SlideShare a Scribd company logo
1 of 12
Platts 2014 Transmission Planning and
Development Conference
June 18-19 Arlington, VA
Resource Adequacy
Methods Moving Forward to Assure Peak Deliverability
Bob Smith
Director, Energy Delivery Asset
Management & Planning
Outline
• APS System and Generation Resources
• Capacity Planning
• Energy Efficiency, Renewable Energy and Demand
Response
• Managing Intermittency
• Grid Modernization
2
Transmission System & Generation
• Electric generating resources
help balance the flow of power
around the state
• Grid built to balance sources of
energy
– Palo Verde and natural gas
generators are located West of
Valley while coal generators are
located North and East
• Generation additions or
retirements change this
balance
• Generation close to customer
demand center (metro-Phx)
improves transmission import
capabilities and maintains a
balanced system
3
Supply-Demand Gap
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
2014 2016 2018 2020 2022 2024 2026 2028
MW
Year
Existing Resources
Existing
Contracts
New Utility-Scale
Resources
4
• Growth in demand
requirements expected to
resume
• Customer resources
expected to triple over
planning horizon
• Renewable Energy Standard
15% by 2025
• Energy Efficiency Standard
22% by 2020
• Additional resource needs
anticipated to be met by
increasingly diverse and
efficient technologies
Demand Requirements
2014-2029 (Forecast)
Future Additional Resources
6,613 MW Expected at Peak
a. New Utility-Scale Resources
Natural Gas
4,205 MW
Renewable Energy
425 MW (818 MW nameplate capacity)
b. New Customer Resources
Energy Efficiency
1,447 MW
Distributed Energy
261 MW (722 MW nameplate capacity)
Demand Response
275 MW
Expected Future Resources
2014
8,124 MW
peak requirement
100% met with
existing resources
2029
12,982 MW
peak requirement
50% met with
existing resources
b
a
Existing Utility-Scale Resources
Existing Contracts
Existing Customer Resources
a New Utility-Scale Resources
New Customer Resourcesb
5
Different Types of Renewables vs. Time of Day
Illustration of future peak demand
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
0
20
40
60
80
100
120
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Load Profile
Fixed Position PV
Single Axis Tracking PV
Wind
CSP w/6 Hr Storage
MW Level of Renewable Output
Hour of Day
MW of System Load
CTs
6
Evolving Customer Demand and Markets
• Growth of solar PV is
changing customer energy
consumption patterns
• Generators must be able to
start and stop multiple times
per day
• Fast starting and ramping
capability is required in
responding to variable output
of renewable resources
7
1,000
2,000
3,000
4,000
5,000
1 3 5 7 9 11 13 15 17 19 21 23
MW
HOUR
Non-Summer Customer Power Consumption
2014 2021 2025 2029
Potential over-
generation followed by
8-hr 3,000 MW
continuous up-ramp
Capacity Contribution of Solar PV
Declines as Deployment Levels IncreaseAPS Forecast Peak Load
With Photovoltaic (Fixed South Facing)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
MW
1st Addition MW PV 2nd Additon PV 3rd Addition PV
0%
10%
20%
30%
40%
50%
60%
0 500 1000 1500 2000 2500
Range of Possible
Penetration by 2025
0
Peak Shifts to Sunset
8
CapacityContributionPercentofNameplate
MW of Nameplate Capacity
Ocotillo Modernization Project
• Retire existing steam units (220 MW) constructed in 1960
• Replace aging steam units with modern combustion turbines
– Install five General Electric LMS 100 combustion turbines – 102 MW each
– Transmission and natural gas pipeline infrastructure optimized
– Net site capacity increased by 290 MW to 620 MW total
• Maintain Valley reliability
– Generation close to load center
– Contingency and voltage support
• Responsive unit operations
– Quick starting and ramping
– Renewable integration
• Environmental attributes
– Emissions and water consumption
• In-service planned for summer 2018
9
Modernized Grid
AMI
AMI Solar
Production
Meters
Automated
Switches
TOAN
TOAN
Fault
Indicators
Substation
Health
Monitoring
Integrated
Volt/VAR
Control
Demand
Response
Fiber
Backhaul
ADMS
EMSTransformer
Load
Management
10
Conclusions
• Transmission system must accommodate entirety
of peak capacity needs
– Reserves
– Back-up capacity
• Diverse resource fleet includes renewables and
energy efficiency
– Significant growth expected
• Flexible generation aligns with capacity needs and
complements growing renewable energy fleet
• Investments in modernizing grid continuing
11
www.aps.com/resources
12

More Related Content

What's hot

Keynote Interview: Texas as a U.S. Flagship for Energy Transition
Keynote Interview: Texas as a U.S. Flagship for Energy TransitionKeynote Interview: Texas as a U.S. Flagship for Energy Transition
Keynote Interview: Texas as a U.S. Flagship for Energy TransitionNicole Green
 
Energy, Nuclear & Sustainable Power: Christopher Bowes, Nabarro
Energy, Nuclear & Sustainable Power: Christopher Bowes, NabarroEnergy, Nuclear & Sustainable Power: Christopher Bowes, Nabarro
Energy, Nuclear & Sustainable Power: Christopher Bowes, NabarroPlace North West
 
Evaluation of the role of energy storages in Europe with TIMES PanEU
Evaluation of the role of energy storages in Europe with TIMES PanEUEvaluation of the role of energy storages in Europe with TIMES PanEU
Evaluation of the role of energy storages in Europe with TIMES PanEUIEA-ETSAP
 
Policy Fair Poster - Molten Carbonate Fuel Cells for SAGD
Policy Fair Poster - Molten Carbonate Fuel Cells for SAGDPolicy Fair Poster - Molten Carbonate Fuel Cells for SAGD
Policy Fair Poster - Molten Carbonate Fuel Cells for SAGDJordan Robinson
 
Unlocking the Innovation Hidden within Today’s Variable-Speed Drives
Unlocking the Innovation Hidden within Today’s Variable-Speed DrivesUnlocking the Innovation Hidden within Today’s Variable-Speed Drives
Unlocking the Innovation Hidden within Today’s Variable-Speed DrivesEMEX
 
V2G: Measuring Electric Vehicle Drivers’ Willingness to Co-create Flexibility...
V2G: Measuring Electric Vehicle Drivers’ Willingness to Co-create Flexibility...V2G: Measuring Electric Vehicle Drivers’ Willingness to Co-create Flexibility...
V2G: Measuring Electric Vehicle Drivers’ Willingness to Co-create Flexibility...IEA-ETSAP
 
Enterprise Europe Network | STORY CAES Demo | David Surplus
Enterprise Europe Network | STORY CAES Demo | David SurplusEnterprise Europe Network | STORY CAES Demo | David Surplus
Enterprise Europe Network | STORY CAES Demo | David SurplusInvest Northern Ireland
 
Flinders Island Isolated Power System (IPS) Connect 2016 S KILMETE PUC
Flinders Island Isolated Power System (IPS) Connect 2016 S KILMETE PUCFlinders Island Isolated Power System (IPS) Connect 2016 S KILMETE PUC
Flinders Island Isolated Power System (IPS) Connect 2016 S KILMETE PUCjames hamilton
 
Technical and economic viability of biogas-based electricity generation for d...
Technical and economic viability of biogas-based electricity generation for d...Technical and economic viability of biogas-based electricity generation for d...
Technical and economic viability of biogas-based electricity generation for d...lenses
 
What is Driving Energy Storage Deployment?
What is Driving Energy Storage Deployment?What is Driving Energy Storage Deployment?
What is Driving Energy Storage Deployment?Cedric Christensen
 
Advanced Energy Storage 10-2010
Advanced Energy Storage 10-2010Advanced Energy Storage 10-2010
Advanced Energy Storage 10-2010Larry Stapleton
 
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...IEA-ETSAP
 
British Experience in Renewable Energy
British Experience in Renewable EnergyBritish Experience in Renewable Energy
British Experience in Renewable Energyenergydialog
 
Future energy markets: how and where?
Future energy markets: how and where?Future energy markets: how and where?
Future energy markets: how and where?Fingrid Oyj
 
Energy, Nuclear & Sustainable Power: Stuart Klosinski, Furness Economic Devel...
Energy, Nuclear & Sustainable Power: Stuart Klosinski, Furness Economic Devel...Energy, Nuclear & Sustainable Power: Stuart Klosinski, Furness Economic Devel...
Energy, Nuclear & Sustainable Power: Stuart Klosinski, Furness Economic Devel...Place North West
 
Case Study: Ensuring Security of Supply Through Flexibility
Case Study: Ensuring Security of Supply Through FlexibilityCase Study: Ensuring Security of Supply Through Flexibility
Case Study: Ensuring Security of Supply Through FlexibilityEMEX
 
Energy, Nuclear & Sustainable Power: Rhodri Owen, Horizon Nuclear Power
Energy, Nuclear & Sustainable Power: Rhodri Owen, Horizon Nuclear PowerEnergy, Nuclear & Sustainable Power: Rhodri Owen, Horizon Nuclear Power
Energy, Nuclear & Sustainable Power: Rhodri Owen, Horizon Nuclear PowerPlace North West
 

What's hot (20)

Keynote Interview: Texas as a U.S. Flagship for Energy Transition
Keynote Interview: Texas as a U.S. Flagship for Energy TransitionKeynote Interview: Texas as a U.S. Flagship for Energy Transition
Keynote Interview: Texas as a U.S. Flagship for Energy Transition
 
Energy, Nuclear & Sustainable Power: Christopher Bowes, Nabarro
Energy, Nuclear & Sustainable Power: Christopher Bowes, NabarroEnergy, Nuclear & Sustainable Power: Christopher Bowes, Nabarro
Energy, Nuclear & Sustainable Power: Christopher Bowes, Nabarro
 
Powering Waste Diversion
Powering Waste DiversionPowering Waste Diversion
Powering Waste Diversion
 
Evaluation of the role of energy storages in Europe with TIMES PanEU
Evaluation of the role of energy storages in Europe with TIMES PanEUEvaluation of the role of energy storages in Europe with TIMES PanEU
Evaluation of the role of energy storages in Europe with TIMES PanEU
 
Policy Fair Poster - Molten Carbonate Fuel Cells for SAGD
Policy Fair Poster - Molten Carbonate Fuel Cells for SAGDPolicy Fair Poster - Molten Carbonate Fuel Cells for SAGD
Policy Fair Poster - Molten Carbonate Fuel Cells for SAGD
 
Unlocking the Innovation Hidden within Today’s Variable-Speed Drives
Unlocking the Innovation Hidden within Today’s Variable-Speed DrivesUnlocking the Innovation Hidden within Today’s Variable-Speed Drives
Unlocking the Innovation Hidden within Today’s Variable-Speed Drives
 
V2G: Measuring Electric Vehicle Drivers’ Willingness to Co-create Flexibility...
V2G: Measuring Electric Vehicle Drivers’ Willingness to Co-create Flexibility...V2G: Measuring Electric Vehicle Drivers’ Willingness to Co-create Flexibility...
V2G: Measuring Electric Vehicle Drivers’ Willingness to Co-create Flexibility...
 
Enterprise Europe Network | STORY CAES Demo | David Surplus
Enterprise Europe Network | STORY CAES Demo | David SurplusEnterprise Europe Network | STORY CAES Demo | David Surplus
Enterprise Europe Network | STORY CAES Demo | David Surplus
 
Flinders Island Isolated Power System (IPS) Connect 2016 S KILMETE PUC
Flinders Island Isolated Power System (IPS) Connect 2016 S KILMETE PUCFlinders Island Isolated Power System (IPS) Connect 2016 S KILMETE PUC
Flinders Island Isolated Power System (IPS) Connect 2016 S KILMETE PUC
 
Technical and economic viability of biogas-based electricity generation for d...
Technical and economic viability of biogas-based electricity generation for d...Technical and economic viability of biogas-based electricity generation for d...
Technical and economic viability of biogas-based electricity generation for d...
 
What is Driving Energy Storage Deployment?
What is Driving Energy Storage Deployment?What is Driving Energy Storage Deployment?
What is Driving Energy Storage Deployment?
 
Advanced Energy Storage 10-2010
Advanced Energy Storage 10-2010Advanced Energy Storage 10-2010
Advanced Energy Storage 10-2010
 
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
 
Sgcp13lloyd
Sgcp13lloydSgcp13lloyd
Sgcp13lloyd
 
British Experience in Renewable Energy
British Experience in Renewable EnergyBritish Experience in Renewable Energy
British Experience in Renewable Energy
 
Future energy markets: how and where?
Future energy markets: how and where?Future energy markets: how and where?
Future energy markets: how and where?
 
Transformational adaptation for the wheatbelt: energy tree cropping - Richard...
Transformational adaptation for the wheatbelt: energy tree cropping - Richard...Transformational adaptation for the wheatbelt: energy tree cropping - Richard...
Transformational adaptation for the wheatbelt: energy tree cropping - Richard...
 
Energy, Nuclear & Sustainable Power: Stuart Klosinski, Furness Economic Devel...
Energy, Nuclear & Sustainable Power: Stuart Klosinski, Furness Economic Devel...Energy, Nuclear & Sustainable Power: Stuart Klosinski, Furness Economic Devel...
Energy, Nuclear & Sustainable Power: Stuart Klosinski, Furness Economic Devel...
 
Case Study: Ensuring Security of Supply Through Flexibility
Case Study: Ensuring Security of Supply Through FlexibilityCase Study: Ensuring Security of Supply Through Flexibility
Case Study: Ensuring Security of Supply Through Flexibility
 
Energy, Nuclear & Sustainable Power: Rhodri Owen, Horizon Nuclear Power
Energy, Nuclear & Sustainable Power: Rhodri Owen, Horizon Nuclear PowerEnergy, Nuclear & Sustainable Power: Rhodri Owen, Horizon Nuclear Power
Energy, Nuclear & Sustainable Power: Rhodri Owen, Horizon Nuclear Power
 

Viewers also liked

Bob Smith TransForum West 5-6-14
Bob Smith TransForum West 5-6-14Bob Smith TransForum West 5-6-14
Bob Smith TransForum West 5-6-14Robert Smith
 
Sensitivity Analysis for Transmission Planning
Sensitivity Analysis for Transmission PlanningSensitivity Analysis for Transmission Planning
Sensitivity Analysis for Transmission Planningsdahman
 
Best Practices for NEPA Compliance and Related Permitting for Projects on In...
Best Practices for NEPA Compliance and Related Permitting for  Projects on In...Best Practices for NEPA Compliance and Related Permitting for  Projects on In...
Best Practices for NEPA Compliance and Related Permitting for Projects on In...Trihydro Corporation
 
FERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New ParadigmFERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New ParadigmDNVGLEnergy
 
TRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIATRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIAArun Muraleedharan
 
Flora Flygt: Clean Power Plan Impact on Transmisssion Planning, Development a...
Flora Flygt: Clean Power Plan Impact on Transmisssion Planning, Development a...Flora Flygt: Clean Power Plan Impact on Transmisssion Planning, Development a...
Flora Flygt: Clean Power Plan Impact on Transmisssion Planning, Development a...EnergyTech2015
 
Point to point microwave
Point to point microwavePoint to point microwave
Point to point microwavenandkishorsuman
 

Viewers also liked (7)

Bob Smith TransForum West 5-6-14
Bob Smith TransForum West 5-6-14Bob Smith TransForum West 5-6-14
Bob Smith TransForum West 5-6-14
 
Sensitivity Analysis for Transmission Planning
Sensitivity Analysis for Transmission PlanningSensitivity Analysis for Transmission Planning
Sensitivity Analysis for Transmission Planning
 
Best Practices for NEPA Compliance and Related Permitting for Projects on In...
Best Practices for NEPA Compliance and Related Permitting for  Projects on In...Best Practices for NEPA Compliance and Related Permitting for  Projects on In...
Best Practices for NEPA Compliance and Related Permitting for Projects on In...
 
FERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New ParadigmFERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New Paradigm
 
TRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIATRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIA
 
Flora Flygt: Clean Power Plan Impact on Transmisssion Planning, Development a...
Flora Flygt: Clean Power Plan Impact on Transmisssion Planning, Development a...Flora Flygt: Clean Power Plan Impact on Transmisssion Planning, Development a...
Flora Flygt: Clean Power Plan Impact on Transmisssion Planning, Development a...
 
Point to point microwave
Point to point microwavePoint to point microwave
Point to point microwave
 

Similar to Bob Smith Platts June 18 2014 Transmission Planning Development

Energy distribution in Pakistan
Energy distribution in PakistanEnergy distribution in Pakistan
Energy distribution in PakistanUzma Fatima Ch.
 
WindFarmFeasibility (1).ppt
WindFarmFeasibility (1).pptWindFarmFeasibility (1).ppt
WindFarmFeasibility (1).pptssuserfdb06f
 
The role of energy storage in planning our energy needs in the UAE
The role of energy storage in planning our energy needs in the UAEThe role of energy storage in planning our energy needs in the UAE
The role of energy storage in planning our energy needs in the UAEReedExhibitionsMiddl
 
Planning for the Future: The Changing World of the Electric Transmission System
Planning for the Future: The Changing World of the Electric Transmission SystemPlanning for the Future: The Changing World of the Electric Transmission System
Planning for the Future: The Changing World of the Electric Transmission SystemSociety of Women Engineers
 
15. Future Power System for the year 2030.pptx
15. Future Power System for the year 2030.pptx15. Future Power System for the year 2030.pptx
15. Future Power System for the year 2030.pptxssuser0f80df
 
The merits of integrating renewables with smarter grid carimet
The merits of integrating renewables with smarter grid   carimetThe merits of integrating renewables with smarter grid   carimet
The merits of integrating renewables with smarter grid carimetRick Case, PMP, P.E.
 
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...Resurgent India
 
Global mining enegy report in 2016
Global mining enegy report in 2016Global mining enegy report in 2016
Global mining enegy report in 2016Evita Lee
 
Fixing Our Power Crisis - EAZ v2 28.10.16
Fixing Our Power Crisis - EAZ v2 28.10.16Fixing Our Power Crisis - EAZ v2 28.10.16
Fixing Our Power Crisis - EAZ v2 28.10.16Kachinga-Wankunda Phiri
 
Energy Storage Systems and Technology
Energy Storage Systems and TechnologyEnergy Storage Systems and Technology
Energy Storage Systems and TechnologyBushveld Energy
 
Phila_Navy Yard Energy Innovation Campus Overview
Phila_Navy Yard Energy Innovation Campus OverviewPhila_Navy Yard Energy Innovation Campus Overview
Phila_Navy Yard Energy Innovation Campus OverviewRodney Jones Sr.
 
Renewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectRenewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectPartha Deb
 
What the duck curve tells us about managing a green grid
What the duck curve tells us about managing a green gridWhat the duck curve tells us about managing a green grid
What the duck curve tells us about managing a green gridAndrew Gelston
 
Energy Report - Strange Brew: Adapting to Changing Fundamentals
Energy Report - Strange Brew: Adapting to Changing FundamentalsEnergy Report - Strange Brew: Adapting to Changing Fundamentals
Energy Report - Strange Brew: Adapting to Changing FundamentalsMarcellus Drilling News
 
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Energy Network marcus evans
 
Quaid‑e‑Azam Solar Park 1.pptx
Quaid‑e‑Azam Solar Park 1.pptxQuaid‑e‑Azam Solar Park 1.pptx
Quaid‑e‑Azam Solar Park 1.pptxFarooqCheema7
 

Similar to Bob Smith Platts June 18 2014 Transmission Planning Development (20)

Energy distribution in Pakistan
Energy distribution in PakistanEnergy distribution in Pakistan
Energy distribution in Pakistan
 
WindFarmFeasibility (1).ppt
WindFarmFeasibility (1).pptWindFarmFeasibility (1).ppt
WindFarmFeasibility (1).ppt
 
The role of energy storage in planning our energy needs in the UAE
The role of energy storage in planning our energy needs in the UAEThe role of energy storage in planning our energy needs in the UAE
The role of energy storage in planning our energy needs in the UAE
 
Planning for the Future: The Changing World of the Electric Transmission System
Planning for the Future: The Changing World of the Electric Transmission SystemPlanning for the Future: The Changing World of the Electric Transmission System
Planning for the Future: The Changing World of the Electric Transmission System
 
15. Future Power System for the year 2030.pptx
15. Future Power System for the year 2030.pptx15. Future Power System for the year 2030.pptx
15. Future Power System for the year 2030.pptx
 
Morales_PES_GM_2015.pdf
Morales_PES_GM_2015.pdfMorales_PES_GM_2015.pdf
Morales_PES_GM_2015.pdf
 
Ntpc business strategy
Ntpc business strategyNtpc business strategy
Ntpc business strategy
 
Supply Products for 24/7 Carbon-Free Energy
Supply Products for 24/7 Carbon-Free EnergySupply Products for 24/7 Carbon-Free Energy
Supply Products for 24/7 Carbon-Free Energy
 
The merits of integrating renewables with smarter grid carimet
The merits of integrating renewables with smarter grid   carimetThe merits of integrating renewables with smarter grid   carimet
The merits of integrating renewables with smarter grid carimet
 
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
 
Global mining enegy report in 2016
Global mining enegy report in 2016Global mining enegy report in 2016
Global mining enegy report in 2016
 
Fixing Our Power Crisis - EAZ v2 28.10.16
Fixing Our Power Crisis - EAZ v2 28.10.16Fixing Our Power Crisis - EAZ v2 28.10.16
Fixing Our Power Crisis - EAZ v2 28.10.16
 
Energy Storage Systems and Technology
Energy Storage Systems and TechnologyEnergy Storage Systems and Technology
Energy Storage Systems and Technology
 
Phila_Navy Yard Energy Innovation Campus Overview
Phila_Navy Yard Energy Innovation Campus OverviewPhila_Navy Yard Energy Innovation Campus Overview
Phila_Navy Yard Energy Innovation Campus Overview
 
Renewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectRenewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot Project
 
Energy Optimization
Energy OptimizationEnergy Optimization
Energy Optimization
 
What the duck curve tells us about managing a green grid
What the duck curve tells us about managing a green gridWhat the duck curve tells us about managing a green grid
What the duck curve tells us about managing a green grid
 
Energy Report - Strange Brew: Adapting to Changing Fundamentals
Energy Report - Strange Brew: Adapting to Changing FundamentalsEnergy Report - Strange Brew: Adapting to Changing Fundamentals
Energy Report - Strange Brew: Adapting to Changing Fundamentals
 
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
 
Quaid‑e‑Azam Solar Park 1.pptx
Quaid‑e‑Azam Solar Park 1.pptxQuaid‑e‑Azam Solar Park 1.pptx
Quaid‑e‑Azam Solar Park 1.pptx
 

Bob Smith Platts June 18 2014 Transmission Planning Development

  • 1. Platts 2014 Transmission Planning and Development Conference June 18-19 Arlington, VA Resource Adequacy Methods Moving Forward to Assure Peak Deliverability Bob Smith Director, Energy Delivery Asset Management & Planning
  • 2. Outline • APS System and Generation Resources • Capacity Planning • Energy Efficiency, Renewable Energy and Demand Response • Managing Intermittency • Grid Modernization 2
  • 3. Transmission System & Generation • Electric generating resources help balance the flow of power around the state • Grid built to balance sources of energy – Palo Verde and natural gas generators are located West of Valley while coal generators are located North and East • Generation additions or retirements change this balance • Generation close to customer demand center (metro-Phx) improves transmission import capabilities and maintains a balanced system 3
  • 4. Supply-Demand Gap - 2,000 4,000 6,000 8,000 10,000 12,000 14,000 2014 2016 2018 2020 2022 2024 2026 2028 MW Year Existing Resources Existing Contracts New Utility-Scale Resources 4 • Growth in demand requirements expected to resume • Customer resources expected to triple over planning horizon • Renewable Energy Standard 15% by 2025 • Energy Efficiency Standard 22% by 2020 • Additional resource needs anticipated to be met by increasingly diverse and efficient technologies Demand Requirements
  • 5. 2014-2029 (Forecast) Future Additional Resources 6,613 MW Expected at Peak a. New Utility-Scale Resources Natural Gas 4,205 MW Renewable Energy 425 MW (818 MW nameplate capacity) b. New Customer Resources Energy Efficiency 1,447 MW Distributed Energy 261 MW (722 MW nameplate capacity) Demand Response 275 MW Expected Future Resources 2014 8,124 MW peak requirement 100% met with existing resources 2029 12,982 MW peak requirement 50% met with existing resources b a Existing Utility-Scale Resources Existing Contracts Existing Customer Resources a New Utility-Scale Resources New Customer Resourcesb 5
  • 6. Different Types of Renewables vs. Time of Day Illustration of future peak demand 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 10,000 0 20 40 60 80 100 120 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Load Profile Fixed Position PV Single Axis Tracking PV Wind CSP w/6 Hr Storage MW Level of Renewable Output Hour of Day MW of System Load CTs 6
  • 7. Evolving Customer Demand and Markets • Growth of solar PV is changing customer energy consumption patterns • Generators must be able to start and stop multiple times per day • Fast starting and ramping capability is required in responding to variable output of renewable resources 7 1,000 2,000 3,000 4,000 5,000 1 3 5 7 9 11 13 15 17 19 21 23 MW HOUR Non-Summer Customer Power Consumption 2014 2021 2025 2029 Potential over- generation followed by 8-hr 3,000 MW continuous up-ramp
  • 8. Capacity Contribution of Solar PV Declines as Deployment Levels IncreaseAPS Forecast Peak Load With Photovoltaic (Fixed South Facing) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 MW 1st Addition MW PV 2nd Additon PV 3rd Addition PV 0% 10% 20% 30% 40% 50% 60% 0 500 1000 1500 2000 2500 Range of Possible Penetration by 2025 0 Peak Shifts to Sunset 8 CapacityContributionPercentofNameplate MW of Nameplate Capacity
  • 9. Ocotillo Modernization Project • Retire existing steam units (220 MW) constructed in 1960 • Replace aging steam units with modern combustion turbines – Install five General Electric LMS 100 combustion turbines – 102 MW each – Transmission and natural gas pipeline infrastructure optimized – Net site capacity increased by 290 MW to 620 MW total • Maintain Valley reliability – Generation close to load center – Contingency and voltage support • Responsive unit operations – Quick starting and ramping – Renewable integration • Environmental attributes – Emissions and water consumption • In-service planned for summer 2018 9
  • 11. Conclusions • Transmission system must accommodate entirety of peak capacity needs – Reserves – Back-up capacity • Diverse resource fleet includes renewables and energy efficiency – Significant growth expected • Flexible generation aligns with capacity needs and complements growing renewable energy fleet • Investments in modernizing grid continuing 11

Editor's Notes

  1. We will also talk about why we chose a specific type of replacement generation – our operating environment is changing especially with all the distributed roof-top solar being added to the system so we’ll provide the context for why this specific type of generation makes sense.
  2. As we have discussed many times, the recession impacted everyone’s businesses and AZ was hit hard and took customer demand growth to essentially zero. Based on outside population and economic forecasts as well as our own, we anticipate AZ’s economy to improve. It’s been a sluggish recovery but we expect growth to resume. About 3% average before customer resources, 2% after customer resources 51,236 GWH - 33,609 GWH = 17,627 / 33,609 = 52.4% or about 35% after EE,DE US Census Bureau AZ Dept of Admin U of A Keller School of Mgt and Bus Other local forecasting agencies and banks for reasonableness Expiring purchase contracts means APS will need additional resources by 2017
  3. About 30% of resource additions are anticipated to come from customers – of course we have no operational control over these resources. Customers decide whether or not to invest, then nature decides whether they operate or not. This places a lot of dependence on the customer to actually make investment decisions, and places a lot of dependence on the utility generation fleet and grid to be able to respond in order to keep the lights on.
  4. Let’s talk now about a concept called intermittency. As for distributed solar photovoltaic (fixed position), the typical output profile in the summer time looks like the blue line. This profile is compared against our typical hourly load profile on our system. We peak (customers demand the most energy) at around 5pm…..still very hot and people starting to get home from work and turn on lights and make dinner. Solutions to this mis-match include single axis tracking solar that tracks the sun as it moves across the horizon, and the use of thermal energy storage like at our Solana facility. Let’s put this in context now of what we talked about earlier when we discussed resource costs. Remember when we discussed the integration costs? The intermittency, or variability, of solar and wind resources necessitates backing wind and solar resources up with natural gas generation. Natural gas generation is flexible and can quickly respond to changing conditions on our system. Of course this has a cost associated with it and we take all that into account when evaluating the relative economics of renewable resources against other alternatives.
  5. While this project has little to do with our longer term procurement needs, by the same token we don’t want to be blind to these needs. So it was important that whatever the generation technology was, it had to be able to support our overall needs to add more responsive/flexible resources. The challenges integrating renewable energy aren’t going away and will just get worse as more renewables (namely roof-top solar) are added to the system. We will need generation that can respond to the intermittency and the fact that solar doesn’t align with our peak very well. Natural gas generation, and specifically the types of fast-starting units we’re adding with this project, will be needed even more-so into the future.
  6. So given the uncertainties around DE deployment that we’ve talked about, the bottom line is how much should we depend on in our resource plans. Today, because of solar production peaks about 1pm and is declining by 5pm, we credit 50% of a project’s nameplate value toward meeting our peak demand. So for 100 MW of distributed solar on our system, we credit 50 MW toward meeting our peak because by the time we peak at 5pm, the sun is lower on the horizon and fixed panel solar produces about 50% of its full capacity by that time of day. For single axis tracking, what we typically use for utility scale applications, we credit 70% capacity value. Now let’s look at the blue chart in the upper right corner. With increasing levels of solar penetration on our system, eventually, the peak that we have to meet with conventional resources (the area in blue) will eventually move toward sunset because solar PV will no longer be producing energy at that time. Once our peak moves to sunset, the capacity value of solar that we can credit toward meeting our peak is zero….meaning that no matter how solar pv is developed at that point, we will still have to add additional resources to meet the later peak. Solar will continue to provide fuel savings benefits, but will not defer new resource additions.
  7. 9
  8. INVESTMENT $170 million over the next 5 years Over 5,000 Communicating Fault Indicators (pinpoints where to look if there is a problem) ADMS (see third item below) $300 million out to 2025 Communication Protocols Cellular Radio (ex: microwave) Fiber optic ADMS / EMS – Advanced Distribution Management System / Energy Management System ($25 MM investment over next five years) Very advanced operating system that allows integration of advanced grid technologies Provides ability to monitor the distribution system components in real-time to optimize performance. AMI – Automated Metering Infrastructure – Project 99.9% complete, completion anticipated end of May. Total devices deployed: 1.1 million Involves 3 basic functions Smart meters – Two-way communication with the utility on electricity usage Communication system – Involves both the hardware and software for encrypted communication between smart meters, substation and distribution automation equipment Meter data management system – Data storage that enables advanced analysis and processing Benefits: Enables customers to manage costs by providing monitoring tools for energy usage, change of service plans, or connect and disconnect service from their computer. Enables APS to offer a host of new programs including “Pick a Due Date”, which allows customers to choose the payment date that best fits their lifestyle. Enables APS to monitor voltage levels and power quality to help ensure reliable service and effectively plan for future energy needs. Provides safety and environmental benefits by avoiding millions of driving miles by APS employees to remotely perform customer read-ins, read-outs, rate changes, disconnects, and reconnects. Produces substantial amounts of new data that can be transformed into actions such as reducing the number of unplanned transformer failures, identifying power outages, and optimizing placement of future grid modernization technologies for even more enhanced performance, monitoring, and control. AMI Solar Production Meters Meters that relay energy the solar installation produces back to data management centers. Automated Switches Provide fault detection and automatic sectionalizing, and are fully SCADA (Supervisory Control and Data Acquisition) compatible - meaning they communicate with control software. They include an integrated battery management system and battery, permitting dead-line operation. Automated Thermostats Demand response component that sends signals to adjust temps on customer thermostats during peak demand. Demand Response Change in end-users’ power usage in response to pricing mechanisms. (Communicating) Fault Indicators – 2.500 to be installed over the next five years Devices that can be installed on distribution lines to detect whether current is flowing on the line and then communicate that status via communications or visual indicator. Fiber Backhaul Refers to fiber optic facilities carrying traffic back to data centers or regional network nodes. This is relevant because all smart grid applications use communication network infrastructures. Integrated Volt/VAR Control (VAR = voltage-ampere reactive) Continuously analyzes and controls regulators and capacitor banks to manage power factor and voltages. This flattens each feeder’s voltage profile and lowers average voltages, resulting in energy savings. Substation Health Monitoring Involves the installation of dissolved gas analysis (DGA) monitors (see TOAN above), transformer health monitors, bushing and breaker monitors to detect and prevent failure of equipment resulting in reduced outages and maintenance. TOAN – Transformer Oil Analysis Automated online monitoring of dissolved gases in transformer oil with analysis and notification of abnormalities. APS invented this in 2005 and was the first in the nation to use it. In 2008, this product earned APS the Edison Award. Transformer Load Management Tool that aggregates historical AMI data to analyze overloaded transformers. “What-If” analysis allows the right-sizing of transformers based on actual meter load information
  9. We will also talk about why we chose a specific type of replacement generation – our operating environment is changing especially with all the distributed roof-top solar being added to the system so we’ll provide the context for why this specific type of generation makes sense.
  10. 12