SlideShare a Scribd company logo
1 of 4
Download to read offline
1
Extract Technology Delivers State-of-the-Art
Sampling Facility to Big Pharma Company
Updating a Sampling Area
with New Containment
Technology
Gary Partington
Technical Sales Manager
Extract Technology
After multiple successful facility projects across the
world, Extract Technology were approached by a major
Pharmaceutical Company and given the challenge to
update the older generation of containment
equipment from 1990’s technology to the advanced
technology available today.
Replacing its predecessor which was installed by ETL in
June, 1999, this state of the art facility covers 27m²
with a large sampling area protected by independent
personnel and material airlocks. This particular system
was designed with the vision that maintaining operator
and product protection would be of paramount
importance. To achieve this, the tried and tested
unidirectional airflow regime that is found within our
range of downflow booths was used. To allow the
facility to maintain regulatory compliance with ISO 5
conditions ensuring product protection, a positive to
ambient pressure regime was used within the airlocks
providing defined barrier between the external
environment and the ISO 5 environment.
2
Rigid Barrier Screen within Facility
Technical process
The Sampling Booth operates with a single pass airflow
regime whereby a clean vertical laminar airflow is
supplied at a velocity of 0.5m/s +/- 10% directly into
the top plenum. After the air has passed over the
operators alleviating any airborne particulate from
their breathing zone, it will be exhausted via the low
level exhaust duct. In addition to the low level
extraction a high level exhaust duct was also
integrated into the rear bulkhead of the booth - this
allowed any particulate at working height to also be
removed from the internal environment. This specific
project housed a local HVAC system which was used to
supply the purified air to both the sampling booth and
airlocks.
Challenged with providing an OEL of less than 1µg/m³
over the task duration, it was decided to integrate a
Rigid Barrier Screen technology into the facility. The
assembly is fitted with a transparent acrylic screen that
houses two glove ports. To ensure ergonomic viability
the screen is mounted on an articulating arm allowing
5 axis of movement. Nevertheless, to achieve the
required OEL of less than 1µg/m³ over the task
duration, set SOP’s (Standard Operating Procedures) of
the screen must be strictly adhered to. The operator
must work behind the acrylic screen through the glove
ports; by doing this a physical barrier is created to
segregate the operator from the product yet still
allowing access to perform their tasks.
The sampling facility housed a sophisticated control
system which allowed for complex and specific
manipulation of the equipment. The on-board PLC
gives signals to the air handling unit informing the unit
at what speed it should be supplying the air to aid in
maintaining the required velocity in various filter
Facility Local Operator Panel
conditions. On-board hardware and systems such as
valves, alarms and the operational sequence of the
facility are all accessible by the integrated HMI. In
addition to the PLC, the facility was fitted with a chart
recorder allowing it to comply with CFR 21 Part 11
regulations. A multitude of monitoring is performed
continuously by various on-board sensors, processed
by the PLC and displayed on the HMI. The monitored
parameters include: booth supply flow, filtration
condition, booth exhaust flow, booth pressure,
oxygen levels, personnel and material airlock
pressure.
A hazardous analysis report supplied by the customer
provided the required ATEX zoning. The unit was
commissioned with both a dust and gas rating with: a
300mm zone around the product was rated to ATEX
Zone 2 IIB T4 and within the exhaust ducts a rating of
Zone 22 IIIB T4.
3
Material Airlock Featuring Client’s Transportation Device
Operational Process
To correctly, safely and efficiently use the sampling
facility the following SOP’s (Standard Operating
Procedures) are utilized:
• Operator starts the facility via the HMI located
outside the airlocks.
• To ensure the facility is in good health all measured
parameters are checked.
• Pallet is placed on rail track transport truck.
• Operator activates external material airlock roller
shutter door (door opened)
• Operator remotely drives the truck into the
material airlock, following the truck into the airlock
to perform the clean down procedures.
• Once preformed the operator exits the material
airlock and de-activates the external roller shutter
door (door closed)
Note: clients transport truck will remain in the material
airlock until the set working pressure is once again
achieved.
• Operator enters personnel airlock.
• Changing procedures take place.
• Operator exits the personnel airlock and enters the
sampling booth.
• Once again the condition of the booth is checked
via the internal magnehelic gauges to ensure
containment is being achieved.
• After this the operator then activates the internal
material airlock roller shutter door. (Door opened)
• The transport truck is driven in via the operator’s
remote control unit.
• Once in place the operator de-activates the roller
shutter door (Door Closed)
• Utilizing the installed work bench and rigid barrier
screen, the operator begins their samplings tasks.
4
Front View of Facility 1
Benefits
• ISO 5 processing conditions
• cGMP finish
• Ergonomic workflow
• Turnkey package
• Custom design to suit client’s process
• Hazardous compliance
• Internal furnishings
• Battery backup LED lighting in airlocks
• PLC control with touch screen HMI interface
• Rapid roller shutter doors for material entry/exit
• Single Pass airflow for liquids/powder handling,
complete with full air handling packages
• Cascading pressure regime
Conclusion
Close collaboration with the customer ensured that the
equipment was engineered to suit their specific needs
and safety requirements. The advanced technology
integrated into the facility provided a more efficient
way to handle highly potent substances. By using a PLC
control system and various conditions monitoring safe
24 hour production within the facility was made
possible, allowing the customer to increase their
production rate without the risk of faulty machinery
compromising the ISO 5 processing conditions.
Learning from previous experience, Extract
Technology were able to add onto the innovative and
educational values of the new facility project.
Although the previous facility was decommissioned
and removed, having its presence on site for 15 years
re-assured the customer that undertaking projects
with Extract Technology will lead to a successful
long term solution.

More Related Content

What's hot

Cip sip-ctd solution-ivt_presentation
Cip sip-ctd solution-ivt_presentationCip sip-ctd solution-ivt_presentation
Cip sip-ctd solution-ivt_presentationAraik Ambartsumyan
 
Application of computer in fermentation
Application of computer in fermentationApplication of computer in fermentation
Application of computer in fermentationsivaprakashsiva
 
Advanced Process Control for ARC
Advanced Process Control for ARCAdvanced Process Control for ARC
Advanced Process Control for ARCanilkc12
 
Heating Ventilation and Air Conditioner HVAC Qualification
Heating Ventilation and Air Conditioner HVAC QualificationHeating Ventilation and Air Conditioner HVAC Qualification
Heating Ventilation and Air Conditioner HVAC QualificationMayur Unde
 
Validation of HVAC pharma geeta TUBE (Utility Systems)
Validation of HVAC pharma geeta TUBE (Utility Systems)Validation of HVAC pharma geeta TUBE (Utility Systems)
Validation of HVAC pharma geeta TUBE (Utility Systems)Saikat Bagchi
 
Maintenance of Instruments & Systems (free chapter download)
Maintenance of Instruments & Systems (free chapter download)Maintenance of Instruments & Systems (free chapter download)
Maintenance of Instruments & Systems (free chapter download)ISA Interchange
 
Hvac validation protocol
Hvac validation protocolHvac validation protocol
Hvac validation protocolvivekccpr21
 
JFTOT IV
JFTOT IVJFTOT IV
JFTOT IVwchupin
 
York National Accounts
York National AccountsYork National Accounts
York National AccountsCesar Joao
 
NEXCOM_APPC_1533T-P20s_Exercise_Strict_Control_Monitoring_over_Steelmaking_Qu...
NEXCOM_APPC_1533T-P20s_Exercise_Strict_Control_Monitoring_over_Steelmaking_Qu...NEXCOM_APPC_1533T-P20s_Exercise_Strict_Control_Monitoring_over_Steelmaking_Qu...
NEXCOM_APPC_1533T-P20s_Exercise_Strict_Control_Monitoring_over_Steelmaking_Qu...Eric Lo
 
Requirements Management Matrix done-1
Requirements Management Matrix done-1Requirements Management Matrix done-1
Requirements Management Matrix done-1Derek Cunningham
 

What's hot (20)

Cip sip-ctd solution-ivt_presentation
Cip sip-ctd solution-ivt_presentationCip sip-ctd solution-ivt_presentation
Cip sip-ctd solution-ivt_presentation
 
Application of computer in fermentation
Application of computer in fermentationApplication of computer in fermentation
Application of computer in fermentation
 
Process control introduction
Process control   introductionProcess control   introduction
Process control introduction
 
Advanced Process Control for ARC
Advanced Process Control for ARCAdvanced Process Control for ARC
Advanced Process Control for ARC
 
Ampule filling and_sealing_machine.ppt1
Ampule filling and_sealing_machine.ppt1Ampule filling and_sealing_machine.ppt1
Ampule filling and_sealing_machine.ppt1
 
Auditing of hvac by parag
Auditing of hvac by paragAuditing of hvac by parag
Auditing of hvac by parag
 
Heating Ventilation and Air Conditioner HVAC Qualification
Heating Ventilation and Air Conditioner HVAC QualificationHeating Ventilation and Air Conditioner HVAC Qualification
Heating Ventilation and Air Conditioner HVAC Qualification
 
Validation of HVAC pharma geeta TUBE (Utility Systems)
Validation of HVAC pharma geeta TUBE (Utility Systems)Validation of HVAC pharma geeta TUBE (Utility Systems)
Validation of HVAC pharma geeta TUBE (Utility Systems)
 
HVAC system
 HVAC system HVAC system
HVAC system
 
Maintenance of Instruments & Systems (free chapter download)
Maintenance of Instruments & Systems (free chapter download)Maintenance of Instruments & Systems (free chapter download)
Maintenance of Instruments & Systems (free chapter download)
 
Hvac validation protocol
Hvac validation protocolHvac validation protocol
Hvac validation protocol
 
JFTOT IV
JFTOT IVJFTOT IV
JFTOT IV
 
York National Accounts
York National AccountsYork National Accounts
York National Accounts
 
Validation of hvac
Validation of hvacValidation of hvac
Validation of hvac
 
Pharmaceutical automation
Pharmaceutical automationPharmaceutical automation
Pharmaceutical automation
 
Hire-Unit-Data-Sheet-1
Hire-Unit-Data-Sheet-1Hire-Unit-Data-Sheet-1
Hire-Unit-Data-Sheet-1
 
NEXCOM_APPC_1533T-P20s_Exercise_Strict_Control_Monitoring_over_Steelmaking_Qu...
NEXCOM_APPC_1533T-P20s_Exercise_Strict_Control_Monitoring_over_Steelmaking_Qu...NEXCOM_APPC_1533T-P20s_Exercise_Strict_Control_Monitoring_over_Steelmaking_Qu...
NEXCOM_APPC_1533T-P20s_Exercise_Strict_Control_Monitoring_over_Steelmaking_Qu...
 
Jatin validation
Jatin validationJatin validation
Jatin validation
 
Requirements Management Matrix done-1
Requirements Management Matrix done-1Requirements Management Matrix done-1
Requirements Management Matrix done-1
 
Process validation of tablets
Process validation of tabletsProcess validation of tablets
Process validation of tablets
 

Similar to casestudyextractbigpharmav1

Ultra safe brochure
Ultra safe brochureUltra safe brochure
Ultra safe brochureHerman Halim
 
Advanced sterile product manufacturing technology
Advanced sterile product manufacturing technologyAdvanced sterile product manufacturing technology
Advanced sterile product manufacturing technologyPriyankaSananse
 
Sterile process validation
Sterile process validationSterile process validation
Sterile process validationSagar Savale
 
Pharmaceutical Engineering Downflow Booth Testing
Pharmaceutical Engineering Downflow Booth TestingPharmaceutical Engineering Downflow Booth Testing
Pharmaceutical Engineering Downflow Booth TestingEric Ferguson
 
HVAC Validation (Air Handling Units).pdf
HVAC Validation (Air Handling Units).pdfHVAC Validation (Air Handling Units).pdf
HVAC Validation (Air Handling Units).pdfBALASUNDARESAN M
 
Equipment validation of fbd
Equipment validation of fbdEquipment validation of fbd
Equipment validation of fbdpriyanka odela
 
Validation utility system
Validation utility systemValidation utility system
Validation utility systemArpitSuralkar
 
Clean Room Pharmaceutical Good Manufacturing Process.pdf
Clean Room Pharmaceutical Good Manufacturing Process.pdfClean Room Pharmaceutical Good Manufacturing Process.pdf
Clean Room Pharmaceutical Good Manufacturing Process.pdfHananZayed4
 
Clean Room Pharmaceutical_ GMP Procedures
Clean Room Pharmaceutical_ GMP ProceduresClean Room Pharmaceutical_ GMP Procedures
Clean Room Pharmaceutical_ GMP ProceduresHananZayed4
 
Sterile products manufacturing
Sterile products manufacturingSterile products manufacturing
Sterile products manufacturingDr. Samia
 
Control room ( Advance Services )
Control room ( Advance Services ) Control room ( Advance Services )
Control room ( Advance Services ) Divyanshu Prakash
 
Validation utility system
Validation utility systemValidation utility system
Validation utility systemPRANJAY PATIL
 
A Healthy Buildings Guide To Reopen Restaurants | EcoEnergy Insights
A Healthy Buildings Guide To Reopen Restaurants | EcoEnergy InsightsA Healthy Buildings Guide To Reopen Restaurants | EcoEnergy Insights
A Healthy Buildings Guide To Reopen Restaurants | EcoEnergy InsightsAmitSharma2980
 
equipmentsvalidation.pdf
equipmentsvalidation.pdfequipmentsvalidation.pdf
equipmentsvalidation.pdfpshashank0409
 

Similar to casestudyextractbigpharmav1 (20)

Ultra safe brochure
Ultra safe brochureUltra safe brochure
Ultra safe brochure
 
Advanced sterile product manufacturing technology
Advanced sterile product manufacturing technologyAdvanced sterile product manufacturing technology
Advanced sterile product manufacturing technology
 
Validation ppt
Validation pptValidation ppt
Validation ppt
 
Sterile process validation
Sterile process validationSterile process validation
Sterile process validation
 
Process automation with respect to Sterile Products
Process automation with respect to Sterile ProductsProcess automation with respect to Sterile Products
Process automation with respect to Sterile Products
 
Pharmaceutical Engineering Downflow Booth Testing
Pharmaceutical Engineering Downflow Booth TestingPharmaceutical Engineering Downflow Booth Testing
Pharmaceutical Engineering Downflow Booth Testing
 
HVAC Validation (Air Handling Units).pdf
HVAC Validation (Air Handling Units).pdfHVAC Validation (Air Handling Units).pdf
HVAC Validation (Air Handling Units).pdf
 
Equipment validation of fbd
Equipment validation of fbdEquipment validation of fbd
Equipment validation of fbd
 
Validation utility system
Validation utility systemValidation utility system
Validation utility system
 
Doc1 copy
Doc1   copyDoc1   copy
Doc1 copy
 
Clean Room Pharmaceutical Good Manufacturing Process.pdf
Clean Room Pharmaceutical Good Manufacturing Process.pdfClean Room Pharmaceutical Good Manufacturing Process.pdf
Clean Room Pharmaceutical Good Manufacturing Process.pdf
 
Clean Room Pharmaceutical_ GMP Procedures
Clean Room Pharmaceutical_ GMP ProceduresClean Room Pharmaceutical_ GMP Procedures
Clean Room Pharmaceutical_ GMP Procedures
 
Sterile products manufacturing
Sterile products manufacturingSterile products manufacturing
Sterile products manufacturing
 
Control room ( Advance Services )
Control room ( Advance Services ) Control room ( Advance Services )
Control room ( Advance Services )
 
Vision ppt presentation
Vision ppt presentationVision ppt presentation
Vision ppt presentation
 
Vision ppt presentation
Vision ppt presentationVision ppt presentation
Vision ppt presentation
 
Validation utility system
Validation utility systemValidation utility system
Validation utility system
 
Validation of hvac system
Validation of hvac systemValidation of hvac system
Validation of hvac system
 
A Healthy Buildings Guide To Reopen Restaurants | EcoEnergy Insights
A Healthy Buildings Guide To Reopen Restaurants | EcoEnergy InsightsA Healthy Buildings Guide To Reopen Restaurants | EcoEnergy Insights
A Healthy Buildings Guide To Reopen Restaurants | EcoEnergy Insights
 
equipmentsvalidation.pdf
equipmentsvalidation.pdfequipmentsvalidation.pdf
equipmentsvalidation.pdf
 

casestudyextractbigpharmav1

  • 1. 1 Extract Technology Delivers State-of-the-Art Sampling Facility to Big Pharma Company Updating a Sampling Area with New Containment Technology Gary Partington Technical Sales Manager Extract Technology After multiple successful facility projects across the world, Extract Technology were approached by a major Pharmaceutical Company and given the challenge to update the older generation of containment equipment from 1990’s technology to the advanced technology available today. Replacing its predecessor which was installed by ETL in June, 1999, this state of the art facility covers 27m² with a large sampling area protected by independent personnel and material airlocks. This particular system was designed with the vision that maintaining operator and product protection would be of paramount importance. To achieve this, the tried and tested unidirectional airflow regime that is found within our range of downflow booths was used. To allow the facility to maintain regulatory compliance with ISO 5 conditions ensuring product protection, a positive to ambient pressure regime was used within the airlocks providing defined barrier between the external environment and the ISO 5 environment.
  • 2. 2 Rigid Barrier Screen within Facility Technical process The Sampling Booth operates with a single pass airflow regime whereby a clean vertical laminar airflow is supplied at a velocity of 0.5m/s +/- 10% directly into the top plenum. After the air has passed over the operators alleviating any airborne particulate from their breathing zone, it will be exhausted via the low level exhaust duct. In addition to the low level extraction a high level exhaust duct was also integrated into the rear bulkhead of the booth - this allowed any particulate at working height to also be removed from the internal environment. This specific project housed a local HVAC system which was used to supply the purified air to both the sampling booth and airlocks. Challenged with providing an OEL of less than 1µg/m³ over the task duration, it was decided to integrate a Rigid Barrier Screen technology into the facility. The assembly is fitted with a transparent acrylic screen that houses two glove ports. To ensure ergonomic viability the screen is mounted on an articulating arm allowing 5 axis of movement. Nevertheless, to achieve the required OEL of less than 1µg/m³ over the task duration, set SOP’s (Standard Operating Procedures) of the screen must be strictly adhered to. The operator must work behind the acrylic screen through the glove ports; by doing this a physical barrier is created to segregate the operator from the product yet still allowing access to perform their tasks. The sampling facility housed a sophisticated control system which allowed for complex and specific manipulation of the equipment. The on-board PLC gives signals to the air handling unit informing the unit at what speed it should be supplying the air to aid in maintaining the required velocity in various filter Facility Local Operator Panel conditions. On-board hardware and systems such as valves, alarms and the operational sequence of the facility are all accessible by the integrated HMI. In addition to the PLC, the facility was fitted with a chart recorder allowing it to comply with CFR 21 Part 11 regulations. A multitude of monitoring is performed continuously by various on-board sensors, processed by the PLC and displayed on the HMI. The monitored parameters include: booth supply flow, filtration condition, booth exhaust flow, booth pressure, oxygen levels, personnel and material airlock pressure. A hazardous analysis report supplied by the customer provided the required ATEX zoning. The unit was commissioned with both a dust and gas rating with: a 300mm zone around the product was rated to ATEX Zone 2 IIB T4 and within the exhaust ducts a rating of Zone 22 IIIB T4.
  • 3. 3 Material Airlock Featuring Client’s Transportation Device Operational Process To correctly, safely and efficiently use the sampling facility the following SOP’s (Standard Operating Procedures) are utilized: • Operator starts the facility via the HMI located outside the airlocks. • To ensure the facility is in good health all measured parameters are checked. • Pallet is placed on rail track transport truck. • Operator activates external material airlock roller shutter door (door opened) • Operator remotely drives the truck into the material airlock, following the truck into the airlock to perform the clean down procedures. • Once preformed the operator exits the material airlock and de-activates the external roller shutter door (door closed) Note: clients transport truck will remain in the material airlock until the set working pressure is once again achieved. • Operator enters personnel airlock. • Changing procedures take place. • Operator exits the personnel airlock and enters the sampling booth. • Once again the condition of the booth is checked via the internal magnehelic gauges to ensure containment is being achieved. • After this the operator then activates the internal material airlock roller shutter door. (Door opened) • The transport truck is driven in via the operator’s remote control unit. • Once in place the operator de-activates the roller shutter door (Door Closed) • Utilizing the installed work bench and rigid barrier screen, the operator begins their samplings tasks.
  • 4. 4 Front View of Facility 1 Benefits • ISO 5 processing conditions • cGMP finish • Ergonomic workflow • Turnkey package • Custom design to suit client’s process • Hazardous compliance • Internal furnishings • Battery backup LED lighting in airlocks • PLC control with touch screen HMI interface • Rapid roller shutter doors for material entry/exit • Single Pass airflow for liquids/powder handling, complete with full air handling packages • Cascading pressure regime Conclusion Close collaboration with the customer ensured that the equipment was engineered to suit their specific needs and safety requirements. The advanced technology integrated into the facility provided a more efficient way to handle highly potent substances. By using a PLC control system and various conditions monitoring safe 24 hour production within the facility was made possible, allowing the customer to increase their production rate without the risk of faulty machinery compromising the ISO 5 processing conditions. Learning from previous experience, Extract Technology were able to add onto the innovative and educational values of the new facility project. Although the previous facility was decommissioned and removed, having its presence on site for 15 years re-assured the customer that undertaking projects with Extract Technology will lead to a successful long term solution.