Innovate UK Project: 21506
ISCF Transforming Construction
Increase productivity, performance and quality in UK construction
in collaboration with Anglia Ruskin University
assisted by
2. Copyright TR Control Solutions Ltd 2019
Background
ISCF Transforming Construction objectives:
• deliver new built assets 50% faster and 33% cheaper
• halve the lifetime carbon emissions
• improve whole-life performance
We have:
• Pulse, an application used for commissioning large, industrial projects
• Extensive experience in manufacturing industry
• eco|Driver, an application for reducing the carbon emissions of buildings
• A record of innovation & a desire to do things better
Hence our Innovate UK application
Specifically by:
• Designing and managing buildings through digitally-enabled performance management
• Constructing quality buildings using a manufacturing approach
• Powering buildings with active energy components and improving build quality
3. Copyright TR Control Solutions Ltd 2019
Justification
According to GIRI (getitright.uk.com/):
…..estimates of total costs of error ranging between 10% and 25% of project cost or
between £10–25Bn per annum across the sector
GIRI research found that the most frequently reported root causes of error were:
Management and Planning (including inadequate supervision)
Communications (including a reluctance to ask questions)
Taking our cue from manufacturing industry, where efforts are focused on prevention
rather than detection, and combining it with the above, our project is focused on the
prevention of errors by improving understanding of the tasks to be performed
4. Copyright TR Control Solutions Ltd 2019
Innovate UK Project (21506), Jan – Dec 2019, £248k
Feasibility study: Adaptive Learning for Zero Defects in Buildings Construction
in conjunction with Anglian Ruskin University
5. Copyright TR Control Solutions Ltd 2019
BIM model
Drawings, specs & work
instructions
Interpretation &
Understanding
Contractor
Errors?
Errors?
Construction process - now
6. Copyright TR Control Solutions Ltd 2019
Errors?
Errors?
Construction process - proposed
Adaptive Learning
Application
Questions to test
understanding with
answers to clarify
7. Copyright TR Control Solutions Ltd 2019
Memory Time
Forgetting Curve
Reinforcing training is important because…
8. Copyright TR Control Solutions Ltd 2019
Checking understanding is important because assumptions can result in error
Well this is how we usually do it!
9. Copyright TR Control Solutions Ltd 2019
12-month feasibility project
We are here
Prototype Ideas
We are engaged with several construction companies
Would you also like to be involved?