SlideShare a Scribd company logo
1 of 11
Download to read offline
1
PROGRESS AND STATUS OF THE
RENEWABLE ENERGY TARGET
BRIEFING PAPER
CLEAN ENERGY COUNCIL
JUNE 2016
PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 2
Investment confidence in Australia’s renewable energy sector has significantly improved
following the legislation of the revised Large-scale Renewable Energy Target (LRET) in mid-
2015, a new Prime Minister that is more supportive of renewable energy and a strong outcome
at the Paris climate change conference.
The level and pace of investment will need to increase substantially in 2016 and 2017 in order
for liable parties to deliver on the 2020 legislated target and obligation. The Clean Energy
Regulator estimates that for this to happen, around 3000 MW of new renewable capacity should
be committed in 2016.
This paper outlines the status of progress towards delivering on the 2020 target of 33,000 GWh
of new large-scale renewable energy generation. While there will be challenges, this paper finds
that there is reason to be optimistic that the required new investment will be delivered within the
required timeframe.
The current situation is as follows:
• In 2015 approximately 15,200 GWh of renewable energy was generated above the pre-
1997 baseline levels established under the Renewable Energy Target (RET) legislation.
• To achieve the 33,000 GWh target, approximately 18,000 GWh of additional annual
renewable energy generation needs to be produced by 2020. This will require around 6000
MW of new generation capacity and will create around $10 billion in new investment and
thousands of jobs in rural and regional Australia.
• Most analysts predict that the current surplus of Large-scale Generation Certificates (LGCs)
will meet liabilities under the RET scheme for approximately two years. Noting it takes
approximately two years from commercial close to construct and commission a new wind
project – less for large scale solar – clearly there needs to be substantial progress
throughout 2016 and 2017 in order for these liable parties to deliver on their future
legislated obligation.
• Approximately 11,000 MW of projects with planning approval, and projects adding up to a
further 6000 MW of capacity are currently going through the planning approval process.
More than enough projects are in the pipeline, ready to deliver the 33,000 GWh target by
2020.
• While liable parties will seek to minimise their cost and commercial exposure in securing
future LGC supply, they also have an obligation to ensure that they secure the necessary
LGCs to meet their annual liability in compliance with the intent of the legislation.
• While overall progress toward the target has not been as rapid as many would like, a range
of developments have continued to improve confidence since mid-2015. Approximately 700
EXECUTIVE SUMMARY
PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 3
MW has been committed towards the RET since the legislative change last year, with
approximately 450 MW of new capacity committed in the past three months alone.
Momentum is clearly building.
• Investment in renewable energy is challenged by a number of factors outside of the control
of the industry. A surplus of highly emission-intensive and aged power plants remain in the
system due to the absence of a clear long-term policy for the electricity generation sector.
The current RET policy has a target that peaks in 2020 (just four years away) and the
scheme ends in 2030, which creates uncertainty with regard to long term merchant LGC
prices. While these factors may create challenges, they do not change the fact that there is
an obligation on liable parties under the legislation to secure LGCs to meet their liabilities
through to 2030.
PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 4
____________________________________________________________
OVERVIEW OF THE LARGE-SCALE RENEWABLE ENERGY TARGET
The Commonwealth Renewable Energy Target (RET) is critical to the deployment of renewable
energy in Australia.
It is split in two parts:
• The Large Scale Renewable Energy Target (LRET) that requires 33,000 GWh of new
generation annually from large scale renewable energy by 2020.
• The Small-Scale Renewable Energy Scheme (SRES) that supports residential and small
commercial renewable energy installations.
After a protracted review, the LRET was amended and the target reduced in mid-2015 with the
support of both major parties. While this restored policy certainty, negative comments related to
renewable energy from then-Prime Minister Tony Abbott prolonged investment uncertainty for
the sector. A change of Prime Minister in late 2015 and a strong outcome at the climate change
conference in Paris in December 2015 finally provided the sector with greater long-term
certainty. Minister for the Environment Greg Hunt’s strong assurances that the Federal
Government will not make any further reductions to the target legislation and that liable parties
are expected to comply with the policy have further improved investor confidence.
It has taken some time for this confidence to flow to commercial transactions and ultimately the
construction of new large-scale renewable energy projects. However there have been a number
of Power Purchase Agreements (PPAs) signed this year, and capacity is also being built on a
‘merchant’ basis, selling into the electricity market without a PPA in place.
____________________________________________________________
CURRENT STATUS
Australian renewable energy generation and capacity as at 31 December 2015 is summarised
as follows.
TABLE 1 SUMMARY OF RENEWABLE ENERGY CAPACITY AND GENERATION IN 2015
Technology Installed capacity (MW) Generation (GWh)
Hydro 7800 14,046 (mostly pre-baseline)
Wind 4187 11,802
Large-scale solar 224 303
Bioenergy 990 3200
Solar Thermal 9.3 27
PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 5
Marine 0.24 0.5
Geothermal 0.12 0.50
Most of Australia’s hydro generation existed prior to the establishment of the RET. Under the
legislation, generation from pre-existing hydro stations does not count towards the 33,000 GWh
target, with the exception of generation that exceeds predetermined baselines.
The 2015 target for the LRET was 18,850,000 LGCs, which is 18,850 GWh or 11.11 percent of
electricity consumption1. Generation from above-baseline large-scale sources totals around
15,200 GWh. The actual number of LGCs surrendered to the Clean Energy Regulator was
higher than this, noting that liable parties were able to use banked certificates (from prior years
where supply was greater than demand) to meet 2015 legislated obligations. Analysis indicates
that this banked surplus (combined with the existing annual generation) is sufficient to support
liable parties in meeting obligations out to around 2017-2018.
In March 2016 the Clean Energy Regulator announced that the combined compliance rate for
the LRET and SRES for 2015 was 99.7 per cent. The regulator said: “Liable entities have
complied with their obligations in recent years and it is pleasing to see this continue.”
____________________________________________________________
NEW GENERATION REQUIRED TO MEET THE RET
To achieve the 33,000 GWh target, approximately 18,000 GWh of additional renewable energy
generation needs to be produced annually by 2020.
Based on current renewable energy technologies this will likely equate to around 6000 MW of
new capacity, depending on the exact mix of technologies that will be deployed. This is likely to
be predominantly from large-scale wind and large-scale solar along with commercial-scale solar
(100 kW to 1 MW behind the meter installations). There is also likely to be some level of new
generation from mini hydro power stations, upgrades and refurbishment of existing hydro power,
bioenergy and a limited amount of ocean energy generation by 2020. Above-baseline hydro
power generation is also expected to increase after the difficult, low-inflow conditions of 2015.
____________________________________________________________
THE CURRENT PROJECT PIPELINE
As at May 2016 there is approximately 500 MW of wind capacity under construction, which will
come online in 2016 and 2017, and 30 MW of large-scale solar under construction and
expected to become operational in 2016. There is also a construction pipeline of commercial-
scale solar projects between 100 kW and 1 MW that will contribute to the LRET target.
1
Clean Energy Regulator, Annual targets and the Renewable Power Percentage, 2016, Available online
http://www.cleanenergyregulator.gov.au/RET/About-the-Renewable-Energy-Target/The-certificate-
market/annual-targets-and-the-renewable-power-percentage
PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 6
The following tables summarise the total development pipeline, showing 8000 MW of wind
projects and 2585 MW of solar PV projects with development approval. It should be noted that
there is likely to be substantial additional large-scale solar capacity in development, given these
projects often do not need to go through statutory planning schemes (and therefore may not be
captured in the below analysis).
WIND
State or
Territory
Under
construction
(MW)
Approved (MW)
In the approvals
system (MW)
Total (MW)
VIC 239 1729 850 2818
NSW 175 2195 4835 7205
QLD 1045 345 1390
WA 1184 170 1354
SA 118 1565 453 2136
TAS 339 339
ACT
NT
TOTAL 532 8057 6653 15,242
SOLAR
State or
Territory
Under
construction
(MW)
Approved (MW)
In the approvals
system (MW)
Total (MW)
VIC 180 180
NSW 110 110
QLD 20 2280 2480
WA 10 10
SA
TAS
ACT 15 10 25
NT 1 1
TOTAL 31 2585 10 2626
It is clear from this summary that more than enough renewable energy projects are approved
than are required to meet the LRET. Of course, not all approved projects will go ahead.
Because the LRET is a market mechanism, only projects that can deliver the lowest cost
renewable energy are likely to be constructed.
Competitiveness is influenced by a combination of factors including resource quality, technology
costs, electricity market conditions, network access and connection and the planning regime in
particular jurisdictions.
PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 7
____________________________________________________________
PROGRESS TOWARDS 2020
While progress toward the target has not been as rapid as the industry would like since mid-
2015, a range of developments in the first half of 2016 has included:
• Commencement of construction at the 175 MW White Rock wind farm in New South Wales
in late April 2016.
• Construction underway on the Ararat wind farm in western Victoria, with 80 MW of capacity
sponsored by the ACT reverse auction and a further 160 MW being built under the RET
scheme, with debt financing from the Clean Energy Financing Corporation.
• The 56 MW Moree Solar Farm was opened in northern New South Wales, the second
largest in Australia. Origin Energy issued a Power Purchase Agreement (PPA), to buy the
electricity produced by the farm for a 15-year period.
• The 100 MW Clare Solar Farm in Queensland has struck a Power Purchase Agreement
with Origin Energy. Fotowatio Renewable Ventures (FRV) will commence construction in
2016, with operations expected to commence in 2017. The PPA will run for 13 years from
the commencement of operations until December 2030.
• The 175 MW Mt Emerald Wind Farm project in Queensland struck a 15-year PPA with
Ergon Energy and is expected to commence construction in 2017.
• AGL announced its Powering Australian Renewables Fund - a new entity tasked with
funding a portfolio of new renewable energy projects, which AGL believes will add up to $2-
3 billion worth of investment that it expects will deliver about 1000 megawatts of new
renewables. The company will contribute $200 million in equity and is seeking investment
partners for the new fund.
• A range of commercial-scale solar projects between 100kW and 1 MW that contribute
towards the LRET scheme.
Since the resolution of the RET in June 2015, approximately 1000 MW of renewable energy
capacity has been committed or commenced construction, approximately 700 MW of which will
contribute toward the RET scheme. The other 300 MW is supported by, and contributing to, the
ACT reverse auction. Momentum is building and in the last three months alone, the White Rock
Wind Farm, Clare Solar Farm and Mt Emerald Wind Farm announcements equate to
approximately 450 MW of new capacity under the RET. While this progress has been positive
for the renewable energy industry, the rate of new build is currently insufficient to meet the
future liability.
However, there are signs of substantial additional commitments throughout the year which will
help to provide additional momentum. These potential projects include:
• The City of Melbourne together with other local governments, cultural and educational
institutions, and private-sector corporations has launched a competitive tender to purchase
PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 8
110 GWh worth of energy from new large scale renewable energy facilities. The tender
closes in June 2016.
• The New South Wales Government tender for 137 GWh of renewable energy for its Sydney
Metro Northwest rail project, which opened in January and closed in March 2016.
• The Australian Renewable Energy Agency (ARENA) is running a large-scale solar funding
round which has short-listed 22 projects and is expected to award a total of $100 million
towards around 200 MW of large- scale solar capacity later in 2016.
• Tenders or expression of interest processes are currently underway from a number of liable
parties including Alinta Energy, Synergy and Ergon Energy.
• A number of state governments have committed to increase the procurement of renewable
energy. This includes Victoria’s tender for around 100 megawatts of new renewable energy
projects, which closed in March 2016.
____________________________________________________________
STATUS OF LIABLE PARTIES
The retail electricity market is dominated by a small number of market participants, which carry
the majority of the overall retail load and therefore liability for the RET. Each of these
participants have a current surplus of LGCs to meet some level of their future liability. Most
analysts predict that the current surplus of LGCs will meet liabilities for approximately two years.
Noting it takes approximately two years from commercial close to construct and commission a
new wind project, and less for large-scale solar, clearly there needs to be substantial progress
throughout 2016 in order for these liable parties to deliver on their future legislated obligation.
The graph below shows the legislated certificate liability2
, and expected generation from existing
assets, assets currently under construction, and approved assets. It also shows the expected
surrender of banked certificates, with data from Green Energy Markets3
.
The potential generation from approved wind and solar projects has been smoothed over three
years, with a consistent build rate for 2018, 2019 and 2020. The graph illustrates that there is
more approved capacity than required under the legislation. The smooth build rate is for
illustrative purposes. In practical terms there is likely to be some level of variation in annual build
rates over this period.
There is clearly a large pipeline of approved projects, and the sector has strong capability and
capacity to deliver materially higher levels of annual deployment. Substantial delays in
committing new projects resulting in larger annual build rates in 2019 and 2020 could however
2
Clean Energy Regulator, 2015, Annual targets. Available online:
http://www.cleanenergyregulator.gov.au/RET/About-the-Renewable-Energy-Target/The-certificate-
market/The-renewable-power-percentage/Annual-targets
3
Green Energy Markets, 2015, Quarterly Renewables Report Q3 2015. Available online:
http://greenmarkets.com.au/news-events/report-quarterly-renewables-report-q3-2015
PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 9
result in some resource constraints that could impact the time and cost to deliver new projects.
This risk can be minimised by liable parties ensuring that early progress is made in commitment
and construction.
Approximately 3000 MW of new large-scale projects are required to reach commercial close so
that they can then commence construction by 2017 and begin generating LGCs by 2018. The
LGC price has increased from around $30 during the RET review to over $80, reflecting the
likely impending shortfall of LGCs. Based on prices achieved by the ACT’s reverse auctions, the
LGC price is above the level required over the life of a contracted project to make it
commercially viable.
As outlined above, approximately 1000 MW of large scale renewable energy projects with
planning approval are now awaiting commercial close in order to progress ton construction.
Most project proponents will require some form of off-take or PPA that can provide certainty of
revenue sufficient to warrant the substantial capital investment.
Liable parties recognise the role of PPA’s in underpinning investment, with a long history of
PPAs in various forms and tenor since the RET was first established in 2001. Understandably,
liable parties will seek PPA forms and tenor that minimise their cost and commercial exposure.
This is the nature of complex commercial negotiations between liable parties and project
proponents. Fundamentally however, liable parties have an obligation to comply with the RET
legislation and ensure that they secure the necessary annual LGC supply to meet their annual
liability.
If liable parties do not comply with their annual obligation they are required to pay a shortfall
0
5000000
10000000
15000000
20000000
25000000
30000000
35000000
40000000
45000000
50000000
2016 2017 2018 2019 2020
MWhorLGCs
Renewable Energy Target and generation
capacity
Surplus certificates
surrendered (according to
Green Markets)
Potential generation from
approved projects - built over
three years
Expected generation from
projects currently under
construction
Generation from existing
assets
LRET target
PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 10
charge of $65 for each LGC they have failed to surrender. This is a tax exclusive amount,
meaning that for a commercial business paying income tax, the tax effective penalty may be as
high as $93. As such, a liable party might be better off from an economic perspective buying
LGCs on the market for up to $93 each. The RET legislation also includes a make-good
provision, whereby if a liable party has not complied in a given year, and rather paid the penalty,
they can provide a valid LGC in the future (up to three years) and surrender this in return for the
$65 penalty.
____________________________________________________________
RENEWABLE ENERGY INVESTMENT CHALLENGES
Investment in renewable energy is challenged by a number of factors outside of the control of
the industry. A surplus of highly emissions-intensive and aged power plants remain in operation
due to the absence of a clear long-term policy for the electricity generation sector and the
barriers to exit facing some of this plant. This creates a challenge for the commercial case for
new renewable energy generation.
The current RET policy has a target that peaks in 2020 (just four years away) and the scheme
ends in 2030, which creates uncertainty with regard to long-term merchant LGC prices.
Investors need confidence that the necessary revenue will be provided over that period to
recover the capital cost of their investment. The sector has long advocated this challenge be
addressed by:
• An increase to the target beyond 2020. The current RET target peaks in 2020, and remains
at that level until 2030. Forecasting the price of LGCs during this period is challenging, and
therefore certainty of project revenue during this period is lower. This obviously makes the
business case for projects more difficult as time goes on. The CEC has always advocated
that the RET target should continue to increase at some level beyond 2020 to provide a
stable growth pipeline and to allow the sector to mature and develop. An increasing role for
renewable energy is consistent with emissions commitments from all major parties. For the
sector to decarbonise, existing and additional zero-emissions generation will be increasingly
important. A challenge for investors is how to quantify/access this value when faced with
questions over the longer-term policy mix for the sector.
• An extension of the RET beyond 2030 to provide long-term certainty. The RET scheme
should continue to remain in place for 15 years after the peak of the target. For the current
target, which peaks in 2020, the scheme should continue until 2035 in order to provide
revenue support for projects committed towards the end of the growth trajectory. The longer-
term revenue support will generally result in lower LGC prices – because the costs are
recovered over a longer period – and therefore lower overall costs to consumers.
One final challenge is the changing nature of the electricity market, and contracting
arrangements with commercial and industrial electricity customers. These contracts are tending
toward shorter tenures and with higher customer churn, creating some challenges for electricity
retailers to anticipate their future LRET liability for this customer segment. These retail
businesses are understandably cautious therefore in committing to long-term renewable energy
projects and LGCs to meet this variable future liability. However, with increasing retail
competition and LGC spot prices now materially above long-term contract prices, there is a
PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 11
clear financial incentive for these retail businesses to enter into some form of longer-term LGC
arrangement for all aspects of their customer liability.
While these factors may currently create challenges, renewable energy is widely expected to
have a strong and growing role in the Australian energy mix. The 33,000 GWh LRET has
bipartisan support and places a legal obligation on liable parties to meet their share of the 2020
liability.

More Related Content

What's hot

Energy Report - Strange Brew: Adapting to Changing Fundamentals
Energy Report - Strange Brew: Adapting to Changing FundamentalsEnergy Report - Strange Brew: Adapting to Changing Fundamentals
Energy Report - Strange Brew: Adapting to Changing FundamentalsMarcellus Drilling News
 
Energy policy aus
Energy policy ausEnergy policy aus
Energy policy ausRohil Kumar
 
China energy roadmap slides
China energy roadmap slidesChina energy roadmap slides
China energy roadmap slidesRoger Atkins
 
Keynote address min at africa energy indaba feb 2019 1
Keynote address min at africa  energy indaba  feb 2019 1Keynote address min at africa  energy indaba  feb 2019 1
Keynote address min at africa energy indaba feb 2019 1aujourlejour1
 
Energy Policy Making in Iceland, With emphasis on geothermal energy utilization
Energy Policy Making in Iceland, With emphasis on geothermal energy utilizationEnergy Policy Making in Iceland, With emphasis on geothermal energy utilization
Energy Policy Making in Iceland, With emphasis on geothermal energy utilizationIceland Geothermal
 
Nextera Energy University of Southern California Investment C
Nextera Energy University of Southern California Investment CNextera Energy University of Southern California Investment C
Nextera Energy University of Southern California Investment CTimothy O'Brien
 
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat
 
New base 680 special 06 september 2015
New base 680 special  06 september 2015New base 680 special  06 september 2015
New base 680 special 06 september 2015Khaled Al Awadi
 
Extending and improving Ontario’s electricity demand management framework
Extending and improving Ontario’s electricity demand management frameworkExtending and improving Ontario’s electricity demand management framework
Extending and improving Ontario’s electricity demand management frameworkEfficiencyCanada
 
Combined heat and power CHP _ ARES _ DOE
Combined heat and power  CHP _ ARES _ DOE Combined heat and power  CHP _ ARES _ DOE
Combined heat and power CHP _ ARES _ DOE Dmitry Tseitlin
 
Spencer Ogden Brochure.Cfm
Spencer Ogden Brochure.CfmSpencer Ogden Brochure.Cfm
Spencer Ogden Brochure.CfmGordonTurner
 
World Energy Inside - Febbraio 2017
World Energy Inside - Febbraio 2017World Energy Inside - Febbraio 2017
World Energy Inside - Febbraio 2017WEC Italia
 
Ne base 07 march 2018 energy news issue 1148 by khaled al awadi
Ne base 07 march 2018 energy news issue   1148  by khaled al awadiNe base 07 march 2018 energy news issue   1148  by khaled al awadi
Ne base 07 march 2018 energy news issue 1148 by khaled al awadiKhaled Al Awadi
 
CRESPAI Presentation
CRESPAI PresentationCRESPAI Presentation
CRESPAI PresentationRamesh Goel
 
Global Renewables Transition Requires Dedicated ETRM Capabilities
Global Renewables Transition Requires Dedicated ETRM CapabilitiesGlobal Renewables Transition Requires Dedicated ETRM Capabilities
Global Renewables Transition Requires Dedicated ETRM CapabilitiesCTRM Center
 
Final Report - P2EBT Task Force_EN
Final Report - P2EBT Task Force_ENFinal Report - P2EBT Task Force_EN
Final Report - P2EBT Task Force_ENWilliam Sabandar
 

What's hot (20)

Energy Report - Strange Brew: Adapting to Changing Fundamentals
Energy Report - Strange Brew: Adapting to Changing FundamentalsEnergy Report - Strange Brew: Adapting to Changing Fundamentals
Energy Report - Strange Brew: Adapting to Changing Fundamentals
 
Energy policy aus
Energy policy ausEnergy policy aus
Energy policy aus
 
China energy roadmap slides
China energy roadmap slidesChina energy roadmap slides
China energy roadmap slides
 
Keynote address min at africa energy indaba feb 2019 1
Keynote address min at africa  energy indaba  feb 2019 1Keynote address min at africa  energy indaba  feb 2019 1
Keynote address min at africa energy indaba feb 2019 1
 
Budget 2020 Open Letter
Budget 2020 Open LetterBudget 2020 Open Letter
Budget 2020 Open Letter
 
Energy Policy Making in Iceland, With emphasis on geothermal energy utilization
Energy Policy Making in Iceland, With emphasis on geothermal energy utilizationEnergy Policy Making in Iceland, With emphasis on geothermal energy utilization
Energy Policy Making in Iceland, With emphasis on geothermal energy utilization
 
Nextera Energy University of Southern California Investment C
Nextera Energy University of Southern California Investment CNextera Energy University of Southern California Investment C
Nextera Energy University of Southern California Investment C
 
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
 
Energy and Natural Resources Cluster Strategy
Energy and Natural Resources Cluster StrategyEnergy and Natural Resources Cluster Strategy
Energy and Natural Resources Cluster Strategy
 
New base 680 special 06 september 2015
New base 680 special  06 september 2015New base 680 special  06 september 2015
New base 680 special 06 september 2015
 
Solar for-students
Solar for-studentsSolar for-students
Solar for-students
 
Extending and improving Ontario’s electricity demand management framework
Extending and improving Ontario’s electricity demand management frameworkExtending and improving Ontario’s electricity demand management framework
Extending and improving Ontario’s electricity demand management framework
 
Combined heat and power CHP _ ARES _ DOE
Combined heat and power  CHP _ ARES _ DOE Combined heat and power  CHP _ ARES _ DOE
Combined heat and power CHP _ ARES _ DOE
 
Spencer Ogden Brochure.Cfm
Spencer Ogden Brochure.CfmSpencer Ogden Brochure.Cfm
Spencer Ogden Brochure.Cfm
 
World Energy Inside - Febbraio 2017
World Energy Inside - Febbraio 2017World Energy Inside - Febbraio 2017
World Energy Inside - Febbraio 2017
 
Ne base 07 march 2018 energy news issue 1148 by khaled al awadi
Ne base 07 march 2018 energy news issue   1148  by khaled al awadiNe base 07 march 2018 energy news issue   1148  by khaled al awadi
Ne base 07 march 2018 energy news issue 1148 by khaled al awadi
 
CRESPAI Presentation
CRESPAI PresentationCRESPAI Presentation
CRESPAI Presentation
 
Global Renewables Transition Requires Dedicated ETRM Capabilities
Global Renewables Transition Requires Dedicated ETRM CapabilitiesGlobal Renewables Transition Requires Dedicated ETRM Capabilities
Global Renewables Transition Requires Dedicated ETRM Capabilities
 
Final Report - P2EBT Task Force_EN
Final Report - P2EBT Task Force_ENFinal Report - P2EBT Task Force_EN
Final Report - P2EBT Task Force_EN
 
Informe energía eólica AWEA (EEUU)
Informe energía eólica AWEA (EEUU)Informe energía eólica AWEA (EEUU)
Informe energía eólica AWEA (EEUU)
 

Similar to Australian Renewable Energy Target Progress Report - June 2016

Environment Magazine Feature
Environment Magazine FeatureEnvironment Magazine Feature
Environment Magazine FeatureNexus Publishing
 
Q4 2017 AES Corporation Earnings Conference Call
Q4 2017 AES Corporation Earnings Conference CallQ4 2017 AES Corporation Earnings Conference Call
Q4 2017 AES Corporation Earnings Conference CallAES_BigSky
 
02 27-18 fourth quarter & fy 2017 financial review final
02 27-18 fourth quarter & fy 2017 financial review final02 27-18 fourth quarter & fy 2017 financial review final
02 27-18 fourth quarter & fy 2017 financial review finalAES_BigSky
 
Intermittent Certainty Final
Intermittent Certainty FinalIntermittent Certainty Final
Intermittent Certainty FinalBertie Readhead
 
11 07 51st annual eei financial conference - original (appendix mw revised)
11 07 51st annual eei financial conference - original (appendix mw revised)11 07 51st annual eei financial conference - original (appendix mw revised)
11 07 51st annual eei financial conference - original (appendix mw revised)AES_BigSky
 
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms Resurgent India
 
AES Third Quarter 2016 Financial Review
AES Third Quarter 2016 Financial ReviewAES Third Quarter 2016 Financial Review
AES Third Quarter 2016 Financial ReviewAES_BigSky
 
11 04-16 third quarter 2016 financial review final (revised mw appendix)
11 04-16 third quarter 2016 financial review final (revised mw appendix)11 04-16 third quarter 2016 financial review final (revised mw appendix)
11 04-16 third quarter 2016 financial review final (revised mw appendix)AES_BigSky
 
Energy efficiency in the tennessee valley
Energy efficiency in the tennessee valleyEnergy efficiency in the tennessee valley
Energy efficiency in the tennessee valleyTNenergy
 
Summary of NETR Published by PWC - Sep 2023
Summary of NETR Published by PWC - Sep 2023Summary of NETR Published by PWC - Sep 2023
Summary of NETR Published by PWC - Sep 2023WeiCongTan4
 
06 14-18 jpm energy conference final
06 14-18 jpm energy conference final06 14-18 jpm energy conference final
06 14-18 jpm energy conference finalAES_BigSky
 
Terna 2017>2021 Enabling Energy Transition
Terna 2017>2021 Enabling Energy TransitionTerna 2017>2021 Enabling Energy Transition
Terna 2017>2021 Enabling Energy TransitionTerna SpA
 
OECD-ENV Vietnam questionnaire key points
OECD-ENV Vietnam questionnaire key pointsOECD-ENV Vietnam questionnaire key points
OECD-ENV Vietnam questionnaire key pointsOECD Environment
 
EERE’s FY2017 Renewable Power Budget Webinar
EERE’s FY2017 Renewable Power Budget WebinarEERE’s FY2017 Renewable Power Budget Webinar
EERE’s FY2017 Renewable Power Budget Webinarmaryvin
 
02 27-18 march investor presentation final
02 27-18 march investor presentation final02 27-18 march investor presentation final
02 27-18 march investor presentation finalAES_BigSky
 
Renewable Energy Sector Funding
Renewable Energy Sector FundingRenewable Energy Sector Funding
Renewable Energy Sector FundingResurgent India
 
Report: New England Energy Landscape Update
Report: New England Energy Landscape UpdateReport: New England Energy Landscape Update
Report: New England Energy Landscape UpdateMarcellus Drilling News
 
Bnef neo2015 executive-summary
Bnef neo2015 executive-summaryBnef neo2015 executive-summary
Bnef neo2015 executive-summaryDmitry Tseitlin
 

Similar to Australian Renewable Energy Target Progress Report - June 2016 (20)

Clean Energy Australia Report
Clean Energy Australia ReportClean Energy Australia Report
Clean Energy Australia Report
 
Environment Magazine Feature
Environment Magazine FeatureEnvironment Magazine Feature
Environment Magazine Feature
 
Q4 2017 AES Corporation Earnings Conference Call
Q4 2017 AES Corporation Earnings Conference CallQ4 2017 AES Corporation Earnings Conference Call
Q4 2017 AES Corporation Earnings Conference Call
 
02 27-18 fourth quarter & fy 2017 financial review final
02 27-18 fourth quarter & fy 2017 financial review final02 27-18 fourth quarter & fy 2017 financial review final
02 27-18 fourth quarter & fy 2017 financial review final
 
Intermittent Certainty Final
Intermittent Certainty FinalIntermittent Certainty Final
Intermittent Certainty Final
 
11 07 51st annual eei financial conference - original (appendix mw revised)
11 07 51st annual eei financial conference - original (appendix mw revised)11 07 51st annual eei financial conference - original (appendix mw revised)
11 07 51st annual eei financial conference - original (appendix mw revised)
 
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms
 
AES Third Quarter 2016 Financial Review
AES Third Quarter 2016 Financial ReviewAES Third Quarter 2016 Financial Review
AES Third Quarter 2016 Financial Review
 
11 04-16 third quarter 2016 financial review final (revised mw appendix)
11 04-16 third quarter 2016 financial review final (revised mw appendix)11 04-16 third quarter 2016 financial review final (revised mw appendix)
11 04-16 third quarter 2016 financial review final (revised mw appendix)
 
Energy efficiency in the tennessee valley
Energy efficiency in the tennessee valleyEnergy efficiency in the tennessee valley
Energy efficiency in the tennessee valley
 
Summary of NETR Published by PWC - Sep 2023
Summary of NETR Published by PWC - Sep 2023Summary of NETR Published by PWC - Sep 2023
Summary of NETR Published by PWC - Sep 2023
 
06 14-18 jpm energy conference final
06 14-18 jpm energy conference final06 14-18 jpm energy conference final
06 14-18 jpm energy conference final
 
Terna 2017>2021 Enabling Energy Transition
Terna 2017>2021 Enabling Energy TransitionTerna 2017>2021 Enabling Energy Transition
Terna 2017>2021 Enabling Energy Transition
 
OECD-ENV Vietnam questionnaire key points
OECD-ENV Vietnam questionnaire key pointsOECD-ENV Vietnam questionnaire key points
OECD-ENV Vietnam questionnaire key points
 
EERE’s FY2017 Renewable Power Budget Webinar
EERE’s FY2017 Renewable Power Budget WebinarEERE’s FY2017 Renewable Power Budget Webinar
EERE’s FY2017 Renewable Power Budget Webinar
 
02 27-18 march investor presentation final
02 27-18 march investor presentation final02 27-18 march investor presentation final
02 27-18 march investor presentation final
 
Renewable Energy Sector Funding
Renewable Energy Sector FundingRenewable Energy Sector Funding
Renewable Energy Sector Funding
 
Report: New England Energy Landscape Update
Report: New England Energy Landscape UpdateReport: New England Energy Landscape Update
Report: New England Energy Landscape Update
 
Bnef neo2015 executive-summary
Bnef neo2015 executive-summaryBnef neo2015 executive-summary
Bnef neo2015 executive-summary
 
Feature story in power today
Feature story in power todayFeature story in power today
Feature story in power today
 

More from Turlough Guerin GAICD FGIA

How to work with petroleum hydrocarbon suppliers to reduce and eliminate cont...
How to work with petroleum hydrocarbon suppliers to reduce and eliminate cont...How to work with petroleum hydrocarbon suppliers to reduce and eliminate cont...
How to work with petroleum hydrocarbon suppliers to reduce and eliminate cont...Turlough Guerin GAICD FGIA
 
Harvard x Course Notes - Technology Entrepreneurship: Lab to Market
Harvard x Course Notes - Technology Entrepreneurship: Lab to MarketHarvard x Course Notes - Technology Entrepreneurship: Lab to Market
Harvard x Course Notes - Technology Entrepreneurship: Lab to MarketTurlough Guerin GAICD FGIA
 
Using Telecommunications to Reduce Your Organisation's Carbon Footprint
Using Telecommunications to Reduce Your Organisation's Carbon FootprintUsing Telecommunications to Reduce Your Organisation's Carbon Footprint
Using Telecommunications to Reduce Your Organisation's Carbon FootprintTurlough Guerin GAICD FGIA
 
Precincts to Support the Delivery of Zero Energy
Precincts to Support the Delivery of Zero EnergyPrecincts to Support the Delivery of Zero Energy
Precincts to Support the Delivery of Zero EnergyTurlough Guerin GAICD FGIA
 
Are your sustainability projects resonating with the business?
Are your sustainability projects resonating with the business?Are your sustainability projects resonating with the business?
Are your sustainability projects resonating with the business?Turlough Guerin GAICD FGIA
 
Harvardx - Technology Entreprenuership - Lab to Market
Harvardx - Technology Entreprenuership - Lab to MarketHarvardx - Technology Entreprenuership - Lab to Market
Harvardx - Technology Entreprenuership - Lab to MarketTurlough Guerin GAICD FGIA
 
Foundations for Net Zero Target Setting Using a Science Based Approach
Foundations for Net Zero Target Setting Using a Science Based ApproachFoundations for Net Zero Target Setting Using a Science Based Approach
Foundations for Net Zero Target Setting Using a Science Based ApproachTurlough Guerin GAICD FGIA
 
Health of-the-australian-construction-industry-research-report
Health of-the-australian-construction-industry-research-reportHealth of-the-australian-construction-industry-research-report
Health of-the-australian-construction-industry-research-reportTurlough Guerin GAICD FGIA
 

More from Turlough Guerin GAICD FGIA (20)

Climate Risk Governance Guide
Climate Risk Governance GuideClimate Risk Governance Guide
Climate Risk Governance Guide
 
Australian Bushfire Climate Plan
Australian Bushfire Climate PlanAustralian Bushfire Climate Plan
Australian Bushfire Climate Plan
 
How to work with petroleum hydrocarbon suppliers to reduce and eliminate cont...
How to work with petroleum hydrocarbon suppliers to reduce and eliminate cont...How to work with petroleum hydrocarbon suppliers to reduce and eliminate cont...
How to work with petroleum hydrocarbon suppliers to reduce and eliminate cont...
 
Harvard x Course Notes - Technology Entrepreneurship: Lab to Market
Harvard x Course Notes - Technology Entrepreneurship: Lab to MarketHarvard x Course Notes - Technology Entrepreneurship: Lab to Market
Harvard x Course Notes - Technology Entrepreneurship: Lab to Market
 
The Rise of Megaprojects
The Rise of MegaprojectsThe Rise of Megaprojects
The Rise of Megaprojects
 
Using Telecommunications to Reduce Your Organisation's Carbon Footprint
Using Telecommunications to Reduce Your Organisation's Carbon FootprintUsing Telecommunications to Reduce Your Organisation's Carbon Footprint
Using Telecommunications to Reduce Your Organisation's Carbon Footprint
 
Bringing Embodied Carbon Upfront
Bringing Embodied Carbon UpfrontBringing Embodied Carbon Upfront
Bringing Embodied Carbon Upfront
 
A New Choice Australias Climate for Growth
A New Choice Australias Climate for GrowthA New Choice Australias Climate for Growth
A New Choice Australias Climate for Growth
 
Roadmap Reducing Food Waste
Roadmap Reducing Food WasteRoadmap Reducing Food Waste
Roadmap Reducing Food Waste
 
Building the Case-for Net Zero
Building the Case-for Net ZeroBuilding the Case-for Net Zero
Building the Case-for Net Zero
 
PWC State of Climate Tech 2020
PWC State of Climate Tech 2020PWC State of Climate Tech 2020
PWC State of Climate Tech 2020
 
First Low Emissions Technology Statement 2020
First Low Emissions Technology Statement 2020First Low Emissions Technology Statement 2020
First Low Emissions Technology Statement 2020
 
The Next Normal in Construction
The Next Normal in Construction The Next Normal in Construction
The Next Normal in Construction
 
Helping Australia Bounce Back
Helping Australia Bounce BackHelping Australia Bounce Back
Helping Australia Bounce Back
 
Sustainable Finance Industry Guide
Sustainable Finance Industry GuideSustainable Finance Industry Guide
Sustainable Finance Industry Guide
 
Precincts to Support the Delivery of Zero Energy
Precincts to Support the Delivery of Zero EnergyPrecincts to Support the Delivery of Zero Energy
Precincts to Support the Delivery of Zero Energy
 
Are your sustainability projects resonating with the business?
Are your sustainability projects resonating with the business?Are your sustainability projects resonating with the business?
Are your sustainability projects resonating with the business?
 
Harvardx - Technology Entreprenuership - Lab to Market
Harvardx - Technology Entreprenuership - Lab to MarketHarvardx - Technology Entreprenuership - Lab to Market
Harvardx - Technology Entreprenuership - Lab to Market
 
Foundations for Net Zero Target Setting Using a Science Based Approach
Foundations for Net Zero Target Setting Using a Science Based ApproachFoundations for Net Zero Target Setting Using a Science Based Approach
Foundations for Net Zero Target Setting Using a Science Based Approach
 
Health of-the-australian-construction-industry-research-report
Health of-the-australian-construction-industry-research-reportHealth of-the-australian-construction-industry-research-report
Health of-the-australian-construction-industry-research-report
 

Recently uploaded

Instant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School SpiritInstant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School Spiritegoetzinger
 
Lundin Gold April 2024 Corporate Presentation v4.pdf
Lundin Gold April 2024 Corporate Presentation v4.pdfLundin Gold April 2024 Corporate Presentation v4.pdf
Lundin Gold April 2024 Corporate Presentation v4.pdfAdnet Communications
 
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...Suhani Kapoor
 
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure serviceCall US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure servicePooja Nehwal
 
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779Delhi Call girls
 
03_Emmanuel Ndiaye_Degroof Petercam.pptx
03_Emmanuel Ndiaye_Degroof Petercam.pptx03_Emmanuel Ndiaye_Degroof Petercam.pptx
03_Emmanuel Ndiaye_Degroof Petercam.pptxFinTech Belgium
 
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130  Available With RoomVIP Kolkata Call Girl Serampore 👉 8250192130  Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Roomdivyansh0kumar0
 
Dividend Policy and Dividend Decision Theories.pptx
Dividend Policy and Dividend Decision Theories.pptxDividend Policy and Dividend Decision Theories.pptx
Dividend Policy and Dividend Decision Theories.pptxanshikagoel52
 
Q3 2024 Earnings Conference Call and Webcast Slides
Q3 2024 Earnings Conference Call and Webcast SlidesQ3 2024 Earnings Conference Call and Webcast Slides
Q3 2024 Earnings Conference Call and Webcast SlidesMarketing847413
 
Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024Bladex
 
Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...
Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...
Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...Pooja Nehwal
 
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Quarter 4- Module 3 Principles of Marketing
Quarter 4- Module 3 Principles of MarketingQuarter 4- Module 3 Principles of Marketing
Quarter 4- Module 3 Principles of MarketingMaristelaRamos12
 
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...ssifa0344
 
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130Suhani Kapoor
 
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...Call Girls in Nagpur High Profile
 
00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptx00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptxFinTech Belgium
 
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...makika9823
 

Recently uploaded (20)

Instant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School SpiritInstant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School Spirit
 
Lundin Gold April 2024 Corporate Presentation v4.pdf
Lundin Gold April 2024 Corporate Presentation v4.pdfLundin Gold April 2024 Corporate Presentation v4.pdf
Lundin Gold April 2024 Corporate Presentation v4.pdf
 
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
 
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure serviceCall US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
 
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
 
03_Emmanuel Ndiaye_Degroof Petercam.pptx
03_Emmanuel Ndiaye_Degroof Petercam.pptx03_Emmanuel Ndiaye_Degroof Petercam.pptx
03_Emmanuel Ndiaye_Degroof Petercam.pptx
 
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130  Available With RoomVIP Kolkata Call Girl Serampore 👉 8250192130  Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Room
 
Dividend Policy and Dividend Decision Theories.pptx
Dividend Policy and Dividend Decision Theories.pptxDividend Policy and Dividend Decision Theories.pptx
Dividend Policy and Dividend Decision Theories.pptx
 
Q3 2024 Earnings Conference Call and Webcast Slides
Q3 2024 Earnings Conference Call and Webcast SlidesQ3 2024 Earnings Conference Call and Webcast Slides
Q3 2024 Earnings Conference Call and Webcast Slides
 
Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024
 
Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...
Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...
Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...
 
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Quarter 4- Module 3 Principles of Marketing
Quarter 4- Module 3 Principles of MarketingQuarter 4- Module 3 Principles of Marketing
Quarter 4- Module 3 Principles of Marketing
 
Commercial Bank Economic Capsule - April 2024
Commercial Bank Economic Capsule - April 2024Commercial Bank Economic Capsule - April 2024
Commercial Bank Economic Capsule - April 2024
 
Veritas Interim Report 1 January–31 March 2024
Veritas Interim Report 1 January–31 March 2024Veritas Interim Report 1 January–31 March 2024
Veritas Interim Report 1 January–31 March 2024
 
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
 
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130
VIP Call Girls Service Dilsukhnagar Hyderabad Call +91-8250192130
 
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
 
00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptx00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptx
 
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
 

Australian Renewable Energy Target Progress Report - June 2016

  • 1. 1 PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET BRIEFING PAPER CLEAN ENERGY COUNCIL JUNE 2016
  • 2. PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 2 Investment confidence in Australia’s renewable energy sector has significantly improved following the legislation of the revised Large-scale Renewable Energy Target (LRET) in mid- 2015, a new Prime Minister that is more supportive of renewable energy and a strong outcome at the Paris climate change conference. The level and pace of investment will need to increase substantially in 2016 and 2017 in order for liable parties to deliver on the 2020 legislated target and obligation. The Clean Energy Regulator estimates that for this to happen, around 3000 MW of new renewable capacity should be committed in 2016. This paper outlines the status of progress towards delivering on the 2020 target of 33,000 GWh of new large-scale renewable energy generation. While there will be challenges, this paper finds that there is reason to be optimistic that the required new investment will be delivered within the required timeframe. The current situation is as follows: • In 2015 approximately 15,200 GWh of renewable energy was generated above the pre- 1997 baseline levels established under the Renewable Energy Target (RET) legislation. • To achieve the 33,000 GWh target, approximately 18,000 GWh of additional annual renewable energy generation needs to be produced by 2020. This will require around 6000 MW of new generation capacity and will create around $10 billion in new investment and thousands of jobs in rural and regional Australia. • Most analysts predict that the current surplus of Large-scale Generation Certificates (LGCs) will meet liabilities under the RET scheme for approximately two years. Noting it takes approximately two years from commercial close to construct and commission a new wind project – less for large scale solar – clearly there needs to be substantial progress throughout 2016 and 2017 in order for these liable parties to deliver on their future legislated obligation. • Approximately 11,000 MW of projects with planning approval, and projects adding up to a further 6000 MW of capacity are currently going through the planning approval process. More than enough projects are in the pipeline, ready to deliver the 33,000 GWh target by 2020. • While liable parties will seek to minimise their cost and commercial exposure in securing future LGC supply, they also have an obligation to ensure that they secure the necessary LGCs to meet their annual liability in compliance with the intent of the legislation. • While overall progress toward the target has not been as rapid as many would like, a range of developments have continued to improve confidence since mid-2015. Approximately 700 EXECUTIVE SUMMARY
  • 3. PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 3 MW has been committed towards the RET since the legislative change last year, with approximately 450 MW of new capacity committed in the past three months alone. Momentum is clearly building. • Investment in renewable energy is challenged by a number of factors outside of the control of the industry. A surplus of highly emission-intensive and aged power plants remain in the system due to the absence of a clear long-term policy for the electricity generation sector. The current RET policy has a target that peaks in 2020 (just four years away) and the scheme ends in 2030, which creates uncertainty with regard to long term merchant LGC prices. While these factors may create challenges, they do not change the fact that there is an obligation on liable parties under the legislation to secure LGCs to meet their liabilities through to 2030.
  • 4. PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 4 ____________________________________________________________ OVERVIEW OF THE LARGE-SCALE RENEWABLE ENERGY TARGET The Commonwealth Renewable Energy Target (RET) is critical to the deployment of renewable energy in Australia. It is split in two parts: • The Large Scale Renewable Energy Target (LRET) that requires 33,000 GWh of new generation annually from large scale renewable energy by 2020. • The Small-Scale Renewable Energy Scheme (SRES) that supports residential and small commercial renewable energy installations. After a protracted review, the LRET was amended and the target reduced in mid-2015 with the support of both major parties. While this restored policy certainty, negative comments related to renewable energy from then-Prime Minister Tony Abbott prolonged investment uncertainty for the sector. A change of Prime Minister in late 2015 and a strong outcome at the climate change conference in Paris in December 2015 finally provided the sector with greater long-term certainty. Minister for the Environment Greg Hunt’s strong assurances that the Federal Government will not make any further reductions to the target legislation and that liable parties are expected to comply with the policy have further improved investor confidence. It has taken some time for this confidence to flow to commercial transactions and ultimately the construction of new large-scale renewable energy projects. However there have been a number of Power Purchase Agreements (PPAs) signed this year, and capacity is also being built on a ‘merchant’ basis, selling into the electricity market without a PPA in place. ____________________________________________________________ CURRENT STATUS Australian renewable energy generation and capacity as at 31 December 2015 is summarised as follows. TABLE 1 SUMMARY OF RENEWABLE ENERGY CAPACITY AND GENERATION IN 2015 Technology Installed capacity (MW) Generation (GWh) Hydro 7800 14,046 (mostly pre-baseline) Wind 4187 11,802 Large-scale solar 224 303 Bioenergy 990 3200 Solar Thermal 9.3 27
  • 5. PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 5 Marine 0.24 0.5 Geothermal 0.12 0.50 Most of Australia’s hydro generation existed prior to the establishment of the RET. Under the legislation, generation from pre-existing hydro stations does not count towards the 33,000 GWh target, with the exception of generation that exceeds predetermined baselines. The 2015 target for the LRET was 18,850,000 LGCs, which is 18,850 GWh or 11.11 percent of electricity consumption1. Generation from above-baseline large-scale sources totals around 15,200 GWh. The actual number of LGCs surrendered to the Clean Energy Regulator was higher than this, noting that liable parties were able to use banked certificates (from prior years where supply was greater than demand) to meet 2015 legislated obligations. Analysis indicates that this banked surplus (combined with the existing annual generation) is sufficient to support liable parties in meeting obligations out to around 2017-2018. In March 2016 the Clean Energy Regulator announced that the combined compliance rate for the LRET and SRES for 2015 was 99.7 per cent. The regulator said: “Liable entities have complied with their obligations in recent years and it is pleasing to see this continue.” ____________________________________________________________ NEW GENERATION REQUIRED TO MEET THE RET To achieve the 33,000 GWh target, approximately 18,000 GWh of additional renewable energy generation needs to be produced annually by 2020. Based on current renewable energy technologies this will likely equate to around 6000 MW of new capacity, depending on the exact mix of technologies that will be deployed. This is likely to be predominantly from large-scale wind and large-scale solar along with commercial-scale solar (100 kW to 1 MW behind the meter installations). There is also likely to be some level of new generation from mini hydro power stations, upgrades and refurbishment of existing hydro power, bioenergy and a limited amount of ocean energy generation by 2020. Above-baseline hydro power generation is also expected to increase after the difficult, low-inflow conditions of 2015. ____________________________________________________________ THE CURRENT PROJECT PIPELINE As at May 2016 there is approximately 500 MW of wind capacity under construction, which will come online in 2016 and 2017, and 30 MW of large-scale solar under construction and expected to become operational in 2016. There is also a construction pipeline of commercial- scale solar projects between 100 kW and 1 MW that will contribute to the LRET target. 1 Clean Energy Regulator, Annual targets and the Renewable Power Percentage, 2016, Available online http://www.cleanenergyregulator.gov.au/RET/About-the-Renewable-Energy-Target/The-certificate- market/annual-targets-and-the-renewable-power-percentage
  • 6. PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 6 The following tables summarise the total development pipeline, showing 8000 MW of wind projects and 2585 MW of solar PV projects with development approval. It should be noted that there is likely to be substantial additional large-scale solar capacity in development, given these projects often do not need to go through statutory planning schemes (and therefore may not be captured in the below analysis). WIND State or Territory Under construction (MW) Approved (MW) In the approvals system (MW) Total (MW) VIC 239 1729 850 2818 NSW 175 2195 4835 7205 QLD 1045 345 1390 WA 1184 170 1354 SA 118 1565 453 2136 TAS 339 339 ACT NT TOTAL 532 8057 6653 15,242 SOLAR State or Territory Under construction (MW) Approved (MW) In the approvals system (MW) Total (MW) VIC 180 180 NSW 110 110 QLD 20 2280 2480 WA 10 10 SA TAS ACT 15 10 25 NT 1 1 TOTAL 31 2585 10 2626 It is clear from this summary that more than enough renewable energy projects are approved than are required to meet the LRET. Of course, not all approved projects will go ahead. Because the LRET is a market mechanism, only projects that can deliver the lowest cost renewable energy are likely to be constructed. Competitiveness is influenced by a combination of factors including resource quality, technology costs, electricity market conditions, network access and connection and the planning regime in particular jurisdictions.
  • 7. PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 7 ____________________________________________________________ PROGRESS TOWARDS 2020 While progress toward the target has not been as rapid as the industry would like since mid- 2015, a range of developments in the first half of 2016 has included: • Commencement of construction at the 175 MW White Rock wind farm in New South Wales in late April 2016. • Construction underway on the Ararat wind farm in western Victoria, with 80 MW of capacity sponsored by the ACT reverse auction and a further 160 MW being built under the RET scheme, with debt financing from the Clean Energy Financing Corporation. • The 56 MW Moree Solar Farm was opened in northern New South Wales, the second largest in Australia. Origin Energy issued a Power Purchase Agreement (PPA), to buy the electricity produced by the farm for a 15-year period. • The 100 MW Clare Solar Farm in Queensland has struck a Power Purchase Agreement with Origin Energy. Fotowatio Renewable Ventures (FRV) will commence construction in 2016, with operations expected to commence in 2017. The PPA will run for 13 years from the commencement of operations until December 2030. • The 175 MW Mt Emerald Wind Farm project in Queensland struck a 15-year PPA with Ergon Energy and is expected to commence construction in 2017. • AGL announced its Powering Australian Renewables Fund - a new entity tasked with funding a portfolio of new renewable energy projects, which AGL believes will add up to $2- 3 billion worth of investment that it expects will deliver about 1000 megawatts of new renewables. The company will contribute $200 million in equity and is seeking investment partners for the new fund. • A range of commercial-scale solar projects between 100kW and 1 MW that contribute towards the LRET scheme. Since the resolution of the RET in June 2015, approximately 1000 MW of renewable energy capacity has been committed or commenced construction, approximately 700 MW of which will contribute toward the RET scheme. The other 300 MW is supported by, and contributing to, the ACT reverse auction. Momentum is building and in the last three months alone, the White Rock Wind Farm, Clare Solar Farm and Mt Emerald Wind Farm announcements equate to approximately 450 MW of new capacity under the RET. While this progress has been positive for the renewable energy industry, the rate of new build is currently insufficient to meet the future liability. However, there are signs of substantial additional commitments throughout the year which will help to provide additional momentum. These potential projects include: • The City of Melbourne together with other local governments, cultural and educational institutions, and private-sector corporations has launched a competitive tender to purchase
  • 8. PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 8 110 GWh worth of energy from new large scale renewable energy facilities. The tender closes in June 2016. • The New South Wales Government tender for 137 GWh of renewable energy for its Sydney Metro Northwest rail project, which opened in January and closed in March 2016. • The Australian Renewable Energy Agency (ARENA) is running a large-scale solar funding round which has short-listed 22 projects and is expected to award a total of $100 million towards around 200 MW of large- scale solar capacity later in 2016. • Tenders or expression of interest processes are currently underway from a number of liable parties including Alinta Energy, Synergy and Ergon Energy. • A number of state governments have committed to increase the procurement of renewable energy. This includes Victoria’s tender for around 100 megawatts of new renewable energy projects, which closed in March 2016. ____________________________________________________________ STATUS OF LIABLE PARTIES The retail electricity market is dominated by a small number of market participants, which carry the majority of the overall retail load and therefore liability for the RET. Each of these participants have a current surplus of LGCs to meet some level of their future liability. Most analysts predict that the current surplus of LGCs will meet liabilities for approximately two years. Noting it takes approximately two years from commercial close to construct and commission a new wind project, and less for large-scale solar, clearly there needs to be substantial progress throughout 2016 in order for these liable parties to deliver on their future legislated obligation. The graph below shows the legislated certificate liability2 , and expected generation from existing assets, assets currently under construction, and approved assets. It also shows the expected surrender of banked certificates, with data from Green Energy Markets3 . The potential generation from approved wind and solar projects has been smoothed over three years, with a consistent build rate for 2018, 2019 and 2020. The graph illustrates that there is more approved capacity than required under the legislation. The smooth build rate is for illustrative purposes. In practical terms there is likely to be some level of variation in annual build rates over this period. There is clearly a large pipeline of approved projects, and the sector has strong capability and capacity to deliver materially higher levels of annual deployment. Substantial delays in committing new projects resulting in larger annual build rates in 2019 and 2020 could however 2 Clean Energy Regulator, 2015, Annual targets. Available online: http://www.cleanenergyregulator.gov.au/RET/About-the-Renewable-Energy-Target/The-certificate- market/The-renewable-power-percentage/Annual-targets 3 Green Energy Markets, 2015, Quarterly Renewables Report Q3 2015. Available online: http://greenmarkets.com.au/news-events/report-quarterly-renewables-report-q3-2015
  • 9. PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 9 result in some resource constraints that could impact the time and cost to deliver new projects. This risk can be minimised by liable parties ensuring that early progress is made in commitment and construction. Approximately 3000 MW of new large-scale projects are required to reach commercial close so that they can then commence construction by 2017 and begin generating LGCs by 2018. The LGC price has increased from around $30 during the RET review to over $80, reflecting the likely impending shortfall of LGCs. Based on prices achieved by the ACT’s reverse auctions, the LGC price is above the level required over the life of a contracted project to make it commercially viable. As outlined above, approximately 1000 MW of large scale renewable energy projects with planning approval are now awaiting commercial close in order to progress ton construction. Most project proponents will require some form of off-take or PPA that can provide certainty of revenue sufficient to warrant the substantial capital investment. Liable parties recognise the role of PPA’s in underpinning investment, with a long history of PPAs in various forms and tenor since the RET was first established in 2001. Understandably, liable parties will seek PPA forms and tenor that minimise their cost and commercial exposure. This is the nature of complex commercial negotiations between liable parties and project proponents. Fundamentally however, liable parties have an obligation to comply with the RET legislation and ensure that they secure the necessary annual LGC supply to meet their annual liability. If liable parties do not comply with their annual obligation they are required to pay a shortfall 0 5000000 10000000 15000000 20000000 25000000 30000000 35000000 40000000 45000000 50000000 2016 2017 2018 2019 2020 MWhorLGCs Renewable Energy Target and generation capacity Surplus certificates surrendered (according to Green Markets) Potential generation from approved projects - built over three years Expected generation from projects currently under construction Generation from existing assets LRET target
  • 10. PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 10 charge of $65 for each LGC they have failed to surrender. This is a tax exclusive amount, meaning that for a commercial business paying income tax, the tax effective penalty may be as high as $93. As such, a liable party might be better off from an economic perspective buying LGCs on the market for up to $93 each. The RET legislation also includes a make-good provision, whereby if a liable party has not complied in a given year, and rather paid the penalty, they can provide a valid LGC in the future (up to three years) and surrender this in return for the $65 penalty. ____________________________________________________________ RENEWABLE ENERGY INVESTMENT CHALLENGES Investment in renewable energy is challenged by a number of factors outside of the control of the industry. A surplus of highly emissions-intensive and aged power plants remain in operation due to the absence of a clear long-term policy for the electricity generation sector and the barriers to exit facing some of this plant. This creates a challenge for the commercial case for new renewable energy generation. The current RET policy has a target that peaks in 2020 (just four years away) and the scheme ends in 2030, which creates uncertainty with regard to long-term merchant LGC prices. Investors need confidence that the necessary revenue will be provided over that period to recover the capital cost of their investment. The sector has long advocated this challenge be addressed by: • An increase to the target beyond 2020. The current RET target peaks in 2020, and remains at that level until 2030. Forecasting the price of LGCs during this period is challenging, and therefore certainty of project revenue during this period is lower. This obviously makes the business case for projects more difficult as time goes on. The CEC has always advocated that the RET target should continue to increase at some level beyond 2020 to provide a stable growth pipeline and to allow the sector to mature and develop. An increasing role for renewable energy is consistent with emissions commitments from all major parties. For the sector to decarbonise, existing and additional zero-emissions generation will be increasingly important. A challenge for investors is how to quantify/access this value when faced with questions over the longer-term policy mix for the sector. • An extension of the RET beyond 2030 to provide long-term certainty. The RET scheme should continue to remain in place for 15 years after the peak of the target. For the current target, which peaks in 2020, the scheme should continue until 2035 in order to provide revenue support for projects committed towards the end of the growth trajectory. The longer- term revenue support will generally result in lower LGC prices – because the costs are recovered over a longer period – and therefore lower overall costs to consumers. One final challenge is the changing nature of the electricity market, and contracting arrangements with commercial and industrial electricity customers. These contracts are tending toward shorter tenures and with higher customer churn, creating some challenges for electricity retailers to anticipate their future LRET liability for this customer segment. These retail businesses are understandably cautious therefore in committing to long-term renewable energy projects and LGCs to meet this variable future liability. However, with increasing retail competition and LGC spot prices now materially above long-term contract prices, there is a
  • 11. PROGRESS AND STATUS OF THE RENEWABLE ENERGY TARGET 11 clear financial incentive for these retail businesses to enter into some form of longer-term LGC arrangement for all aspects of their customer liability. While these factors may currently create challenges, renewable energy is widely expected to have a strong and growing role in the Australian energy mix. The 33,000 GWh LRET has bipartisan support and places a legal obligation on liable parties to meet their share of the 2020 liability.