9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
Project te zlatibor 2x 500 kw (1)
1. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
THE PROJECT BIOMASS POWER PLANT 2 x 500 KW ELECTRICAL CAPACITY
ON THE LOCATION ZLATIBOR R.SRBIJA
February 2015
Full title of the Projekt:
CHP Power Plant 2x 500 KW of electrical power or
4 MW thermal energy from biomass
Zlatibor
Republika Srbija
Acronym of the proposed action:
CHP Zlatibor
from biomass
Co-ordinator:
(Organisation, Address)
EKO POSLOVI INŽENJERING D.O.O. Beograd
2. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
The Project Biomass Power Plant
2 x 500 KW Electrical Capacity
on the location Zlatibor R.Srbija
Republic of Serbia
TE-TO Zlatibor
The Project has:
1. Basic characteristics of Project
2. Description of location
3. Biomass gasification power system
4. 2 x 500 KW Syngas Generator Set
5. Finasijska Analiza Projekta Energane
6. Detaljni Katastarski Plan
7. Sve Dozvole I Saglasnosti I Mišljenja
8. Detaljna Finasijska Analiza Projekta
3. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
1. Basic characteristics of Project
The intention of the project is to build a cogeneration plant for the production of electricity and heat using the new technology
of gasification of wood biomass forestry activities such as pieces of wood, leaves, branches originating from deciduous and
coniferous trees.
The total installed capacity of the plant will be 9.6 MW of electricity and 10.8 MW of thermal energy (which is the first stage is
spent in the dryer), and its implementation will be carried out in three stages
2.Description of location
Figure 1: Location of the location in relation to the community center
4. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
Figure 2: Immediately surrounding the subject location
3.Biomass gasification power system
As you may know, the biomass gasification power generation system consists three parts: gasification system, gas
purification system, gas generator set. We produce the complete system.
For the gasifier we have fixed bed gasifier(downdraft and updraft) or circulating fluidized bed gasifier.
For the gas purification system, we have wet purification system and dry purification system.
For the gas generator set, we are also the one of the biggest low-speed and medium-speed engine company in
China which has more than 60 years’ history.
For gasification system(gasifier and purification system), we have 2 x 1000KW.
For generator set, we have 2 x 1000KW for low heat value gas from biomass gasifier.
5. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
Raw materials
requirements are as
follows S/N
Raw material* Feedstock input
(KG) per 1 kwh
1 Saw dust 1.3~1.5 kg/kW h
2 woodchip 1.2~1.5 kg/kW h
3 Coconut fiber dust 1.5~2.0 kg/kW h
4 straw 1.6~1.8 kg/kW h
5 Palm bunch 1.6~1.9 kg/kW h
6 Rice husk 1.6~1.8 kg/kW h
7 Crop stalk 1.6~1.8 kg/kW h
Gasifitacion power system in our factory
6. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
4. 2 x 500 KW Syngas Generator Set
1.Syngas Engine: 16V300 series,16 cylinders, V build,600rpm,Engine
manufacturer cooperate with German MAN;
2.Engine Ignition System: Altronic, Made in USA;
3.Speed Governor: Heinzmann, Made in Germany
7. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
5.Finasijska Analiza Projekta Energane
FINANSIJSKA ANALIZA PROJEKTA ENERGANE
SNAGE 2 x 500 KW EL ENERGIJE
NA LOKACIJI ZLATIBOR R.SRBIJA
FinasijskI parametri
Kredit € 1.474.000
Kredit u % 74%
Učešce € 520.000
Novčani ulog € 80.000
Nenovčani ulog -Lokacija 1ha (ili veca) € 220.000
Nenovčani ulog-Know-How, Tehnička Doc i Sve Dozvole i Saglasnosti € 220.000
Učešce u % 26%
Dužina trajanja projekta 12 godina
Trajanje analitičkog modela 1 godina
Ukupne obaveze zbirno
Grejs period 1 godina
Period povrata Kredita 12 godina
Odnos pozitivnog povrata novčanog toka- Bruto Margina 59%
Ostvarena kamata (godišnje) 3%
Ostvarena kamata (ukupno) € 287.430
Margine projekta
Bruto margina (nakon povrata investicije)% 59,44%
Neto margina (nakon povrata investicije)% 46,12%
Bruto margina (nakon povrata investicije) € 7.861.844
Neto margina (nakon povrata investicije) € 6.100.414
Parametri Projekata - Zlatibor
na drvenu biomasu snage 1MW električne energije
Veličina Projekta u MW (VPMW) 1,00
Totalni Broj Radnih Sati po Godini (THG) 7.500
Prodaja Električne Energije po MW (PEEPMW) € 136,00
Trajanje Realizacije Projekta po Godini (TPG) 1
PRIHOD
Prodaja Električne Energije po Godini (PEEPG) = PPEEPMW * THG *VMW*TPG € 1.020.000
8. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
U prihod nisu uračunati benefiti od prodaje nus proizvoda koji su :
Aktivni ugalj u količini od 15% od 10000t biomase, po ceni od 80 €/t, 1500t*80€=120000€
Mazu u količini od 3% od 10000t biomase, po ceni od 400€/t, 300t*400€=120000€
U periodu od 20 dana dostavicemo ugovore o dugoročno otkupu nus proizvoda € 240.000
TROŠKOVI
Indirektni Troškovi
Kredit u % (KF%) € 1.474.000
Godišnji Interes kredita u % (GIKF%) 3%
Vreme Trajanja Kreditnog Finasiranja u Godinama(VTKFG) 12
Prosečna Godišnja Otplata Kredita Finasiranja (PGOKF) € 158.120
Operativni Troškovi ukupno za 12 god rada € 7.125.586
Operativni Troškovi -prosecni/ na godisnjem nivou € 593.799
Materijal
Biomasa 9000t x 30€ € 270.000
Projektom su predvidjene tri opcije snabdevanja biomasom:
Prva opcija :od JP Srbija Šume(dostavljamo Pismo o mogucnostima JP)
Druga opcija: od privatnih dobavljača
Treca opcija: sopsveni zasad brzorasuceg drveta na 300ha
Energija i gorivo € 30.000
Vehicle registration and fuel service € 30.000
Troškovi opreme i kancelarije € 55.200
Pravni poslovi € 3.600
Računovodstvo € 6.000
Servis i održavanje gasnog motora € 18.000
Servis i održavanje opreme € 12.000
Osiguranje € 12.000
Troškovi kancelarije € 3.600
Zakup lokacije € 0
Unapredjenje Tehnologije € 0
ZARADA
Ukupna Zarada
Godišnja Ukupna Zarada nakon TOT (GUZ) = PEEPG-TOT € 426.201
Neto Zarada
Godišnja Neto Zarada posle(GNZ) TOT, & GT = TOT - GT € 404.891
Taxes
Godišnja Taksa (porez na dobit) u % (GT%) 5%
Godišnja Taksa (GT) = (GUZ - GOFK) * GT% € 21.310
9. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
Grafik novčanog toka
Grafik tačke preloma
€ 1.000.000
€ 0
€ 1.000.000
€ 2.000.000
€ 3.000.000
€ 4.000.000
€ 5.000.000
AxisTitle
Cumulative Cashflow
Income
Direct Costs
Indirect Costs
€ 0
€ 2.000.000
€ 4.000.000
€ 6.000.000
€ 8.000.000
€ 10.000.000
€ 12.000.000
1 2 3 4 5 6 7 8 9 10 11 12 II III IV V VI VII VIII IX X XI XII
Revenue
Cost
10. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
6. Detaljni Katastarski Plan
11. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
12. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
13. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
14. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
15. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
7. Sve Dozvole I Saglasnosti I Mišljenja
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
8. Detaljna Finasijska Analiza Projekta
46. FINANSIJSKA ANALIZA PROJEKTA ENERGANE
SNAGE 2 x 500 KW EL ENERGIJE
NA LOKACIJI ZLATIBOR R.SRBIJA
Kredit € 1,474,000
Kredit u % 74%
Učešce € 520,000
Novčani ulog € 80,000
Nenovčani ulog ‐Lokacija 1ha (ili veca € 220,000
Nenovčani ulog‐Know‐How, Tehnička Doc i Sve Dozvole i Saglasnost € 220,000
Učešce u % 26%
Dužina trajanja projekta 12 godina
Trajanje analitičkog modela 1 godina
Grejs period 1 godina
Period povrata Kredita 12 godina
Odnos pozitivnog povrata novčanog toka‐ Bruto Margina 59%
Ostvarena kamata (godišnje) 3%
Ostvarena kamata (ukupno) € 287,430
Bruto margina (nakon povrata investicije)% 59.44%
Neto margina (nakon povrata investicije)% 46.12%
Bruto margina (nakon povrata investicije) € 7,861,844
Neto margina (nakon povrata investicije) € 6,100,414
i
Veličina Projekta u MW (VPMW) 1.00
Totalni Broj Radnih Sati po Godini (THG) 7,500
Prodaja Električne Energije po MW (PEEPMW) € 136.00
Trajanje Realizacije Projekta po Godini (TPG) 1
Prodaja Električne Energije po Godini (PEEPG) = PPEEPMW * THG *VMW*TPG € 1,020,000
U prihod nisu uračunati benefiti od prodaje nus proizvoda koji su :
Aktivni ugalj u količini od 15% od 10000t biomase, po ceni od 80 €/t, 1500t*80€=120000€
Mazu u količini od 3% od 10000t biomase, po ceni od 400€/t, 300t*400€=120000€
U periodu od 20 dana dostavicemo ugovore o dugoročno otkupu nus proizvoda € 240,000
Kredit u % (KF%) € 1,474,000
Godišnji Interes kredita u % (GIKF%) 3%
Vreme Trajanja Kreditnog Finasiranja u Godinama(VTKFG) 12
Prosečna Godišnja Otplata Kredita Finasiranja (PGOKF) € 158,120
Operativni Troškovi ukupno za 12 god rada € 7,125,586
Operativni Troškovi ‐prosecni/ na godisnjem nivou € 593,799
Materijal
Biomasa 9000t x 30€ € 270,000
Projektom su predvidjene tri opcije snabdevanja biomasom:
Prva opcija :od JP Srbija Šume(dostavljamo Pismo o mogucnostima JP)
Druga opcija: od privatnih dobavljača (u prilogu su Ugovori za 3‐5 godina snabdevanja)
Treca opcija: sopsveni zasad brzorasuceg drveta na 300ha (godisnji prinos veci od 9000t)
Energija i gorivo € 30,000
Vehicle registration and fuel service € 30,000
Troškovi opreme i kancelarije € 55,200
Pravni poslovi € 3,600
Računovodstvo € 6,000
Servis i održavanje gasnog motora € 18,000
Servis i održavanje opreme € 12,000
Osiguranje € 12,000
Troškovi kancelarije € 3,600
Zakup lokacije € 0
Unapredjenje Tehnologije € 0
Godišnja Ukupna Zarada nakon TOT (GUZ) = PEEPG‐TOT € 426,201
Godišnja Neto Zarada posle(GNZ) TOT, & GT = TOT ‐ GT € 404,891
Godišnja Taksa (porez na dobit) u % (GT%) 5%
Godišnja Taksa (GT) = (GUZ ‐ GOFK) * GT% € 21,310
Neto Zarada
PRIHOD
TROŠKOVI
Indirektni Troškovi
Taxes
ZARADA
FinasijskI parametri
Ukupne obaveze zbirno
Margine projekta
Parametri Projekata ‐ Zlatibor
na drvenu biomasu snage 1MW električne energije
Ukupna Zarada
51. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12.
Income Year Year Year Year Year Year Year Year Year Year Year Year Year
Income Type Per 1MW Per months Per year Total
Snaga energane 1
MW El. Energ. € 136 € 85,000 € 1,020,000 € 12,864,000 € 1,644,000 € 1,020,000 € 1,020,000 € 1,020,000 € 1,020,000 € 1,020,000 € 1,020,000 € 1,020,000 € 1,020,000 € 1,020,000 € 1,020,000 € 1,020,000
U prihod nisu uračunati benefiti od prodaje nus proizvoda koji su :
Aktivni ugalj u količini od 15% od 10000t biomase, po ceni od 120 €/t, 1500t*80€=120000€
Mazu u količini od 3% od 10000t biomase, po ceni od 400€/t, 300t*400€=120000€
56. The Project Biomass Power Plant
on the location Zlatibor R.Srbija
25.02.2015.
EKOP POSLOVI INŽENJERING D.O.O.
Milutina Milankovica 7V
1070 Novi Beograd
Grafik novčanog toka
Grafik tačke preloma
€ 1.000.000
€ 0
€ 1.000.000
€ 2.000.000
€ 3.000.000
€ 4.000.000
€ 5.000.000
AxisTitle
Cumulative Cashflow
Income
Direct Costs
Indirect Costs
€ 0
€ 2.000.000
€ 4.000.000
€ 6.000.000
€ 8.000.000
€ 10.000.000
€ 12.000.000
1 2 3 4 5 6 7 8 9 10 11 12 II III IV V VI VII VIII IX X XI XII
Revenue
Cost