SlideShare a Scribd company logo
1 of 54
UNIT-IVUNIT-IV
Economic Operation of PowerEconomic Operation of Power
SystemsSystems
ā€¢ Md Irshad Ahmad
ā€¢ Irshad.ahmad@jit.edu.in
ā€¢ Electrical Engineering Department
ā€¢ Subject: : POWER STATION PRACTICE
ā€¢ (NEE /NENā€“702)
ContentsContents
ā€¢ UNIT-IV:Economic Operation of Power
Systems:
ā€¢ Characteristics of steam and hydro-
plants,Constraints in operation
ā€¢ Economic load scheduling of thermal plants
Neglecting and considering transmission
Losses,
ā€¢ Penalty factor, loss coefficients, Incremental
transmission loss. Hydrothermal
Scheduling.
Retail Electricity PricesRetail Electricity Prices
ā€¢ There are many fixed and variable costs
associated with power systems, which
ultimately contribute to determining retail
electricity prices.
ā€¢ The major variable operating cost is
associated with generation, primarily due
to fuel costs:
ā€“ Roughly 30% to 50% of retail costs.
ā€¢ Retail prices also reflect the capital costs
of building the generation, transmission,
and distribution system as well as other 33
Power System EconomicPower System Economic
OperationOperation
ā€¢ Different generation technologies vary in
the:
ā€“ capital costs necessary to build the generator
ā€“ fuel costs to actually produce electric power
ā€¢ For example:
ā€“ nuclear and hydro have high capital costs and
low operating costs.
ā€“ Natural gas generators have low capital costs,
and (with gas available from fracking)
moderate operating costs. 44
Economic Dispatch:Economic Dispatch:
FormulationFormulation
ļ¬The goal of economic dispatch is to
determine the generation dispatch that
minimizes the instantaneous operating
cost, subject to the constraint that total
generation = total load + losses
T
1
1
Minimize C ( )
Such that
m
i Gi
i
m
Gi D Losses
i
C P
P P P
=
=
= +
āˆ‘
āˆ‘
@
Initially we'll
ignore generator
limits and the
losses
55
Unconstrained MinimizationUnconstrained Minimization
ļ¬This is a minimization problem with a
single equality constraint
ļ¬For an unconstrained minimization a
necessary (but not sufficient) condition
for a minimum is the gradient of the
function must be zero,
ļ¬The gradient generalizes the first
derivative for multi-variable problems:
1 2
( ) ( ) ( )
( ) , , ,
nx x x
ļ£® ļ£¹āˆ‚ āˆ‚ āˆ‚
āˆ‡ ļ£Æ ļ£ŗāˆ‚ āˆ‚ āˆ‚ļ£° ļ£»
f x f x f x
f x K@
( )āˆ‡ =f x 0
66
Minimization with EqualityMinimization with Equality
ConstraintConstraintļ¬When the minimization is constrained with
an equality constraint we can solve the
problem using the method of Lagrange
Multipliers
ļ¬Key idea is to represent a constrained
minimization problem as an unconstrained
problem.That is, for the general problem
minimize ( ) s.t. ( )
We define the Lagrangian L( , ) ( ) ( )
Then a necessary condition for a minimum is the
L ( , ) 0 and L ( , ) 0
T
=
= +
āˆ‡ = āˆ‡ =xĪ»
f x g x 0
xĪ» f x Ī» g x
xĪ» x Ī» 77
Economic Dispatch LagrangianEconomic Dispatch Lagrangian
G
1 1
G
For the economic dispatch we have a minimization
constrained with a single equality constraint
L( , ) ( ) ( ) (no losses)
The necessary conditions for a minimum are
L( , )
m m
i Gi D Gi
i i
Gi
C P P P
dC
P
Ī» Ī»
Ī»
= =
= + āˆ’
āˆ‚
=
āˆ‚
āˆ‘ āˆ‘P
P
1
( )
0 (for 1 to )
0
i Gi
Gi
m
D Gi
i
P
i m
dP
P P
Ī»
=
āˆ’ = =
āˆ’ =āˆ‘
88
Economic Dispatch ExampleEconomic Dispatch Example
1 2
2
1 1 1 1
2
2 2 2 2
1 1
1
What is economic dispatch for a two generator
system 500 MW and
( ) 1000 20 0.01 $/h
( ) 400 15 0.03 $/h
Using the Lagrange multiplier method we know:
( )
20 0.0
D G G
G G G
G G G
G
G
P P P
C P P P
C P P P
dC P
dP
Ī»
= + =
= + +
= + +
āˆ’ = + 1
2 2
2
2
1 2
2 0
( )
15 0.06 0
500 0
G
G
G
G
G G
P
dC P
P
dP
P P
Ī»
Ī» Ī»
āˆ’ =
āˆ’ = + āˆ’ =
āˆ’ āˆ’ =
99
Economic Dispatch Example,Economic Dispatch Example,
contā€™dcontā€™d
1
2
1 2
1
2
1
2
We therefore need to solve three linear equations
20 0.02 0
15 0.06 0
500 0
0.02 0 1 20
0 0.06 1 15
1 1 0 500
312.5 MW
187.5 MW
26.2 $/MW
G
G
G G
G
G
G
G
P
P
P P
P
P
P
P
Ī»
Ī»
Ī»
Ī»
+ āˆ’ =
+ āˆ’ =
āˆ’ āˆ’ =
āˆ’ āˆ’ļ£® ļ£¹ļ£® ļ£¹ ļ£® ļ£¹
ļ£Æ ļ£ŗļ£Æ ļ£ŗ ļ£Æ ļ£ŗāˆ’ = āˆ’
ļ£Æ ļ£ŗļ£Æ ļ£ŗ ļ£Æ ļ£ŗ
āˆ’ āˆ’ āˆ’ļ£Æ ļ£ŗļ£Æ ļ£ŗ ļ£Æ ļ£ŗļ£° ļ£»ļ£° ļ£» ļ£° ļ£»
ļ£® ļ£¹
ļ£Æ ļ£ŗ =
ļ£Æ ļ£ŗ
ļ£Æ ļ£ŗļ£° ļ£» h
ļ£® ļ£¹
ļ£Æ ļ£ŗ
ļ£Æ ļ£ŗ
ļ£Æ ļ£ŗļ£° ļ£» 1010
Economic dispatch example,Economic dispatch example,
contā€™dcontā€™d
ā€¢ At the solution, both generators have the same
marginal (or incremental) cost, and this common
marginal cost is equal to Ī».
ā€¢ Intuition behind solution:
ā€“ If marginal costs of generators were different, then by
decreasing production at higher marginal cost generator,
and increasing production at lower marginal cost
generator we could lower overall costs.
ā€“ Generalizes to any number of generators.
ā€¢ If demand changes, then change in total costs can
be estimated from Ī».
1111
Economic dispatch example,Economic dispatch example,
contā€™dcontā€™d
ā€¢ Another way to solve the equations is to:
ā€“ Rearrange the first two equations to solve for
PG1 and PG2 in terms of Ī»,
ā€“ Plug into third equation and solve for Ī»,
ā€“ Use the solved value of Ī» to evaluate PG1 and
PG2.
ā€¢ This works even when relationship
between generation levels and Ī» is more
complicated:
ā€“ Equations are more complicated than linear 1212
Lambda-Iteration SolutionLambda-Iteration Solution
MethodMethod
ā€¢ Discussion on previous page leads to
ā€œlambda-iterationā€ method:
ā€“ this method requires a unique mapping from a
value of lambda (marginal cost) to each
generatorā€™s MW output:
ā€“ for any choice of lambda (common marginal
cost), the generators collectively produce a total
MW output,
ā€“ the method then starts with values of lambda
below and above the optimal value
(corresponding to too little and too much total
output), and then iteratively brackets the optimalā€¢ 1313
( ).Gi
P Ī»
Lambda-Iteration AlgorithmLambda-Iteration Algorithm
L H
1 1
H L
M H L
H M
1
L M
Pick and such that
( ) 0 ( ) 0
While Do
( )/2
If ( ) 0 Then
Else
End While
m m
L H
Gi D Gi D
i i
m
M
Gi D
i
P P P P
P P
Ī» Ī»
Ī» Ī»
Ī» Ī» Īµ
Ī» Ī» Ī»
Ī» Ī» Ī»
Ī» Ī»
= =
=
āˆ’ < āˆ’ >
āˆ’ >
= +
āˆ’ > =
=
āˆ‘ āˆ‘
āˆ‘
1414
Lambda-Iteration: GraphicalLambda-Iteration: Graphical
ViewView
In the graph shown below for each value of lambda
there is a unique PGi for each generator. This
relationship is the PGi(Ī») function.
1515
Lambda-Iteration ExampleLambda-Iteration Example
1 1 1
2 2 2
3 3 3
1 2 3
Consider a three generator system with
( ) 15 0.02 $/MWh
( ) 20 0.01 $/MWh
( ) 18 0.025 $/MWh
and with constraint 1000MW
Rewriting generation as a function of , (
G G
G G
G G
G G G
Gi
IC P P
IC P P
IC P P
P P P
P
Ī»
Ī»
Ī»
Ī»
= + =
= + =
= + =
+ + =
G1 G2
G3
),
we have
15 20
P ( ) P ( )
0.02 0.01
18
P ( )
0.025
Ī»
Ī» Ī»
Ī» Ī»
Ī»
Ī»
āˆ’ āˆ’
= =
āˆ’
= 1616
Lambda-Iteration Example,Lambda-Iteration Example,
contā€™dcontā€™dm
Gi
i=1
m
Gi
i=1
1
H
1
Pick so P ( ) 1000 0 and
P ( ) 1000 0
Try 20 then (20) 1000
15 20 18
1000 670 MW
0.02 0.01 0.025
Try 30 then (30) 1000 1230 MW
L L
H
m
L
Gi
i
m
Gi
i
P
P
Ī» Ī»
Ī»
Ī»
Ī» Ī» Ī»
Ī»
=
=
āˆ’ <
āˆ’ >
= āˆ’ =
āˆ’ āˆ’ āˆ’
+ + āˆ’ = āˆ’
= āˆ’ =
āˆ‘
āˆ‘
āˆ‘
āˆ‘
1717
Lambda-Iteration Example,Lambda-Iteration Example,
contā€™dcontā€™d
1
1
Pick convergence tolerance 0.05 $/MWh
Then iterate since 0.05
( )/ 2 25
Then since (25) 1000 280 we set 25
Since 25 20 0.05
(25 20)/ 2 22.5
(22.5) 1000 195 we set 2
H L
M H L
m
H
Gi
i
M
m
L
Gi
i
P
P
Īµ
Ī» Ī»
Ī» Ī» Ī»
Ī»
Ī»
Ī»
=
=
=
āˆ’ >
= + =
āˆ’ = =
āˆ’ >
= + =
āˆ’ = āˆ’ =
āˆ‘
āˆ‘ 2.5
1818
Lambda-Iteration Example,Lambda-Iteration Example,
contā€™dcontā€™d
H
*
*
1
2
3
Continue iterating until 0.05
The solution value of , , is 23.53 $/MWh
Once is known we can calculate the
23.53 15
(23.5) 426 MW
0.02
23.53 20
(23.5) 353 MW
0.01
23.53 18
(23.5)
0.025
L
Gi
G
G
G
P
P
P
P
Ī» Ī»
Ī» Ī»
Ī»
āˆ’ <
āˆ’
= =
āˆ’
= =
āˆ’
= 221 MW=
1919
Thirty Bus ED ExampleThirty Bus ED Example
Case is economically dispatched (without considering
the incremental impact of the system losses).
2020
Generator MW LimitsGenerator MW Limits
ļ¬Generators have limits on the minimum
and maximum amount of power they can
produce
ļ¬Typically the minimum limit is not zero.
ļ¬Because of varying system economics
usually many generators in a system are
operated at their maximum MW limits:
ļ¬Baseload generators are at their maximum
limits except during the off-peak.
2121
Lambda-Iteration with GenLambda-Iteration with Gen
LimitsLimits
,max
,max
In the lambda-iteration method the limits are taken
into account when calculating ( ) :
if calculated production for
then set ( )
if calculated production for
Gi
Gi Gi
Gi Gi
P
P P
P P
Ī»
Ī»
>
=
,min
,minthen set ( )
Gi Gi
Gi Gi
P P
P PĪ»
<
=
2222
Lambda-Iteration Gen LimitLambda-Iteration Gen Limit
ExampleExample
G1 G2
G3
1 2 3
1
In the previous three generator example assume
the same cost characteristics but also with limits
0 P 300 MW 100 P 500 MW
200 P 600 MW
With limits we get:
(20) 1000 (20) (20) (20) 10
m
Gi G G G
i
P P P P
=
ā‰¤ ā‰¤ ā‰¤ ā‰¤
ā‰¤ ā‰¤
āˆ’ = + + āˆ’āˆ‘
1
00
250 100 200 1000
450 MW (compared to 670MW)
(30) 1000 300 500 480 1000 280 MW
m
Gi
i
P
=
= + + āˆ’
= āˆ’ āˆ’
āˆ’ = + + āˆ’ =āˆ‘
2323
Lambda-Iteration LimitLambda-Iteration Limit
Example,contā€™dExample,contā€™dAgain we continue iterating until the convergence
condition is satisfied.
With limits the final solution of , is 24.43 $/MWh
(compared to 23.53 $/MWh without limits).
Maximum limits will always caus
Ī»
1
2
3
e to either increase
or remain the same.
Final solution is:
(24.43) 300 MW (at maximum limit)
(24.43) 443 MW
(24.43) 257 MW
G
G
G
P
P
P
Ī»
=
=
=
2424
Back of Envelope ValuesBack of Envelope Values
ļ¬$/MWhr = fuelcost * heatrate + variable O&M
ļ¬Typical incremental costs can be roughly
approximated:
ā€“ Typical heatrate for a coal plant is 10, modern
combustion turbine is 10, combined cycle plant
is 6 to 8, older combustion turbine 15.
ā€“ Fuel costs ($/MBtu) are quite variable, with
current values around 2 for coal, 3 to 5 for
natural gas, 0.5 for nuclear, probably 10 for fuel
oil.
ā€“ Hydro costs tend to be quite low, but are fuel
(water) constrained 2525
Inclusion of TransmissionInclusion of Transmission
LossesLosses
ļ¬The losses on the transmission system
are a function of the generation dispatch.
ļ¬In general, using generators closer to the
load results in lower losses
ļ¬This impact on losses should be
included when doing the economic
dispatch
ļ¬Losses can be included by slightly
rewriting the Lagrangian to include
G
1 1
L( , ) ( ) ( )
m m
i Gi D L G Gi
i i
C P P P P PĪ» Ī»
= =
ļ£« ļ£¶
= + + āˆ’ļ£¬ Ć·
ļ£­ ļ£ø
āˆ‘ āˆ‘P
2626
Impact of Transmission LossesImpact of Transmission Losses
G
1 1
G
The inclusion of losses then impacts the necessary
conditions for an optimal economic dispatch:
L( , ) ( ) ( ) .
The necessary conditions for a minimum are now:
L( , )
m m
i Gi D L G Gi
i i
C P P P P PĪ» Ī»
Ī»
= =
ļ£« ļ£¶
= + + āˆ’ļ£¬ Ć·
ļ£­ ļ£ø
āˆ‚
āˆ‚
āˆ‘ āˆ‘P
P
1
( ) ( )
1 0
( ) 0
i Gi L G
Gi Gi Gi
m
D L G Gi
i
dC P P P
P dP P
P P P P
Ī»
=
ļ£« ļ£¶āˆ‚
= āˆ’ āˆ’ =ļ£¬ Ć·āˆ‚ļ£­ ļ£ø
+ āˆ’ =āˆ‘
2727
Impact of Transmission LossesImpact of Transmission Losses
th
( ) ( )
Solving for , we get: 1 0
( )1
( )
1
Define the penalty factor for the generator
(don't confuse with Lagrangian L!!!)
1
( )
1
i Gi L G
Gi Gi
i Gi
GiL G
Gi
i
i
L G
Gi
dC P P P
dP P
dC P
dPP P
P
L i
L
P P
P
Ī» Ī»
Ī»
ļ£« ļ£¶āˆ‚
āˆ’ āˆ’ =ļ£¬ Ć·āˆ‚ļ£­ ļ£ø
=
ļ£« ļ£¶āˆ‚
āˆ’ļ£¬ Ć·āˆ‚ļ£­ ļ£ø
=
ļ£« āˆ‚
āˆ’ļ£¬ āˆ‚ļ£­
ļ£¶
Ć·
ļ£ø
The penalty factor
at the slack bus is
always unity!
2828
Impact of Transmission LossesImpact of Transmission Losses
1 1 1 2 2 2
The condition for optimal dispatch with losses is then
( ) ( ) ( )
1
. So, if increasing increases
( )
1
( )
the losses then 0 1.0
This makes generator
G G m m Gm
i Gi
L G
Gi
L G
i
Gi
L IC P L IC P L IC P
L P
P P
P
P P
L
P
Ī»= = =
=
ļ£« ļ£¶āˆ‚
āˆ’ļ£¬ Ć·āˆ‚ļ£­ ļ£ø
āˆ‚
> ā‡’ >
āˆ‚
appear to be more expensive
(i.e., it is penalized). Likewise 1.0 makes a generator
appear less expensive.
i
i
L <
2929
Calculation of Penalty FactorsCalculation of Penalty Factors
Unfortunately, the analytic calculation of is
somewhat involved. The problem is a small change
in the generation at impacts the flows and hence
the losses throughout the entire system. However,
i
Gi
L
P
using a power flow you can approximate this function
by making a small change to and then seeing how
the losses change:
( ) ( ) 1
( )
1
Gi
L G L G
i
L GGi Gi
Gi
P
P P P P
L
P PP P
P
āˆ‚ āˆ†
ā‰ˆ ā‰ˆ
āˆ†āˆ‚ āˆ† āˆ’
āˆ†
3030
Two Bus Penalty FactorTwo Bus Penalty Factor
ExampleExample
2 2
2 2
( ) ( ) 0.37
0.0387 0.037
10
0.9627 0.9643
L G L G
G G
P P P P MW
P P MW
L L
āˆ‚ āˆ† āˆ’
= āˆ’ = = āˆ’
āˆ‚ āˆ†
= ā‰ˆ
3131
Thirty Bus ED ExampleThirty Bus ED Example
Now consider losses.
Because of the penalty factors the generator incremental
costs are no longer identical.
3232
Area Supply CurveArea Supply Curve
0 100 200 300 400
Total AreaGeneration(MW)
0.00
2.50
5.00
7.50
10.00
The area supply curve shows the cost to produce the
next MW of electricity, assuming area is economically
dispatched
Supply
curve for
thirty bus
system
3333
Economic Dispatch - SummaryEconomic Dispatch - Summary
ļ¬Economic dispatch determines the best way to
minimize the current generator operating costs.
ļ¬The lambda-iteration method is a good approach
for solving the economic dispatch problem:
ā€“ generator limits are easily handled,
ā€“ penalty factors are used to consider the impact of
losses.
ļ¬Economic dispatch is not concerned with
determining which units to turn on/off (this is the
unit commitment problem).
ļ¬Basic form of economic dispatch ignores the
transmission system limitations.
3434
Security Constrained EDSecurity Constrained ED
or Optimal Power Flowor Optimal Power Flow
ļ¬Transmission constraints often limit ability to
use lower cost power.
ļ¬Such limits require deviations from what
would otherwise be minimum cost dispatch
in order to maintain system ā€œsecurity.ā€
ļ¬Need to solve or approximate power flow in
order to consider transmission constraints.
3535
Security Constrained EDSecurity Constrained ED
or Optimal Power Flowor Optimal Power Flow
ļ¬The goal of a security constrained ED or
optimal power flow (OPF) is to determine
the ā€œbestā€ way to instantaneously operate
a power system, considering transmission
limits.
ļ¬Usually ā€œbestā€ = minimizing operating
cost, while keeping flows on transmission
below limits.
ļ¬In three bus case the generation at bus 3
must be limited to avoid overloading the 3636
Security Constrained DispatchSecurity Constrained Dispatch
Bus 2 Bus 1
Bus 3Home Area
Scheduled Transactions
357 MW
179 MVR
194 MW
448 MW
19 MVR
232 MVR
179 MW
89 MVR
1.00 PU
-22 MW
4 MVR
22 MW
-4 MVR
-142 MW
49 MVR
145 MW
-37 MVR
124 MW
-33 MVR
-122 MW
41 MVR
1.00 PU
1.00 PU
0 MW
37 MVR100%
100%
100 MW
OFF AGC
AVR ON
AGC ON
AVR ON
100.0 MW
Need to dispatch to keep line
from bus 3 to bus 2 from overloading
3737
Multi-Area OperationMulti-Area Operation
ļ¬In multi-area system, ā€œrulesā€ have been established
regarding transactions on tie-lines:
ā€“ In Eastern interconnection, in principle, up to ā€œnominalā€
thermal interconnection capacity,
ā€“ In Western interconnection there are more complicated
rules
ļ¬The actual power that flows through the entire
network depends on the impedance of the
transmission lines, and ultimately determine what
are acceptable patterns of dispatch:
ļ¬Can result in need to ā€œcurtailā€ transactions that
otherwise satisfy rules.
ļ¬Economically uncompensated flow through other
areas is known as ā€œparallel pathā€ or ā€œloop flows.ā€
ļ¬Since ERCOT is one area, all of the flows on AC
lines are inside ERCOT and there is no
uncompensated flow on AC lines. 3838
Power System EconomicPower System Economic
OperationOperation
ā€¢ Fuel cost to generate a MWh can vary
widely from technology to technology.
ā€¢ For some types of units, such as hydro,
ā€œfuelā€ costs are zero but the limit on total
available water gives it an implicit value.
ā€¢ For thermal units it is much easier to
characterize costs.
ā€¢ We will focus on minimizing the variable
operating costs (primarily fuel costs) to
meet demand. 3939
Power System EconomicPower System Economic
OperationOperation
ā€¢ Power system loads are cyclical.
ā€¢ Therefore the installed generation capacity
is usually much greater than the current
load.
ā€¢ This means that there are typically many
ways we could meet the current load.
ā€¢ Since different states have different mixes
of generation, we will consider how
generally to minimize the variable
operating costs given an arbitrary, 4040
Thermal versus OtherThermal versus Other
GenerationGenerationļ¬The main types of generating units are
thermal and hydro, with wind and solar
rapidly growing.
ļ¬For hydro the fuel (water) is free but there
may be many constraints on operation:
ā€“ fixed amounts of water available,
ā€“ reservoir levels must be managed and
coordinated,
ā€“ downstream flow rates for fish and navigation.
ļ¬Hydro optimization is typically longer term
(many months or years).
ļ¬We will concentrate on dispatchable
thermal units, looking at short-term 4141
Generator typesGenerator types
ļ¬Traditionally utilities have had three broad
groups of generators:
ā€“ ā€œBaseloadā€ units: large coal/nuclear; almost
always on at max.
ā€“ ā€œMidload,ā€ ā€˜intermediate,ā€ or ā€œcyclingā€ units: smaller
coal or gas that cycle on/off daily or weekly.
ā€“ ā€œPeakerā€ units: combustion turbines used only for
several hours. during periods of high demand
4242
Block Diagram of Thermal UnitBlock Diagram of Thermal Unit
ā€¢To optimize generation costs we need to develop
cost relationships between net power out and
operating costs.
ā€¢Between 2-10% of power is used within the
generating plant; this is known as the auxiliary 4343
Thermal generator Cost CurvesThermal generator Cost Curves
ļ¬Thermal generator costs are typically
represented by one or other of the
following four curves
ā€“ input/output (I/O) curve
ā€“ fuel-cost curve
ā€“ heat-rate curve
ā€“ incremental cost curve
ļ¬For reference
- 1 Btu (British thermal unit) = 1054 J
- 1 MBtu = 1x106
Btu
- 1 MBtu = 0.29 MWh 4444
I/O CurveI/O Curve
ļ¬The IO curve plots fuel input (in
MBtu/hr) versus net MW output.
4545
Fuel-cost CurveFuel-cost Curve
ļ¬The fuel-cost curve is the I/O curve
multiplied by fuel cost.
ļ¬A typical cost for coal is $ 1.70/MBtu.
4646
Heat-rate CurveHeat-rate Curve
ā€¢ Plots the average number of MBtu/hr of fuel
input needed per MW of output.
ā€¢ Heat-rate curve is the I/O curve divided by
MW.
Best heat-rate for most efficient coal
units is around 9.0
4747
Incremental (Marginal) costIncremental (Marginal) cost
CurveCurveļ¬Plots the incremental $/MWh as a
function of MW.
ļ¬Found by differentiating the cost curve.
4848
Mathematical Formulation ofMathematical Formulation of
CostsCostsļ¬Generator cost curves are usually not
smooth. However the curves can
usually be adequately approximated
using piece-wise smooth, functions.
ļ¬Two approximations predominate:
ā€“ quadratic or cubic functions
ā€“ piecewise linear functions
ļ¬We'll assume a quadratic
approximation: 2
( ) $/hr (fuel-cost)
( )
( ) 2 $/MWh
i Gi i i Gi i Gi
i Gi
i Gi i i Gi
Gi
C P P P
dC P
IC P P
dP
Ī± Ī² Ī³
Ī² Ī³
= + +
= = +
4949
Coal Usage ExampleCoal Usage Example
ā€¢A 500 MW (net) generator is 35% efficient.
It is being supplied with coal costing $1.70
per MBtu and with heat content 9000 Btu
per pound. What is the coal usage in
lbs/hr? What is the cost?
At 35% efficiency required fuel input per hour is
500 MWh 1428 MWh 1 MBtu 4924 MBtu
hr 0.35 hr 0.29 MWh hr
4924 MBtu 1 lb 547,111 lbs
hr 0.009MBtu hr
4924 MBtu $1.70
Cost = 8370.8 $/hr or $16.74/MWh
hr MBtu
= Ɨ =
Ɨ
Ɨ =
Ɨ =
5050
Wasting Coal ExampleWasting Coal Example
ā€¢Assume a 100W lamp is left on by
mistake for 8 hours, and that the electricity
is supplied by the previous coal plant and
that transmission/distribution losses are
20%. How much coal has he/she
wasted?
With 20% losses, a 100W load on for 8 hrs requires
1 kWh of energy. With 35% gen. efficiency this requires
1 kWh 1 MWh 1 MBtu 1 lb
1.09 lb
0.35 1000 kWh 0.29 MWh 0.009MBtu
Ɨ Ɨ Ɨ =
5151
Incremental Cost ExampleIncremental Cost Example
2
1 1 1 1
2
2 2 2 2
1 1
1 1 1
1
2 2
2 2 2
2
For a two generator system assume
( ) 1000 20 0.01 $/hr
( ) 400 15 0.03 $/hr
Then
( )
( ) 20 0.02 $/MWh
( )
( ) 15 0.06 $/MWh
G G G
G G G
G
G G
G
G
G G
G
C P P P
C P P P
dC P
IC P P
dP
dC P
IC P P
dP
= + +
= + +
= = +
= = +
5252
Incremental Cost Example,Incremental Cost Example,
cont'dcont'd
1 2
2
1
2
2
1
2
If 250 MW and 150 MW Then
(250) 1000 20 250 0.01 250 $ 6625/hr
(150) 400 15 150 0.03 150 $6025/hr
Then
(250) 20 0.02 250 $ 25/MWh
(150) 15 0.06 150 $ 24/MWh
G GP P
C
C
IC
IC
= =
= + Ɨ + Ɨ =
= + Ɨ + Ɨ =
= + Ɨ =
= + Ɨ =
5353
5454
THANK YOUTHANK YOU

More Related Content

What's hot

Solution to ELD problem
Solution to ELD problemSolution to ELD problem
Solution to ELD problemNaveena Navi
Ā 
Economic load dispatch
Economic load dispatchEconomic load dispatch
Economic load dispatchVipin Pandey
Ā 
Optimization of power sytem
Optimization of power sytemOptimization of power sytem
Optimization of power sytemshawon1981
Ā 
Cost of electricity generation
Cost of electricity generationCost of electricity generation
Cost of electricity generationSerajul Haque
Ā 
Economic load dispatch
Economic load dispatchEconomic load dispatch
Economic load dispatchvikram anand
Ā 
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMSOPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMSIAEME Publication
Ā 
Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment Pritesh Priyadarshi
Ā 
Economic load dispatch
Economic load dispatch Economic load dispatch
Economic load dispatch MANGESHKULKARNI72
Ā 
Economic load dispatch
Economic load  dispatchEconomic load  dispatch
Economic load dispatchDeepak John
Ā 
Unit Commitment
Unit CommitmentUnit Commitment
Unit Commitmentrohitdasari
Ā 
Economic Dispatch Research paper solution slides
Economic Dispatch Research paper solution slidesEconomic Dispatch Research paper solution slides
Economic Dispatch Research paper solution slidesMuhammad Abdullah
Ā 
A presentation on economic load dispatch
A presentation on economic load dispatchA presentation on economic load dispatch
A presentation on economic load dispatchsouravsahoo28
Ā 
Economic Dispatch of Generated Power Using Modified Lambda-Iteration Method
Economic Dispatch of Generated Power Using Modified Lambda-Iteration MethodEconomic Dispatch of Generated Power Using Modified Lambda-Iteration Method
Economic Dispatch of Generated Power Using Modified Lambda-Iteration MethodIOSR Journals
Ā 
Hydrothermal scheduling
Hydrothermal schedulingHydrothermal scheduling
Hydrothermal schedulingASHIRBAD BARIK
Ā 
Optimal load scheduling
Optimal load schedulingOptimal load scheduling
Optimal load schedulingMayank Sharma
Ā 
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATION
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATIONECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATION
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATIONMln Phaneendra
Ā 
Input output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental costInput output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental costEklavya Sharma
Ā 
Lecture 16
Lecture 16Lecture 16
Lecture 16Forward2025
Ā 

What's hot (20)

Solution to ELD problem
Solution to ELD problemSolution to ELD problem
Solution to ELD problem
Ā 
Economic load dispatch
Economic load dispatchEconomic load dispatch
Economic load dispatch
Ā 
Optimization of power sytem
Optimization of power sytemOptimization of power sytem
Optimization of power sytem
Ā 
Cost of electricity generation
Cost of electricity generationCost of electricity generation
Cost of electricity generation
Ā 
Economic load dispatch
Economic load dispatchEconomic load dispatch
Economic load dispatch
Ā 
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMSOPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
Ā 
Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment
Ā 
A Case Study of Economic Load Dispatch for a Thermal Power Plant using Partic...
A Case Study of Economic Load Dispatch for a Thermal Power Plant using Partic...A Case Study of Economic Load Dispatch for a Thermal Power Plant using Partic...
A Case Study of Economic Load Dispatch for a Thermal Power Plant using Partic...
Ā 
Economic load dispatch
Economic load dispatch Economic load dispatch
Economic load dispatch
Ā 
Economic load dispatch
Economic load  dispatchEconomic load  dispatch
Economic load dispatch
Ā 
Unit Commitment
Unit CommitmentUnit Commitment
Unit Commitment
Ā 
Economic Dispatch Research paper solution slides
Economic Dispatch Research paper solution slidesEconomic Dispatch Research paper solution slides
Economic Dispatch Research paper solution slides
Ā 
Unit commitment
Unit commitmentUnit commitment
Unit commitment
Ā 
A presentation on economic load dispatch
A presentation on economic load dispatchA presentation on economic load dispatch
A presentation on economic load dispatch
Ā 
Economic Dispatch of Generated Power Using Modified Lambda-Iteration Method
Economic Dispatch of Generated Power Using Modified Lambda-Iteration MethodEconomic Dispatch of Generated Power Using Modified Lambda-Iteration Method
Economic Dispatch of Generated Power Using Modified Lambda-Iteration Method
Ā 
Hydrothermal scheduling
Hydrothermal schedulingHydrothermal scheduling
Hydrothermal scheduling
Ā 
Optimal load scheduling
Optimal load schedulingOptimal load scheduling
Optimal load scheduling
Ā 
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATION
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATIONECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATION
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATION
Ā 
Input output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental costInput output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental cost
Ā 
Lecture 16
Lecture 16Lecture 16
Lecture 16
Ā 

Similar to Economic Operation of Power Systems

Power System analysis slides - economic dispatch
Power System analysis slides - economic dispatchPower System analysis slides - economic dispatch
Power System analysis slides - economic dispatchThiyagarajan Rajalakshmi
Ā 
Lecture_16.ppt
Lecture_16.pptLecture_16.ppt
Lecture_16.pptKifle Godana
Ā 
ECE476_2016_Lect17.pptx
ECE476_2016_Lect17.pptxECE476_2016_Lect17.pptx
ECE476_2016_Lect17.pptxFeehaAreej
Ā 
Economic Load Dispatch.ppt
Economic Load Dispatch.pptEconomic Load Dispatch.ppt
Economic Load Dispatch.pptSuraj Dhungel
Ā 
ECE 505 Final project
ECE 505 Final project ECE 505 Final project
ECE 505 Final project ?? ?
Ā 
Computer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and securityComputer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and securityAdama Science and Technology University
Ā 
Economicloaddispatch 111213025406-phpapp01
Economicloaddispatch 111213025406-phpapp01Economicloaddispatch 111213025406-phpapp01
Economicloaddispatch 111213025406-phpapp01vikram anand
Ā 
Biosight: Quantitative Methods for Policy Analysis - Introduction to GAMS, Li...
Biosight: Quantitative Methods for Policy Analysis - Introduction to GAMS, Li...Biosight: Quantitative Methods for Policy Analysis - Introduction to GAMS, Li...
Biosight: Quantitative Methods for Policy Analysis - Introduction to GAMS, Li...IFPRI-EPTD
Ā 
Analyses of reactive power compensation schemes in MV/LV Networks with RE infeed
Analyses of reactive power compensation schemes in MV/LV Networks with RE infeedAnalyses of reactive power compensation schemes in MV/LV Networks with RE infeed
Analyses of reactive power compensation schemes in MV/LV Networks with RE infeedAushiq Ali Memon
Ā 
economic load dispatch and unit commitment power_system_operation.pdf
economic load dispatch and unit commitment power_system_operation.pdfeconomic load dispatch and unit commitment power_system_operation.pdf
economic load dispatch and unit commitment power_system_operation.pdfArnabChakraborty499766
Ā 
Chapter 18
Chapter 18Chapter 18
Chapter 18Tha Mike
Ā 
Ch08
Ch08Ch08
Ch08waiwai28
Ā 
Cs electric product information for micro grid concept power for all 24 x7 (...
Cs electric product information for micro grid concept power for all  24 x7 (...Cs electric product information for micro grid concept power for all  24 x7 (...
Cs electric product information for micro grid concept power for all 24 x7 (...Mahesh Chandra Manav
Ā 
Module2-Automatic-Generation-control.ppt
Module2-Automatic-Generation-control.pptModule2-Automatic-Generation-control.ppt
Module2-Automatic-Generation-control.pptkvvbapiraju2
Ā 
1 mrac for inverted pendulum
1 mrac for inverted pendulum1 mrac for inverted pendulum
1 mrac for inverted pendulumnazir1988
Ā 
Lecture 15
Lecture 15Lecture 15
Lecture 15Forward2025
Ā 
Multi-Objective Aspects of Distribution Network Volt-VAr Optimization
Multi-Objective Aspects of Distribution Network Volt-VAr OptimizationMulti-Objective Aspects of Distribution Network Volt-VAr Optimization
Multi-Objective Aspects of Distribution Network Volt-VAr OptimizationPower System Operation
Ā 

Similar to Economic Operation of Power Systems (20)

Power System analysis slides - economic dispatch
Power System analysis slides - economic dispatchPower System analysis slides - economic dispatch
Power System analysis slides - economic dispatch
Ā 
Lecture_16.ppt
Lecture_16.pptLecture_16.ppt
Lecture_16.ppt
Ā 
ECE476_2016_Lect17.pptx
ECE476_2016_Lect17.pptxECE476_2016_Lect17.pptx
ECE476_2016_Lect17.pptx
Ā 
ECE4762011_Lect16.ppt
ECE4762011_Lect16.pptECE4762011_Lect16.ppt
ECE4762011_Lect16.ppt
Ā 
Economic Load Dispatch.ppt
Economic Load Dispatch.pptEconomic Load Dispatch.ppt
Economic Load Dispatch.ppt
Ā 
ECE 505 Final project
ECE 505 Final project ECE 505 Final project
ECE 505 Final project
Ā 
UNIT-4-PPT.ppt
UNIT-4-PPT.pptUNIT-4-PPT.ppt
UNIT-4-PPT.ppt
Ā 
Computer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and securityComputer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and security
Ā 
Economicloaddispatch 111213025406-phpapp01
Economicloaddispatch 111213025406-phpapp01Economicloaddispatch 111213025406-phpapp01
Economicloaddispatch 111213025406-phpapp01
Ā 
aaoczc2252
aaoczc2252aaoczc2252
aaoczc2252
Ā 
Biosight: Quantitative Methods for Policy Analysis - Introduction to GAMS, Li...
Biosight: Quantitative Methods for Policy Analysis - Introduction to GAMS, Li...Biosight: Quantitative Methods for Policy Analysis - Introduction to GAMS, Li...
Biosight: Quantitative Methods for Policy Analysis - Introduction to GAMS, Li...
Ā 
Analyses of reactive power compensation schemes in MV/LV Networks with RE infeed
Analyses of reactive power compensation schemes in MV/LV Networks with RE infeedAnalyses of reactive power compensation schemes in MV/LV Networks with RE infeed
Analyses of reactive power compensation schemes in MV/LV Networks with RE infeed
Ā 
economic load dispatch and unit commitment power_system_operation.pdf
economic load dispatch and unit commitment power_system_operation.pdfeconomic load dispatch and unit commitment power_system_operation.pdf
economic load dispatch and unit commitment power_system_operation.pdf
Ā 
Chapter 18
Chapter 18Chapter 18
Chapter 18
Ā 
Ch08
Ch08Ch08
Ch08
Ā 
Cs electric product information for micro grid concept power for all 24 x7 (...
Cs electric product information for micro grid concept power for all  24 x7 (...Cs electric product information for micro grid concept power for all  24 x7 (...
Cs electric product information for micro grid concept power for all 24 x7 (...
Ā 
Module2-Automatic-Generation-control.ppt
Module2-Automatic-Generation-control.pptModule2-Automatic-Generation-control.ppt
Module2-Automatic-Generation-control.ppt
Ā 
1 mrac for inverted pendulum
1 mrac for inverted pendulum1 mrac for inverted pendulum
1 mrac for inverted pendulum
Ā 
Lecture 15
Lecture 15Lecture 15
Lecture 15
Ā 
Multi-Objective Aspects of Distribution Network Volt-VAr Optimization
Multi-Objective Aspects of Distribution Network Volt-VAr OptimizationMulti-Objective Aspects of Distribution Network Volt-VAr Optimization
Multi-Objective Aspects of Distribution Network Volt-VAr Optimization
Ā 

More from Md Irshad Ahmad

Academic Council Meet PPT- 19
Academic Council Meet PPT- 19Academic Council Meet PPT- 19
Academic Council Meet PPT- 19Md Irshad Ahmad
Ā 
Power station practice (NEE-702) unit-5
Power station practice (NEE-702) unit-5Power station practice (NEE-702) unit-5
Power station practice (NEE-702) unit-5Md Irshad Ahmad
Ā 
Power station practice (NEE-702) unit-3
Power station practice (NEE-702) unit-3Power station practice (NEE-702) unit-3
Power station practice (NEE-702) unit-3Md Irshad Ahmad
Ā 
Power station practice (NEE-702) unit-2
Power station practice (NEE-702) unit-2Power station practice (NEE-702) unit-2
Power station practice (NEE-702) unit-2Md Irshad Ahmad
Ā 
Power station practice (NEE- 702) unit-1
Power station practice (NEE- 702) unit-1Power station practice (NEE- 702) unit-1
Power station practice (NEE- 702) unit-1Md Irshad Ahmad
Ā 
Electrical measurement & measuring instruments [emmi (nee-302) -unit-5]
Electrical measurement & measuring instruments [emmi  (nee-302) -unit-5]Electrical measurement & measuring instruments [emmi  (nee-302) -unit-5]
Electrical measurement & measuring instruments [emmi (nee-302) -unit-5]Md Irshad Ahmad
Ā 
Electrical measurement &amp; measuring instruments [emmi (nee-302) -unit-4]
Electrical measurement &amp; measuring instruments [emmi  (nee-302) -unit-4]Electrical measurement &amp; measuring instruments [emmi  (nee-302) -unit-4]
Electrical measurement &amp; measuring instruments [emmi (nee-302) -unit-4]Md Irshad Ahmad
Ā 
Electrical measurement &amp; measuring instruments [emmi (nee-302) -unit-3]
Electrical measurement &amp; measuring instruments [emmi  (nee-302) -unit-3]Electrical measurement &amp; measuring instruments [emmi  (nee-302) -unit-3]
Electrical measurement &amp; measuring instruments [emmi (nee-302) -unit-3]Md Irshad Ahmad
Ā 
Electrical measurement &amp; measuring instruments [emmi (nee-302) -unit-2]
Electrical measurement &amp; measuring instruments [emmi  (nee-302) -unit-2]Electrical measurement &amp; measuring instruments [emmi  (nee-302) -unit-2]
Electrical measurement &amp; measuring instruments [emmi (nee-302) -unit-2]Md Irshad Ahmad
Ā 
ELECTRICAL MEASUREMENT & MEASURING INSTRUMENTS [Emmi- (NEE-302) -unit-1]
ELECTRICAL MEASUREMENT & MEASURING INSTRUMENTS [Emmi- (NEE-302) -unit-1]ELECTRICAL MEASUREMENT & MEASURING INSTRUMENTS [Emmi- (NEE-302) -unit-1]
ELECTRICAL MEASUREMENT & MEASURING INSTRUMENTS [Emmi- (NEE-302) -unit-1]Md Irshad Ahmad
Ā 
Switchgear and protection 5
Switchgear and protection 5Switchgear and protection 5
Switchgear and protection 5Md Irshad Ahmad
Ā 
Switchgear and protection 4
Switchgear and protection 4Switchgear and protection 4
Switchgear and protection 4Md Irshad Ahmad
Ā 
Switchgear and protection 3
Switchgear and protection 3Switchgear and protection 3
Switchgear and protection 3Md Irshad Ahmad
Ā 
Switchgear and protection 2
Switchgear and protection 2Switchgear and protection 2
Switchgear and protection 2Md Irshad Ahmad
Ā 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1Md Irshad Ahmad
Ā 

More from Md Irshad Ahmad (20)

Academic Council Meet PPT- 19
Academic Council Meet PPT- 19Academic Council Meet PPT- 19
Academic Council Meet PPT- 19
Ā 
Power station practice (NEE-702) unit-5
Power station practice (NEE-702) unit-5Power station practice (NEE-702) unit-5
Power station practice (NEE-702) unit-5
Ā 
Power station practice (NEE-702) unit-3
Power station practice (NEE-702) unit-3Power station practice (NEE-702) unit-3
Power station practice (NEE-702) unit-3
Ā 
Power station practice (NEE-702) unit-2
Power station practice (NEE-702) unit-2Power station practice (NEE-702) unit-2
Power station practice (NEE-702) unit-2
Ā 
Power station practice (NEE- 702) unit-1
Power station practice (NEE- 702) unit-1Power station practice (NEE- 702) unit-1
Power station practice (NEE- 702) unit-1
Ā 
Electrical measurement & measuring instruments [emmi (nee-302) -unit-5]
Electrical measurement & measuring instruments [emmi  (nee-302) -unit-5]Electrical measurement & measuring instruments [emmi  (nee-302) -unit-5]
Electrical measurement & measuring instruments [emmi (nee-302) -unit-5]
Ā 
Electrical measurement &amp; measuring instruments [emmi (nee-302) -unit-4]
Electrical measurement &amp; measuring instruments [emmi  (nee-302) -unit-4]Electrical measurement &amp; measuring instruments [emmi  (nee-302) -unit-4]
Electrical measurement &amp; measuring instruments [emmi (nee-302) -unit-4]
Ā 
Electrical measurement &amp; measuring instruments [emmi (nee-302) -unit-3]
Electrical measurement &amp; measuring instruments [emmi  (nee-302) -unit-3]Electrical measurement &amp; measuring instruments [emmi  (nee-302) -unit-3]
Electrical measurement &amp; measuring instruments [emmi (nee-302) -unit-3]
Ā 
Electrical measurement &amp; measuring instruments [emmi (nee-302) -unit-2]
Electrical measurement &amp; measuring instruments [emmi  (nee-302) -unit-2]Electrical measurement &amp; measuring instruments [emmi  (nee-302) -unit-2]
Electrical measurement &amp; measuring instruments [emmi (nee-302) -unit-2]
Ā 
ELECTRICAL MEASUREMENT & MEASURING INSTRUMENTS [Emmi- (NEE-302) -unit-1]
ELECTRICAL MEASUREMENT & MEASURING INSTRUMENTS [Emmi- (NEE-302) -unit-1]ELECTRICAL MEASUREMENT & MEASURING INSTRUMENTS [Emmi- (NEE-302) -unit-1]
ELECTRICAL MEASUREMENT & MEASURING INSTRUMENTS [Emmi- (NEE-302) -unit-1]
Ā 
Power quality 5
Power quality 5Power quality 5
Power quality 5
Ā 
Power quality 4
Power quality 4Power quality 4
Power quality 4
Ā 
Power quality 3
Power quality 3Power quality 3
Power quality 3
Ā 
Power quality 2
Power quality 2Power quality 2
Power quality 2
Ā 
Power quality 1
Power quality 1Power quality 1
Power quality 1
Ā 
Switchgear and protection 5
Switchgear and protection 5Switchgear and protection 5
Switchgear and protection 5
Ā 
Switchgear and protection 4
Switchgear and protection 4Switchgear and protection 4
Switchgear and protection 4
Ā 
Switchgear and protection 3
Switchgear and protection 3Switchgear and protection 3
Switchgear and protection 3
Ā 
Switchgear and protection 2
Switchgear and protection 2Switchgear and protection 2
Switchgear and protection 2
Ā 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
Ā 

Recently uploaded

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
Ā 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
Ā 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
Ā 
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”soniya singh
Ā 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
Ā 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
Ā 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
Ā 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
Ā 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
Ā 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
Ā 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
Ā 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoĆ£o Esperancinha
Ā 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
Ā 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
Ā 
Gurgaon āœ”ļø9711147426āœØCall In girls Gurgaon Sector 51 escort service
Gurgaon āœ”ļø9711147426āœØCall In girls Gurgaon Sector 51 escort serviceGurgaon āœ”ļø9711147426āœØCall In girls Gurgaon Sector 51 escort service
Gurgaon āœ”ļø9711147426āœØCall In girls Gurgaon Sector 51 escort servicejennyeacort
Ā 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
Ā 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
Ā 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
Ā 

Recently uploaded (20)

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
Ā 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
Ā 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
Ā 
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Ā 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
Ā 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
Ā 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
Ā 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
Ā 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Ā 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Ā 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
Ā 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
Ā 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Ā 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Ā 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
Ā 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
Ā 
Gurgaon āœ”ļø9711147426āœØCall In girls Gurgaon Sector 51 escort service
Gurgaon āœ”ļø9711147426āœØCall In girls Gurgaon Sector 51 escort serviceGurgaon āœ”ļø9711147426āœØCall In girls Gurgaon Sector 51 escort service
Gurgaon āœ”ļø9711147426āœØCall In girls Gurgaon Sector 51 escort service
Ā 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
Ā 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
Ā 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
Ā 

Economic Operation of Power Systems

  • 1. UNIT-IVUNIT-IV Economic Operation of PowerEconomic Operation of Power SystemsSystems ā€¢ Md Irshad Ahmad ā€¢ Irshad.ahmad@jit.edu.in ā€¢ Electrical Engineering Department ā€¢ Subject: : POWER STATION PRACTICE ā€¢ (NEE /NENā€“702)
  • 2. ContentsContents ā€¢ UNIT-IV:Economic Operation of Power Systems: ā€¢ Characteristics of steam and hydro- plants,Constraints in operation ā€¢ Economic load scheduling of thermal plants Neglecting and considering transmission Losses, ā€¢ Penalty factor, loss coefficients, Incremental transmission loss. Hydrothermal Scheduling.
  • 3. Retail Electricity PricesRetail Electricity Prices ā€¢ There are many fixed and variable costs associated with power systems, which ultimately contribute to determining retail electricity prices. ā€¢ The major variable operating cost is associated with generation, primarily due to fuel costs: ā€“ Roughly 30% to 50% of retail costs. ā€¢ Retail prices also reflect the capital costs of building the generation, transmission, and distribution system as well as other 33
  • 4. Power System EconomicPower System Economic OperationOperation ā€¢ Different generation technologies vary in the: ā€“ capital costs necessary to build the generator ā€“ fuel costs to actually produce electric power ā€¢ For example: ā€“ nuclear and hydro have high capital costs and low operating costs. ā€“ Natural gas generators have low capital costs, and (with gas available from fracking) moderate operating costs. 44
  • 5. Economic Dispatch:Economic Dispatch: FormulationFormulation ļ¬The goal of economic dispatch is to determine the generation dispatch that minimizes the instantaneous operating cost, subject to the constraint that total generation = total load + losses T 1 1 Minimize C ( ) Such that m i Gi i m Gi D Losses i C P P P P = = = + āˆ‘ āˆ‘ @ Initially we'll ignore generator limits and the losses 55
  • 6. Unconstrained MinimizationUnconstrained Minimization ļ¬This is a minimization problem with a single equality constraint ļ¬For an unconstrained minimization a necessary (but not sufficient) condition for a minimum is the gradient of the function must be zero, ļ¬The gradient generalizes the first derivative for multi-variable problems: 1 2 ( ) ( ) ( ) ( ) , , , nx x x ļ£® ļ£¹āˆ‚ āˆ‚ āˆ‚ āˆ‡ ļ£Æ ļ£ŗāˆ‚ āˆ‚ āˆ‚ļ£° ļ£» f x f x f x f x K@ ( )āˆ‡ =f x 0 66
  • 7. Minimization with EqualityMinimization with Equality ConstraintConstraintļ¬When the minimization is constrained with an equality constraint we can solve the problem using the method of Lagrange Multipliers ļ¬Key idea is to represent a constrained minimization problem as an unconstrained problem.That is, for the general problem minimize ( ) s.t. ( ) We define the Lagrangian L( , ) ( ) ( ) Then a necessary condition for a minimum is the L ( , ) 0 and L ( , ) 0 T = = + āˆ‡ = āˆ‡ =xĪ» f x g x 0 xĪ» f x Ī» g x xĪ» x Ī» 77
  • 8. Economic Dispatch LagrangianEconomic Dispatch Lagrangian G 1 1 G For the economic dispatch we have a minimization constrained with a single equality constraint L( , ) ( ) ( ) (no losses) The necessary conditions for a minimum are L( , ) m m i Gi D Gi i i Gi C P P P dC P Ī» Ī» Ī» = = = + āˆ’ āˆ‚ = āˆ‚ āˆ‘ āˆ‘P P 1 ( ) 0 (for 1 to ) 0 i Gi Gi m D Gi i P i m dP P P Ī» = āˆ’ = = āˆ’ =āˆ‘ 88
  • 9. Economic Dispatch ExampleEconomic Dispatch Example 1 2 2 1 1 1 1 2 2 2 2 2 1 1 1 What is economic dispatch for a two generator system 500 MW and ( ) 1000 20 0.01 $/h ( ) 400 15 0.03 $/h Using the Lagrange multiplier method we know: ( ) 20 0.0 D G G G G G G G G G G P P P C P P P C P P P dC P dP Ī» = + = = + + = + + āˆ’ = + 1 2 2 2 2 1 2 2 0 ( ) 15 0.06 0 500 0 G G G G G G P dC P P dP P P Ī» Ī» Ī» āˆ’ = āˆ’ = + āˆ’ = āˆ’ āˆ’ = 99
  • 10. Economic Dispatch Example,Economic Dispatch Example, contā€™dcontā€™d 1 2 1 2 1 2 1 2 We therefore need to solve three linear equations 20 0.02 0 15 0.06 0 500 0 0.02 0 1 20 0 0.06 1 15 1 1 0 500 312.5 MW 187.5 MW 26.2 $/MW G G G G G G G G P P P P P P P P Ī» Ī» Ī» Ī» + āˆ’ = + āˆ’ = āˆ’ āˆ’ = āˆ’ āˆ’ļ£® ļ£¹ļ£® ļ£¹ ļ£® ļ£¹ ļ£Æ ļ£ŗļ£Æ ļ£ŗ ļ£Æ ļ£ŗāˆ’ = āˆ’ ļ£Æ ļ£ŗļ£Æ ļ£ŗ ļ£Æ ļ£ŗ āˆ’ āˆ’ āˆ’ļ£Æ ļ£ŗļ£Æ ļ£ŗ ļ£Æ ļ£ŗļ£° ļ£»ļ£° ļ£» ļ£° ļ£» ļ£® ļ£¹ ļ£Æ ļ£ŗ = ļ£Æ ļ£ŗ ļ£Æ ļ£ŗļ£° ļ£» h ļ£® ļ£¹ ļ£Æ ļ£ŗ ļ£Æ ļ£ŗ ļ£Æ ļ£ŗļ£° ļ£» 1010
  • 11. Economic dispatch example,Economic dispatch example, contā€™dcontā€™d ā€¢ At the solution, both generators have the same marginal (or incremental) cost, and this common marginal cost is equal to Ī». ā€¢ Intuition behind solution: ā€“ If marginal costs of generators were different, then by decreasing production at higher marginal cost generator, and increasing production at lower marginal cost generator we could lower overall costs. ā€“ Generalizes to any number of generators. ā€¢ If demand changes, then change in total costs can be estimated from Ī». 1111
  • 12. Economic dispatch example,Economic dispatch example, contā€™dcontā€™d ā€¢ Another way to solve the equations is to: ā€“ Rearrange the first two equations to solve for PG1 and PG2 in terms of Ī», ā€“ Plug into third equation and solve for Ī», ā€“ Use the solved value of Ī» to evaluate PG1 and PG2. ā€¢ This works even when relationship between generation levels and Ī» is more complicated: ā€“ Equations are more complicated than linear 1212
  • 13. Lambda-Iteration SolutionLambda-Iteration Solution MethodMethod ā€¢ Discussion on previous page leads to ā€œlambda-iterationā€ method: ā€“ this method requires a unique mapping from a value of lambda (marginal cost) to each generatorā€™s MW output: ā€“ for any choice of lambda (common marginal cost), the generators collectively produce a total MW output, ā€“ the method then starts with values of lambda below and above the optimal value (corresponding to too little and too much total output), and then iteratively brackets the optimalā€¢ 1313 ( ).Gi P Ī»
  • 14. Lambda-Iteration AlgorithmLambda-Iteration Algorithm L H 1 1 H L M H L H M 1 L M Pick and such that ( ) 0 ( ) 0 While Do ( )/2 If ( ) 0 Then Else End While m m L H Gi D Gi D i i m M Gi D i P P P P P P Ī» Ī» Ī» Ī» Ī» Ī» Īµ Ī» Ī» Ī» Ī» Ī» Ī» Ī» Ī» = = = āˆ’ < āˆ’ > āˆ’ > = + āˆ’ > = = āˆ‘ āˆ‘ āˆ‘ 1414
  • 15. Lambda-Iteration: GraphicalLambda-Iteration: Graphical ViewView In the graph shown below for each value of lambda there is a unique PGi for each generator. This relationship is the PGi(Ī») function. 1515
  • 16. Lambda-Iteration ExampleLambda-Iteration Example 1 1 1 2 2 2 3 3 3 1 2 3 Consider a three generator system with ( ) 15 0.02 $/MWh ( ) 20 0.01 $/MWh ( ) 18 0.025 $/MWh and with constraint 1000MW Rewriting generation as a function of , ( G G G G G G G G G Gi IC P P IC P P IC P P P P P P Ī» Ī» Ī» Ī» = + = = + = = + = + + = G1 G2 G3 ), we have 15 20 P ( ) P ( ) 0.02 0.01 18 P ( ) 0.025 Ī» Ī» Ī» Ī» Ī» Ī» Ī» āˆ’ āˆ’ = = āˆ’ = 1616
  • 17. Lambda-Iteration Example,Lambda-Iteration Example, contā€™dcontā€™dm Gi i=1 m Gi i=1 1 H 1 Pick so P ( ) 1000 0 and P ( ) 1000 0 Try 20 then (20) 1000 15 20 18 1000 670 MW 0.02 0.01 0.025 Try 30 then (30) 1000 1230 MW L L H m L Gi i m Gi i P P Ī» Ī» Ī» Ī» Ī» Ī» Ī» Ī» = = āˆ’ < āˆ’ > = āˆ’ = āˆ’ āˆ’ āˆ’ + + āˆ’ = āˆ’ = āˆ’ = āˆ‘ āˆ‘ āˆ‘ āˆ‘ 1717
  • 18. Lambda-Iteration Example,Lambda-Iteration Example, contā€™dcontā€™d 1 1 Pick convergence tolerance 0.05 $/MWh Then iterate since 0.05 ( )/ 2 25 Then since (25) 1000 280 we set 25 Since 25 20 0.05 (25 20)/ 2 22.5 (22.5) 1000 195 we set 2 H L M H L m H Gi i M m L Gi i P P Īµ Ī» Ī» Ī» Ī» Ī» Ī» Ī» Ī» = = = āˆ’ > = + = āˆ’ = = āˆ’ > = + = āˆ’ = āˆ’ = āˆ‘ āˆ‘ 2.5 1818
  • 19. Lambda-Iteration Example,Lambda-Iteration Example, contā€™dcontā€™d H * * 1 2 3 Continue iterating until 0.05 The solution value of , , is 23.53 $/MWh Once is known we can calculate the 23.53 15 (23.5) 426 MW 0.02 23.53 20 (23.5) 353 MW 0.01 23.53 18 (23.5) 0.025 L Gi G G G P P P P Ī» Ī» Ī» Ī» Ī» āˆ’ < āˆ’ = = āˆ’ = = āˆ’ = 221 MW= 1919
  • 20. Thirty Bus ED ExampleThirty Bus ED Example Case is economically dispatched (without considering the incremental impact of the system losses). 2020
  • 21. Generator MW LimitsGenerator MW Limits ļ¬Generators have limits on the minimum and maximum amount of power they can produce ļ¬Typically the minimum limit is not zero. ļ¬Because of varying system economics usually many generators in a system are operated at their maximum MW limits: ļ¬Baseload generators are at their maximum limits except during the off-peak. 2121
  • 22. Lambda-Iteration with GenLambda-Iteration with Gen LimitsLimits ,max ,max In the lambda-iteration method the limits are taken into account when calculating ( ) : if calculated production for then set ( ) if calculated production for Gi Gi Gi Gi Gi P P P P P Ī» Ī» > = ,min ,minthen set ( ) Gi Gi Gi Gi P P P PĪ» < = 2222
  • 23. Lambda-Iteration Gen LimitLambda-Iteration Gen Limit ExampleExample G1 G2 G3 1 2 3 1 In the previous three generator example assume the same cost characteristics but also with limits 0 P 300 MW 100 P 500 MW 200 P 600 MW With limits we get: (20) 1000 (20) (20) (20) 10 m Gi G G G i P P P P = ā‰¤ ā‰¤ ā‰¤ ā‰¤ ā‰¤ ā‰¤ āˆ’ = + + āˆ’āˆ‘ 1 00 250 100 200 1000 450 MW (compared to 670MW) (30) 1000 300 500 480 1000 280 MW m Gi i P = = + + āˆ’ = āˆ’ āˆ’ āˆ’ = + + āˆ’ =āˆ‘ 2323
  • 24. Lambda-Iteration LimitLambda-Iteration Limit Example,contā€™dExample,contā€™dAgain we continue iterating until the convergence condition is satisfied. With limits the final solution of , is 24.43 $/MWh (compared to 23.53 $/MWh without limits). Maximum limits will always caus Ī» 1 2 3 e to either increase or remain the same. Final solution is: (24.43) 300 MW (at maximum limit) (24.43) 443 MW (24.43) 257 MW G G G P P P Ī» = = = 2424
  • 25. Back of Envelope ValuesBack of Envelope Values ļ¬$/MWhr = fuelcost * heatrate + variable O&M ļ¬Typical incremental costs can be roughly approximated: ā€“ Typical heatrate for a coal plant is 10, modern combustion turbine is 10, combined cycle plant is 6 to 8, older combustion turbine 15. ā€“ Fuel costs ($/MBtu) are quite variable, with current values around 2 for coal, 3 to 5 for natural gas, 0.5 for nuclear, probably 10 for fuel oil. ā€“ Hydro costs tend to be quite low, but are fuel (water) constrained 2525
  • 26. Inclusion of TransmissionInclusion of Transmission LossesLosses ļ¬The losses on the transmission system are a function of the generation dispatch. ļ¬In general, using generators closer to the load results in lower losses ļ¬This impact on losses should be included when doing the economic dispatch ļ¬Losses can be included by slightly rewriting the Lagrangian to include G 1 1 L( , ) ( ) ( ) m m i Gi D L G Gi i i C P P P P PĪ» Ī» = = ļ£« ļ£¶ = + + āˆ’ļ£¬ Ć· ļ£­ ļ£ø āˆ‘ āˆ‘P 2626
  • 27. Impact of Transmission LossesImpact of Transmission Losses G 1 1 G The inclusion of losses then impacts the necessary conditions for an optimal economic dispatch: L( , ) ( ) ( ) . The necessary conditions for a minimum are now: L( , ) m m i Gi D L G Gi i i C P P P P PĪ» Ī» Ī» = = ļ£« ļ£¶ = + + āˆ’ļ£¬ Ć· ļ£­ ļ£ø āˆ‚ āˆ‚ āˆ‘ āˆ‘P P 1 ( ) ( ) 1 0 ( ) 0 i Gi L G Gi Gi Gi m D L G Gi i dC P P P P dP P P P P P Ī» = ļ£« ļ£¶āˆ‚ = āˆ’ āˆ’ =ļ£¬ Ć·āˆ‚ļ£­ ļ£ø + āˆ’ =āˆ‘ 2727
  • 28. Impact of Transmission LossesImpact of Transmission Losses th ( ) ( ) Solving for , we get: 1 0 ( )1 ( ) 1 Define the penalty factor for the generator (don't confuse with Lagrangian L!!!) 1 ( ) 1 i Gi L G Gi Gi i Gi GiL G Gi i i L G Gi dC P P P dP P dC P dPP P P L i L P P P Ī» Ī» Ī» ļ£« ļ£¶āˆ‚ āˆ’ āˆ’ =ļ£¬ Ć·āˆ‚ļ£­ ļ£ø = ļ£« ļ£¶āˆ‚ āˆ’ļ£¬ Ć·āˆ‚ļ£­ ļ£ø = ļ£« āˆ‚ āˆ’ļ£¬ āˆ‚ļ£­ ļ£¶ Ć· ļ£ø The penalty factor at the slack bus is always unity! 2828
  • 29. Impact of Transmission LossesImpact of Transmission Losses 1 1 1 2 2 2 The condition for optimal dispatch with losses is then ( ) ( ) ( ) 1 . So, if increasing increases ( ) 1 ( ) the losses then 0 1.0 This makes generator G G m m Gm i Gi L G Gi L G i Gi L IC P L IC P L IC P L P P P P P P L P Ī»= = = = ļ£« ļ£¶āˆ‚ āˆ’ļ£¬ Ć·āˆ‚ļ£­ ļ£ø āˆ‚ > ā‡’ > āˆ‚ appear to be more expensive (i.e., it is penalized). Likewise 1.0 makes a generator appear less expensive. i i L < 2929
  • 30. Calculation of Penalty FactorsCalculation of Penalty Factors Unfortunately, the analytic calculation of is somewhat involved. The problem is a small change in the generation at impacts the flows and hence the losses throughout the entire system. However, i Gi L P using a power flow you can approximate this function by making a small change to and then seeing how the losses change: ( ) ( ) 1 ( ) 1 Gi L G L G i L GGi Gi Gi P P P P P L P PP P P āˆ‚ āˆ† ā‰ˆ ā‰ˆ āˆ†āˆ‚ āˆ† āˆ’ āˆ† 3030
  • 31. Two Bus Penalty FactorTwo Bus Penalty Factor ExampleExample 2 2 2 2 ( ) ( ) 0.37 0.0387 0.037 10 0.9627 0.9643 L G L G G G P P P P MW P P MW L L āˆ‚ āˆ† āˆ’ = āˆ’ = = āˆ’ āˆ‚ āˆ† = ā‰ˆ 3131
  • 32. Thirty Bus ED ExampleThirty Bus ED Example Now consider losses. Because of the penalty factors the generator incremental costs are no longer identical. 3232
  • 33. Area Supply CurveArea Supply Curve 0 100 200 300 400 Total AreaGeneration(MW) 0.00 2.50 5.00 7.50 10.00 The area supply curve shows the cost to produce the next MW of electricity, assuming area is economically dispatched Supply curve for thirty bus system 3333
  • 34. Economic Dispatch - SummaryEconomic Dispatch - Summary ļ¬Economic dispatch determines the best way to minimize the current generator operating costs. ļ¬The lambda-iteration method is a good approach for solving the economic dispatch problem: ā€“ generator limits are easily handled, ā€“ penalty factors are used to consider the impact of losses. ļ¬Economic dispatch is not concerned with determining which units to turn on/off (this is the unit commitment problem). ļ¬Basic form of economic dispatch ignores the transmission system limitations. 3434
  • 35. Security Constrained EDSecurity Constrained ED or Optimal Power Flowor Optimal Power Flow ļ¬Transmission constraints often limit ability to use lower cost power. ļ¬Such limits require deviations from what would otherwise be minimum cost dispatch in order to maintain system ā€œsecurity.ā€ ļ¬Need to solve or approximate power flow in order to consider transmission constraints. 3535
  • 36. Security Constrained EDSecurity Constrained ED or Optimal Power Flowor Optimal Power Flow ļ¬The goal of a security constrained ED or optimal power flow (OPF) is to determine the ā€œbestā€ way to instantaneously operate a power system, considering transmission limits. ļ¬Usually ā€œbestā€ = minimizing operating cost, while keeping flows on transmission below limits. ļ¬In three bus case the generation at bus 3 must be limited to avoid overloading the 3636
  • 37. Security Constrained DispatchSecurity Constrained Dispatch Bus 2 Bus 1 Bus 3Home Area Scheduled Transactions 357 MW 179 MVR 194 MW 448 MW 19 MVR 232 MVR 179 MW 89 MVR 1.00 PU -22 MW 4 MVR 22 MW -4 MVR -142 MW 49 MVR 145 MW -37 MVR 124 MW -33 MVR -122 MW 41 MVR 1.00 PU 1.00 PU 0 MW 37 MVR100% 100% 100 MW OFF AGC AVR ON AGC ON AVR ON 100.0 MW Need to dispatch to keep line from bus 3 to bus 2 from overloading 3737
  • 38. Multi-Area OperationMulti-Area Operation ļ¬In multi-area system, ā€œrulesā€ have been established regarding transactions on tie-lines: ā€“ In Eastern interconnection, in principle, up to ā€œnominalā€ thermal interconnection capacity, ā€“ In Western interconnection there are more complicated rules ļ¬The actual power that flows through the entire network depends on the impedance of the transmission lines, and ultimately determine what are acceptable patterns of dispatch: ļ¬Can result in need to ā€œcurtailā€ transactions that otherwise satisfy rules. ļ¬Economically uncompensated flow through other areas is known as ā€œparallel pathā€ or ā€œloop flows.ā€ ļ¬Since ERCOT is one area, all of the flows on AC lines are inside ERCOT and there is no uncompensated flow on AC lines. 3838
  • 39. Power System EconomicPower System Economic OperationOperation ā€¢ Fuel cost to generate a MWh can vary widely from technology to technology. ā€¢ For some types of units, such as hydro, ā€œfuelā€ costs are zero but the limit on total available water gives it an implicit value. ā€¢ For thermal units it is much easier to characterize costs. ā€¢ We will focus on minimizing the variable operating costs (primarily fuel costs) to meet demand. 3939
  • 40. Power System EconomicPower System Economic OperationOperation ā€¢ Power system loads are cyclical. ā€¢ Therefore the installed generation capacity is usually much greater than the current load. ā€¢ This means that there are typically many ways we could meet the current load. ā€¢ Since different states have different mixes of generation, we will consider how generally to minimize the variable operating costs given an arbitrary, 4040
  • 41. Thermal versus OtherThermal versus Other GenerationGenerationļ¬The main types of generating units are thermal and hydro, with wind and solar rapidly growing. ļ¬For hydro the fuel (water) is free but there may be many constraints on operation: ā€“ fixed amounts of water available, ā€“ reservoir levels must be managed and coordinated, ā€“ downstream flow rates for fish and navigation. ļ¬Hydro optimization is typically longer term (many months or years). ļ¬We will concentrate on dispatchable thermal units, looking at short-term 4141
  • 42. Generator typesGenerator types ļ¬Traditionally utilities have had three broad groups of generators: ā€“ ā€œBaseloadā€ units: large coal/nuclear; almost always on at max. ā€“ ā€œMidload,ā€ ā€˜intermediate,ā€ or ā€œcyclingā€ units: smaller coal or gas that cycle on/off daily or weekly. ā€“ ā€œPeakerā€ units: combustion turbines used only for several hours. during periods of high demand 4242
  • 43. Block Diagram of Thermal UnitBlock Diagram of Thermal Unit ā€¢To optimize generation costs we need to develop cost relationships between net power out and operating costs. ā€¢Between 2-10% of power is used within the generating plant; this is known as the auxiliary 4343
  • 44. Thermal generator Cost CurvesThermal generator Cost Curves ļ¬Thermal generator costs are typically represented by one or other of the following four curves ā€“ input/output (I/O) curve ā€“ fuel-cost curve ā€“ heat-rate curve ā€“ incremental cost curve ļ¬For reference - 1 Btu (British thermal unit) = 1054 J - 1 MBtu = 1x106 Btu - 1 MBtu = 0.29 MWh 4444
  • 45. I/O CurveI/O Curve ļ¬The IO curve plots fuel input (in MBtu/hr) versus net MW output. 4545
  • 46. Fuel-cost CurveFuel-cost Curve ļ¬The fuel-cost curve is the I/O curve multiplied by fuel cost. ļ¬A typical cost for coal is $ 1.70/MBtu. 4646
  • 47. Heat-rate CurveHeat-rate Curve ā€¢ Plots the average number of MBtu/hr of fuel input needed per MW of output. ā€¢ Heat-rate curve is the I/O curve divided by MW. Best heat-rate for most efficient coal units is around 9.0 4747
  • 48. Incremental (Marginal) costIncremental (Marginal) cost CurveCurveļ¬Plots the incremental $/MWh as a function of MW. ļ¬Found by differentiating the cost curve. 4848
  • 49. Mathematical Formulation ofMathematical Formulation of CostsCostsļ¬Generator cost curves are usually not smooth. However the curves can usually be adequately approximated using piece-wise smooth, functions. ļ¬Two approximations predominate: ā€“ quadratic or cubic functions ā€“ piecewise linear functions ļ¬We'll assume a quadratic approximation: 2 ( ) $/hr (fuel-cost) ( ) ( ) 2 $/MWh i Gi i i Gi i Gi i Gi i Gi i i Gi Gi C P P P dC P IC P P dP Ī± Ī² Ī³ Ī² Ī³ = + + = = + 4949
  • 50. Coal Usage ExampleCoal Usage Example ā€¢A 500 MW (net) generator is 35% efficient. It is being supplied with coal costing $1.70 per MBtu and with heat content 9000 Btu per pound. What is the coal usage in lbs/hr? What is the cost? At 35% efficiency required fuel input per hour is 500 MWh 1428 MWh 1 MBtu 4924 MBtu hr 0.35 hr 0.29 MWh hr 4924 MBtu 1 lb 547,111 lbs hr 0.009MBtu hr 4924 MBtu $1.70 Cost = 8370.8 $/hr or $16.74/MWh hr MBtu = Ɨ = Ɨ Ɨ = Ɨ = 5050
  • 51. Wasting Coal ExampleWasting Coal Example ā€¢Assume a 100W lamp is left on by mistake for 8 hours, and that the electricity is supplied by the previous coal plant and that transmission/distribution losses are 20%. How much coal has he/she wasted? With 20% losses, a 100W load on for 8 hrs requires 1 kWh of energy. With 35% gen. efficiency this requires 1 kWh 1 MWh 1 MBtu 1 lb 1.09 lb 0.35 1000 kWh 0.29 MWh 0.009MBtu Ɨ Ɨ Ɨ = 5151
  • 52. Incremental Cost ExampleIncremental Cost Example 2 1 1 1 1 2 2 2 2 2 1 1 1 1 1 1 2 2 2 2 2 2 For a two generator system assume ( ) 1000 20 0.01 $/hr ( ) 400 15 0.03 $/hr Then ( ) ( ) 20 0.02 $/MWh ( ) ( ) 15 0.06 $/MWh G G G G G G G G G G G G G G C P P P C P P P dC P IC P P dP dC P IC P P dP = + + = + + = = + = = + 5252
  • 53. Incremental Cost Example,Incremental Cost Example, cont'dcont'd 1 2 2 1 2 2 1 2 If 250 MW and 150 MW Then (250) 1000 20 250 0.01 250 $ 6625/hr (150) 400 15 150 0.03 150 $6025/hr Then (250) 20 0.02 250 $ 25/MWh (150) 15 0.06 150 $ 24/MWh G GP P C C IC IC = = = + Ɨ + Ɨ = = + Ɨ + Ɨ = = + Ɨ = = + Ɨ = 5353