SlideShare a Scribd company logo
1 of 6
Chemtura New Jersey Hub 1020 King Georges Road, Fords NJ 08863 +1.732.738.1000
Critical Equipment Identification and
Preventative Action Plan
Executive Summary
This report’s objective is to identify the mechanical equipment critical to production and then
propose an action plan to prevent critical failures. We identified critical equipment by reviewing work
ordersfromJanuary1, 2015 until August3, 2016 anddiscussingnotable issueswiththe operationsteam.
Impact isdriven bylossof productiondue todowntime forrepairs/safetyconcerns andqualityissues.As
a resultof the investigationtwoincidentswere identifiedascausingexcessive downtime:ablownrupture
diskand brokenagitator blades.The DCS processdrivenissuesare all relativelysmall events,butaddup
to substantial downtime. The main recommendations are to reduce blown rupture disk downtime by
installingisolationvalves, and preventbroken agitator blades by increasing the bolt size while following
OEM recommendations. The preventative actionplanisdetailedatthisreport’sconclusion.
Critical Equipment Identification
Incidents Identified by SAP Work Order Patterns
These incidentswerediscoveredthroughworkorders andidentifypossible failures.Onlythe six active
reactorswere investigated.
Reactor 410
1. AgitatorGasketFlange Failure
2. External HotOil Coil Leak
3. Rupture DiskFailure
4. DCS ProcessDrivenIssues
Reactor 420
1. AgitatorBlades Fall Off
2. DCS ProcessDrivenIssues
Reactor 430
1. ReceiverPhase ProbesMalfunction
2. SteadyBearingWearto Failure
3. DCS ProcessDrivenIssues
Chemtura New Jersey Hub Page 1
Reactor 710
1. Internal CoolingCoil Leak
2. GasketFailure onTotal Condenser
3. External HotOil Coil Leak
4. DCS Process DrivenIssues
Reactor 711
1. External Coil HotOil Leak
2. DCS ProcessDrivenIssues
Reactor 715
1. Leakon ExpansionJoint
2. External HotOil Coil Leak
3. SecondaryRupture DiskFailure
4. DCS ProcessDrivenIssues
Incidents Identified by the Investigative Team
A team was puttogetherto discussa critical equipmentfailuresanddowntime.Teammembersinclude:
John Spampinato (Maintenance), Yifun Su (Engineering), Jenalyn Clegg (Productions), and Nathan
Schaefer (Engineering/Maintenance) discussed issues that caused downtime over the past few months.
The resultsof the inquiryare as follows:
Event Consequence
AgitatorFlange Gasket
Failure
Loss of vacuum, product could overflow from vessel,
intrusion of air into batch causes discoloration
External HotOil Coil Leak Damages insulation and creates a smoldering fire
Total CondenserGasket
Failure
Loss of vacuum, recoveredacidcouldoverflow fromvessel,
intrusion of air into batch causes discoloration
Rupture DiskFailure Loss of vacuum
AgitatorBladesFall Off Loss of agitation
Phase Probes
Malfunction
Excessive dumping of recovered acid into lower receiver,
batch cycle time increases
SecondaryRupture Disk
Failure
Loss of vacuum
DCS ProcessDriven
Issues
Batch Stalls
Internal CoolingCoil Leak
Water spills into batch slowing the cycle or preventing the
reaction from completion
Chemtura New Jersey Hub Page 2
Most Consequential Critical Equipment Failures
Combiningthe SAPworkorderdataandthe anecdote knowledgeof productions/maintenance,these are
the six mostflagrantcritical equipmentfailuresbyreactorduringthe lastyear:
Number of Occurrences
Reactor
Hot
Oil
Leak
Vacuum
Issue
Gasket
Failure
DCS
Process
Issues
Dislodged
Agitator
Blades
Blown
Rupture
Disk
410 X* X X
420 X X
430 X X
710 X X X X X
711 X X
715 X X X
*Safety Issue
Preventative ActionPlan
Gasket Failures (Agitator Flange, Total Condenser)
There have beenseveral vacuumissuesduetogasketfailuresthathave resultedinexcessivecycle
time and productdiscoloration,whichrequiresrework. Gasketsare essentiallygooduntil failure andare
difficulttoperformpreventative maintenance on. One optionwouldbe to group gasketsby sectionand
replace a certainnumberof gasketson a predetermined basis.Removingfunctional parts isnotefficient
and notrecommended.
Recommendations:
 Replace all vacuum jet nozzles and install booster pumps on condenser cooling water.
Thiswill enhance the currentreactorvacuum systems(nozzlesordered).
 Ensure that newgasketsare made from the rightmaterial forthe application
 Use properbolttighteningproceduresandtorqueing asperOEM recommendations.
External Hot Oil Coil Leak
External hot oil coils leaks have been identified as one of the top six critical equipment issues.
Patchinga hotoil leaknotonlyrepresentssignificantdown time,butcanalsopresentasafetyissue. Inan
incident on R-410, a hot oil coil leak was only discovered due to a smoldering fire in the insulation
surroundingthe vessel. There have alsobeenhotoil coil leaksonotherreactors.
Recommendations:
 To preventasmolderingfireinthe insulation,all the currentinsulationcouldbe replaced
withfire retardantblockfoam.Re-insulatingareactorrequires2weeks of downtimeand
cost about $55,000. Recommend reinsulating one reactor a year for the next six years
duringthe summershutdown. (AlsoanFMGlobal Insurance Recommendation)
Chemtura New Jersey Hub Page 3
 Circulate the hot oil cycle through the reactor coils at 200°F during the weekends to
preventhotoil leaksfromoccurring. The Fordsplantwasbuiltfora24/7 operation.Total
shutdown on weekends allows the metal to fully contract and then a hard start on
Monday expects the coils to rapidly adjust to the increased heat. Such fluctuations put
undue stresson the coil.
 All repairsonbutt weldswillhave additional sleeve installed.
Agitator Blades Fall Off
Due to stress on the R-420 agitator bolts,the bolthead (securingthe agitatorblade to the shaft
hub) has shearedawayfromthe boltshaftcausingone of the six bladestofall.
Probable cause:
 Overtighteningof the bolts
 Wrong hardnessof bolt
 Impact bysolids
 Fatigue
 Holesonhub or blade have become worn(largerthanoriginal specification)
Recommendations:
 Do not use lockwashers as perOEM recommendation
 Increase boltwidthfrom 5/8”to3/4”. Increasingthe boltdiameterrequiresenlargingthe
shaft hub holes and the agitator blade holes. A new system could be purchased for
$20,000, but the recommendationisto retrofitthe existingblades.
 Install basketsinall vessel man-wayswithagitators.A solidpieceof compressedpowders
could fall through the man-way and strike the agitator blades causing the bolts to shear
or breakingthe blade atthe bolt holes.
 Use torque wrenchperOEM specifications
 Replace boltsafterapredeterminedtime period
 Review procedure for replacing rupture disks. Current procedure is to install blank on
reactor rupture disk vent line on roof requiringall reactors to be cooled down to 200F.
Recommend installing blank on rupture disk vent line located on reactor. This would
eliminatethe excessive downtime.
DCS Process Driven Issues
The DCS processdrivenissuesare classifiedinto3instances:fielddevice failures(transmitters),
valve issues(electrical ormechanical),andcommunicationhardware.
Withinthe pastyear, fielddevices have failedthatthenresultinDCSalarmsor erratic
automatedbehavior.Anincidentoccurredwiththe R-430 phase probesinthe upperreceiver.The
probeswere readingwaterwasflowingbackintothe reactorwhenorganicwasactuallyflowingback
intothe reactor. Subsequently,the DCSsystemdumpedupto30,000lbs of aciddownto waste water
Chemtura New Jersey Hub Page 4
treatmentwhichsignificantlyincreasedacidadditionsandcycle time. The probesneededtobe removed
fromthe upperreceiverandre-adjustedtothe acidconductivity.
Recommendations:
 Purchasednewphase probeswhichwere adjustedonthe bench(resolved)
 Remove sightglassondecanterandcleanto allow visual interface(resolved)
 Relocatedlightbehindsightglass(resolved)
Valve issues canbe dividedintoundefinedvalvesandDCSalarms.Undefinedvalvesoccurwhen
a valve doesnotfullyopenorclose due to eitheranelectrical ormechanical issues.Inthe case of a
mechanicfailure,the levelswitchhasproperlysignaledtoopenthe valve,butthe valve mechanically
will notfullyopen.Inthe case of an electrical failure,the levelswitchhasnotcorrectlysignaled tofully
opena valve,butthe valve ismechanicallysound.Inthe case of a valve alarm, a valve takestoolongto
openor close andthe DCS systemgeneratesawarning. Production continuesas the valve eventually
opens,butthe operatorsrecordthe alarm.One solutionistoincrease the time the DCSsoftware
allocatesfora valve toopenor close,butsuch a fix onlytreatsa symptomof the problem.If a valve
takeslongerthannormal to operate,itisa signthatvalve isbeginningtofail.
Recommendations:
 Replace valvesinthe eventof amechanical failure (replacementvalvespurchased)
 Adjustthe limitswitchif itoff-setorreplace the limitswitchif itismalfunctioning(limit
switchesandsolenoidcoilspurchased)
 Stroke the valve several timesandsee if the alarmresolvesitself.
 Recordthe incidentandwrite aworkorderto maintenance forfurtherinquiry.
The most frequent communicationhardware failureisthe relaymodule onthe pumps.The
operatorssignal the pumpto start inthe control room, the pumpdoesn’tstart. In actuality,the DCShas
signaledthe pumptostart, buta fuse blew inthe starter.A relaymodule has16 channelsandcan only
be replacedduringa shutdownwithoutdisruptingproduction.We have noticedthisstarterblownfuse
inlessthan 10% of our relaymodules,butare lookingintoanothermodel.
Recommendations:
 Physicallychange the pumpchannel inthe relaymodel,andthenchange the channel in
the DCS software (immediatesolution)
 Replace all blownrelaymoduleswithanupgradedmodule fromPhoenix Contacts.Not
enoughdataexiststodetermine if thisnew module isthe solutiontothe blow starter
(long-termsolution)
NOTE: Inconclusiontoall DCS processdrivenissues,oftentimesthereare extenuating
mechanical orelectricissuesthatresultinthe DCSprogram notperformingasexpected.The operators
needtodocumentthese issuesandthe mechanics/electriciansneedtodocumentanyworktheydoon
DCS complaints.If we see atrendin unexpectedDCSbehavior,the maintenance/engineering
departmentwill take the appropriatecorrectivemeasures.
Chemtura New Jersey Hub Page 5
Internal Cooling Coil Leak
If a cooling coil severely fails during a reactor, water will flood into reactor and immediately
evaporate with the possibility of over pressurizing the vessel. As with all coils, leaks are difficult to do
preventative maintenance for. Normal procedure is to test coils that are suspected to have mechanical
integrity issues. All coils on tanks are tested per MI every five years. During the July 2016 shutdown, a
hydrostatictestwasdone on R-710 and discoverednoleak.
Recommendations:
 Hydrostaticallytestcoilsat200 psigfor two hours to verifytheirmechanical integrity
 Patch coilswithleaksandre-hydrostaticallytest
 Replace the entire R-710 coil as the coolingcoil has14 patches(Inprogress)
 PMall coilsevery5yearsor as needed
Rupture Disk Failure (Primary and Secondary)
Every reactor and refinerisequippedwitharupture diskto relive pressure inthe eventof over-
pressurization (greater than 10 psi). Because all rupture disks blow to a common vessel, every reactor
needstobe cooleddowninorderto replace one blownrupture disk.
Recommendations:
 Install isolationvalvestoallow rupturedisktobe repairedwithoutimpactingproduction.
Butterfly valves needs to purchased and installed ($10,000 each). This will require
installinginterlocks andanMOC witha PSR.
 Add inspection port to rupture disk vent line to make annual PM and MI inspection
quickerwithlessriskof damagingthe rupture diskandcreatingvacuumleaks.
 Install block and bleed valves on water lines to decreases chance of water entering a
reactor while hot andover-pressurizingsystemwithsteam(CAPEXapproved)

More Related Content

What's hot

Merkel wiper auas
Merkel wiper auasMerkel wiper auas
Merkel wiper auaswalleseals
 
Avoiding the costly challenges of seized coupling bolts in hydropower plants ...
Avoiding the costly challenges of seized coupling bolts in hydropower plants ...Avoiding the costly challenges of seized coupling bolts in hydropower plants ...
Avoiding the costly challenges of seized coupling bolts in hydropower plants ...Deb Wong
 
Caterpillar cat 252 b skid steer loader (prefix scp) service repair manual (s...
Caterpillar cat 252 b skid steer loader (prefix scp) service repair manual (s...Caterpillar cat 252 b skid steer loader (prefix scp) service repair manual (s...
Caterpillar cat 252 b skid steer loader (prefix scp) service repair manual (s...fusjezsfkskefmsme
 
Landing nipples X & XN
Landing nipples X & XN Landing nipples X & XN
Landing nipples X & XN Elsayed Amer
 
Completion equipment packer part #2
Completion equipment packer part #2Completion equipment packer part #2
Completion equipment packer part #2Elsayed Amer
 
Slot Drain Systems Submittal
Slot Drain Systems SubmittalSlot Drain Systems Submittal
Slot Drain Systems SubmittalDevan Cronshaw
 
Goel Scientific General information and introduction
Goel Scientific General information and introductionGoel Scientific General information and introduction
Goel Scientific General information and introductionGoel Scientific
 

What's hot (9)

Merkel wiper auas
Merkel wiper auasMerkel wiper auas
Merkel wiper auas
 
Avoiding the costly challenges of seized coupling bolts in hydropower plants ...
Avoiding the costly challenges of seized coupling bolts in hydropower plants ...Avoiding the costly challenges of seized coupling bolts in hydropower plants ...
Avoiding the costly challenges of seized coupling bolts in hydropower plants ...
 
Caterpillar cat 252 b skid steer loader (prefix scp) service repair manual (s...
Caterpillar cat 252 b skid steer loader (prefix scp) service repair manual (s...Caterpillar cat 252 b skid steer loader (prefix scp) service repair manual (s...
Caterpillar cat 252 b skid steer loader (prefix scp) service repair manual (s...
 
Landing nipples X & XN
Landing nipples X & XN Landing nipples X & XN
Landing nipples X & XN
 
Completion equipment packer part #2
Completion equipment packer part #2Completion equipment packer part #2
Completion equipment packer part #2
 
Slot Drain Systems Submittal
Slot Drain Systems SubmittalSlot Drain Systems Submittal
Slot Drain Systems Submittal
 
SPE 134239
SPE 134239SPE 134239
SPE 134239
 
Goel Scientific General information and introduction
Goel Scientific General information and introductionGoel Scientific General information and introduction
Goel Scientific General information and introduction
 
Production packer
Production packerProduction packer
Production packer
 

Viewers also liked

Silver Front Contact Paste for Photovoltaic Applications
Silver Front Contact Paste for Photovoltaic ApplicationsSilver Front Contact Paste for Photovoltaic Applications
Silver Front Contact Paste for Photovoltaic ApplicationsNathan Schaefer
 
PRINTED RFID USING SCREEN PRINTING
PRINTED RFID USING SCREEN PRINTINGPRINTED RFID USING SCREEN PRINTING
PRINTED RFID USING SCREEN PRINTINGNita samantaray
 
Printing processes
Printing processesPrinting processes
Printing processesJutka Czirok
 
InterFulfillment - The Canadian eCommerce solution built around your business
InterFulfillment -  The Canadian eCommerce solution built around your businessInterFulfillment -  The Canadian eCommerce solution built around your business
InterFulfillment - The Canadian eCommerce solution built around your businessAdayra Lg
 
Style Guide - Alexis
Style Guide - AlexisStyle Guide - Alexis
Style Guide - AlexisAlexis Morgan
 
Authenticity of ahadith
Authenticity of ahadithAuthenticity of ahadith
Authenticity of ahadithMaheenRaza88
 
Tecnalia - 2015/12/11 Feria Bizhirik Erakusketa
Tecnalia - 2015/12/11 Feria Bizhirik ErakusketaTecnalia - 2015/12/11 Feria Bizhirik Erakusketa
Tecnalia - 2015/12/11 Feria Bizhirik ErakusketaBizhirik
 
Jubilares - 10/12/2015 Feria Bizhirik Erakusketa
Jubilares - 10/12/2015 Feria Bizhirik ErakusketaJubilares - 10/12/2015 Feria Bizhirik Erakusketa
Jubilares - 10/12/2015 Feria Bizhirik ErakusketaBizhirik
 
Level 2 Computerised Bookkeeping
Level 2 Computerised BookkeepingLevel 2 Computerised Bookkeeping
Level 2 Computerised BookkeepingVanessa King
 
Roles and functions of educational technology in the first century education
Roles and functions of educational technology in the first century educationRoles and functions of educational technology in the first century education
Roles and functions of educational technology in the first century educationLilanie Bellingan
 
2016 Mazda CX-3 SUV Nashville
2016 Mazda CX-3 SUV Nashville2016 Mazda CX-3 SUV Nashville
2016 Mazda CX-3 SUV NashvilleNelsonMazda
 
Automated Nitrogen Drying
Automated Nitrogen DryingAutomated Nitrogen Drying
Automated Nitrogen DryingNathan Schaefer
 
Gangaur Rituals
Gangaur RitualsGangaur Rituals
Gangaur RitualsSareez
 
Film Funding Research
Film Funding ResearchFilm Funding Research
Film Funding Researchmedcalfbro
 
Spitz,Gina_EvaluatingTeachingandLearning_Nov2014
Spitz,Gina_EvaluatingTeachingandLearning_Nov2014Spitz,Gina_EvaluatingTeachingandLearning_Nov2014
Spitz,Gina_EvaluatingTeachingandLearning_Nov2014Gina Spitz, Ph.D.
 

Viewers also liked (20)

Silver Front Contact Paste for Photovoltaic Applications
Silver Front Contact Paste for Photovoltaic ApplicationsSilver Front Contact Paste for Photovoltaic Applications
Silver Front Contact Paste for Photovoltaic Applications
 
PRINTED RFID USING SCREEN PRINTING
PRINTED RFID USING SCREEN PRINTINGPRINTED RFID USING SCREEN PRINTING
PRINTED RFID USING SCREEN PRINTING
 
Printing processes
Printing processesPrinting processes
Printing processes
 
InterFulfillment - The Canadian eCommerce solution built around your business
InterFulfillment -  The Canadian eCommerce solution built around your businessInterFulfillment -  The Canadian eCommerce solution built around your business
InterFulfillment - The Canadian eCommerce solution built around your business
 
Style Guide - Alexis
Style Guide - AlexisStyle Guide - Alexis
Style Guide - Alexis
 
MCGazetteArticle
MCGazetteArticleMCGazetteArticle
MCGazetteArticle
 
Authenticity of ahadith
Authenticity of ahadithAuthenticity of ahadith
Authenticity of ahadith
 
Tecnalia - 2015/12/11 Feria Bizhirik Erakusketa
Tecnalia - 2015/12/11 Feria Bizhirik ErakusketaTecnalia - 2015/12/11 Feria Bizhirik Erakusketa
Tecnalia - 2015/12/11 Feria Bizhirik Erakusketa
 
Jubilares - 10/12/2015 Feria Bizhirik Erakusketa
Jubilares - 10/12/2015 Feria Bizhirik ErakusketaJubilares - 10/12/2015 Feria Bizhirik Erakusketa
Jubilares - 10/12/2015 Feria Bizhirik Erakusketa
 
Level 2 Computerised Bookkeeping
Level 2 Computerised BookkeepingLevel 2 Computerised Bookkeeping
Level 2 Computerised Bookkeeping
 
Roles and functions of educational technology in the first century education
Roles and functions of educational technology in the first century educationRoles and functions of educational technology in the first century education
Roles and functions of educational technology in the first century education
 
2016 Mazda CX-3 SUV Nashville
2016 Mazda CX-3 SUV Nashville2016 Mazda CX-3 SUV Nashville
2016 Mazda CX-3 SUV Nashville
 
Θεωρία αριθμών
Θεωρία αριθμώνΘεωρία αριθμών
Θεωρία αριθμών
 
Automated Nitrogen Drying
Automated Nitrogen DryingAutomated Nitrogen Drying
Automated Nitrogen Drying
 
levellingrisk
levellingrisklevellingrisk
levellingrisk
 
Gangaur Rituals
Gangaur RitualsGangaur Rituals
Gangaur Rituals
 
Design Samples
Design SamplesDesign Samples
Design Samples
 
Film Funding Research
Film Funding ResearchFilm Funding Research
Film Funding Research
 
NABARD by suresh kumar panda
NABARD by suresh kumar pandaNABARD by suresh kumar panda
NABARD by suresh kumar panda
 
Spitz,Gina_EvaluatingTeachingandLearning_Nov2014
Spitz,Gina_EvaluatingTeachingandLearning_Nov2014Spitz,Gina_EvaluatingTeachingandLearning_Nov2014
Spitz,Gina_EvaluatingTeachingandLearning_Nov2014
 

Similar to Critical Equipment Identification and Preventative Action Plan

Refrigerant Piping Handbook.pdf
Refrigerant Piping Handbook.pdfRefrigerant Piping Handbook.pdf
Refrigerant Piping Handbook.pdfssuser642327
 
IRJET- Design Modifications in Cryogenic Pressure Relief Valve to Elimina...
IRJET-  	  Design Modifications in Cryogenic Pressure Relief Valve to Elimina...IRJET-  	  Design Modifications in Cryogenic Pressure Relief Valve to Elimina...
IRJET- Design Modifications in Cryogenic Pressure Relief Valve to Elimina...IRJET Journal
 
Service_C-CC-CW-Valve.pdf
Service_C-CC-CW-Valve.pdfService_C-CC-CW-Valve.pdf
Service_C-CC-CW-Valve.pdfrheri1
 
Bearingcalculation
BearingcalculationBearingcalculation
Bearingcalculationehsan ataei
 
Condition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaCondition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaUdhayakumar Venkataraman
 
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...fjskekqazdmmem
 
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...fujsjfjskekemmem
 
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...fjjsfkskemem
 
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...ufjjdjjkskemme
 
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...fujsjefjkskeksmem
 
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...ufuusjjfjkskekmem
 
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...ufujjdfjjskekemm
 
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...fjskeawsekdmme
 
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...fjskekqaswdmmem
 
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...kfdjkskdmm
 
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...ufjjdfjkskemfmme
 
MDM Series Magnetic Drive Pump
MDM Series Magnetic Drive PumpMDM Series Magnetic Drive Pump
MDM Series Magnetic Drive PumpIwaki America Inc.
 

Similar to Critical Equipment Identification and Preventative Action Plan (20)

New Ideas for Repairing Gearboxes and Generators
New Ideas for Repairing Gearboxes and GeneratorsNew Ideas for Repairing Gearboxes and Generators
New Ideas for Repairing Gearboxes and Generators
 
Refrigerant Piping Handbook.pdf
Refrigerant Piping Handbook.pdfRefrigerant Piping Handbook.pdf
Refrigerant Piping Handbook.pdf
 
Fugitive Emissions
Fugitive EmissionsFugitive Emissions
Fugitive Emissions
 
IRJET- Design Modifications in Cryogenic Pressure Relief Valve to Elimina...
IRJET-  	  Design Modifications in Cryogenic Pressure Relief Valve to Elimina...IRJET-  	  Design Modifications in Cryogenic Pressure Relief Valve to Elimina...
IRJET- Design Modifications in Cryogenic Pressure Relief Valve to Elimina...
 
Service_C-CC-CW-Valve.pdf
Service_C-CC-CW-Valve.pdfService_C-CC-CW-Valve.pdf
Service_C-CC-CW-Valve.pdf
 
Bearingcalculation
BearingcalculationBearingcalculation
Bearingcalculation
 
Condition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaCondition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performa
 
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
 
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
 
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
 
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
 
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
 
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
 
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs541 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
 
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
 
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs600 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
 
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
 
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
Kawasaki fs481 v 4 stroke air-cooled v-twin gasoline engine service repair ma...
 
MDM Series Magnetic Drive Pump
MDM Series Magnetic Drive PumpMDM Series Magnetic Drive Pump
MDM Series Magnetic Drive Pump
 
Giuseppe_Tommasone.pdf
Giuseppe_Tommasone.pdfGiuseppe_Tommasone.pdf
Giuseppe_Tommasone.pdf
 

Critical Equipment Identification and Preventative Action Plan

  • 1. Chemtura New Jersey Hub 1020 King Georges Road, Fords NJ 08863 +1.732.738.1000 Critical Equipment Identification and Preventative Action Plan Executive Summary This report’s objective is to identify the mechanical equipment critical to production and then propose an action plan to prevent critical failures. We identified critical equipment by reviewing work ordersfromJanuary1, 2015 until August3, 2016 anddiscussingnotable issueswiththe operationsteam. Impact isdriven bylossof productiondue todowntime forrepairs/safetyconcerns andqualityissues.As a resultof the investigationtwoincidentswere identifiedascausingexcessive downtime:ablownrupture diskand brokenagitator blades.The DCS processdrivenissuesare all relativelysmall events,butaddup to substantial downtime. The main recommendations are to reduce blown rupture disk downtime by installingisolationvalves, and preventbroken agitator blades by increasing the bolt size while following OEM recommendations. The preventative actionplanisdetailedatthisreport’sconclusion. Critical Equipment Identification Incidents Identified by SAP Work Order Patterns These incidentswerediscoveredthroughworkorders andidentifypossible failures.Onlythe six active reactorswere investigated. Reactor 410 1. AgitatorGasketFlange Failure 2. External HotOil Coil Leak 3. Rupture DiskFailure 4. DCS ProcessDrivenIssues Reactor 420 1. AgitatorBlades Fall Off 2. DCS ProcessDrivenIssues Reactor 430 1. ReceiverPhase ProbesMalfunction 2. SteadyBearingWearto Failure 3. DCS ProcessDrivenIssues
  • 2. Chemtura New Jersey Hub Page 1 Reactor 710 1. Internal CoolingCoil Leak 2. GasketFailure onTotal Condenser 3. External HotOil Coil Leak 4. DCS Process DrivenIssues Reactor 711 1. External Coil HotOil Leak 2. DCS ProcessDrivenIssues Reactor 715 1. Leakon ExpansionJoint 2. External HotOil Coil Leak 3. SecondaryRupture DiskFailure 4. DCS ProcessDrivenIssues Incidents Identified by the Investigative Team A team was puttogetherto discussa critical equipmentfailuresanddowntime.Teammembersinclude: John Spampinato (Maintenance), Yifun Su (Engineering), Jenalyn Clegg (Productions), and Nathan Schaefer (Engineering/Maintenance) discussed issues that caused downtime over the past few months. The resultsof the inquiryare as follows: Event Consequence AgitatorFlange Gasket Failure Loss of vacuum, product could overflow from vessel, intrusion of air into batch causes discoloration External HotOil Coil Leak Damages insulation and creates a smoldering fire Total CondenserGasket Failure Loss of vacuum, recoveredacidcouldoverflow fromvessel, intrusion of air into batch causes discoloration Rupture DiskFailure Loss of vacuum AgitatorBladesFall Off Loss of agitation Phase Probes Malfunction Excessive dumping of recovered acid into lower receiver, batch cycle time increases SecondaryRupture Disk Failure Loss of vacuum DCS ProcessDriven Issues Batch Stalls Internal CoolingCoil Leak Water spills into batch slowing the cycle or preventing the reaction from completion
  • 3. Chemtura New Jersey Hub Page 2 Most Consequential Critical Equipment Failures Combiningthe SAPworkorderdataandthe anecdote knowledgeof productions/maintenance,these are the six mostflagrantcritical equipmentfailuresbyreactorduringthe lastyear: Number of Occurrences Reactor Hot Oil Leak Vacuum Issue Gasket Failure DCS Process Issues Dislodged Agitator Blades Blown Rupture Disk 410 X* X X 420 X X 430 X X 710 X X X X X 711 X X 715 X X X *Safety Issue Preventative ActionPlan Gasket Failures (Agitator Flange, Total Condenser) There have beenseveral vacuumissuesduetogasketfailuresthathave resultedinexcessivecycle time and productdiscoloration,whichrequiresrework. Gasketsare essentiallygooduntil failure andare difficulttoperformpreventative maintenance on. One optionwouldbe to group gasketsby sectionand replace a certainnumberof gasketson a predetermined basis.Removingfunctional parts isnotefficient and notrecommended. Recommendations:  Replace all vacuum jet nozzles and install booster pumps on condenser cooling water. Thiswill enhance the currentreactorvacuum systems(nozzlesordered).  Ensure that newgasketsare made from the rightmaterial forthe application  Use properbolttighteningproceduresandtorqueing asperOEM recommendations. External Hot Oil Coil Leak External hot oil coils leaks have been identified as one of the top six critical equipment issues. Patchinga hotoil leaknotonlyrepresentssignificantdown time,butcanalsopresentasafetyissue. Inan incident on R-410, a hot oil coil leak was only discovered due to a smoldering fire in the insulation surroundingthe vessel. There have alsobeenhotoil coil leaksonotherreactors. Recommendations:  To preventasmolderingfireinthe insulation,all the currentinsulationcouldbe replaced withfire retardantblockfoam.Re-insulatingareactorrequires2weeks of downtimeand cost about $55,000. Recommend reinsulating one reactor a year for the next six years duringthe summershutdown. (AlsoanFMGlobal Insurance Recommendation)
  • 4. Chemtura New Jersey Hub Page 3  Circulate the hot oil cycle through the reactor coils at 200°F during the weekends to preventhotoil leaksfromoccurring. The Fordsplantwasbuiltfora24/7 operation.Total shutdown on weekends allows the metal to fully contract and then a hard start on Monday expects the coils to rapidly adjust to the increased heat. Such fluctuations put undue stresson the coil.  All repairsonbutt weldswillhave additional sleeve installed. Agitator Blades Fall Off Due to stress on the R-420 agitator bolts,the bolthead (securingthe agitatorblade to the shaft hub) has shearedawayfromthe boltshaftcausingone of the six bladestofall. Probable cause:  Overtighteningof the bolts  Wrong hardnessof bolt  Impact bysolids  Fatigue  Holesonhub or blade have become worn(largerthanoriginal specification) Recommendations:  Do not use lockwashers as perOEM recommendation  Increase boltwidthfrom 5/8”to3/4”. Increasingthe boltdiameterrequiresenlargingthe shaft hub holes and the agitator blade holes. A new system could be purchased for $20,000, but the recommendationisto retrofitthe existingblades.  Install basketsinall vessel man-wayswithagitators.A solidpieceof compressedpowders could fall through the man-way and strike the agitator blades causing the bolts to shear or breakingthe blade atthe bolt holes.  Use torque wrenchperOEM specifications  Replace boltsafterapredeterminedtime period  Review procedure for replacing rupture disks. Current procedure is to install blank on reactor rupture disk vent line on roof requiringall reactors to be cooled down to 200F. Recommend installing blank on rupture disk vent line located on reactor. This would eliminatethe excessive downtime. DCS Process Driven Issues The DCS processdrivenissuesare classifiedinto3instances:fielddevice failures(transmitters), valve issues(electrical ormechanical),andcommunicationhardware. Withinthe pastyear, fielddevices have failedthatthenresultinDCSalarmsor erratic automatedbehavior.Anincidentoccurredwiththe R-430 phase probesinthe upperreceiver.The probeswere readingwaterwasflowingbackintothe reactorwhenorganicwasactuallyflowingback intothe reactor. Subsequently,the DCSsystemdumpedupto30,000lbs of aciddownto waste water
  • 5. Chemtura New Jersey Hub Page 4 treatmentwhichsignificantlyincreasedacidadditionsandcycle time. The probesneededtobe removed fromthe upperreceiverandre-adjustedtothe acidconductivity. Recommendations:  Purchasednewphase probeswhichwere adjustedonthe bench(resolved)  Remove sightglassondecanterandcleanto allow visual interface(resolved)  Relocatedlightbehindsightglass(resolved) Valve issues canbe dividedintoundefinedvalvesandDCSalarms.Undefinedvalvesoccurwhen a valve doesnotfullyopenorclose due to eitheranelectrical ormechanical issues.Inthe case of a mechanicfailure,the levelswitchhasproperlysignaledtoopenthe valve,butthe valve mechanically will notfullyopen.Inthe case of an electrical failure,the levelswitchhasnotcorrectlysignaled tofully opena valve,butthe valve ismechanicallysound.Inthe case of a valve alarm, a valve takestoolongto openor close andthe DCS systemgeneratesawarning. Production continuesas the valve eventually opens,butthe operatorsrecordthe alarm.One solutionistoincrease the time the DCSsoftware allocatesfora valve toopenor close,butsuch a fix onlytreatsa symptomof the problem.If a valve takeslongerthannormal to operate,itisa signthatvalve isbeginningtofail. Recommendations:  Replace valvesinthe eventof amechanical failure (replacementvalvespurchased)  Adjustthe limitswitchif itoff-setorreplace the limitswitchif itismalfunctioning(limit switchesandsolenoidcoilspurchased)  Stroke the valve several timesandsee if the alarmresolvesitself.  Recordthe incidentandwrite aworkorderto maintenance forfurtherinquiry. The most frequent communicationhardware failureisthe relaymodule onthe pumps.The operatorssignal the pumpto start inthe control room, the pumpdoesn’tstart. In actuality,the DCShas signaledthe pumptostart, buta fuse blew inthe starter.A relaymodule has16 channelsandcan only be replacedduringa shutdownwithoutdisruptingproduction.We have noticedthisstarterblownfuse inlessthan 10% of our relaymodules,butare lookingintoanothermodel. Recommendations:  Physicallychange the pumpchannel inthe relaymodel,andthenchange the channel in the DCS software (immediatesolution)  Replace all blownrelaymoduleswithanupgradedmodule fromPhoenix Contacts.Not enoughdataexiststodetermine if thisnew module isthe solutiontothe blow starter (long-termsolution) NOTE: Inconclusiontoall DCS processdrivenissues,oftentimesthereare extenuating mechanical orelectricissuesthatresultinthe DCSprogram notperformingasexpected.The operators needtodocumentthese issuesandthe mechanics/electriciansneedtodocumentanyworktheydoon DCS complaints.If we see atrendin unexpectedDCSbehavior,the maintenance/engineering departmentwill take the appropriatecorrectivemeasures.
  • 6. Chemtura New Jersey Hub Page 5 Internal Cooling Coil Leak If a cooling coil severely fails during a reactor, water will flood into reactor and immediately evaporate with the possibility of over pressurizing the vessel. As with all coils, leaks are difficult to do preventative maintenance for. Normal procedure is to test coils that are suspected to have mechanical integrity issues. All coils on tanks are tested per MI every five years. During the July 2016 shutdown, a hydrostatictestwasdone on R-710 and discoverednoleak. Recommendations:  Hydrostaticallytestcoilsat200 psigfor two hours to verifytheirmechanical integrity  Patch coilswithleaksandre-hydrostaticallytest  Replace the entire R-710 coil as the coolingcoil has14 patches(Inprogress)  PMall coilsevery5yearsor as needed Rupture Disk Failure (Primary and Secondary) Every reactor and refinerisequippedwitharupture diskto relive pressure inthe eventof over- pressurization (greater than 10 psi). Because all rupture disks blow to a common vessel, every reactor needstobe cooleddowninorderto replace one blownrupture disk. Recommendations:  Install isolationvalvestoallow rupturedisktobe repairedwithoutimpactingproduction. Butterfly valves needs to purchased and installed ($10,000 each). This will require installinginterlocks andanMOC witha PSR.  Add inspection port to rupture disk vent line to make annual PM and MI inspection quickerwithlessriskof damagingthe rupture diskandcreatingvacuumleaks.  Install block and bleed valves on water lines to decreases chance of water entering a reactor while hot andover-pressurizingsystemwithsteam(CAPEXapproved)