L12 - Studio 5000 and Logix: Basics Lab
For Classroom Use Only!
Important User Information
This documentation, whether, illustrative, printed, “online” or electronic (hereinafter “Documentation”) is intended for use only as
a learning aid when using Rockwell Automation approved demonstration hardware, software and firmware. The Documentation
should only be used as a learning tool by qualified professionals.
The variety of uses for the hardware, software and firmware (hereinafter “Products”) described in this Documentation, mandates
that those responsible for the application and use of those Products must satisfy themselves that all necessary steps have been
taken to ensure that each application and actual use meets all performance and safety requirements, including any applicable
laws, regulations, codes and standards in addition to any applicable technical documents.
In no event will Rockwell Automation, Inc., or any of its affiliate or subsidiary companies (hereinafter “Rockwell Automation”) be
responsible or liable for any indirect or consequential damages resulting from the use or application of the Products described in
this Documentation. Rockwell Automation does not assume responsibility or liability for damages of any kind based on the
alleged use of, or reliance on, this Documentation.
No patent liability is assumed by Rockwell Automation with respect to use of information, circuits, equipment, or software
described in the Documentation.
Except as specifically agreed in writing as part of a maintenance or support contract, equipment users are responsible for:
• properly using, calibrating, operating, monitoring and maintaining all Products consistent with all Rockwell Automation
or third-party provided instructions, warnings, recommendations and documentation;
• ensuring that only properly trained personnel use, operate and maintain the Products at all times;
• staying informed of all Product updates and alerts and implementing all updates and fixes; and
• all other factors affecting the Products that are outside of the direct control of Rockwell Automation.
Reproduction of the contents of the Documentation, in whole or in part, without written permission of Rockwell Automation is
prohibited.
Throughout this manual we use the following notes to make you aware of safety considerations:
Identifies information about practices or circumstances
that can cause an explosion in a hazardous environment,
which may lead to personal injury or death, property damage, or economic loss.
Identifies information that is critical for successful application and understanding of the product.
Identifies information about practices or circumstances that can lead to personal injury or death, property
damage, or economic loss. Attentions help you:
• identify a hazard
• avoid a hazard
• recognize the consequence
Labels may be located on or inside the drive to alert people that dangerous voltage may be present.
Labels may be located on or inside the drive to alert people that surfaces may be dangerous temperatures.
3 of 40
Studio5000LogixDesigner®:BasicsLab
Contents
Before you begin ........................................................................................................................................... 4
Lab 1: Creating a Project .............................................................................................................................. 5
Launching Studio 5000 Configuration Software................................................................................................................................ 5
Creating a New Controller Project .................................................................................................................................................... 6
Lab2: Configuring I/O.................................................................................................................................... 9
Adding ControlLogix I/O.................................................................................................................................................................... 9
Lab 3: Monitoring/Editing Tags ................................................................................................................... 14
Lab 4: Adding Ladder Logic ........................................................................................................................ 18
Adding Ladder Logic to the Main Routine....................................................................................................................................... 18
Lab 5: Tasks and programs ........................................................................................................................ 23
Lab 6: Download and Run........................................................................................................................... 25
Lab 7: User Defined Types (UDT) .............................................................................................................. 30
Creating User Defined Types.......................................................................................................................................................... 30
Monitoring UDT Tags...................................................................................................................................................................... 30
Lab 8: AOIs ................................................................................................................................................. 32
Using an AOI................................................................................................................................................................................... 32
Lab 9: Using Logical Organizer................................................................................................................... 34
Using the Logical Organizer............................................................................................................................................................ 34
Lab 10: Trends ........................................................................................................................................... 37
Running a Trend............................................................................................................................................................................. 37
4 of 40
Before you begin
About this lab
This session provides you with an opportunity to explore the Studio 5000 Logix Designer software and the ControlLogix
hardware platform. The session steps through creating a new project, programming, and downloading to a controller.
This lab takes approximately 105 minutes to complete.
Tools & prerequisites
Studio 5000 Logix Designer
RSLinx Classic
C:Lab FilesBasics LogixLogix_Basics_Lab_Demo_Project.ACD
ControlLogix L85E demo box
Tip Text – The text inside this gray box is supplemental information. This text can include FYIs, useful tips,
and other related information
5 of 40
Lab 1: Creating a Project
Tip Text – The text inside this gray box is supplemental information. This text can include FYIs, useful tips,
and other related information
This lab section should take roughly 20 minutes to complete.
Launching Studio 5000 Configuration Software
In this section of the lab, you will launch the Studio 5000 software, which will allow you to configure and program a controller.
1. Double-click on the Studio 5000 icon on the Desktop to launch Studio 5000 software
The Studio 5000 Splash Screen appears
Tip - To see what versions of Studio 5000 you have installed on your computer, select About under the
Explore section.
6 of 40
Creating a New Controller Project
In this portion of the lab, you will create an offline project using a ControlLogix controller.
2. Select New Project under the Create section.
3. When the New Project pop-up is displayed, select Logix and type ‘1756-L85E’ in the Search field.
4. Type ‘Intro_Lab_Control_Project’ into the name field.
5. Press the Next button.
6. When the Project Configuration window appears, fill it in as follows:
7 of 40
Select V31
Select 1756-A7 7-Slot ControlLogix Chassis
Select Slot 0
Select No Protection
Add a project description ‘Logix Basics Lab’
Click Finish
8 of 40
End of lab
Controller
Faceplate
I/O Configuration
Instructions
toolbar
Programming
area
Controller
Organizer
Controller Organizer and
Logical Organizer Tabs
Tasks, Programs,
and Routines
User Defined and
Predefined Datatypes
9 of 40
Lab2: Configuring I/O
We will now configure I/O for the project. To communicate with I/O modules you must add modules to the I/O Configuration
folder (also referred to as the I/O tree).
Adding ControlLogix I/O
You will continue to use the project already open.
1. In the I/O Configuration Folder, right click on 1756 Backplane and select New Module.
2. The Select Module Type window appears. Type “IB16” in the search box.
3. Select the 1756-IB16IF module and click Create
10 of 40
Module Configuration Wizard
Whenever you add an I/O module to the system you will go through the Module Configuration Wizard. The
Wizard allows you to step through the entire configuration needed for a module. You can access this
information later by double clicking on a module in the I/O Configuration folder or through the tag
monitor/editor.
With the Logix family, there are no dip switches or jumpers needed to configure I/O modules. I/O modules
are software configured. This saves time when setting up a system. The configuration for all modules is part
of the controller’s program and is downloaded to the module from the controller. This allows for ease of
installation or replacement if an I/O module fails.
4. The new module window appears. Enter the Name Digital_Input and Slot 3 parameters as shown below.
11 of 40
5. Click on the Connection tab to observe the Requested Packet Interval data. We will leave the default at 20
milliseconds.
Requested Packet Interval (RPI)
The Requested Packet Interval specifies the period at which data is updated to and from the module. RPIs
are configured in milliseconds. The range is .5ms to 750ms.
6. Click on OK to close the wizard.
7. In the Select Module Type window, type in “IF8” into the filter box and select the 1756-IF8I module.
12 of 40
8. Click on Create. The new module window appears.
9. Fill in the name “Analog_Input” and select Slot 5.
10. Select the Configuration tab to configure the analog module.
13 of 40
11. Select the Voltage radio button, and select the Input Range: 0V to 10V.
12. Click OK.
13. Close the Select Module Type dialogue.
End of lab
14 of 40
Lab 3: Monitoring/Editing Tags
In this lab, we will explore theTag Monitor/Editor in Studio 5000.
.
1. From the Controller Organizer double-click on Controller Tags.
Notice that there are several “Local” tags. These are the tags that were created when local I/O modules were added to the I/O
Config. The tag Monitor/Editor window appears. Notice in the lower left corner of the window two tabs labeled Monitor Tags and
Edit Tags as shown below.
2. Expand and explore the tags for the I/O modules by clicking the arrow icon .
• :C - Configuration tags hold the module configuration and are designated by a “:C” in the tag name.
• :I - Input tags have “:I” in the tag name.
• :O - Output tags have a “:O” in the name.
3. Notice the different tags types and members.
15 of 40
4. Click on the tab Edit Tags.
5. Scroll to the bottom and add three BOOLEAN tags, START, STOP, and RUNNING as shown.
6. Right click on the Start tag you created and select Edit “Start” Properties
7. Select Alias as a type and notice that the Tag Properties window changed.
16 of 40
8. Click on the down arrow for Alias For.
9. Expand Local:3:I by clicking on the arrow and select all the way down tree to Local:3:I.Pt[0].Data.
17 of 40
Tag Properties will now appear as follows:
START will now be aliased to Local:3:I.Pt[0].Data, which is the first input point on the 1756-IB16IF module. Notice in the edit
tags windows the alias and alias for columns now have the address selected. Using the tag START will be equivalent to using
the I/O tag “Local:3:I.Pt[0].data”
End of lab
18 of 40
Lab 4: Adding Ladder Logic
Adding Ladder Logic to the Main Routine
In this section of the lab you will add some code. During the labs we will only utilize ladder logic programming, but Logix
controllers also can be programmed using Function Block, Sequential Function Charts, and Structured Text. This allows
selection of the programming language that best fits an application.
1. In the Controller Organizer expand the MainProgram folder by clicking on the arrow . Once expanded, the
MainProgram will appear as shown below:
19 of 40
2. Double-click the MainRoutine icon and maximize the ladder window if it is not maximized.
This will open the routine editor. An empty rung will already exist as shown below: The red color of the rung and the circled “x”
next to the rung indicate the rung is incomplete.
3. From the instruction toolbar, left click and hold on the Examine On (XIC) instruction and drag the XIC onto
rung 0 until the green dot appears. Release the mouse button at the location you wish to place your instruction.
Verify your rung appears like the figure below:
20 of 40
4. From the instruction toolbar, left click and hold on the Output Energize (OTE) instruction onto the right of
the rung
FYI - If you place an instruction in the wrong location on a rung, simply click and hold on the instruction and
drag it to the correct location.
Verify the rung appears as follows:
As you can see the free form editing in Studio 5000 can help speed development. You do not have to place
an instruction and tie an address to it before you add the next instruction.
21 of 40
5. Double click on the “?” above the XIC instruction to get a drop down as shown.
6. Select the drop down and find and select the START tag
7. The rung should look as follows
22 of 40
8. Add RUNNING to the OTE so the rung appears as follows
See, we can quickly and easily add instructions and tags using Logix Designer!
End of lab
23 of 40
Lab 5: Tasks and programs
1. Right click on Tasks and select New Task
2. Create a new task of type periodic, name My Task, with a period of 250 ms, and OK to create the task.
3. Now, let’s add a program to it. Right click on the My_Task folder and select New Program.
24 of 40
4. Call the program My_Program and schedule in My_Task and click OK
5. Right click on My_Program and Add a new Routine.
6. Give the routine the name My_Routine and click OK.
That’s all! We have now created a new task, program, and routine that will execute every 250 ms. We could
now add any logic we wished.
End of lab
25 of 40
Lab 6: Download and Run
The layout of the L85E demo box we will be using.
1. Close the currently open project and save it as any name you like.
We will not need this project again. We will now use a previously built project.
26 of 40
2. Open the file
C:Lab FilesBasics LogixLogix_Basics_Lab_Demo_Project.ACD
Notice that the project has three tasks.
3. Select Who Active as shown
27 of 40
4. Select the L85E in the who window that shows up and select Download
5. Put the controller into run mode if prompted, OR, put the controller in run mode from the Rem Prog tab.
Verify the controller is in Remote Run mode as shown below
.
28 of 40
6. Open the MainRoutine shown below and navigate to rung 4
7. Push and hold the DI0 button on the demo box and verify the rung looks like the following
Notice the DO0 light is also on. It is wired to Local:4:O.Pt[0].Data
8. Open the Demo_Event_Routine.
9. Try any of the push buttons. Try push button DI2. Notice how the rungs behave..
You should see at least one of the ADD instructions increment when a button is pushed.
10. Right click on the Demo_Event_Task and select properties, then click configure tab.
Notice how the event task has been configured..
29 of 40
11. Open the local tags of the Demo_Event_Program.
Notice that the tag values can be viewed here too. Try pushing some buttons.
12. Open the Periodic Routine. Notice the Add instruction incrementing once a second.
13. Try viewing the properties of the periodic task and verify the period is 1 second.
14. Try pushing the DI3 push button several times.
Notice how the DO3 light responds. It is wired to Local:4:O.Pt[3].Data
End of lab
30 of 40
Lab 7: User Defined Types (UDT)
Creating User Defined Types
In this section of the lab you will create a custom User Defined Type (UDT).
What is a UDT and what is it good for?
A UDT is good for organizing related data into a single structure. A UDT allows a single tag to hold multiple
members. Each member can be given a unique name to describe the data it holds. The members are
accessed by the main tag name, followed by a period, followed by the member name.
Continue to use the project already open.
1. Open the continuous task MainRoutine
2. Go to rung 3
Noted there is a tag based on a UDT already filled in. This tag has a member of gallons and a member of Liters.
Notice that the values of the tags are shown on the instruction. The multiply instruction converts the number in gallons to liters.
3. Click on the number just below gallons, type “34” or any desired value, and press enter. Notice that the Liters
value updates automatically.
Monitoring UDT Tags
4. Double click the Parameters and Local Tags under the MainProgram and expand the Gallons_to_Liters tag.
Notice the values are also shown here. Make sure to select the Monitor Tags tab.
5. The values for gallons can be modified directly in the monitor screen by changing the value in the Value column.
Change the gallons value and watch that liters updates to corresponding value.
31 of 40
The UDT allows associated data to be stored under a single main tag instead of using completely separate
tags. This makes it easier to keep track of data and keep it more organized. The UDT name itself can
document what the data is for.
End of lab
32 of 40
Lab 8: AOIs
Using an AOI
1. Open the MainRoutine
2. Navigate to rung 6
3. .Turn the DI4 dial on and off. When the dial is on, notice that the Signal_Output tag alternates between 0 and 1
cause an output light to go on and off.
33 of 40
4. Right click on the Signal_Light instruction and select open logic.
5. Turn the dial DI4 again on and off. Watch the inner workings of the instruction in real time!
6. Close the Signal_Light Logic.
7. Right click on the instruction again and choose Open Definition
8. Feel free to explore the tabs, especially the Parameters and also Local Tags
AOI’s allow code to be encapsulated into a single instruction. This allows common code and functionality to be clearly
defined and easily reused. The AOI can be reused as many times as desired. Each AOI should typically have a unique
backing tag.
End of lab
34 of 40
Lab 9: Using Logical Organizer
Using the Logical Organizer
1. Click on the Logical Organizer tab
By default, all of the programs in the Controller Organizer are shown as an ungrouped list. Only the programs, and not the
tasks, are shown. We can use the organizer to group the programs. We can use a “folder” object to group the programs.
2. To add a new folder, right click on the Logical Model folder -> Add -> New Folder
3. Enter the name ‘My_Demo_Box’ and click OK.
35 of 40
4. Click and drag the three programs onto My_Demo_Box so that they are grouped under the My_Demo_Box
folder as shown.
5. Click on the Controller Organizer and notice that the programs and tasks haven’t changed.
36 of 40
Notice that the programs we are using to run the demo box are now grouped together. Anyone looking at the
Logical Organizer will have a better idea that both program are being used to run the demo box. In general,
the organizer is used to group the program code to model the physical or logical application.
End of lab
37 of 40
Lab 10: Trends
Trending
Basic Trending in Studio 5000 allows you to view data sampled over a time period in a graphical display.
Data is sampled at a periodic rate that is configurable from 1 millisecond to 30 minutes. Studio 5000 will
allow you to create a trend and save it as part of your project file.
Basic Trending has these constraints: you can trend data elements of type BOOL, SINT, INT, DINT, and
REAL, you are limited to sampling eight unique data elements in a single trend.
Running a Trend
1. From the Controller Organizer, expand Trends and select Demo_Trend_Sine_Wave.
2. Start the trend by clicking on the RUN button located toward the upper left of the Trend dialog box.
3. This trend has been set up to capture sine wave data. Watch as the sine wave builds
38 of 40
4. After you are satisfied it really is a sine wave, close the trend.
5. Open the trend Demo_Trend_Start_Stop
6. Run the trend
Notice nothing happens
7. Now press the DI0 button
Notice the trend start to run. This trend has been configured to start on the press of DI1.
8. Now press DI3.
Notice there are some samples after the press of the button. The amount of samples stored before or after a
press is configurable!
9. Stop the trend
10. Right click on the graph background and select “Chart Properties”.
11. Navigate to the Pens tab, the Start Trigger tab, and Stop Trigger tab and notice the configuration like that below.
Feel free to explore! If you stopped the trend, try change some of the properties to see the effect they will have.
Remember to apply and start the trend again!
39 of 40
By default, each tag will be independently scaled to its observed min/max values. If desired, the scaling
options can be changed under the chart properties - Y axis tab.
There are also other options in the trend properties such as a start and stop trigger and pen colors.
12. When you are finished investigating the trend, click Stop and close the trend window.
End of lab
40 of 40Publication XXXX-XX###X-EN-P — Month Year Copyright© 2016 Rockwell Automation, Inc. All rights reserved.
Supersedes Publication XXXX-XX###X-EN-P — Month Year

More Related Content

What's hot

New holland tv145 tractor service repair manual
New holland tv145 tractor service repair manualNew holland tv145 tractor service repair manual
New holland tv145 tractor service repair manualudfujjsejkkem
 
New holland mh6.6 wheel excavator service repair manual
New holland mh6.6 wheel excavator service repair manualNew holland mh6.6 wheel excavator service repair manual
New holland mh6.6 wheel excavator service repair manualjkmsme ekdmm
 
Case wx185 hydraulic excavator service repair manual
Case wx185 hydraulic excavator service repair manualCase wx185 hydraulic excavator service repair manual
Case wx185 hydraulic excavator service repair manualfusjefjjskekmem
 
013 50001-001 spy-elite_operators_manual_rev_e
013 50001-001 spy-elite_operators_manual_rev_e013 50001-001 spy-elite_operators_manual_rev_e
013 50001-001 spy-elite_operators_manual_rev_eSteph Cliche
 
Perkins 850 series 854 f e34ta industrial engine service repair manual
Perkins 850 series 854 f e34ta industrial engine service repair manualPerkins 850 series 854 f e34ta industrial engine service repair manual
Perkins 850 series 854 f e34ta industrial engine service repair manualfjjskkefksme
 

What's hot (6)

New holland tv145 tractor service repair manual
New holland tv145 tractor service repair manualNew holland tv145 tractor service repair manual
New holland tv145 tractor service repair manual
 
New holland mh6.6 wheel excavator service repair manual
New holland mh6.6 wheel excavator service repair manualNew holland mh6.6 wheel excavator service repair manual
New holland mh6.6 wheel excavator service repair manual
 
Case wx185 hydraulic excavator service repair manual
Case wx185 hydraulic excavator service repair manualCase wx185 hydraulic excavator service repair manual
Case wx185 hydraulic excavator service repair manual
 
Lock Out / Tag Out
Lock Out / Tag OutLock Out / Tag Out
Lock Out / Tag Out
 
013 50001-001 spy-elite_operators_manual_rev_e
013 50001-001 spy-elite_operators_manual_rev_e013 50001-001 spy-elite_operators_manual_rev_e
013 50001-001 spy-elite_operators_manual_rev_e
 
Perkins 850 series 854 f e34ta industrial engine service repair manual
Perkins 850 series 854 f e34ta industrial engine service repair manualPerkins 850 series 854 f e34ta industrial engine service repair manual
Perkins 850 series 854 f e34ta industrial engine service repair manual
 

Similar to Studio 5000 Basics Lab

Similar to Studio 5000 Basics Lab (20)

Factory talk assetcentre installation guide
Factory talk assetcentre installation guideFactory talk assetcentre installation guide
Factory talk assetcentre installation guide
 
1756 pm015 -en-p
1756 pm015 -en-p1756 pm015 -en-p
1756 pm015 -en-p
 
Ppt
PptPpt
Ppt
 
Mikroe465
Mikroe465Mikroe465
Mikroe465
 
Mountain Stream Group: Portfolio Sample - Technical Manual Development
Mountain Stream Group: Portfolio Sample - Technical Manual DevelopmentMountain Stream Group: Portfolio Sample - Technical Manual Development
Mountain Stream Group: Portfolio Sample - Technical Manual Development
 
Viewse um006 -en-e (1)
Viewse um006 -en-e (1)Viewse um006 -en-e (1)
Viewse um006 -en-e (1)
 
A73074 01
A73074 01A73074 01
A73074 01
 
2010 06 ess user guide_v5
2010 06 ess user guide_v52010 06 ess user guide_v5
2010 06 ess user guide_v5
 
1756 pm008 -en-p
1756 pm008 -en-p1756 pm008 -en-p
1756 pm008 -en-p
 
PLC: Hands on PLC programing with RSLOGIX500 a and Logixpro
PLC: Hands on PLC programing with RSLOGIX500 a and Logixpro PLC: Hands on PLC programing with RSLOGIX500 a and Logixpro
PLC: Hands on PLC programing with RSLOGIX500 a and Logixpro
 
Panelviewplusmanual
PanelviewplusmanualPanelviewplusmanual
Panelviewplusmanual
 
Faronics Anti-executable Standard User Guide
Faronics Anti-executable Standard User GuideFaronics Anti-executable Standard User Guide
Faronics Anti-executable Standard User Guide
 
ISE-802.1X-MAB
ISE-802.1X-MABISE-802.1X-MAB
ISE-802.1X-MAB
 
Autel AL619 User Manual
Autel AL619 User ManualAutel AL619 User Manual
Autel AL619 User Manual
 
Autel MaxiLink ML619 User Manual
Autel MaxiLink ML619 User ManualAutel MaxiLink ML619 User Manual
Autel MaxiLink ML619 User Manual
 
Tr7500 series software_en-v6-7-0
Tr7500 series software_en-v6-7-0Tr7500 series software_en-v6-7-0
Tr7500 series software_en-v6-7-0
 
Atv212 programming manual
Atv212 programming manualAtv212 programming manual
Atv212 programming manual
 
Cycle_Count_Approval_Process.pdf
Cycle_Count_Approval_Process.pdfCycle_Count_Approval_Process.pdf
Cycle_Count_Approval_Process.pdf
 
PICDEM2PlusUserGuide.pdf
PICDEM2PlusUserGuide.pdfPICDEM2PlusUserGuide.pdf
PICDEM2PlusUserGuide.pdf
 
IBM X346 User guide
IBM X346 User guideIBM X346 User guide
IBM X346 User guide
 

Recently uploaded

the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Studio 5000 Basics Lab

  • 1. L12 - Studio 5000 and Logix: Basics Lab For Classroom Use Only!
  • 2. Important User Information This documentation, whether, illustrative, printed, “online” or electronic (hereinafter “Documentation”) is intended for use only as a learning aid when using Rockwell Automation approved demonstration hardware, software and firmware. The Documentation should only be used as a learning tool by qualified professionals. The variety of uses for the hardware, software and firmware (hereinafter “Products”) described in this Documentation, mandates that those responsible for the application and use of those Products must satisfy themselves that all necessary steps have been taken to ensure that each application and actual use meets all performance and safety requirements, including any applicable laws, regulations, codes and standards in addition to any applicable technical documents. In no event will Rockwell Automation, Inc., or any of its affiliate or subsidiary companies (hereinafter “Rockwell Automation”) be responsible or liable for any indirect or consequential damages resulting from the use or application of the Products described in this Documentation. Rockwell Automation does not assume responsibility or liability for damages of any kind based on the alleged use of, or reliance on, this Documentation. No patent liability is assumed by Rockwell Automation with respect to use of information, circuits, equipment, or software described in the Documentation. Except as specifically agreed in writing as part of a maintenance or support contract, equipment users are responsible for: • properly using, calibrating, operating, monitoring and maintaining all Products consistent with all Rockwell Automation or third-party provided instructions, warnings, recommendations and documentation; • ensuring that only properly trained personnel use, operate and maintain the Products at all times; • staying informed of all Product updates and alerts and implementing all updates and fixes; and • all other factors affecting the Products that are outside of the direct control of Rockwell Automation. Reproduction of the contents of the Documentation, in whole or in part, without written permission of Rockwell Automation is prohibited. Throughout this manual we use the following notes to make you aware of safety considerations: Identifies information about practices or circumstances that can cause an explosion in a hazardous environment, which may lead to personal injury or death, property damage, or economic loss. Identifies information that is critical for successful application and understanding of the product. Identifies information about practices or circumstances that can lead to personal injury or death, property damage, or economic loss. Attentions help you: • identify a hazard • avoid a hazard • recognize the consequence Labels may be located on or inside the drive to alert people that dangerous voltage may be present. Labels may be located on or inside the drive to alert people that surfaces may be dangerous temperatures.
  • 3. 3 of 40 Studio5000LogixDesigner®:BasicsLab Contents Before you begin ........................................................................................................................................... 4 Lab 1: Creating a Project .............................................................................................................................. 5 Launching Studio 5000 Configuration Software................................................................................................................................ 5 Creating a New Controller Project .................................................................................................................................................... 6 Lab2: Configuring I/O.................................................................................................................................... 9 Adding ControlLogix I/O.................................................................................................................................................................... 9 Lab 3: Monitoring/Editing Tags ................................................................................................................... 14 Lab 4: Adding Ladder Logic ........................................................................................................................ 18 Adding Ladder Logic to the Main Routine....................................................................................................................................... 18 Lab 5: Tasks and programs ........................................................................................................................ 23 Lab 6: Download and Run........................................................................................................................... 25 Lab 7: User Defined Types (UDT) .............................................................................................................. 30 Creating User Defined Types.......................................................................................................................................................... 30 Monitoring UDT Tags...................................................................................................................................................................... 30 Lab 8: AOIs ................................................................................................................................................. 32 Using an AOI................................................................................................................................................................................... 32 Lab 9: Using Logical Organizer................................................................................................................... 34 Using the Logical Organizer............................................................................................................................................................ 34 Lab 10: Trends ........................................................................................................................................... 37 Running a Trend............................................................................................................................................................................. 37
  • 4. 4 of 40 Before you begin About this lab This session provides you with an opportunity to explore the Studio 5000 Logix Designer software and the ControlLogix hardware platform. The session steps through creating a new project, programming, and downloading to a controller. This lab takes approximately 105 minutes to complete. Tools & prerequisites Studio 5000 Logix Designer RSLinx Classic C:Lab FilesBasics LogixLogix_Basics_Lab_Demo_Project.ACD ControlLogix L85E demo box Tip Text – The text inside this gray box is supplemental information. This text can include FYIs, useful tips, and other related information
  • 5. 5 of 40 Lab 1: Creating a Project Tip Text – The text inside this gray box is supplemental information. This text can include FYIs, useful tips, and other related information This lab section should take roughly 20 minutes to complete. Launching Studio 5000 Configuration Software In this section of the lab, you will launch the Studio 5000 software, which will allow you to configure and program a controller. 1. Double-click on the Studio 5000 icon on the Desktop to launch Studio 5000 software The Studio 5000 Splash Screen appears Tip - To see what versions of Studio 5000 you have installed on your computer, select About under the Explore section.
  • 6. 6 of 40 Creating a New Controller Project In this portion of the lab, you will create an offline project using a ControlLogix controller. 2. Select New Project under the Create section. 3. When the New Project pop-up is displayed, select Logix and type ‘1756-L85E’ in the Search field. 4. Type ‘Intro_Lab_Control_Project’ into the name field. 5. Press the Next button. 6. When the Project Configuration window appears, fill it in as follows:
  • 7. 7 of 40 Select V31 Select 1756-A7 7-Slot ControlLogix Chassis Select Slot 0 Select No Protection Add a project description ‘Logix Basics Lab’ Click Finish
  • 8. 8 of 40 End of lab Controller Faceplate I/O Configuration Instructions toolbar Programming area Controller Organizer Controller Organizer and Logical Organizer Tabs Tasks, Programs, and Routines User Defined and Predefined Datatypes
  • 9. 9 of 40 Lab2: Configuring I/O We will now configure I/O for the project. To communicate with I/O modules you must add modules to the I/O Configuration folder (also referred to as the I/O tree). Adding ControlLogix I/O You will continue to use the project already open. 1. In the I/O Configuration Folder, right click on 1756 Backplane and select New Module. 2. The Select Module Type window appears. Type “IB16” in the search box. 3. Select the 1756-IB16IF module and click Create
  • 10. 10 of 40 Module Configuration Wizard Whenever you add an I/O module to the system you will go through the Module Configuration Wizard. The Wizard allows you to step through the entire configuration needed for a module. You can access this information later by double clicking on a module in the I/O Configuration folder or through the tag monitor/editor. With the Logix family, there are no dip switches or jumpers needed to configure I/O modules. I/O modules are software configured. This saves time when setting up a system. The configuration for all modules is part of the controller’s program and is downloaded to the module from the controller. This allows for ease of installation or replacement if an I/O module fails. 4. The new module window appears. Enter the Name Digital_Input and Slot 3 parameters as shown below.
  • 11. 11 of 40 5. Click on the Connection tab to observe the Requested Packet Interval data. We will leave the default at 20 milliseconds. Requested Packet Interval (RPI) The Requested Packet Interval specifies the period at which data is updated to and from the module. RPIs are configured in milliseconds. The range is .5ms to 750ms. 6. Click on OK to close the wizard. 7. In the Select Module Type window, type in “IF8” into the filter box and select the 1756-IF8I module.
  • 12. 12 of 40 8. Click on Create. The new module window appears. 9. Fill in the name “Analog_Input” and select Slot 5. 10. Select the Configuration tab to configure the analog module.
  • 13. 13 of 40 11. Select the Voltage radio button, and select the Input Range: 0V to 10V. 12. Click OK. 13. Close the Select Module Type dialogue. End of lab
  • 14. 14 of 40 Lab 3: Monitoring/Editing Tags In this lab, we will explore theTag Monitor/Editor in Studio 5000. . 1. From the Controller Organizer double-click on Controller Tags. Notice that there are several “Local” tags. These are the tags that were created when local I/O modules were added to the I/O Config. The tag Monitor/Editor window appears. Notice in the lower left corner of the window two tabs labeled Monitor Tags and Edit Tags as shown below. 2. Expand and explore the tags for the I/O modules by clicking the arrow icon . • :C - Configuration tags hold the module configuration and are designated by a “:C” in the tag name. • :I - Input tags have “:I” in the tag name. • :O - Output tags have a “:O” in the name. 3. Notice the different tags types and members.
  • 15. 15 of 40 4. Click on the tab Edit Tags. 5. Scroll to the bottom and add three BOOLEAN tags, START, STOP, and RUNNING as shown. 6. Right click on the Start tag you created and select Edit “Start” Properties 7. Select Alias as a type and notice that the Tag Properties window changed.
  • 16. 16 of 40 8. Click on the down arrow for Alias For. 9. Expand Local:3:I by clicking on the arrow and select all the way down tree to Local:3:I.Pt[0].Data.
  • 17. 17 of 40 Tag Properties will now appear as follows: START will now be aliased to Local:3:I.Pt[0].Data, which is the first input point on the 1756-IB16IF module. Notice in the edit tags windows the alias and alias for columns now have the address selected. Using the tag START will be equivalent to using the I/O tag “Local:3:I.Pt[0].data” End of lab
  • 18. 18 of 40 Lab 4: Adding Ladder Logic Adding Ladder Logic to the Main Routine In this section of the lab you will add some code. During the labs we will only utilize ladder logic programming, but Logix controllers also can be programmed using Function Block, Sequential Function Charts, and Structured Text. This allows selection of the programming language that best fits an application. 1. In the Controller Organizer expand the MainProgram folder by clicking on the arrow . Once expanded, the MainProgram will appear as shown below:
  • 19. 19 of 40 2. Double-click the MainRoutine icon and maximize the ladder window if it is not maximized. This will open the routine editor. An empty rung will already exist as shown below: The red color of the rung and the circled “x” next to the rung indicate the rung is incomplete. 3. From the instruction toolbar, left click and hold on the Examine On (XIC) instruction and drag the XIC onto rung 0 until the green dot appears. Release the mouse button at the location you wish to place your instruction. Verify your rung appears like the figure below:
  • 20. 20 of 40 4. From the instruction toolbar, left click and hold on the Output Energize (OTE) instruction onto the right of the rung FYI - If you place an instruction in the wrong location on a rung, simply click and hold on the instruction and drag it to the correct location. Verify the rung appears as follows: As you can see the free form editing in Studio 5000 can help speed development. You do not have to place an instruction and tie an address to it before you add the next instruction.
  • 21. 21 of 40 5. Double click on the “?” above the XIC instruction to get a drop down as shown. 6. Select the drop down and find and select the START tag 7. The rung should look as follows
  • 22. 22 of 40 8. Add RUNNING to the OTE so the rung appears as follows See, we can quickly and easily add instructions and tags using Logix Designer! End of lab
  • 23. 23 of 40 Lab 5: Tasks and programs 1. Right click on Tasks and select New Task 2. Create a new task of type periodic, name My Task, with a period of 250 ms, and OK to create the task. 3. Now, let’s add a program to it. Right click on the My_Task folder and select New Program.
  • 24. 24 of 40 4. Call the program My_Program and schedule in My_Task and click OK 5. Right click on My_Program and Add a new Routine. 6. Give the routine the name My_Routine and click OK. That’s all! We have now created a new task, program, and routine that will execute every 250 ms. We could now add any logic we wished. End of lab
  • 25. 25 of 40 Lab 6: Download and Run The layout of the L85E demo box we will be using. 1. Close the currently open project and save it as any name you like. We will not need this project again. We will now use a previously built project.
  • 26. 26 of 40 2. Open the file C:Lab FilesBasics LogixLogix_Basics_Lab_Demo_Project.ACD Notice that the project has three tasks. 3. Select Who Active as shown
  • 27. 27 of 40 4. Select the L85E in the who window that shows up and select Download 5. Put the controller into run mode if prompted, OR, put the controller in run mode from the Rem Prog tab. Verify the controller is in Remote Run mode as shown below .
  • 28. 28 of 40 6. Open the MainRoutine shown below and navigate to rung 4 7. Push and hold the DI0 button on the demo box and verify the rung looks like the following Notice the DO0 light is also on. It is wired to Local:4:O.Pt[0].Data 8. Open the Demo_Event_Routine. 9. Try any of the push buttons. Try push button DI2. Notice how the rungs behave.. You should see at least one of the ADD instructions increment when a button is pushed. 10. Right click on the Demo_Event_Task and select properties, then click configure tab. Notice how the event task has been configured..
  • 29. 29 of 40 11. Open the local tags of the Demo_Event_Program. Notice that the tag values can be viewed here too. Try pushing some buttons. 12. Open the Periodic Routine. Notice the Add instruction incrementing once a second. 13. Try viewing the properties of the periodic task and verify the period is 1 second. 14. Try pushing the DI3 push button several times. Notice how the DO3 light responds. It is wired to Local:4:O.Pt[3].Data End of lab
  • 30. 30 of 40 Lab 7: User Defined Types (UDT) Creating User Defined Types In this section of the lab you will create a custom User Defined Type (UDT). What is a UDT and what is it good for? A UDT is good for organizing related data into a single structure. A UDT allows a single tag to hold multiple members. Each member can be given a unique name to describe the data it holds. The members are accessed by the main tag name, followed by a period, followed by the member name. Continue to use the project already open. 1. Open the continuous task MainRoutine 2. Go to rung 3 Noted there is a tag based on a UDT already filled in. This tag has a member of gallons and a member of Liters. Notice that the values of the tags are shown on the instruction. The multiply instruction converts the number in gallons to liters. 3. Click on the number just below gallons, type “34” or any desired value, and press enter. Notice that the Liters value updates automatically. Monitoring UDT Tags 4. Double click the Parameters and Local Tags under the MainProgram and expand the Gallons_to_Liters tag. Notice the values are also shown here. Make sure to select the Monitor Tags tab. 5. The values for gallons can be modified directly in the monitor screen by changing the value in the Value column. Change the gallons value and watch that liters updates to corresponding value.
  • 31. 31 of 40 The UDT allows associated data to be stored under a single main tag instead of using completely separate tags. This makes it easier to keep track of data and keep it more organized. The UDT name itself can document what the data is for. End of lab
  • 32. 32 of 40 Lab 8: AOIs Using an AOI 1. Open the MainRoutine 2. Navigate to rung 6 3. .Turn the DI4 dial on and off. When the dial is on, notice that the Signal_Output tag alternates between 0 and 1 cause an output light to go on and off.
  • 33. 33 of 40 4. Right click on the Signal_Light instruction and select open logic. 5. Turn the dial DI4 again on and off. Watch the inner workings of the instruction in real time! 6. Close the Signal_Light Logic. 7. Right click on the instruction again and choose Open Definition 8. Feel free to explore the tabs, especially the Parameters and also Local Tags AOI’s allow code to be encapsulated into a single instruction. This allows common code and functionality to be clearly defined and easily reused. The AOI can be reused as many times as desired. Each AOI should typically have a unique backing tag. End of lab
  • 34. 34 of 40 Lab 9: Using Logical Organizer Using the Logical Organizer 1. Click on the Logical Organizer tab By default, all of the programs in the Controller Organizer are shown as an ungrouped list. Only the programs, and not the tasks, are shown. We can use the organizer to group the programs. We can use a “folder” object to group the programs. 2. To add a new folder, right click on the Logical Model folder -> Add -> New Folder 3. Enter the name ‘My_Demo_Box’ and click OK.
  • 35. 35 of 40 4. Click and drag the three programs onto My_Demo_Box so that they are grouped under the My_Demo_Box folder as shown. 5. Click on the Controller Organizer and notice that the programs and tasks haven’t changed.
  • 36. 36 of 40 Notice that the programs we are using to run the demo box are now grouped together. Anyone looking at the Logical Organizer will have a better idea that both program are being used to run the demo box. In general, the organizer is used to group the program code to model the physical or logical application. End of lab
  • 37. 37 of 40 Lab 10: Trends Trending Basic Trending in Studio 5000 allows you to view data sampled over a time period in a graphical display. Data is sampled at a periodic rate that is configurable from 1 millisecond to 30 minutes. Studio 5000 will allow you to create a trend and save it as part of your project file. Basic Trending has these constraints: you can trend data elements of type BOOL, SINT, INT, DINT, and REAL, you are limited to sampling eight unique data elements in a single trend. Running a Trend 1. From the Controller Organizer, expand Trends and select Demo_Trend_Sine_Wave. 2. Start the trend by clicking on the RUN button located toward the upper left of the Trend dialog box. 3. This trend has been set up to capture sine wave data. Watch as the sine wave builds
  • 38. 38 of 40 4. After you are satisfied it really is a sine wave, close the trend. 5. Open the trend Demo_Trend_Start_Stop 6. Run the trend Notice nothing happens 7. Now press the DI0 button Notice the trend start to run. This trend has been configured to start on the press of DI1. 8. Now press DI3. Notice there are some samples after the press of the button. The amount of samples stored before or after a press is configurable! 9. Stop the trend 10. Right click on the graph background and select “Chart Properties”. 11. Navigate to the Pens tab, the Start Trigger tab, and Stop Trigger tab and notice the configuration like that below. Feel free to explore! If you stopped the trend, try change some of the properties to see the effect they will have. Remember to apply and start the trend again!
  • 39. 39 of 40 By default, each tag will be independently scaled to its observed min/max values. If desired, the scaling options can be changed under the chart properties - Y axis tab. There are also other options in the trend properties such as a start and stop trigger and pen colors. 12. When you are finished investigating the trend, click Stop and close the trend window. End of lab
  • 40. 40 of 40Publication XXXX-XX###X-EN-P — Month Year Copyright© 2016 Rockwell Automation, Inc. All rights reserved. Supersedes Publication XXXX-XX###X-EN-P — Month Year