Fire Protection System Concept
TMMGT-ORO
Toyota Motor Manufacturing de Guanajuato
1
I N D E X
1.Fire Alarm System
1-1 Fire Alarm Loop Diagram
1-2 Fire Alarm Route Map
2.Fire Water System
2-1 Fire fighting Concept
2-2 Fire Water piping Main
2-3 FACP Monitoring Concept
3.Fire Protection Communication System
4.Fire Alarm Interlock system
4-1 General Flow Diagram
4-2 Interlock Details
① Common to #200Paint & #400Resin
② Fan Interlock Stop(#200Paint)
③ Fan Interlock Stop(#200Paint)
④ Fan Interlock Stop(#200Paint)
⑤ Air Conditioner & Fan Interlock Stop(#200Paint)
⑥ Fan Interlock Stop(#200Paint)
⑦ Fan Interlock Stop(#400Resin)
⑧ Air Conditioner & Fan Interlock Stop(#400Resin)
⑨ Fan Interlock Stop(#400Resin)
⑩ Air Conditioner & Fan Interlock Stop(#400Resin)
⑪ Air Conditioner & Fan Interlock Stop(#400Resin)
1-1 全体Loop系統図
#200
Paint
(FACP)
#301
QC
(FACP)
#304
LTF
:Package2
:Package3
:Package7
:Package5
:Fire equipment
control panel
:FA Loop
(Optical Cable)
Security
Office
(Main FACP)
Fire pump House
EAST
Substation
(FACP)
#400
Resin
FACP
#300
Assembly
FACP
#100
Press
(FACP)
#150
Welding
(FACP)
#201
OIL STORE
(FACP)
#510
WWTP/WTP
(Mirror FACP)
OSS
Substation
FACP
Main
Substation
(FACP)
:Metal cable
:FA Loop(Underground)
(Optical Cable)
1.Fire Alarm System
1-1 Fire Alarm Loop Diagram
#602
Shop Office
(FACP)
2
外構
OIL STORE
Receiver
QC
Receiver
W ELDING
Receiver
PRESS
Receiver
Loop w iring
PAINT
Receiver
M ain Receiver
-M irro r
( Utility Office)
SHOP OFFICE
Receiver
RESIN
Receiver
M ain Receiver
( Secu rity o ffice)
ASSEMBLY
Receiver
Autom atic Fire Detector I nstallation Area
1.Fire Alarm System
1-2 Fire Alarm Route Map
3
Assem bly Tire Storag e Area
Press Pit
Paint
Resin
Shop Office
Dang erous Goods
W arehouse
※En tire b uilding is cov ered b y fire hy dra n t.
QC Paint Clinic
Audit
fire w ater
tank,
Fire
exting uishing
pum p
Loop Piping
Riser
• Plan for disaster prevention equipm ent according to
Mexico's NOM standards, Toyota g ood products condition.
• Sprinkler installed in hig h risk area.
For hig h ceiling part, autom atic fire detector is installed
since the sprinkler is not effective
.
・ Press pit
・ Paint
・ Resin
・ Paint area in QC, AUDI T area
・ Tire storag e area in Assem bly
・ Shop Office
・ Hazardous Material Storag e ( Oil Store)
• The entire building is covered w ith indoor and
outdoor fire hydrants.
• Fire pum p and fire w ater tank are
installed in the W W TP area.
• W ith the m ain piping as an outdoor loop,
a riser pipe is installed for each shop.
• Fire Pum p Operation outline
・ Pressure: 155 PSI or m ore → Jockey pum p OFF
・ Pressure: 150 PSI or less → One jockey pum p ON
・ Pressure: 145 PSI or less → Tw o jockey pum ps ON
・ Pressure: 135 PSI or less → Electric fire pum p ON
・ Pressure: 125 PSI or less → Diesel fire pum p ON
2.Fire Water System
4
2-1Fire Fighting Concept 2-2 Fire Water Piping Main
Sprinkler Fire Hydrant
2.Fire Water System
2-3 FACP Monitoring Concept
5
Security
Office
(Gate
House)
#100
Press
#150
Welding
#200
Paint
#300
Assembly
#301
QC
#400
Resin
#510
Utility
Office
#602
Shop
Office
Main
Switch
gear
OSS
Switch
Gear
EAST
Substation
①
Security Office
(Gate House)
〇 〇 〇 〇 〇 〇 〇 〇 〇 〇 〇 〇
② #100 Press 〇
③ #150 Welding 〇
④ #200 Paint 〇
⑤ #300 Assembly 〇
⑥ #301 QC 〇
⑦ #400 Resin 〇
⑧ #510 Utility Office 〇 〇 〇 〇 〇 〇 〇 〇 〇 〇 〇 〇
⑨ #602 Shop Office 〇
⑩ Main Switch gear 〇
⑪ OSS Switch Gear 〇
⑫ EAST Substation 〇
MONITORING AREA
FACP
FACP(Fire Alarm Control Panel)Monitoring area correspondence table
3.Fire Protection Communication System
6
Break of Fire (incl. Fail Alarm)
Manual Pull Station
- Activated
Hydrant/Sprinkler Riser
Switch- Activated
Automatic Fire
Detector- Activated
Process FACP
- Activated
FIRE DETERMINED
If Detector
Activates more
than (2) nos.
+ Start Strobe &
Rumbling in the Shop
+ Start Evacuation of
Shop Member
FIRE DETERMINED
In the Shop
FIRE ALARM
DETECTED
On Site Check
FIRE ALARM DETECTED
In the Shop
If Fire Confirmed
Cancel the Alarm
Check the Fail Alarm
Route Cause
On Site Check
+ TMMGT Fire
Brigade Start Initial
extinguish works
+ Request Public
Fire Dept. supports
If Risk, Spread of
Fire to Other Shop
Activate Strobe &
Rumbling in All Shop
+ Start Evacuation of
All Team Member
Local FACP
Central FACP
+ Start Strobe &
Rumbling in All Shop
YES
YES
NO
+ Start Strobe &
Rumbling in the Zone
All Plant Public
Announcement for
Non-Evacuation
YES
NO
NO
All Plant Public
Announcement for
Evacuation
(*manual operation)
4.Fire Alarm Interlock system
4-1 General Flow Diagram
7
Break of Fire (incl. Fail Alarm)
Manual Pull Station
- Activated
Hydrant/Sprinkler Riser
Switch- Activated
Automatic Fire
Detector- Activated
Process FACP
- Activated *2
FIRE DETERMINED
If Detector
Activates more
than (2) nos.
If Paint Mix Activated
+ Stop All Fan in the Shop
Except EU (Paint Confined Space*3)
Local FACP
YES
+ Stop All Fan
Except Paint Mix
YES
NO
Start Fire Pump Run
FIRE DETERMINED
In the Shop
Central FACP
FIRE PUMP RUN
Notification
*3 : EU fan is controlled by the signal from Process FACP.
*1 : Fire Water Riser Except for Process Riser.
*1
*2 : Including Fire Water Riser for Process Riser Switch from Local FACP
If the building FACP fire is confirmed
(Manual Pull station operation or two or more sensors)
1. Maintenance mode (Process side unwarned state)
2. Send status signal to FACP
3. Transfer status signal to MAIN FACP
FACP FACP
PDP-T007
MAIN FACP
HVAC
Control
Panel
EU-01~07
EF/HVAC
RISER
#200 Paint Shop
#400 Resin Shop
PDP-T007
Other than part of T004 and T006
SAF/WEF/REF
etc
Detector
Pull station
Strobe
Detector
Pull station
Strobe
:PROCESS
:BUILDING
Security Office
STOP
STOP
STOP
②
③
PDP-T004
PDP-T006
PU/REF/EAF
etc(For Mixing room)
:Signal line
:Power line
RISER
For Mixing
room
RISER
For Process
Maintenance mode (Process side unwarranted status)
STOP
①
4-2 Interlock Details
① Common to #200Paint & #400Resin
8
If the building FACP fire is confirmed
(Manual Pull station operation or two or more sensors)
1. Strobe & Phone sound in the hall
2. Send a fire signal to FACP for Process
3. Stop air conditioning ventilation (PDP)
4. EU (PDP-T 007) does not stop
5. PU & REF, part of EAF (machine related to mixing room) will not stop
6. Moved fire signal to MAIN FACP
FACP FACP
PDP-T007
MAIN FACP
HVAC
Control
Panel
EU-01~07
EF/HVAC
RISER
#200 Paint Shop
PDP-T007
Other than part of T004 and T006
SAF/WEF/REF
etc
Detector
Pull station
Strobe
Detector
Pull station
Strobe
:PROCESS
:BUILDING
Security Office
STOP
STOP
STOP
②
④
③
⑥
①
⑤
PDP-T004
PDP-T006
PU/REF/EAF
etc(For Mixing room)
:Signal line
:Power line
RISER
For Mixing
room
RISER
For Process
(Manual Pull station operation or two or more sensors)
STOP
4-2 Interlock Details
② Fan Interlock Stop(#200Paint)
9
If the building FACP fire is confirmed
(If RISER (sprinkler) is activated)
1. Strobe & Phone sound in the hall
2. Send a fire signal to FACP for Process
3. Stop air conditioning ventilation (PDP)
4. EU (PDP-T 007) does not stop
5. PU & REF, part of EAF (machine related to mixing room) will not stop
6. Moved fire signal to MAIN FACP
FACP FACP
PDP-T007
MAIN FACP
HVAC
Control
Panel
EU-01~07
EF/HVAC
RISER
#200 Paint Shop
PDP-T007
T004,T006の一部以外
SAF/WEF/REF
etc
Detector
Pull station
Strobe
Detector
Pull station
Strobe
:PROCESS
:BUILDING
Security Office
STOP
STOP
STOP
②
④
③
⑥
①
⑤
PDP-T004
PDP-T006
PU/REF/EAF
etc(For Mixing room)
:Signal line
:Power line
RISER
For Mixing
room
RISER
For Process
(If RISER (sprinkler) is activated)
STOP
4-2 Interlock Details
③ Fan Interlock Stop(#200Paint)
10
If the building FACP fire is confirmed
(When FACP for Process is activated)
1. Receive a fire confirmation signal from FACP for Process
2. Strobe & Phone sound in the hall
3. Stop air conditioning ventilation (PDP)
4. Stop the EU (PDP-T 007)
5. PU & REF, part of EAF (machine related to mixing room) will not stop
6. Moved fire signal to MAIN FACP
FACP FACP
PDP-T007
MAIN FACP
HVAC
Control
Panel
EU-01~07
EF/HVAC
RISER
#200 Paint Shop
PDP-T007
T004,T006Other than part of
SAF/WEF/REF
etc
Detector
Pull station
Strobe
Detector
Pull station
Strobe
:PROCESS
:BUILDING
Security Office
STOP
STOP
STOP
①
④
③
⑥
②
⑤
PDP-T004
PDP-T006
PU/REF/EAF
etc(For Mixing room)
:Signal line
:Power line
RISER
For Mixing
room
RISER
For Process
STOP
(When FACP for Process is activated)
4-2 Interlock Details
④ Fan Interlock Stop(#200Paint)
11
If the building FACP fire is confirmed
(When RISER for Mixing room is activated)
1. Strobe & Phone sound in the hall
2. Send a fire signal to FACP for Process
3. Stop air conditioning ventilation (PDP)
4. EU (PDP-T 007) does not stop
5. PU & REF, part of EAF (the machine related to the mixing room) stop
6. Moved fire signal to MAIN FACP
FACP FACP
PDP-T007
MAIN FACP
HVAC
Control
Panel
EU-01~07
EF/HVAC
RISER
#200 Paint Shop
PDP-T007
T004,T006 Other than part of
SAF/WEF/REF
etc
Detector
Pull station
Strobe
Detector
Pull station
Strobe
:PROCESS
:BUILDING
Security Office
STOP
STOP
STOP
②
④
③
⑥
①
⑤
PDP-T004
PDP-T006
PU/REF/EAF
etc(For Mixing room)
:Signal line
:Power line
RISER
For Mixing
room
RISER
For Process
STOP
(When RISER (sprinkler) for Mixing room is activated)
4-2 Interlock Details
⑤ Air Conditioner & Fan Interlock Stop(#200Paint)
12
If the building FACP fire is confirmed
(If RISER for Process is activated)
1. Send RISER activation signal to FACP for Process
2. Receive a fire confirmation signal from FACP for Process
3. Strobe & Phone in the hall
4. Stop air conditioning ventilation (PDP)
5. EU (PDP-T 007) shut down
6. PU & REF, part of EAF (machine related to mixing room) will not stop
7. Moved fire signal to MAIN FACP
FACP FACP
PDP-T007
MAIN FACP
HVAC
Control
Panel
EU-01~07
EF/HVAC
RISER
#200 Paint Shop
PDP-T007
Other than part of T004 and T006
SAF/WEF/REF
etc
Detector
Pull station
Strobe
Detector
Pull station
Strobe
:PROCESS
:BUILDING
Security Office
STOP
STOP
STOP
①
⑤
④
⑦
③
⑥
PDP-T004
PDP-T006
PU/REF/EAF
etc(For Mixing room)
:Signal line
:Power line
RISER
For Mixing
room
RISER
For Process
(If RISER for Process (sprinkler) is activated)
②
4-2 Interlock Details
⑥ Fan Interlock Stop(#200Paint)
13
If the building FACP fire is confirmed
(Manual Pull station operation or two or more sensors)
1. Strobe & Phone sound in the hall
2. Send a fire signal to FACP for Process
3. Stop air conditioning ventilation (PDP)
4. PU & REF, part of EAF (machine related to mixing room) will not stop
5. Moved fire signal to MAIN FACP
FACP FACP
MAIN FACP
HVAC
Control
Panel
EF/HVAC
RISER
#400 Resin Shop
PDP-R002
Other than part of
SAF/WEF/REF
etc
Detector
Pull station
Strobe
Detector
Pull station
Strobe
:PROCESS
:BUILDING
Security Office
STOP
STOP
②
③
⑥
①
⑤
PDP-R002
Part of
PU/REF/EAF
etc(For Mixing room)
:Signal line
:Power line
RISER
For Mixing
room
RISER
For Process
(Manual Pull station operation or two or more sensors)
STOP
4-2 Interlock Details
⑦ Fan Interlock Stop(#400Resin)
14
If the building FACP fire is confirmed
(If RISER (sprinkler) is activated)
1. Strobe & Phone sound in the hall
2. Send a fire signal to FACP for Process
3. Stop air conditioning ventilation (PDP)
4. PU & REF, part of EAF (machine related to mixing room) will not stop
5. Moved fire signal to MAIN FACP
FACP FACP
MAIN FACP
HVAC
Control
Panel
EF/HVAC
RISER
#400 Resin Shop
PDP-R002
Other than part of
SAF/WEF/REF
etc
Detector
Pull station
Strobe
Detector
Pull station
Strobe
:PROCESS
:BUILDING
Security Office
STOP
STOP
②
③
⑤
①
④
PDP-R002
Part of
PU/REF/EAF
etc(For Mixing room)
:Signal line
:Power line
RISER
For Mixing
room
RISER
For Process
(If RISER (sprinkler) is activated)
STOP
4-2 Interlock Details
⑧ Air Conditioner & Fan Interlock Stop(#400Resin)
15
If the building FACP fire is confirmed
(When FACP for Process is activated)
1. Receive a fire confirmation signal from FACP for Process
2. Strobe & Phone sound in the hall
3. Stop air conditioning ventilation (PDP)
4. PU & REF, part of EAF (machine related to mixing room) will not stop
5. Moved fire signal to MAIN FACP
FACP FACP
MAIN FACP
HVAC
Control
Panel
EF/HVAC
RISER
#400 Resin Shop
PDP-R002
Other than part of
SAF/WEF/REF
etc
Detector
Pull station
Strobe
Detector
Pull station
Strobe
:PROCESS
:BUILDING
Security Office
STOP
STOP
①
③
⑤
②
④
PDP-R002
Part of
PU/REF/EAF
etc(For Mixing room)
:Signal line
:Power line
RISER
For Mixing
room
RISER
For Process
STOP
(When FACP for Process is activated)
4-2 Interlock Details
⑨ Fan Interlock Stop(#400Resin)
16
If the building FACP fire is confirmed
(When RISER for Mixing room is activated)
1. Strobe & Phone sound in the hall
2. Send a fire signal to FACP for Process
3. Stop air conditioning ventilation (PDP)
4. EU (PDP-T 007) does not stop
5. PU & REF, part of EAF (the machine related to the mixing room) stop
6. Moved fire signal to MAIN FACP
FACP FACP
MAIN FACP
HVAC
Control
Panel
EF/HVAC
RISER
#400 Resin Shop
PDP-R002
Other than part of
SAF/WEF/REF
etc
Detector
Pull station
Strobe
Detector
Pull station
Strobe
:PROCESS
:BUILDING
Security Office
STOP
STOP
②
③
⑥
①
⑤
PDP-R002
Other than part of
PU/REF/EAF
etc(For Mixing room)
:Signal line
:Power line
RISER
For Mixing
room
RISER
For Process
When RISER (sprinkler) for Mixing room is activated
STOP
4-2 Interlock Details
⑩ Air Conditioner & Fan Interlock Stop(#400Resin)
17
If the building FACP fire is confirmed
(If RISER for Process is activated)
1. Send RISER activation signal to FACP for Process
2. Receive a fire confirmation signal from 2FACP for Process
3. Strobe & Phone in the hall
4. Stop air conditioning ventilation (PDP)
5. EU (PDP-T 007) shut down
6. PU & REF, part of EAF (machine related to mixing room) will not stop
7. Moved fire signal to MAIN FACP
FACP FACP
MAIN FACP
HVAC
Control
Panel
EF/HVAC
RISER
#400 Resin Shop
PDP-R002
Other than part of
SAF/WEF/REF
etc
Detector
Pull station
Strobe
Detector
Pull station
Strobe
:PROCESS
:BUILDING
Security Office
STOP
STOP
①
④
⑥
③
⑤
PDP-R002
Part of
PU/REF/EAF
etc(For Mixing room)
:Signal line
:Power line
RISER
For Mixing
room
RISER
For Process
(If RISER for Process (sprinkler) is activated)
②
4-2 Interlock Details
⑪ Air Conditioner & Fan Interlock Stop(#400Resin)
18
Interlocking with LTF Fire pump house
FACP
RISER
Detector
Pull station
Strobe
CP
Foam fire control board
Main CP
Assembly
or
QC
MAIN FACP
Security Office
:LTF
:BUILDING
Signal overview
1 Start signal of foam fire extinguishing equipment
Send a signal to the adjacent building FACP
2 Output the start signal of foam extinguishing
equipment to Main FACP
3 Signals a fire confirmation signal to a foam fire
extinguishing control board at the time of building fire
Output, stop valve and supply pump
①
②
FACP
RISER
Detector
Strobe
CP
Fire extinguishing pump control board
Fire Pump
Utility
Office
MAIN FACP
Security Office
:LTF
:BUILDING
Signal overview
1 fire extinguishing pump start signal
Signal Utility Office FACP
2 Output the fire pump start signal to Main FACP
①
②
Valve Pump
③
STOP STOP
4-2 Interlock Details
⑫ LTF & Fire Pump House Interlock
19

More Related Content

Similar to Fire Protection System Concept .pptx

Ga al july_august
Ga al july_augustGa al july_august
Ga al july_augusttsksc186
 
Mid america julyaugust
Mid america julyaugustMid america julyaugust
Mid america julyaugusttsksc186
 
Indiana july august
Indiana july augustIndiana july august
Indiana july augusttsksc186
 
Wilmington july august
Wilmington july augustWilmington july august
Wilmington july augusttsksc186
 
Kansas july august
Kansas july augustKansas july august
Kansas july augusttsksc186
 
Buffalo july august
Buffalo july augustBuffalo july august
Buffalo july augusttsksc186
 
Norfolk july august
Norfolk july augustNorfolk july august
Norfolk july augusttsksc186
 
Flint july august
Flint july augustFlint july august
Flint july augusttsksc186
 
Arkansas july august
Arkansas july augustArkansas july august
Arkansas july augusttsksc186
 
Desmoines july august
Desmoines july augustDesmoines july august
Desmoines july augusttsksc186
 
Cleveland july august
Cleveland july augustCleveland july august
Cleveland july augusttsksc186
 
Greensboro july august
Greensboro july augustGreensboro july august
Greensboro july augusttsksc186
 
Dayton july august
Dayton july augustDayton july august
Dayton july augusttsksc186
 
Honda OBD2 Codes
Honda OBD2 CodesHonda OBD2 Codes
Honda OBD2 CodesTim Miller
 
K85000-0391 -- Releasing Module Flyer.pdf
K85000-0391 -- Releasing Module Flyer.pdfK85000-0391 -- Releasing Module Flyer.pdf
K85000-0391 -- Releasing Module Flyer.pdfSecorpSAS
 
POF Internship report ali raza 12-ENC-33
POF Internship report ali raza 12-ENC-33POF Internship report ali raza 12-ENC-33
POF Internship report ali raza 12-ENC-33Ali Raza
 
Microtrans differential pressure and airflow signal processor
Microtrans differential  pressure and airflow signal processorMicrotrans differential  pressure and airflow signal processor
Microtrans differential pressure and airflow signal processorxanderGal123
 
Gulfsouth july august
Gulfsouth july augustGulfsouth july august
Gulfsouth july augusttsksc186
 

Similar to Fire Protection System Concept .pptx (20)

Ga al july_august
Ga al july_augustGa al july_august
Ga al july_august
 
Mid america julyaugust
Mid america julyaugustMid america julyaugust
Mid america julyaugust
 
Indiana july august
Indiana july augustIndiana july august
Indiana july august
 
Wilmington july august
Wilmington july augustWilmington july august
Wilmington july august
 
Kansas july august
Kansas july augustKansas july august
Kansas july august
 
Buffalo july august
Buffalo july augustBuffalo july august
Buffalo july august
 
Norfolk july august
Norfolk july augustNorfolk july august
Norfolk july august
 
Flint july august
Flint july augustFlint july august
Flint july august
 
Arkansas july august
Arkansas july augustArkansas july august
Arkansas july august
 
Desmoines july august
Desmoines july augustDesmoines july august
Desmoines july august
 
Cleveland july august
Cleveland july augustCleveland july august
Cleveland july august
 
Greensboro july august
Greensboro july augustGreensboro july august
Greensboro july august
 
Dayton july august
Dayton july augustDayton july august
Dayton july august
 
Honda OBD2 Codes
Honda OBD2 CodesHonda OBD2 Codes
Honda OBD2 Codes
 
Due Diligence TEM 220201.pptx
Due Diligence TEM 220201.pptxDue Diligence TEM 220201.pptx
Due Diligence TEM 220201.pptx
 
K85000-0391 -- Releasing Module Flyer.pdf
K85000-0391 -- Releasing Module Flyer.pdfK85000-0391 -- Releasing Module Flyer.pdf
K85000-0391 -- Releasing Module Flyer.pdf
 
POF Internship report ali raza 12-ENC-33
POF Internship report ali raza 12-ENC-33POF Internship report ali raza 12-ENC-33
POF Internship report ali raza 12-ENC-33
 
Microtrans differential pressure and airflow signal processor
Microtrans differential  pressure and airflow signal processorMicrotrans differential  pressure and airflow signal processor
Microtrans differential pressure and airflow signal processor
 
Gulfsouth july august
Gulfsouth july augustGulfsouth july august
Gulfsouth july august
 
MITSUBISHI ELECTRIC SPLIT-TYPE
MITSUBISHI ELECTRIC SPLIT-TYPEMITSUBISHI ELECTRIC SPLIT-TYPE
MITSUBISHI ELECTRIC SPLIT-TYPE
 

Recently uploaded

Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 

Recently uploaded (20)

Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 

Fire Protection System Concept .pptx

  • 1. Fire Protection System Concept TMMGT-ORO Toyota Motor Manufacturing de Guanajuato
  • 2. 1 I N D E X 1.Fire Alarm System 1-1 Fire Alarm Loop Diagram 1-2 Fire Alarm Route Map 2.Fire Water System 2-1 Fire fighting Concept 2-2 Fire Water piping Main 2-3 FACP Monitoring Concept 3.Fire Protection Communication System 4.Fire Alarm Interlock system 4-1 General Flow Diagram 4-2 Interlock Details ① Common to #200Paint & #400Resin ② Fan Interlock Stop(#200Paint) ③ Fan Interlock Stop(#200Paint) ④ Fan Interlock Stop(#200Paint) ⑤ Air Conditioner & Fan Interlock Stop(#200Paint) ⑥ Fan Interlock Stop(#200Paint) ⑦ Fan Interlock Stop(#400Resin) ⑧ Air Conditioner & Fan Interlock Stop(#400Resin) ⑨ Fan Interlock Stop(#400Resin) ⑩ Air Conditioner & Fan Interlock Stop(#400Resin) ⑪ Air Conditioner & Fan Interlock Stop(#400Resin)
  • 3. 1-1 全体Loop系統図 #200 Paint (FACP) #301 QC (FACP) #304 LTF :Package2 :Package3 :Package7 :Package5 :Fire equipment control panel :FA Loop (Optical Cable) Security Office (Main FACP) Fire pump House EAST Substation (FACP) #400 Resin FACP #300 Assembly FACP #100 Press (FACP) #150 Welding (FACP) #201 OIL STORE (FACP) #510 WWTP/WTP (Mirror FACP) OSS Substation FACP Main Substation (FACP) :Metal cable :FA Loop(Underground) (Optical Cable) 1.Fire Alarm System 1-1 Fire Alarm Loop Diagram #602 Shop Office (FACP) 2
  • 4. 外構 OIL STORE Receiver QC Receiver W ELDING Receiver PRESS Receiver Loop w iring PAINT Receiver M ain Receiver -M irro r ( Utility Office) SHOP OFFICE Receiver RESIN Receiver M ain Receiver ( Secu rity o ffice) ASSEMBLY Receiver Autom atic Fire Detector I nstallation Area 1.Fire Alarm System 1-2 Fire Alarm Route Map 3
  • 5. Assem bly Tire Storag e Area Press Pit Paint Resin Shop Office Dang erous Goods W arehouse ※En tire b uilding is cov ered b y fire hy dra n t. QC Paint Clinic Audit fire w ater tank, Fire exting uishing pum p Loop Piping Riser • Plan for disaster prevention equipm ent according to Mexico's NOM standards, Toyota g ood products condition. • Sprinkler installed in hig h risk area. For hig h ceiling part, autom atic fire detector is installed since the sprinkler is not effective . ・ Press pit ・ Paint ・ Resin ・ Paint area in QC, AUDI T area ・ Tire storag e area in Assem bly ・ Shop Office ・ Hazardous Material Storag e ( Oil Store) • The entire building is covered w ith indoor and outdoor fire hydrants. • Fire pum p and fire w ater tank are installed in the W W TP area. • W ith the m ain piping as an outdoor loop, a riser pipe is installed for each shop. • Fire Pum p Operation outline ・ Pressure: 155 PSI or m ore → Jockey pum p OFF ・ Pressure: 150 PSI or less → One jockey pum p ON ・ Pressure: 145 PSI or less → Tw o jockey pum ps ON ・ Pressure: 135 PSI or less → Electric fire pum p ON ・ Pressure: 125 PSI or less → Diesel fire pum p ON 2.Fire Water System 4 2-1Fire Fighting Concept 2-2 Fire Water Piping Main Sprinkler Fire Hydrant
  • 6. 2.Fire Water System 2-3 FACP Monitoring Concept 5 Security Office (Gate House) #100 Press #150 Welding #200 Paint #300 Assembly #301 QC #400 Resin #510 Utility Office #602 Shop Office Main Switch gear OSS Switch Gear EAST Substation ① Security Office (Gate House) 〇 〇 〇 〇 〇 〇 〇 〇 〇 〇 〇 〇 ② #100 Press 〇 ③ #150 Welding 〇 ④ #200 Paint 〇 ⑤ #300 Assembly 〇 ⑥ #301 QC 〇 ⑦ #400 Resin 〇 ⑧ #510 Utility Office 〇 〇 〇 〇 〇 〇 〇 〇 〇 〇 〇 〇 ⑨ #602 Shop Office 〇 ⑩ Main Switch gear 〇 ⑪ OSS Switch Gear 〇 ⑫ EAST Substation 〇 MONITORING AREA FACP FACP(Fire Alarm Control Panel)Monitoring area correspondence table
  • 7. 3.Fire Protection Communication System 6 Break of Fire (incl. Fail Alarm) Manual Pull Station - Activated Hydrant/Sprinkler Riser Switch- Activated Automatic Fire Detector- Activated Process FACP - Activated FIRE DETERMINED If Detector Activates more than (2) nos. + Start Strobe & Rumbling in the Shop + Start Evacuation of Shop Member FIRE DETERMINED In the Shop FIRE ALARM DETECTED On Site Check FIRE ALARM DETECTED In the Shop If Fire Confirmed Cancel the Alarm Check the Fail Alarm Route Cause On Site Check + TMMGT Fire Brigade Start Initial extinguish works + Request Public Fire Dept. supports If Risk, Spread of Fire to Other Shop Activate Strobe & Rumbling in All Shop + Start Evacuation of All Team Member Local FACP Central FACP + Start Strobe & Rumbling in All Shop YES YES NO + Start Strobe & Rumbling in the Zone All Plant Public Announcement for Non-Evacuation YES NO NO All Plant Public Announcement for Evacuation (*manual operation)
  • 8. 4.Fire Alarm Interlock system 4-1 General Flow Diagram 7 Break of Fire (incl. Fail Alarm) Manual Pull Station - Activated Hydrant/Sprinkler Riser Switch- Activated Automatic Fire Detector- Activated Process FACP - Activated *2 FIRE DETERMINED If Detector Activates more than (2) nos. If Paint Mix Activated + Stop All Fan in the Shop Except EU (Paint Confined Space*3) Local FACP YES + Stop All Fan Except Paint Mix YES NO Start Fire Pump Run FIRE DETERMINED In the Shop Central FACP FIRE PUMP RUN Notification *3 : EU fan is controlled by the signal from Process FACP. *1 : Fire Water Riser Except for Process Riser. *1 *2 : Including Fire Water Riser for Process Riser Switch from Local FACP
  • 9. If the building FACP fire is confirmed (Manual Pull station operation or two or more sensors) 1. Maintenance mode (Process side unwarned state) 2. Send status signal to FACP 3. Transfer status signal to MAIN FACP FACP FACP PDP-T007 MAIN FACP HVAC Control Panel EU-01~07 EF/HVAC RISER #200 Paint Shop #400 Resin Shop PDP-T007 Other than part of T004 and T006 SAF/WEF/REF etc Detector Pull station Strobe Detector Pull station Strobe :PROCESS :BUILDING Security Office STOP STOP STOP ② ③ PDP-T004 PDP-T006 PU/REF/EAF etc(For Mixing room) :Signal line :Power line RISER For Mixing room RISER For Process Maintenance mode (Process side unwarranted status) STOP ① 4-2 Interlock Details ① Common to #200Paint & #400Resin 8
  • 10. If the building FACP fire is confirmed (Manual Pull station operation or two or more sensors) 1. Strobe & Phone sound in the hall 2. Send a fire signal to FACP for Process 3. Stop air conditioning ventilation (PDP) 4. EU (PDP-T 007) does not stop 5. PU & REF, part of EAF (machine related to mixing room) will not stop 6. Moved fire signal to MAIN FACP FACP FACP PDP-T007 MAIN FACP HVAC Control Panel EU-01~07 EF/HVAC RISER #200 Paint Shop PDP-T007 Other than part of T004 and T006 SAF/WEF/REF etc Detector Pull station Strobe Detector Pull station Strobe :PROCESS :BUILDING Security Office STOP STOP STOP ② ④ ③ ⑥ ① ⑤ PDP-T004 PDP-T006 PU/REF/EAF etc(For Mixing room) :Signal line :Power line RISER For Mixing room RISER For Process (Manual Pull station operation or two or more sensors) STOP 4-2 Interlock Details ② Fan Interlock Stop(#200Paint) 9
  • 11. If the building FACP fire is confirmed (If RISER (sprinkler) is activated) 1. Strobe & Phone sound in the hall 2. Send a fire signal to FACP for Process 3. Stop air conditioning ventilation (PDP) 4. EU (PDP-T 007) does not stop 5. PU & REF, part of EAF (machine related to mixing room) will not stop 6. Moved fire signal to MAIN FACP FACP FACP PDP-T007 MAIN FACP HVAC Control Panel EU-01~07 EF/HVAC RISER #200 Paint Shop PDP-T007 T004,T006の一部以外 SAF/WEF/REF etc Detector Pull station Strobe Detector Pull station Strobe :PROCESS :BUILDING Security Office STOP STOP STOP ② ④ ③ ⑥ ① ⑤ PDP-T004 PDP-T006 PU/REF/EAF etc(For Mixing room) :Signal line :Power line RISER For Mixing room RISER For Process (If RISER (sprinkler) is activated) STOP 4-2 Interlock Details ③ Fan Interlock Stop(#200Paint) 10
  • 12. If the building FACP fire is confirmed (When FACP for Process is activated) 1. Receive a fire confirmation signal from FACP for Process 2. Strobe & Phone sound in the hall 3. Stop air conditioning ventilation (PDP) 4. Stop the EU (PDP-T 007) 5. PU & REF, part of EAF (machine related to mixing room) will not stop 6. Moved fire signal to MAIN FACP FACP FACP PDP-T007 MAIN FACP HVAC Control Panel EU-01~07 EF/HVAC RISER #200 Paint Shop PDP-T007 T004,T006Other than part of SAF/WEF/REF etc Detector Pull station Strobe Detector Pull station Strobe :PROCESS :BUILDING Security Office STOP STOP STOP ① ④ ③ ⑥ ② ⑤ PDP-T004 PDP-T006 PU/REF/EAF etc(For Mixing room) :Signal line :Power line RISER For Mixing room RISER For Process STOP (When FACP for Process is activated) 4-2 Interlock Details ④ Fan Interlock Stop(#200Paint) 11
  • 13. If the building FACP fire is confirmed (When RISER for Mixing room is activated) 1. Strobe & Phone sound in the hall 2. Send a fire signal to FACP for Process 3. Stop air conditioning ventilation (PDP) 4. EU (PDP-T 007) does not stop 5. PU & REF, part of EAF (the machine related to the mixing room) stop 6. Moved fire signal to MAIN FACP FACP FACP PDP-T007 MAIN FACP HVAC Control Panel EU-01~07 EF/HVAC RISER #200 Paint Shop PDP-T007 T004,T006 Other than part of SAF/WEF/REF etc Detector Pull station Strobe Detector Pull station Strobe :PROCESS :BUILDING Security Office STOP STOP STOP ② ④ ③ ⑥ ① ⑤ PDP-T004 PDP-T006 PU/REF/EAF etc(For Mixing room) :Signal line :Power line RISER For Mixing room RISER For Process STOP (When RISER (sprinkler) for Mixing room is activated) 4-2 Interlock Details ⑤ Air Conditioner & Fan Interlock Stop(#200Paint) 12
  • 14. If the building FACP fire is confirmed (If RISER for Process is activated) 1. Send RISER activation signal to FACP for Process 2. Receive a fire confirmation signal from FACP for Process 3. Strobe & Phone in the hall 4. Stop air conditioning ventilation (PDP) 5. EU (PDP-T 007) shut down 6. PU & REF, part of EAF (machine related to mixing room) will not stop 7. Moved fire signal to MAIN FACP FACP FACP PDP-T007 MAIN FACP HVAC Control Panel EU-01~07 EF/HVAC RISER #200 Paint Shop PDP-T007 Other than part of T004 and T006 SAF/WEF/REF etc Detector Pull station Strobe Detector Pull station Strobe :PROCESS :BUILDING Security Office STOP STOP STOP ① ⑤ ④ ⑦ ③ ⑥ PDP-T004 PDP-T006 PU/REF/EAF etc(For Mixing room) :Signal line :Power line RISER For Mixing room RISER For Process (If RISER for Process (sprinkler) is activated) ② 4-2 Interlock Details ⑥ Fan Interlock Stop(#200Paint) 13
  • 15. If the building FACP fire is confirmed (Manual Pull station operation or two or more sensors) 1. Strobe & Phone sound in the hall 2. Send a fire signal to FACP for Process 3. Stop air conditioning ventilation (PDP) 4. PU & REF, part of EAF (machine related to mixing room) will not stop 5. Moved fire signal to MAIN FACP FACP FACP MAIN FACP HVAC Control Panel EF/HVAC RISER #400 Resin Shop PDP-R002 Other than part of SAF/WEF/REF etc Detector Pull station Strobe Detector Pull station Strobe :PROCESS :BUILDING Security Office STOP STOP ② ③ ⑥ ① ⑤ PDP-R002 Part of PU/REF/EAF etc(For Mixing room) :Signal line :Power line RISER For Mixing room RISER For Process (Manual Pull station operation or two or more sensors) STOP 4-2 Interlock Details ⑦ Fan Interlock Stop(#400Resin) 14
  • 16. If the building FACP fire is confirmed (If RISER (sprinkler) is activated) 1. Strobe & Phone sound in the hall 2. Send a fire signal to FACP for Process 3. Stop air conditioning ventilation (PDP) 4. PU & REF, part of EAF (machine related to mixing room) will not stop 5. Moved fire signal to MAIN FACP FACP FACP MAIN FACP HVAC Control Panel EF/HVAC RISER #400 Resin Shop PDP-R002 Other than part of SAF/WEF/REF etc Detector Pull station Strobe Detector Pull station Strobe :PROCESS :BUILDING Security Office STOP STOP ② ③ ⑤ ① ④ PDP-R002 Part of PU/REF/EAF etc(For Mixing room) :Signal line :Power line RISER For Mixing room RISER For Process (If RISER (sprinkler) is activated) STOP 4-2 Interlock Details ⑧ Air Conditioner & Fan Interlock Stop(#400Resin) 15
  • 17. If the building FACP fire is confirmed (When FACP for Process is activated) 1. Receive a fire confirmation signal from FACP for Process 2. Strobe & Phone sound in the hall 3. Stop air conditioning ventilation (PDP) 4. PU & REF, part of EAF (machine related to mixing room) will not stop 5. Moved fire signal to MAIN FACP FACP FACP MAIN FACP HVAC Control Panel EF/HVAC RISER #400 Resin Shop PDP-R002 Other than part of SAF/WEF/REF etc Detector Pull station Strobe Detector Pull station Strobe :PROCESS :BUILDING Security Office STOP STOP ① ③ ⑤ ② ④ PDP-R002 Part of PU/REF/EAF etc(For Mixing room) :Signal line :Power line RISER For Mixing room RISER For Process STOP (When FACP for Process is activated) 4-2 Interlock Details ⑨ Fan Interlock Stop(#400Resin) 16
  • 18. If the building FACP fire is confirmed (When RISER for Mixing room is activated) 1. Strobe & Phone sound in the hall 2. Send a fire signal to FACP for Process 3. Stop air conditioning ventilation (PDP) 4. EU (PDP-T 007) does not stop 5. PU & REF, part of EAF (the machine related to the mixing room) stop 6. Moved fire signal to MAIN FACP FACP FACP MAIN FACP HVAC Control Panel EF/HVAC RISER #400 Resin Shop PDP-R002 Other than part of SAF/WEF/REF etc Detector Pull station Strobe Detector Pull station Strobe :PROCESS :BUILDING Security Office STOP STOP ② ③ ⑥ ① ⑤ PDP-R002 Other than part of PU/REF/EAF etc(For Mixing room) :Signal line :Power line RISER For Mixing room RISER For Process When RISER (sprinkler) for Mixing room is activated STOP 4-2 Interlock Details ⑩ Air Conditioner & Fan Interlock Stop(#400Resin) 17
  • 19. If the building FACP fire is confirmed (If RISER for Process is activated) 1. Send RISER activation signal to FACP for Process 2. Receive a fire confirmation signal from 2FACP for Process 3. Strobe & Phone in the hall 4. Stop air conditioning ventilation (PDP) 5. EU (PDP-T 007) shut down 6. PU & REF, part of EAF (machine related to mixing room) will not stop 7. Moved fire signal to MAIN FACP FACP FACP MAIN FACP HVAC Control Panel EF/HVAC RISER #400 Resin Shop PDP-R002 Other than part of SAF/WEF/REF etc Detector Pull station Strobe Detector Pull station Strobe :PROCESS :BUILDING Security Office STOP STOP ① ④ ⑥ ③ ⑤ PDP-R002 Part of PU/REF/EAF etc(For Mixing room) :Signal line :Power line RISER For Mixing room RISER For Process (If RISER for Process (sprinkler) is activated) ② 4-2 Interlock Details ⑪ Air Conditioner & Fan Interlock Stop(#400Resin) 18
  • 20. Interlocking with LTF Fire pump house FACP RISER Detector Pull station Strobe CP Foam fire control board Main CP Assembly or QC MAIN FACP Security Office :LTF :BUILDING Signal overview 1 Start signal of foam fire extinguishing equipment Send a signal to the adjacent building FACP 2 Output the start signal of foam extinguishing equipment to Main FACP 3 Signals a fire confirmation signal to a foam fire extinguishing control board at the time of building fire Output, stop valve and supply pump ① ② FACP RISER Detector Strobe CP Fire extinguishing pump control board Fire Pump Utility Office MAIN FACP Security Office :LTF :BUILDING Signal overview 1 fire extinguishing pump start signal Signal Utility Office FACP 2 Output the fire pump start signal to Main FACP ① ② Valve Pump ③ STOP STOP 4-2 Interlock Details ⑫ LTF & Fire Pump House Interlock 19