SlideShare a Scribd company logo
1 of 3
Download to read offline
  1	
  
A	
  SOLUTION	
  TO	
  THE	
  LRET	
  IMPASSE	
  THAT	
  DELIVERS	
  A	
  REDUCED	
  WIND	
  FARM	
  BUILD	
  TO	
  THE	
  
GOVERNMENT	
  BUT	
  PROVIDES	
  STABLE	
  GROWTH	
  THAT	
  THE	
  WIND	
  INDUSTRY	
  CRAVES	
  
By	
  Simon	
  Mathis,	
  MBA,	
  MA	
  (Cantab)	
  
	
  
Executive	
  Summary	
  
	
  
Concerns	
   have	
   been	
   expressed	
   by	
   the	
   Government	
   (and	
   worked	
   over	
   by	
   the	
   Warburton	
  
Review)	
  that	
  lower	
  than	
  expected	
  electricity	
  demand	
  in	
  2020	
  will	
  see	
  renewables,	
  supported	
  
by	
  the	
  RET,	
  take	
  an	
  unacceptable	
  amount	
  of	
  supply	
  from	
  existing	
  non-­‐renewable	
  generators.	
  
With	
  the	
  recommendations	
  of	
  the	
  Warburton	
  review	
  largely	
  discredited	
  the	
  potential	
  has	
  
risen	
  for	
  a	
  middle	
  ground	
  solution	
  to	
  be	
  adopted	
  that	
  can	
  satisfy	
  the	
  needs	
  (not	
  demands)	
  of	
  
most	
  stakeholders.	
  By	
  delaying	
  the	
  delivery	
  of	
  the	
  fixed	
  target	
  of	
  41GWh	
  to	
  2023	
  with	
  an	
  
associated	
  limited	
  extension	
  of	
  the	
  scheme	
  to	
  2035	
  it	
  is	
  possible	
  to	
  continue	
  to	
  support	
  the	
  
growth	
  of	
  the	
  large-­‐scale	
  renewable	
  industry	
  in	
  Australia	
  at	
  an	
  acceptable	
  overall	
  cost.	
  
	
  
Some	
   basic	
   context/facts	
   about	
   the	
   workings	
   of	
   the	
   large-­‐scale	
   renewable	
   energy	
   target	
  
(“LRET”)	
  and	
  certificate	
  market.	
  
	
  
a) When	
  the	
  target	
  was	
  expanded	
  from	
  9.5TWh	
  to	
  45TWh	
  in	
  2009/2010	
  the	
  scheme	
  was	
  
also	
  extended	
  from	
  2020	
  to	
  2030	
  providing	
  a	
  wind-­‐fall	
  gain	
  for	
  those	
  existing	
  accredited	
  
generators	
   with	
   long	
   operating	
   lives	
   able	
   to	
   create	
   up	
   to	
   another	
   10	
   years	
   of	
  
REC’s/LGC’s.	
  (Note	
  wind	
  turbine	
  generators	
  have	
  a	
  typical	
  useful	
  life	
  of	
  only	
  20	
  to	
  25	
  
years).	
   I	
   raise	
   this	
   point	
   because	
   any	
   changes	
   to	
   the	
   LRET	
   will	
   have	
   effects	
   on	
   both	
  
existing	
  and	
  proposed	
  generators	
  but	
  some	
  of	
  those	
  generators	
  will	
  be	
  looking	
  to	
  secure	
  
support	
  that	
  wasn’t	
  in	
  existence	
  when	
  investment	
  decisions	
  were	
  originally	
  made.	
  
b) My	
  forecast	
  of	
  the	
  surplus	
  of	
  Large	
  Generation	
  Certificates	
  (“LGC’s”)	
  post	
  surrender	
  in	
  
2014	
  for	
  compliance	
  and	
  green-­‐power	
  is	
  ~24.9	
  million.	
  Without	
  any	
  further	
  build	
  beyond	
  
what	
  is	
  already	
  in	
  the	
  construction	
  pipeline	
  this	
  surplus	
  will	
  not	
  be	
  used	
  up	
  even	
  under	
  
the	
  current	
  targets	
  until	
  sometime	
  in	
  2018.	
  
c) The	
  surplus	
  acts	
  to	
  defer	
  commitment	
  to	
  new	
  renewable	
  generation.	
  The	
  fixed	
  end	
  date	
  
(2030)	
  of	
  the	
  LRET	
  means	
  that	
  the	
  later	
  the	
  date	
  a	
  renewable	
  generator	
  starts	
  operating	
  
the	
  fewer	
  LGC’s	
  it	
  can	
  create	
  and	
  therefore	
  (all	
  other	
  factors	
  being	
  equal)	
  the	
  higher	
  the	
  
price	
  per	
  LGC	
  it	
  must	
  earn.	
  If	
  wind	
  energy	
  is	
  the	
  LGC	
  price	
  barometer	
  then	
  any	
  generator	
  
starting	
   operations	
   from	
   2021	
   would	
   require	
   an	
   LGC	
   price	
   in	
   excess	
   of	
   the	
   $65	
   /LGC	
  
penalty	
  price.	
  
d) The	
   current	
   LRET	
   requires	
   an	
   additional	
   ~2,250	
   MW	
   of	
   wind	
   or	
   the	
   equivalent	
   to	
   be	
  
operating	
  by	
  2018,	
  ~4,100	
  MW	
  to	
  be	
  operating	
  by	
  2019	
  and	
  ~2,250	
  MW	
  to	
  be	
  operating	
  
by	
  2020.	
  When	
  compared	
  with	
  the	
  total	
  installed	
  base	
  of	
  wind	
  farms	
  of	
  3,610	
  MW	
  plus	
  
556	
  MW	
  under	
  construction	
  this	
  is	
  a	
  tall	
  order	
  for	
  an	
  industry	
  currently	
  in	
  the	
  doldrums	
  
of	
  regulatory	
  uncertainty	
  and	
  if	
  delivered	
  will	
  almost	
  certainly	
  involve	
  inefficiencies	
  and	
  
added	
   costs.	
   The	
   pinch	
   point	
   is	
   not	
   in	
   the	
   development	
   phases	
   of	
   site	
   identification,	
  
community,	
  environment	
  and	
  planning	
  approvals	
  but	
  in	
  delivery.	
  The	
  wind	
  industry	
  will	
  
argue	
   against	
   delays	
   due	
   to	
   fears	
   of	
   the	
   coming	
   of	
   large-­‐scale	
   solar	
   price	
  
competitiveness	
  and	
  a	
  loss	
  of	
  share	
  of	
  the	
  LRET	
  by	
  wind.	
  
e) The	
  recommendations	
  of	
  the	
  Warburton	
  review	
  are	
  flawed	
  not	
  just	
  because	
  they	
  kill	
  all	
  
future	
  large-­‐scale	
  renewable	
  energy	
  development	
  but	
  also	
  because	
  they	
  fail	
  to	
  deal	
  at	
  all	
  
with	
   the	
   LGC	
   surplus	
   meaning	
   the	
   price	
   of	
   LGC’s	
   could	
   fall	
   to	
   zero	
   necessitating	
  
compensation/market	
  support.	
  
	
  
  2	
  
Core	
  characteristics	
  of	
  a	
  middle	
  ground	
  solution	
  
	
  
What	
  could	
  a	
  middle	
  ground	
  (addresses	
  conservative	
  concerns	
  that	
  too	
  much	
  generation	
  is	
  
being	
   forced	
   into	
   the	
   market	
   to	
   the	
   detriment	
   of	
   existing	
   non-­‐renewable	
   generators	
   but	
  
supports	
  the	
  continued	
  growth	
  of	
  the	
  renewable	
  energy	
  industry)	
  solution	
  look	
  like?	
  
	
  
i) Fixed	
  targets	
  until	
  at	
  least	
  the	
  LGC	
  surplus	
  is	
  used	
  up	
  (without	
  the	
  absolute	
  certainty	
  
of	
  the	
  requirement	
  for	
  new	
  renewable	
  generation	
  build	
  the	
  price	
  of	
  LGC’s	
  cannot	
  
recover	
  to	
  supportive	
  levels).	
  
ii) Targets	
  that	
  support	
  a	
  sensible	
  new	
  build	
  program	
  of	
  1,000	
  to	
  1,500	
  MW	
  of	
  wind	
  or	
  
equivalent	
   per	
   annum.	
   Such	
   a	
   new	
   build	
   program	
   will	
   be	
   sufficient	
   to	
   attract	
  
efficiencies	
  across	
  the	
  project	
  life-­‐cycle	
  meaning	
  delivery	
  at	
  least	
  cost.	
  
iii) A	
   scheme	
   that	
   rewards	
   new	
   projects	
   with	
   LGC’s	
   for	
   a	
   minimum	
   of	
   15	
   years	
   and	
  
preferably	
  20	
  years	
  to	
  ensure	
  acceptable	
  LGC	
  prices.	
  
iv) A	
  scheme	
  that	
  avoids	
  the	
  costs	
  associated	
  with	
  extending	
  support	
  beyond	
  2030	
  to	
  
existing	
  renewable	
  generators.	
  
	
  
Solution	
  
	
  
1) Adjust	
  targets	
  down	
  from	
  2018	
  to	
  support	
  a	
  delayed	
  build	
  of	
  max	
  1,500	
  MW	
  wind	
  or	
  
equivalent	
  per	
  annum.	
  
2) Extend	
  the	
  LRET	
  to	
  2035	
  BUT	
  limit	
  the	
  accreditation	
  of	
  existing	
  generators	
  to	
  2030	
  and	
  
adjust	
  targets	
  from	
  2031	
  to	
  account	
  for	
  lost	
  existing	
  generation.	
  
3) Implied	
  new	
  target	
  levels:	
  
	
  
	
   2015	
   2016	
   2017	
   2018	
   2019	
   2020	
   2021	
   2022	
   2023	
   2030	
   2031	
   2035	
  
Current	
  
41TWh	
  
18.85	
   21.431	
   26.031	
   30.631	
   35.231	
   41.850	
   41	
   41	
   41	
   41	
   0	
   0	
  
Delayed	
  
41	
  TWh	
  
18.85	
   21.431	
   26.031	
   28.351	
   25.303	
   29.765	
   33.374	
   37.838	
   41	
   41	
   25.47	
   25.47	
  
Change	
   0%	
   0%	
   0%	
   -­‐7%	
   -­‐28%	
   -­‐29%	
   -­‐19%	
   -­‐8%	
   0%	
   0%	
   na	
   na	
  
	
  
4) Expected	
  LGC	
  price	
  path	
  (assuming	
  an	
  underlying	
  electricity	
  price	
  of	
  real	
  $40/MWh)	
  with	
  
prices	
  falling	
  due	
  to	
  the	
  scheme	
  extension	
  
	
  
	
   2015	
   2016	
   2017	
   2018	
   2019	
   2020	
   2021	
   2022	
   2023	
   2030	
   2031	
   2035	
  
Current	
  
41TWh	
  
$42.0	
   $45.6	
   $49.5	
   $53.8	
   $58.6	
   $64.4	
   $66.3	
   $68.3	
   $70.3	
   $86.5	
   0	
   0	
  
Delayed	
  
41	
  TWh	
  
$33.9	
   $36.8	
   $40.0	
   $43.4	
   $46.3	
   $49.3	
   $53.3	
   $58.6	
   $64.4	
   $79.6	
   $82.0	
   $92.3	
  
Change	
   -­‐19%	
   -­‐19%	
   -­‐19%	
   -­‐19%	
   -­‐21%	
   -­‐23%	
   -­‐20%	
   -­‐14%	
   -­‐8%	
   -­‐8%	
   na	
   na	
  
	
  
5) Gross	
   LGC	
   cost	
   of	
   additional	
   capacity	
   in	
   2014	
   $’s	
   =	
   $16.9bn	
   vs	
   $15.5bn	
   with	
   current	
  
targets.	
  	
  
6) Actual	
  cost	
  difference	
  should	
  be	
  lower	
  due	
  to	
  gains	
  from	
  avoiding	
  the	
  huge	
  build	
  in	
  2019	
  
AND	
  real	
  gains	
  in	
  efficiency,	
  costs	
  over	
  time,	
  which	
  have	
  not	
  been	
  factored	
  in.	
  
	
  
Arguments	
  against	
  
	
  
1) Lower	
   price	
   expectations	
   for	
   LGC’s	
   will	
   impact	
   existing	
   renewable	
   generators	
   BUT	
   as	
  
explained	
  above	
  some	
  of	
  these	
  generators	
  have	
  already	
  experienced	
  windfall	
  gains	
  from	
  
  3	
  
the	
  extension	
  in	
  2009/2010	
  from	
  2020	
  to	
  2030	
  and	
  on	
  balance	
  are	
  probably	
  still	
  ahead.	
  
Others	
  who	
  have	
  built	
  without	
  the	
  protection	
  of	
  an	
  off-­‐take	
  contract	
  will	
  be	
  negatively	
  
impacted.	
  	
  
2) Lower	
   price	
   expectations	
   for	
   LGC’s	
   will	
   impact	
   on	
   the	
   book	
   value	
   of	
   the	
   surplus	
   BUT	
  
most	
  of	
  that	
  surplus	
  is	
  held	
  by	
  retailers	
  and	
  banked	
  against	
  surrender	
  for	
  compliance	
  or	
  
green-­‐power	
  and	
  isn’t	
  traded	
  on	
  market.	
  
3) There	
  is	
  an	
  increase	
  in	
  the	
  gross	
  real	
  cost	
  of	
  the	
  scheme	
  BUT	
  that	
  increased	
  cost	
  in	
  real	
  
terms	
  is	
  marginal	
  and	
  spread	
  over	
  more	
  years	
  meaning	
  the	
  annual	
  cost	
  is	
  lower.	
  
4) These	
   levels	
   of	
   renewable	
   generation	
   will	
   displace	
   non-­‐renewable	
   generation	
   that	
   is	
  
currently	
   dispatched	
   and	
   may	
   still	
   result	
   in	
   more	
   than	
   20%	
   of	
   generation	
   from	
  
renewable	
   sources	
   by	
   2020	
   BUT	
   will	
   support	
   the	
   objectives	
   of	
   the	
   Renewable	
   Energy	
  
Act,	
  which	
  had	
  bi-­‐partisan	
  support	
  until	
  last	
  year.	
  	
  
	
  
Disclaimer	
  –	
  This	
  analysis	
  is	
  a	
  personal	
  perspective.	
  

More Related Content

What's hot

Transformation In Utilities and Energy
Transformation In Utilities and Energy Transformation In Utilities and Energy
Transformation In Utilities and Energy REV Partners
 
Corporate Presentation CPFL Energia
Corporate Presentation CPFL Energia  Corporate Presentation CPFL Energia
Corporate Presentation CPFL Energia CPFL RI
 
Impact of technology uncertainty on future low-carbon pathways in the UK
Impact of technology uncertainty on future low-carbon pathways in the UKImpact of technology uncertainty on future low-carbon pathways in the UK
Impact of technology uncertainty on future low-carbon pathways in the UKIEA-ETSAP
 
Tariff policy of India: Salient Points
Tariff policy of India: Salient Points Tariff policy of India: Salient Points
Tariff policy of India: Salient Points Amitava Nag
 
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...OECD Environment
 
CREO 2019 power sector outlook
CREO 2019 power sector outlookCREO 2019 power sector outlook
CREO 2019 power sector outlookKaare Sandholt
 
CPFL Investor Day 2019
CPFL Investor Day 2019CPFL Investor Day 2019
CPFL Investor Day 2019CPFL RI
 
CPFL ENERGIA_INSTITUTIONAL PRESENTATION
CPFL ENERGIA_INSTITUTIONAL PRESENTATIONCPFL ENERGIA_INSTITUTIONAL PRESENTATION
CPFL ENERGIA_INSTITUTIONAL PRESENTATIONCPFL RI
 
Making tariff rationalization for domestic consumers a winning proposition fo...
Making tariff rationalization for domestic consumers a winning proposition fo...Making tariff rationalization for domestic consumers a winning proposition fo...
Making tariff rationalization for domestic consumers a winning proposition fo...AurovilleConsulting
 
Impacts of deep decarbonization pathways on the Italian energy intensive indu...
Impacts of deep decarbonization pathways on the Italian energy intensive indu...Impacts of deep decarbonization pathways on the Italian energy intensive indu...
Impacts of deep decarbonization pathways on the Italian energy intensive indu...IEA-ETSAP
 
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...Resurgent India
 
The pan arab interconnection project latest update
The pan arab interconnection project latest updateThe pan arab interconnection project latest update
The pan arab interconnection project latest updateRCREEE
 
Institutional Presentation Aug/20
Institutional Presentation Aug/20Institutional Presentation Aug/20
Institutional Presentation Aug/20ersa_ri
 
Comparing hard-linking (TIMES-MSA) and soft-linking (TIMES-HERMES) methodolog...
Comparing hard-linking (TIMES-MSA) and soft-linking (TIMES-HERMES) methodolog...Comparing hard-linking (TIMES-MSA) and soft-linking (TIMES-HERMES) methodolog...
Comparing hard-linking (TIMES-MSA) and soft-linking (TIMES-HERMES) methodolog...IEA-ETSAP
 
Corporate Presentation CPFL Energia - August 2017
Corporate Presentation CPFL Energia - August 2017Corporate Presentation CPFL Energia - August 2017
Corporate Presentation CPFL Energia - August 2017CPFL RI
 
Evaluating the Development and Impact of Feed-In Tariffs
Evaluating the Development and Impact of Feed-In TariffsEvaluating the Development and Impact of Feed-In Tariffs
Evaluating the Development and Impact of Feed-In TariffsDirk Volkmann
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India sanjeev jain
 
Transnational Trade of Electricity
Transnational Trade of ElectricityTransnational Trade of Electricity
Transnational Trade of ElectricityIPPAI
 

What's hot (20)

Transformation In Utilities and Energy
Transformation In Utilities and Energy Transformation In Utilities and Energy
Transformation In Utilities and Energy
 
Corporate Presentation CPFL Energia
Corporate Presentation CPFL Energia  Corporate Presentation CPFL Energia
Corporate Presentation CPFL Energia
 
Impact of technology uncertainty on future low-carbon pathways in the UK
Impact of technology uncertainty on future low-carbon pathways in the UKImpact of technology uncertainty on future low-carbon pathways in the UK
Impact of technology uncertainty on future low-carbon pathways in the UK
 
Tariff policy of India: Salient Points
Tariff policy of India: Salient Points Tariff policy of India: Salient Points
Tariff policy of India: Salient Points
 
Levellised generic tariff
Levellised generic tariffLevellised generic tariff
Levellised generic tariff
 
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
 
CREO 2019 power sector outlook
CREO 2019 power sector outlookCREO 2019 power sector outlook
CREO 2019 power sector outlook
 
CPFL Investor Day 2019
CPFL Investor Day 2019CPFL Investor Day 2019
CPFL Investor Day 2019
 
CPFL ENERGIA_INSTITUTIONAL PRESENTATION
CPFL ENERGIA_INSTITUTIONAL PRESENTATIONCPFL ENERGIA_INSTITUTIONAL PRESENTATION
CPFL ENERGIA_INSTITUTIONAL PRESENTATION
 
Making tariff rationalization for domestic consumers a winning proposition fo...
Making tariff rationalization for domestic consumers a winning proposition fo...Making tariff rationalization for domestic consumers a winning proposition fo...
Making tariff rationalization for domestic consumers a winning proposition fo...
 
Impacts of deep decarbonization pathways on the Italian energy intensive indu...
Impacts of deep decarbonization pathways on the Italian energy intensive indu...Impacts of deep decarbonization pathways on the Italian energy intensive indu...
Impacts of deep decarbonization pathways on the Italian energy intensive indu...
 
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
 
SHAMS Dubai
SHAMS DubaiSHAMS Dubai
SHAMS Dubai
 
The pan arab interconnection project latest update
The pan arab interconnection project latest updateThe pan arab interconnection project latest update
The pan arab interconnection project latest update
 
Institutional Presentation Aug/20
Institutional Presentation Aug/20Institutional Presentation Aug/20
Institutional Presentation Aug/20
 
Comparing hard-linking (TIMES-MSA) and soft-linking (TIMES-HERMES) methodolog...
Comparing hard-linking (TIMES-MSA) and soft-linking (TIMES-HERMES) methodolog...Comparing hard-linking (TIMES-MSA) and soft-linking (TIMES-HERMES) methodolog...
Comparing hard-linking (TIMES-MSA) and soft-linking (TIMES-HERMES) methodolog...
 
Corporate Presentation CPFL Energia - August 2017
Corporate Presentation CPFL Energia - August 2017Corporate Presentation CPFL Energia - August 2017
Corporate Presentation CPFL Energia - August 2017
 
Evaluating the Development and Impact of Feed-In Tariffs
Evaluating the Development and Impact of Feed-In TariffsEvaluating the Development and Impact of Feed-In Tariffs
Evaluating the Development and Impact of Feed-In Tariffs
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India
 
Transnational Trade of Electricity
Transnational Trade of ElectricityTransnational Trade of Electricity
Transnational Trade of Electricity
 

Similar to A Solution to the LRET Impasse

Australian Renewable Energy Target Progress Report - June 2016
Australian Renewable Energy Target Progress Report - June 2016Australian Renewable Energy Target Progress Report - June 2016
Australian Renewable Energy Target Progress Report - June 2016Turlough Guerin GAICD FGIA
 
Draft Article - V1
Draft Article - V1Draft Article - V1
Draft Article - V1Ajay Nanda
 
SmartestEnergy: The transition to new renewable subsidy schemes June 2015
SmartestEnergy: The transition to new renewable subsidy schemes June 2015SmartestEnergy: The transition to new renewable subsidy schemes June 2015
SmartestEnergy: The transition to new renewable subsidy schemes June 2015SmartestEnergy
 
IEA World Energy Outlook 2020 launch-presentation
IEA World Energy Outlook 2020 launch-presentationIEA World Energy Outlook 2020 launch-presentation
IEA World Energy Outlook 2020 launch-presentationEnergy for One World
 
Doe 2013 Eere Congressional Budget Request
Doe 2013 Eere Congressional Budget RequestDoe 2013 Eere Congressional Budget Request
Doe 2013 Eere Congressional Budget RequestLarry Stapleton
 
Capital Power 2016 BMO Capital Markets Infrastructure & Utilities conference ...
Capital Power 2016 BMO Capital Markets Infrastructure & Utilities conference ...Capital Power 2016 BMO Capital Markets Infrastructure & Utilities conference ...
Capital Power 2016 BMO Capital Markets Infrastructure & Utilities conference ...Capital Power
 
Bvga hundleby icoe 2016
Bvga hundleby icoe 2016Bvga hundleby icoe 2016
Bvga hundleby icoe 2016BVG Associates
 
National Renewable Energy Program (NREP) 2020-2040 and sector updates, Ruby G...
National Renewable Energy Program (NREP) 2020-2040 and sector updates, Ruby G...National Renewable Energy Program (NREP) 2020-2040 and sector updates, Ruby G...
National Renewable Energy Program (NREP) 2020-2040 and sector updates, Ruby G...OECD Environment
 
Bnef neo2015 executive-summary
Bnef neo2015 executive-summaryBnef neo2015 executive-summary
Bnef neo2015 executive-summaryDmitry Tseitlin
 
Operational Challenges of Renewable Generation Integration in GCC
Operational Challenges of Renewable Generation Integration in GCCOperational Challenges of Renewable Generation Integration in GCC
Operational Challenges of Renewable Generation Integration in GCCPower System Operation
 
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015Scott Clausen
 
Energy efficiency in the tennessee valley
Energy efficiency in the tennessee valleyEnergy efficiency in the tennessee valley
Energy efficiency in the tennessee valleyTNenergy
 
Poyry - Within day flexibilitypress - Point of View
Poyry - Within day flexibilitypress - Point of ViewPoyry - Within day flexibilitypress - Point of View
Poyry - Within day flexibilitypress - Point of ViewPöyry
 
VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...
VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...
VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...Dr. Oliver Massmann
 
Ceew ceew cef market handbook q1 2020-21 10 sep20
Ceew   ceew cef market handbook q1 2020-21 10 sep20Ceew   ceew cef market handbook q1 2020-21 10 sep20
Ceew ceew cef market handbook q1 2020-21 10 sep20Mayank Munjal
 
VIETNAM – POWER SECTOR REFORM COMPETITIVE AUCTION MECHANISM FOR NEW GENERATI...
VIETNAM – POWER SECTOR REFORM  COMPETITIVE AUCTION MECHANISM FOR NEW GENERATI...VIETNAM – POWER SECTOR REFORM  COMPETITIVE AUCTION MECHANISM FOR NEW GENERATI...
VIETNAM – POWER SECTOR REFORM COMPETITIVE AUCTION MECHANISM FOR NEW GENERATI...Dr. Oliver Massmann
 
Scenario analysis of data centres in the Irish energy system
Scenario analysis of data centres in the Irish energy systemScenario analysis of data centres in the Irish energy system
Scenario analysis of data centres in the Irish energy systemIEA-ETSAP
 

Similar to A Solution to the LRET Impasse (20)

Australian Renewable Energy Target Progress Report - June 2016
Australian Renewable Energy Target Progress Report - June 2016Australian Renewable Energy Target Progress Report - June 2016
Australian Renewable Energy Target Progress Report - June 2016
 
Draft Article - V1
Draft Article - V1Draft Article - V1
Draft Article - V1
 
SmartestEnergy: The transition to new renewable subsidy schemes June 2015
SmartestEnergy: The transition to new renewable subsidy schemes June 2015SmartestEnergy: The transition to new renewable subsidy schemes June 2015
SmartestEnergy: The transition to new renewable subsidy schemes June 2015
 
IEA World Energy Outlook 2020 launch-presentation
IEA World Energy Outlook 2020 launch-presentationIEA World Energy Outlook 2020 launch-presentation
IEA World Energy Outlook 2020 launch-presentation
 
Doe 2013 Eere Congressional Budget Request
Doe 2013 Eere Congressional Budget RequestDoe 2013 Eere Congressional Budget Request
Doe 2013 Eere Congressional Budget Request
 
Capital Power 2016 BMO Capital Markets Infrastructure & Utilities conference ...
Capital Power 2016 BMO Capital Markets Infrastructure & Utilities conference ...Capital Power 2016 BMO Capital Markets Infrastructure & Utilities conference ...
Capital Power 2016 BMO Capital Markets Infrastructure & Utilities conference ...
 
Bvga hundleby icoe 2016
Bvga hundleby icoe 2016Bvga hundleby icoe 2016
Bvga hundleby icoe 2016
 
National Renewable Energy Program (NREP) 2020-2040 and sector updates, Ruby G...
National Renewable Energy Program (NREP) 2020-2040 and sector updates, Ruby G...National Renewable Energy Program (NREP) 2020-2040 and sector updates, Ruby G...
National Renewable Energy Program (NREP) 2020-2040 and sector updates, Ruby G...
 
Concepts of economic attributes part 1
Concepts of economic attributes part 1Concepts of economic attributes part 1
Concepts of economic attributes part 1
 
Concepts of economic attributes part 1
Concepts of economic attributes part 1Concepts of economic attributes part 1
Concepts of economic attributes part 1
 
Bnef neo2015 executive-summary
Bnef neo2015 executive-summaryBnef neo2015 executive-summary
Bnef neo2015 executive-summary
 
Operational Challenges of Renewable Generation Integration in GCC
Operational Challenges of Renewable Generation Integration in GCCOperational Challenges of Renewable Generation Integration in GCC
Operational Challenges of Renewable Generation Integration in GCC
 
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015
 
Energy efficiency in the tennessee valley
Energy efficiency in the tennessee valleyEnergy efficiency in the tennessee valley
Energy efficiency in the tennessee valley
 
Poyry - Within day flexibilitypress - Point of View
Poyry - Within day flexibilitypress - Point of ViewPoyry - Within day flexibilitypress - Point of View
Poyry - Within day flexibilitypress - Point of View
 
Small Power Generation Plant
Small Power Generation PlantSmall Power Generation Plant
Small Power Generation Plant
 
VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...
VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...
VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...
 
Ceew ceew cef market handbook q1 2020-21 10 sep20
Ceew   ceew cef market handbook q1 2020-21 10 sep20Ceew   ceew cef market handbook q1 2020-21 10 sep20
Ceew ceew cef market handbook q1 2020-21 10 sep20
 
VIETNAM – POWER SECTOR REFORM COMPETITIVE AUCTION MECHANISM FOR NEW GENERATI...
VIETNAM – POWER SECTOR REFORM  COMPETITIVE AUCTION MECHANISM FOR NEW GENERATI...VIETNAM – POWER SECTOR REFORM  COMPETITIVE AUCTION MECHANISM FOR NEW GENERATI...
VIETNAM – POWER SECTOR REFORM COMPETITIVE AUCTION MECHANISM FOR NEW GENERATI...
 
Scenario analysis of data centres in the Irish energy system
Scenario analysis of data centres in the Irish energy systemScenario analysis of data centres in the Irish energy system
Scenario analysis of data centres in the Irish energy system
 

A Solution to the LRET Impasse

  • 1.   1   A  SOLUTION  TO  THE  LRET  IMPASSE  THAT  DELIVERS  A  REDUCED  WIND  FARM  BUILD  TO  THE   GOVERNMENT  BUT  PROVIDES  STABLE  GROWTH  THAT  THE  WIND  INDUSTRY  CRAVES   By  Simon  Mathis,  MBA,  MA  (Cantab)     Executive  Summary     Concerns   have   been   expressed   by   the   Government   (and   worked   over   by   the   Warburton   Review)  that  lower  than  expected  electricity  demand  in  2020  will  see  renewables,  supported   by  the  RET,  take  an  unacceptable  amount  of  supply  from  existing  non-­‐renewable  generators.   With  the  recommendations  of  the  Warburton  review  largely  discredited  the  potential  has   risen  for  a  middle  ground  solution  to  be  adopted  that  can  satisfy  the  needs  (not  demands)  of   most  stakeholders.  By  delaying  the  delivery  of  the  fixed  target  of  41GWh  to  2023  with  an   associated  limited  extension  of  the  scheme  to  2035  it  is  possible  to  continue  to  support  the   growth  of  the  large-­‐scale  renewable  industry  in  Australia  at  an  acceptable  overall  cost.     Some   basic   context/facts   about   the   workings   of   the   large-­‐scale   renewable   energy   target   (“LRET”)  and  certificate  market.     a) When  the  target  was  expanded  from  9.5TWh  to  45TWh  in  2009/2010  the  scheme  was   also  extended  from  2020  to  2030  providing  a  wind-­‐fall  gain  for  those  existing  accredited   generators   with   long   operating   lives   able   to   create   up   to   another   10   years   of   REC’s/LGC’s.  (Note  wind  turbine  generators  have  a  typical  useful  life  of  only  20  to  25   years).   I   raise   this   point   because   any   changes   to   the   LRET   will   have   effects   on   both   existing  and  proposed  generators  but  some  of  those  generators  will  be  looking  to  secure   support  that  wasn’t  in  existence  when  investment  decisions  were  originally  made.   b) My  forecast  of  the  surplus  of  Large  Generation  Certificates  (“LGC’s”)  post  surrender  in   2014  for  compliance  and  green-­‐power  is  ~24.9  million.  Without  any  further  build  beyond   what  is  already  in  the  construction  pipeline  this  surplus  will  not  be  used  up  even  under   the  current  targets  until  sometime  in  2018.   c) The  surplus  acts  to  defer  commitment  to  new  renewable  generation.  The  fixed  end  date   (2030)  of  the  LRET  means  that  the  later  the  date  a  renewable  generator  starts  operating   the  fewer  LGC’s  it  can  create  and  therefore  (all  other  factors  being  equal)  the  higher  the   price  per  LGC  it  must  earn.  If  wind  energy  is  the  LGC  price  barometer  then  any  generator   starting   operations   from   2021   would   require   an   LGC   price   in   excess   of   the   $65   /LGC   penalty  price.   d) The   current   LRET   requires   an   additional   ~2,250   MW   of   wind   or   the   equivalent   to   be   operating  by  2018,  ~4,100  MW  to  be  operating  by  2019  and  ~2,250  MW  to  be  operating   by  2020.  When  compared  with  the  total  installed  base  of  wind  farms  of  3,610  MW  plus   556  MW  under  construction  this  is  a  tall  order  for  an  industry  currently  in  the  doldrums   of  regulatory  uncertainty  and  if  delivered  will  almost  certainly  involve  inefficiencies  and   added   costs.   The   pinch   point   is   not   in   the   development   phases   of   site   identification,   community,  environment  and  planning  approvals  but  in  delivery.  The  wind  industry  will   argue   against   delays   due   to   fears   of   the   coming   of   large-­‐scale   solar   price   competitiveness  and  a  loss  of  share  of  the  LRET  by  wind.   e) The  recommendations  of  the  Warburton  review  are  flawed  not  just  because  they  kill  all   future  large-­‐scale  renewable  energy  development  but  also  because  they  fail  to  deal  at  all   with   the   LGC   surplus   meaning   the   price   of   LGC’s   could   fall   to   zero   necessitating   compensation/market  support.    
  • 2.   2   Core  characteristics  of  a  middle  ground  solution     What  could  a  middle  ground  (addresses  conservative  concerns  that  too  much  generation  is   being   forced   into   the   market   to   the   detriment   of   existing   non-­‐renewable   generators   but   supports  the  continued  growth  of  the  renewable  energy  industry)  solution  look  like?     i) Fixed  targets  until  at  least  the  LGC  surplus  is  used  up  (without  the  absolute  certainty   of  the  requirement  for  new  renewable  generation  build  the  price  of  LGC’s  cannot   recover  to  supportive  levels).   ii) Targets  that  support  a  sensible  new  build  program  of  1,000  to  1,500  MW  of  wind  or   equivalent   per   annum.   Such   a   new   build   program   will   be   sufficient   to   attract   efficiencies  across  the  project  life-­‐cycle  meaning  delivery  at  least  cost.   iii) A   scheme   that   rewards   new   projects   with   LGC’s   for   a   minimum   of   15   years   and   preferably  20  years  to  ensure  acceptable  LGC  prices.   iv) A  scheme  that  avoids  the  costs  associated  with  extending  support  beyond  2030  to   existing  renewable  generators.     Solution     1) Adjust  targets  down  from  2018  to  support  a  delayed  build  of  max  1,500  MW  wind  or   equivalent  per  annum.   2) Extend  the  LRET  to  2035  BUT  limit  the  accreditation  of  existing  generators  to  2030  and   adjust  targets  from  2031  to  account  for  lost  existing  generation.   3) Implied  new  target  levels:       2015   2016   2017   2018   2019   2020   2021   2022   2023   2030   2031   2035   Current   41TWh   18.85   21.431   26.031   30.631   35.231   41.850   41   41   41   41   0   0   Delayed   41  TWh   18.85   21.431   26.031   28.351   25.303   29.765   33.374   37.838   41   41   25.47   25.47   Change   0%   0%   0%   -­‐7%   -­‐28%   -­‐29%   -­‐19%   -­‐8%   0%   0%   na   na     4) Expected  LGC  price  path  (assuming  an  underlying  electricity  price  of  real  $40/MWh)  with   prices  falling  due  to  the  scheme  extension       2015   2016   2017   2018   2019   2020   2021   2022   2023   2030   2031   2035   Current   41TWh   $42.0   $45.6   $49.5   $53.8   $58.6   $64.4   $66.3   $68.3   $70.3   $86.5   0   0   Delayed   41  TWh   $33.9   $36.8   $40.0   $43.4   $46.3   $49.3   $53.3   $58.6   $64.4   $79.6   $82.0   $92.3   Change   -­‐19%   -­‐19%   -­‐19%   -­‐19%   -­‐21%   -­‐23%   -­‐20%   -­‐14%   -­‐8%   -­‐8%   na   na     5) Gross   LGC   cost   of   additional   capacity   in   2014   $’s   =   $16.9bn   vs   $15.5bn   with   current   targets.     6) Actual  cost  difference  should  be  lower  due  to  gains  from  avoiding  the  huge  build  in  2019   AND  real  gains  in  efficiency,  costs  over  time,  which  have  not  been  factored  in.     Arguments  against     1) Lower   price   expectations   for   LGC’s   will   impact   existing   renewable   generators   BUT   as   explained  above  some  of  these  generators  have  already  experienced  windfall  gains  from  
  • 3.   3   the  extension  in  2009/2010  from  2020  to  2030  and  on  balance  are  probably  still  ahead.   Others  who  have  built  without  the  protection  of  an  off-­‐take  contract  will  be  negatively   impacted.     2) Lower   price   expectations   for   LGC’s   will   impact   on   the   book   value   of   the   surplus   BUT   most  of  that  surplus  is  held  by  retailers  and  banked  against  surrender  for  compliance  or   green-­‐power  and  isn’t  traded  on  market.   3) There  is  an  increase  in  the  gross  real  cost  of  the  scheme  BUT  that  increased  cost  in  real   terms  is  marginal  and  spread  over  more  years  meaning  the  annual  cost  is  lower.   4) These   levels   of   renewable   generation   will   displace   non-­‐renewable   generation   that   is   currently   dispatched   and   may   still   result   in   more   than   20%   of   generation   from   renewable   sources   by   2020   BUT   will   support   the   objectives   of   the   Renewable   Energy   Act,  which  had  bi-­‐partisan  support  until  last  year.       Disclaimer  –  This  analysis  is  a  personal  perspective.