Global Tubing's Director of Coiled Pipeline Ivo Bozukov was a guest speaker at the 2017 DUG Permian Basin conference on April 3. Bozukov's presentation focuses on coiled line pipe and the advantages over other pipeline products.
2. COMPANY HISTORY
2017 DUG PERMIAN
• Greenfield, Private Equity Investment in 2007
• Currently, a JV between privately owned company Quantum
Energy Partners and publicly traded Forum Energy Technologies
(NYSE: FET)
• ~50,000,000ft of coiled tubing delivered since April 2009
• Products sold in over 30 countries and 6 continents
• Key staff has over 250 years of combined experience in coiled
pipeline and flexible pipe
• Our team has been instrumental in delivering projects of over 1
Million feet of offshore Coiled Line Pipe around the world.
• Through commitment to technology and customer service, our
company is helping our customers improve their corporate
performance
3. WHAT IS COILED LINE PIPE
2017 DUG PERMIAN
• Developed during WWII – “Project P.L.U.T.O.”
• Subsequently the development split into a few distinct technologies:
– Flexible Steel Reinforced Pipe (API 17J)
– Coiled Line Pipe (API 5LCP)
– Steel Pipe (ASTM GRADE B/ API 5L) jointed and coiled
4. EVOLUTION NOT REVOLUTION
2017 DUG PERMIAN
• Coiled Line Pipe is an evolutionary development in our industry as it
utilizes the use of the trusted steel pipe grades and combines it with
the fast spoolable deployment.
• Coiled Line Pipe allows for safer, faster and cheaper project
completion by cutting the pipeline installation time.
1) … 65% less man hours.
2) … 61% less equipment hours.
3) … reduced risks related to safety and quality.
4) … smaller Right of Way and minimal environmental impact.
6. PERMIAN CASE STUDY
2017 DUG PERMIAN
Project: Coiled Line Pipe for Natural Gas Line
Location: Hobbs, New Mexico
Application: Fuel Gas
Material Spec: 4” Nominal OD, Schedule 40, A53/X52C Coiled Line
Pipe
Length: 3,700 Feet
7. SOUTH TEXAS CASE STUDY
2017 DUG PERMIAN
Project: Coiled Line Pipe for Medium Pressure Flowline
Location: Big Wells, Texas
Application: Crude Oil - Multiphase
Material Spec: 4” Nominal OD, Schedule 40, A53/X52C Coiled Line
Pipe
Length: 11,600 Feet
8. ROCKIES CASE STUDY
2017 DUG PERMIAN
Project: Coiled Line Pipe for High Pressure Flowline
Location: Ft Morgan, Colorado
Application: Crude Oil - Multiphase
Material Spec: 2” Nominal OD, Schedule 80, A53/X52C Coiled Line
Pipe
Length: 42,300 Feet
10. SUMMARY
2017 DUG PERMIAN
• 97% less connections in a
mile of pipeline
• 3 Layer FBE/CP/PP (PE)
coatings represent the most
advanced and versatile
coating systems available.
• Time tested industry
standards
Coiled Tubing Pipeline Other Pipeline Products
• Steel Pipe requires a weld, coat &
X-ray every 40’
• Composites require expensive
and unproven connections
• FBE weathers poorly
• FBE/ARO is costly and hard to
bend during HDDs
• New and un-developed standards
• Trusted standards, but no growth
Global Tubing provided 3,700 ft of Coiled Line Pipe from stock to quickly deliver the quantity requested by OXY.
• The Coiled Line Pipe installation, from unloading to ditch, was 4 times faster than stick steel pipe.
• The entire pipeline length required only 5 welds (including the riser connections), which were faster and more cost efficient than composite connections and did not require special staff or equipment.
• Pipe crossings were completed by pushing the pipe under, while deploying into the ditch. There were no pipe cuts and no damage to the pipeline’s protective coating or the pipeline itself.
Global Tubing answered the needs of the customer by supplying 11,600 ft of Coiled Line Pipe from stock to deliver the entire quantity requested in eight (8) spools only.
• The pipe was delivered to site, the Coiled Line Pipe installation from unloading to ditch was 3 times faster than stick steel pipe.
• The entire pipeline length required 14 welds (including the riser connections, pipeline crossings and road bores).
• Eight (8) pipeline and road crossings were completed successfully, by pushing and/or pulling the required pipe length in place, while deploying into the ditch and electrostatically testing the coating for damage at the same time.