SlideShare a Scribd company logo
1 of 14
The importance of
integration of subsurface
with surface facilities design
John Harley, Regional Director INTECSEA Consulting
David Gorsuch, Technical Director OPC
WorleyParsons Structure
Major
Engineering
Project Delivery
 Strong FEL technical team
 Deepwater SURF
 Topsides Facilities
 Floating Solutions
 FA
 CAPEX
 Offshore commissioning
 Decommissioning (Aberdeen)
 Regulations, consents and licences
 UK energy market, including market reforms
 Energy industry policy
 Proven successful relationships with Governments,
including DECC
 Transaction Services
North Sea
Fabrication Subsea
& Topside modules
WorleyParsons Group and Friends
Major
Engineering
Project Delivery
 Strong FEL technical team
 Deepwater SURF
 Topsides Facilities
 Floating Solutions
 FA
 CAPEX
 Offshore commissioning
 Decommissioning (Aberdeen)
 Regulations, consents and licences
 UK energy market, including market reforms
 Energy industry policy
 Proven successful relationships with Governments,
including DECC
 Transaction Services
North Sea
Fabrication Subsea
& Topside modules
What is Value?
 Value - Defined as “The material or monetary worth of
something”.
 Maximum Value - the correct development, chosen first time,
right-sized
 Inefficiency – Defined as “the magnitude of the value
that can be lost”
 Risks not clearly identified and resolved
Value Destruction – an example
200 MMbbl of recoverable oil
No sales gas product
1200 m water depth
Fast track project
(36 months to first oil)
25 year production life
Oil price of $100/bbl
Inflation at 2.5%
200 MMbbl of recoverable oil
No sales gas product
1200 m water depth
Fast track project (36 months to first oil)
25 year production life
Oil price of $100/bbl
Inflation at 2.5%
 Initial production plateau not achieved
 Only 65% of intended production for 3 years
Production Profile
Same total oil recovered,
but slower rate of recovery
Pre-Tax NPV
Missed Plateau Value Impact
Original FDP Missed Plateau
NPV, MM$ 4,074 3,621
Delta, MM$ - -453
Delta, % - -11.1%
IRR, % 22% 20%
 Additional Production and Water Injector wells needed after only 2
years of operation
 CAPEX required for drilling, equipment procurement and installation.
(Loss of production during installation/hook-up/commissioning is ignored)
Additional Wells Value Impact
Original FDP Missed Plateau Extra Wells
DRILLEX, MM$ 1,600 1,600 2,400
CAPEX, MM$ 3,220 3,220 4,220
Total, MM$ 4,820 4,820 6,620
Delta, % - 0% +37%
 Pre-Tax NPV severely eroded
 IRRs remain attractive
(IRR by itself is not a reliable indicator of good/bad project)
Value Impact
Original FDP Missed Plateau Extra Wells
NPV, MM$ 4,074 3,621 2,075
Delta, MM$ - -453 -2,000
Delta, % - -11.1% -55.2%
IRR, % 22% 20% 16%
Value Protection
FRAMING
EVALUATE
Integrated
Production
Modelling
Cost/ Schedule
Economic
modelling
AUDITRESERVES
FINDINGS
AllCREDIBLEOPTIONS
Prospect Metrics
Economic Profile
Current Risk Level
Understand commitments
Business Plan
Comparative life cycle costs
New Business plan
Exit strategy
DSP
ANALYSE
Current Plan FID
RECOMMENDVISUALISEDrivers
AUDITFDP
Non-Tech Risks
Oilfield Production Consultants (OPC)
The OPC-Worley Parsons INTECSEA partnership
 Who are OPC? We are a specialist supplier of subsurface engineering,
geosciences and production technology expertise globally for over 25 years.
OPC offices – London, Aberdeen, Stavanger, Houston, Astana, Doha & Basra.
 The strategic partnership with INTECSEA /WorleyParsons is designed to allow
proper integration of predictions of the behaviour of the sub-surface with
surface facilities design.
 Our aim – a fully integrated Reservoir to Market (R2M) full field development
planning platform
Integrating reservoir understanding (OPC Group)… with surface facilities design (WorleyParsons Group)
Oilfield Production Consultants (OPC)
The value of the partnership
The importance of integration of subsurface with surface facilities design
 Communication – passing the right information at the right time and using
the right vocabulary.
 Management of uncertainty – designing for robustness not optimisation
 Front-end loading of facilities design – ensuring all the appropriate
options are considered.
Optimal FDP
Oilfield Production Consultants (OPC)
Low Oil Price Scenario (LOPS) planning
Adapting to a new world…
 Many plans developed in the context of $100 oil no longer make sense.
 Assets still need to be monetised and revenue needs to be generated. In
many cases, this is still possible but requires a fresh look at the
development.
 OPC and INTECSEA/WorleyParsons can help companies to carry out
Prospect Re-framing (PReF) by stepping back and taking a completely new,
holistic view of developments against the backdrop of…
 $50 oil
 Low appetite for risk
Thank you
David Gorsuch
Technical Director
Oilfield Production Consultants (OPC) Ltd
1-2 Apollo Studios, Charlton Kin’s Road,
London NW5 2SB
Mob: +44 (0)7585 770455
Tel: +44 (0)20 7428 1111
e-mail: david.gorsuch@opc.co.uk ww.opc.co.uk
John Harley
Regional Director
Consulting
Lansbury Estate
102 Lower Guildford Road,
Surrey, GU21 2EP
Direct: +44 (0) 1483 878 504
Mobile: +44 (0) 7760 669 199
john.harley@worleyparsons.com
www.worleyparsons.com

More Related Content

What's hot

Webinar: Carbon capture through innovative comercial structuring in the canad...
Webinar: Carbon capture through innovative comercial structuring in the canad...Webinar: Carbon capture through innovative comercial structuring in the canad...
Webinar: Carbon capture through innovative comercial structuring in the canad...Global CCS Institute
 
New base 562 special 17 march 2015
New base 562 special 17 march  2015New base 562 special 17 march  2015
New base 562 special 17 march 2015Khaled Al Awadi
 
New base special 04 february 2014
New base special  04 february 2014New base special  04 february 2014
New base special 04 february 2014Khaled Al Awadi
 
Webinar: CCS major project development lessons from the ZeroGen experience
Webinar: CCS major project development lessons from the ZeroGen experienceWebinar: CCS major project development lessons from the ZeroGen experience
Webinar: CCS major project development lessons from the ZeroGen experienceGlobal CCS Institute
 
Cabot Oil & Gas Marcellus & Eagle Ford Presentation at BOA Merrill Lynch Glob...
Cabot Oil & Gas Marcellus & Eagle Ford Presentation at BOA Merrill Lynch Glob...Cabot Oil & Gas Marcellus & Eagle Ford Presentation at BOA Merrill Lynch Glob...
Cabot Oil & Gas Marcellus & Eagle Ford Presentation at BOA Merrill Lynch Glob...Marcellus Drilling News
 
New base special 26 february 2014
New base special  26 february 2014New base special  26 february 2014
New base special 26 february 2014Khaled Al Awadi
 
Ot interim report q4 – 2016
Ot interim report q4 – 2016Ot interim report q4 – 2016
Ot interim report q4 – 2016Natasja de Jong
 
Technology in BP - Factsheet
Technology in BP - FactsheetTechnology in BP - Factsheet
Technology in BP - Factsheetbp
 
New base special 08 june 2014
New base special  08 june 2014New base special  08 june 2014
New base special 08 june 2014Khaled Al Awadi
 
Cabot Oil & Gas Slide Presentation at Merrill Lunch Energy Conference
Cabot Oil & Gas Slide Presentation at Merrill Lunch Energy ConferenceCabot Oil & Gas Slide Presentation at Merrill Lunch Energy Conference
Cabot Oil & Gas Slide Presentation at Merrill Lunch Energy ConferenceMarcellus Drilling News
 
AZMET-Newsletter 2016-17
AZMET-Newsletter 2016-17AZMET-Newsletter 2016-17
AZMET-Newsletter 2016-17Charl Du Preez
 
06 01-18 rdc investor deck
06 01-18 rdc investor deck06 01-18 rdc investor deck
06 01-18 rdc investor deckRowanCompanies
 
New base special 12 february 2014
New base special  12 february 2014New base special  12 february 2014
New base special 12 february 2014Khaled Al Awadi
 
Pareto securities corporate bond conference 23 January 2014
Pareto securities corporate bond conference 23 January 2014Pareto securities corporate bond conference 23 January 2014
Pareto securities corporate bond conference 23 January 2014PA Resources AB
 
BluMakers: Oilsands Game Changers. Eliminating Tailing Ponds - very profitably.
BluMakers: Oilsands Game Changers. Eliminating Tailing Ponds - very profitably.BluMakers: Oilsands Game Changers. Eliminating Tailing Ponds - very profitably.
BluMakers: Oilsands Game Changers. Eliminating Tailing Ponds - very profitably.BluMakers, SageCos, Sage OverDrives
 
Project Synopsis - Modular Refineries
Project Synopsis - Modular RefineriesProject Synopsis - Modular Refineries
Project Synopsis - Modular RefineriesAlabo BRIGGS
 
Capital Power 2015 Annual Meeting Presentation
Capital Power 2015 Annual Meeting PresentationCapital Power 2015 Annual Meeting Presentation
Capital Power 2015 Annual Meeting PresentationCapital Power
 
PA Resources Q4 Interim report
PA Resources Q4 Interim report PA Resources Q4 Interim report
PA Resources Q4 Interim report PA Resources AB
 
New base energy news october 2018 no 1202 by khaled al awadi
New base energy news october 2018 no 1202  by khaled al awadiNew base energy news october 2018 no 1202  by khaled al awadi
New base energy news october 2018 no 1202 by khaled al awadiKhaled Al Awadi
 

What's hot (20)

Webinar: Carbon capture through innovative comercial structuring in the canad...
Webinar: Carbon capture through innovative comercial structuring in the canad...Webinar: Carbon capture through innovative comercial structuring in the canad...
Webinar: Carbon capture through innovative comercial structuring in the canad...
 
New base 562 special 17 march 2015
New base 562 special 17 march  2015New base 562 special 17 march  2015
New base 562 special 17 march 2015
 
New base special 04 february 2014
New base special  04 february 2014New base special  04 february 2014
New base special 04 february 2014
 
Webinar: CCS major project development lessons from the ZeroGen experience
Webinar: CCS major project development lessons from the ZeroGen experienceWebinar: CCS major project development lessons from the ZeroGen experience
Webinar: CCS major project development lessons from the ZeroGen experience
 
Cabot Oil & Gas Marcellus & Eagle Ford Presentation at BOA Merrill Lynch Glob...
Cabot Oil & Gas Marcellus & Eagle Ford Presentation at BOA Merrill Lynch Glob...Cabot Oil & Gas Marcellus & Eagle Ford Presentation at BOA Merrill Lynch Glob...
Cabot Oil & Gas Marcellus & Eagle Ford Presentation at BOA Merrill Lynch Glob...
 
New base special 26 february 2014
New base special  26 february 2014New base special  26 february 2014
New base special 26 february 2014
 
Ot interim report q4 – 2016
Ot interim report q4 – 2016Ot interim report q4 – 2016
Ot interim report q4 – 2016
 
Technology in BP - Factsheet
Technology in BP - FactsheetTechnology in BP - Factsheet
Technology in BP - Factsheet
 
New base special 08 june 2014
New base special  08 june 2014New base special  08 june 2014
New base special 08 june 2014
 
Cabot Oil & Gas Slide Presentation at Merrill Lunch Energy Conference
Cabot Oil & Gas Slide Presentation at Merrill Lunch Energy ConferenceCabot Oil & Gas Slide Presentation at Merrill Lunch Energy Conference
Cabot Oil & Gas Slide Presentation at Merrill Lunch Energy Conference
 
AZMET-Newsletter 2016-17
AZMET-Newsletter 2016-17AZMET-Newsletter 2016-17
AZMET-Newsletter 2016-17
 
06 01-18 rdc investor deck
06 01-18 rdc investor deck06 01-18 rdc investor deck
06 01-18 rdc investor deck
 
New base special 12 february 2014
New base special  12 february 2014New base special  12 february 2014
New base special 12 february 2014
 
Q1 2013 corporate update
Q1 2013 corporate updateQ1 2013 corporate update
Q1 2013 corporate update
 
Pareto securities corporate bond conference 23 January 2014
Pareto securities corporate bond conference 23 January 2014Pareto securities corporate bond conference 23 January 2014
Pareto securities corporate bond conference 23 January 2014
 
BluMakers: Oilsands Game Changers. Eliminating Tailing Ponds - very profitably.
BluMakers: Oilsands Game Changers. Eliminating Tailing Ponds - very profitably.BluMakers: Oilsands Game Changers. Eliminating Tailing Ponds - very profitably.
BluMakers: Oilsands Game Changers. Eliminating Tailing Ponds - very profitably.
 
Project Synopsis - Modular Refineries
Project Synopsis - Modular RefineriesProject Synopsis - Modular Refineries
Project Synopsis - Modular Refineries
 
Capital Power 2015 Annual Meeting Presentation
Capital Power 2015 Annual Meeting PresentationCapital Power 2015 Annual Meeting Presentation
Capital Power 2015 Annual Meeting Presentation
 
PA Resources Q4 Interim report
PA Resources Q4 Interim report PA Resources Q4 Interim report
PA Resources Q4 Interim report
 
New base energy news october 2018 no 1202 by khaled al awadi
New base energy news october 2018 no 1202  by khaled al awadiNew base energy news october 2018 no 1202  by khaled al awadi
New base energy news october 2018 no 1202 by khaled al awadi
 

Viewers also liked

Separador de hidrocarburos,separador de grasas, bombeo, pluviales, tratamient...
Separador de hidrocarburos,separador de grasas, bombeo, pluviales, tratamient...Separador de hidrocarburos,separador de grasas, bombeo, pluviales, tratamient...
Separador de hidrocarburos,separador de grasas, bombeo, pluviales, tratamient...Techneau España S.L.
 
Girish-Kabra-Centrica-Energy1
Girish-Kabra-Centrica-Energy1Girish-Kabra-Centrica-Energy1
Girish-Kabra-Centrica-Energy1Girish Kabra
 
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedMajor CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedEnergy Construction Forum
 
000-GENERAL presentation_rev06
000-GENERAL presentation_rev06000-GENERAL presentation_rev06
000-GENERAL presentation_rev06Stefan Erents
 
Limpieza tanque Estaciòn de Bombeo Servidas catuche 2007
Limpieza tanque Estaciòn de Bombeo Servidas catuche 2007Limpieza tanque Estaciòn de Bombeo Servidas catuche 2007
Limpieza tanque Estaciòn de Bombeo Servidas catuche 2007Nombre Apellidos
 
Decision making in the oil and gas industry
Decision making in the oil and gas industryDecision making in the oil and gas industry
Decision making in the oil and gas industryPalantir_Solutions
 
Field Development Project Report - EAB_7_157
Field Development Project Report - EAB_7_157Field Development Project Report - EAB_7_157
Field Development Project Report - EAB_7_157Shaoor Kamal
 
Enterprise Project Management
Enterprise Project ManagementEnterprise Project Management
Enterprise Project ManagementMartin Mehalchin
 
Mantenimiento de estaciones de bombeo
Mantenimiento de estaciones de bombeoMantenimiento de estaciones de bombeo
Mantenimiento de estaciones de bombeoJ' Melendez
 
Manual de operación y mantenimiento estacion de bombeo de desague
Manual de operación y mantenimiento estacion de bombeo de desagueManual de operación y mantenimiento estacion de bombeo de desague
Manual de operación y mantenimiento estacion de bombeo de desagueWilmer Mara Q
 
Las Centrales HidroeléCtricas
Las Centrales HidroeléCtricasLas Centrales HidroeléCtricas
Las Centrales HidroeléCtricasE4A30JOSELUIS
 
Centrales Hidroelectricas
Centrales HidroelectricasCentrales Hidroelectricas
Centrales Hidroelectricasiomax
 
Centrales hidroelectricas
Centrales hidroelectricasCentrales hidroelectricas
Centrales hidroelectricasSandra Cañas
 
Las 5 Principales Centrales Hidroeléctricas en el Perú.
Las 5 Principales Centrales Hidroeléctricas en el Perú.Las 5 Principales Centrales Hidroeléctricas en el Perú.
Las 5 Principales Centrales Hidroeléctricas en el Perú.Daniel Alave
 
Accelerated conceptual engineering (ACE)
Accelerated conceptual engineering (ACE)Accelerated conceptual engineering (ACE)
Accelerated conceptual engineering (ACE)Assetdev
 

Viewers also liked (20)

Separador de hidrocarburos,separador de grasas, bombeo, pluviales, tratamient...
Separador de hidrocarburos,separador de grasas, bombeo, pluviales, tratamient...Separador de hidrocarburos,separador de grasas, bombeo, pluviales, tratamient...
Separador de hidrocarburos,separador de grasas, bombeo, pluviales, tratamient...
 
Girish-Kabra-Centrica-Energy1
Girish-Kabra-Centrica-Energy1Girish-Kabra-Centrica-Energy1
Girish-Kabra-Centrica-Energy1
 
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedMajor CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
 
000-GENERAL presentation_rev06
000-GENERAL presentation_rev06000-GENERAL presentation_rev06
000-GENERAL presentation_rev06
 
Obras estación bombeo 0
Obras estación bombeo 0Obras estación bombeo 0
Obras estación bombeo 0
 
Limpieza tanque Estaciòn de Bombeo Servidas catuche 2007
Limpieza tanque Estaciòn de Bombeo Servidas catuche 2007Limpieza tanque Estaciòn de Bombeo Servidas catuche 2007
Limpieza tanque Estaciòn de Bombeo Servidas catuche 2007
 
Construcción estación de bombeo
Construcción estación de bombeoConstrucción estación de bombeo
Construcción estación de bombeo
 
Decision making in the oil and gas industry
Decision making in the oil and gas industryDecision making in the oil and gas industry
Decision making in the oil and gas industry
 
Field Development Project Report - EAB_7_157
Field Development Project Report - EAB_7_157Field Development Project Report - EAB_7_157
Field Development Project Report - EAB_7_157
 
Enterprise Project Management
Enterprise Project ManagementEnterprise Project Management
Enterprise Project Management
 
Diseño estación de bombeo
Diseño estación de bombeoDiseño estación de bombeo
Diseño estación de bombeo
 
MSc group project presentation
MSc group project presentationMSc group project presentation
MSc group project presentation
 
Mantenimiento de estaciones de bombeo
Mantenimiento de estaciones de bombeoMantenimiento de estaciones de bombeo
Mantenimiento de estaciones de bombeo
 
Manual de operación y mantenimiento estacion de bombeo de desague
Manual de operación y mantenimiento estacion de bombeo de desagueManual de operación y mantenimiento estacion de bombeo de desague
Manual de operación y mantenimiento estacion de bombeo de desague
 
Iso 9001 2015
Iso 9001 2015Iso 9001 2015
Iso 9001 2015
 
Las Centrales HidroeléCtricas
Las Centrales HidroeléCtricasLas Centrales HidroeléCtricas
Las Centrales HidroeléCtricas
 
Centrales Hidroelectricas
Centrales HidroelectricasCentrales Hidroelectricas
Centrales Hidroelectricas
 
Centrales hidroelectricas
Centrales hidroelectricasCentrales hidroelectricas
Centrales hidroelectricas
 
Las 5 Principales Centrales Hidroeléctricas en el Perú.
Las 5 Principales Centrales Hidroeléctricas en el Perú.Las 5 Principales Centrales Hidroeléctricas en el Perú.
Las 5 Principales Centrales Hidroeléctricas en el Perú.
 
Accelerated conceptual engineering (ACE)
Accelerated conceptual engineering (ACE)Accelerated conceptual engineering (ACE)
Accelerated conceptual engineering (ACE)
 

Similar to The Importance of Integration of subsurface with surface facilities design

Energold Q1 2016 Corporate Presentation
Energold Q1 2016 Corporate PresentationEnergold Q1 2016 Corporate Presentation
Energold Q1 2016 Corporate PresentationAdnet Communications
 
Energold Drilling Corp. - Presentation
Energold Drilling Corp. - PresentationEnergold Drilling Corp. - Presentation
Energold Drilling Corp. - PresentationAdnet Communications
 
Generic slides: AMEC in the Middle East, Africa and CIS
Generic slides: AMEC in the Middle East, Africa and CISGeneric slides: AMEC in the Middle East, Africa and CIS
Generic slides: AMEC in the Middle East, Africa and CISZhenya85
 
JP Morgan Inaugural Energy Equity Investor Conference
JP Morgan Inaugural Energy Equity Investor ConferenceJP Morgan Inaugural Energy Equity Investor Conference
JP Morgan Inaugural Energy Equity Investor ConferenceDevon Energy Corporation
 
Energold Drilling Corp. Corporate Presentation May 2018
Energold Drilling Corp. Corporate Presentation May 2018Energold Drilling Corp. Corporate Presentation May 2018
Energold Drilling Corp. Corporate Presentation May 2018Adnet Communications
 
Energold Corporate Presentation - September 2015
Energold Corporate Presentation - September 2015Energold Corporate Presentation - September 2015
Energold Corporate Presentation - September 2015Adnet Communications
 
Exxon Mobil Annual Report 2006
Exxon Mobil Annual Report 2006Exxon Mobil Annual Report 2006
Exxon Mobil Annual Report 2006earningsreport
 
In Situ Oil Sands SOR Reduction Initiative
In Situ Oil Sands SOR Reduction InitiativeIn Situ Oil Sands SOR Reduction Initiative
In Situ Oil Sands SOR Reduction Initiativephilbrown49
 

Similar to The Importance of Integration of subsurface with surface facilities design (20)

Energold Presentation
Energold PresentationEnergold Presentation
Energold Presentation
 
Energold Q1 2016 Corporate Presentation
Energold Q1 2016 Corporate PresentationEnergold Q1 2016 Corporate Presentation
Energold Q1 2016 Corporate Presentation
 
Energold Drilling Corp. - Presentation
Energold Drilling Corp. - PresentationEnergold Drilling Corp. - Presentation
Energold Drilling Corp. - Presentation
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate Presentation
 
Generic slides: AMEC in the Middle East, Africa and CIS
Generic slides: AMEC in the Middle East, Africa and CISGeneric slides: AMEC in the Middle East, Africa and CIS
Generic slides: AMEC in the Middle East, Africa and CIS
 
JP Morgan Inaugural Energy Equity Investor Conference
JP Morgan Inaugural Energy Equity Investor ConferenceJP Morgan Inaugural Energy Equity Investor Conference
JP Morgan Inaugural Energy Equity Investor Conference
 
Corporate Presentation June 2017
Corporate Presentation June 2017Corporate Presentation June 2017
Corporate Presentation June 2017
 
Egd
EgdEgd
Egd
 
Presentation
PresentationPresentation
Presentation
 
Energold Drilling Corp. Corporate Presentation May 2018
Energold Drilling Corp. Corporate Presentation May 2018Energold Drilling Corp. Corporate Presentation May 2018
Energold Drilling Corp. Corporate Presentation May 2018
 
Egd dec2015
Egd dec2015Egd dec2015
Egd dec2015
 
July2016
July2016July2016
July2016
 
Egd nov2013
Egd nov2013Egd nov2013
Egd nov2013
 
Energold Presentation - July 2014
Energold Presentation - July 2014Energold Presentation - July 2014
Energold Presentation - July 2014
 
Energold Corporate Presentation - September 2015
Energold Corporate Presentation - September 2015Energold Corporate Presentation - September 2015
Energold Corporate Presentation - September 2015
 
Energold presentation-sept2016
Energold presentation-sept2016Energold presentation-sept2016
Energold presentation-sept2016
 
Energold Presentation - May 2016
Energold Presentation - May 2016Energold Presentation - May 2016
Energold Presentation - May 2016
 
Exxon Mobil Annual Report 2006
Exxon Mobil Annual Report 2006Exxon Mobil Annual Report 2006
Exxon Mobil Annual Report 2006
 
In Situ Oil Sands SOR Reduction Initiative
In Situ Oil Sands SOR Reduction InitiativeIn Situ Oil Sands SOR Reduction Initiative
In Situ Oil Sands SOR Reduction Initiative
 
Sept2018 egd
Sept2018 egdSept2018 egd
Sept2018 egd
 

Recently uploaded

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 

Recently uploaded (20)

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 

The Importance of Integration of subsurface with surface facilities design

  • 1. The importance of integration of subsurface with surface facilities design John Harley, Regional Director INTECSEA Consulting David Gorsuch, Technical Director OPC
  • 2. WorleyParsons Structure Major Engineering Project Delivery  Strong FEL technical team  Deepwater SURF  Topsides Facilities  Floating Solutions  FA  CAPEX  Offshore commissioning  Decommissioning (Aberdeen)  Regulations, consents and licences  UK energy market, including market reforms  Energy industry policy  Proven successful relationships with Governments, including DECC  Transaction Services North Sea Fabrication Subsea & Topside modules
  • 3. WorleyParsons Group and Friends Major Engineering Project Delivery  Strong FEL technical team  Deepwater SURF  Topsides Facilities  Floating Solutions  FA  CAPEX  Offshore commissioning  Decommissioning (Aberdeen)  Regulations, consents and licences  UK energy market, including market reforms  Energy industry policy  Proven successful relationships with Governments, including DECC  Transaction Services North Sea Fabrication Subsea & Topside modules
  • 4. What is Value?  Value - Defined as “The material or monetary worth of something”.  Maximum Value - the correct development, chosen first time, right-sized  Inefficiency – Defined as “the magnitude of the value that can be lost”  Risks not clearly identified and resolved
  • 5. Value Destruction – an example 200 MMbbl of recoverable oil No sales gas product 1200 m water depth Fast track project (36 months to first oil) 25 year production life Oil price of $100/bbl Inflation at 2.5% 200 MMbbl of recoverable oil No sales gas product 1200 m water depth Fast track project (36 months to first oil) 25 year production life Oil price of $100/bbl Inflation at 2.5%
  • 6.  Initial production plateau not achieved  Only 65% of intended production for 3 years Production Profile Same total oil recovered, but slower rate of recovery
  • 7. Pre-Tax NPV Missed Plateau Value Impact Original FDP Missed Plateau NPV, MM$ 4,074 3,621 Delta, MM$ - -453 Delta, % - -11.1% IRR, % 22% 20%
  • 8.  Additional Production and Water Injector wells needed after only 2 years of operation  CAPEX required for drilling, equipment procurement and installation. (Loss of production during installation/hook-up/commissioning is ignored) Additional Wells Value Impact Original FDP Missed Plateau Extra Wells DRILLEX, MM$ 1,600 1,600 2,400 CAPEX, MM$ 3,220 3,220 4,220 Total, MM$ 4,820 4,820 6,620 Delta, % - 0% +37%
  • 9.  Pre-Tax NPV severely eroded  IRRs remain attractive (IRR by itself is not a reliable indicator of good/bad project) Value Impact Original FDP Missed Plateau Extra Wells NPV, MM$ 4,074 3,621 2,075 Delta, MM$ - -453 -2,000 Delta, % - -11.1% -55.2% IRR, % 22% 20% 16%
  • 10. Value Protection FRAMING EVALUATE Integrated Production Modelling Cost/ Schedule Economic modelling AUDITRESERVES FINDINGS AllCREDIBLEOPTIONS Prospect Metrics Economic Profile Current Risk Level Understand commitments Business Plan Comparative life cycle costs New Business plan Exit strategy DSP ANALYSE Current Plan FID RECOMMENDVISUALISEDrivers AUDITFDP Non-Tech Risks
  • 11. Oilfield Production Consultants (OPC) The OPC-Worley Parsons INTECSEA partnership  Who are OPC? We are a specialist supplier of subsurface engineering, geosciences and production technology expertise globally for over 25 years. OPC offices – London, Aberdeen, Stavanger, Houston, Astana, Doha & Basra.  The strategic partnership with INTECSEA /WorleyParsons is designed to allow proper integration of predictions of the behaviour of the sub-surface with surface facilities design.  Our aim – a fully integrated Reservoir to Market (R2M) full field development planning platform Integrating reservoir understanding (OPC Group)… with surface facilities design (WorleyParsons Group)
  • 12. Oilfield Production Consultants (OPC) The value of the partnership The importance of integration of subsurface with surface facilities design  Communication – passing the right information at the right time and using the right vocabulary.  Management of uncertainty – designing for robustness not optimisation  Front-end loading of facilities design – ensuring all the appropriate options are considered. Optimal FDP
  • 13. Oilfield Production Consultants (OPC) Low Oil Price Scenario (LOPS) planning Adapting to a new world…  Many plans developed in the context of $100 oil no longer make sense.  Assets still need to be monetised and revenue needs to be generated. In many cases, this is still possible but requires a fresh look at the development.  OPC and INTECSEA/WorleyParsons can help companies to carry out Prospect Re-framing (PReF) by stepping back and taking a completely new, holistic view of developments against the backdrop of…  $50 oil  Low appetite for risk
  • 14. Thank you David Gorsuch Technical Director Oilfield Production Consultants (OPC) Ltd 1-2 Apollo Studios, Charlton Kin’s Road, London NW5 2SB Mob: +44 (0)7585 770455 Tel: +44 (0)20 7428 1111 e-mail: david.gorsuch@opc.co.uk ww.opc.co.uk John Harley Regional Director Consulting Lansbury Estate 102 Lower Guildford Road, Surrey, GU21 2EP Direct: +44 (0) 1483 878 504 Mobile: +44 (0) 7760 669 199 john.harley@worleyparsons.com www.worleyparsons.com

Editor's Notes

  1. We are going to focus on the Field Development Value Chain This is where value is created in the monetisation of an asset but without protection can be destroyed through the chain. First some definitions We need to define value in our case we may see this as the correct development, chosen first time, right-sized. Prevents excessive costs in over conservative designs, prevents against post-FEED project stop / recycle, developments that are more likely to stay on schedule, developments that are less likely to miss production plateau. Inefficiency = issues not clearly identified and resolved. Much of that inefficiency comes through poor decision making. Adding data will help resolve issues and remove uncertainties and assumptions, and therefore risk. Fewer unresolved issues leads to greater efficiency and less value destruction.
  2. In the FDP value chain let us look at how value can be trickled away through inefficient decision making and lack of risk awareness using a modified historical deepwater field. Sanitised and simplistic – but just something to give an appreciation of the magnitude of the value that can be lost at the early stages of a development This is a “fast track” schedule – real but unusual in that it might set a benchmark for many CEO’s & banks to emulate
  3. Highlights: The reference a large reservoir circa 3bn bbl in place, which means this wasn’t such an issue – there was so much value in the field with high oil prices and the driver was speed….. Not necessarily so much emphasis on capital efficiency What about today? Note the underachievement in production - Somewhere in the order of 2/3 of predicted production was achieved over the first 3 years In addition, during this period, additional production and water injection wells were drilled & tied-in to increase the production The same amount of oil is recovered, it is just recovered a bit later – so how does this impact the value?
  4. Missed plateau production for initial years No impact on CAPEX A loss in NPV terms of $450 million Still an attractive IRR at 20% Not an insignificant amount………… (IRR still looks good though)
  5. The missed production in itself didn’t add anything on to the CAPEX – additional wells certainly do though An additional x production and y water injection wells (50% more wells) were required in the first couple of years to try to raise production. Reservoir was clearly (although not exclusively) the issue here – lack of definition prior to production commencing. Out of interest, typically a 15% cost reduction across all equipment, installation, drilling, commissioning etc. would produce an improvement in NPV of approximately $400 million
  6. $2 BILLION lost from original NPV But, you have a project with an “attractive” IRR of 16% - this could be spun as a great success This would still be considered a viable project - but it could have been so much better………..
  7. How do we help clients define, protect and therefore maximise value through the chain? We make sure that the business drivers are articulated and recorded. That they are agreed with all stake holders. That the strategic decisions such as whether this is a stand alone development, partnering, contract strategy and schedule duration look like all meet those drivers. That they are embedded in the decision framework going forward. That the tactical level decisions of appraisal drilling, subsea spread, production and facilities solutions are all recorded and auditable back to the strategic business drivers. We do this by bringing the right people into the value chain from our and client side and enabling them to make informed quality decisions in a formal decision framework. We help them to look at all possible options for a development and weed it down to all of the credible developments that meet the business drivers. We are geared specifically to help our clients to analyse those credible developments for technology readiness, CAPEX implications, economic metrics, robustness and importantly we help them to understand the technical and non technical risks that surround the field limits such as commercial and geopolitical risks. We see it as helping our clients to sleep better at night by helping them to make informed decisions at the appropriate time. But more than this. Aligning our technical surface strength with OPC allows us to import an understanding of subsurface risk into the client business plan. David will now take us through that.
  8. Why is integration of subsurface with surface facilities design important? Bullet 1 - Different things are important to those involved in understanding the subsurface and those responsible for surface facilities design. For a reservoir engineer, a fluid with a condensate gas ratio of 1 bbl/MMscf is essentially the same as a fluid with a CGR of 2 bbl/MMscf. Both are "dry gas". For a surface facilities engineer, they are very different. Engagement of the two teams from the very beginning helps to ensure that information is properly propagated from the subsurface stage of the study to the surface facilities design stage. Bullet 2 - The levels of uncertainty involved in the subsurface and surface facilities design are very different. In the context of surface facilities design, almost everything is known or knowable. In the subsurface, a great deal of stuff is unknowable. This gives different mindsets in the two communities. A surface facilities design engineer tends to focus on optimisation of the design for the expected inputs. In practice however, a design that is robust in the face of unavoidable uncertainties may be a much better bet. For example, the condensate gas ratio of the produced fluid may not be known with certainty. A design that can cope with anything between 60 bbl/MMscf and 90 bbl/MMscf may be a much better bet than a design that is optimised for 60 bbl/MMscf but will not be able to cope with 90 bbl/MMscf. Bullet 3 - Front-end loading discussions between the subsurface professionals and the surface facilities design engineers may also allow consideration of a much wider range of possibilities. For example, a gas field may be vulnerable to water production. Two approaches could be adopted. Wells could be drilled to minimise the risk of water production and Surface facilities constructed with minimal water handling capability. Alternatively, simpler and cheaper well could be drilled, increasing the risk of water production, and surface facilities constructed that could handle the produced water. Early engagement of the subsurface and surface facilities professionals will allow the best choice to be made as early as possible.