Evaluating Transportation
Alternatives
By: Renzo Rufin Polino
Evaluating Transportation Alternatives
The basic concept of an evaluation is simple and
straightforward, but the actual process itself can be
complex.
A transportation improvement can be viewed as a
mechanism for producing a result desired by a
society at a price.
The question is, “will the benefits of the project
be worth the cost?”
Evaluating Transportation Alternatives
The results of the “four-step demand forecasting
process” furnish the necessary input data to prepare
an evaluation of the relative worth of alternative
projects.
The objective of an evaluation is to furnish the
appropriate information about the outcome of each
alternative so that a selection can be made.
An essential input in the evaluation process is to
know what information will be important in making
project selection.
Evaluating Transportation Alternatives
In some instances, a single criterion may be
paramount (such as cost).
In other cases, there may be many objectives to
be achieved.
The decision maker may wish to have the relative
outcome of each alternative expressed as a single
number, whereas at other times, it may be more
helpful to see the results individually for each
criteria and each alternative.
Evaluating Transportation Alternatives
Evaluating Transportation Alternatives
Evaluation can also be made after a project is
completed to determine if the outcomes of the
project are as had been anticipated.
Post Factor evaluation can be very helpful in
formulating information useful for evaluating
similar projects elsewhere or in making
modifications in original designs.
Evaluating Transportation Alternatives
Identifying Project Stakeholders
Examples of groups (“stakeholders”) that could be
affected by a transportation project include
System users
Transportation management
Citizens in the community
Business
Local, state, and national government
Evaluating Transportation Alternatives
Identifying Project Stakeholders
For smaller projects, stakeholders will usually be limited to
the system users and transportation management.
A clear definition of whose viewpoint is being considered
in the evaluation is necessary.
A transportation project can affect these groups either
positively or negatively.
For example, a major project could increase business or
expanded construction activity could trigger an economic
boom in the area. The project might also require taking
of land, or it could create other environmental effects.
Evaluating Transportation Alternatives
Selecting Evaluation Criteria
A transportation project is intended to
accomplish one or more goals and objectives.
If the goal is to reduce accidents, the criteria can
be measured as the number of accidents expected
to occur for each of the alternativesconsidered.
If another goal is to improve mobility, the criteria
could be travel speed or travel time.
Evaluating Transportation Alternatives
Selecting Evaluation Criteria
Criteria selection is a basic element of the
evaluation process, because they become the basis
on which each project (alternative) is compared.
It is important that the criteria be related as
closely as possible to the stated objectives.
Criteria selected should be easy to measure and
sensitive to changes made in each alternative.
Evaluating Transportation Alternatives
Selecting Evaluation Criteria
It is better to limit the number of criteria to those
that will be most helpful in reaching a decision.
Too much information can be confusing and
counterproductive, and could create uncertainly and
could encourage a decision on political basis.
Evaluating Transportation Alternatives
Selecting Evaluation Criteria
Examples of Criteria Used for Evaluating Transportation
Alternatives
 Capital Costs
 Construction
 Right-of-way
 Vehicles
 Maintenance costs
 Facility operating costs
 Travel time cost
 Vehicle operating costs
 Accident costs
Evaluating Transportation Alternatives
Measures of Effectiveness (MOE)
The numerical or relative results for each criterion
are called Measures of Effectiveness (MOE).
It is necessary to decide how the MOEs will be
used in the evaluation process.
There are three different approaches.
Evaluating Transportation Alternatives
Measures of Effectiveness (MOE)
One approach is to convert each MOE to a common unit
(“money”), and then, for each alternative, compute the
summation for all measures (criteria).
For example, if the cost of an accident is known and the
value of travel time can be determined, then it would be
possible to compute a single number that would represent
the total cost of each alternative, since the costs of
construction, maintenance, and operation are already in
monetary terms.
Evaluating Transportation Alternatives
Measures of Effectiveness (MOE)
A second approach is to convert each measure of
effectiveness (MOE) to a numerical score.
For example, if a project alternatives does well in one
criterion, it is given a high score; if it does poorly in another
criterion, it is given a low score. A single number can be
calculated that represents the weighted average score of all
MOEs that were considered.
This approach is similar to calculating grades in a course!
Evaluating Transportation Alternatives
Measures of Effectiveness (MOE)
A third way is to identify the MOE for each alternative in
a matrix form, with no attempt to combine them.
This approach furnished the maximum amount of
information without prejudging wither how the MOE
should be combined or their relative importance.
Evaluating Transportation Alternatives
Evaluation Procedure and Decision Making
How well will the evaluation process assist in making a
decision?
The decision maker typically needs to know what the costs
of the project will be (in many instances this alone will
determine the outcome).
Another question may be, do the benefits justify the
expenditure of funds for transportation, or would the
money be better spent elsewhere?
It may be necessary to carry out a sensitivity analysis that
shows a range of values rather than a singlenumber.
Evaluating Transportation Alternatives
Evaluation Procedure and Decision Making
The decision maker may want to know the cost to
highway users as a result of travel delays during
construction.
Also of interest may be the length of time necessary to
finish the project, since public officials are often interested
in seeing work completed during their administration.
The source of funds for the project and othermatters
dealing with its implementation will also be of concern.
Thus, in addition to the fairly straightforward problem of
evaluation based on a selected set of measurable criteria, the
transportation engineer must be prepared to answer any and
all questions about the projects and its implications.
Evaluation Based On Economic Criteria
Elements of Cost
 The cost of a transportation facility improvement
includes two components
First Cost- engineering design, right-of-way, and
construction.
Continuing Cost- maintenance, operation, and
administration.
Evaluation Based On Economic Criteria
Elements of Cost
 Expenses for administration or other overhead charges
are usually excluded in an economic evaluation because
they will be incurred regardless of whether or not the
project is selected (sunk cost).
 Salvage value is the worth of an asset at the end of its
service life (usually considered in economic evaluation).
Evaluation Based On Economic Criteria
Elements of Cost
 Three commonly used measures of user costsare:
Vehicle operating costs
Travel time costs
costs of accidents
They are sometimes referred to as benefits since the
improvements to a transportation facility are likely to reduce
(lower) the cost of vehicle operation, cost of travel time,
and cost of accidents.
Evaluation Based On Economic Criteria
 Interaction Between Road User Costs and Highway
Geometric and Operational Factors
Economic Evaluation Methods
An economic evaluation of a transportation projectis
completed using one of the followingmethods:
Present Worth (PW)
Equivalent Uniform Annual Cost (EUAC)
Benefit-Cost Ratio (BCR)
Internal Rate of Return(ROR)
Economic Evaluation Methods
Present Worth (PW) is the most straightforward of the
methods, since it represents the current value of all costs
that will be incurred over the lifetime of theproject.
Net Present Worth (NPW) is the PW of a given cash flow
that has both receipts and disbursements.
Economic Evaluation Methods
NPW of a projectis:
Economic Evaluation Methods
Equivalent Uniform Annual Worth (EUAW) is a
conversion of a given cash flow to a series of equal annual
amounts. If the amounts are considered to occur at the end
of the interest period,then
Economic Evaluation Methods
Similarly,
Economic Evaluation Methods
The benefit-Cost Ratio (BCR) is a ratio of the PW of net project
benefits and net project costs.
The formula for BCR is:
Where,
B2/1 =
C2/1 =
reduction in user and operation costs between higher cost
alternative 2 and lower cost alternative 1, expressed as PW
or EUAB
increase in facility costs, expressed as PW or EUAC
If the BCR is 1 or greater, then the higher cost alternative is
economically attractive. If BCR is less than 1, this alternative isdiscarded.
2/1
2/1
C
BCR 
B2 /1
Economic Evaluation Methods
Internal Rate of Return (ROR) method determines the
interest rate at which the PW of reductions in user and
operation costs B2/1 equals the PW of increases in facility
costs C2/1.
If the ROR exceeds the interest rate, the higher cost
project is retained. If the ROR is less than the interest rate,
the higher cost project is eliminated.
The procedure for comparison is similar to that used in
the BCR method.
Economic Evaluation Methods
Illustration
The department of traffic is considering three improvement plans for a heavily
traveled intersection within the city. The improvement is expected to achieve
three objectives: improve travel speeds, increase safety, and reduce operating
expenses for drivers. The annual dollar value of savings compared with existing
conditions for each criterion as well as additional construction and maintenance
costs is shown in as follows. If the economic life of the road is considered to be
50 years and the discount (interest) rate is 3%, which alternative should be
selected?
Economic Evaluation Methods
Illustration
Economic Evaluation Methods
Illustration
Economic Evaluation Methods
Illustration
Economic Evaluation Methods
Illustration
34
Economic Evaluation Methods
Illustration
35
• Solve by ROR Method:
(in this situation, we solve for the
interest rate for which NPW = 0
1. Compute ROR for alternative I versus DN:
NPW= 0 = -185,000 + (-1500+5000+3000+500)(P/A-i-50)
(P/A-i-50) = 185000/7000 = 26.428
{(1+i)50 – 1}/i(1+i)50 = 26.428
Solving, i = 2.6%
► Since ROR is less than 3%, we discard alternative I.
Economic Evaluation Methods
Illustration
• Solve by ROR Method: (in this situation, we
solve for the interest rate for which NPW = 0
2. Compute ROR for alternative II versus DN:
NPW= 0 = -220,000 + (-2500+5000+6500+500)(P/A-i-50)
(P/A-i-50) = 220000/9500 = 23.16
{(1+i)50 – 1}/i(1+i)50 = 23.16
Solving, i = 3.6%
► Since ROR is greater than 3%, we select alternative II over
DN.
Economic Evaluation Methods
Illustration
37
• Solve by ROR Method: (in this situation, we solve
for the interest rate for which NPW = 0
3. Compute ROR for alternative III versus alternative II:
NPW= 0 = -(310,000-220,000) + (12,800-9,500)(P/A-i-50)
(P/A-i-50) = 90000/3300 = 27.27
{(1+i)50 – 1}/i(1+i)50 = 27.27
Solving, i = 2.7%
► Since the increased investment in alternative III yields an ROR
less than 3%, we do not select alternative III,
but again pick alternative II.
THE END

More Related Content

What's hot

10 Capacity and LOS Analysis for Freeway (Traffic Engineering هندسة المرور & ...
10 Capacity and LOS Analysis for Freeway (Traffic Engineering هندسة المرور & ...10 Capacity and LOS Analysis for Freeway (Traffic Engineering هندسة المرور & ...
10 Capacity and LOS Analysis for Freeway (Traffic Engineering هندسة المرور & ...Hossam Shafiq I
 
Growth Factor Method of Trip Generation
Growth Factor Method of Trip GenerationGrowth Factor Method of Trip Generation
Growth Factor Method of Trip GenerationSibesh Singh
 
3-Trip Generation-Distribution ( Transportation and Traffic Engineering Dr. S...
3-Trip Generation-Distribution ( Transportation and Traffic Engineering Dr. S...3-Trip Generation-Distribution ( Transportation and Traffic Engineering Dr. S...
3-Trip Generation-Distribution ( Transportation and Traffic Engineering Dr. S...Hossam Shafiq I
 
Highway route location
Highway route locationHighway route location
Highway route locationwrya hade
 
Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineeringPralhad Kore
 
Four-stage Sequential Planning
Four-stage Sequential PlanningFour-stage Sequential Planning
Four-stage Sequential PlanningKaranParmar386528
 
Traffic enginering highway capacity and los print mood publish
Traffic enginering highway capacity and los print mood publishTraffic enginering highway capacity and los print mood publish
Traffic enginering highway capacity and los print mood publishGizaw Mekonnen
 
Chapter 8 travel demand
Chapter 8 travel demandChapter 8 travel demand
Chapter 8 travel demandDharmes Patel
 
Freeway & Highway LOS (Transportation Engineering)
Freeway & Highway LOS (Transportation Engineering)Freeway & Highway LOS (Transportation Engineering)
Freeway & Highway LOS (Transportation Engineering)Hossam Shafiq I
 
L19 Basic Freeway and Multilane Segments
L19 Basic Freeway and Multilane Segments L19 Basic Freeway and Multilane Segments
L19 Basic Freeway and Multilane Segments Hossam Shafiq I
 
Highway Geometric Design control and criteria-2
Highway Geometric Design control and criteria-2Highway Geometric Design control and criteria-2
Highway Geometric Design control and criteria-2Muhammad Faisal
 
Traffic Volume Studies
Traffic Volume StudiesTraffic Volume Studies
Traffic Volume StudiesMd Tanvir Alam
 
maintenance and rehabilitation of pavements by Roshan .ppt
maintenance and rehabilitation of pavements by Roshan .pptmaintenance and rehabilitation of pavements by Roshan .ppt
maintenance and rehabilitation of pavements by Roshan .pptRoshani Shahi
 
Horizontal alignment of Roads
Horizontal alignment of RoadsHorizontal alignment of Roads
Horizontal alignment of RoadsLatif Hyder Wadho
 
Introduction to highway engineering
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineeringAavani Thampi
 

What's hot (20)

Trip generation
Trip generationTrip generation
Trip generation
 
10 Capacity and LOS Analysis for Freeway (Traffic Engineering هندسة المرور & ...
10 Capacity and LOS Analysis for Freeway (Traffic Engineering هندسة المرور & ...10 Capacity and LOS Analysis for Freeway (Traffic Engineering هندسة المرور & ...
10 Capacity and LOS Analysis for Freeway (Traffic Engineering هندسة المرور & ...
 
Growth Factor Method of Trip Generation
Growth Factor Method of Trip GenerationGrowth Factor Method of Trip Generation
Growth Factor Method of Trip Generation
 
3-Trip Generation-Distribution ( Transportation and Traffic Engineering Dr. S...
3-Trip Generation-Distribution ( Transportation and Traffic Engineering Dr. S...3-Trip Generation-Distribution ( Transportation and Traffic Engineering Dr. S...
3-Trip Generation-Distribution ( Transportation and Traffic Engineering Dr. S...
 
Highway route location
Highway route locationHighway route location
Highway route location
 
TRANSPORT SUPPLY AND DEMAND
TRANSPORT SUPPLY AND DEMANDTRANSPORT SUPPLY AND DEMAND
TRANSPORT SUPPLY AND DEMAND
 
Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineering
 
Four-stage Sequential Planning
Four-stage Sequential PlanningFour-stage Sequential Planning
Four-stage Sequential Planning
 
Traffic speed study
Traffic speed studyTraffic speed study
Traffic speed study
 
04 transport modelling
04 transport modelling04 transport modelling
04 transport modelling
 
Intersection designs ppt
Intersection designs pptIntersection designs ppt
Intersection designs ppt
 
Traffic enginering highway capacity and los print mood publish
Traffic enginering highway capacity and los print mood publishTraffic enginering highway capacity and los print mood publish
Traffic enginering highway capacity and los print mood publish
 
Chapter 8 travel demand
Chapter 8 travel demandChapter 8 travel demand
Chapter 8 travel demand
 
Freeway & Highway LOS (Transportation Engineering)
Freeway & Highway LOS (Transportation Engineering)Freeway & Highway LOS (Transportation Engineering)
Freeway & Highway LOS (Transportation Engineering)
 
L19 Basic Freeway and Multilane Segments
L19 Basic Freeway and Multilane Segments L19 Basic Freeway and Multilane Segments
L19 Basic Freeway and Multilane Segments
 
Highway Geometric Design control and criteria-2
Highway Geometric Design control and criteria-2Highway Geometric Design control and criteria-2
Highway Geometric Design control and criteria-2
 
Traffic Volume Studies
Traffic Volume StudiesTraffic Volume Studies
Traffic Volume Studies
 
maintenance and rehabilitation of pavements by Roshan .ppt
maintenance and rehabilitation of pavements by Roshan .pptmaintenance and rehabilitation of pavements by Roshan .ppt
maintenance and rehabilitation of pavements by Roshan .ppt
 
Horizontal alignment of Roads
Horizontal alignment of RoadsHorizontal alignment of Roads
Horizontal alignment of Roads
 
Introduction to highway engineering
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineering
 

Similar to 428096463-EVALUATING-TRANSPORTATION-ALTERNATIVES-ppt-pptx.pptx

PUBLIC PRIVATE PARTNERSHIP MANAGEMENT-Module.pptx
PUBLIC PRIVATE PARTNERSHIP MANAGEMENT-Module.pptxPUBLIC PRIVATE PARTNERSHIP MANAGEMENT-Module.pptx
PUBLIC PRIVATE PARTNERSHIP MANAGEMENT-Module.pptxkipkorirkoech5
 
COST-BENEFIT ANALYSIS (2010)-1.ppt
COST-BENEFIT ANALYSIS (2010)-1.pptCOST-BENEFIT ANALYSIS (2010)-1.ppt
COST-BENEFIT ANALYSIS (2010)-1.pptNamanyaBetrum1
 
Strategic cost management
Strategic cost managementStrategic cost management
Strategic cost managementVaibhav Banjan
 
Cost benefit analysis
Cost benefit analysisCost benefit analysis
Cost benefit analysisaryan_raj
 
A Model for Life-Cycle Benefit and Cost Analysis
A Model for Life-Cycle Benefit and Cost AnalysisA Model for Life-Cycle Benefit and Cost Analysis
A Model for Life-Cycle Benefit and Cost AnalysisSadegh Tabatabaei
 
A consistent method to determine flexible criteria weights
A consistent method to determine flexible criteria weightsA consistent method to determine flexible criteria weights
A consistent method to determine flexible criteria weightsarmankoopal
 
Project Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project EstimationProject Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project EstimationVandalRay
 
6 ECON ANalysis for project appraisal.pdf
6 ECON ANalysis for project appraisal.pdf6 ECON ANalysis for project appraisal.pdf
6 ECON ANalysis for project appraisal.pdfTanmay209179
 
Assetmanagement
AssetmanagementAssetmanagement
AssetmanagementBarry Hol
 
Cost benefit analysis of resources
Cost benefit analysis of resourcesCost benefit analysis of resources
Cost benefit analysis of resourcesAl Jubaer
 
11822, 1017 AM Estimating and Managing Costshttpsleo
11822, 1017 AM Estimating and Managing Costshttpsleo11822, 1017 AM Estimating and Managing Costshttpsleo
11822, 1017 AM Estimating and Managing CostshttpsleoSantosConleyha
 
11822, 1017 AM Estimating and Managing Costshttpsleo
11822, 1017 AM Estimating and Managing Costshttpsleo11822, 1017 AM Estimating and Managing Costshttpsleo
11822, 1017 AM Estimating and Managing CostshttpsleoBenitoSumpter862
 
Linear modeling in Transportation problem: Need of reliable Public transporta...
Linear modeling in Transportation problem: Need of reliable Public transporta...Linear modeling in Transportation problem: Need of reliable Public transporta...
Linear modeling in Transportation problem: Need of reliable Public transporta...IOSR Journals
 
Cost benefit and cost effective analysis
Cost benefit and cost effective analysis Cost benefit and cost effective analysis
Cost benefit and cost effective analysis Mohamed Sheikh Omar
 
International Journal of Business and Management Invention (IJBMI)
International Journal of Business and Management Invention (IJBMI)International Journal of Business and Management Invention (IJBMI)
International Journal of Business and Management Invention (IJBMI)inventionjournals
 
Parsimonious Best Worst Method
Parsimonious Best Worst MethodParsimonious Best Worst Method
Parsimonious Best Worst MethodBME
 
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...IOSR Journals
 
project cost management.pptx
project cost management.pptxproject cost management.pptx
project cost management.pptxInayatSheikh1
 

Similar to 428096463-EVALUATING-TRANSPORTATION-ALTERNATIVES-ppt-pptx.pptx (20)

PUBLIC PRIVATE PARTNERSHIP MANAGEMENT-Module.pptx
PUBLIC PRIVATE PARTNERSHIP MANAGEMENT-Module.pptxPUBLIC PRIVATE PARTNERSHIP MANAGEMENT-Module.pptx
PUBLIC PRIVATE PARTNERSHIP MANAGEMENT-Module.pptx
 
COST-BENEFIT ANALYSIS (2010)-1.ppt
COST-BENEFIT ANALYSIS (2010)-1.pptCOST-BENEFIT ANALYSIS (2010)-1.ppt
COST-BENEFIT ANALYSIS (2010)-1.ppt
 
Strategic cost management
Strategic cost managementStrategic cost management
Strategic cost management
 
Cost benefit analysis
Cost benefit analysisCost benefit analysis
Cost benefit analysis
 
A Model for Life-Cycle Benefit and Cost Analysis
A Model for Life-Cycle Benefit and Cost AnalysisA Model for Life-Cycle Benefit and Cost Analysis
A Model for Life-Cycle Benefit and Cost Analysis
 
A consistent method to determine flexible criteria weights
A consistent method to determine flexible criteria weightsA consistent method to determine flexible criteria weights
A consistent method to determine flexible criteria weights
 
Project Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project EstimationProject Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project Estimation
 
6 ECON ANalysis for project appraisal.pdf
6 ECON ANalysis for project appraisal.pdf6 ECON ANalysis for project appraisal.pdf
6 ECON ANalysis for project appraisal.pdf
 
Assetmanagement
AssetmanagementAssetmanagement
Assetmanagement
 
Cost benefit analysis of resources
Cost benefit analysis of resourcesCost benefit analysis of resources
Cost benefit analysis of resources
 
11822, 1017 AM Estimating and Managing Costshttpsleo
11822, 1017 AM Estimating and Managing Costshttpsleo11822, 1017 AM Estimating and Managing Costshttpsleo
11822, 1017 AM Estimating and Managing Costshttpsleo
 
11822, 1017 AM Estimating and Managing Costshttpsleo
11822, 1017 AM Estimating and Managing Costshttpsleo11822, 1017 AM Estimating and Managing Costshttpsleo
11822, 1017 AM Estimating and Managing Costshttpsleo
 
Linear modeling in Transportation problem: Need of reliable Public transporta...
Linear modeling in Transportation problem: Need of reliable Public transporta...Linear modeling in Transportation problem: Need of reliable Public transporta...
Linear modeling in Transportation problem: Need of reliable Public transporta...
 
Cost benefit and cost effective analysis
Cost benefit and cost effective analysis Cost benefit and cost effective analysis
Cost benefit and cost effective analysis
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
Evaluation workshop DfT June2014
Evaluation workshop DfT June2014Evaluation workshop DfT June2014
Evaluation workshop DfT June2014
 
International Journal of Business and Management Invention (IJBMI)
International Journal of Business and Management Invention (IJBMI)International Journal of Business and Management Invention (IJBMI)
International Journal of Business and Management Invention (IJBMI)
 
Parsimonious Best Worst Method
Parsimonious Best Worst MethodParsimonious Best Worst Method
Parsimonious Best Worst Method
 
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
 
project cost management.pptx
project cost management.pptxproject cost management.pptx
project cost management.pptx
 

Recently uploaded

UNIT-III-TRANSMISSION SYSTEMS REAR AXLES
UNIT-III-TRANSMISSION SYSTEMS REAR AXLESUNIT-III-TRANSMISSION SYSTEMS REAR AXLES
UNIT-III-TRANSMISSION SYSTEMS REAR AXLESDineshKumar4165
 
办理埃默里大学毕业证Emory毕业证原版一比一
办理埃默里大学毕业证Emory毕业证原版一比一办理埃默里大学毕业证Emory毕业证原版一比一
办理埃默里大学毕业证Emory毕业证原版一比一mkfnjj
 
Russian Call Girls Delhi Indirapuram {9711199171} Aarvi Gupta ✌️Independent ...
Russian  Call Girls Delhi Indirapuram {9711199171} Aarvi Gupta ✌️Independent ...Russian  Call Girls Delhi Indirapuram {9711199171} Aarvi Gupta ✌️Independent ...
Russian Call Girls Delhi Indirapuram {9711199171} Aarvi Gupta ✌️Independent ...shivangimorya083
 
(办理学位证)墨尔本大学毕业证(Unimelb毕业证书)成绩单留信学历认证原版一模一样
(办理学位证)墨尔本大学毕业证(Unimelb毕业证书)成绩单留信学历认证原版一模一样(办理学位证)墨尔本大学毕业证(Unimelb毕业证书)成绩单留信学历认证原版一模一样
(办理学位证)墨尔本大学毕业证(Unimelb毕业证书)成绩单留信学历认证原版一模一样whjjkkk
 
BLUE VEHICLES the kids picture show 2024
BLUE VEHICLES the kids picture show 2024BLUE VEHICLES the kids picture show 2024
BLUE VEHICLES the kids picture show 2024AHOhOops1
 
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhi
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhiHauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhi
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhiHot Call Girls In Sector 58 (Noida)
 
如何办理(UC毕业证书)堪培拉大学毕业证毕业证成绩单原版一比一
如何办理(UC毕业证书)堪培拉大学毕业证毕业证成绩单原版一比一如何办理(UC毕业证书)堪培拉大学毕业证毕业证成绩单原版一比一
如何办理(UC毕业证书)堪培拉大学毕业证毕业证成绩单原版一比一fjjwgk
 
定制昆士兰大学毕业证(本硕)UQ学位证书原版一比一
定制昆士兰大学毕业证(本硕)UQ学位证书原版一比一定制昆士兰大学毕业证(本硕)UQ学位证书原版一比一
定制昆士兰大学毕业证(本硕)UQ学位证书原版一比一fjjhfuubb
 
What Could Cause A VW Tiguan's Radiator Fan To Stop Working
What Could Cause A VW Tiguan's Radiator Fan To Stop WorkingWhat Could Cause A VW Tiguan's Radiator Fan To Stop Working
What Could Cause A VW Tiguan's Radiator Fan To Stop WorkingEscondido German Auto
 
2024 TOP 10 most fuel-efficient vehicles according to the US agency
2024 TOP 10 most fuel-efficient vehicles according to the US agency2024 TOP 10 most fuel-efficient vehicles according to the US agency
2024 TOP 10 most fuel-efficient vehicles according to the US agencyHyundai Motor Group
 
( Best ) Genuine Call Girls In Mandi House =DELHI-| 8377087607
( Best ) Genuine Call Girls In Mandi House =DELHI-| 8377087607( Best ) Genuine Call Girls In Mandi House =DELHI-| 8377087607
( Best ) Genuine Call Girls In Mandi House =DELHI-| 8377087607dollysharma2066
 
Call Girls in Karachi | +923081633338 | Karachi Call Girls
Call Girls in Karachi  | +923081633338 | Karachi Call GirlsCall Girls in Karachi  | +923081633338 | Karachi Call Girls
Call Girls in Karachi | +923081633338 | Karachi Call GirlsAyesha Khan
 
GREEN VEHICLES the kids picture show 2024
GREEN VEHICLES the kids picture show 2024GREEN VEHICLES the kids picture show 2024
GREEN VEHICLES the kids picture show 2024AHOhOops1
 
FULL ENJOY - 9953040155 Call Girls in Sector 61 | Noida
FULL ENJOY - 9953040155 Call Girls in Sector 61 | NoidaFULL ENJOY - 9953040155 Call Girls in Sector 61 | Noida
FULL ENJOY - 9953040155 Call Girls in Sector 61 | NoidaMalviyaNagarCallGirl
 
Innovating Manufacturing with CNC Technology
Innovating Manufacturing with CNC TechnologyInnovating Manufacturing with CNC Technology
Innovating Manufacturing with CNC Technologyquickpartslimitlessm
 
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证jjrehjwj11gg
 
2024 WRC Hyundai World Rally Team’s i20 N Rally1 Hybrid
2024 WRC Hyundai World Rally Team’s i20 N Rally1 Hybrid2024 WRC Hyundai World Rally Team’s i20 N Rally1 Hybrid
2024 WRC Hyundai World Rally Team’s i20 N Rally1 HybridHyundai Motor Group
 
UNOSAFE ELEVATOR PRIVATE LTD BANGALORE BROUCHER
UNOSAFE ELEVATOR PRIVATE LTD BANGALORE BROUCHERUNOSAFE ELEVATOR PRIVATE LTD BANGALORE BROUCHER
UNOSAFE ELEVATOR PRIVATE LTD BANGALORE BROUCHERunosafeads
 
如何办理(Flinders毕业证)查理斯特大学毕业证毕业证成绩单原版一比一
如何办理(Flinders毕业证)查理斯特大学毕业证毕业证成绩单原版一比一如何办理(Flinders毕业证)查理斯特大学毕业证毕业证成绩单原版一比一
如何办理(Flinders毕业证)查理斯特大学毕业证毕业证成绩单原版一比一ypfy7p5ld
 
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样umasea
 

Recently uploaded (20)

UNIT-III-TRANSMISSION SYSTEMS REAR AXLES
UNIT-III-TRANSMISSION SYSTEMS REAR AXLESUNIT-III-TRANSMISSION SYSTEMS REAR AXLES
UNIT-III-TRANSMISSION SYSTEMS REAR AXLES
 
办理埃默里大学毕业证Emory毕业证原版一比一
办理埃默里大学毕业证Emory毕业证原版一比一办理埃默里大学毕业证Emory毕业证原版一比一
办理埃默里大学毕业证Emory毕业证原版一比一
 
Russian Call Girls Delhi Indirapuram {9711199171} Aarvi Gupta ✌️Independent ...
Russian  Call Girls Delhi Indirapuram {9711199171} Aarvi Gupta ✌️Independent ...Russian  Call Girls Delhi Indirapuram {9711199171} Aarvi Gupta ✌️Independent ...
Russian Call Girls Delhi Indirapuram {9711199171} Aarvi Gupta ✌️Independent ...
 
(办理学位证)墨尔本大学毕业证(Unimelb毕业证书)成绩单留信学历认证原版一模一样
(办理学位证)墨尔本大学毕业证(Unimelb毕业证书)成绩单留信学历认证原版一模一样(办理学位证)墨尔本大学毕业证(Unimelb毕业证书)成绩单留信学历认证原版一模一样
(办理学位证)墨尔本大学毕业证(Unimelb毕业证书)成绩单留信学历认证原版一模一样
 
BLUE VEHICLES the kids picture show 2024
BLUE VEHICLES the kids picture show 2024BLUE VEHICLES the kids picture show 2024
BLUE VEHICLES the kids picture show 2024
 
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhi
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhiHauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhi
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhi
 
如何办理(UC毕业证书)堪培拉大学毕业证毕业证成绩单原版一比一
如何办理(UC毕业证书)堪培拉大学毕业证毕业证成绩单原版一比一如何办理(UC毕业证书)堪培拉大学毕业证毕业证成绩单原版一比一
如何办理(UC毕业证书)堪培拉大学毕业证毕业证成绩单原版一比一
 
定制昆士兰大学毕业证(本硕)UQ学位证书原版一比一
定制昆士兰大学毕业证(本硕)UQ学位证书原版一比一定制昆士兰大学毕业证(本硕)UQ学位证书原版一比一
定制昆士兰大学毕业证(本硕)UQ学位证书原版一比一
 
What Could Cause A VW Tiguan's Radiator Fan To Stop Working
What Could Cause A VW Tiguan's Radiator Fan To Stop WorkingWhat Could Cause A VW Tiguan's Radiator Fan To Stop Working
What Could Cause A VW Tiguan's Radiator Fan To Stop Working
 
2024 TOP 10 most fuel-efficient vehicles according to the US agency
2024 TOP 10 most fuel-efficient vehicles according to the US agency2024 TOP 10 most fuel-efficient vehicles according to the US agency
2024 TOP 10 most fuel-efficient vehicles according to the US agency
 
( Best ) Genuine Call Girls In Mandi House =DELHI-| 8377087607
( Best ) Genuine Call Girls In Mandi House =DELHI-| 8377087607( Best ) Genuine Call Girls In Mandi House =DELHI-| 8377087607
( Best ) Genuine Call Girls In Mandi House =DELHI-| 8377087607
 
Call Girls in Karachi | +923081633338 | Karachi Call Girls
Call Girls in Karachi  | +923081633338 | Karachi Call GirlsCall Girls in Karachi  | +923081633338 | Karachi Call Girls
Call Girls in Karachi | +923081633338 | Karachi Call Girls
 
GREEN VEHICLES the kids picture show 2024
GREEN VEHICLES the kids picture show 2024GREEN VEHICLES the kids picture show 2024
GREEN VEHICLES the kids picture show 2024
 
FULL ENJOY - 9953040155 Call Girls in Sector 61 | Noida
FULL ENJOY - 9953040155 Call Girls in Sector 61 | NoidaFULL ENJOY - 9953040155 Call Girls in Sector 61 | Noida
FULL ENJOY - 9953040155 Call Girls in Sector 61 | Noida
 
Innovating Manufacturing with CNC Technology
Innovating Manufacturing with CNC TechnologyInnovating Manufacturing with CNC Technology
Innovating Manufacturing with CNC Technology
 
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证
 
2024 WRC Hyundai World Rally Team’s i20 N Rally1 Hybrid
2024 WRC Hyundai World Rally Team’s i20 N Rally1 Hybrid2024 WRC Hyundai World Rally Team’s i20 N Rally1 Hybrid
2024 WRC Hyundai World Rally Team’s i20 N Rally1 Hybrid
 
UNOSAFE ELEVATOR PRIVATE LTD BANGALORE BROUCHER
UNOSAFE ELEVATOR PRIVATE LTD BANGALORE BROUCHERUNOSAFE ELEVATOR PRIVATE LTD BANGALORE BROUCHER
UNOSAFE ELEVATOR PRIVATE LTD BANGALORE BROUCHER
 
如何办理(Flinders毕业证)查理斯特大学毕业证毕业证成绩单原版一比一
如何办理(Flinders毕业证)查理斯特大学毕业证毕业证成绩单原版一比一如何办理(Flinders毕业证)查理斯特大学毕业证毕业证成绩单原版一比一
如何办理(Flinders毕业证)查理斯特大学毕业证毕业证成绩单原版一比一
 
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样
 

428096463-EVALUATING-TRANSPORTATION-ALTERNATIVES-ppt-pptx.pptx

  • 2. Evaluating Transportation Alternatives The basic concept of an evaluation is simple and straightforward, but the actual process itself can be complex. A transportation improvement can be viewed as a mechanism for producing a result desired by a society at a price. The question is, “will the benefits of the project be worth the cost?”
  • 3. Evaluating Transportation Alternatives The results of the “four-step demand forecasting process” furnish the necessary input data to prepare an evaluation of the relative worth of alternative projects. The objective of an evaluation is to furnish the appropriate information about the outcome of each alternative so that a selection can be made. An essential input in the evaluation process is to know what information will be important in making project selection.
  • 4. Evaluating Transportation Alternatives In some instances, a single criterion may be paramount (such as cost). In other cases, there may be many objectives to be achieved. The decision maker may wish to have the relative outcome of each alternative expressed as a single number, whereas at other times, it may be more helpful to see the results individually for each criteria and each alternative.
  • 6. Evaluating Transportation Alternatives Evaluation can also be made after a project is completed to determine if the outcomes of the project are as had been anticipated. Post Factor evaluation can be very helpful in formulating information useful for evaluating similar projects elsewhere or in making modifications in original designs.
  • 7. Evaluating Transportation Alternatives Identifying Project Stakeholders Examples of groups (“stakeholders”) that could be affected by a transportation project include System users Transportation management Citizens in the community Business Local, state, and national government
  • 8. Evaluating Transportation Alternatives Identifying Project Stakeholders For smaller projects, stakeholders will usually be limited to the system users and transportation management. A clear definition of whose viewpoint is being considered in the evaluation is necessary. A transportation project can affect these groups either positively or negatively. For example, a major project could increase business or expanded construction activity could trigger an economic boom in the area. The project might also require taking of land, or it could create other environmental effects.
  • 9. Evaluating Transportation Alternatives Selecting Evaluation Criteria A transportation project is intended to accomplish one or more goals and objectives. If the goal is to reduce accidents, the criteria can be measured as the number of accidents expected to occur for each of the alternativesconsidered. If another goal is to improve mobility, the criteria could be travel speed or travel time.
  • 10. Evaluating Transportation Alternatives Selecting Evaluation Criteria Criteria selection is a basic element of the evaluation process, because they become the basis on which each project (alternative) is compared. It is important that the criteria be related as closely as possible to the stated objectives. Criteria selected should be easy to measure and sensitive to changes made in each alternative.
  • 11. Evaluating Transportation Alternatives Selecting Evaluation Criteria It is better to limit the number of criteria to those that will be most helpful in reaching a decision. Too much information can be confusing and counterproductive, and could create uncertainly and could encourage a decision on political basis.
  • 12. Evaluating Transportation Alternatives Selecting Evaluation Criteria Examples of Criteria Used for Evaluating Transportation Alternatives  Capital Costs  Construction  Right-of-way  Vehicles  Maintenance costs  Facility operating costs  Travel time cost  Vehicle operating costs  Accident costs
  • 13. Evaluating Transportation Alternatives Measures of Effectiveness (MOE) The numerical or relative results for each criterion are called Measures of Effectiveness (MOE). It is necessary to decide how the MOEs will be used in the evaluation process. There are three different approaches.
  • 14. Evaluating Transportation Alternatives Measures of Effectiveness (MOE) One approach is to convert each MOE to a common unit (“money”), and then, for each alternative, compute the summation for all measures (criteria). For example, if the cost of an accident is known and the value of travel time can be determined, then it would be possible to compute a single number that would represent the total cost of each alternative, since the costs of construction, maintenance, and operation are already in monetary terms.
  • 15. Evaluating Transportation Alternatives Measures of Effectiveness (MOE) A second approach is to convert each measure of effectiveness (MOE) to a numerical score. For example, if a project alternatives does well in one criterion, it is given a high score; if it does poorly in another criterion, it is given a low score. A single number can be calculated that represents the weighted average score of all MOEs that were considered. This approach is similar to calculating grades in a course!
  • 16. Evaluating Transportation Alternatives Measures of Effectiveness (MOE) A third way is to identify the MOE for each alternative in a matrix form, with no attempt to combine them. This approach furnished the maximum amount of information without prejudging wither how the MOE should be combined or their relative importance.
  • 17. Evaluating Transportation Alternatives Evaluation Procedure and Decision Making How well will the evaluation process assist in making a decision? The decision maker typically needs to know what the costs of the project will be (in many instances this alone will determine the outcome). Another question may be, do the benefits justify the expenditure of funds for transportation, or would the money be better spent elsewhere? It may be necessary to carry out a sensitivity analysis that shows a range of values rather than a singlenumber.
  • 18. Evaluating Transportation Alternatives Evaluation Procedure and Decision Making The decision maker may want to know the cost to highway users as a result of travel delays during construction. Also of interest may be the length of time necessary to finish the project, since public officials are often interested in seeing work completed during their administration. The source of funds for the project and othermatters dealing with its implementation will also be of concern. Thus, in addition to the fairly straightforward problem of evaluation based on a selected set of measurable criteria, the transportation engineer must be prepared to answer any and all questions about the projects and its implications.
  • 19. Evaluation Based On Economic Criteria Elements of Cost  The cost of a transportation facility improvement includes two components First Cost- engineering design, right-of-way, and construction. Continuing Cost- maintenance, operation, and administration.
  • 20. Evaluation Based On Economic Criteria Elements of Cost  Expenses for administration or other overhead charges are usually excluded in an economic evaluation because they will be incurred regardless of whether or not the project is selected (sunk cost).  Salvage value is the worth of an asset at the end of its service life (usually considered in economic evaluation).
  • 21. Evaluation Based On Economic Criteria Elements of Cost  Three commonly used measures of user costsare: Vehicle operating costs Travel time costs costs of accidents They are sometimes referred to as benefits since the improvements to a transportation facility are likely to reduce (lower) the cost of vehicle operation, cost of travel time, and cost of accidents.
  • 22. Evaluation Based On Economic Criteria  Interaction Between Road User Costs and Highway Geometric and Operational Factors
  • 23. Economic Evaluation Methods An economic evaluation of a transportation projectis completed using one of the followingmethods: Present Worth (PW) Equivalent Uniform Annual Cost (EUAC) Benefit-Cost Ratio (BCR) Internal Rate of Return(ROR)
  • 24. Economic Evaluation Methods Present Worth (PW) is the most straightforward of the methods, since it represents the current value of all costs that will be incurred over the lifetime of theproject. Net Present Worth (NPW) is the PW of a given cash flow that has both receipts and disbursements.
  • 26. Economic Evaluation Methods Equivalent Uniform Annual Worth (EUAW) is a conversion of a given cash flow to a series of equal annual amounts. If the amounts are considered to occur at the end of the interest period,then
  • 28. Economic Evaluation Methods The benefit-Cost Ratio (BCR) is a ratio of the PW of net project benefits and net project costs. The formula for BCR is: Where, B2/1 = C2/1 = reduction in user and operation costs between higher cost alternative 2 and lower cost alternative 1, expressed as PW or EUAB increase in facility costs, expressed as PW or EUAC If the BCR is 1 or greater, then the higher cost alternative is economically attractive. If BCR is less than 1, this alternative isdiscarded. 2/1 2/1 C BCR  B2 /1
  • 29. Economic Evaluation Methods Internal Rate of Return (ROR) method determines the interest rate at which the PW of reductions in user and operation costs B2/1 equals the PW of increases in facility costs C2/1. If the ROR exceeds the interest rate, the higher cost project is retained. If the ROR is less than the interest rate, the higher cost project is eliminated. The procedure for comparison is similar to that used in the BCR method.
  • 30. Economic Evaluation Methods Illustration The department of traffic is considering three improvement plans for a heavily traveled intersection within the city. The improvement is expected to achieve three objectives: improve travel speeds, increase safety, and reduce operating expenses for drivers. The annual dollar value of savings compared with existing conditions for each criterion as well as additional construction and maintenance costs is shown in as follows. If the economic life of the road is considered to be 50 years and the discount (interest) rate is 3%, which alternative should be selected?
  • 35. Economic Evaluation Methods Illustration 35 • Solve by ROR Method: (in this situation, we solve for the interest rate for which NPW = 0 1. Compute ROR for alternative I versus DN: NPW= 0 = -185,000 + (-1500+5000+3000+500)(P/A-i-50) (P/A-i-50) = 185000/7000 = 26.428 {(1+i)50 – 1}/i(1+i)50 = 26.428 Solving, i = 2.6% ► Since ROR is less than 3%, we discard alternative I.
  • 36. Economic Evaluation Methods Illustration • Solve by ROR Method: (in this situation, we solve for the interest rate for which NPW = 0 2. Compute ROR for alternative II versus DN: NPW= 0 = -220,000 + (-2500+5000+6500+500)(P/A-i-50) (P/A-i-50) = 220000/9500 = 23.16 {(1+i)50 – 1}/i(1+i)50 = 23.16 Solving, i = 3.6% ► Since ROR is greater than 3%, we select alternative II over DN.
  • 37. Economic Evaluation Methods Illustration 37 • Solve by ROR Method: (in this situation, we solve for the interest rate for which NPW = 0 3. Compute ROR for alternative III versus alternative II: NPW= 0 = -(310,000-220,000) + (12,800-9,500)(P/A-i-50) (P/A-i-50) = 90000/3300 = 27.27 {(1+i)50 – 1}/i(1+i)50 = 27.27 Solving, i = 2.7% ► Since the increased investment in alternative III yields an ROR less than 3%, we do not select alternative III, but again pick alternative II.