SlideShare a Scribd company logo
1 of 14
Project Selection and Estimating TechniqueSpencer
O’BrienCPMGT/303: Project Estimating and Control
Techniques
August 17, 2020
Dr. Tony J. Taylor
Project Selection and Estimating Technique
As an action, Merriam-Webster.com defines estimating as “to
produce a statement of the approximate cost of” and, an item,
also defines an estimate as “a statement of the cost of work to
be done”. When incorporated into the project environment, the
action of estimating costs is seen as a process of developing an
approximation of the monetary resources need to complete
project activities (Project Management Institute, Inc., 2013).
With the above definitions in mind, the following report defines
two estimating methods, along with their potential for use
within the project setting. These estimating methods, known as
Top-Down Estimating and Bottom-Up Estimating, provide a
forecast of costs to separate aspects of the project.
2
Top-Down Estimating
Top-Down estimating is a project estimating method that
estimates the entire project initially, followed by separate tasks
within the project scope. Being not as specific as Bottom-Up
Estimating, the intent of Top-Down Estimating is to provide an
overall estimate for the assessment and analyzation of whether
the project will coincide within the budget allocated for the
project itself. In simpler terms, Top-Down Estimating is
performed before the project team has been developed, to
provide the authorizing stakeholders an evaluation tool in which
to determine if the project will proceed.
Bottom-Up Estimating
Bottom-Up Estimating is a method in which to determine an
estimated cost by starting with individual tasks, thereby ending
with the overall project cost last. Being detailed in nature, this
method is more commonly used throughout the various project
budget aspects. Bottom-Up Estimating is typically performed
later in the project phases than Top-Down, and in many cases
depends on the work breakdown structure in which to complete.
With the performance of this method being later in the project,
it allows a more specific input from those taking part in the
actual project itself.
Estimating Methods
The Project Management Institute offers us several
techniques in which to assist the above methods, as follows:
· Analogous Estimating – Utilizing data from organizational
assets in the way of lessons learned, Analogous Estimating
“uses the values such as scope, cost, budget, and duration or
measures of scale such as size, weight, and complexity from a
previous, similar project as the basis for estimating the same
parameter or measurement for a current project” (Project
Management Institute, Inc., 2013).
· Expert Judgement – As with the other various project
management groups, the use of expertise judgement can be
utilized, providing the project manager a more factual estimate.
Expert Judgment is just that, and individual (or group) that is
experienced in the field requiring an estimated cost, with their
experience not only in the assumed installation labor hours, but
of the material/associated costs, as well.
· Parametric Estimating – Utilizing data from organizational
assets as well, Parametric Estimating calculates project (or
activity) cost by using the statistical data offered by a project
(or activity) similar in scope and calculating based on the
parameters of the project being estimated. A common method of
Parametric Estimating is to obtain the square footage cost of a
typical (typical in this case meaning one of many) project and
using the cost as a multiplier or unit. This unit would be used to
calculate the new projects cost by determining the its total
square footage and multiplying it by the unit.
· Three-Point Estimating – Three-Point Estimating is a method
in which to determine three separate activity scenarios (Most
likely, Optimistic, Pessimistic) and calculating an average of
their sum, respectively. Before discussing the two separate
averaging calculations, it is first necessary to define the three
activity scenarios:
· Most Likely – If looking at the scenarios as a low, middle, and
high, Most Likely would be the middle. As it is titled, most
likely is the determination of an activity cost as it would “most
likely” be performed, with an obvious level of contingency.
· Optimistic – As its name implies, Optimistic is the low value
scenario, meaning an activity cost based on prime conditions,
with no level of contingency.
· Pessimistic – Being the worst-case scenario for activity cost,
this looks at all the possibilities of risk and supplies cost for the
high end of the calculation.
Moving forward, the two averaging calculations are known as
the Triangular Distribution and the Beta Distribution. The
Triangular Distribution is quite simple, with the sum of the
scenarios being divided by 3, thereby giving an overall average
cost of the activity. The Beta Distribution is somewhat different
in its ability to supply an average that carries the overall weight
of the Most Likely scenario. Beta Distribution is calculated by
obtaining multiplying Most Likely by 4, and then adding
Optimistic and Pessimistic. Being this is the sum of 6 data
inputs, it is averaged by dividing by 6, thereby providing a
weighted average cost of the activity.
Conclusion
Though many means and methods can be determined in
estimating projects, as project managers we must utilize proven
techniques in which to provide accurate estimates, tailored to
meet the various project demanded scenarios, all the while in a
direct and productive manner. Within Top-Down and Bottom-
Up Estimating, and the various techniques given above, these
means and methods should provide just that, a tool in which the
project manager can ensure a successfully performed project.
References
Definition of estimate. https://www.merriam-
webster.com/dictionary/estimating
Project Management Institute, Inc. (2013). A Guide to the
Project Management Body of Knowledge (PMBOK®
Guide) (5th ed.). Newtown Square, PA: Project Management
Institute, Inc.
Week One - Assignment Content
1.
Top of Form
Explain the factors that determine how a company selects a
project.
Differentiate between top-down and bottom-up estimates,
including when each would be used.
· Top-Down – This type of estimating is generally less accurate;
it is used at the beginning of the project when developing the
overall scope statement or project charter for rough orders of
magnitude estimating in general project planning within the
organization. (pg. 197)
· Bottom-Up – This type of estimating is generally more
accurate because it starts at the bottom with the detailed costs
of all specific components of each work activity and
progressively forms the sum of all costs used in estimating the
project budget. (pg.197)
Determine the methods for estimating project costs.
· Analogues Cost Estimating – uses information from previous
project activities that are similar in scope, complexity, and
requirements of deliverable as a comparable for estimating costs
of new project activities. (pg. 193)
· Parametric Cost Estimating – uses the same bases of analogous
estimating from historical data of previous projects and similar
activities but utilizes a statistical or scalable component to
derive a relevant cost estimate. (pg. 194)
· Three-Point Cost estimating – cost information of components
within work activities that would suggest not only one absolute
value, but also a range of value that might represent a variety of
influences that could swing the cost to a positive or negative
direction. Three-point cost estimating utilizes both optimistic
and pessimistic values to calculate an expected cost. (pg. 194-
195)
Explain the types of costs.
· Direct Cost – These costs are associated directly with work
activities required to produce project deliverables. (pg. 190)
· Labor
· Materials
· Equipment
· Consulting
· Travel
· Indirect Costs – These costs include all other operations costs
incurred by the organization to support the production of a
project deliverable. (pg.190)
· Overhead expenses
· Administrative costs
· Indirect labor
· Indirect materials
Format your 700- to 1,050-word paper consistent with APA
guidelines.
Submit the assignment.
Bottom of Form
Reference
Wilson, R. (2014). A Comprehensive Guide to Project
Management Schedule and Cost Control: Methods and Models
for Managing the Project Lifecycle.
Week One
-
Assignment Content
1.
Explain
the factors that determine how a company selects a project.
Differentiate
between top
-
down and bottom
-
up estimates, including when each would be used.
·
Top
-
Down
–
This type of estimating is
generally less accurate; it is used at the beginning of the
project when developing the overall scope statement or project
charter for rough orders of
magnitude estimating in general project planning within the
organization.
(pg. 197)
·
Bottom
-
Up
–
This typ
e of estimating is generally more accurate because it starts at
the bottom
with the detailed costs of all specific components of each work
activity and progressively forms
the sum of all costs used in estimating the project budget.
(pg.197)
Determine
the
methods for estimating project costs.
·
Analogues
Cost Estimating
–
uses information from previous project activities that are
similar
in scope, complexity, and requirements of deliverable as a
comparable for estimating costs of
new project activities.
(pg. 193)
·
Parametric Cost Estimating
–
uses the same bases of analogou
s estimating from historical data
of previous projects and similar activities but utilizes a
statistical or scalable component to
derive a relevant cost estimate.
(pg. 194)
·
Three
-
Point Cost estimating
–
cost information of components within work activities that
would suggest not only one absolute value, but also a range of
value that might represent a
variety of influences that could swing the cost to a positive or
negative direction. Three
-
point
cost es
timating utilizes both
optimistic
and
pessimistic
values to calculate an expected cost.
(pg.
194
-
195)
Explain
the types of costs.
·
Direct Cost
–
These
costs are
associated
directly with
work activities required to produce
project
deliverables
.
(pg. 190)
o
Labor
o
Materials
o
E
quipment
o
Consulting
o
Travel
·
Indirect Costs
–
These costs
include all other operations cost
s incurred by the organization to
support the production of a project
deliverable
.
(pg.190)
o
Overhead expenses
o
Administrative costs
o
Indirect labor
o
Indirect materials
Format
your 700
-
to 1,050
-
word paper consistent with APA guidelines.
Submit
the assignment.
Week One - Assignment Content
1.
Explain the factors that determine how a company selects a
project.
Differentiate between top-down and bottom-up estimates,
including when each would be used.
-Down – This type of estimating is generally less
accurate; it is used at the beginning of the
project when developing the overall scope statement or project
charter for rough orders of
magnitude estimating in general project planning within the
organization. (pg. 197)
-Up – This type of estimating is generally more
accurate because it starts at the bottom
with the detailed costs of all specific components of each work
activity and progressively forms
the sum of all costs used in estimating the project budget.
(pg.197)
Determine the methods for estimating project costs.
Analogues Cost Estimating – uses information from previous
project activities that are similar
in scope, complexity, and requirements of deliverable as a
comparable for estimating costs of
new project activities. (pg. 193)
– uses the same bases of
analogous estimating from historical data
of previous projects and similar activities but utilizes a
statistical or scalable component to
derive a relevant cost estimate. (pg. 194)
-Point Cost estimating – cost information of
components within work activities that
would suggest not only one absolute value, but also a range of
value that might represent a
variety of influences that could swing the cost to a positive or
negative direction. Three-point
cost estimating utilizes both optimistic and pessimistic values to
calculate an expected cost. (pg.
194-195)
Explain the types of costs.
– These costs are associated directly with work
activities required to produce
project deliverables. (pg. 190)
o Labor
o Materials
o Equipment
o Consulting
o Travel
– These costs include all other operations costs
incurred by the organization to
support the production of a project deliverable. (pg.190)
o Overhead expenses
o Administrative costs
o Indirect labor
o Indirect materials
Format your 700- to 1,050-word paper consistent with APA
guidelines.
Submit the assignment.

More Related Content

What's hot

PM Notebook - Appendix H - Formula Sheet
PM Notebook - Appendix H - Formula SheetPM Notebook - Appendix H - Formula Sheet
PM Notebook - Appendix H - Formula SheetMohammad Elsheimy
 
Quality Assurance and Cost Control for Construction
Quality Assurance and Cost Control for ConstructionQuality Assurance and Cost Control for Construction
Quality Assurance and Cost Control for ConstructionRich Purtell
 
ForecastIT 1. Introduction to Forecasting
ForecastIT 1. Introduction to ForecastingForecastIT 1. Introduction to Forecasting
ForecastIT 1. Introduction to ForecastingDeepThought, Inc.
 
Project Cost.pdf
Project Cost.pdfProject Cost.pdf
Project Cost.pdf341741357
 
FORECASTING
FORECASTINGFORECASTING
FORECASTINGkzoe1996
 
Measurements Methods of forecasting errors
Measurements Methods of forecasting errorsMeasurements Methods of forecasting errors
Measurements Methods of forecasting errorsVikram Kadari
 
Forecasting Models & Their Applications
Forecasting Models & Their ApplicationsForecasting Models & Their Applications
Forecasting Models & Their ApplicationsMahmudul Hasan
 
Mba ii pmom_unit-1.3 forecasting a
Mba ii pmom_unit-1.3 forecasting aMba ii pmom_unit-1.3 forecasting a
Mba ii pmom_unit-1.3 forecasting aRai University
 
Project cost & control
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
 
PM Notebook - Appendix C - Data Representation Tools
PM Notebook - Appendix C - Data Representation ToolsPM Notebook - Appendix C - Data Representation Tools
PM Notebook - Appendix C - Data Representation ToolsMohammad Elsheimy
 

What's hot (20)

PM Notebook - Appendix H - Formula Sheet
PM Notebook - Appendix H - Formula SheetPM Notebook - Appendix H - Formula Sheet
PM Notebook - Appendix H - Formula Sheet
 
Quality Assurance and Cost Control for Construction
Quality Assurance and Cost Control for ConstructionQuality Assurance and Cost Control for Construction
Quality Assurance and Cost Control for Construction
 
ForecastIT 1. Introduction to Forecasting
ForecastIT 1. Introduction to ForecastingForecastIT 1. Introduction to Forecasting
ForecastIT 1. Introduction to Forecasting
 
Project Cost.pdf
Project Cost.pdfProject Cost.pdf
Project Cost.pdf
 
FORECASTING
FORECASTINGFORECASTING
FORECASTING
 
FORECASTING MODELS
FORECASTING MODELSFORECASTING MODELS
FORECASTING MODELS
 
Measurements Methods of forecasting errors
Measurements Methods of forecasting errorsMeasurements Methods of forecasting errors
Measurements Methods of forecasting errors
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Forecasting Models & Their Applications
Forecasting Models & Their ApplicationsForecasting Models & Their Applications
Forecasting Models & Their Applications
 
PERT
PERTPERT
PERT
 
Mba ii pmom_unit-1.3 forecasting a
Mba ii pmom_unit-1.3 forecasting aMba ii pmom_unit-1.3 forecasting a
Mba ii pmom_unit-1.3 forecasting a
 
Cost management
Cost managementCost management
Cost management
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Forecasting
ForecastingForecasting
Forecasting
 
05 forecasting
05 forecasting05 forecasting
05 forecasting
 
Chapter 13
Chapter 13Chapter 13
Chapter 13
 
Focus forecasting bmb
Focus forecasting bmbFocus forecasting bmb
Focus forecasting bmb
 
M&l case
M&l caseM&l case
M&l case
 
PM Notebook - Appendix C - Data Representation Tools
PM Notebook - Appendix C - Data Representation ToolsPM Notebook - Appendix C - Data Representation Tools
PM Notebook - Appendix C - Data Representation Tools
 
Chapter 3_OM
Chapter 3_OMChapter 3_OM
Chapter 3_OM
 

Similar to Project selection and estimating technique spencer o’briencpmgt303

Cost management
Cost managementCost management
Cost managementshkadry
 
Project Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project EstimationProject Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project EstimationVandalRay
 
PM Estimation techniques
PM Estimation techniquesPM Estimation techniques
PM Estimation techniquesChander Parkash
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration EstimationHarsh Behl
 
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
 WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES? WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?MirzaNuman1
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templatesHoa PN Thaycacac
 
Constructiion cost estimating 2017
Constructiion cost estimating 2017Constructiion cost estimating 2017
Constructiion cost estimating 2017Peter Cholakis
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxSudipBalLama
 
Web Engineering - Web Effort Estimation
Web Engineering - Web Effort EstimationWeb Engineering - Web Effort Estimation
Web Engineering - Web Effort EstimationNosheen Qamar
 
Top down
Top downTop down
Top downNino Ho
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxDr. ABEER KHALID MANSOUR
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimationSomashekar S.M
 
software-project-management-unit-2.ppt
software-project-management-unit-2.pptsoftware-project-management-unit-2.ppt
software-project-management-unit-2.pptMaanbahadurkhadka
 
software-project-management-unit-2-220808125214-00921612 (1).pdf
software-project-management-unit-2-220808125214-00921612 (1).pdfsoftware-project-management-unit-2-220808125214-00921612 (1).pdf
software-project-management-unit-2-220808125214-00921612 (1).pdfVinoth Kumar
 
Introduction of civil engineering.pdf
Introduction of civil engineering.pdfIntroduction of civil engineering.pdf
Introduction of civil engineering.pdfbkbk37
 

Similar to Project selection and estimating technique spencer o’briencpmgt303 (20)

Cost management
Cost managementCost management
Cost management
 
Project Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project EstimationProject Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project Estimation
 
PM Estimation techniques
PM Estimation techniquesPM Estimation techniques
PM Estimation techniques
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration Estimation
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
 WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES? WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
 
Project mgt
Project mgtProject mgt
Project mgt
 
Term paper spm
Term paper spmTerm paper spm
Term paper spm
 
Sm presentation
Sm presentationSm presentation
Sm presentation
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templates
 
Constructiion cost estimating 2017
Constructiion cost estimating 2017Constructiion cost estimating 2017
Constructiion cost estimating 2017
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptx
 
Web Engineering - Web Effort Estimation
Web Engineering - Web Effort EstimationWeb Engineering - Web Effort Estimation
Web Engineering - Web Effort Estimation
 
Top down
Top downTop down
Top down
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptx
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
software-project-management-unit-2.ppt
software-project-management-unit-2.pptsoftware-project-management-unit-2.ppt
software-project-management-unit-2.ppt
 
software-project-management-unit-2-220808125214-00921612 (1).pdf
software-project-management-unit-2-220808125214-00921612 (1).pdfsoftware-project-management-unit-2-220808125214-00921612 (1).pdf
software-project-management-unit-2-220808125214-00921612 (1).pdf
 
Introduction of civil engineering.pdf
Introduction of civil engineering.pdfIntroduction of civil engineering.pdf
Introduction of civil engineering.pdf
 

More from MARK547399

After watching the video on Earmarks httpswww.khanacademy..docx
After watching the video on Earmarks httpswww.khanacademy..docxAfter watching the video on Earmarks httpswww.khanacademy..docx
After watching the video on Earmarks httpswww.khanacademy..docxMARK547399
 
After watching City of God (Brazil, 2002) and reading Chapter 8 .docx
After watching City of God (Brazil, 2002) and reading Chapter 8 .docxAfter watching City of God (Brazil, 2002) and reading Chapter 8 .docx
After watching City of God (Brazil, 2002) and reading Chapter 8 .docxMARK547399
 
After watching the video, Ten Strategies of a World-Class Comp.docx
After watching the video, Ten Strategies of a World-Class Comp.docxAfter watching the video, Ten Strategies of a World-Class Comp.docx
After watching the video, Ten Strategies of a World-Class Comp.docxMARK547399
 
After the recent security breach, Always Fresh decided to form a com.docx
After the recent security breach, Always Fresh decided to form a com.docxAfter the recent security breach, Always Fresh decided to form a com.docx
After the recent security breach, Always Fresh decided to form a com.docxMARK547399
 
After taking this course and learning about various art forms, d.docx
After taking this course and learning about various art forms, d.docxAfter taking this course and learning about various art forms, d.docx
After taking this course and learning about various art forms, d.docxMARK547399
 
After watching the documentary Citizenfour and completing the re.docx
After watching the documentary Citizenfour and completing the re.docxAfter watching the documentary Citizenfour and completing the re.docx
After watching the documentary Citizenfour and completing the re.docxMARK547399
 
After watching the George Méliès film A Trip to the Moon (1.docx
After watching the George Méliès film A Trip to the Moon (1.docxAfter watching the George Méliès film A Trip to the Moon (1.docx
After watching the George Méliès film A Trip to the Moon (1.docxMARK547399
 
After reviewing your latest submission, the CIO has found some areas.docx
After reviewing your latest submission, the CIO has found some areas.docxAfter reviewing your latest submission, the CIO has found some areas.docx
After reviewing your latest submission, the CIO has found some areas.docxMARK547399
 
After watching the video, Euro Doomed Bloomberg QuickTakes, do some.docx
After watching the video, Euro Doomed Bloomberg QuickTakes, do some.docxAfter watching the video, Euro Doomed Bloomberg QuickTakes, do some.docx
After watching the video, Euro Doomed Bloomberg QuickTakes, do some.docxMARK547399
 
After watching Adam Driver’s TED talk about his journey from bei.docx
After watching Adam Driver’s TED talk about his journey from bei.docxAfter watching Adam Driver’s TED talk about his journey from bei.docx
After watching Adam Driver’s TED talk about his journey from bei.docxMARK547399
 
After watching all the films in Week Two’s content (with the excepti.docx
After watching all the films in Week Two’s content (with the excepti.docxAfter watching all the films in Week Two’s content (with the excepti.docx
After watching all the films in Week Two’s content (with the excepti.docxMARK547399
 
After time traveling through many periods in some of our oldest .docx
After time traveling through many periods in some of our oldest .docxAfter time traveling through many periods in some of our oldest .docx
After time traveling through many periods in some of our oldest .docxMARK547399
 
After studying the course materials located on Module 1., answer.docx
After studying the course materials located on Module 1., answer.docxAfter studying the course materials located on Module 1., answer.docx
After studying the course materials located on Module 1., answer.docxMARK547399
 
After reviewing your latest submission, the CIO has found some a.docx
After reviewing your latest submission, the CIO has found some a.docxAfter reviewing your latest submission, the CIO has found some a.docx
After reviewing your latest submission, the CIO has found some a.docxMARK547399
 
After reviewing Zinns and Schweikarts personal assumptions, belief.docx
After reviewing Zinns and Schweikarts personal assumptions, belief.docxAfter reviewing Zinns and Schweikarts personal assumptions, belief.docx
After reviewing Zinns and Schweikarts personal assumptions, belief.docxMARK547399
 
After reviewing the resources provided, do you believe that we posse.docx
After reviewing the resources provided, do you believe that we posse.docxAfter reviewing the resources provided, do you believe that we posse.docx
After reviewing the resources provided, do you believe that we posse.docxMARK547399
 
After reading The Successful Organization Keeping the Talent .docx
After reading The Successful Organization Keeping the Talent .docxAfter reading The Successful Organization Keeping the Talent .docx
After reading The Successful Organization Keeping the Talent .docxMARK547399
 
After reviewing the policy brief by the Urban Institute on the pros .docx
After reviewing the policy brief by the Urban Institute on the pros .docxAfter reviewing the policy brief by the Urban Institute on the pros .docx
After reviewing the policy brief by the Urban Institute on the pros .docxMARK547399
 
After reflecting on this week’s overview and textbook reading, discu.docx
After reflecting on this week’s overview and textbook reading, discu.docxAfter reflecting on this week’s overview and textbook reading, discu.docx
After reflecting on this week’s overview and textbook reading, discu.docxMARK547399
 
After reading this weeks resources including Ready or Not Protecti.docx
After reading this weeks resources including Ready or Not Protecti.docxAfter reading this weeks resources including Ready or Not Protecti.docx
After reading this weeks resources including Ready or Not Protecti.docxMARK547399
 

More from MARK547399 (20)

After watching the video on Earmarks httpswww.khanacademy..docx
After watching the video on Earmarks httpswww.khanacademy..docxAfter watching the video on Earmarks httpswww.khanacademy..docx
After watching the video on Earmarks httpswww.khanacademy..docx
 
After watching City of God (Brazil, 2002) and reading Chapter 8 .docx
After watching City of God (Brazil, 2002) and reading Chapter 8 .docxAfter watching City of God (Brazil, 2002) and reading Chapter 8 .docx
After watching City of God (Brazil, 2002) and reading Chapter 8 .docx
 
After watching the video, Ten Strategies of a World-Class Comp.docx
After watching the video, Ten Strategies of a World-Class Comp.docxAfter watching the video, Ten Strategies of a World-Class Comp.docx
After watching the video, Ten Strategies of a World-Class Comp.docx
 
After the recent security breach, Always Fresh decided to form a com.docx
After the recent security breach, Always Fresh decided to form a com.docxAfter the recent security breach, Always Fresh decided to form a com.docx
After the recent security breach, Always Fresh decided to form a com.docx
 
After taking this course and learning about various art forms, d.docx
After taking this course and learning about various art forms, d.docxAfter taking this course and learning about various art forms, d.docx
After taking this course and learning about various art forms, d.docx
 
After watching the documentary Citizenfour and completing the re.docx
After watching the documentary Citizenfour and completing the re.docxAfter watching the documentary Citizenfour and completing the re.docx
After watching the documentary Citizenfour and completing the re.docx
 
After watching the George Méliès film A Trip to the Moon (1.docx
After watching the George Méliès film A Trip to the Moon (1.docxAfter watching the George Méliès film A Trip to the Moon (1.docx
After watching the George Méliès film A Trip to the Moon (1.docx
 
After reviewing your latest submission, the CIO has found some areas.docx
After reviewing your latest submission, the CIO has found some areas.docxAfter reviewing your latest submission, the CIO has found some areas.docx
After reviewing your latest submission, the CIO has found some areas.docx
 
After watching the video, Euro Doomed Bloomberg QuickTakes, do some.docx
After watching the video, Euro Doomed Bloomberg QuickTakes, do some.docxAfter watching the video, Euro Doomed Bloomberg QuickTakes, do some.docx
After watching the video, Euro Doomed Bloomberg QuickTakes, do some.docx
 
After watching Adam Driver’s TED talk about his journey from bei.docx
After watching Adam Driver’s TED talk about his journey from bei.docxAfter watching Adam Driver’s TED talk about his journey from bei.docx
After watching Adam Driver’s TED talk about his journey from bei.docx
 
After watching all the films in Week Two’s content (with the excepti.docx
After watching all the films in Week Two’s content (with the excepti.docxAfter watching all the films in Week Two’s content (with the excepti.docx
After watching all the films in Week Two’s content (with the excepti.docx
 
After time traveling through many periods in some of our oldest .docx
After time traveling through many periods in some of our oldest .docxAfter time traveling through many periods in some of our oldest .docx
After time traveling through many periods in some of our oldest .docx
 
After studying the course materials located on Module 1., answer.docx
After studying the course materials located on Module 1., answer.docxAfter studying the course materials located on Module 1., answer.docx
After studying the course materials located on Module 1., answer.docx
 
After reviewing your latest submission, the CIO has found some a.docx
After reviewing your latest submission, the CIO has found some a.docxAfter reviewing your latest submission, the CIO has found some a.docx
After reviewing your latest submission, the CIO has found some a.docx
 
After reviewing Zinns and Schweikarts personal assumptions, belief.docx
After reviewing Zinns and Schweikarts personal assumptions, belief.docxAfter reviewing Zinns and Schweikarts personal assumptions, belief.docx
After reviewing Zinns and Schweikarts personal assumptions, belief.docx
 
After reviewing the resources provided, do you believe that we posse.docx
After reviewing the resources provided, do you believe that we posse.docxAfter reviewing the resources provided, do you believe that we posse.docx
After reviewing the resources provided, do you believe that we posse.docx
 
After reading The Successful Organization Keeping the Talent .docx
After reading The Successful Organization Keeping the Talent .docxAfter reading The Successful Organization Keeping the Talent .docx
After reading The Successful Organization Keeping the Talent .docx
 
After reviewing the policy brief by the Urban Institute on the pros .docx
After reviewing the policy brief by the Urban Institute on the pros .docxAfter reviewing the policy brief by the Urban Institute on the pros .docx
After reviewing the policy brief by the Urban Institute on the pros .docx
 
After reflecting on this week’s overview and textbook reading, discu.docx
After reflecting on this week’s overview and textbook reading, discu.docxAfter reflecting on this week’s overview and textbook reading, discu.docx
After reflecting on this week’s overview and textbook reading, discu.docx
 
After reading this weeks resources including Ready or Not Protecti.docx
After reading this weeks resources including Ready or Not Protecti.docxAfter reading this weeks resources including Ready or Not Protecti.docx
After reading this weeks resources including Ready or Not Protecti.docx
 

Recently uploaded

call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.arsicmarija21
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxsqpmdrvczh
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptxSherlyMaeNeri
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 

Recently uploaded (20)

call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptx
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 

Project selection and estimating technique spencer o’briencpmgt303

  • 1. Project Selection and Estimating TechniqueSpencer O’BrienCPMGT/303: Project Estimating and Control Techniques August 17, 2020 Dr. Tony J. Taylor Project Selection and Estimating Technique As an action, Merriam-Webster.com defines estimating as “to produce a statement of the approximate cost of” and, an item, also defines an estimate as “a statement of the cost of work to be done”. When incorporated into the project environment, the action of estimating costs is seen as a process of developing an approximation of the monetary resources need to complete project activities (Project Management Institute, Inc., 2013). With the above definitions in mind, the following report defines two estimating methods, along with their potential for use within the project setting. These estimating methods, known as Top-Down Estimating and Bottom-Up Estimating, provide a forecast of costs to separate aspects of the project. 2 Top-Down Estimating Top-Down estimating is a project estimating method that estimates the entire project initially, followed by separate tasks within the project scope. Being not as specific as Bottom-Up Estimating, the intent of Top-Down Estimating is to provide an overall estimate for the assessment and analyzation of whether the project will coincide within the budget allocated for the project itself. In simpler terms, Top-Down Estimating is performed before the project team has been developed, to provide the authorizing stakeholders an evaluation tool in which to determine if the project will proceed. Bottom-Up Estimating
  • 2. Bottom-Up Estimating is a method in which to determine an estimated cost by starting with individual tasks, thereby ending with the overall project cost last. Being detailed in nature, this method is more commonly used throughout the various project budget aspects. Bottom-Up Estimating is typically performed later in the project phases than Top-Down, and in many cases depends on the work breakdown structure in which to complete. With the performance of this method being later in the project, it allows a more specific input from those taking part in the actual project itself. Estimating Methods The Project Management Institute offers us several techniques in which to assist the above methods, as follows: · Analogous Estimating – Utilizing data from organizational assets in the way of lessons learned, Analogous Estimating “uses the values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter or measurement for a current project” (Project Management Institute, Inc., 2013). · Expert Judgement – As with the other various project management groups, the use of expertise judgement can be utilized, providing the project manager a more factual estimate. Expert Judgment is just that, and individual (or group) that is experienced in the field requiring an estimated cost, with their experience not only in the assumed installation labor hours, but of the material/associated costs, as well. · Parametric Estimating – Utilizing data from organizational assets as well, Parametric Estimating calculates project (or activity) cost by using the statistical data offered by a project (or activity) similar in scope and calculating based on the parameters of the project being estimated. A common method of Parametric Estimating is to obtain the square footage cost of a typical (typical in this case meaning one of many) project and using the cost as a multiplier or unit. This unit would be used to
  • 3. calculate the new projects cost by determining the its total square footage and multiplying it by the unit. · Three-Point Estimating – Three-Point Estimating is a method in which to determine three separate activity scenarios (Most likely, Optimistic, Pessimistic) and calculating an average of their sum, respectively. Before discussing the two separate averaging calculations, it is first necessary to define the three activity scenarios: · Most Likely – If looking at the scenarios as a low, middle, and high, Most Likely would be the middle. As it is titled, most likely is the determination of an activity cost as it would “most likely” be performed, with an obvious level of contingency. · Optimistic – As its name implies, Optimistic is the low value scenario, meaning an activity cost based on prime conditions, with no level of contingency. · Pessimistic – Being the worst-case scenario for activity cost, this looks at all the possibilities of risk and supplies cost for the high end of the calculation. Moving forward, the two averaging calculations are known as the Triangular Distribution and the Beta Distribution. The Triangular Distribution is quite simple, with the sum of the scenarios being divided by 3, thereby giving an overall average cost of the activity. The Beta Distribution is somewhat different in its ability to supply an average that carries the overall weight of the Most Likely scenario. Beta Distribution is calculated by obtaining multiplying Most Likely by 4, and then adding Optimistic and Pessimistic. Being this is the sum of 6 data inputs, it is averaged by dividing by 6, thereby providing a weighted average cost of the activity. Conclusion Though many means and methods can be determined in estimating projects, as project managers we must utilize proven techniques in which to provide accurate estimates, tailored to meet the various project demanded scenarios, all the while in a direct and productive manner. Within Top-Down and Bottom-
  • 4. Up Estimating, and the various techniques given above, these means and methods should provide just that, a tool in which the project manager can ensure a successfully performed project. References Definition of estimate. https://www.merriam- webster.com/dictionary/estimating Project Management Institute, Inc. (2013). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (5th ed.). Newtown Square, PA: Project Management Institute, Inc. Week One - Assignment Content 1. Top of Form Explain the factors that determine how a company selects a project. Differentiate between top-down and bottom-up estimates, including when each would be used. · Top-Down – This type of estimating is generally less accurate; it is used at the beginning of the project when developing the overall scope statement or project charter for rough orders of magnitude estimating in general project planning within the organization. (pg. 197)
  • 5. · Bottom-Up – This type of estimating is generally more accurate because it starts at the bottom with the detailed costs of all specific components of each work activity and progressively forms the sum of all costs used in estimating the project budget. (pg.197) Determine the methods for estimating project costs. · Analogues Cost Estimating – uses information from previous project activities that are similar in scope, complexity, and requirements of deliverable as a comparable for estimating costs of new project activities. (pg. 193) · Parametric Cost Estimating – uses the same bases of analogous estimating from historical data of previous projects and similar activities but utilizes a statistical or scalable component to derive a relevant cost estimate. (pg. 194) · Three-Point Cost estimating – cost information of components within work activities that would suggest not only one absolute value, but also a range of value that might represent a variety of influences that could swing the cost to a positive or negative direction. Three-point cost estimating utilizes both optimistic and pessimistic values to calculate an expected cost. (pg. 194- 195) Explain the types of costs. · Direct Cost – These costs are associated directly with work activities required to produce project deliverables. (pg. 190) · Labor · Materials · Equipment · Consulting · Travel · Indirect Costs – These costs include all other operations costs incurred by the organization to support the production of a
  • 6. project deliverable. (pg.190) · Overhead expenses · Administrative costs · Indirect labor · Indirect materials Format your 700- to 1,050-word paper consistent with APA guidelines. Submit the assignment. Bottom of Form Reference Wilson, R. (2014). A Comprehensive Guide to Project Management Schedule and Cost Control: Methods and Models for Managing the Project Lifecycle. Week One - Assignment Content 1. Explain the factors that determine how a company selects a project. Differentiate
  • 7. between top - down and bottom - up estimates, including when each would be used. · Top - Down – This type of estimating is generally less accurate; it is used at the beginning of the project when developing the overall scope statement or project charter for rough orders of magnitude estimating in general project planning within the organization. (pg. 197) · Bottom - Up – This typ e of estimating is generally more accurate because it starts at the bottom
  • 8. with the detailed costs of all specific components of each work activity and progressively forms the sum of all costs used in estimating the project budget. (pg.197) Determine the methods for estimating project costs. · Analogues Cost Estimating – uses information from previous project activities that are similar in scope, complexity, and requirements of deliverable as a comparable for estimating costs of new project activities. (pg. 193) · Parametric Cost Estimating – uses the same bases of analogou s estimating from historical data of previous projects and similar activities but utilizes a
  • 9. statistical or scalable component to derive a relevant cost estimate. (pg. 194) · Three - Point Cost estimating – cost information of components within work activities that would suggest not only one absolute value, but also a range of value that might represent a variety of influences that could swing the cost to a positive or negative direction. Three - point cost es timating utilizes both optimistic and pessimistic values to calculate an expected cost. (pg. 194 - 195) Explain the types of costs.
  • 10. · Direct Cost – These costs are associated directly with work activities required to produce project deliverables . (pg. 190) o Labor o Materials o E quipment o Consulting
  • 11. o Travel · Indirect Costs – These costs include all other operations cost s incurred by the organization to support the production of a project deliverable . (pg.190) o Overhead expenses o Administrative costs o Indirect labor o Indirect materials
  • 12. Format your 700 - to 1,050 - word paper consistent with APA guidelines. Submit the assignment. Week One - Assignment Content 1. Explain the factors that determine how a company selects a project. Differentiate between top-down and bottom-up estimates, including when each would be used. -Down – This type of estimating is generally less accurate; it is used at the beginning of the project when developing the overall scope statement or project charter for rough orders of magnitude estimating in general project planning within the organization. (pg. 197) -Up – This type of estimating is generally more accurate because it starts at the bottom with the detailed costs of all specific components of each work activity and progressively forms the sum of all costs used in estimating the project budget.
  • 13. (pg.197) Determine the methods for estimating project costs. Analogues Cost Estimating – uses information from previous project activities that are similar in scope, complexity, and requirements of deliverable as a comparable for estimating costs of new project activities. (pg. 193) – uses the same bases of analogous estimating from historical data of previous projects and similar activities but utilizes a statistical or scalable component to derive a relevant cost estimate. (pg. 194) -Point Cost estimating – cost information of components within work activities that would suggest not only one absolute value, but also a range of value that might represent a variety of influences that could swing the cost to a positive or negative direction. Three-point cost estimating utilizes both optimistic and pessimistic values to calculate an expected cost. (pg. 194-195) Explain the types of costs. – These costs are associated directly with work activities required to produce project deliverables. (pg. 190) o Labor o Materials o Equipment o Consulting o Travel – These costs include all other operations costs
  • 14. incurred by the organization to support the production of a project deliverable. (pg.190) o Overhead expenses o Administrative costs o Indirect labor o Indirect materials Format your 700- to 1,050-word paper consistent with APA guidelines. Submit the assignment.