SlideShare a Scribd company logo
1 of 4
Download to read offline
CONNE US
SCAN WITH LAYAR
2014 | Volume 5 | Number 2
The Baker Hughes Magazine
Common Goals
Team concept heightens efficiency
gains in Colombian foothills
Drilling the “Eel”
New RSS drilling method
awakens Gabon’s mature field
H2O Pros
Strength of Water Management
organization runs deep
Revival in the
Heartland
New ESP technology extending
well life in near-abandoned
Mississippian Lime play
PhotoscourtesyofEquion
A study of the past leads to
the discovery of innovative
new solutions that deliver
a well program 25% more
cost efficient than that of the
operator’s original well plan.
It is also paving the way for a
sustainable future.
efine
esign
eliver
uplicateD
5 | | 6bakerhughes.com
ith some wells
in Colombia’s
hydrocarbon-rich
Casanare foothills
taking more than
340 days to drill
and complete, at costs up to USD 80 million,
it is easy to see why Equion Energia Ltd.
sought a performance breakthrough in its
well-planning operations.
Equion is a joint venture company between
Colombia’s state-owned oil company
Ecopetrol and Talisman Energy, a Canada-
based exploration and production company.
Equion acquired BP’s assets in Colombia
in January 2011 when BP sold all of its
oil and gas exploration, production, and
transportation holdings there. Among the
assets were interests in five producing
fields in the Casanare foothills of eastern
Colombia that, for more than 20 years, have
been among the world’s most challenging
drilling and completion environments.
With a limited amount of time to recover
hydrocarbon reserves in some of its contract
areas (some as soon as 2020), and with
operations reaching a performance plateau
with current technology, knowledge,
and experience, Equion embarked on
an ambitious, sustainable plan in 2011.
Equion’s objective for its Well of the Future
project was to optimize the processes
necessary to construct and complete the
challenging wells, with the ultimate goal of
making each well 30% more efficient.
By applying the Define, Measure, Analyze,
Improve, Control (DMAIC) continuous
improvement technique, and with Baker
Hughes as its technology partner, Equion has
drilled and completed the first well under the
new philosophy—a dual-purpose (producer/
injector) directional well—at significant
savings compared to the original plan.
Although an unfortunate sidetrack due to
a catastrophic failure of a third-party tool
occurred, the first well still resulted in 23%
savings in time (65 days) and 25.3% savings
in costs (USD 17.4 million).
“This was an extraordinary achievement,”
says Carlos Vargas, vice president of Drilling
and Completions for Equion. “The original
goal for the Well of the Future project
was to get a reduction in cost and time
of 30% in the first three wells. Achieving
the savings in time and in cost that we
did on the first well is a great starting
point for our project. Clearly, we have the
opportunity to continue improving our
performance and we will adjust our goals
in subsequent wells.”
Along with this operational breakthrough,
Vargas says the Well of the Future project
has created another milestone: it has
defined a new way for Equion and
Baker Hughes to work together.
“The DMAIC continuous improvement
philosophy created a common collaboration
and cooperation environment between our
companies,” Vargas says. “This new way to
work created a tremendous improvement
in our performance through innovative
solutions to better manage the critical
technical and operational challenges in
our complex, deep foothills wells.”
Identifying major challenges
The Colombian foothills are characterized by
their geological complexity of high-tectonic
stresses, borehole instability, and high
geological uncertainty, along with deep,
hard-rock, and low-porosity reservoirs.Taken
together, these present costly and challenging
drilling and completion conditions.
“Traditional well planning operations in
the area typically followed a sequential
process that is usually sufficient for
designing ‘normal’ wells, but they didn’t
encourage cross-discipline innovation in
such a challenging drilling environment,”
says Alexander Valdivieso, project manager
for Equion. “Therefore, we created a
dedicated multidisciplinary team with its
own workspace and gave it enough time
to analyze past well-planning operations
through an interdisciplinary approach
aligned with the DMAIC methodology.
The project began with the identification
and categorization of the most important
nonproductive time [NPT] and invisible
lost-time [ILT] sources for the area, followed
by the root cause analysis for the most
important ones.”
Ranking highest on the list of challenges
contributing to NPT and ILT were issues
related to wellbore stability, hole/casing
size relationship, fluid systems, drilling
inefficiencies, and running the 7-in. and
5-in. liners to total depth.
A series of peer-assist meetings followed
among Baker Hughes and Equion subject
matter experts, third parties, and partners,
where ideas and solutions for the main
problems in each discipline were captured
and compiled.
“Some 600 suggestions came from those
initial peer meetings,” says Mario Pacione,
project manager for Baker Hughes. “Once
the team received an actual well, we
categorized possible solutions based on
the particular risks and hazards identified
for that well, and delivered the final well
program, which included a totally new well
casing architecture.”
Applying the right solutions
„„ Borehole/casing sizes
Using technical and statistical analyses with
the assistance of engineering students from
a local university, the Well of the Future team
challenged the traditional casing design used
in the area with a new casing architecture
based on standard hole and casing sizes.
“Based on experience from another field,
Equion had started using nonconventional
hole sizes and running nonconventional-
sized casings and liners,” Pacione says.
“The conventional design had less clearance
between the open hole and the casing,
which has worked well in less-challenging
environments. However, in our case, this
resulted in additional costs because of the
need for special-sized drilling tools and
fairly long delivery times.”
The nonconventional-sized casing had also
introduced severe operational challenges
while trying to run equipment in a tight
hole across unstable formations. “Just by
changing the mechanical design, compared
to the previously planned well-spend using
the conventional way of thinking, we were
already expecting to save 13% in time and
almost 18.5% in costs,” Pacione says.
In addition, the team found that the use of
conventional hole and casing/liner sizes in
the upper sections decreased drilling time by
having less rock to remove. It also simplified
logistics and reduced equipment costs.
“From the beginning, Equion made it clear
that it wanted a technical partner to develop
fit-for-purpose technologies,” Pacione says.
“Not only did the Baker Hughes completion
teams design, build, and test new 7-in.
and 5-in. ZXP-D™
compression-set liner
packers, but they did it in record time.
This was a perfect example of how
Baker Hughes—not just the Well of the
Future team on the ground in Bogota—
was committed to this project.”
„„ Wellbore stability/fluid systems
The instability of the Carboneras formation
(overburden) is one of the biggest sources
of NPT. Stuck pipe, pack-off incidents,
liner-top packer failures, nonadherence to
procedures, and squeeze operations are
the main culprits, representing 53% of all
NPT in the Piedemonte field. Hard reaming,
extra circulation, and controlled rate of
penetration were major contributors to ILT.
However, after 20 years of drilling in the
foothills, the root cause for the instability of
the Carboneras formation remains unknown
mainly because of the lack of information
across this interval, which had no production
interest and had never been logged.
Because of these underlying circumstances,
the Well of the Future team realized that
real-time geomechanical services would be
critical to the project’s success.
The team, therefore, chose the Baker Hughes
SoundTrak™
acoustic logging-while-
drilling service, which enables real-time
pore pressure prediction and geological
characterization.The team also introduced
the Baker Hughes OnTrak™
measurement-
while-drilling service, which delivers
resistivity data for pore pressure prediction
and identification of weak zones, along
with azimuthal gamma ray data, which
enables dip picking even in larger hole sizes.
This real-time data was used to identify
bed boundaries and formation dips, aid
directional control, and update the geological
and geomechanical models to help determine
the correct mud weights for hole
stability in an assertive
manner.
W
This new way to work created a tremendous
improvement in our performance through innovative
solutions to better manage the critical technical and
operational challenges in our complex, deep foothills wells.
“
Carlos Vargas, vice president of Drilling and Completions for Equion
”
D M A I C
[ Define, Measure, Analyze, Improve, Control ]
| 8bakerhughes.com7 |
“Real-time drilling geomechanics
services verified the existence not only of
microfractures but also of natural fractures
of unknown sizes in the upper sections,” says
Carlos Almeida, a Baker Hughes real-time
drilling geomechanics engineer assigned to
the project. “One of the potential causes
of the instability was the fluid invasion/
lubrication of these microfractures,
particularly while using oil-based muds.
Considering that, our fluids experts
formulated a sealing strategy based on a
wide coverage of particle sizes in the mud
system, from ultrafine nano-materials for
sealing microfractures to a variety of coarse
materials for sealing natural fractures.”
Jairo Peñuela, fluids advisor for Equion
Energia, adds, “The introduction of the
nanotechnology also resulted in a good
cost and benefit replacement for traditional
graphites. This technology was part of a new
stability strategy implemented in the area,
which included the use of fluids with tight
filtrate, wide selection of sealing agents
with broad particle-size diameter, use of
asphalts, and correct mud weight. All of this
contributed to delivering one of the best
records in terms of borehole stability ever
achieved in the field, especially along the
12¼-in. and 8½-in. sections.”
The 8½-in. section was drilled through a
4,000-ft [1219-m] overlapped and folded-
down section of the Florena structure for
more than 100 days with no instability
issues. “We proved that the correct mud
density and sealing strategy were the most
important factors in controlling the borehole
stability,” Peñuela says.
„„ Drilling services/drill bits/liners
Drilling challenges in the 17,272-ft (5265-m)
well were numerous. First, high formation
dipping tendencies in the overburden
affected directional control. To counter this,
the Baker Hughes drilling team introduced
to the Colombia market the 26-in. AutoTrak™
rotary steerable system (RSS), which helps
control verticality without limiting drilling
parameters such as weight-on-bit (WOB).
Together, with the Baker Hughes Kymera™
hybrid drill bit, drilling performance
improved 10% in the 26-in. section.
Hybrid bit technology combines advanced
technologies from roller cone and PDC bits
to address difficult-to-drill formations where
neither of the conventional bit technologies
alone delivers satisfactory performance.
Better borehole quality was achieved in
the other sections, using the Baker Hughes
AutoTrak™
G3™
RSS with longer-gauge
PDC bits, which reduced hole spiraling. This
assisted in reducing torque and drag on
subsequent well operations.
In addition, the team deployed the
Baker Hughes CoPilot™
real-time drilling
optimization service, which captures and
analyzes downhole data concerning WOB,
torque, bottomhole assembly bending
moment, annular pressure data (for
equivalent circulating density/hole cleaning
monitoring), and other downhole conditions.
This service was supported by application
engineers in the Baker Hughes BEACON™
advisory center and in Equion’s Smart Room,
both located in Bogota.
Problems associated with running liners to
section total depth was another historical
major source of NPT and ILT. “This
happened because of the hard reaming
that normally was needed due to poor hole
quality and hole spiraling and/or borehole
instability,” says Juan Diego Santander, an
Equion drilling engineer. “In several cases,
the hard-reaming operation resulted in
damage to the top liner packer with long
remedial works and sometimes liners could
not be run to total depth due to excessive
torque that exceeded the ratings of the
liner couplings.”
To alleviate these problems, the team
proposed the use of the ZXP-D liner hanger
equipment and the SDD™
liner hanger
system with high-torque connections
for tubulars. “This technology had been
successfully used in the area in a different
size, but the design did not exist for the
required sizes of this particular application
[7-in. x 95
/8-in. and 5-in. x 7-in.],” Pacione
says. “Once again, the Baker Hughes
completions team rose to the challenge,
and, in record time, created new designs,
tested, approved, built, and delivered
them—another key component of this
successful project.”
The future
Equion’s license for this field expires in six
years, so there is limited time to drill the
remaining wells. The Well of the Future
team is adding more subject matter experts,
geologists, reservoir engineers, and other
people with the right skillsets to target a
next goal.
“The team’s goal was on improving well
construction,” Vargas says. “As we move
into the second phase of the project, we are
setting the more ambitious goal of focusing
on productivity based on a sustainable
performance in the construction of the well.
During the execution and evaluation of the
first well, we were able to identify several
areas of improvement and lessons learned
that we will incorporate into our plans to
evolve the concept going forward.
“The Well of the Future is the beginning of
a new collaboration—a cooperative way
to work between Equion and Baker Hughes
in which we are one team looking for ways
to share our goals based on our needs.
By applying this new way to work, we
can envision a vast array of opportunities
opening up for our companies.”
>> Mario Pacione (left) and
Alexander Valdivieso, Well of
the Future project managers
for Baker Hughes and
Equion, respectively
Just by changing the mechanical design, compared to
the previously planned well-spend using the conventional
way of thinking, we were already expecting to save
13% in time and almost 18.5% in costs.
“
Mario Pacione, project manager for Baker Hughes
”
| 10bakerhughes.com9 |

More Related Content

What's hot

jerry-pinder-resume
jerry-pinder-resumejerry-pinder-resume
jerry-pinder-resumeJerry Pinder
 
20160704 Carline_Andrew
20160704 Carline_Andrew20160704 Carline_Andrew
20160704 Carline_AndrewAndrew Carline
 
Tim Rathsam Work History
Tim Rathsam Work HistoryTim Rathsam Work History
Tim Rathsam Work HistoryTim Rathsam
 
Bakken Artificial Lift & Production Optimization Congress 2014
Bakken Artificial Lift & Production Optimization Congress 2014 Bakken Artificial Lift & Production Optimization Congress 2014
Bakken Artificial Lift & Production Optimization Congress 2014 marketinglbcg
 
CarbonNet storage site characterisation and selection process
CarbonNet storage site characterisation and selection processCarbonNet storage site characterisation and selection process
CarbonNet storage site characterisation and selection processGlobal CCS Institute
 
RESUME_ARCHITH_SANKER_ATKINS
RESUME_ARCHITH_SANKER_ATKINSRESUME_ARCHITH_SANKER_ATKINS
RESUME_ARCHITH_SANKER_ATKINSarchith sanker
 
Workover Optimization & Horizontal Well Intervention 2014
Workover Optimization & Horizontal Well Intervention 2014Workover Optimization & Horizontal Well Intervention 2014
Workover Optimization & Horizontal Well Intervention 2014LBCG
 
underground_4-page_12142015_LR
underground_4-page_12142015_LRunderground_4-page_12142015_LR
underground_4-page_12142015_LRAnne Fellini
 
Global Status of CCS: 2016. Saline Aquifer Storage Performance at the Quest C...
Global Status of CCS: 2016. Saline Aquifer Storage Performance at the Quest C...Global Status of CCS: 2016. Saline Aquifer Storage Performance at the Quest C...
Global Status of CCS: 2016. Saline Aquifer Storage Performance at the Quest C...Global CCS Institute
 
TJ Dickey Resume.docx complete
TJ Dickey Resume.docx completeTJ Dickey Resume.docx complete
TJ Dickey Resume.docx completeTj Dickey
 
Resume - RJ Roof_Rev1_21Oct16
Resume - RJ Roof_Rev1_21Oct16Resume - RJ Roof_Rev1_21Oct16
Resume - RJ Roof_Rev1_21Oct16Ron Roof
 
Institute’s Americas office launches The Global Status of CCS: 2016 at the Cl...
Institute’s Americas office launches The Global Status of CCS: 2016 at the Cl...Institute’s Americas office launches The Global Status of CCS: 2016 at the Cl...
Institute’s Americas office launches The Global Status of CCS: 2016 at the Cl...Global CCS Institute
 
Peter Bartlett - Personal CV (March 2016)
Peter Bartlett - Personal CV (March 2016)Peter Bartlett - Personal CV (March 2016)
Peter Bartlett - Personal CV (March 2016)Bartlett (Perth)
 

What's hot (20)

jerry-pinder-resume
jerry-pinder-resumejerry-pinder-resume
jerry-pinder-resume
 
Highbank Resources 43-101 Technical Report
Highbank Resources 43-101 Technical Report Highbank Resources 43-101 Technical Report
Highbank Resources 43-101 Technical Report
 
20160704 Carline_Andrew
20160704 Carline_Andrew20160704 Carline_Andrew
20160704 Carline_Andrew
 
Tim Rathsam Work History
Tim Rathsam Work HistoryTim Rathsam Work History
Tim Rathsam Work History
 
Bakken Artificial Lift & Production Optimization Congress 2014
Bakken Artificial Lift & Production Optimization Congress 2014 Bakken Artificial Lift & Production Optimization Congress 2014
Bakken Artificial Lift & Production Optimization Congress 2014
 
Topside
TopsideTopside
Topside
 
CarbonNet storage site characterisation and selection process
CarbonNet storage site characterisation and selection processCarbonNet storage site characterisation and selection process
CarbonNet storage site characterisation and selection process
 
RESUME_ARCHITH_SANKER_ATKINS
RESUME_ARCHITH_SANKER_ATKINSRESUME_ARCHITH_SANKER_ATKINS
RESUME_ARCHITH_SANKER_ATKINS
 
Workover Optimization & Horizontal Well Intervention 2014
Workover Optimization & Horizontal Well Intervention 2014Workover Optimization & Horizontal Well Intervention 2014
Workover Optimization & Horizontal Well Intervention 2014
 
underground_4-page_12142015_LR
underground_4-page_12142015_LRunderground_4-page_12142015_LR
underground_4-page_12142015_LR
 
Curriculum Vitae
Curriculum VitaeCurriculum Vitae
Curriculum Vitae
 
Global Status of CCS: 2016. Saline Aquifer Storage Performance at the Quest C...
Global Status of CCS: 2016. Saline Aquifer Storage Performance at the Quest C...Global Status of CCS: 2016. Saline Aquifer Storage Performance at the Quest C...
Global Status of CCS: 2016. Saline Aquifer Storage Performance at the Quest C...
 
TJ Dickey Resume.docx complete
TJ Dickey Resume.docx completeTJ Dickey Resume.docx complete
TJ Dickey Resume.docx complete
 
Resume - RJ Roof_Rev1_21Oct16
Resume - RJ Roof_Rev1_21Oct16Resume - RJ Roof_Rev1_21Oct16
Resume - RJ Roof_Rev1_21Oct16
 
Tringale Resume 9-2-14
Tringale Resume 9-2-14Tringale Resume 9-2-14
Tringale Resume 9-2-14
 
Institute’s Americas office launches The Global Status of CCS: 2016 at the Cl...
Institute’s Americas office launches The Global Status of CCS: 2016 at the Cl...Institute’s Americas office launches The Global Status of CCS: 2016 at the Cl...
Institute’s Americas office launches The Global Status of CCS: 2016 at the Cl...
 
Balanced Mix Design & Cracking Test
Balanced Mix Design & Cracking TestBalanced Mix Design & Cracking Test
Balanced Mix Design & Cracking Test
 
Mohamed Fahim 2015
Mohamed Fahim 2015Mohamed Fahim 2015
Mohamed Fahim 2015
 
Peter Bartlett - Personal CV (March 2016)
Peter Bartlett - Personal CV (March 2016)Peter Bartlett - Personal CV (March 2016)
Peter Bartlett - Personal CV (March 2016)
 
SHREYAS__SABNIS CV
SHREYAS__SABNIS CVSHREYAS__SABNIS CV
SHREYAS__SABNIS CV
 

Similar to CONNEXUS_WoF_2

CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1Dan Caouette
 
Benefit from geotube stacking technology & analysis
Benefit from geotube stacking technology & analysisBenefit from geotube stacking technology & analysis
Benefit from geotube stacking technology & analysispjgomezd
 
baker hughes Annual Report 2002
baker hughes  Annual Report 2002baker hughes  Annual Report 2002
baker hughes Annual Report 2002finance26
 
EOR vs. Storage, Ed Steadman, EERC
EOR vs. Storage, Ed Steadman, EERCEOR vs. Storage, Ed Steadman, EERC
EOR vs. Storage, Ed Steadman, EERCGlobal CCS Institute
 
2016 Harry H. Mellon Awards in Job Order Contracting | Gordian
2016 Harry H. Mellon Awards in Job Order Contracting | Gordian2016 Harry H. Mellon Awards in Job Order Contracting | Gordian
2016 Harry H. Mellon Awards in Job Order Contracting | GordianGordian
 
Rosental Alex 19 Oct09
Rosental Alex 19 Oct09Rosental Alex 19 Oct09
Rosental Alex 19 Oct09arosental
 
The Cleaner Seas Project Alliance
The Cleaner Seas Project AllianceThe Cleaner Seas Project Alliance
The Cleaner Seas Project AllianceUGL Limited
 
Highlight Projects - R Petrinack
Highlight Projects - R PetrinackHighlight Projects - R Petrinack
Highlight Projects - R PetrinackRick Petrinack
 
Improving Efficiency Tight Gas
Improving Efficiency Tight GasImproving Efficiency Tight Gas
Improving Efficiency Tight GasNeil Harvey
 
Goliat Field Trip
Goliat Field TripGoliat Field Trip
Goliat Field TripEni
 
Hydrovac Contractors Bay Area Unleashing the Power of Hydro Excavation.pdf
Hydrovac Contractors Bay Area Unleashing the Power of Hydro Excavation.pdfHydrovac Contractors Bay Area Unleashing the Power of Hydro Excavation.pdf
Hydrovac Contractors Bay Area Unleashing the Power of Hydro Excavation.pdfTec
 

Similar to CONNEXUS_WoF_2 (20)

CONNEXUS_WoF_1
CONNEXUS_WoF_1CONNEXUS_WoF_1
CONNEXUS_WoF_1
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1
 
Benefit from geotube stacking technology & analysis
Benefit from geotube stacking technology & analysisBenefit from geotube stacking technology & analysis
Benefit from geotube stacking technology & analysis
 
baker hughes Annual Report 2002
baker hughes  Annual Report 2002baker hughes  Annual Report 2002
baker hughes Annual Report 2002
 
EOR vs. Storage, Ed Steadman, EERC
EOR vs. Storage, Ed Steadman, EERCEOR vs. Storage, Ed Steadman, EERC
EOR vs. Storage, Ed Steadman, EERC
 
2016 Harry H. Mellon Awards in Job Order Contracting | Gordian
2016 Harry H. Mellon Awards in Job Order Contracting | Gordian2016 Harry H. Mellon Awards in Job Order Contracting | Gordian
2016 Harry H. Mellon Awards in Job Order Contracting | Gordian
 
Roy Shilling
Roy ShillingRoy Shilling
Roy Shilling
 
Rosental Alex 19 Oct09
Rosental Alex 19 Oct09Rosental Alex 19 Oct09
Rosental Alex 19 Oct09
 
The Cleaner Seas Project Alliance
The Cleaner Seas Project AllianceThe Cleaner Seas Project Alliance
The Cleaner Seas Project Alliance
 
Capston
CapstonCapston
Capston
 
CaseStudy-ECOFOXl
CaseStudy-ECOFOXlCaseStudy-ECOFOXl
CaseStudy-ECOFOXl
 
[IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme
[IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme [IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme
[IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme
 
Highlight Projects - R Petrinack
Highlight Projects - R PetrinackHighlight Projects - R Petrinack
Highlight Projects - R Petrinack
 
project management UOC-1
project management UOC-1project management UOC-1
project management UOC-1
 
Improving Efficiency Tight Gas
Improving Efficiency Tight GasImproving Efficiency Tight Gas
Improving Efficiency Tight Gas
 
Goliat Field Trip
Goliat Field TripGoliat Field Trip
Goliat Field Trip
 
Siw Issue 3
Siw Issue 3Siw Issue 3
Siw Issue 3
 
RailWorks-Today-April-2016-L
RailWorks-Today-April-2016-LRailWorks-Today-April-2016-L
RailWorks-Today-April-2016-L
 
Hydrovac Contractors Bay Area Unleashing the Power of Hydro Excavation.pdf
Hydrovac Contractors Bay Area Unleashing the Power of Hydro Excavation.pdfHydrovac Contractors Bay Area Unleashing the Power of Hydro Excavation.pdf
Hydrovac Contractors Bay Area Unleashing the Power of Hydro Excavation.pdf
 
Olmsted SAME Article
Olmsted SAME ArticleOlmsted SAME Article
Olmsted SAME Article
 

CONNEXUS_WoF_2

  • 1. CONNE US SCAN WITH LAYAR 2014 | Volume 5 | Number 2 The Baker Hughes Magazine Common Goals Team concept heightens efficiency gains in Colombian foothills Drilling the “Eel” New RSS drilling method awakens Gabon’s mature field H2O Pros Strength of Water Management organization runs deep Revival in the Heartland New ESP technology extending well life in near-abandoned Mississippian Lime play
  • 2. PhotoscourtesyofEquion A study of the past leads to the discovery of innovative new solutions that deliver a well program 25% more cost efficient than that of the operator’s original well plan. It is also paving the way for a sustainable future. efine esign eliver uplicateD 5 | | 6bakerhughes.com
  • 3. ith some wells in Colombia’s hydrocarbon-rich Casanare foothills taking more than 340 days to drill and complete, at costs up to USD 80 million, it is easy to see why Equion Energia Ltd. sought a performance breakthrough in its well-planning operations. Equion is a joint venture company between Colombia’s state-owned oil company Ecopetrol and Talisman Energy, a Canada- based exploration and production company. Equion acquired BP’s assets in Colombia in January 2011 when BP sold all of its oil and gas exploration, production, and transportation holdings there. Among the assets were interests in five producing fields in the Casanare foothills of eastern Colombia that, for more than 20 years, have been among the world’s most challenging drilling and completion environments. With a limited amount of time to recover hydrocarbon reserves in some of its contract areas (some as soon as 2020), and with operations reaching a performance plateau with current technology, knowledge, and experience, Equion embarked on an ambitious, sustainable plan in 2011. Equion’s objective for its Well of the Future project was to optimize the processes necessary to construct and complete the challenging wells, with the ultimate goal of making each well 30% more efficient. By applying the Define, Measure, Analyze, Improve, Control (DMAIC) continuous improvement technique, and with Baker Hughes as its technology partner, Equion has drilled and completed the first well under the new philosophy—a dual-purpose (producer/ injector) directional well—at significant savings compared to the original plan. Although an unfortunate sidetrack due to a catastrophic failure of a third-party tool occurred, the first well still resulted in 23% savings in time (65 days) and 25.3% savings in costs (USD 17.4 million). “This was an extraordinary achievement,” says Carlos Vargas, vice president of Drilling and Completions for Equion. “The original goal for the Well of the Future project was to get a reduction in cost and time of 30% in the first three wells. Achieving the savings in time and in cost that we did on the first well is a great starting point for our project. Clearly, we have the opportunity to continue improving our performance and we will adjust our goals in subsequent wells.” Along with this operational breakthrough, Vargas says the Well of the Future project has created another milestone: it has defined a new way for Equion and Baker Hughes to work together. “The DMAIC continuous improvement philosophy created a common collaboration and cooperation environment between our companies,” Vargas says. “This new way to work created a tremendous improvement in our performance through innovative solutions to better manage the critical technical and operational challenges in our complex, deep foothills wells.” Identifying major challenges The Colombian foothills are characterized by their geological complexity of high-tectonic stresses, borehole instability, and high geological uncertainty, along with deep, hard-rock, and low-porosity reservoirs.Taken together, these present costly and challenging drilling and completion conditions. “Traditional well planning operations in the area typically followed a sequential process that is usually sufficient for designing ‘normal’ wells, but they didn’t encourage cross-discipline innovation in such a challenging drilling environment,” says Alexander Valdivieso, project manager for Equion. “Therefore, we created a dedicated multidisciplinary team with its own workspace and gave it enough time to analyze past well-planning operations through an interdisciplinary approach aligned with the DMAIC methodology. The project began with the identification and categorization of the most important nonproductive time [NPT] and invisible lost-time [ILT] sources for the area, followed by the root cause analysis for the most important ones.” Ranking highest on the list of challenges contributing to NPT and ILT were issues related to wellbore stability, hole/casing size relationship, fluid systems, drilling inefficiencies, and running the 7-in. and 5-in. liners to total depth. A series of peer-assist meetings followed among Baker Hughes and Equion subject matter experts, third parties, and partners, where ideas and solutions for the main problems in each discipline were captured and compiled. “Some 600 suggestions came from those initial peer meetings,” says Mario Pacione, project manager for Baker Hughes. “Once the team received an actual well, we categorized possible solutions based on the particular risks and hazards identified for that well, and delivered the final well program, which included a totally new well casing architecture.” Applying the right solutions „„ Borehole/casing sizes Using technical and statistical analyses with the assistance of engineering students from a local university, the Well of the Future team challenged the traditional casing design used in the area with a new casing architecture based on standard hole and casing sizes. “Based on experience from another field, Equion had started using nonconventional hole sizes and running nonconventional- sized casings and liners,” Pacione says. “The conventional design had less clearance between the open hole and the casing, which has worked well in less-challenging environments. However, in our case, this resulted in additional costs because of the need for special-sized drilling tools and fairly long delivery times.” The nonconventional-sized casing had also introduced severe operational challenges while trying to run equipment in a tight hole across unstable formations. “Just by changing the mechanical design, compared to the previously planned well-spend using the conventional way of thinking, we were already expecting to save 13% in time and almost 18.5% in costs,” Pacione says. In addition, the team found that the use of conventional hole and casing/liner sizes in the upper sections decreased drilling time by having less rock to remove. It also simplified logistics and reduced equipment costs. “From the beginning, Equion made it clear that it wanted a technical partner to develop fit-for-purpose technologies,” Pacione says. “Not only did the Baker Hughes completion teams design, build, and test new 7-in. and 5-in. ZXP-D™ compression-set liner packers, but they did it in record time. This was a perfect example of how Baker Hughes—not just the Well of the Future team on the ground in Bogota— was committed to this project.” „„ Wellbore stability/fluid systems The instability of the Carboneras formation (overburden) is one of the biggest sources of NPT. Stuck pipe, pack-off incidents, liner-top packer failures, nonadherence to procedures, and squeeze operations are the main culprits, representing 53% of all NPT in the Piedemonte field. Hard reaming, extra circulation, and controlled rate of penetration were major contributors to ILT. However, after 20 years of drilling in the foothills, the root cause for the instability of the Carboneras formation remains unknown mainly because of the lack of information across this interval, which had no production interest and had never been logged. Because of these underlying circumstances, the Well of the Future team realized that real-time geomechanical services would be critical to the project’s success. The team, therefore, chose the Baker Hughes SoundTrak™ acoustic logging-while- drilling service, which enables real-time pore pressure prediction and geological characterization.The team also introduced the Baker Hughes OnTrak™ measurement- while-drilling service, which delivers resistivity data for pore pressure prediction and identification of weak zones, along with azimuthal gamma ray data, which enables dip picking even in larger hole sizes. This real-time data was used to identify bed boundaries and formation dips, aid directional control, and update the geological and geomechanical models to help determine the correct mud weights for hole stability in an assertive manner. W This new way to work created a tremendous improvement in our performance through innovative solutions to better manage the critical technical and operational challenges in our complex, deep foothills wells. “ Carlos Vargas, vice president of Drilling and Completions for Equion ” D M A I C [ Define, Measure, Analyze, Improve, Control ] | 8bakerhughes.com7 |
  • 4. “Real-time drilling geomechanics services verified the existence not only of microfractures but also of natural fractures of unknown sizes in the upper sections,” says Carlos Almeida, a Baker Hughes real-time drilling geomechanics engineer assigned to the project. “One of the potential causes of the instability was the fluid invasion/ lubrication of these microfractures, particularly while using oil-based muds. Considering that, our fluids experts formulated a sealing strategy based on a wide coverage of particle sizes in the mud system, from ultrafine nano-materials for sealing microfractures to a variety of coarse materials for sealing natural fractures.” Jairo Peñuela, fluids advisor for Equion Energia, adds, “The introduction of the nanotechnology also resulted in a good cost and benefit replacement for traditional graphites. This technology was part of a new stability strategy implemented in the area, which included the use of fluids with tight filtrate, wide selection of sealing agents with broad particle-size diameter, use of asphalts, and correct mud weight. All of this contributed to delivering one of the best records in terms of borehole stability ever achieved in the field, especially along the 12¼-in. and 8½-in. sections.” The 8½-in. section was drilled through a 4,000-ft [1219-m] overlapped and folded- down section of the Florena structure for more than 100 days with no instability issues. “We proved that the correct mud density and sealing strategy were the most important factors in controlling the borehole stability,” Peñuela says. „„ Drilling services/drill bits/liners Drilling challenges in the 17,272-ft (5265-m) well were numerous. First, high formation dipping tendencies in the overburden affected directional control. To counter this, the Baker Hughes drilling team introduced to the Colombia market the 26-in. AutoTrak™ rotary steerable system (RSS), which helps control verticality without limiting drilling parameters such as weight-on-bit (WOB). Together, with the Baker Hughes Kymera™ hybrid drill bit, drilling performance improved 10% in the 26-in. section. Hybrid bit technology combines advanced technologies from roller cone and PDC bits to address difficult-to-drill formations where neither of the conventional bit technologies alone delivers satisfactory performance. Better borehole quality was achieved in the other sections, using the Baker Hughes AutoTrak™ G3™ RSS with longer-gauge PDC bits, which reduced hole spiraling. This assisted in reducing torque and drag on subsequent well operations. In addition, the team deployed the Baker Hughes CoPilot™ real-time drilling optimization service, which captures and analyzes downhole data concerning WOB, torque, bottomhole assembly bending moment, annular pressure data (for equivalent circulating density/hole cleaning monitoring), and other downhole conditions. This service was supported by application engineers in the Baker Hughes BEACON™ advisory center and in Equion’s Smart Room, both located in Bogota. Problems associated with running liners to section total depth was another historical major source of NPT and ILT. “This happened because of the hard reaming that normally was needed due to poor hole quality and hole spiraling and/or borehole instability,” says Juan Diego Santander, an Equion drilling engineer. “In several cases, the hard-reaming operation resulted in damage to the top liner packer with long remedial works and sometimes liners could not be run to total depth due to excessive torque that exceeded the ratings of the liner couplings.” To alleviate these problems, the team proposed the use of the ZXP-D liner hanger equipment and the SDD™ liner hanger system with high-torque connections for tubulars. “This technology had been successfully used in the area in a different size, but the design did not exist for the required sizes of this particular application [7-in. x 95 /8-in. and 5-in. x 7-in.],” Pacione says. “Once again, the Baker Hughes completions team rose to the challenge, and, in record time, created new designs, tested, approved, built, and delivered them—another key component of this successful project.” The future Equion’s license for this field expires in six years, so there is limited time to drill the remaining wells. The Well of the Future team is adding more subject matter experts, geologists, reservoir engineers, and other people with the right skillsets to target a next goal. “The team’s goal was on improving well construction,” Vargas says. “As we move into the second phase of the project, we are setting the more ambitious goal of focusing on productivity based on a sustainable performance in the construction of the well. During the execution and evaluation of the first well, we were able to identify several areas of improvement and lessons learned that we will incorporate into our plans to evolve the concept going forward. “The Well of the Future is the beginning of a new collaboration—a cooperative way to work between Equion and Baker Hughes in which we are one team looking for ways to share our goals based on our needs. By applying this new way to work, we can envision a vast array of opportunities opening up for our companies.” >> Mario Pacione (left) and Alexander Valdivieso, Well of the Future project managers for Baker Hughes and Equion, respectively Just by changing the mechanical design, compared to the previously planned well-spend using the conventional way of thinking, we were already expecting to save 13% in time and almost 18.5% in costs. “ Mario Pacione, project manager for Baker Hughes ” | 10bakerhughes.com9 |