SlideShare a Scribd company logo
1 of 59
Download to read offline
SCADA – RTU INTERFACE
BY
S . GANESH BABU
SCADA DEFINED
• A formal definition of SCADA system, as
recommended by IEEE, is:
• “A collection of equipment that will provide
an operator at a remote location with
sufficient information to determine the
status of a particular equipment or a
process and cause actions to take place
regarding that equipment or process
without being physically present”.
4/25/2014 2
s ganesh babu
Power System Automation
• A power system consists of devices that
generate, transmit, and distribute power.
• Power system automation is the act of
automatically controlling the power system via
automated processes within computers and
intelligent I&C devices.
• It consists of three major processes:
• data acquisition,
• power system supervision,
• and power system control, all, working in a
coordinated automatic fashion.
4/25/2014 3
s ganesh babu
Power System Automation (CONT’D)
• Data acquisition refers to;
• Collecting data in the form of measured analog
current or voltage values,
• The open or closed status of contact points.
• Control refers to sending command messages
to a device to operate the I&C (A collection of
devices that monitor, control and protect the
system is referred as instrumentation and
control
(I&C) system)and power system devices
4/25/2014 4
s ganesh babu
INSTRUMENTATION SUB SYSTEM:
 Measurement and feeding of various parameters such as :
 Voltage, Current, power, circuit breaker status, and alarms
needs a supporting sub system.
 The parameters are fed into the substation telemetry
equipment called RTU ( Remote telemetry unit or remote
terminal unit).
 Analogs:
 Bus voltage: source : bus potential transformer.
 and currents in all feeders and transformers: source –
current transformers.
4/25/2014 5
s ganesh babu
INSTRUMENTATION SUB SYSTEM (CONT’D)
 Power in MW, KVAR, Power factor from LV
breaker.
 Analogue measurements carried out by
Industrial standard transducers with an
output of 4 – 20mA and 1 to 5v D.C.
4/25/2014 6
s ganesh babu
STATUS INPUTS:
 Breaker “ON / OFF” status.
 Alarms for oil, buch’olz, oil and winding
temperature.
 OLTC positions for transformers.
 Capacitor banks.
 All status inputs calls for voltage free
contact terminals.

4/25/2014 7
s ganesh babu
SCAN RATE
 Central control room monitors a series of mixture
of analog and status inputs the frequency of which
is decided by the priorities and fleeting events.
 Scanning rate depends on nature of substation
parameters.
 Voltage rating and type of substation.
 Non fleeting status and analog would require a
scanning rate 0f 2 to 3 minutes.
 Fleeting and high priority inputs require a
scanning rate of 5 to 10 secs and is decided based
on the following factors.
4/25/2014 8
s ganesh babu
SCAN RATE CONT’D
 Importance of the substation to the grid.
 Voltage rating : Higher the voltage rating, the
more the importance,
 Cost factor, which decides the type of
communication and the choice of the scan rate.
 Ex: High Speed TDMA link between central
control center and the substation and its
exclusivity.

4/25/2014 9
s ganesh babu
Applications of SCADA System
 Automatic Switching
 Emergency Load shedding
 Re-routing services for station maintenance
 Automatic transfer schemes
 Load sectionalizing
 Custom, automatic reclosing schemes
 Automatic service restoration
 Circuit breaker control and interlocking
 Feeder automation and fault recovery
4/25/2014 10
s ganesh babu
Applications of SCADA System
 Protection and Control
• Circuit breaker lockout
• Protective relay interface/interaction
• Dynamic protective relay setting for
dynamic station topology
 Voltage Regulation Management
• Load Tap Changer (LTC) control
• Voltage regulator control
• Capacitor control
4/25/2014 11
s ganesh babu
Applications of SCADA System
 Transformer Management
• Parameter monitoring and alarming
• Real-time modeling
• Interface to existing transformer monitors
 Automatic System Diagnostics
• Power apparatus health monitoring
• PLC and communications self monitoring
• Report and alarm on IED self diagnostics
4/25/2014 12
s ganesh babu
Applications of SCADA System
 Maintenance and Safety
 Kirk Key interlock management
 Maintenance ‘Lock-out/Tag-out
management
 Automatic circuit isolation
control
4/25/2014 13
s ganesh babu
Applications of SCADA System
 Station MMIs – Graphical User
Interface (GUI)
 Interface real-time single-line displays
 Interactive real-time breaker and switch
control display
 On-line operation and maintenance logs
 Sequence of events recording
 IED detail displays
 Parameter trending displays
4/25/2014 14
s ganesh babu
Advantages of SCADA system in power sector
 Increased reliability, lower costs.
 Forecasting accurate demand supply
management
 Faster restoration of power in case of a break
down
 Better active and reactive power
management
 Reduced maintenance cost, conditioning
monitoring
 Reduce human influence and errors
 Assists operator for faster decision making
 Automated meter reading
 Easy fault diagnosis
4/25/2014 15
s ganesh babu
Additional advantages of SCADA system in power
sector
 Availability of information
 Analysis of information
 Decision making
 Optimized system operation (competitive
environment)
 Equipment condition monitoring (ECM)
 Equipment parameters are automatically
tracked to detect abnormalities.
 Timely action, Extended life
 ECM IEDs available
 Sequence Of Events (SOE) recording
4/25/2014 16
s ganesh babu
SCADA System
 A SCADA system generally
consists of a master
station and a number of
geographically dispersed
Remote Terminal Units
(RTUs), all interconnected
to master station via a
variety of communication
channels.
4/25/2014 17
s ganesh babu
Supervisory Remote Terminal Units
 RTU is the eyes, ears and
hands of the Master
Station.
 In most applications the
RTU is the slave of the
Master Station, but in
some applications the RTU
is equipped with internal
computational and/or
optimizing capabilities.
4/25/2014 18
s ganesh babu
4/25/2014 19
s ganesh babu
Remote Terminal Units
 AVAILABILITY:
 The availability of the RTU shall
be 0.999 over the 12 month
period of maintenance exclusive
of communication channel and
other purchaser caused down
time.
 Availability =
MTBF / ( MTBF + MTTR)
 MTBF = Mean Time between
failure
 MTTR = Mean Time to repair
4/25/2014 20
s ganesh babu
REMOTE TERMINAL UNITS (RTU)
 RTU consists of:
 The protocol processor module
 Communication module
 Data processing Module
 I/O modules for analog inputs
 Digital input and output
 RTU signals from transducers, relays, breaker
auxiliary switches, and TVMs.
 Data transmitted to DCC through
communication media (TDMA and MAR)
4/25/2014 21
s ganesh babu
REMOTE TERMINAL UNITS (RTU)
 Functions of RTU include
 Input scanning
 Alarm,
 And change of state detection.
 With high degree of reliability,
security and integrity.
4/25/2014 22
s ganesh babu
Transmission and coding system of RTU.
 The I/O channels are defined based on the need of each
substation, and the RTU is configured accordingly.
 These modules interface through memory mapping to the
micro processor.
 The RTU scans analogue and digital data non stop, and
stores the analogue information after converting it in its
memory.
 The RTU’s at each substation are accessed and addressed
independently.
 The electrical and communication format to the mail port
is usually RS 232.
4/25/2014 23
s ganesh babu
SYSTEM DIAGNOSTICS
 Typical diagnostics and indications provided in the RTU are :
 Power LED:
Indicates power applied to the base board when switched on.
 RUN LED:
Indicates healthy operating system.
 LPAT LED:
Indicates too low voltage on the input side.
 Watch Dog time out LED.
 Status LED:
Gives a binary coded output if the system fails a soft ware
confidence test.
4/25/2014 24
s ganesh babu
SYSTEM DIAGNOSTICS (cont’d)
 Diagnostic capability at the I/O module level.
 Hardware read back at telecom and output circuit
for verification of data at the field connection
point.
 Verification of memory and certain peripheral
chips in operating system.
 Communication diagnostics to indicate activity on
the receiver and transmitter lines for both main
and local ports.
4/25/2014 25
s ganesh babu
Communication Subsystem
 The communication subsystem is
the interface between the
communication network and the
RTU internal logic.
 This subsystem receives the
messages from the master,
interprets the message, initiates
action within the RTU, and sends an
appropriate response to the master.
4/25/2014 26
s ganesh babu
Communication Subsystem (cont’d)
 PRIMARY COMMUNICATION
 64 kbps TDM/TDMA (time division multiple
access operating in 2.3/2.5 GHZ band and
the out stations extend to EHV stations.
 SECONDARY COMMUNICATION:
 Is 9.6 KBPS MAR (multiple access
Radio) system operating in 849/943
MHZ band.
 Mar remotes are located in all 33/11
kv substations.
4/25/2014 27
s ganesh babu
4/25/2014 28
s ganesh babu
Logic Subsystem
 The logic subsystem consists of the
main microprocessor and the database.
 It handles all major processing, time
keeping, and control sensing.
 It also handles analog-to digital
conversions and computation
/optimization, if required.
4/25/2014 29
s ganesh babu
Termination Subsystem
 The termination subsystem provides the
interface between the RTU logic and
external equipment such as the
communications lines, primary power
source and the substation devices.
 These assemblies must be designed to
protect the RTU logic from the harsh
environment of the station.
4/25/2014 30
s ganesh babu
Power Supply Subsystem
 The power supply, like the termination
subsystem, must meet the various voltage
surge standards.
 The power supply convenes primary power,
usually from the substation battery, to the
supply requirements of the other RTUs
subsystem.
 If a station battery is not available, the unit is
normally ordered for ac operation with built-
in battery back-up to cover several hours of
operation.
 Care should be exercised in selecting an ac
supply circuit to assure a reliable and stable,
noise-fee source.
4/25/2014 31
s ganesh babu
Communication
 In addition, occurrences of noise on the
communication channel seeks
reinforcements in the form of additional
master station and RTU hardware and
software design to ensure distortion free
signal transfer.
 Communication channels limit the speed
at which data acquisition and control can
be performed, thus affecting the master
station man-machine interface and
applications software design.
4/25/2014 32
s ganesh babu
Communication channels
4/25/2014 33
s ganesh babu
4/25/2014 34
s ganesh babu
SCADA System Configurations
 The configurations of communication
systems are dictated by the following:
 Number of RTUs
 Number of points at RTUs and required
update rates
 Location of RTUs
 Communication facilities available
 Communication equipment and techniques
available
4/25/2014 35
s ganesh babu
SCADA System Configurations
 Block diagram for a
one-on-one SCADA
system configuration,
with a master unit
for each remote unit
M R 1
M R2
4/25/2014 36
s ganesh babu
SCADA System Configurations
 Block diagram for
a star or hub
SCADA system
configuration, with
one master unit
for several
remotes, but with
only one remote
on each
communication
channel.
M
4/25/2014 37
s ganesh babu
SCADA System Configurations
 Block diagram for a party-line SCADA system
configuration, with several remote units on a
single communication channel.
M
R1 R2 R3 R4
4/25/2014 38
s ganesh babu
SCADA System Configurations
 Block diagram for
a SCADA system
configuration,
combining the
characteristics of
the star and part-
line configurations,
with one master
and several
remotes on each of
various
communication
channels
M
R2
R1
R3
R4
R7
R8
R6
R5
4/25/2014 39
s ganesh babu
4/25/2014 40
s ganesh babu
SUBSTATION SYSTEM
 Consists of two marshalling boxes accommodating:
 One, Interfaces the substation equipments with the
RTU.
 Accommodates transducers, TVM’s, contactors etc.,
 The other panel holds all other radio and
communication accessories along with RTU.
 The interfacing work at the substation
includes:
 Erection of SCADA marshalling panel, either
designed and custom made, or fabricated.
 Fixing of components and accessories,
 Wiring and dressing of the wires to be connected to
the components.
4/25/2014 41
s ganesh babu
Transducer
Input 5 A/1A
Output 4-20 mA
4/25/2014 42
s ganesh babu
Digital data (on/off) may have alarms attached
to one state or the other.
4/25/2014 43
s ganesh babu
Pulse data (e.g counting revolutions of a meter)
is normally accumulated or counted.
4/25/2014 44
s ganesh babu
4/25/2014 45
s ganesh babu
4/25/2014 46
s ganesh babu
4/25/2014 47
s ganesh babu
4/25/2014 48
s ganesh babu
4/25/2014 49
s ganesh babu
4/25/2014 50
s ganesh babu
4/25/2014 51
s ganesh babu
SUBSTATION SYSTEM (CONT’D)
 Laying of 4 core and 10 core cables
from the field/ control room to the
panel including formation of cable duct
where ever required.
 Termination of the leads at appropriate
points including crimping of lugs and
provision of ferrules.
 Providing of Earth connection to the
marshalling box from the equi-potential
bar.
4/25/2014 52
s ganesh babu
SUBSTATION SYSTEM (CONT’D)
 Ensuring vermin proof cable entry points in
the marshalling box with the provision of
suitable cable glands.
 The components that are housed in the
SCADA marshalling box are:
 AC current transducer to every feeder to
measure Y phase current.
 Secure make electronic trivector meter for
measurement of TVM parameters at power
transformer LV breakers.
 Voltage transducers to measure HV and LV
voltages.
4/25/2014 53
s ganesh babu
SUBSTATION SYSTEM (CONT’D)
 Position transducers to indicate the tap
position.
 DC voltage transducers to measure D .C.
voltage.
 48V DC contactors to initiate close and
trip pulse to the breaker.
 48V contactors to raise and lower taps on
the OLTC.
 220/24 V contactors for annunciating
buch’olz and temperature alarms for each
transformer.
4/25/2014 54
s ganesh babu
4/25/2014 55
s ganesh babu
CABLES
 Signal cables shall be of a type and installed in
a manner so to reduce common-mode and
induced noise to a minimum.
 Metallic shields shall be employed on all
cables. All grounding of shields and signal
circuits shall be at one point only to prevent
ground loops, except where double shielded
cable is used, in which case the outer shield
may be grounded at both ends.
4/25/2014 s ganesh babu 56
CABLES
 All terminals and terminal blocks shall
be clearly identified.
 All connectors, cable harnesses and
inter – rack wiring shall be clearly
identified so that no ambiguity can occur.
 Connector pin numbering shall be
identical at each and of the cable.
4/25/2014 s ganesh babu 57
48V DC battery with Float cum boost charger
 Supplies DC voltage to RTU
and the contactors which
activates the operation of
OLTC and breaker
operations.
4/25/2014 58
s ganesh babu
Thank you all for
a patient
listening!
4/25/2014 59
s ganesh babu

More Related Content

Similar to Optimize SCADA-RTU Interface Document

Scada For G Mgt
Scada For G MgtScada For G Mgt
Scada For G MgtAnil Patil
 
Scada Based Online Circuit Breaker Monitoring System
Scada Based Online Circuit Breaker Monitoring SystemScada Based Online Circuit Breaker Monitoring System
Scada Based Online Circuit Breaker Monitoring SystemIOSR Journals
 
Scada system Final Hakeem luqman pak version.pptx
Scada system Final Hakeem luqman pak version.pptxScada system Final Hakeem luqman pak version.pptx
Scada system Final Hakeem luqman pak version.pptxFaisalSheraz4
 
Computer Applications in Power Systems 2023 SECOND.pdf
Computer Applications in Power Systems 2023 SECOND.pdfComputer Applications in Power Systems 2023 SECOND.pdf
Computer Applications in Power Systems 2023 SECOND.pdfhussenbelew
 
A low cost short range wireless embedded system for multiple parameter control
A low cost short range wireless embedded system for multiple parameter controlA low cost short range wireless embedded system for multiple parameter control
A low cost short range wireless embedded system for multiple parameter controleSAT Journals
 
A low cost short range wireless embedded system for multiple parameter control
A low cost short range wireless embedded system for multiple parameter controlA low cost short range wireless embedded system for multiple parameter control
A low cost short range wireless embedded system for multiple parameter controleSAT Publishing House
 
Fundamentals of Automation Technology 20EE43P C-20 Lab Manual SCADA.pdf
Fundamentals of Automation Technology 20EE43P C-20  Lab Manual SCADA.pdfFundamentals of Automation Technology 20EE43P C-20  Lab Manual SCADA.pdf
Fundamentals of Automation Technology 20EE43P C-20 Lab Manual SCADA.pdfTHANMAY JS
 
Scada and power system automation
Scada and power system automationScada and power system automation
Scada and power system automationShubham Kapoor
 
Remote Terminal Unit (RTU) in SCADA.pptx
Remote Terminal Unit (RTU) in SCADA.pptxRemote Terminal Unit (RTU) in SCADA.pptx
Remote Terminal Unit (RTU) in SCADA.pptxDrAyyarKandasamy
 
SCADA only for the advance version of the module
SCADA only for the advance version of the moduleSCADA only for the advance version of the module
SCADA only for the advance version of the moduleAJITTHAKUR68
 
SCADA Assignment.pptx
SCADA Assignment.pptxSCADA Assignment.pptx
SCADA Assignment.pptxssuser1831ba
 
PLC and SCADA communication
PLC and SCADA communicationPLC and SCADA communication
PLC and SCADA communicationTalha Shaikh
 
Wireless SCADA Data Communications
Wireless SCADA Data CommunicationsWireless SCADA Data Communications
Wireless SCADA Data CommunicationsDaniel Ehrenreich
 
Wireless Valve Monitoring System From Rotork
Wireless Valve Monitoring System From RotorkWireless Valve Monitoring System From Rotork
Wireless Valve Monitoring System From RotorkCTi Controltech
 
Airtificial Intelligence in Power System
Airtificial Intelligence in Power SystemAirtificial Intelligence in Power System
Airtificial Intelligence in Power SystemPratik Doshi
 
IRJET - Automated Monitoring Test Rig for Circuit Breaker Operation
IRJET -  	  Automated Monitoring Test Rig for Circuit Breaker OperationIRJET -  	  Automated Monitoring Test Rig for Circuit Breaker Operation
IRJET - Automated Monitoring Test Rig for Circuit Breaker OperationIRJET Journal
 

Similar to Optimize SCADA-RTU Interface Document (20)

Scada For G Mgt
Scada For G MgtScada For G Mgt
Scada For G Mgt
 
Scada Based Online Circuit Breaker Monitoring System
Scada Based Online Circuit Breaker Monitoring SystemScada Based Online Circuit Breaker Monitoring System
Scada Based Online Circuit Breaker Monitoring System
 
Scada System
Scada  SystemScada  System
Scada System
 
Scada system Final Hakeem luqman pak version.pptx
Scada system Final Hakeem luqman pak version.pptxScada system Final Hakeem luqman pak version.pptx
Scada system Final Hakeem luqman pak version.pptx
 
Computer Applications in Power Systems 2023 SECOND.pdf
Computer Applications in Power Systems 2023 SECOND.pdfComputer Applications in Power Systems 2023 SECOND.pdf
Computer Applications in Power Systems 2023 SECOND.pdf
 
A low cost short range wireless embedded system for multiple parameter control
A low cost short range wireless embedded system for multiple parameter controlA low cost short range wireless embedded system for multiple parameter control
A low cost short range wireless embedded system for multiple parameter control
 
A low cost short range wireless embedded system for multiple parameter control
A low cost short range wireless embedded system for multiple parameter controlA low cost short range wireless embedded system for multiple parameter control
A low cost short range wireless embedded system for multiple parameter control
 
Customized Monitoring and Assessment of Circuit Breaker Operations in Differe...
Customized Monitoring and Assessment of Circuit Breaker Operations in Differe...Customized Monitoring and Assessment of Circuit Breaker Operations in Differe...
Customized Monitoring and Assessment of Circuit Breaker Operations in Differe...
 
Fundamentals of Automation Technology 20EE43P C-20 Lab Manual SCADA.pdf
Fundamentals of Automation Technology 20EE43P C-20  Lab Manual SCADA.pdfFundamentals of Automation Technology 20EE43P C-20  Lab Manual SCADA.pdf
Fundamentals of Automation Technology 20EE43P C-20 Lab Manual SCADA.pdf
 
UNIT-5-PPT.ppt
UNIT-5-PPT.pptUNIT-5-PPT.ppt
UNIT-5-PPT.ppt
 
Scada and power system automation
Scada and power system automationScada and power system automation
Scada and power system automation
 
Remote Terminal Unit (RTU) in SCADA.pptx
Remote Terminal Unit (RTU) in SCADA.pptxRemote Terminal Unit (RTU) in SCADA.pptx
Remote Terminal Unit (RTU) in SCADA.pptx
 
SCADA only for the advance version of the module
SCADA only for the advance version of the moduleSCADA only for the advance version of the module
SCADA only for the advance version of the module
 
SCADA Assignment.pptx
SCADA Assignment.pptxSCADA Assignment.pptx
SCADA Assignment.pptx
 
PLC and SCADA communication
PLC and SCADA communicationPLC and SCADA communication
PLC and SCADA communication
 
Wireless SCADA Data Communications
Wireless SCADA Data CommunicationsWireless SCADA Data Communications
Wireless SCADA Data Communications
 
Wireless Valve Monitoring System From Rotork
Wireless Valve Monitoring System From RotorkWireless Valve Monitoring System From Rotork
Wireless Valve Monitoring System From Rotork
 
Airtificial Intelligence in Power System
Airtificial Intelligence in Power SystemAirtificial Intelligence in Power System
Airtificial Intelligence in Power System
 
IRJET - Automated Monitoring Test Rig for Circuit Breaker Operation
IRJET -  	  Automated Monitoring Test Rig for Circuit Breaker OperationIRJET -  	  Automated Monitoring Test Rig for Circuit Breaker Operation
IRJET - Automated Monitoring Test Rig for Circuit Breaker Operation
 
Fps scada
Fps scadaFps scada
Fps scada
 

More from NagsSuresh

highvoltagecircuitbreakers-180415102549.pdf
highvoltagecircuitbreakers-180415102549.pdfhighvoltagecircuitbreakers-180415102549.pdf
highvoltagecircuitbreakers-180415102549.pdfNagsSuresh
 
dineshcb-210227061032.pptx
dineshcb-210227061032.pptxdineshcb-210227061032.pptx
dineshcb-210227061032.pptxNagsSuresh
 
Introduction_to_Kiln_Control_Operator_Development._1686913164.pdf
Introduction_to_Kiln_Control_Operator_Development._1686913164.pdfIntroduction_to_Kiln_Control_Operator_Development._1686913164.pdf
Introduction_to_Kiln_Control_Operator_Development._1686913164.pdfNagsSuresh
 
motor_1684283145.pdf
motor_1684283145.pdfmotor_1684283145.pdf
motor_1684283145.pdfNagsSuresh
 
Pumps_alignment_1684283213.pdf
Pumps_alignment_1684283213.pdfPumps_alignment_1684283213.pdf
Pumps_alignment_1684283213.pdfNagsSuresh
 

More from NagsSuresh (6)

highvoltagecircuitbreakers-180415102549.pdf
highvoltagecircuitbreakers-180415102549.pdfhighvoltagecircuitbreakers-180415102549.pdf
highvoltagecircuitbreakers-180415102549.pdf
 
dineshcb-210227061032.pptx
dineshcb-210227061032.pptxdineshcb-210227061032.pptx
dineshcb-210227061032.pptx
 
PPT.pptx
PPT.pptxPPT.pptx
PPT.pptx
 
Introduction_to_Kiln_Control_Operator_Development._1686913164.pdf
Introduction_to_Kiln_Control_Operator_Development._1686913164.pdfIntroduction_to_Kiln_Control_Operator_Development._1686913164.pdf
Introduction_to_Kiln_Control_Operator_Development._1686913164.pdf
 
motor_1684283145.pdf
motor_1684283145.pdfmotor_1684283145.pdf
motor_1684283145.pdf
 
Pumps_alignment_1684283213.pdf
Pumps_alignment_1684283213.pdfPumps_alignment_1684283213.pdf
Pumps_alignment_1684283213.pdf
 

Recently uploaded

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 

Optimize SCADA-RTU Interface Document

  • 1. SCADA – RTU INTERFACE BY S . GANESH BABU
  • 2. SCADA DEFINED • A formal definition of SCADA system, as recommended by IEEE, is: • “A collection of equipment that will provide an operator at a remote location with sufficient information to determine the status of a particular equipment or a process and cause actions to take place regarding that equipment or process without being physically present”. 4/25/2014 2 s ganesh babu
  • 3. Power System Automation • A power system consists of devices that generate, transmit, and distribute power. • Power system automation is the act of automatically controlling the power system via automated processes within computers and intelligent I&C devices. • It consists of three major processes: • data acquisition, • power system supervision, • and power system control, all, working in a coordinated automatic fashion. 4/25/2014 3 s ganesh babu
  • 4. Power System Automation (CONT’D) • Data acquisition refers to; • Collecting data in the form of measured analog current or voltage values, • The open or closed status of contact points. • Control refers to sending command messages to a device to operate the I&C (A collection of devices that monitor, control and protect the system is referred as instrumentation and control (I&C) system)and power system devices 4/25/2014 4 s ganesh babu
  • 5. INSTRUMENTATION SUB SYSTEM:  Measurement and feeding of various parameters such as :  Voltage, Current, power, circuit breaker status, and alarms needs a supporting sub system.  The parameters are fed into the substation telemetry equipment called RTU ( Remote telemetry unit or remote terminal unit).  Analogs:  Bus voltage: source : bus potential transformer.  and currents in all feeders and transformers: source – current transformers. 4/25/2014 5 s ganesh babu
  • 6. INSTRUMENTATION SUB SYSTEM (CONT’D)  Power in MW, KVAR, Power factor from LV breaker.  Analogue measurements carried out by Industrial standard transducers with an output of 4 – 20mA and 1 to 5v D.C. 4/25/2014 6 s ganesh babu
  • 7. STATUS INPUTS:  Breaker “ON / OFF” status.  Alarms for oil, buch’olz, oil and winding temperature.  OLTC positions for transformers.  Capacitor banks.  All status inputs calls for voltage free contact terminals.  4/25/2014 7 s ganesh babu
  • 8. SCAN RATE  Central control room monitors a series of mixture of analog and status inputs the frequency of which is decided by the priorities and fleeting events.  Scanning rate depends on nature of substation parameters.  Voltage rating and type of substation.  Non fleeting status and analog would require a scanning rate 0f 2 to 3 minutes.  Fleeting and high priority inputs require a scanning rate of 5 to 10 secs and is decided based on the following factors. 4/25/2014 8 s ganesh babu
  • 9. SCAN RATE CONT’D  Importance of the substation to the grid.  Voltage rating : Higher the voltage rating, the more the importance,  Cost factor, which decides the type of communication and the choice of the scan rate.  Ex: High Speed TDMA link between central control center and the substation and its exclusivity.  4/25/2014 9 s ganesh babu
  • 10. Applications of SCADA System  Automatic Switching  Emergency Load shedding  Re-routing services for station maintenance  Automatic transfer schemes  Load sectionalizing  Custom, automatic reclosing schemes  Automatic service restoration  Circuit breaker control and interlocking  Feeder automation and fault recovery 4/25/2014 10 s ganesh babu
  • 11. Applications of SCADA System  Protection and Control • Circuit breaker lockout • Protective relay interface/interaction • Dynamic protective relay setting for dynamic station topology  Voltage Regulation Management • Load Tap Changer (LTC) control • Voltage regulator control • Capacitor control 4/25/2014 11 s ganesh babu
  • 12. Applications of SCADA System  Transformer Management • Parameter monitoring and alarming • Real-time modeling • Interface to existing transformer monitors  Automatic System Diagnostics • Power apparatus health monitoring • PLC and communications self monitoring • Report and alarm on IED self diagnostics 4/25/2014 12 s ganesh babu
  • 13. Applications of SCADA System  Maintenance and Safety  Kirk Key interlock management  Maintenance ‘Lock-out/Tag-out management  Automatic circuit isolation control 4/25/2014 13 s ganesh babu
  • 14. Applications of SCADA System  Station MMIs – Graphical User Interface (GUI)  Interface real-time single-line displays  Interactive real-time breaker and switch control display  On-line operation and maintenance logs  Sequence of events recording  IED detail displays  Parameter trending displays 4/25/2014 14 s ganesh babu
  • 15. Advantages of SCADA system in power sector  Increased reliability, lower costs.  Forecasting accurate demand supply management  Faster restoration of power in case of a break down  Better active and reactive power management  Reduced maintenance cost, conditioning monitoring  Reduce human influence and errors  Assists operator for faster decision making  Automated meter reading  Easy fault diagnosis 4/25/2014 15 s ganesh babu
  • 16. Additional advantages of SCADA system in power sector  Availability of information  Analysis of information  Decision making  Optimized system operation (competitive environment)  Equipment condition monitoring (ECM)  Equipment parameters are automatically tracked to detect abnormalities.  Timely action, Extended life  ECM IEDs available  Sequence Of Events (SOE) recording 4/25/2014 16 s ganesh babu
  • 17. SCADA System  A SCADA system generally consists of a master station and a number of geographically dispersed Remote Terminal Units (RTUs), all interconnected to master station via a variety of communication channels. 4/25/2014 17 s ganesh babu
  • 18. Supervisory Remote Terminal Units  RTU is the eyes, ears and hands of the Master Station.  In most applications the RTU is the slave of the Master Station, but in some applications the RTU is equipped with internal computational and/or optimizing capabilities. 4/25/2014 18 s ganesh babu
  • 20. Remote Terminal Units  AVAILABILITY:  The availability of the RTU shall be 0.999 over the 12 month period of maintenance exclusive of communication channel and other purchaser caused down time.  Availability = MTBF / ( MTBF + MTTR)  MTBF = Mean Time between failure  MTTR = Mean Time to repair 4/25/2014 20 s ganesh babu
  • 21. REMOTE TERMINAL UNITS (RTU)  RTU consists of:  The protocol processor module  Communication module  Data processing Module  I/O modules for analog inputs  Digital input and output  RTU signals from transducers, relays, breaker auxiliary switches, and TVMs.  Data transmitted to DCC through communication media (TDMA and MAR) 4/25/2014 21 s ganesh babu
  • 22. REMOTE TERMINAL UNITS (RTU)  Functions of RTU include  Input scanning  Alarm,  And change of state detection.  With high degree of reliability, security and integrity. 4/25/2014 22 s ganesh babu
  • 23. Transmission and coding system of RTU.  The I/O channels are defined based on the need of each substation, and the RTU is configured accordingly.  These modules interface through memory mapping to the micro processor.  The RTU scans analogue and digital data non stop, and stores the analogue information after converting it in its memory.  The RTU’s at each substation are accessed and addressed independently.  The electrical and communication format to the mail port is usually RS 232. 4/25/2014 23 s ganesh babu
  • 24. SYSTEM DIAGNOSTICS  Typical diagnostics and indications provided in the RTU are :  Power LED: Indicates power applied to the base board when switched on.  RUN LED: Indicates healthy operating system.  LPAT LED: Indicates too low voltage on the input side.  Watch Dog time out LED.  Status LED: Gives a binary coded output if the system fails a soft ware confidence test. 4/25/2014 24 s ganesh babu
  • 25. SYSTEM DIAGNOSTICS (cont’d)  Diagnostic capability at the I/O module level.  Hardware read back at telecom and output circuit for verification of data at the field connection point.  Verification of memory and certain peripheral chips in operating system.  Communication diagnostics to indicate activity on the receiver and transmitter lines for both main and local ports. 4/25/2014 25 s ganesh babu
  • 26. Communication Subsystem  The communication subsystem is the interface between the communication network and the RTU internal logic.  This subsystem receives the messages from the master, interprets the message, initiates action within the RTU, and sends an appropriate response to the master. 4/25/2014 26 s ganesh babu
  • 27. Communication Subsystem (cont’d)  PRIMARY COMMUNICATION  64 kbps TDM/TDMA (time division multiple access operating in 2.3/2.5 GHZ band and the out stations extend to EHV stations.  SECONDARY COMMUNICATION:  Is 9.6 KBPS MAR (multiple access Radio) system operating in 849/943 MHZ band.  Mar remotes are located in all 33/11 kv substations. 4/25/2014 27 s ganesh babu
  • 29. Logic Subsystem  The logic subsystem consists of the main microprocessor and the database.  It handles all major processing, time keeping, and control sensing.  It also handles analog-to digital conversions and computation /optimization, if required. 4/25/2014 29 s ganesh babu
  • 30. Termination Subsystem  The termination subsystem provides the interface between the RTU logic and external equipment such as the communications lines, primary power source and the substation devices.  These assemblies must be designed to protect the RTU logic from the harsh environment of the station. 4/25/2014 30 s ganesh babu
  • 31. Power Supply Subsystem  The power supply, like the termination subsystem, must meet the various voltage surge standards.  The power supply convenes primary power, usually from the substation battery, to the supply requirements of the other RTUs subsystem.  If a station battery is not available, the unit is normally ordered for ac operation with built- in battery back-up to cover several hours of operation.  Care should be exercised in selecting an ac supply circuit to assure a reliable and stable, noise-fee source. 4/25/2014 31 s ganesh babu
  • 32. Communication  In addition, occurrences of noise on the communication channel seeks reinforcements in the form of additional master station and RTU hardware and software design to ensure distortion free signal transfer.  Communication channels limit the speed at which data acquisition and control can be performed, thus affecting the master station man-machine interface and applications software design. 4/25/2014 32 s ganesh babu
  • 35. SCADA System Configurations  The configurations of communication systems are dictated by the following:  Number of RTUs  Number of points at RTUs and required update rates  Location of RTUs  Communication facilities available  Communication equipment and techniques available 4/25/2014 35 s ganesh babu
  • 36. SCADA System Configurations  Block diagram for a one-on-one SCADA system configuration, with a master unit for each remote unit M R 1 M R2 4/25/2014 36 s ganesh babu
  • 37. SCADA System Configurations  Block diagram for a star or hub SCADA system configuration, with one master unit for several remotes, but with only one remote on each communication channel. M 4/25/2014 37 s ganesh babu
  • 38. SCADA System Configurations  Block diagram for a party-line SCADA system configuration, with several remote units on a single communication channel. M R1 R2 R3 R4 4/25/2014 38 s ganesh babu
  • 39. SCADA System Configurations  Block diagram for a SCADA system configuration, combining the characteristics of the star and part- line configurations, with one master and several remotes on each of various communication channels M R2 R1 R3 R4 R7 R8 R6 R5 4/25/2014 39 s ganesh babu
  • 41. SUBSTATION SYSTEM  Consists of two marshalling boxes accommodating:  One, Interfaces the substation equipments with the RTU.  Accommodates transducers, TVM’s, contactors etc.,  The other panel holds all other radio and communication accessories along with RTU.  The interfacing work at the substation includes:  Erection of SCADA marshalling panel, either designed and custom made, or fabricated.  Fixing of components and accessories,  Wiring and dressing of the wires to be connected to the components. 4/25/2014 41 s ganesh babu
  • 42. Transducer Input 5 A/1A Output 4-20 mA 4/25/2014 42 s ganesh babu
  • 43. Digital data (on/off) may have alarms attached to one state or the other. 4/25/2014 43 s ganesh babu
  • 44. Pulse data (e.g counting revolutions of a meter) is normally accumulated or counted. 4/25/2014 44 s ganesh babu
  • 52. SUBSTATION SYSTEM (CONT’D)  Laying of 4 core and 10 core cables from the field/ control room to the panel including formation of cable duct where ever required.  Termination of the leads at appropriate points including crimping of lugs and provision of ferrules.  Providing of Earth connection to the marshalling box from the equi-potential bar. 4/25/2014 52 s ganesh babu
  • 53. SUBSTATION SYSTEM (CONT’D)  Ensuring vermin proof cable entry points in the marshalling box with the provision of suitable cable glands.  The components that are housed in the SCADA marshalling box are:  AC current transducer to every feeder to measure Y phase current.  Secure make electronic trivector meter for measurement of TVM parameters at power transformer LV breakers.  Voltage transducers to measure HV and LV voltages. 4/25/2014 53 s ganesh babu
  • 54. SUBSTATION SYSTEM (CONT’D)  Position transducers to indicate the tap position.  DC voltage transducers to measure D .C. voltage.  48V DC contactors to initiate close and trip pulse to the breaker.  48V contactors to raise and lower taps on the OLTC.  220/24 V contactors for annunciating buch’olz and temperature alarms for each transformer. 4/25/2014 54 s ganesh babu
  • 56. CABLES  Signal cables shall be of a type and installed in a manner so to reduce common-mode and induced noise to a minimum.  Metallic shields shall be employed on all cables. All grounding of shields and signal circuits shall be at one point only to prevent ground loops, except where double shielded cable is used, in which case the outer shield may be grounded at both ends. 4/25/2014 s ganesh babu 56
  • 57. CABLES  All terminals and terminal blocks shall be clearly identified.  All connectors, cable harnesses and inter – rack wiring shall be clearly identified so that no ambiguity can occur.  Connector pin numbering shall be identical at each and of the cable. 4/25/2014 s ganesh babu 57
  • 58. 48V DC battery with Float cum boost charger  Supplies DC voltage to RTU and the contactors which activates the operation of OLTC and breaker operations. 4/25/2014 58 s ganesh babu
  • 59. Thank you all for a patient listening! 4/25/2014 59 s ganesh babu