Six Myths about Ontologies: The Basics of Formal Ontology
11164 2013-tmt-revamping sts l.pptx
1. MGM OMG , Officine Meccaniche Galileo s.r.l.
PRESENTATION OF THE MAIN REVAMPING
YEAR 2013-14
Description: n.2 SHIP TO SHORE CRANES FOR TMT
Terminal: TMT, Trieste, Italy
Type of revamping: Heightening, increasing boom length,, new aux trolley, general
maintenance.
Job: 11164
Year: 2013-2014
EPC: OMG
ITALIAN DESIGN, EUROPEAN COMPONENTS
Design made in Italy
M.Mestriner
Deputy Commercial Director
T. +39 0429 77 83 88 / M. +39 345 255 07 10
E. m.mestriner@mbomg.com / omg.mestriner@gmail.com
2. SCOPE OF THE JOB
1.-Total hoist lift, from 47 m to 54 m under spreder
2.-Increase boom lenght from 18 row to 20 row
3.-Increase nominal load from 40t to 45t under spreader
4.-Full NDT test and check of the structure 100%
5.-CE certification full responsability of the cranes
6.-Residual lyfe cycle 1,500,000 cycles
7.-Original crane Reggiane
DELIVERY: 2013/2014, 6/4 MONTHS EACH CRANE
MGM OMG -‐ Revamping of n.2 STS cranes at TMT Port, Italy
3. !
MGM OMG -‐ Revamping of n.2 STS cranes at TMT Port, Italy
4. Area:
10.000
square meters
MGM OMG -‐ Revamping of n.2 STS cranes at TMT Port, Italy
6. MAIN LIFTING EQUIPMENT
Heightening using OMG’s cage.
Cage: designed by OMG, property of OMG.
Nominal load of the cage: 300t/corner
MGM OMG -‐ Revamping of n.2 STS cranes at TMT Port, Italy
7. MGM OMG -‐ Revamping of n.2 STS cranes at TMT Port, Italy