SlideShare a Scribd company logo
1 of 3
Rick Petrinack
Project Manager
Highlight Projects for Discussion:
Remote Bank Facility Construction
The client identified a need to replace an ageing owned facility which was not cost feasible to repair
and expand. Adding to the challenge was an accelerated replacement schedule and a very remote NW
British Columbia coastal location.
The project requirements ruled out most traditional redevelopment approaches. As such it was
recommended that a prefabricated modular structure ready to install onto a completed foundation be
considered. However local roadways were far too treacherous to support the transport of a modular
structure. The prefabricated facility was loaded onto a barge in the port of Vancouver for transport to
local port facilities near the site. Where final transportation of the structure was completed by more
traditional means. Local trades completed the final construction details and site development. The
opportunity to reduce freight and installation costs of the client trade fixtures, fixed assets and
technical equipment was attained by completing as much as possible prior to shipment from the port
of Vancouver. All of the unique and challenging requirements of the project were met along with
providing the client with a value added facility.
Budget 3.5 M
Construction Conflict Resolution
Midway through the construction of a 2 story 16,000 sq/ft 3.5 M early childhood facility the owner
discovered that the project schedule had slipped by 6 months, was significantly over budget and
communication between the primary stakeholders had totally broken down. The owner requested 3rd
party consultation to re establish stakeholder communication and control over the project. An active
communication and month long embedment was undertaken to establish the key road blocks, design
and implement a plan to regain control. The personal, communicative approach re-established
working relationships between the stakeholders and provided a bridge to resolve disputes and
disagreements. The collaborative plan was implemented and regained control over the schedule,
budget and working relationships. Additionally a dispute register and mandatory attendance at weekly
site meetings improved project performance. Schedule timing was recovered, cost over-runs were
rationalized and working relationships were mended paving the way for future developments.
Seniors Complex Environmental Remediation/
Reconstruction
The owners of a 4 story 200 suite s extended stay seniors facility commissioned a building envelope
investigation the results of which confirmed extensive water intrusion and subsequent mold growth.
The impact to clients, especially those whose immune systems were compromised was extensive. The
challenges were a) maintaining a minimum occupancy rate of 80% for the landlord, b) minimizing
exposure to residents and staff, c) maintaining consistent and clear communication to all stakeholders.
Planning and execution of the 16 month project was successfully completed by a) establishing three
working groups who reported to the project manager they were i) resident contact group, ii) owner
contact group and iii) a facility group, b) investing in extensive upfront planning with the three
working groups, c) concentrating work on one working floor and one swing floor at a time,
d) amalgamating all of the stakeholder information, e) constant regular non stop communication with
the stakeholders. Remediation, reconstruction and repairs to the building envelope were completed on
schedule with minimal resident disruption.
Budget 4.5 M
Bank Facility Environmental Remediation/
Reconstruction
Results of a planned Indoor Air Quality Assessment noted minimally elevated PCB levels within a
branch facility. While the levels were well within acceptable guidelines any indication proved to be
unacceptable for the client and options for addressing the condition were sought. This large suburban
shopping centre branch is sandwiched in-between other tenants in a centre with no interior cru or
exterior pad relocation opportunities temporary or otherwise. Additionally options for relocation within
the immediate area or considering a branch closure were not acceptable. As a result determining the
source and remediation of the offending PCB’s would have to be addressed in place. The single
guiding consideration going forward was limiting any additional exposure physical and emotional to
clients and staff. As such additional intrusive testing was completed after regular business hours which
proved to be challenging. Traditional exploratory soil sampling bore holes were required throughout
the facility requiring extensive facility cleaning, repairs and air quality testing with on site results to
successfully reopen for business daily during the investigative process. Once the source of
contamination was identified an exposure limiting remediation process needed to be designed. To do
so a non descript entrance structure was constructed on an available exterior wall of the branch inside
which an access shaft was excavated to below floor slab level. This shaft provided an entry point to
under slab spaces for excavation equipment and manpower while also allowing an exit point for
contaminated soils. Contaminated soils were removed from site nightly to a remote secured transfer
area prior to disposal. Once remediation and final air quality testing was completed the excavated
area was stabilized and outfitted with a ground water removal system and an access port for regular
air quality testing. The access shaft was backfilled and removalof entrance structure completed. All
work was completed to required regulations and standards without exposing clients or staff to unsafe
levels of PCB’s or emotional stress. Zero days were lost while completing this project as a result clients
and staff were able to conduct business as normal.
Budget 5 M
Bank Facilities Closure Program
The client had decided to implement an aggressive branch closure program to divest themselves of
unproductive and ageing infrastructure. The program covered an extremely large geographical area
where traditionally four facility managers were assigned with a lengthy, involved and detailed process.
The client began to express their displeasure with the lack of performance not only with the branch
closures but with other core areas of the facility manager responsibilities. At risk was a crucial client
relationship, possible default of a contract and the damage to a national company reputation. Along
with the personal toll it was taking on the facility managers themselves. The proposed solution to
restructure the branch closures as a program which could then be better managed by a single point of
contact. This approach allowed for greater attention to detail, process and on time completions the
client was anticipating. Additionally some unplanned cost savings and a more manageable work load
for the facility management group as a result.
Budget 6.5 M
Remote Bank Facility Construction

More Related Content

What's hot

Roy Ong CV (2015)
Roy Ong CV (2015)Roy Ong CV (2015)
Roy Ong CV (2015)Roy Ong
 
ENR MOUNTAIN STATES 2013 BEST PROJECTS AWARD
ENR MOUNTAIN STATES 2013 BEST PROJECTS AWARDENR MOUNTAIN STATES 2013 BEST PROJECTS AWARD
ENR MOUNTAIN STATES 2013 BEST PROJECTS AWARDPhilip Tunnah
 
KBE Laboratories 2011
KBE Laboratories 2011 KBE Laboratories 2011
KBE Laboratories 2011 charkins
 
R mayers_CV 2302
R mayers_CV 2302R mayers_CV 2302
R mayers_CV 2302Rhod Mayers
 
Managing The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy ProjectsManaging The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy Projectsmtingle
 
Dale Buzzelli Resume
Dale Buzzelli ResumeDale Buzzelli Resume
Dale Buzzelli ResumeDale Buzzelli
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project PresentationWayne Holley
 
TJJ Linked In Resume 3.20.16
TJJ Linked In Resume 3.20.16TJJ Linked In Resume 3.20.16
TJJ Linked In Resume 3.20.16Tom Johnson
 
2016 Wesley Plaisted
2016 Wesley Plaisted2016 Wesley Plaisted
2016 Wesley PlaistedWes Plaisted
 
Shakeel ahmed resume
Shakeel ahmed  resumeShakeel ahmed  resume
Shakeel ahmed resumeShakeel Ahmed
 
TJJ Master Resume 4.08.16
TJJ Master Resume 4.08.16TJJ Master Resume 4.08.16
TJJ Master Resume 4.08.16Tom Johnson
 
Building a comissioning guideline
Building a comissioning guidelineBuilding a comissioning guideline
Building a comissioning guidelineZuzi Evangelista
 
Integration of modules on site _ final
Integration of modules on site _ finalIntegration of modules on site _ final
Integration of modules on site _ finalScott Coombes
 

What's hot (20)

Roy Ong CV (2015)
Roy Ong CV (2015)Roy Ong CV (2015)
Roy Ong CV (2015)
 
ENR MOUNTAIN STATES 2013 BEST PROJECTS AWARD
ENR MOUNTAIN STATES 2013 BEST PROJECTS AWARDENR MOUNTAIN STATES 2013 BEST PROJECTS AWARD
ENR MOUNTAIN STATES 2013 BEST PROJECTS AWARD
 
KBE Laboratories 2011
KBE Laboratories 2011 KBE Laboratories 2011
KBE Laboratories 2011
 
R mayers_CV 2302
R mayers_CV 2302R mayers_CV 2302
R mayers_CV 2302
 
Managing The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy ProjectsManaging The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy Projects
 
Caro, Jose J 11 9
Caro, Jose J 11 9Caro, Jose J 11 9
Caro, Jose J 11 9
 
Dale Buzzelli Resume
Dale Buzzelli ResumeDale Buzzelli Resume
Dale Buzzelli Resume
 
Stephen Cordova Final CV
Stephen Cordova Final CVStephen Cordova Final CV
Stephen Cordova Final CV
 
David Purfield
David PurfieldDavid Purfield
David Purfield
 
Sunil-CV-Latest
Sunil-CV-LatestSunil-CV-Latest
Sunil-CV-Latest
 
Joshua Ibbertson CV 2015
Joshua Ibbertson CV 2015Joshua Ibbertson CV 2015
Joshua Ibbertson CV 2015
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project Presentation
 
TJJ Linked In Resume 3.20.16
TJJ Linked In Resume 3.20.16TJJ Linked In Resume 3.20.16
TJJ Linked In Resume 3.20.16
 
Resume 2015 .doc 2
Resume 2015 .doc 2Resume 2015 .doc 2
Resume 2015 .doc 2
 
2016 Wesley Plaisted
2016 Wesley Plaisted2016 Wesley Plaisted
2016 Wesley Plaisted
 
Shakeel ahmed resume
Shakeel ahmed  resumeShakeel ahmed  resume
Shakeel ahmed resume
 
TJJ Master Resume 4.08.16
TJJ Master Resume 4.08.16TJJ Master Resume 4.08.16
TJJ Master Resume 4.08.16
 
Building a comissioning guideline
Building a comissioning guidelineBuilding a comissioning guideline
Building a comissioning guideline
 
CV - Azwyn Abd Aziz
CV - Azwyn Abd AzizCV - Azwyn Abd Aziz
CV - Azwyn Abd Aziz
 
Integration of modules on site _ final
Integration of modules on site _ finalIntegration of modules on site _ final
Integration of modules on site _ final
 

Viewers also liked

Location recces
Location reccesLocation recces
Location reccesshakeel99
 
A Natural way to keep your Dog Healthy with Dogsee Chew
 A Natural way to keep your Dog Healthy with Dogsee Chew A Natural way to keep your Dog Healthy with Dogsee Chew
A Natural way to keep your Dog Healthy with Dogsee ChewDogseechew
 
CSHISC Workforce Development Kit
CSHISC Workforce Development KitCSHISC Workforce Development Kit
CSHISC Workforce Development KitDaren Dawson
 
Ahmed Naeim Kamel CV 5-2-2016
Ahmed Naeim Kamel  CV 5-2-2016Ahmed Naeim Kamel  CV 5-2-2016
Ahmed Naeim Kamel CV 5-2-2016AHMED NAEIM
 
обзор 2016-моторные-виды-страхования
обзор 2016-моторные-виды-страхованияобзор 2016-моторные-виды-страхования
обзор 2016-моторные-виды-страхованияmResearcher
 
Pursuing sustainability
Pursuing sustainabilityPursuing sustainability
Pursuing sustainabilityNele Schmitz
 
pk presentation on marketing communication
pk presentation on marketing communicationpk presentation on marketing communication
pk presentation on marketing communicationVijay r chari
 
Payday Loans Ohio- Cash Loans aid for All are in Bad Credit
Payday Loans Ohio- Cash Loans aid for All are in Bad CreditPayday Loans Ohio- Cash Loans aid for All are in Bad Credit
Payday Loans Ohio- Cash Loans aid for All are in Bad CreditMark Hing
 
dnaltb-a5-brochure-en_web
dnaltb-a5-brochure-en_webdnaltb-a5-brochure-en_web
dnaltb-a5-brochure-en_webKaren Kirsten
 
History of the radio
History of the radioHistory of the radio
History of the radioalfiedaysh
 
Cuestionario de Wall-e
Cuestionario de Wall-eCuestionario de Wall-e
Cuestionario de Wall-eAngie Rivera
 
Black at Bryn Mawr: What's Next?
Black at Bryn Mawr: What's Next? Black at Bryn Mawr: What's Next?
Black at Bryn Mawr: What's Next? Monica Mercado
 

Viewers also liked (16)

Awards
AwardsAwards
Awards
 
Location recces
Location reccesLocation recces
Location recces
 
A Natural way to keep your Dog Healthy with Dogsee Chew
 A Natural way to keep your Dog Healthy with Dogsee Chew A Natural way to keep your Dog Healthy with Dogsee Chew
A Natural way to keep your Dog Healthy with Dogsee Chew
 
CSHISC Workforce Development Kit
CSHISC Workforce Development KitCSHISC Workforce Development Kit
CSHISC Workforce Development Kit
 
yessica hult 2
yessica hult 2yessica hult 2
yessica hult 2
 
Ahmed Naeim Kamel CV 5-2-2016
Ahmed Naeim Kamel  CV 5-2-2016Ahmed Naeim Kamel  CV 5-2-2016
Ahmed Naeim Kamel CV 5-2-2016
 
Proyectos
ProyectosProyectos
Proyectos
 
обзор 2016-моторные-виды-страхования
обзор 2016-моторные-виды-страхованияобзор 2016-моторные-виды-страхования
обзор 2016-моторные-виды-страхования
 
Pursuing sustainability
Pursuing sustainabilityPursuing sustainability
Pursuing sustainability
 
pk presentation on marketing communication
pk presentation on marketing communicationpk presentation on marketing communication
pk presentation on marketing communication
 
Payday Loans Ohio- Cash Loans aid for All are in Bad Credit
Payday Loans Ohio- Cash Loans aid for All are in Bad CreditPayday Loans Ohio- Cash Loans aid for All are in Bad Credit
Payday Loans Ohio- Cash Loans aid for All are in Bad Credit
 
dnaltb-a5-brochure-en_web
dnaltb-a5-brochure-en_webdnaltb-a5-brochure-en_web
dnaltb-a5-brochure-en_web
 
History of the radio
History of the radioHistory of the radio
History of the radio
 
Resume
ResumeResume
Resume
 
Cuestionario de Wall-e
Cuestionario de Wall-eCuestionario de Wall-e
Cuestionario de Wall-e
 
Black at Bryn Mawr: What's Next?
Black at Bryn Mawr: What's Next? Black at Bryn Mawr: What's Next?
Black at Bryn Mawr: What's Next?
 

Similar to Remote Bank Facility Construction

2016 Harry H. Mellon Awards in Job Order Contracting | Gordian
2016 Harry H. Mellon Awards in Job Order Contracting | Gordian2016 Harry H. Mellon Awards in Job Order Contracting | Gordian
2016 Harry H. Mellon Awards in Job Order Contracting | GordianGordian
 
Ed resume 2017.docx current
Ed resume   2017.docx currentEd resume   2017.docx current
Ed resume 2017.docx currentEdward Budney
 
Changing the Face at the Busiest Airport in the World th.docx
Changing the Face  at the Busiest Airport  in the World th.docxChanging the Face  at the Busiest Airport  in the World th.docx
Changing the Face at the Busiest Airport in the World th.docxcravennichole326
 
Rushden Splash Pool
Rushden Splash PoolRushden Splash Pool
Rushden Splash PoolPick_Everard
 
Changing the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docxChanging the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docxcravennichole326
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1Dan Caouette
 
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docx
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docxRUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docx
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docxagnesdcarey33086
 
Resume - Mark Torabinejad-23 June 2016
Resume - Mark Torabinejad-23 June 2016Resume - Mark Torabinejad-23 June 2016
Resume - Mark Torabinejad-23 June 2016Mark Torabinejad
 
William Faoro - 4pResumeM1
William Faoro - 4pResumeM1William Faoro - 4pResumeM1
William Faoro - 4pResumeM1William Faoro PE
 
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docxMargaritoWhitt221
 
Composite Resume Latest Version
Composite  Resume Latest VersionComposite  Resume Latest Version
Composite Resume Latest VersionRichard Law
 
Surrey education case study
Surrey education case studySurrey education case study
Surrey education case studyFreelancelanders
 
Vimal, Civil Engr CV
Vimal, Civil Engr CVVimal, Civil Engr CV
Vimal, Civil Engr CVvimal nc
 

Similar to Remote Bank Facility Construction (20)

2016 Harry H. Mellon Awards in Job Order Contracting | Gordian
2016 Harry H. Mellon Awards in Job Order Contracting | Gordian2016 Harry H. Mellon Awards in Job Order Contracting | Gordian
2016 Harry H. Mellon Awards in Job Order Contracting | Gordian
 
Ed resume 2017.docx current
Ed resume   2017.docx currentEd resume   2017.docx current
Ed resume 2017.docx current
 
Changing the Face at the Busiest Airport in the World th.docx
Changing the Face  at the Busiest Airport  in the World th.docxChanging the Face  at the Busiest Airport  in the World th.docx
Changing the Face at the Busiest Airport in the World th.docx
 
Rushden Splash Pool
Rushden Splash PoolRushden Splash Pool
Rushden Splash Pool
 
Rushden Splash Pool
Rushden Splash PoolRushden Splash Pool
Rushden Splash Pool
 
Changing the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docxChanging the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docx
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1
 
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docx
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docxRUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docx
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docx
 
Resume - Mark Torabinejad-23 June 2016
Resume - Mark Torabinejad-23 June 2016Resume - Mark Torabinejad-23 June 2016
Resume - Mark Torabinejad-23 June 2016
 
Portfolio
PortfolioPortfolio
Portfolio
 
Resume
Resume Resume
Resume
 
Richard (Rik) Stuart Barnett Resume
Richard (Rik) Stuart Barnett ResumeRichard (Rik) Stuart Barnett Resume
Richard (Rik) Stuart Barnett Resume
 
CV~PW~02-02-16 Opus
CV~PW~02-02-16 OpusCV~PW~02-02-16 Opus
CV~PW~02-02-16 Opus
 
William Faoro - 4pResumeM1
William Faoro - 4pResumeM1William Faoro - 4pResumeM1
William Faoro - 4pResumeM1
 
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
 
Resume 3-16-15docx
Resume 3-16-15docxResume 3-16-15docx
Resume 3-16-15docx
 
Composite Resume Latest Version
Composite  Resume Latest VersionComposite  Resume Latest Version
Composite Resume Latest Version
 
Surrey education case study
Surrey education case studySurrey education case study
Surrey education case study
 
Vimal, Civil Engr CV
Vimal, Civil Engr CVVimal, Civil Engr CV
Vimal, Civil Engr CV
 

Remote Bank Facility Construction

  • 1. Rick Petrinack Project Manager Highlight Projects for Discussion: Remote Bank Facility Construction The client identified a need to replace an ageing owned facility which was not cost feasible to repair and expand. Adding to the challenge was an accelerated replacement schedule and a very remote NW British Columbia coastal location. The project requirements ruled out most traditional redevelopment approaches. As such it was recommended that a prefabricated modular structure ready to install onto a completed foundation be considered. However local roadways were far too treacherous to support the transport of a modular structure. The prefabricated facility was loaded onto a barge in the port of Vancouver for transport to local port facilities near the site. Where final transportation of the structure was completed by more traditional means. Local trades completed the final construction details and site development. The opportunity to reduce freight and installation costs of the client trade fixtures, fixed assets and technical equipment was attained by completing as much as possible prior to shipment from the port of Vancouver. All of the unique and challenging requirements of the project were met along with providing the client with a value added facility. Budget 3.5 M Construction Conflict Resolution Midway through the construction of a 2 story 16,000 sq/ft 3.5 M early childhood facility the owner discovered that the project schedule had slipped by 6 months, was significantly over budget and communication between the primary stakeholders had totally broken down. The owner requested 3rd party consultation to re establish stakeholder communication and control over the project. An active communication and month long embedment was undertaken to establish the key road blocks, design and implement a plan to regain control. The personal, communicative approach re-established working relationships between the stakeholders and provided a bridge to resolve disputes and disagreements. The collaborative plan was implemented and regained control over the schedule, budget and working relationships. Additionally a dispute register and mandatory attendance at weekly site meetings improved project performance. Schedule timing was recovered, cost over-runs were rationalized and working relationships were mended paving the way for future developments. Seniors Complex Environmental Remediation/ Reconstruction The owners of a 4 story 200 suite s extended stay seniors facility commissioned a building envelope investigation the results of which confirmed extensive water intrusion and subsequent mold growth. The impact to clients, especially those whose immune systems were compromised was extensive. The challenges were a) maintaining a minimum occupancy rate of 80% for the landlord, b) minimizing exposure to residents and staff, c) maintaining consistent and clear communication to all stakeholders. Planning and execution of the 16 month project was successfully completed by a) establishing three working groups who reported to the project manager they were i) resident contact group, ii) owner contact group and iii) a facility group, b) investing in extensive upfront planning with the three working groups, c) concentrating work on one working floor and one swing floor at a time, d) amalgamating all of the stakeholder information, e) constant regular non stop communication with the stakeholders. Remediation, reconstruction and repairs to the building envelope were completed on schedule with minimal resident disruption. Budget 4.5 M
  • 2. Bank Facility Environmental Remediation/ Reconstruction Results of a planned Indoor Air Quality Assessment noted minimally elevated PCB levels within a branch facility. While the levels were well within acceptable guidelines any indication proved to be unacceptable for the client and options for addressing the condition were sought. This large suburban shopping centre branch is sandwiched in-between other tenants in a centre with no interior cru or exterior pad relocation opportunities temporary or otherwise. Additionally options for relocation within the immediate area or considering a branch closure were not acceptable. As a result determining the source and remediation of the offending PCB’s would have to be addressed in place. The single guiding consideration going forward was limiting any additional exposure physical and emotional to clients and staff. As such additional intrusive testing was completed after regular business hours which proved to be challenging. Traditional exploratory soil sampling bore holes were required throughout the facility requiring extensive facility cleaning, repairs and air quality testing with on site results to successfully reopen for business daily during the investigative process. Once the source of contamination was identified an exposure limiting remediation process needed to be designed. To do so a non descript entrance structure was constructed on an available exterior wall of the branch inside which an access shaft was excavated to below floor slab level. This shaft provided an entry point to under slab spaces for excavation equipment and manpower while also allowing an exit point for contaminated soils. Contaminated soils were removed from site nightly to a remote secured transfer area prior to disposal. Once remediation and final air quality testing was completed the excavated area was stabilized and outfitted with a ground water removal system and an access port for regular air quality testing. The access shaft was backfilled and removalof entrance structure completed. All work was completed to required regulations and standards without exposing clients or staff to unsafe levels of PCB’s or emotional stress. Zero days were lost while completing this project as a result clients and staff were able to conduct business as normal. Budget 5 M Bank Facilities Closure Program The client had decided to implement an aggressive branch closure program to divest themselves of unproductive and ageing infrastructure. The program covered an extremely large geographical area where traditionally four facility managers were assigned with a lengthy, involved and detailed process. The client began to express their displeasure with the lack of performance not only with the branch closures but with other core areas of the facility manager responsibilities. At risk was a crucial client relationship, possible default of a contract and the damage to a national company reputation. Along with the personal toll it was taking on the facility managers themselves. The proposed solution to restructure the branch closures as a program which could then be better managed by a single point of contact. This approach allowed for greater attention to detail, process and on time completions the client was anticipating. Additionally some unplanned cost savings and a more manageable work load for the facility management group as a result. Budget 6.5 M