcornish
 
Software Process Improvement.ppt
Software Process Improvement.pptSoftware Process Improvement.ppt
Software Process Improvement.pptNadarDinesh
 
Importance of software quality metrics
Importance of software quality metricsImportance of software quality metrics
Importance of software quality metricsPiyush Sohaney
 
Quality management procedures
Quality management proceduresQuality management procedures
Quality management proceduresselinasimpson1201
 

Similar to A lean model based outlook on cost & quality optimization in software projects (20)

Pmbok 5th planning process group part three
Pmbok 5th planning process group part threePmbok 5th planning process group part three
Pmbok 5th planning process group part three
 
L07 quality management
L07 quality managementL07 quality management
L07 quality management
 
Spc assignment
Spc assignmentSpc assignment
Spc assignment
 
Test performance indicators
Test performance indicatorsTest performance indicators
Test performance indicators
 
Next Generation Testing
Next Generation TestingNext Generation Testing
Next Generation Testing
 
Jurnal an example of using key performance indicators for software development
Jurnal   an example of using key performance indicators for software developmentJurnal   an example of using key performance indicators for software development
Jurnal an example of using key performance indicators for software development
 
Quality management system process
Quality management system processQuality management system process
Quality management system process
 
Quality management in projects
Quality management in projectsQuality management in projects
Quality management in projects
 
Project quality management
Project quality managementProject quality management
Project quality management
 
Improving the roi of software quality assurance activities
Improving the roi of software quality assurance activitiesImproving the roi of software quality assurance activities
Improving the roi of software quality assurance activities
 
Ch 7 integrating quality activities in the projectlife cycle
Ch 7 integrating quality activities in the projectlife cycleCh 7 integrating quality activities in the projectlife cycle
Ch 7 integrating quality activities in the projectlife cycle
 
Software Productivity Framework
Software Productivity Framework Software Productivity Framework
Software Productivity Framework
 
Ipc india newsletter feb19_article_ms_seema sabikhi
Ipc india newsletter feb19_article_ms_seema sabikhiIpc india newsletter feb19_article_ms_seema sabikhi
Ipc india newsletter feb19_article_ms_seema sabikhi
 
Presentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajanPresentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajan
 
Lightweight Processes: A Definition
Lightweight Processes: A DefinitionLightweight Processes: A Definition
Lightweight Processes: A Definition
 
Applying Lean Sigma Into Validation
Applying Lean Sigma Into ValidationApplying Lean Sigma Into Validation
Applying Lean Sigma Into Validation
 
Software Process Improvement.ppt
Software Process Improvement.pptSoftware Process Improvement.ppt
Software Process Improvement.ppt
 
Importance of software quality metrics
Importance of software quality metricsImportance of software quality metrics
Importance of software quality metrics
 
Quality management procedures
Quality management proceduresQuality management procedures
Quality management procedures
 
Quality - An Introduction-170715
Quality - An Introduction-170715Quality - An Introduction-170715
Quality - An Introduction-170715
 

More from Sonata Software

What makes a good travel reservation software.pptx
What makes a good travel reservation software.pptxWhat makes a good travel reservation software.pptx
What makes a good travel reservation software.pptxSonata Software
 
The future of travel and tourism post pandemic
The future of travel and tourism post pandemicThe future of travel and tourism post pandemic
The future of travel and tourism post pandemicSonata Software
 
Data & Analytics with CIS & Microsoft Platforms
Data & Analytics with CIS & Microsoft PlatformsData & Analytics with CIS & Microsoft Platforms
Data & Analytics with CIS & Microsoft PlatformsSonata Software
 
Leading Digital Business Change
Leading Digital Business ChangeLeading Digital Business Change
Leading Digital Business ChangeSonata Software
 
Microsoft Dynamics 365 - The Mordern Retail Platform
Microsoft Dynamics 365 - The Mordern Retail PlatformMicrosoft Dynamics 365 - The Mordern Retail Platform
Microsoft Dynamics 365 - The Mordern Retail PlatformSonata Software
 
Retail Digital Transformation
Retail Digital TransformationRetail Digital Transformation
Retail Digital TransformationSonata Software
 
Digital Ready Retailing with Brick & Click
Digital Ready Retailing with Brick & ClickDigital Ready Retailing with Brick & Click
Digital Ready Retailing with Brick & ClickSonata Software
 
Implementing the seamless customer journey
Implementing the seamless customer journeyImplementing the seamless customer journey
Implementing the seamless customer journeySonata Software
 
Sonata presentation to Advisors
Sonata presentation to Advisors Sonata presentation to Advisors
Sonata presentation to Advisors Sonata Software
 
Transportation management setup in AX 2012 R3
Transportation management setup in AX 2012 R3Transportation management setup in AX 2012 R3
Transportation management setup in AX 2012 R3Sonata Software
 
Data import export integration tool
Data import export integration toolData import export integration tool
Data import export integration toolSonata Software
 
Omni-channel retail : The new normal
Omni-channel retail : The new normalOmni-channel retail : The new normal
Omni-channel retail : The new normalSonata Software
 
The changing rules of customer engagement
The changing rules of customer engagementThe changing rules of customer engagement
The changing rules of customer engagementSonata Software
 
Implementation of Risk-Based Approach for Quality & Cost Optimization
Implementation of Risk-Based Approach for Quality & Cost OptimizationImplementation of Risk-Based Approach for Quality & Cost Optimization
Implementation of Risk-Based Approach for Quality & Cost OptimizationSonata Software
 
Website people-our-workplace
Website people-our-workplaceWebsite people-our-workplace
Website people-our-workplaceSonata Software
 
POV - Climate change solution for the airline industry
POV - Climate change solution for the airline industryPOV - Climate change solution for the airline industry
POV - Climate change solution for the airline industrySonata Software
 

More from Sonata Software (17)

What makes a good travel reservation software.pptx
What makes a good travel reservation software.pptxWhat makes a good travel reservation software.pptx
What makes a good travel reservation software.pptx
 
The future of travel and tourism post pandemic
The future of travel and tourism post pandemicThe future of travel and tourism post pandemic
The future of travel and tourism post pandemic
 
Data & Analytics with CIS & Microsoft Platforms
Data & Analytics with CIS & Microsoft PlatformsData & Analytics with CIS & Microsoft Platforms
Data & Analytics with CIS & Microsoft Platforms
 
Leading Digital Business Change
Leading Digital Business ChangeLeading Digital Business Change
Leading Digital Business Change
 
Microsoft Dynamics 365 - The Mordern Retail Platform
Microsoft Dynamics 365 - The Mordern Retail PlatformMicrosoft Dynamics 365 - The Mordern Retail Platform
Microsoft Dynamics 365 - The Mordern Retail Platform
 
Retail Digital Transformation
Retail Digital TransformationRetail Digital Transformation
Retail Digital Transformation
 
Digital Ready Retailing with Brick & Click
Digital Ready Retailing with Brick & ClickDigital Ready Retailing with Brick & Click
Digital Ready Retailing with Brick & Click
 
Implementing the seamless customer journey
Implementing the seamless customer journeyImplementing the seamless customer journey
Implementing the seamless customer journey
 
Sonata presentation to Advisors
Sonata presentation to Advisors Sonata presentation to Advisors
Sonata presentation to Advisors
 
Transportation management setup in AX 2012 R3
Transportation management setup in AX 2012 R3Transportation management setup in AX 2012 R3
Transportation management setup in AX 2012 R3
 
Data import export integration tool
Data import export integration toolData import export integration tool
Data import export integration tool
 
India Agile Week 2015
India Agile Week 2015India Agile Week 2015
India Agile Week 2015
 
Omni-channel retail : The new normal
Omni-channel retail : The new normalOmni-channel retail : The new normal
Omni-channel retail : The new normal
 
The changing rules of customer engagement
The changing rules of customer engagementThe changing rules of customer engagement
The changing rules of customer engagement
 
Implementation of Risk-Based Approach for Quality & Cost Optimization
Implementation of Risk-Based Approach for Quality & Cost OptimizationImplementation of Risk-Based Approach for Quality & Cost Optimization
Implementation of Risk-Based Approach for Quality & Cost Optimization
 
Website people-our-workplace
Website people-our-workplaceWebsite people-our-workplace
Website people-our-workplace
 
POV - Climate change solution for the airline industry
POV - Climate change solution for the airline industryPOV - Climate change solution for the airline industry
POV - Climate change solution for the airline industry
 

Recently uploaded

How to Track Employee Performance A Comprehensive Guide.pdf
How to Track Employee Performance A Comprehensive Guide.pdfHow to Track Employee Performance A Comprehensive Guide.pdf
How to Track Employee Performance A Comprehensive Guide.pdfLivetecs LLC
 
Maximizing Efficiency and Profitability with OnePlan’s Professional Service A...
Maximizing Efficiency and Profitability with OnePlan’s Professional Service A...Maximizing Efficiency and Profitability with OnePlan’s Professional Service A...
Maximizing Efficiency and Profitability with OnePlan’s Professional Service A...OnePlan Solutions
 
KnowAPIs-UnknownPerf-jaxMainz-2024 (1).pptx
KnowAPIs-UnknownPerf-jaxMainz-2024 (1).pptxKnowAPIs-UnknownPerf-jaxMainz-2024 (1).pptx
KnowAPIs-UnknownPerf-jaxMainz-2024 (1).pptxTier1 app
 
Buds n Tech IT Solutions: Top-Notch Web Services in Noida
Buds n Tech IT Solutions: Top-Notch Web Services in NoidaBuds n Tech IT Solutions: Top-Notch Web Services in Noida
Buds n Tech IT Solutions: Top-Notch Web Services in Noidabntitsolutionsrishis
 
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASE
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASEBATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASE
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASEOrtus Solutions, Corp
 
React Server Component in Next.js by Hanief Utama
React Server Component in Next.js by Hanief UtamaReact Server Component in Next.js by Hanief Utama
React Server Component in Next.js by Hanief UtamaHanief Utama
 
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed Data
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed DataAlluxio Monthly Webinar | Cloud-Native Model Training on Distributed Data
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed DataAlluxio, Inc.
 
SpotFlow: Tracking Method Calls and States at Runtime
SpotFlow: Tracking Method Calls and States at RuntimeSpotFlow: Tracking Method Calls and States at Runtime
SpotFlow: Tracking Method Calls and States at Runtimeandrehoraa
 
Recruitment Management Software Benefits (Infographic)
Recruitment Management Software Benefits (Infographic)Recruitment Management Software Benefits (Infographic)
Recruitment Management Software Benefits (Infographic)Hr365.us smith
 
Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...
Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...
Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...Matt Ray
 
Automate your Kamailio Test Calls - Kamailio World 2024
Automate your Kamailio Test Calls - Kamailio World 2024Automate your Kamailio Test Calls - Kamailio World 2024
Automate your Kamailio Test Calls - Kamailio World 2024Andreas Granig
 
英国UN学位证,北安普顿大学毕业证书1:1制作
英国UN学位证,北安普顿大学毕业证书1:1制作英国UN学位证,北安普顿大学毕业证书1:1制作
英国UN学位证,北安普顿大学毕业证书1:1制作qr0udbr0
 
What is Fashion PLM and Why Do You Need It
What is Fashion PLM and Why Do You Need ItWhat is Fashion PLM and Why Do You Need It
What is Fashion PLM and Why Do You Need ItWave PLM
 
Folding Cheat Sheet #4 - fourth in a series
Folding Cheat Sheet #4 - fourth in a seriesFolding Cheat Sheet #4 - fourth in a series
Folding Cheat Sheet #4 - fourth in a seriesPhilip Schwarz
 
Cloud Data Center Network Construction - IEEE
Cloud Data Center Network Construction - IEEECloud Data Center Network Construction - IEEE
Cloud Data Center Network Construction - IEEEVICTOR MAESTRE RAMIREZ
 
Balasore Best It Company|| Top 10 IT Company || Balasore Software company Odisha
Balasore Best It Company|| Top 10 IT Company || Balasore Software company OdishaBalasore Best It Company|| Top 10 IT Company || Balasore Software company Odisha
Balasore Best It Company|| Top 10 IT Company || Balasore Software company Odishasmiwainfosol
 
Software Project Health Check: Best Practices and Techniques for Your Product...
Software Project Health Check: Best Practices and Techniques for Your Product...Software Project Health Check: Best Practices and Techniques for Your Product...
Software Project Health Check: Best Practices and Techniques for Your Product...Velvetech LLC
 
What is Advanced Excel and what are some best practices for designing and cre...
What is Advanced Excel and what are some best practices for designing and cre...What is Advanced Excel and what are some best practices for designing and cre...
What is Advanced Excel and what are some best practices for designing and cre...Technogeeks
 

Recently uploaded (20)

How to Track Employee Performance A Comprehensive Guide.pdf
How to Track Employee Performance A Comprehensive Guide.pdfHow to Track Employee Performance A Comprehensive Guide.pdf
How to Track Employee Performance A Comprehensive Guide.pdf
 
Maximizing Efficiency and Profitability with OnePlan’s Professional Service A...
Maximizing Efficiency and Profitability with OnePlan’s Professional Service A...Maximizing Efficiency and Profitability with OnePlan’s Professional Service A...
Maximizing Efficiency and Profitability with OnePlan’s Professional Service A...
 
KnowAPIs-UnknownPerf-jaxMainz-2024 (1).pptx
KnowAPIs-UnknownPerf-jaxMainz-2024 (1).pptxKnowAPIs-UnknownPerf-jaxMainz-2024 (1).pptx
KnowAPIs-UnknownPerf-jaxMainz-2024 (1).pptx
 
Buds n Tech IT Solutions: Top-Notch Web Services in Noida
Buds n Tech IT Solutions: Top-Notch Web Services in NoidaBuds n Tech IT Solutions: Top-Notch Web Services in Noida
Buds n Tech IT Solutions: Top-Notch Web Services in Noida
 
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASE
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASEBATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASE
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASE
 
React Server Component in Next.js by Hanief Utama
React Server Component in Next.js by Hanief UtamaReact Server Component in Next.js by Hanief Utama
React Server Component in Next.js by Hanief Utama
 
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed Data
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed DataAlluxio Monthly Webinar | Cloud-Native Model Training on Distributed Data
Alluxio Monthly Webinar | Cloud-Native Model Training on Distributed Data
 
2.pdf Ejercicios de programación competitiva
2.pdf Ejercicios de programación competitiva2.pdf Ejercicios de programación competitiva
2.pdf Ejercicios de programación competitiva
 
SpotFlow: Tracking Method Calls and States at Runtime
SpotFlow: Tracking Method Calls and States at RuntimeSpotFlow: Tracking Method Calls and States at Runtime
SpotFlow: Tracking Method Calls and States at Runtime
 
Recruitment Management Software Benefits (Infographic)
Recruitment Management Software Benefits (Infographic)Recruitment Management Software Benefits (Infographic)
Recruitment Management Software Benefits (Infographic)
 
Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...
Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...
Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...
 
Automate your Kamailio Test Calls - Kamailio World 2024
Automate your Kamailio Test Calls - Kamailio World 2024Automate your Kamailio Test Calls - Kamailio World 2024
Automate your Kamailio Test Calls - Kamailio World 2024
 
英国UN学位证,北安普顿大学毕业证书1:1制作
英国UN学位证,北安普顿大学毕业证书1:1制作英国UN学位证,北安普顿大学毕业证书1:1制作
英国UN学位证,北安普顿大学毕业证书1:1制作
 
What is Fashion PLM and Why Do You Need It
What is Fashion PLM and Why Do You Need ItWhat is Fashion PLM and Why Do You Need It
What is Fashion PLM and Why Do You Need It
 
Hot Sexy call girls in Patel Nagar🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Patel Nagar🔝 9953056974 🔝 escort ServiceHot Sexy call girls in Patel Nagar🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Patel Nagar🔝 9953056974 🔝 escort Service
 
Folding Cheat Sheet #4 - fourth in a series
Folding Cheat Sheet #4 - fourth in a seriesFolding Cheat Sheet #4 - fourth in a series
Folding Cheat Sheet #4 - fourth in a series
 
Cloud Data Center Network Construction - IEEE
Cloud Data Center Network Construction - IEEECloud Data Center Network Construction - IEEE
Cloud Data Center Network Construction - IEEE
 
Balasore Best It Company|| Top 10 IT Company || Balasore Software company Odisha
Balasore Best It Company|| Top 10 IT Company || Balasore Software company OdishaBalasore Best It Company|| Top 10 IT Company || Balasore Software company Odisha
Balasore Best It Company|| Top 10 IT Company || Balasore Software company Odisha
 
Software Project Health Check: Best Practices and Techniques for Your Product...
Software Project Health Check: Best Practices and Techniques for Your Product...Software Project Health Check: Best Practices and Techniques for Your Product...
Software Project Health Check: Best Practices and Techniques for Your Product...
 
What is Advanced Excel and what are some best practices for designing and cre...
What is Advanced Excel and what are some best practices for designing and cre...What is Advanced Excel and what are some best practices for designing and cre...
What is Advanced Excel and what are some best practices for designing and cre...
 

A lean model based outlook on cost & quality optimization in software projects

  • 1. A Lean Model Based Outlook on Cost and Quality Optimization in Software Projects STC 2009 Kalyanam Kannan
  • 2. www.sonata-software.com Page No. 2 Abstract A large quantum of effort and research is being invested to address the Cost and Quality factors in software projects. Though the solutions, models and methodologies are well established through experimented processes, adoption and optimization of the required parameters for a specific project to obtain predictable and acceptable quality with minimum costs has always remained a challenge. This paper discusses the Lean process in detail with the help of project data and demonstrates that simple, affordable and adoptable processes are more economical and focused on quality. Also, it is observed that the Lean Model enables a project to be well monitored and controlled by focusing on critical elements, thereby reducing overheads of bulky documentation and irrelevant processes. The above findings are statistically analyzed using the coefficient of variation, which strikes a direct correlation with the predictable quality in a project.
  • 3. Page No. 3 Lean Model – An Overview The quality and cost of software are two important areas under constant vigil during the process of software development and delivery. The quality of software bears a direct correlation with the thought process and steps followed to achieve the expected output. The costs involved in executing a streamlined work process and repeatable steps for software development are considered to be significant overheads in the industry. Several teams and groups have been continuously working on a model to achieve high quality with minimum investments of effort and costs. The Lean process takes a simple approach to address this business challenge by eliminating unwanted steps in a project or product development, which translates into ample and required benefits, to remove overheads. A Lean Model focuses on eliminating activities that do not add any value to the project and fatty processes in a lifecycle. The model also offers multiple advantages by allocating more time and effort for product critical areas and thus minimizing effort for a particular process activity, which would normally be less significant for the entire application. In other words, elimination of wasteful activities from the quality control processes in a lifecycle helps tailor a process, which is more efficient and can be easily adhered to. The Lean Model implementation is a combined change in the strategic and operational processes. (Not too sure about controls)There are several tools and working models that need to be altered and optimized to remove or minimize wasteful activities to attain efficiency and optimization. The generic Lean principles of software development are well established and the same is presented below for reference: 1. Eliminate waste: Eliminate any process activity that is not adding value to the project delivery 2. Amplify learning: A sustainable model to manage knowledge and repeatable process to replicate the knowledge sharing across the projects. (Tools: Feedback, iterations, synchronization and set-based development) 3. Decide as late as possible: Decision to incorporate the required processes for effective delivery so that the cost and effort involved for change canbe avoided. Tools: Options thinking, the last responsible moment and decision-making. 4. Deliver as fast as possible: Faster delivery resulting in optimized cost and better productivity. Tools: Pull systems, Queuing Theory and cost of delay.
  • 4. Page No. 4 5. Empower the team: Encourage people to take responsibility, get motivated and work as a team, and responsibility for the outcome and authority to make it happen. Tools: Self-determination, motivation, leadership and expertise. 6. Build integrity: Customer’s experience with the delivery, whereas conceptual integrity is how well the architecture and system components work together to bring about the perceived integrity. Obviously, testing-unit and integration testing, is a major part of integrity. Tools: Perceived integrity, conceptual integrity, refactoring and testing. 7. See the whole: Holiostic and end-to-end approach for projects so the end point implementation and business value is thought through during the initial stage of the project and risks identified and mitigated. 8. Tools: Measurement and contracts. This White Paper extensively follows Lean principles in the areas of quality control and quality management by eliminating unwanted processes, and improving team integration and integrity. It also discusses the outcomes of the observations in detail. An attempt has been made to analyze data from various projects and the effort expended in each of the processes and operational activities. The percentage effort from these activities is mapped to the Lean Model of working and the reduction in effort in the respective activity areas is predicted. The quality of the deliverables is measured using defect detection efficiency and coefficient of variation, which is a measure of risk. Finally, the said parameters and observations are compared between the Lean and Normal Models. Sample Study – Data Analysis and Prediction The aforementioned Lean Model was applied to a sample of projects from Travel domain, which consisted of Web applications, BI systems, data warehouses, staging area database and mainframe systems. The finite data on effort spent on each of the project activities, listed below for quality control, were obtained from ABTS (Activity- Based Tracking System) and the release data, such as coverage, test cases, defect leakage, were obtained from the test and project management tools. The sample data from the above mentioned projects were studied in detail by breaking them into Planning, Analysis, Development and Testing phases, as done in any other development model, and all standard processes were monitored throughout this study. The activity parameters given below were incorporated into the Lean Model and redistribution of the probable effort was carried out with the help of coefficient of variation for the mentioned activities. In all these cases, the risk parameter was maintained at less than 3% for projected Lean activity percentages. The results of the Lean Model were compared with those of the Standard Process Model. The results
  • 5. Page No. 5 found were encouraging and highlighted a substantial amount of efficiency, thereby reducing and eliminating processes and activities that did not value add. The sample consisted of application development projects of the Travel domain. The activities studied, using the Standard Process Model, are given below. The parameters related to quality control are also discussed in this section with their appropriate weightings in percentages. Table 1: Effort Distribution on Process Activity Parameters ________________________________________________________ Phase Activity Parameters % Effort ________________________________________________________ Analysis Requirement Analysis 5 Requirement Clarifications 5 Technology Feasibility Analysis 3 Quality Strategy 5 Effort Estimation 4 Design Test Strategy 3 High Level Test Scenarios 3 Test Reviews 5 RTM 5 Development Test Plan Development 5 Test Case Development 18 Test Review 5 Design-Test Case Updation 5 Testing Test Execution 15 Defect Logging 5 Defect Analysis 2 Test Documentation 5 Test Signoff 2 __________________________________________________________ The table above provides effort distribution across various activities to achieve a controlled and monitored quality process for predictable software releases. The data in the table and the proportion of efforts are correlated with the quality of projects, which is measured using defect detection efficiency as one of the key parameters, while quality index was measured using Test Maturity Model-based indices. The available reports based on data and overall risk, derived from quality index, are represented in the graphs below:
  • 6. Page No. 6 Figure 1 : Quality Index, DDE and Risk Trend (Normal Model) Figure 2 : Quality Index, DDE and Risk Trend (Lean Model) Figure 3 : Quality Index Comparision for Normal and Lean Samples The graphs above provide details of the sample projects in terms of Quality Index (QI), Defect Detection Efficiency (DDE) and Coefficient of Variation (CoV). Figure 1 provides details of those trends in the projects, which followed standard processes based on the Capability Maturity Model (CMM) and it is observed that the average quality index, DDE and CoV were around 7, 85% and 30 respectively. Figure 2 provides simulated data for Lean Model and it is observed that the average quality index, DDE and CoV were around 8, 90% and 25, in that order. The improvement in quality from an overall perspective is discussed in detail in the sections below. The aforesaid sample projects were fitted into the framework of Lean Development Model, in which the non-value add processes were minimized by using efficient tools and thinner documentation processes. The proven seven stages of the Lean Model were applied in each and every stage, and the benefits were compounded in each of these areas and the overall efficiency was observed. The overall Lean Process implementation was provided in a tabular format. 0 1 2 3 4 5 6 7 8 9 0 20 40 60 80 100 120 sample 1 sample 2 sample 3 sample 4 sample 5 sample 6 sample 7 sample 8 sample 9 sample 10 COV DDE QI 0 1 2 3 4 5 6 7 8 9 0 20 40 60 80 100 120 sample 1 sample 2 sample 3 sample 4 sample 5 sample 6 sample 7 sample 8 sample 9 sample 10 COV DDE QI 0 1 2 3 4 5 6 7 8 9 sample 1 sample 2 sample 3 sample 4 sample 5 sample 6 sample 7 sample 8 sample 9 sample 10 QI(NPM) QI (LPM)
  • 7. Page No. 7 The reduction in effort due to usage of the Lean Model was based on iterations, where the CoV (risk) did not exceed a value of 30. Also, it should be noted that the below mentioned effort distribution is prone to change if the absolute value of CoV is altered. In general, higher the risk coefficient, more is the effort reduction using the Lean Model. This also provides a wide range of scope for Risk-Based Testing (RBT) and is a promising area for further analysis and research. Figure 3 depicts the difference between the Normal Process-based approach and Lean Process-based approach for quality index values. Although both the models use the same set of activities towards delivery, the percentage and amount of focus provided for each of the activity is better managed in the Lean Process, which is likely to yield better quality behavior as displayed above. Lean Model Analysis and Discussions It is observed by means of this hypothesis that around 29% of effort in quality control can be saved and utilized for various other purposes. The Lean Model gains importance because the effort saved can be used in the areas of coverage and reviews, which enhance the quality and predictability of software. The reduction in effort has direct impact on cost savings, and the processes can be fine-tuned to achieve cost and effort optimization. The findings on quality of the projects taken as sample provide the following indicators and help us identify the areas of importance to achieve quality and cost reduction. Table 2: Percentage effort distribution in normal and lean process models % Effort Distributi on Estim ate Waste Effecti ve learni ng Decide Late Delive r Fast Empo wer Team Integrity Holistic View Lean Distribu tion Requirement Analysis 5 5 5 3 3 4 3 2 6.0 Requirement Clarifications 5 1 3 5 5 2 2 2 2.9 Technology Feasibility Analysis 3 2 2 3 3 3 3 3 3.0 Quality Strategy 5 3 3 5 4 3 3 3 4.0 Effort Estimation 4 1 3 1 5 3 3 5 3.0 Test Strategy 3 3 1 3 3 3 3 3 2.7 High Level Test Scenarios 3 3 2 2 3 3 3 3 3.0 Test Reviews 5 2 2 3 5 3 5 5 2.1 RTM 5 1 5 3 5 5 5 5 4.1 Test Plan Development 5 5 3 5 5 5 5 2 4.3 Test Case Development 18 20 15 20 20 20 20 10 14.3 Test Review 5 1 2 5 5 5 5 2 3.6 Design-Test Case Up gradation 5 1 1 1 1 1 1 1 1.0 Test execution 15 15 15 10 15 15 15 10 10.6
  • 8. Page No. 8 % Effort Distributi on Estim ate Waste Effecti ve learni ng Decide Late Delive r Fast Empo wer Team Integrity Holistic View Lean Distribu tion Defect Logging 5 2 2 2 2 2 2 2 2.0 Defect Analysis 2 2 2 2 2 2 2 2 1.0 Test Documentation 5 1 1 1 1 1 1 1 1.0 Test Signoff 2 2 2 2 2 2 2 2 2.0 Overall View 100 70.6 Figure 4: Percentage effort distribution in normal and lean process models The figure above provides an insight into effort distribution in a Quality Control Model. It is obvious from the graph that the critical steps or processes were accorded more importance and weightings as compared to the Standard Model. This helps address the issues of quality and cost in an effective manner. A greater amount of effort for requirement analysis, quality strategy and effort estimation considerably decreased the test case development and test execution efforts. A holistic approach and understanding business criticality of the application or project under development resulted in decreased effort during the testing phase and minimized the wastages on clarifications. Elimination of Waste Elimination of waste in the sample projects discussed above was based on the following: 0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 20% Requirement Analysis Requirement Clarifications Technology FeasibilityAnalysis Quality Strategy Effort Estimation TestStrategy HighLevel TestScenarios TestReviews RTM TestPlan Development TestCase Development TestReview Design-Test CaseUpdation Testexecution DefectLogging DefectAnalysis TestDocumentation TestSignoff Effort Distribution Lean Distribution
  • 9. Page No. 9  Development of a software / code and a test case, which were waiting to be tested or integrated  Incapability to test the code due to non-availability of any other components  Development of irrelevant test cases, which were not to be used immediately  Wait for clarifications and defect details  Excess documentation or effort duplication in terms of reporting In other words, as per Lean thinking, anything not adding any value to the project was considered to be waste. This included:  unnecessary test cases and excessive unwanted coverage  Unclear requirements and unnecessary documentation  Complex communication procedures and non-agreed upon engagement models In order to be able to eliminate waste, one should be able to recognize it. For example:  If some activity could be bypassed or the result could be achieved without it, it is waste.  Any quality control activity that is not completed and needs to be repeated is also a waste.  Extra processes and features not often used by project teams are waste.  Waiting for other activities and teams for integration of code and related processes is also considered as waste.  Defects of lower quality are waste. Managerial overheads not generating real value are waste. In the sample projects, a value stream mapping was carried out and waste was minimized, as reflected in Table 2. Most of the waste was eliminated during phases of requirements understanding and requirement mapping to the test cases, ultimately saving more effort for test development and execution. A better understanding of the overall project and realistic effort estimates also proved helpful in elimination of wastages from the project. As per an analysis, reduction of 30% waste -- in terms of effort due to requirement understanding, proper effort estimation and overall business understanding of the project -- helped trim the process activity efforts. The quality of the deliverables, measured in terms of defect leakage and risk (CoV), also showed satisfactory quality levels.
  • 10. Page No. 10 Amplify learning – Feedback mechanism The best approach to improve quality and amplify learning within the teams is to get timely feedback from the testing and quality teams. Most of the defects should be prevented by running tests as soon as the code is written and delivered. Instead of adding more documentation or making detailed plans, different ideas should be experimented with by writing code. The process of user requirements gathering should also be simplified by presenting screens to the end-users and asking them for inputs through a simple, workable process. This specific Lean activity plays a major role in Lean quality control. The high-impact area or the major beneficiary of this activity is the development team. A considerable amount of effort can be saved by getting feedback from the testing team immediately after the software release. More the knowledge of the testing and quality teams, higher are the benefits of integration and business-based acceptance of the software with minimum defects. The sample study predicted that improving the business knowledge of the testing and quality teams benefited the project by:  Providing faster feedback to the development teams  Providing end-to-end test scenarios for integration of code  Reducing the effort in the development of unwanted test conditions for a specific release  Reducing the time delay in release process during production The simulations based on the above-mentioned benefits predicted a 15% reduction in cycle time due to integrated and appropriate learning and sharing mechanisms. This also involved setting up a centralized knowledge management system and planned meetings during the project period. The findings were in line with the definition of learning given below: “The learning process is sped up by usage of short iteration cycles – each one coupled with refactoring and integration testing. Increasing feedback via short feedback sessions with customers helps when determining the current phase of development and adjusting efforts for future improvements. During those short sessions, both customer representatives and the development team learn more about the domain problem and figure out possible solutions for further development. Thus, the customers better understand their needs, based on the existing results of development efforts, and the developers learn how to better satisfy those needs. Another idea in the communication and learning process with a customer is set-based development – this concentrates on communicating the constraints of the future solution and not the possible solutions, thus, promoting the birth of the solution via dialog with the customer.”
  • 11. Page No. 11 Decide as late as possible – Minimize assumptions and predictions There are several aspects to be taken care of in a complex software development environment. The approach of deciding the change as late as possible, will help reduce assumptions and predictions during the course of the project and get real requirements and clarifications based on a simple and effective process. This prevents A lot of rework in the later stages. The iterative approach promotes a simple principle – the ability to adapt to changes and correct mistakes -- which might be very costly if discovered after the release of the software. In a nutshell, this approach prescribes efforts only on a complete and clear understanding of requirements, and advises against investment of any efforts in assumptions and predictions, which may need re-work (end up in re-work?????) during the final stages of the project. The sample study and simulated data concluded that around 10% of excess effort was being wasted due to commencement of project activities without a clear understanding of the requirements. The same is also reiterated in the Agile Development Model Deliver as fast as possible – Decrease iteration time The sample projects developed using Agile Development Model responded well to the dynamic customer needs and demands in a shorter period of time. Caution should be exercised in communicating and following integrated team approach during development and testing, so there are no discrepancies between the perceived product / project and the actual product / project developed. Business requirements have become more dynamic due to compelling needs of the industry, and therefore, the processes and methodologies should be adaptable, flexible and effective, to facilitate faster delivery. The Lean Model exactly falls in line with the business needs and helps the customers decide what they really need. Empower the team – Decisive team and proper engagement Team engagement and working agreement between business owners, development teams and quality teams play a very critical role in the success and quality of delivery. It is important to agree on a simple process, through which requirements and changes will be communicated and clarifications will be addressed. The decisiveness of the identified members of the team adds value and proves to be the central success factor for the Lean Model. Defect management and acceptance of the project heavily depends on the engagement model as it influences the cycle time and creates a chain effect throughout the lifecycle. The sample project data revealed the delay and ambiguity during development, testing and acceptance due to lack of decisions at various stages, which resulted in a
  • 12. Page No. 12 cumulative effect leading to delay and shortening of testing cycles. This resulted in lesser test coverage and delays in delivery. Building integrity – Deliver business value Integrity of software is rated on the basis of various factors like flexibility, maintainability, efficiency and responsiveness. This is normally achieved through face to face discussions and finally delivers a project full of potential that yields the expected outcome and addresses the business requirements with minimum possible efforts. The process of building integrity also proves that understanding of business requirements is critical to test a project or product for its long-term usability and its ability to cater to the changing market needs. See the whole – Holistic approach Software quality should not be restricted to testing; it should also cover and encompass the entire software development lifecycle. It is interesting to note that all activities in the lifecycle are interdependent. A holistic approach to the entire development model, with minimum processes and small repeatable activities, is the key differentiator of the Lean Model. The sample study demonstrated that there was a considerable reduction in effort, with faster releases, when quality was controlled through a managed model, brought about by interaction among various project stakeholders. This established the effectiveness of various small processes -- like stand-up meetings, status updates, triage priorities, daily feedback mechanism, etc. -- in a day-to-day working environment. Conclusion The sample projects provided some vital data, which evidenced that efficiency could be enhanced and processes could be improved by using the Lean Model:  The cost to quality and subsequently, the effort is likely to be reduced by 30% by using the Lean Model. Focusing on vital tasks like requirement understanding and making strategies also leads to effort reduction in the test case development and execution phases.  The predicted reduction in effort and increase in productivity is attributed to elimination of wastes like waiting period for clarifications, and planning the test cases and activities in the right sequence, so testing was not affected due to non-availability of integration and systems. At the time of writing this paper, the team was working at around 80-85% productivity and going Lean was expected to enhance this to around 95%.  It is expected that the cycle time will be reduced by 30% owing to effective feedback from testing, automated build and deployment practices. The Lean Model seems to be the future of software quality control as it falls in line with the industry slogan “Enhanced Quality and Reduced Cost.” Optimization of this model and its customization for specific projects would lead to benefits as it recommends execution of only those activities that bring value add to the project and thereby, provide more time for and focus more on the critical success factors in a project.
  • 13. Page No. 13 It is also very vital to note that suitable and capable resources are a pre-condition to adopt the Lean Model for a project. References: 1. Mary Poppendieck, Tom Poppendieck Lean Software Development: An Agile Toolkit for Software Development Managers 2. Lean Software Institute - Testing in Lean Software Development 3. Jeffrey k. Liker , The Toyota Way: 14 Management Principles from the World's Greatest Manufacturer