Flawless Project Delivery.ppt
1. Flawless Project Delivery
UEOD – UEQ Web: http://sww.pdo.shell.om/sites/UEOD/UEQ/default.aspx?CatID=14be6793-4ad7-4159-8213-0d842c3bd271
Published by: UEQ Department – In Pursuit of excellence
Flawless Project Delivery (FPD)
FPD programme utilizes systematic approach, based on lessons learned from past projects and aims to identify
the potential flaws, their root causes and develop/implement mitigating actions at respective project phases to
reduce negative impact of the flaws.
FPD Main Elements
FPD Road Map
FPD BEST PRACTICE EXAMPLES
FLAWLESS
PROCESS
DELIVERY MAP
FLAWLESS PROCESS
DELIVERY
DESCRIPTION
FLAWS AND
LESSONS
LEARNT
DATABASE
IMPLEMENTATION
ROAD MAP
Q
SPECIFICATIONS
KEY
PERFORMANCE
INDICATORS
NARRATIVE
SHEETS
Flaw:
Flaws are actual or potential problems that could
delay, or have an adverse impact on HSE,
production, quality, or costs, and subsequently impact
upon successful commissioning, start-up, and first-
cycle operation of new facilities.
Flaws are grouped into Q Areas, e. g.:
Q Area FPD KPI On
Targ
et
Above
Target
From To
External
Tightness
Number of leaks classified as High Risks (as per
Project RAM)
0 -
Start
of
pre-
comm
.
End
of
CSU
Internal
Tightness
Number of TSO Valves not meeting Tightness
Specification (ANSI Class V and VI only)
1 0
Ext. & Int.
Tightness
Number of days start-up was delayed due to
External or Internal Tightness Issues
1 <1
Cleanliness Number of days start-up was delayed due to
presence of Undesired Foreign Bodies
1 0
Mech. Static
Integrity
Number of days start-up was delayed due to Static
Equipment Failure
1 0
Novelty &
Complexity
Number of days start-up was delayed due to
troubles with known Novel Equipment
1 0
Number of newly emerging Novel Equipment (i.e.
during commissioning to start-up)
0 0
Number of days start-up was delayed due to lack of
understanding of Complex Systems
1 0
Oper. &
Maint’bility
No. O&M Tasks, as per agreed checklist that cannot
be performed as desired due to O&M factors
1 0
Typical KPI for FPD
DATA Base
Novelty and Complexity
Mitigation
• Early review and identification of
Complexity items
• Risk management of items
simplify
earlier / more testing
early training / simulator
Tightness
(Internal/External)
Mitigation
• Proper specifications during engineering
• Training / awareness
• Testing / Auditing with corresponding KPI’s
Q Area Examples
Company’s FPD Team
Responsible for agreeing
philosophies / targets /
standards, monitoring
progress.
Responsible for coordinating
between other Contractors (if
applicable)
Contractor’s FPD
Team
Responsible for delivering
FPD programme for
Contractor’s Scope, for
specific Q Areas, coordinating
relevant activities across
project team
UOP4 Team
Support, Coaching, Best Practices, Facilitate Workshops
FPD is part of Operation Readiness &
Assurance (OR&A) Process.
The process Owner of OR&A is: UOP4.
Related document is PR-1612: Procedure for
Operations Readiness & Assurance.
For Further information, see web reference:
FPD Roles & Responsibilities
Plant
Performance
CSU - first period of operation
Typical Plant
Performance
Curve over time
FPD Start-up and Operation
Target date for production
Reputation
HSE
$$$
PLANT PERFORMANCE AFTER COMPLETION: FPD
• Tightness
• Cleanliness
• Functional Integrity
• O&M
• HSE in transition
• Novelty & Complexity
• Testing
• Competence and exp.
• Coinciding events
• Information
http://sww-
orakle.shell.com/orakle/Homepage/Lib
rary/Tools/FLAWS/FLAWS-2_main.htm
Reference to Web:
Hans Rontetltap UOP4
Custodian of FPD Programme:
http://sww.pdo.shell.om/sites/UEOD/U
OP/OAP/default.aspx
Cleanliness
Mitigation
• Correct Equipment Hygiene
(storage, packaging, protection)
• Construction Hygiene
• Procedures for blowing / flushing
• Design to facilitate this
• Auditing with corresponding KPI’s
Brainstorm Flaw Register Q Plan
KPI
Progress
Reports
RAM
Processes &
Procedures
contains:
- List of Flaws/Risks
- Ranking
- Mitigating actions
- Action party
- Status
FPD
Management
System
Contracts
Relationship with Contract / Project
Quality Plan
FPD programme is described in Project /
Contract Quality Plan as one of the interface
programmes related to OR&A Process.