Genpact phase-2 work progress photo report-2.pptx

  1. 1. Genpact Phase-2 Cherryhill Pending works Photo Report Date : 3-May-19
  2. 2. CBRE | Page 2 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL ODC 4 floor sanding & primer works pending.
  3. 3. CBRE | Page 3 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL ODC 4 floor sanding & primer works pending.
  4. 4. CBRE | Page 4 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL ODC 4 floor sanding & primer works pending Putty works still under progress.
  5. 5. CBRE | Page 5 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL Meeting room putty works to be commenced.
  6. 6. CBRE | Page 6 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL • Gypsum Band finishing works pending. • putty primer works are pending.
  7. 7. CBRE | Page 7 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL Meeting room 5, putty works not even started.
  8. 8. CBRE | Page 8 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL Meeting room 2 & 3 putty works to be commenced.
  9. 9. CBRE | Page 9 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL VC room gypsum band works are pending which delay the grid ceiling works commencement and putty, primer works yet to be commenced.
  10. 10. CBRE | Page 10 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL Training room putty and primer works are pending.
  11. 11. CBRE | Page 11 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL Training room-2 putty and primer works are pending.
  12. 12. CBRE | Page 12 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL Meeting room-1 putty and primer works are pending.
  13. 13. CBRE | Page 13 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL Washroom wall Dado works completion still pending.
  14. 14. CBRE | Page 14 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL Washroom wall Dado works completion still pending.
  15. 15. CBRE | Page 15 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL Lift lobby tiling works not yet started.
  16. 16. CBRE | Page 16 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL Lift lobby tiling works not yet started.
  17. 17. CBRE | Page 17 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL Note : Above are the pending activities which should be closed on high priority, which are directly impacting project delivery timelines and other works.
  18. 18. CBRE | Page 18 PROPRIETARY INFORMATION OF CBRE — PRIVILEGED & CONFIDENTIAL THANK YOU

×