Modern Coach Factory, Raebareli
Presentation on
“Study Of Shell Manufacturing Process at
MCF/RBL”
Under the guidance of: Submitted by:
Mr. Umesh Singh Shikhar Gupta (VT-294)
(SSE, Training) 1403040099
B.Tech/ME/4th year/B
Shell Manufacturing
• The manufacturing of the shell is accomplished
with the assembly of Under frame, Side Walls,
Roof and Roof Bearer, End-Wall Assembly.
• The raw metal comes in the form of rolls of the
metal sheets. Three types of metallic sheets are
used at MCF/RBL viz.
• SSA (Stainless Steel Austenitic)
• SSF (Stainless Steel Ferritic)
• CS (Corten Steel)
Shell Manufacturing
1. Side Wall Manufacturing
2. Roof Manufacturing
3. Roof Bearer Manufacturing
4. Underframe Manufacturing
5. Center Buffer Coupler
5. Assembly of Shell
6. Skin Tensioning of Shell
1. Side Wall Manufacturing
• Sheets from CTLS are now fed to CTLS
machine i.e. cut to length cum slitter machine.
• CTLS uncoils the sheet and straightens the
sheets without altering actual thickness and
other parameters of the sheet. After
straightening the sheet Slitting operation is
performed on the sheet.
• The thickness of sidewall sheets is 2mm.
CTLS Line
CTLS Line
1.Side Wall Manufacturing
• The SSA comes in the size of 1.25 mm, 1.75 mm;
SSF comes in the sizes of 2 mm, 4 mm, 6 mm and
Corten Steel comes in the size of 3.16 mm, 4 mm,
5 mm, 6 mm.
• When the sheets are processed in the CTL line,
the processed sheets are being sent to three
stations viz. Shearing machine, Laser Cutting
machine and Press brake machine (800 tonnes,
160 tonnes, 200 tonnes, 400tonnes).
Laser Cutting Machine
• LCM (Laser Cutting Machine) is used to cut
complicated types of profile with a help of the
Laser. At MCF/RBL LCM is used to cut z-
members, U-channels, Angle, Rib, Roof flange,
brackets, etc.
Laser cutting and Welding machine
• LCWM (Laser Cutting and Welding machine) is
used to cut the complicated profiles like
window panels of 3-Tier and 2-Tier. It cuts the
required complicated profile with great
accuracy and finish. The operation of LCWM is
automated and the machine is CNC type.
Laser cutting and Welding machine
• When the window panels are cut from side
wall sheet then the sheet is send to the CNC
800 Ton Hydraulic Press Machine to form the
window curve of GS, SLR type coaches.
Laser cutting and Welding machine
Pick and place robot of LCWM
Cutting and welding head of LCWM
Welding Head performing laser welding of butt joined sheets
When the window panels are cut from side wall
sheet then the sheet is send to the CNC 800 Ton
Hydraulic Press Machine to form the window
curve of GS, SLR type coaches.
• Now the members are held in their positions. The
side wall assembly is now carried to the Robotic
MIG-Welding station. Where the intersecting
members are weld with each other. This machine
is CNC type and its operation is based on
programme.
• This completes the welding of intersecting
members. Now the CNC spot welding machine
welds the Sheet and members. Note that CNC
MIG- Welding welds the member to member and
CNC Resistance Spot welding is used to weld the
member and sheets.
• Now this completes the side wall assembly.
CNC spot welding machine
CNC Robotic MIG Welding m/c
2. Roof Manufacturing
• Roof sheets are manufactured from 1.25 &
1.7mm Austenitic Stainless Steel. Roof Arches
are manufactured from 2 mm Ferritic Steel.
End plate and angles are manufactured from 4
mm Ferritic Steel. The middle portion of the
roof sheet is plain and manufactured from 1.7
mm Austenitic Steel. The roof is light weight
as compared to ICF coaches.
• The sheets are now formed into shape
consisting of crests and troughs with the help
of CNC 200 ton Hydraulic Press Brake
machine. The material used for roof sheets is
SS.
• These z-sections are now bend into a curve
shape with the help of CNC Stretch-Bending
machine keeping in mind the radius to be
provided to the roof.
CNC Stretch Bending machine
Roof Assembly station
• The end edge of the roof is made into the uniform surface by
removing the crest and troughs. This is achieved by cutting
the edge surface deformities and hammering in so that it
takes the smooth and uniform shape as shown in the figure
below.
Assembled roof with ventilator
3. Roof Bearer manufacturing
• The roof bearer is intermediate component used to join the side wall with
the roof. It is not possible to join the roof directly with the side wall
assembly so roof bearer is used as an intermediate component between
the side wall assembly and roof assembly. The reason is such large radius
of bend can only be achieved by use of an intermediate component.
4. Under Frame Manufacturing
• Under frame is the base of any coach on which
the coach body is being build. It must be
sufficiently strong and resistant
• Cross members are held at their respective
positions also brackets are inserted between
them. After this under frame is advanced to the
Robotic MIG Welding station where robotic arms
perform the continuous run welding between
mating parts, these robotic arms are controlled
by a CNC controller based on a program
4. Under Frame Manufacturing
Cross members being welded to under frame
CNC Robotic MIG Welding station
• Then the floor made of corrugated sheets of 1.25
mm thick is plug weld from the top to the cross
members. Then the under frame is inverted and
various components like yaw damper, water tank
mounting brackets are welded at their respective
positions.
• Up to this, whatever we have studied were the
major components of shell. But apart from these
in the completion of the shell body some ready to
assemble components like End wall Assembly is
weld to close the ends of the coach. End wall is
made of ferritic steel. To reduce its weight holes
provided in all stiffeners.
End Wall assembly
5. Centre Buffer coupler
• The coupler provides a means of mechanically
connecting individual adjacent vehicles to
make a train. The coupler is located at both
ends of each vehicle. When connected to a
coupler of an adjacent vehicle, it allows the
vehicles to move independently to
accommodate track curvature and elevation
change while remaining connected (coupled)
together.
5. Centre Buffer coupler
• LHB coaches have been provided with tight lock
centre buffer couplers instead of screw coupling.
• Couplers have anti climbing features because of
vertical interlocking. Couplers have adequate
strength for:
• Satisfactory hauling of a train of 26 coaches at
110 kmph
• Satisfactory hauling of a train of 18 coaches at
160 kmph
Schematic of CBC
Actual CBC installed
6. Assembly of Shell
• Various steps are involved in the assembly of a
shell are. It starts with the mounting of under
frame, side walls are being carried from their
stations to the assembly station with the help
of EOT crane. This side wall is positioned and
placed over the edge of under frame.
6. Assembly of Shell
• Initially side walls are supported by welding
them with steel rods which are welded to the
floor for making sure that the side wall is
perfectly vertical.
• Manual tacking at specific distances is
required to ensure the perfect mating edge for
feeding it to the robotic MIG welding machine
which performs continuous run welding.
Manual MIG welding equipment
• Now the roof is being carried with the help of
EOT crane to the shell assembly station and is
put over the side walls.
• The shell is now moved to the CNC MIG
welding machine which welds the edges and
makes the whole shell into a single solid shell.
This machine uses two robotic arms whose
operation is based on a program fed to
controller of CNC machine.
CNC MIG Welding station
Manual tacking of side wall and under frame
7. Skin Tensioning of Shell
• After the assembly of shell, the final operation
which is done is Skin Tensioning.
A worker doing Skin Tensioning 4 Nozzle torch
Skin Tensioning have the following
advantages:
1. Stress relieving
2. Grain refining
3. Hardening of outer sheets
4. Checking of stress corrosions and good look
5. Uniform Shape relieve dents
7. Skin Tensioning of Shell
Skin Tensioning equipment
train manufacturing procedure.pdf

More Related Content

Similar to train manufacturing procedure.pdf

UNIT3-Special casting processmechanica.ppt
UNIT3-Special casting processmechanica.pptUNIT3-Special casting processmechanica.ppt
UNIT3-Special casting processmechanica.pptPraveen Kumar
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated ColumnAnees Khan
 
Matt Baum Design Engineer Portfolio
Matt Baum Design Engineer PortfolioMatt Baum Design Engineer Portfolio
Matt Baum Design Engineer PortfolioMatthew Baum
 
-Training-Report-at-rail-coach-factory-RCF-pdf.pdf
-Training-Report-at-rail-coach-factory-RCF-pdf.pdf-Training-Report-at-rail-coach-factory-RCF-pdf.pdf
-Training-Report-at-rail-coach-factory-RCF-pdf.pdfSimranjit24
 
Working of Metals.pdf .
Working of Metals.pdf                            .Working of Metals.pdf                            .
Working of Metals.pdf .happycocoman
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniqueIEI GSC
 
PRESENTATION ON DESIGN AND MANUFACTURE OF METRO CAR BODY
PRESENTATION ON DESIGN AND MANUFACTURE OF METRO CAR BODYPRESENTATION ON DESIGN AND MANUFACTURE OF METRO CAR BODY
PRESENTATION ON DESIGN AND MANUFACTURE OF METRO CAR BODYSyedYahya4
 
Design & Manufacturing of Metro Car Body.pdf
Design & Manufacturing of Metro Car Body.pdfDesign & Manufacturing of Metro Car Body.pdf
Design & Manufacturing of Metro Car Body.pdfravibhaknp
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdfFaizanSolanki
 
NMRC Civil Construction
NMRC Civil Construction NMRC Civil Construction
NMRC Civil Construction ajinkyaraj
 
Manufacturing of Large Electrical Machine
Manufacturing of Large Electrical MachineManufacturing of Large Electrical Machine
Manufacturing of Large Electrical MachineVAIBHAV SINGH
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar rautSAGAR RAUT
 
Mivan aluminium formwork
Mivan aluminium formworkMivan aluminium formwork
Mivan aluminium formworkMumtaz Alam
 
IRJET- Fabrication of Roller Bending Machine
IRJET-  	  Fabrication of Roller Bending MachineIRJET-  	  Fabrication of Roller Bending Machine
IRJET- Fabrication of Roller Bending MachineIRJET Journal
 
Mivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentationMivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentationCivilTY09AdityaGaval
 

Similar to train manufacturing procedure.pdf (20)

UNIT3-Special casting processmechanica.ppt
UNIT3-Special casting processmechanica.pptUNIT3-Special casting processmechanica.ppt
UNIT3-Special casting processmechanica.ppt
 
Metal Forging
Metal ForgingMetal Forging
Metal Forging
 
Bwel presentation
Bwel presentationBwel presentation
Bwel presentation
 
Formwork
FormworkFormwork
Formwork
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
 
Matt Baum Design Engineer Portfolio
Matt Baum Design Engineer PortfolioMatt Baum Design Engineer Portfolio
Matt Baum Design Engineer Portfolio
 
-Training-Report-at-rail-coach-factory-RCF-pdf.pdf
-Training-Report-at-rail-coach-factory-RCF-pdf.pdf-Training-Report-at-rail-coach-factory-RCF-pdf.pdf
-Training-Report-at-rail-coach-factory-RCF-pdf.pdf
 
Working of Metals.pdf .
Working of Metals.pdf                            .Working of Metals.pdf                            .
Working of Metals.pdf .
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
 
PRESENTATION ON DESIGN AND MANUFACTURE OF METRO CAR BODY
PRESENTATION ON DESIGN AND MANUFACTURE OF METRO CAR BODYPRESENTATION ON DESIGN AND MANUFACTURE OF METRO CAR BODY
PRESENTATION ON DESIGN AND MANUFACTURE OF METRO CAR BODY
 
Design & Manufacturing of Metro Car Body.pdf
Design & Manufacturing of Metro Car Body.pdfDesign & Manufacturing of Metro Car Body.pdf
Design & Manufacturing of Metro Car Body.pdf
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdf
 
Mivan tech
Mivan techMivan tech
Mivan tech
 
NMRC Civil Construction
NMRC Civil Construction NMRC Civil Construction
NMRC Civil Construction
 
Manufacturing of Large Electrical Machine
Manufacturing of Large Electrical MachineManufacturing of Large Electrical Machine
Manufacturing of Large Electrical Machine
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar raut
 
Mivan aluminium formwork
Mivan aluminium formworkMivan aluminium formwork
Mivan aluminium formwork
 
IRJET- Fabrication of Roller Bending Machine
IRJET-  	  Fabrication of Roller Bending MachineIRJET-  	  Fabrication of Roller Bending Machine
IRJET- Fabrication of Roller Bending Machine
 
Mivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentationMivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentation
 

Recently uploaded

Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 

Recently uploaded (20)

Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 

train manufacturing procedure.pdf

  • 1. Modern Coach Factory, Raebareli Presentation on “Study Of Shell Manufacturing Process at MCF/RBL” Under the guidance of: Submitted by: Mr. Umesh Singh Shikhar Gupta (VT-294) (SSE, Training) 1403040099 B.Tech/ME/4th year/B
  • 2. Shell Manufacturing • The manufacturing of the shell is accomplished with the assembly of Under frame, Side Walls, Roof and Roof Bearer, End-Wall Assembly. • The raw metal comes in the form of rolls of the metal sheets. Three types of metallic sheets are used at MCF/RBL viz. • SSA (Stainless Steel Austenitic) • SSF (Stainless Steel Ferritic) • CS (Corten Steel)
  • 3. Shell Manufacturing 1. Side Wall Manufacturing 2. Roof Manufacturing 3. Roof Bearer Manufacturing 4. Underframe Manufacturing 5. Center Buffer Coupler 5. Assembly of Shell 6. Skin Tensioning of Shell
  • 4. 1. Side Wall Manufacturing • Sheets from CTLS are now fed to CTLS machine i.e. cut to length cum slitter machine. • CTLS uncoils the sheet and straightens the sheets without altering actual thickness and other parameters of the sheet. After straightening the sheet Slitting operation is performed on the sheet. • The thickness of sidewall sheets is 2mm.
  • 7. 1.Side Wall Manufacturing • The SSA comes in the size of 1.25 mm, 1.75 mm; SSF comes in the sizes of 2 mm, 4 mm, 6 mm and Corten Steel comes in the size of 3.16 mm, 4 mm, 5 mm, 6 mm. • When the sheets are processed in the CTL line, the processed sheets are being sent to three stations viz. Shearing machine, Laser Cutting machine and Press brake machine (800 tonnes, 160 tonnes, 200 tonnes, 400tonnes).
  • 8. Laser Cutting Machine • LCM (Laser Cutting Machine) is used to cut complicated types of profile with a help of the Laser. At MCF/RBL LCM is used to cut z- members, U-channels, Angle, Rib, Roof flange, brackets, etc.
  • 9. Laser cutting and Welding machine • LCWM (Laser Cutting and Welding machine) is used to cut the complicated profiles like window panels of 3-Tier and 2-Tier. It cuts the required complicated profile with great accuracy and finish. The operation of LCWM is automated and the machine is CNC type.
  • 10. Laser cutting and Welding machine • When the window panels are cut from side wall sheet then the sheet is send to the CNC 800 Ton Hydraulic Press Machine to form the window curve of GS, SLR type coaches.
  • 11. Laser cutting and Welding machine
  • 12. Pick and place robot of LCWM
  • 13. Cutting and welding head of LCWM
  • 14. Welding Head performing laser welding of butt joined sheets
  • 15. When the window panels are cut from side wall sheet then the sheet is send to the CNC 800 Ton Hydraulic Press Machine to form the window curve of GS, SLR type coaches.
  • 16. • Now the members are held in their positions. The side wall assembly is now carried to the Robotic MIG-Welding station. Where the intersecting members are weld with each other. This machine is CNC type and its operation is based on programme. • This completes the welding of intersecting members. Now the CNC spot welding machine welds the Sheet and members. Note that CNC MIG- Welding welds the member to member and CNC Resistance Spot welding is used to weld the member and sheets. • Now this completes the side wall assembly.
  • 17. CNC spot welding machine
  • 18. CNC Robotic MIG Welding m/c
  • 19. 2. Roof Manufacturing • Roof sheets are manufactured from 1.25 & 1.7mm Austenitic Stainless Steel. Roof Arches are manufactured from 2 mm Ferritic Steel. End plate and angles are manufactured from 4 mm Ferritic Steel. The middle portion of the roof sheet is plain and manufactured from 1.7 mm Austenitic Steel. The roof is light weight as compared to ICF coaches.
  • 20. • The sheets are now formed into shape consisting of crests and troughs with the help of CNC 200 ton Hydraulic Press Brake machine. The material used for roof sheets is SS. • These z-sections are now bend into a curve shape with the help of CNC Stretch-Bending machine keeping in mind the radius to be provided to the roof.
  • 23. • The end edge of the roof is made into the uniform surface by removing the crest and troughs. This is achieved by cutting the edge surface deformities and hammering in so that it takes the smooth and uniform shape as shown in the figure below.
  • 24. Assembled roof with ventilator
  • 25. 3. Roof Bearer manufacturing • The roof bearer is intermediate component used to join the side wall with the roof. It is not possible to join the roof directly with the side wall assembly so roof bearer is used as an intermediate component between the side wall assembly and roof assembly. The reason is such large radius of bend can only be achieved by use of an intermediate component.
  • 26. 4. Under Frame Manufacturing • Under frame is the base of any coach on which the coach body is being build. It must be sufficiently strong and resistant • Cross members are held at their respective positions also brackets are inserted between them. After this under frame is advanced to the Robotic MIG Welding station where robotic arms perform the continuous run welding between mating parts, these robotic arms are controlled by a CNC controller based on a program
  • 27. 4. Under Frame Manufacturing
  • 28. Cross members being welded to under frame
  • 29. CNC Robotic MIG Welding station
  • 30. • Then the floor made of corrugated sheets of 1.25 mm thick is plug weld from the top to the cross members. Then the under frame is inverted and various components like yaw damper, water tank mounting brackets are welded at their respective positions. • Up to this, whatever we have studied were the major components of shell. But apart from these in the completion of the shell body some ready to assemble components like End wall Assembly is weld to close the ends of the coach. End wall is made of ferritic steel. To reduce its weight holes provided in all stiffeners.
  • 32. 5. Centre Buffer coupler • The coupler provides a means of mechanically connecting individual adjacent vehicles to make a train. The coupler is located at both ends of each vehicle. When connected to a coupler of an adjacent vehicle, it allows the vehicles to move independently to accommodate track curvature and elevation change while remaining connected (coupled) together.
  • 33. 5. Centre Buffer coupler • LHB coaches have been provided with tight lock centre buffer couplers instead of screw coupling. • Couplers have anti climbing features because of vertical interlocking. Couplers have adequate strength for: • Satisfactory hauling of a train of 26 coaches at 110 kmph • Satisfactory hauling of a train of 18 coaches at 160 kmph
  • 34. Schematic of CBC Actual CBC installed
  • 35. 6. Assembly of Shell • Various steps are involved in the assembly of a shell are. It starts with the mounting of under frame, side walls are being carried from their stations to the assembly station with the help of EOT crane. This side wall is positioned and placed over the edge of under frame.
  • 36. 6. Assembly of Shell • Initially side walls are supported by welding them with steel rods which are welded to the floor for making sure that the side wall is perfectly vertical. • Manual tacking at specific distances is required to ensure the perfect mating edge for feeding it to the robotic MIG welding machine which performs continuous run welding.
  • 37. Manual MIG welding equipment
  • 38. • Now the roof is being carried with the help of EOT crane to the shell assembly station and is put over the side walls. • The shell is now moved to the CNC MIG welding machine which welds the edges and makes the whole shell into a single solid shell. This machine uses two robotic arms whose operation is based on a program fed to controller of CNC machine.
  • 39. CNC MIG Welding station
  • 40. Manual tacking of side wall and under frame
  • 41. 7. Skin Tensioning of Shell • After the assembly of shell, the final operation which is done is Skin Tensioning. A worker doing Skin Tensioning 4 Nozzle torch
  • 42. Skin Tensioning have the following advantages: 1. Stress relieving 2. Grain refining 3. Hardening of outer sheets 4. Checking of stress corrosions and good look 5. Uniform Shape relieve dents
  • 43. 7. Skin Tensioning of Shell