E-menu system development plan
1. Created date: 10 June 2012
Last updated: 11 Aug 2012
Create by Traitet Th.
2. DETAILED PLAN OF DISSERTATION
Start Meeting #2 Meeting #3 Draft system analysis First prototype of Final prototype of Finish
Project with supervisor with supervisor and design e-menu system e-menu system Project
1 June 19 June at 3.30pm 3 July at 1pm documents by 17 Aug by 5 Sep 10 Sep
by 22 July
Draft literature Contact Gathering System System Coding, testing and Develop final
review restaurant requirements analysis design interview prototype
9-17 June 18-30 June 1-8 July 10-15 July 16-22July 23 July – 17 Aug 18 Aug – 5 Sep
3.5 MONTHS
Contact for SHU Receive Final analysis Early Presented
Delayed for 12 days the first & final
Project Plan Web services feedback from and design
But the final prototype is Prototype
9-17 June Server stakeholders document
almost finished. on 20 Jul & 10
18-30 June 7-17 Aug 18-22Aug
Aug
Gathering Draft artifact and
requirements document of Finalize artifact and document of
in advance dissertation dissertation 18 Aug – 9 Sep
on 20, 29 June 16 July – 10 Aug
Draft Literature Summit formal letter Summarise List Submit overarching Receive advice Hand-in
Review to chosen restaurant of requirements documentation from supervisor dissertation
18 Jun by 31 May by 8 July 10 Sep
9 Aug 14 Aug
(Meeting at 1pm)
Schedule
1. Present the first prototype at restaurant on 20 July 2012 and
2. Present the final prototype at restaurant & interview on 10 August 2012
Issue
1. Delay of making artifact document because of development issues. However, process of coding can be finished by 17
August.
2. Delay of making the final prototype and interview from 5 September to 9 September because the restaurant manager 2
was unavailable.
3. ACTION PLAN OF “PREPARATION STAGE”
IN JUNE 2012
Jun-12
No Description Due-date Measurement
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Plan
1 Project Start Date 01-Jun-12 Actual
Result
Plan Draft literature review
2 Draft literature review 18-Jun-12 Actual Draft literature review
Result
Plan Contact restaurant & web services server
Contact restaurant &
3 30-Jun-12 Actual Contact restaurant & web services server
web services server
Result
Activities
1. Prepared draft literature review and dissertation document format between 9 – 17 June (Finished)
2. Sent e-mail to request using .NET and SQL servers provided by the university on 16 June (Finished, available until 28 Feb
2013)
3. Meeting with supervisor on 19 June at 3.30pm (Finished) 3
4. Meeting with the restaurant owner on 20 June at 1pm (Finished)
4. ACTION PLAN OF “SYSTEM ANALYSIS & DESIGN STAGE”
BETWEEN JULY AND AUGUST
Jul-12 Aug-12
Measur
No Description Due-date
ement 1 2 3 4 5 6 7 8 9 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 1 2 3 4 5 6 7 8 9 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3
0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1
Plan Gathering Req. Receive Feedback
Gather
8-Jul-12 Gathering Req. Gathering Req.
4 requirements Actual
16-Aug-12
and feedbacks
Result
Plan System Analysis
Iterative Process Final
Analyse system Analysis
and create 15-Jul-12
5 Actual Analyse system and create document artifacts
documents & 23-Aug-12
artifact
Result
Plan Iterative Process
System Design Final Design
Design system
and create 22-Jul-12
6 Actual Design system and create document artifacts
documents & 23-Aug-12
artifact
Result
Need to finalize the artifact after getting feedback from a presentation of
the first prototype.
Activities
1. Present the first prototype on 20 July 2012 by using website & some user interfaces on iPad
2. Present the final prototype on 10 Sep 2012 by using video presentation, website and application on iPad
Issues
1. Developing on iPad by was really slow because I was not familiar with the objective-c language. Therefore, the first prototype was
mainly presented on .NET website. However, I could take advantage from creating .NET website because it could test web
services developed before implementing on iPad by xCode lanaguage. 4
5. ACTION PLAN OF “IMPLMENTATION AND DOCUMENTATION STAGE”
BETWEEN JULY AND SEPTERMBER
Jul-12 Aug-12 Sep-12
Measure
No Description Due-date
ment 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 1 2 3 4 5 6 7 8 9 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 1 2 3 4 5 6 7 8 9 1
6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 0
Plan Develop the first prototype: Develop, test the application Develop the final prototype and interview
Implement e-
menu (Coding, 17-Jul-12 Actual Frist
Develop the final prototype and interview
7 Prototype
testing and 5-Sep-12
interview) Result
Plan Create document & artifacts for dissertation Finalise document & artifacts for dissertation
Create
documents & 10-Aug-12
8 Actual Create document & artifacts for dissertation Final document & artifacts for dissertation
artefacts for 10-Sep-12
dissertation
Result
Having more time to focus document because prototype
Plan and interview was already finished on 10 Aug 2012
Submit
9 overarching 10-Aug-12 Actual
documentation Insufficient information need to focus more following
Result marking criteria and portfolio templates
Plan
Receive
10 comment back 16-Aug-12 Actual
from supervisor
Result
Plan
Hand-in
11 10-Sep-12 Actual
dissertation
Result
Activities
1. Present the final prototype & interview between 6-10 Aug 2012
Issues
1. Delay of making document because of developing issues. However, process of coding can be finished by 17 Aug 2012.
5
6. SUMMARY OF ACTIVITIES AT THE RESTAURANT
Activities: Discussion, presentation, getting feedback and interviews
No Date Time Activities
1 29-Jun-12 14.00 - 16.00 Discussing and observing with the restaurant manager#1
2 06-Jul-12 14.00 - 17.00 Discussing and observing with the restaurant manager and waiting staffs#2
3 12-Jul-12 18.00 - 23.00 Discussing and observing with the restaurant manager and waiting staffs#3
14.00-16.30 Presenting the first prototype and getting feedback from restaurant manager
4 20-Jul-12
18.00 - 23.00 Observation by working as a waiter at the restaurant
15.00-16.00 Presenting the final prototype
5 10-Aug Interviewing the restaurant manager, waiting staffs and chefs
16.30 - 23.30
Final observing with the restaurant manager, waiting staffs and chefs#4
Main activities: Discussion, presentation, getting feedback and interviews
6