SlideShare a Scribd company logo
1 of 23
Analysis of Optimum Intershot Delay Arrangement Using Signature Hole
Method to Control Ground Vibration at Pit Pinang South ,
PT Kaltim Prima Coal, Sangatta.
Muhamad Rizky
03121402003
Universitas Sriwijaya, Indonesia
muhamad.rizky6694@gmail.com
Thesis
Bachelor Degree of Mining Engineering Department
UNIVERSITAS SRIWIJAYA
INTRODUCTION
INTRODUCTION
BACKGROUND
• The Signature hole method is not only an interesting theory, it works in
the field. Combined with electronic detonators and advanced
modeling software, it provides a huge benefit in vibration level
reduction. Without changing the charge per delay, results between 30%
and 70% of PPV reduction can be achieved with an accuracy of
prediction of 10%.
(THE TRUTH ABOUT SIGNATURE HOLE METHOD 2010 Thierry Bernard Technologie, DNA-Blast
Software, Nice, France)
Signature hole method
Intershot delay
INTRODUCTION
OBJECTIVE
General Objective :
Determining The optimum Intershot Delay using
Signature Hole Method combined with electronoc to
achieve PPV target max. 3 mm/s in Pit Pinang South.
Spesific Objective :
• Undertsanding The Technical Planning of Signature
Hole Method.
• Understanding The Analysis of Signature Waveform
to determine The Optimum Intershot delay.
• Understanding The Simulation of Intershot Delay in
Software Shotplus.
• Knowing The Actual PPV of Using the intershot delay
from Field Trial.
• The Research Location in Pit Pinang South and
Lithology assumed Homogen.
• Tie up system used with electronic detonator.
• The research did not change blasting geometry
and charging quantity and hence did not analyze
fragmentation and cost.
• Method Used in reducing ground vibration level
is Signature Hole Method through conducting
simulation and field trial toward intershot delay.
SCOPE
INTRODUCTION
RESEARCH FLOWCHART
Trial Signature Hole Project
Data Processing and Analysing
Split Signature Hole Wave --- Get Representative Signature Hole Wave
Simulate Signature Hole Analysis -- Get PPV result from varians of intershot delay
Determine Intershot Delay --- Get Optimum Intershot Delay
Simulate in Software --- Get the Timing Design
Field Trial of Optimum Intershot Delay
Not ValidValid
EvaluationRecommendation
Conclusion
S I G N AT U R E H O L E A N A LY S I S
( S H A )
PROJECT PLANNING
SIG. HOLE -1 SIG. HOLE -2
PRODUCTION HOLE
DATA PROCESSING
Blastmate III
File of Vibration data
Blastware 10
2. Read data Using Blastware
3. Convert to .txt file4. Analyze and process the data in Microsoft ecxcel
Split signature wave, analyze with Signature hole analysis, Determine
optimum Intershot Delay
1. Record blasting vibration
SIGNATURE HOLE ANALYSIS
𝑷𝑷𝑽 = (𝑻 𝟐)+(𝑽 𝟐)+(𝑳 𝟐)
Note :
T = tranversal wave velocity
V = vertikal wave velocity
L = longitudinal wave velocity
Linier superposition theory
Analisis signature hole was conducted based on linier superposition theory. Peak particle
velocity (PPV) can be determined by this equation:
Constructive Interference Destructive Interference
Wave Resultant
The Sum of each Individual Wave
SIGNATURE HOLE ANALYSIS (SHA)
Simulation of Signature Hole Analysis is based on Linier Superposition Concept (The Sum Of
Amplitudes of Velocity at the same time). Peak Particle Velocity (PPV) is determined by this
equation:
𝑷𝑷𝑽 = (𝑻 𝟐)+(𝑽 𝟐)+(𝑳 𝟐)
Information :
T = Velocity Amplitude of Transversal Wave
V = Velocity Amplitude of Vertical Wave
L = Velocity Amplitude of Longitudinal Wave
1 -0.0159 0 -0.0159
2 -0.0159 0 -0.0159
3 -0.0159 0 -0.0159
4 0.0317 0 0.0317
5 0.0317 0 0.0317
6 0.0794 0 0.0794
7 0.0794 0 0.0794
8 0.0952 0 0.0952
9 0.0952 0 0.0952
10 0.0794 0 0.0794
11 0.0952 0 0.0952
12 0.0476 0 0.0476
13 0.0476 0 0.0476
14 0.0159 0 0.0159
15 0.0159 0 0.0159
16 0.0159 0 0.0159
17 0.0476 0 0.0476
18 0.0635 0 0.0635
19 0.0317 0 0.0317
20 0.0317 0 0.0317
21 0.0635 -0.0159 0.0476
22 0.0476 -0.0159 0.0317
23 0.0159 -0.0159 0
24 0.0317 0.0317 0.0634
25 0 0.0317 0.0317
26 -0.0159 0.0794 0.0635
27 -0.0159 0.0794 0.0635
28 0 0.0952 0.0952
29 -0.0317 0.0952 0.0635
30 -0.0476 0.0794 0.0318
31 -0.0476 0.0952 0.0476
32 -0.0635 0.0476 -0.0159
33 -0.0794 0.0476 -0.0318
34 -0.0794 0.0159 -0.0635
35 -0.0635 0.0159 -0.0476
36 -0.0635 0.0159 -0.0476
37 -0.0952 0.0476 -0.0476
38 -0.0635 0.0635 0
39 -0.0794 0.0317 -0.0477
40 -0.0635 0.0317 -0.0318
41 -0.0317 0.0635 0.0318
42 -0.0159 0.0476 0.0317
43 0.0317 0.0159 0.0476
44 0.0794 0.0317 0.1111
45 0.0794 0 0.0794
46 0.0794 -0.0159 0.0635
47 0.0952 -0.0159 0.0793
48 0 0 0
49 0 -0.0317 -0.0317
50 0 -0.0476 -0.0476
51 0 -0.0476 -0.0476
52 0 -0.0635 -0.0635
53 0 -0.0794 -0.0794
54 0 -0.0794 -0.0794
55 0 -0.0635 -0.0635
56 0 -0.0635 -0.0635
57 0 -0.0952 -0.0952
58 0 -0.0635 -0.0635
59 0 -0.0794 -0.0794
60 0 -0.0635 -0.0635
61 0 -0.0317 -0.0317
62 0 -0.0159 -0.0159
63 0 0.0317 0.0317
64 0 0.0794 0.0794
65 0 0.0794 0.0794
66 0 0.0794 0.0794
67 0 0.0952 0.0952
1 -0.222 0 -0.222
2 -0.175 0 -0.175
3 -0.159 0 -0.159
4 -0.0635 0 -0.0635
5 0 0 0
6 0.0476 0 0.0476
7 0.111 0 0.111
8 0.159 0 0.159
9 0.159 0 0.159
10 0.159 0 0.159
11 0.127 0 0.127
12 0.0952 0 0.0952
13 0.0794 0 0.0794
14 0.0794 0 0.0794
15 0.111 0 0.111
16 0.159 0 0.159
17 0.175 0 0.175
18 0.254 0 0.254
19 0.381 0 0.381
20 0.444 0 0.444
21 0.524 -0.222 0.302
22 0.603 -0.175 0.428
23 0.683 -0.159 0.524
24 0.746 -0.0635 0.6825
25 0.778 0 0.778
26 0.762 0.0476 0.8096
27 0.698 0.111 0.809
28 0.635 0.159 0.794
29 0.54 0.159 0.699
30 0.444 0.159 0.603
31 0.365 0.127 0.492
32 0.302 0.0952 0.3972
33 0.27 0.0794 0.3494
34 0.206 0.0794 0.2854
35 0.159 0.111 0.27
36 0.143 0.159 0.302
37 0.143 0.175 0.318
38 0.127 0.254 0.381
39 0.111 0.381 0.492
40 0.0794 0.444 0.5234
41 0.0317 0.524 0.5557
42 -0.0159 0.603 0.5871
43 -0.0952 0.683 0.5878
44 -0.206 0.746 0.54
45 -0.333 0.778 0.445
46 -0.444 0.762 0.318
47 -0.556 0.698 0.142
48 0 0.635 0.635
49 0 0.54 0.54
50 0 0.444 0.444
51 0 0.365 0.365
52 0 0.302 0.302
53 0 0.27 0.27
54 0 0.206 0.206
55 0 0.159 0.159
56 0 0.143 0.143
57 0 0.143 0.143
58 0 0.127 0.127
59 0 0.111 0.111
60 0 0.0794 0.0794
61 0 0.0317 0.0317
62 0 -0.0159 -0.0159
63 0 -0.0952 -0.0952
64 0 -0.206 -0.206
65 0 -0.333 -0.333
66 0 -0.444 -0.444
67 0 -0.556 -0.556
1 0.0952 0 0.0952
2 0.0794 0 0.0794
3 0.0794 0 0.0794
4 0.0476 0 0.0476
5 0.0317 0 0.0317
6 0.0317 0 0.0317
7 -0.0159 0 -0.0159
8 -0.0476 0 -0.0476
9 -0.0952 0 -0.0952
10 -0.0952 0 -0.0952
11 -0.0794 0 -0.0794
12 -0.0794 0 -0.0794
13 -0.0635 0 -0.0635
14 -0.0635 0 -0.0635
15 -0.0476 0 -0.0476
16 -0.0635 0 -0.0635
17 -0.0635 0 -0.0635
18 -0.111 0 -0.111
19 -0.159 0 -0.159
20 -0.159 0 -0.159
21 -0.175 0.0952 -0.0798
22 -0.206 0.0794 -0.1266
23 -0.206 0.0794 -0.1266
24 -0.238 0.0476 -0.1904
25 -0.19 0.0317 -0.1583
26 -0.19 0.0317 -0.1583
27 -0.143 -0.0159 -0.1589
28 -0.127 -0.0476 -0.1746
29 -0.0794 -0.0952 -0.1746
30 -0.0635 -0.0952 -0.1587
31 -0.0476 -0.0794 -0.127
32 0 -0.0794 -0.0794
33 0 -0.0635 -0.0635
34 0 -0.0635 -0.0635
35 0 -0.0476 -0.0476
36 0 -0.0635 -0.0635
37 0.0159 -0.0635 -0.0476
38 -0.0159 -0.111 -0.1269
39 -0.0159 -0.159 -0.1749
40 0 -0.159 -0.159
41 0 -0.175 -0.175
42 0.0159 -0.206 -0.1901
43 0.0317 -0.206 -0.1743
44 0.0317 -0.238 -0.2063
45 0.0317 -0.19 -0.1583
46 0.0794 -0.19 -0.1106
47 0.0635 -0.143 -0.0795
48 0 -0.127 -0.127
49 0 -0.0794 -0.0794
50 0 -0.0635 -0.0635
51 0 -0.0476 -0.0476
52 0 0 0
53 0 0 0
54 0 0 0
55 0 0 0
56 0 0 0
57 0 0.0159 0.0159
58 0 -0.0159 -0.0159
59 0 -0.0159 -0.0159
60 0 0 0
61 0 0 0
62 0 0.0159 0.0159
63 0 0.0317 0.0317
64 0 0.0317 0.0317
65 0 0.0317 0.0317
66 0 0.0794 0.0794
67 0 0.0635 0.0635
Tranversal LongitudinalVertical
0.242074
0.192827
0.178433
0.085457
0.044831
0.097852
0.137398
0.191337
0.208344
0.201614
0.177472
0.13279
0.11226
0.102905
0.121818
0.171948
0.192154
0.284375
0.414061
0.472675
0.315971
0.447456
0.539077
0.711392
0.794574
0.827371
0.826899
0.818526
0.723269
0.624344
0.510352
0.40537
0.356544
0.299195
0.278265
0.312253
0.325047
0.401578
0.524337
0.547941
0.583471
0.617923
0.614943
0.588645
0.478945
0.34262
0.181032
0.647575
0.546726
0.451037
0.371156
0.308604
0.281433
0.220772
0.171211
0.156465
0.172525
0.142878
0.137398
0.101669
0.044831
0.02754
0.105227
0.223036
0.3438
0.457979
0.567654
PPV
PPV. 0.82 mm/s
NOTE
Based on Signature Hole Analysis – Simulation with
several Intershot Delays
(8ms, 16ms, 32ms, 40ms, 48ms, 56ms, 64ms, 72ms, 80ms, 88ms, 96ms,
104ms)
64 ms is the Optimum Intershot Delay to reduce
vibration, that will result PPV 1.68
Therefore, There was a Decreasing of PPV at about
16.34% from the Simulation Using Linier
Superposition Concept
Example : Signature Hole Wave
PPV : 2.011
SHA – Simulation
Intershot Delay 64 ms
PPV : 1.682
SHA – Simulation
Intershot Delay 32 ms
PPV : 3.145
SHA SIMULATIONUsing Microsoft Excel 2010
DATA
No. Tanggal Trial
Signature
hole
Titik
Ukur
D (m) L (m) PC (Kg) T (m) Ket.
1 02/05/2016
PN11WK17
P1
SH-1 A 755 8.5 126 5 No
2 13/05/2016
PN21WK19
P1
SH-1 A 564 5.4 69 3.5 No
3 03/06/2016
PN20WK22
P1
SH-1 A 740 5.4 70 3.1 No
SH-2 A 733 5 70 3.1 No
4 11/06/2016
PN30WK23
P2
SH-1 B 695 10.5 205 6.5 Yes
SH-2 B 705 9.5 174 6.5 Yes
5 30/06/2016
PN22WK25
P1
SH-1 A 1007 4 63 2.8 No
SH-2 A 1018 4.5 74 3.3 No
6 30/06/2016
PN02WK26
P1
SH-1 C 882 5.2 83 3.3 Yes
SH-2 C 891 5.3 83 3.3 Yes
7 30/06/2016
PN13WK26
P1
SH-1 A 598 5.8 92 3.5 Yes
SH-1 C 757 5.8 92 3.5 Yes
SIGNATURE HOLE PROJECT
Blasting
Parameters
Value
Burden 7.4 m
Spasi 8.5 m
Hole Diameter 200 mm
Blasthole Inclination Vertical
Detonator Elektronik (Unitonic 600)
Initiation System Box Cut - Rectangular Staggered
Delay System 48 ms (Inter-hole) dan 104 ms (Inter-
row)
DATA- PN30WK23
Signature Hole 2Signature Hole 1
PPV Result – TRIAL Simulation with varians Intershot Delay
Optimum intershot delay was determined at 40 ms
SHA SIMULATION – PN30WK23
Signature Hole D (m) H (m) C (kg) T (m) PPV (mm/s) PPV PH (mm/s)
SH-1
700
10.5 205 6.5 2.69
6.16
SH-2 9.5 9.5 6.5 2.44
PPV Decreasing: 60.7% PPV Decreasing : 66.7%
SH-1 SH-2
PH
Signature Hole D (m) H (m) C (kg) T (m) PPV (mm/s) PPV PH (mm/s)
SH-1
885
5.4 83 3.3 0.815
2.06
SH-2 5.2 83 3.3 0.526
SHA SIMULATION – PN02WK26
PPV Result – TRIAL Simulation with varians Intershot Delay
Signature Hole 2Signature Hole 1
Optimum intershot delay was determined at 40 ms
SHA SIMULATION – PN02WK26
DATA – PN02WK26
8 ms 4.03 mm/s
16 ms 1.78 mm/s
24 ms 1.31 mm/s
32 ms 0.92 mm/s
40 ms 0.92 mm/s
48 ms 0.97 mm/s
56 ms 0.98 mm/s
64 ms 1.35 mm/s
72 ms 1.28 mm/s
80 ms 1.05 mm/s
88 ms 1.26 mm/s
96 ms 1.04 mm/s
104 ms 1.22 mm/s
PPV MAX.INTERSHOT DELAY
8 ms 6.24 mm/s
16 ms 2.53 mm/s
24 ms 2.28 mm/s
32 ms 1.53 mm/s
40 ms 1.32 mm/s
48 ms 1.39 mm/s
56 ms 1.43 mm/s
64 ms 1.93 mm/s
72 ms 2.68 mm/s
80 ms 2 mm/s
88 ms 2.13 mm/s
96 ms 1.5 mm/s
104 ms 1.56 mm/s
PPV MAX.INTERSHOT DELAY
PPV Decreasing 55.33%PPV Decreasing : 35.9 %
SH-1 SH-2
PH
DATA – PN13WK26
Signature Hole D (m) H (m) C (kg) T (m) PPV (mm/s) PPV PH (mm/s)
SH 600 5.8 92 3.5 1.13 3.3
Signature Hole D (m) H (m) C (kg) T (m) PPV (mm/s) PPV PH (mm/s)
SH 757 5.8 92 3.5 0.65 2.22
Signature Hole Signature Hole
8 ms 9 mm/s
16 ms 3.44 mm/s
24 ms 2.58 mm/s
32 ms 2.05 mm/s
40 ms 1.32 mm/s
48 ms 1.34 mm/s
56 ms 1.66 mm/s
64 ms 1.66 mm/s
72 ms 2.63 mm/s
80 ms 1.66 mm/s
88 ms 1.5 mm/s
96 ms 2.12 mm/s
104 ms 1.84 mm/s
PPV MAX.INTERSHOT DELAY
8 ms 6.6 mm/s
16 ms 2.26 mm/s
24 ms 1.73 mm/s
32 ms 1.43 mm/s
40 ms 1.08 mm/s
48 ms 1.26 mm/s
56 ms 1.3 mm/s
64 ms 1.11 mm/s
72 ms 1.4 mm/s
80 ms 1.1 mm/s
88 ms 0.94 mm/s
96 ms 1.12 mm/s
104 ms 1.11 mm/s
PPV MAX.INTERSHOT DELAY
Optimum intershot delay was determined at 40 ms
PPV Decreasing : 60 % PPV Decreasing : 51.3 %
SH-1 SH-1
PH PH
Data of Signature Holes PPV actual PPV (Trial 40 ms) Decreasing
PN30WK23 SH1 6.16 2.42 60.70%
SH2 6.16 2.05 66.70%
PN02WK26 SH3 2.06 1.32 35.90%
SH4 2.06 0.92 55.30%
PN13WK26 SH5 3.3 1.32 60%
SH6 2.22 1.08 51.30%
Average PPV decreasing
54.98 %
• From SHA, The Optimum intershot delay was determined at 40 ms – (lowest PPV)
• The Simulation of Using Intershot delay 40 ms showed avarage PPV decreasing at about 54.98%.
RESUME
PPV 1.52 mm/s
TRIAL #1
PPV 1.83 mm/s
FIELD TRIAL
TRIAL #2
Intershot delay 40 ms
Trial
D
(m)
MIC
(kg)
PPV
actual
PPV Plan
(loading sheet)
From engineer
Var.
PPV Decreasing
(%)
PN10WK30 635 100 1.83 2.86 1.03 36.014
PN05WK31 590 100 1.52 2.99 1.47 49.164
RESUME OF FIELD TRIAL
Average PPV Decreasing
42.58 %
According to field trials using intershot delay 40 ms, they
resulted average PPV decreasing at about 42.58%
CLOSING
SUMMARY
Based on previous result mentioned, hence there can be summarized that:
1. Ground vibration control using signature hole analysis by applicating the optimum intershot delay can be
conducted trough several steps, among such steps are:
• Planning made was focused at 1-2 holes blast for the signature holes from blasting plan made by engineer.
Applicate delay timing about 3 second between signature hole and production holes.
• Vibration recording uses Blastmate III. Data that can be read in Blastware 10 need to be converted to .txt
file
• Wave splitting between Signature hole and production hole and data pocessing can be done through
Microsoft excel to determine the optimum intershot delay.
2. Simulation of Signature Hole Analysis (SHA) using Microsoft excelnachieved the optimum intershot delay at 40
ms with average PPV decreasing at about 54.98 %.
3. Applicating Intershot delay 40 ms in field trials achieved average PPV decreasing at about 42.58.
REFERENCES
Bernard, T. (2010). The Truth About Signature Hole Method. Nice, France: Thierry Bernard Technologie. .
Cunningham C. V. B. (2000). The effect of timing precision on control of blasting effects. Proceedings 1st EFEE Conference
on Explosives and Blasting Technique. Munich. pp. 123–127.
Gokhale B.V. (2009). Rotary drilling and blasting in large surface mines. Leiden, Netherland: CRC Press/Balkema.
Hustrulid, W. (1999). Blasting Principles For Open Pit Mining Volume 1. Rotterdam: A.A. Balkema.
Jimeno, C.L. dan Jimeno, E.L. (1995). Drilling and Blasting of Rocks. Rotterdam: A.A. Balkema.
Koesnaryo ,S. (2001). Pemboran Untuk Penyediaan Lubang Ledak. Yogyakarta: Teknik Pertambangan, UPN ‘Veteran’.
Konya, C.J., and Walter, E.J. (1990). Surface Blast Design. New Jersey, U.S.A: Prentice Hall. Englewood Cliffs.
Kusumaatmaja, S. (1996). Kepmen LH No.49 Tahun 1996: Baku Tingkat Getaran. Jakarta : MENLH.
Richards, A. B., Evans, R., and Moore A. J. (1994). Blast Vibration Control and Assessment Techniques. Proceedings of the
Fourth Large Open Pit Mining Conference, Australian Institute of Mining & Metallurgy. Perth, Western Australia.
SNI. (2010). SNI 7571:Baku Tingkat Getaran Peledakan pada Kegiatan Tambang Terbuka Terhadap Bangunan. Bandung:
BSN.
Turnbull, B. (2008). Just for the Record: Signature Hole Analysis. New York, USA: Instantel.
Yang, R., Scovira, D. S., & Patterson, N. J. (2009). An integrated approach of signature hole vibration monitoring and
modeling for quarry vibration control. International symposium on Rock fragmentation by blasting, London. pp. 597-
605.
THANK YOU
Muhamad Rizky
03121402003
Universitas Sriwijaya, Indonesia
muhamad.rizky6694@gmail.com

More Related Content

What's hot (20)

Flame safety lamp fsl
Flame safety lamp fslFlame safety lamp fsl
Flame safety lamp fsl
 
Longwall Mining
Longwall MiningLongwall Mining
Longwall Mining
 
Blast Design-2.pdf
Blast Design-2.pdfBlast Design-2.pdf
Blast Design-2.pdf
 
Subsidence
SubsidenceSubsidence
Subsidence
 
Methane drainage
Methane drainageMethane drainage
Methane drainage
 
Mine fire and extinguisher
Mine fire and extinguisher Mine fire and extinguisher
Mine fire and extinguisher
 
Board & Pillar
Board & PillarBoard & Pillar
Board & Pillar
 
Pillar design
Pillar designPillar design
Pillar design
 
Subsidence in coal mines
Subsidence in coal minesSubsidence in coal mines
Subsidence in coal mines
 
Bord Pillar
Bord PillarBord Pillar
Bord Pillar
 
Applicability of hydraulic mining
Applicability of hydraulic miningApplicability of hydraulic mining
Applicability of hydraulic mining
 
Design of openpit mining
Design of openpit miningDesign of openpit mining
Design of openpit mining
 
Basics of drilling 1
Basics of drilling 1Basics of drilling 1
Basics of drilling 1
 
Mine environmental eng ii
Mine environmental  eng iiMine environmental  eng ii
Mine environmental eng ii
 
Continuous miner
Continuous minerContinuous miner
Continuous miner
 
longwall mining
longwall mininglongwall mining
longwall mining
 
Haulage system in Mines
Haulage system in MinesHaulage system in Mines
Haulage system in Mines
 
Rock Drilling and Types of Rock Drilling
Rock Drilling and Types of Rock DrillingRock Drilling and Types of Rock Drilling
Rock Drilling and Types of Rock Drilling
 
Strata control
Strata control Strata control
Strata control
 
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W Z
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W ZTYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W Z
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W Z
 

Similar to Ground Vibration Control Using Signature Hole Method - Thesis BE Mining, Universitas Sriwijaya

R. De Santis, M. Fioramanti, A. Girardi, C. Pappalardo - The track record of...
R. De Santis, M. Fioramanti, A. Girardi,  C. Pappalardo - The track record of...R. De Santis, M. Fioramanti, A. Girardi,  C. Pappalardo - The track record of...
R. De Santis, M. Fioramanti, A. Girardi, C. Pappalardo - The track record of...Istituto nazionale di statistica
 
Rigidez de Dos Pórticos para Dos Niveles de Piso - Albañilería Estructural
Rigidez de Dos Pórticos para Dos Niveles de Piso - Albañilería EstructuralRigidez de Dos Pórticos para Dos Niveles de Piso - Albañilería Estructural
Rigidez de Dos Pórticos para Dos Niveles de Piso - Albañilería EstructuralIRMA Trejo Amado
 
Laser Scanning Inspection Report-Reference
Laser Scanning Inspection Report-ReferenceLaser Scanning Inspection Report-Reference
Laser Scanning Inspection Report-Reference灿 冯
 
PREDICTION OF TOOL WEAR USING ARTIFICIAL NEURAL NETWORK IN TURNING OF MILD STEEL
PREDICTION OF TOOL WEAR USING ARTIFICIAL NEURAL NETWORK IN TURNING OF MILD STEELPREDICTION OF TOOL WEAR USING ARTIFICIAL NEURAL NETWORK IN TURNING OF MILD STEEL
PREDICTION OF TOOL WEAR USING ARTIFICIAL NEURAL NETWORK IN TURNING OF MILD STEELSourav Samanta
 
#3 boss buffer od under size final
#3 boss buffer od under size final#3 boss buffer od under size final
#3 boss buffer od under size finalKRSAshishKumar
 
ABB POLIM-H..N High Voltage Surge Arresters AC up to 72 kV - AC Surge Arreste...
ABB POLIM-H..N High Voltage Surge Arresters AC up to 72 kV - AC Surge Arreste...ABB POLIM-H..N High Voltage Surge Arresters AC up to 72 kV - AC Surge Arreste...
ABB POLIM-H..N High Voltage Surge Arresters AC up to 72 kV - AC Surge Arreste...Thorne & Derrick International
 
стандарт хэвийн тархалт
стандарт хэвийн тархалтстандарт хэвийн тархалт
стандарт хэвийн тархалтAdilbishiin Gelegjamts
 
DSD-NL 2014 - iMOD Symposium - 9. iPEST - iMOD parameter estimation, Peter Ve...
DSD-NL 2014 - iMOD Symposium - 9. iPEST - iMOD parameter estimation, Peter Ve...DSD-NL 2014 - iMOD Symposium - 9. iPEST - iMOD parameter estimation, Peter Ve...
DSD-NL 2014 - iMOD Symposium - 9. iPEST - iMOD parameter estimation, Peter Ve...Deltares
 
PosterFormatRNYF(1)
PosterFormatRNYF(1)PosterFormatRNYF(1)
PosterFormatRNYF(1)Usman Khalid
 
Tarea 2 hidraulica iii-cabrera arias roberto alejandro
Tarea 2 hidraulica iii-cabrera arias roberto alejandroTarea 2 hidraulica iii-cabrera arias roberto alejandro
Tarea 2 hidraulica iii-cabrera arias roberto alejandroAlejandro Cabrera
 
Multi Objective Optimization of PMEDM Process Parameter by Topsis Method
Multi Objective Optimization of PMEDM Process Parameter by Topsis MethodMulti Objective Optimization of PMEDM Process Parameter by Topsis Method
Multi Objective Optimization of PMEDM Process Parameter by Topsis Methodijtsrd
 
An Introduction to Statistical Methods and Data Analysis.pdf
An Introduction to Statistical Methods and Data Analysis.pdfAn Introduction to Statistical Methods and Data Analysis.pdf
An Introduction to Statistical Methods and Data Analysis.pdfSandra Valenzuela
 

Similar to Ground Vibration Control Using Signature Hole Method - Thesis BE Mining, Universitas Sriwijaya (20)

R. De Santis, M. Fioramanti, A. Girardi, C. Pappalardo - The track record of...
R. De Santis, M. Fioramanti, A. Girardi,  C. Pappalardo - The track record of...R. De Santis, M. Fioramanti, A. Girardi,  C. Pappalardo - The track record of...
R. De Santis, M. Fioramanti, A. Girardi, C. Pappalardo - The track record of...
 
Rigidez de Dos Pórticos para Dos Niveles de Piso - Albañilería Estructural
Rigidez de Dos Pórticos para Dos Niveles de Piso - Albañilería EstructuralRigidez de Dos Pórticos para Dos Niveles de Piso - Albañilería Estructural
Rigidez de Dos Pórticos para Dos Niveles de Piso - Albañilería Estructural
 
Change Point Analysis (CPA)
Change Point Analysis (CPA)Change Point Analysis (CPA)
Change Point Analysis (CPA)
 
Tk catalog english_18_1
Tk catalog english_18_1Tk catalog english_18_1
Tk catalog english_18_1
 
Laser Scanning Inspection Report-Reference
Laser Scanning Inspection Report-ReferenceLaser Scanning Inspection Report-Reference
Laser Scanning Inspection Report-Reference
 
PREDICTION OF TOOL WEAR USING ARTIFICIAL NEURAL NETWORK IN TURNING OF MILD STEEL
PREDICTION OF TOOL WEAR USING ARTIFICIAL NEURAL NETWORK IN TURNING OF MILD STEELPREDICTION OF TOOL WEAR USING ARTIFICIAL NEURAL NETWORK IN TURNING OF MILD STEEL
PREDICTION OF TOOL WEAR USING ARTIFICIAL NEURAL NETWORK IN TURNING OF MILD STEEL
 
Data Science Is More Than Just Statistics
Data Science Is More Than Just StatisticsData Science Is More Than Just Statistics
Data Science Is More Than Just Statistics
 
#3 boss buffer od under size final
#3 boss buffer od under size final#3 boss buffer od under size final
#3 boss buffer od under size final
 
Tabla z
Tabla zTabla z
Tabla z
 
FLT catalog
FLT catalogFLT catalog
FLT catalog
 
ABB POLIM-H..N High Voltage Surge Arresters AC up to 72 kV - AC Surge Arreste...
ABB POLIM-H..N High Voltage Surge Arresters AC up to 72 kV - AC Surge Arreste...ABB POLIM-H..N High Voltage Surge Arresters AC up to 72 kV - AC Surge Arreste...
ABB POLIM-H..N High Voltage Surge Arresters AC up to 72 kV - AC Surge Arreste...
 
стандарт хэвийн тархалт
стандарт хэвийн тархалтстандарт хэвийн тархалт
стандарт хэвийн тархалт
 
DSD-NL 2014 - iMOD Symposium - 9. iPEST - iMOD parameter estimation, Peter Ve...
DSD-NL 2014 - iMOD Symposium - 9. iPEST - iMOD parameter estimation, Peter Ve...DSD-NL 2014 - iMOD Symposium - 9. iPEST - iMOD parameter estimation, Peter Ve...
DSD-NL 2014 - iMOD Symposium - 9. iPEST - iMOD parameter estimation, Peter Ve...
 
AMW FIXTURES
AMW FIXTURESAMW FIXTURES
AMW FIXTURES
 
PosterFormatRNYF(1)
PosterFormatRNYF(1)PosterFormatRNYF(1)
PosterFormatRNYF(1)
 
AMW FIXTURES
AMW FIXTURESAMW FIXTURES
AMW FIXTURES
 
Tarea 2 hidraulica iii-cabrera arias roberto alejandro
Tarea 2 hidraulica iii-cabrera arias roberto alejandroTarea 2 hidraulica iii-cabrera arias roberto alejandro
Tarea 2 hidraulica iii-cabrera arias roberto alejandro
 
Multi Objective Optimization of PMEDM Process Parameter by Topsis Method
Multi Objective Optimization of PMEDM Process Parameter by Topsis MethodMulti Objective Optimization of PMEDM Process Parameter by Topsis Method
Multi Objective Optimization of PMEDM Process Parameter by Topsis Method
 
An Introduction to Statistical Methods and Data Analysis.pdf
An Introduction to Statistical Methods and Data Analysis.pdfAn Introduction to Statistical Methods and Data Analysis.pdf
An Introduction to Statistical Methods and Data Analysis.pdf
 
AMW FIXTURES
AMW FIXTURESAMW FIXTURES
AMW FIXTURES
 

Recently uploaded

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 

Recently uploaded (20)

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 

Ground Vibration Control Using Signature Hole Method - Thesis BE Mining, Universitas Sriwijaya

  • 1. Analysis of Optimum Intershot Delay Arrangement Using Signature Hole Method to Control Ground Vibration at Pit Pinang South , PT Kaltim Prima Coal, Sangatta. Muhamad Rizky 03121402003 Universitas Sriwijaya, Indonesia muhamad.rizky6694@gmail.com Thesis Bachelor Degree of Mining Engineering Department UNIVERSITAS SRIWIJAYA
  • 3. INTRODUCTION BACKGROUND • The Signature hole method is not only an interesting theory, it works in the field. Combined with electronic detonators and advanced modeling software, it provides a huge benefit in vibration level reduction. Without changing the charge per delay, results between 30% and 70% of PPV reduction can be achieved with an accuracy of prediction of 10%. (THE TRUTH ABOUT SIGNATURE HOLE METHOD 2010 Thierry Bernard Technologie, DNA-Blast Software, Nice, France) Signature hole method Intershot delay
  • 4. INTRODUCTION OBJECTIVE General Objective : Determining The optimum Intershot Delay using Signature Hole Method combined with electronoc to achieve PPV target max. 3 mm/s in Pit Pinang South. Spesific Objective : • Undertsanding The Technical Planning of Signature Hole Method. • Understanding The Analysis of Signature Waveform to determine The Optimum Intershot delay. • Understanding The Simulation of Intershot Delay in Software Shotplus. • Knowing The Actual PPV of Using the intershot delay from Field Trial. • The Research Location in Pit Pinang South and Lithology assumed Homogen. • Tie up system used with electronic detonator. • The research did not change blasting geometry and charging quantity and hence did not analyze fragmentation and cost. • Method Used in reducing ground vibration level is Signature Hole Method through conducting simulation and field trial toward intershot delay. SCOPE
  • 5. INTRODUCTION RESEARCH FLOWCHART Trial Signature Hole Project Data Processing and Analysing Split Signature Hole Wave --- Get Representative Signature Hole Wave Simulate Signature Hole Analysis -- Get PPV result from varians of intershot delay Determine Intershot Delay --- Get Optimum Intershot Delay Simulate in Software --- Get the Timing Design Field Trial of Optimum Intershot Delay Not ValidValid EvaluationRecommendation Conclusion
  • 6. S I G N AT U R E H O L E A N A LY S I S ( S H A )
  • 7. PROJECT PLANNING SIG. HOLE -1 SIG. HOLE -2 PRODUCTION HOLE
  • 8. DATA PROCESSING Blastmate III File of Vibration data Blastware 10 2. Read data Using Blastware 3. Convert to .txt file4. Analyze and process the data in Microsoft ecxcel Split signature wave, analyze with Signature hole analysis, Determine optimum Intershot Delay 1. Record blasting vibration
  • 9. SIGNATURE HOLE ANALYSIS 𝑷𝑷𝑽 = (𝑻 𝟐)+(𝑽 𝟐)+(𝑳 𝟐) Note : T = tranversal wave velocity V = vertikal wave velocity L = longitudinal wave velocity Linier superposition theory Analisis signature hole was conducted based on linier superposition theory. Peak particle velocity (PPV) can be determined by this equation: Constructive Interference Destructive Interference Wave Resultant The Sum of each Individual Wave
  • 10. SIGNATURE HOLE ANALYSIS (SHA) Simulation of Signature Hole Analysis is based on Linier Superposition Concept (The Sum Of Amplitudes of Velocity at the same time). Peak Particle Velocity (PPV) is determined by this equation: 𝑷𝑷𝑽 = (𝑻 𝟐)+(𝑽 𝟐)+(𝑳 𝟐) Information : T = Velocity Amplitude of Transversal Wave V = Velocity Amplitude of Vertical Wave L = Velocity Amplitude of Longitudinal Wave 1 -0.0159 0 -0.0159 2 -0.0159 0 -0.0159 3 -0.0159 0 -0.0159 4 0.0317 0 0.0317 5 0.0317 0 0.0317 6 0.0794 0 0.0794 7 0.0794 0 0.0794 8 0.0952 0 0.0952 9 0.0952 0 0.0952 10 0.0794 0 0.0794 11 0.0952 0 0.0952 12 0.0476 0 0.0476 13 0.0476 0 0.0476 14 0.0159 0 0.0159 15 0.0159 0 0.0159 16 0.0159 0 0.0159 17 0.0476 0 0.0476 18 0.0635 0 0.0635 19 0.0317 0 0.0317 20 0.0317 0 0.0317 21 0.0635 -0.0159 0.0476 22 0.0476 -0.0159 0.0317 23 0.0159 -0.0159 0 24 0.0317 0.0317 0.0634 25 0 0.0317 0.0317 26 -0.0159 0.0794 0.0635 27 -0.0159 0.0794 0.0635 28 0 0.0952 0.0952 29 -0.0317 0.0952 0.0635 30 -0.0476 0.0794 0.0318 31 -0.0476 0.0952 0.0476 32 -0.0635 0.0476 -0.0159 33 -0.0794 0.0476 -0.0318 34 -0.0794 0.0159 -0.0635 35 -0.0635 0.0159 -0.0476 36 -0.0635 0.0159 -0.0476 37 -0.0952 0.0476 -0.0476 38 -0.0635 0.0635 0 39 -0.0794 0.0317 -0.0477 40 -0.0635 0.0317 -0.0318 41 -0.0317 0.0635 0.0318 42 -0.0159 0.0476 0.0317 43 0.0317 0.0159 0.0476 44 0.0794 0.0317 0.1111 45 0.0794 0 0.0794 46 0.0794 -0.0159 0.0635 47 0.0952 -0.0159 0.0793 48 0 0 0 49 0 -0.0317 -0.0317 50 0 -0.0476 -0.0476 51 0 -0.0476 -0.0476 52 0 -0.0635 -0.0635 53 0 -0.0794 -0.0794 54 0 -0.0794 -0.0794 55 0 -0.0635 -0.0635 56 0 -0.0635 -0.0635 57 0 -0.0952 -0.0952 58 0 -0.0635 -0.0635 59 0 -0.0794 -0.0794 60 0 -0.0635 -0.0635 61 0 -0.0317 -0.0317 62 0 -0.0159 -0.0159 63 0 0.0317 0.0317 64 0 0.0794 0.0794 65 0 0.0794 0.0794 66 0 0.0794 0.0794 67 0 0.0952 0.0952 1 -0.222 0 -0.222 2 -0.175 0 -0.175 3 -0.159 0 -0.159 4 -0.0635 0 -0.0635 5 0 0 0 6 0.0476 0 0.0476 7 0.111 0 0.111 8 0.159 0 0.159 9 0.159 0 0.159 10 0.159 0 0.159 11 0.127 0 0.127 12 0.0952 0 0.0952 13 0.0794 0 0.0794 14 0.0794 0 0.0794 15 0.111 0 0.111 16 0.159 0 0.159 17 0.175 0 0.175 18 0.254 0 0.254 19 0.381 0 0.381 20 0.444 0 0.444 21 0.524 -0.222 0.302 22 0.603 -0.175 0.428 23 0.683 -0.159 0.524 24 0.746 -0.0635 0.6825 25 0.778 0 0.778 26 0.762 0.0476 0.8096 27 0.698 0.111 0.809 28 0.635 0.159 0.794 29 0.54 0.159 0.699 30 0.444 0.159 0.603 31 0.365 0.127 0.492 32 0.302 0.0952 0.3972 33 0.27 0.0794 0.3494 34 0.206 0.0794 0.2854 35 0.159 0.111 0.27 36 0.143 0.159 0.302 37 0.143 0.175 0.318 38 0.127 0.254 0.381 39 0.111 0.381 0.492 40 0.0794 0.444 0.5234 41 0.0317 0.524 0.5557 42 -0.0159 0.603 0.5871 43 -0.0952 0.683 0.5878 44 -0.206 0.746 0.54 45 -0.333 0.778 0.445 46 -0.444 0.762 0.318 47 -0.556 0.698 0.142 48 0 0.635 0.635 49 0 0.54 0.54 50 0 0.444 0.444 51 0 0.365 0.365 52 0 0.302 0.302 53 0 0.27 0.27 54 0 0.206 0.206 55 0 0.159 0.159 56 0 0.143 0.143 57 0 0.143 0.143 58 0 0.127 0.127 59 0 0.111 0.111 60 0 0.0794 0.0794 61 0 0.0317 0.0317 62 0 -0.0159 -0.0159 63 0 -0.0952 -0.0952 64 0 -0.206 -0.206 65 0 -0.333 -0.333 66 0 -0.444 -0.444 67 0 -0.556 -0.556 1 0.0952 0 0.0952 2 0.0794 0 0.0794 3 0.0794 0 0.0794 4 0.0476 0 0.0476 5 0.0317 0 0.0317 6 0.0317 0 0.0317 7 -0.0159 0 -0.0159 8 -0.0476 0 -0.0476 9 -0.0952 0 -0.0952 10 -0.0952 0 -0.0952 11 -0.0794 0 -0.0794 12 -0.0794 0 -0.0794 13 -0.0635 0 -0.0635 14 -0.0635 0 -0.0635 15 -0.0476 0 -0.0476 16 -0.0635 0 -0.0635 17 -0.0635 0 -0.0635 18 -0.111 0 -0.111 19 -0.159 0 -0.159 20 -0.159 0 -0.159 21 -0.175 0.0952 -0.0798 22 -0.206 0.0794 -0.1266 23 -0.206 0.0794 -0.1266 24 -0.238 0.0476 -0.1904 25 -0.19 0.0317 -0.1583 26 -0.19 0.0317 -0.1583 27 -0.143 -0.0159 -0.1589 28 -0.127 -0.0476 -0.1746 29 -0.0794 -0.0952 -0.1746 30 -0.0635 -0.0952 -0.1587 31 -0.0476 -0.0794 -0.127 32 0 -0.0794 -0.0794 33 0 -0.0635 -0.0635 34 0 -0.0635 -0.0635 35 0 -0.0476 -0.0476 36 0 -0.0635 -0.0635 37 0.0159 -0.0635 -0.0476 38 -0.0159 -0.111 -0.1269 39 -0.0159 -0.159 -0.1749 40 0 -0.159 -0.159 41 0 -0.175 -0.175 42 0.0159 -0.206 -0.1901 43 0.0317 -0.206 -0.1743 44 0.0317 -0.238 -0.2063 45 0.0317 -0.19 -0.1583 46 0.0794 -0.19 -0.1106 47 0.0635 -0.143 -0.0795 48 0 -0.127 -0.127 49 0 -0.0794 -0.0794 50 0 -0.0635 -0.0635 51 0 -0.0476 -0.0476 52 0 0 0 53 0 0 0 54 0 0 0 55 0 0 0 56 0 0 0 57 0 0.0159 0.0159 58 0 -0.0159 -0.0159 59 0 -0.0159 -0.0159 60 0 0 0 61 0 0 0 62 0 0.0159 0.0159 63 0 0.0317 0.0317 64 0 0.0317 0.0317 65 0 0.0317 0.0317 66 0 0.0794 0.0794 67 0 0.0635 0.0635 Tranversal LongitudinalVertical 0.242074 0.192827 0.178433 0.085457 0.044831 0.097852 0.137398 0.191337 0.208344 0.201614 0.177472 0.13279 0.11226 0.102905 0.121818 0.171948 0.192154 0.284375 0.414061 0.472675 0.315971 0.447456 0.539077 0.711392 0.794574 0.827371 0.826899 0.818526 0.723269 0.624344 0.510352 0.40537 0.356544 0.299195 0.278265 0.312253 0.325047 0.401578 0.524337 0.547941 0.583471 0.617923 0.614943 0.588645 0.478945 0.34262 0.181032 0.647575 0.546726 0.451037 0.371156 0.308604 0.281433 0.220772 0.171211 0.156465 0.172525 0.142878 0.137398 0.101669 0.044831 0.02754 0.105227 0.223036 0.3438 0.457979 0.567654 PPV PPV. 0.82 mm/s
  • 11. NOTE Based on Signature Hole Analysis – Simulation with several Intershot Delays (8ms, 16ms, 32ms, 40ms, 48ms, 56ms, 64ms, 72ms, 80ms, 88ms, 96ms, 104ms) 64 ms is the Optimum Intershot Delay to reduce vibration, that will result PPV 1.68 Therefore, There was a Decreasing of PPV at about 16.34% from the Simulation Using Linier Superposition Concept Example : Signature Hole Wave PPV : 2.011 SHA – Simulation Intershot Delay 64 ms PPV : 1.682 SHA – Simulation Intershot Delay 32 ms PPV : 3.145 SHA SIMULATIONUsing Microsoft Excel 2010
  • 12. DATA
  • 13. No. Tanggal Trial Signature hole Titik Ukur D (m) L (m) PC (Kg) T (m) Ket. 1 02/05/2016 PN11WK17 P1 SH-1 A 755 8.5 126 5 No 2 13/05/2016 PN21WK19 P1 SH-1 A 564 5.4 69 3.5 No 3 03/06/2016 PN20WK22 P1 SH-1 A 740 5.4 70 3.1 No SH-2 A 733 5 70 3.1 No 4 11/06/2016 PN30WK23 P2 SH-1 B 695 10.5 205 6.5 Yes SH-2 B 705 9.5 174 6.5 Yes 5 30/06/2016 PN22WK25 P1 SH-1 A 1007 4 63 2.8 No SH-2 A 1018 4.5 74 3.3 No 6 30/06/2016 PN02WK26 P1 SH-1 C 882 5.2 83 3.3 Yes SH-2 C 891 5.3 83 3.3 Yes 7 30/06/2016 PN13WK26 P1 SH-1 A 598 5.8 92 3.5 Yes SH-1 C 757 5.8 92 3.5 Yes SIGNATURE HOLE PROJECT Blasting Parameters Value Burden 7.4 m Spasi 8.5 m Hole Diameter 200 mm Blasthole Inclination Vertical Detonator Elektronik (Unitonic 600) Initiation System Box Cut - Rectangular Staggered Delay System 48 ms (Inter-hole) dan 104 ms (Inter- row)
  • 14. DATA- PN30WK23 Signature Hole 2Signature Hole 1 PPV Result – TRIAL Simulation with varians Intershot Delay Optimum intershot delay was determined at 40 ms SHA SIMULATION – PN30WK23 Signature Hole D (m) H (m) C (kg) T (m) PPV (mm/s) PPV PH (mm/s) SH-1 700 10.5 205 6.5 2.69 6.16 SH-2 9.5 9.5 6.5 2.44 PPV Decreasing: 60.7% PPV Decreasing : 66.7% SH-1 SH-2 PH
  • 15. Signature Hole D (m) H (m) C (kg) T (m) PPV (mm/s) PPV PH (mm/s) SH-1 885 5.4 83 3.3 0.815 2.06 SH-2 5.2 83 3.3 0.526 SHA SIMULATION – PN02WK26 PPV Result – TRIAL Simulation with varians Intershot Delay Signature Hole 2Signature Hole 1 Optimum intershot delay was determined at 40 ms SHA SIMULATION – PN02WK26 DATA – PN02WK26 8 ms 4.03 mm/s 16 ms 1.78 mm/s 24 ms 1.31 mm/s 32 ms 0.92 mm/s 40 ms 0.92 mm/s 48 ms 0.97 mm/s 56 ms 0.98 mm/s 64 ms 1.35 mm/s 72 ms 1.28 mm/s 80 ms 1.05 mm/s 88 ms 1.26 mm/s 96 ms 1.04 mm/s 104 ms 1.22 mm/s PPV MAX.INTERSHOT DELAY 8 ms 6.24 mm/s 16 ms 2.53 mm/s 24 ms 2.28 mm/s 32 ms 1.53 mm/s 40 ms 1.32 mm/s 48 ms 1.39 mm/s 56 ms 1.43 mm/s 64 ms 1.93 mm/s 72 ms 2.68 mm/s 80 ms 2 mm/s 88 ms 2.13 mm/s 96 ms 1.5 mm/s 104 ms 1.56 mm/s PPV MAX.INTERSHOT DELAY PPV Decreasing 55.33%PPV Decreasing : 35.9 % SH-1 SH-2 PH
  • 16. DATA – PN13WK26 Signature Hole D (m) H (m) C (kg) T (m) PPV (mm/s) PPV PH (mm/s) SH 600 5.8 92 3.5 1.13 3.3 Signature Hole D (m) H (m) C (kg) T (m) PPV (mm/s) PPV PH (mm/s) SH 757 5.8 92 3.5 0.65 2.22 Signature Hole Signature Hole 8 ms 9 mm/s 16 ms 3.44 mm/s 24 ms 2.58 mm/s 32 ms 2.05 mm/s 40 ms 1.32 mm/s 48 ms 1.34 mm/s 56 ms 1.66 mm/s 64 ms 1.66 mm/s 72 ms 2.63 mm/s 80 ms 1.66 mm/s 88 ms 1.5 mm/s 96 ms 2.12 mm/s 104 ms 1.84 mm/s PPV MAX.INTERSHOT DELAY 8 ms 6.6 mm/s 16 ms 2.26 mm/s 24 ms 1.73 mm/s 32 ms 1.43 mm/s 40 ms 1.08 mm/s 48 ms 1.26 mm/s 56 ms 1.3 mm/s 64 ms 1.11 mm/s 72 ms 1.4 mm/s 80 ms 1.1 mm/s 88 ms 0.94 mm/s 96 ms 1.12 mm/s 104 ms 1.11 mm/s PPV MAX.INTERSHOT DELAY Optimum intershot delay was determined at 40 ms PPV Decreasing : 60 % PPV Decreasing : 51.3 % SH-1 SH-1 PH PH
  • 17. Data of Signature Holes PPV actual PPV (Trial 40 ms) Decreasing PN30WK23 SH1 6.16 2.42 60.70% SH2 6.16 2.05 66.70% PN02WK26 SH3 2.06 1.32 35.90% SH4 2.06 0.92 55.30% PN13WK26 SH5 3.3 1.32 60% SH6 2.22 1.08 51.30% Average PPV decreasing 54.98 % • From SHA, The Optimum intershot delay was determined at 40 ms – (lowest PPV) • The Simulation of Using Intershot delay 40 ms showed avarage PPV decreasing at about 54.98%. RESUME
  • 18. PPV 1.52 mm/s TRIAL #1 PPV 1.83 mm/s FIELD TRIAL TRIAL #2 Intershot delay 40 ms
  • 19. Trial D (m) MIC (kg) PPV actual PPV Plan (loading sheet) From engineer Var. PPV Decreasing (%) PN10WK30 635 100 1.83 2.86 1.03 36.014 PN05WK31 590 100 1.52 2.99 1.47 49.164 RESUME OF FIELD TRIAL Average PPV Decreasing 42.58 % According to field trials using intershot delay 40 ms, they resulted average PPV decreasing at about 42.58%
  • 21. SUMMARY Based on previous result mentioned, hence there can be summarized that: 1. Ground vibration control using signature hole analysis by applicating the optimum intershot delay can be conducted trough several steps, among such steps are: • Planning made was focused at 1-2 holes blast for the signature holes from blasting plan made by engineer. Applicate delay timing about 3 second between signature hole and production holes. • Vibration recording uses Blastmate III. Data that can be read in Blastware 10 need to be converted to .txt file • Wave splitting between Signature hole and production hole and data pocessing can be done through Microsoft excel to determine the optimum intershot delay. 2. Simulation of Signature Hole Analysis (SHA) using Microsoft excelnachieved the optimum intershot delay at 40 ms with average PPV decreasing at about 54.98 %. 3. Applicating Intershot delay 40 ms in field trials achieved average PPV decreasing at about 42.58.
  • 22. REFERENCES Bernard, T. (2010). The Truth About Signature Hole Method. Nice, France: Thierry Bernard Technologie. . Cunningham C. V. B. (2000). The effect of timing precision on control of blasting effects. Proceedings 1st EFEE Conference on Explosives and Blasting Technique. Munich. pp. 123–127. Gokhale B.V. (2009). Rotary drilling and blasting in large surface mines. Leiden, Netherland: CRC Press/Balkema. Hustrulid, W. (1999). Blasting Principles For Open Pit Mining Volume 1. Rotterdam: A.A. Balkema. Jimeno, C.L. dan Jimeno, E.L. (1995). Drilling and Blasting of Rocks. Rotterdam: A.A. Balkema. Koesnaryo ,S. (2001). Pemboran Untuk Penyediaan Lubang Ledak. Yogyakarta: Teknik Pertambangan, UPN ‘Veteran’. Konya, C.J., and Walter, E.J. (1990). Surface Blast Design. New Jersey, U.S.A: Prentice Hall. Englewood Cliffs. Kusumaatmaja, S. (1996). Kepmen LH No.49 Tahun 1996: Baku Tingkat Getaran. Jakarta : MENLH. Richards, A. B., Evans, R., and Moore A. J. (1994). Blast Vibration Control and Assessment Techniques. Proceedings of the Fourth Large Open Pit Mining Conference, Australian Institute of Mining & Metallurgy. Perth, Western Australia. SNI. (2010). SNI 7571:Baku Tingkat Getaran Peledakan pada Kegiatan Tambang Terbuka Terhadap Bangunan. Bandung: BSN. Turnbull, B. (2008). Just for the Record: Signature Hole Analysis. New York, USA: Instantel. Yang, R., Scovira, D. S., & Patterson, N. J. (2009). An integrated approach of signature hole vibration monitoring and modeling for quarry vibration control. International symposium on Rock fragmentation by blasting, London. pp. 597- 605.
  • 23. THANK YOU Muhamad Rizky 03121402003 Universitas Sriwijaya, Indonesia muhamad.rizky6694@gmail.com