SlideShare a Scribd company logo
1 of 49
SPRING BOX
Using the following presentation
assumes that individuals have a basic
knowledge of construction. The user
should be able to adjust
measurements and quantities
depending on their specific site
requirements. The exact
measurements will depend on the
site specific design criteria, but at a
minimum, the spring box should have
three PVC pipes exiting the box (one
for the main line, one for future
expansion, and one overflow) and an
access door. Cement should be mixed
to local specifications depending on
the type of materials available.
Disclaimer
Materials
•1 tube (6m) PVC pipe
•The size of pipe will be a function of the flow from
the spring
• Three or Four PVC elbows of size equal to tube
•2 lbs of tie wire
• 100kg of 3/8” reinforcing rods (rebar)
• Twenty (20) x 50kg bags cement
• 2 cubic meter sand
• 2 cubic meters gravel
•5 cubic meters large stone (15+ cm diameter)
•1 lb of 2-1/2” nail
•1 lb of 4” nails
•Three (3) wood boards 10” x 3/4” x 12’
•Six (6) wood boards 2” x 4” x 6’
•One (1) wood post 3” x 3” x 6’
•One (1) 2” bronze lock for access door
• Once the spring has been
identified, determine a
convenient location to build
the spring box wall. In this case
where the banks of the pool
narrowed into a stream.
• clear away as much of the
rocks and foliage as possible,
both within the spring pool and
the surrounding banks.
Getting Started
• It is important to have several areas flattened
for work
• A flat area, approximately 2.5m, in diameter will
be needed for mixing concrete
•Space should be cleared to store sand and
gravel
• The area where the spring comes to the
surface should be dug out, flattened, and all
large stones (greater than 10cm diameter)
should be removed
Getting Started
Site Preparation
Flatten an area for mixing of concrete
Remove all stones and level the area
Where the spring surfaces
Sand storage area
Gravel Storage Area
• Once the spring has
been cleared of
debris, begin to fill it
with rocks, starting
from the spring
source Spring Source
Spring cleared of all debris
and made level, ready to
place stones
Getting Started
Preparing the Spring
Spring Surfaces,
water flows in this
direction
Preparing the Spring
Spring Surfaces,
water flows in this
direction
Fill this area with
stone
An area should be left clear in this
location approximately 1m x 1m x
0.7m depth. This space will be used
to construct a box where water will
collect before exiting the box.
Continue to fill the spring with large
stone (15cm-50cm diameter) until the
area is filled and matches the
contours of the surrounding land
Preparing the Spring
• Dig two trenches on either side of the spring to
be filled with cement. The “wings” will serve to
capture groundwater into the spring box
The “Wings”
Trench or “Wing”
Trenches dug to either
side of the spring
Try to maintain a 40cm to 50cm
width for the trench. It is okay if the
trench becomes wider. Sometimes
it is necessary to widen the trench
to remove large stones.
“Wing” or trench
“Wing” or trench
Next slide shown
looking into trench
If possible, continue
digging away from the
spring until water is no
longer seeping in from the
end of the trench here
Water should not being
seeping in from this wall
Spring source
Layout
1m
As Needed
AsNeeded
This area should be
flat and free of any
large stones
Spring Surfaces,
water flows in this
direction
PVC pipe exiting the spring box with
elbow turned upwards at this end
Constructing the spring box wall
Spring Box Wall Locations
Concrete
Trench
•Build a mold that will fit inside the
trench and across the front wall of
the spring box
•The form should provide a wall
thickness of at least 10cm
•A rebar frame should be built that
will fit inside the form
•It will be placed in the center of the
mold, allowing 5cm clear cover
between the form walls on all sides
Front Wall
Attach the rods using
small pieces of metal
wire, ensuring that once
tied, there are no sharp
tails left.
For rods that are
parallel to each other, a
simple wrap round and
twist with a pair of pliers,
will be sufficient
How to Tie Rebar
For rods that are
perpendicular to each other
use an “iron workers knot “
illustrated in the pictures
opposite.
How to Tie Rebar
• Construct a wooden form for the
spring box wall. It should be large
enough to span the three sides of the
spring box. The form for the front wall
should have holes cut in the center at
the bottom of the form to allow PVC
Pipe (minimum 3 tubes) to fit through
• Construct the rebar frame to fit inside
the form
• Leave holes in the bottom of the
frame for PVC Pipe (minimum 3 tubes)
Rebar Wall Frame (Plan)
1m
AsNeeded
AsNeeded
•The rebar frame should be built to fit
inside the wooden form, matching the
contour of the trenches
•5cm clear cover should be maintained
between rebar and wooden mold for
concrete
Rebar Wall Frame (Elevation)
Space left open for
PVC tubing
Maintain 10cm spacing, number of bars will vary
Maintain10cmspacing,numberof
barswillvary
Rebar Wall Frame
Trench
Trench
Area dug out,
stones removed,
then refilled with
stone (15-50cm
diameter)
Hole in place for
tubing
• Place the form walls
across the stream
• Insert the rebar
frame within the
form walls, ensuring
that the holes
through which the
tubes will fit, are
aligned
• Insert the at least
three tubes through
the holes.
• The tubing will have
a 90° elbow attached
to the end contained
within the spring box.
• One tube will be used as an
overflow. Be sure this pipe
sits with the top of the
elbow (where water will
enter) at least 10cm above
the other tubes. You may
need to place sand or
pebbles under them to
ensure this is the case.
• Block gaps left between the
tubes and the hole cut into
the mould walls. In this case,
empty cement bags were
used.
• Ensure that the
mould walls are
supported so they do
not collapse under
the weight of the
cement
• Remaining wood
boards can be used
and stones are make
good supports
• Pour dry cement into the
bottom of the form to
absorb standing water
• Now, add wet cement until
the mould is full
• The mix should be 3 parts
gravel to 1 part sand to one
part cement by volume
Preparing the Spring
Spring Surfaces,
water flows in this
direction
This area filled
with stone
Place rocks in order to create a box
1m x 1m x 0.7m depth. Water will
collect in this area before exiting the
spring capture box.
• Continue to add
rocks to create a box
• The dimensions
should be
approximately L 1m x
W 1m x D 70cm
• Build the roof over the
pool to the same level as
the surrounding rocks
• Be sure to score the
wood in the area of the
access door
• You must be able to
break out the wood in
this area with a hammer
• See following slides for
more information
• Place a box with the dimensions of
30cm x 30cm x 30cm over the roof
of the tank, above the tubing, to
provide space to insert the access
door
• The wood in the area under the
form should be precut along the
edges of the access door
• The roof will be covered with
concrete except in this area.
• The precut sections of wood can
be knocked out with a hammer
after concrete has sufficiently
cured
• The door will lift off from this
spot, and you must be able to
enter the spring box from this
spot.
Rebar Roof Frame
Access Door Form in Place
Trench
Trench
Trench
Trench
Rebar Roof frame in Place
Rebar Roof Frame (Front View)
Access Door Form in Place
Trench
Trench
Rebar Roof Frame (Plan)
Maintain 10cm spacing, number of bars will vary
Maintain10cmspacing,numberof
barswillvary
Rebar Roof Frame (Elevation)
Maintain 10cm to 20cm spacing, number of bars will vary
Maintain20cm
spacing,numberof
barswillvary
• Reinforce the roof with
rebar
• Tie bars together with wire
to form a grid.
• The grid will extend out over
the surrounding rocks, but
need not cover the whole
area
• Attach iron rods over
the roof of the tank,
forming a semi circle
surrounding the trap
door.
• This semi-circle will
form a wall to prevent
contaminated run-off
entering through the
trapdoor.
• Flatten any rods from
the metal frame that
are protruding from
the wall mould
• Fill any gaps between
the wooden roof
supports and the
rock bed.
• Cover the roof
support and rock bed
with water, to allow
the cement greater
adhesiveness
• Cover the entire roof of
the tank and rock bed
with cement.
• Use wooden planks to
surround the tank to
ensure a neat finish.
• Some concrete should
be added around the
perimeter of the future
access door to create a
ridge
• The access door will fit
over this raised section
• Attach rebar
horizontally across
the rods shaped as a
semi-circle.
• Cut wood and attach
them to the semi
circle to form a mold
• Leave a gap of 10cm
between forms to fill
with concrete
• Once the cement has
dried, the moulds can
be taken off the tank.
• The front of the tank
will need a layer of
grout to leave a
finished surface.
• A mix of 2 parts sand
to 1 part cement will
be used.
The Access Door
• A form should be placed over the
box where water collects before
exiting the spring capture box
• The access door will allow for
periodic cleaning and maintenance
of the spring capture box.
• The following slides show how to
construct a lid for the box.
•Rebar should be equally spaced at
10cm apart
•The wood form should have inside
dimensions of 35cm x 35cm x 10cm
•Maintain 5cm clear cover between
form and rebar
• To make the access door to the spring
box first create a 30cm x 30cm form.
• Add rebar as shown, maintaining 5cm
clear cover around the perimeter
• Pour concrete to top of form (10cm)
• A handle, made of rebar, may be added
at the center by tying a rectangular
section of rebar to the center square of
bar created
Spring Box_compressed
Spring Box_compressed
Spring Box_compressed

More Related Content

What's hot

Principles of brick masonry Principles & Significance ppt
Principles of brick masonry Principles & Significance pptPrinciples of brick masonry Principles & Significance ppt
Principles of brick masonry Principles & Significance pptshabir rufai
 
Pointing and finishing
Pointing and finishingPointing and finishing
Pointing and finishingkajal018
 
Rat Trap Bond - Advantages, Disadvantages, Construction, Purpose, Estimation ...
Rat Trap Bond - Advantages, Disadvantages, Construction, Purpose, Estimation ...Rat Trap Bond - Advantages, Disadvantages, Construction, Purpose, Estimation ...
Rat Trap Bond - Advantages, Disadvantages, Construction, Purpose, Estimation ...ADNAN AHMAD
 
wall masonary,door,paint and trusses
wall masonary,door,paint and trusseswall masonary,door,paint and trusses
wall masonary,door,paint and trusseslithakoshi
 
Adenta renovation finishes schedule
Adenta renovation finishes scheduleAdenta renovation finishes schedule
Adenta renovation finishes scheduleNana Barima
 
Tutor l1 brick technology
Tutor l1 brick technologyTutor l1 brick technology
Tutor l1 brick technologyLuke D'Arcy
 
Construction Materials and Engineering - Module III - Lecture Notes
Construction Materials and Engineering - Module III - Lecture NotesConstruction Materials and Engineering - Module III - Lecture Notes
Construction Materials and Engineering - Module III - Lecture NotesSHAMJITH KM
 
Cavity walls
Cavity wallsCavity walls
Cavity wallsMani Das
 
BRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUIBRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUISUBHENDU SAMUI
 

What's hot (20)

Brick Masonry Fall 09
Brick Masonry Fall 09Brick Masonry Fall 09
Brick Masonry Fall 09
 
Principles of brick masonry Principles & Significance ppt
Principles of brick masonry Principles & Significance pptPrinciples of brick masonry Principles & Significance ppt
Principles of brick masonry Principles & Significance ppt
 
Pointing and finishing
Pointing and finishingPointing and finishing
Pointing and finishing
 
Plastering by mani
Plastering by maniPlastering by mani
Plastering by mani
 
Rat Trap Bond - Advantages, Disadvantages, Construction, Purpose, Estimation ...
Rat Trap Bond - Advantages, Disadvantages, Construction, Purpose, Estimation ...Rat Trap Bond - Advantages, Disadvantages, Construction, Purpose, Estimation ...
Rat Trap Bond - Advantages, Disadvantages, Construction, Purpose, Estimation ...
 
Masonry work
Masonry workMasonry work
Masonry work
 
Brick work
Brick workBrick work
Brick work
 
wall masonary,door,paint and trusses
wall masonary,door,paint and trusseswall masonary,door,paint and trusses
wall masonary,door,paint and trusses
 
Adenta renovation finishes schedule
Adenta renovation finishes scheduleAdenta renovation finishes schedule
Adenta renovation finishes schedule
 
Tutor l1 brick technology
Tutor l1 brick technologyTutor l1 brick technology
Tutor l1 brick technology
 
MORTAR BUILDING MATERIALS
MORTAR BUILDING MATERIALSMORTAR BUILDING MATERIALS
MORTAR BUILDING MATERIALS
 
Bricks (2)
Bricks (2)Bricks (2)
Bricks (2)
 
7.rat trap bonds
7.rat trap bonds7.rat trap bonds
7.rat trap bonds
 
Eport work copy pdf
Eport work copy pdfEport work copy pdf
Eport work copy pdf
 
Masonry Part 2 F 09
Masonry  Part 2  F 09Masonry  Part 2  F 09
Masonry Part 2 F 09
 
Bricks
BricksBricks
Bricks
 
Construction Materials and Engineering - Module III - Lecture Notes
Construction Materials and Engineering - Module III - Lecture NotesConstruction Materials and Engineering - Module III - Lecture Notes
Construction Materials and Engineering - Module III - Lecture Notes
 
Cavity walls
Cavity wallsCavity walls
Cavity walls
 
BRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUIBRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUI
 
Manual plastering
Manual plasteringManual plastering
Manual plastering
 

Similar to Spring Box_compressed

How to Make a Lavamanos-RoundBASE
How to Make a Lavamanos-RoundBASEHow to Make a Lavamanos-RoundBASE
How to Make a Lavamanos-RoundBASELynn Roberts
 
How to Make a Lavamanos-RoundBASE
How to Make a Lavamanos-RoundBASEHow to Make a Lavamanos-RoundBASE
How to Make a Lavamanos-RoundBASELynn Roberts
 
house construction
house constructionhouse construction
house constructionAbhinav Saha
 
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxSPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxswethasekhar5
 
How to construct a suimple garden pond
How to construct a suimple garden pondHow to construct a suimple garden pond
How to construct a suimple garden pondPraveen Sudarsan
 
Compost toilet manual
Compost toilet manualCompost toilet manual
Compost toilet manualPavel Druziak
 
Brickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdfBrickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdfAbhinavSahu45
 
BRICK MASONRY.pptx
BRICK MASONRY.pptxBRICK MASONRY.pptx
BRICK MASONRY.pptxAjay Kumar
 
How to build a lavamanos apls guatemala
How to build a lavamanos apls guatemalaHow to build a lavamanos apls guatemala
How to build a lavamanos apls guatemalawaloart
 
How to construct a suimple garden pond
How to construct a suimple garden pondHow to construct a suimple garden pond
How to construct a suimple garden pondZulaiha Amaria
 
Bricks & Plastering
Bricks & PlasteringBricks & Plastering
Bricks & PlasteringTanvir Araf
 
Pouring concrete into formwork
Pouring concrete into formwork Pouring concrete into formwork
Pouring concrete into formwork Dosy21
 
1 biomass based biogas plant
1 biomass based biogas plant1 biomass based biogas plant
1 biomass based biogas plantDanesh Kumar
 
Stone Works Canada Alan Block garden walls install catalog
Stone Works Canada Alan Block garden walls install catalogStone Works Canada Alan Block garden walls install catalog
Stone Works Canada Alan Block garden walls install catalogStone Works Canada
 
Class 4 & 5 planning and design of greenhouses (1)
Class 4 & 5 planning and design of greenhouses (1)Class 4 & 5 planning and design of greenhouses (1)
Class 4 & 5 planning and design of greenhouses (1)Priyanka Priyadarshini
 
Aim for quality in construction
Aim for quality in constructionAim for quality in construction
Aim for quality in constructionpracticalanswerssl
 
5.2 brick and stone MASONRY.pptx
5.2 brick and stone MASONRY.pptx5.2 brick and stone MASONRY.pptx
5.2 brick and stone MASONRY.pptxAmrithaVijay
 

Similar to Spring Box_compressed (20)

How to Make a Lavamanos-RoundBASE
How to Make a Lavamanos-RoundBASEHow to Make a Lavamanos-RoundBASE
How to Make a Lavamanos-RoundBASE
 
How to Make a Lavamanos-RoundBASE
How to Make a Lavamanos-RoundBASEHow to Make a Lavamanos-RoundBASE
How to Make a Lavamanos-RoundBASE
 
house construction
house constructionhouse construction
house construction
 
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxSPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
 
How to construct a suimple garden pond
How to construct a suimple garden pondHow to construct a suimple garden pond
How to construct a suimple garden pond
 
Compost toilet manual
Compost toilet manualCompost toilet manual
Compost toilet manual
 
Brickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdfBrickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdf
 
FLOORING
FLOORINGFLOORING
FLOORING
 
BRICK MASONRY.pptx
BRICK MASONRY.pptxBRICK MASONRY.pptx
BRICK MASONRY.pptx
 
How to build a lavamanos apls guatemala
How to build a lavamanos apls guatemalaHow to build a lavamanos apls guatemala
How to build a lavamanos apls guatemala
 
How to construct a suimple garden pond
How to construct a suimple garden pondHow to construct a suimple garden pond
How to construct a suimple garden pond
 
Bricks & Plastering
Bricks & PlasteringBricks & Plastering
Bricks & Plastering
 
Pouring concrete into formwork
Pouring concrete into formwork Pouring concrete into formwork
Pouring concrete into formwork
 
1 biomass based biogas plant
1 biomass based biogas plant1 biomass based biogas plant
1 biomass based biogas plant
 
Stone Works Canada Alan Block garden walls install catalog
Stone Works Canada Alan Block garden walls install catalogStone Works Canada Alan Block garden walls install catalog
Stone Works Canada Alan Block garden walls install catalog
 
Slabs and types
Slabs and typesSlabs and types
Slabs and types
 
Fresh Concrete.pdf
Fresh Concrete.pdfFresh Concrete.pdf
Fresh Concrete.pdf
 
Class 4 & 5 planning and design of greenhouses (1)
Class 4 & 5 planning and design of greenhouses (1)Class 4 & 5 planning and design of greenhouses (1)
Class 4 & 5 planning and design of greenhouses (1)
 
Aim for quality in construction
Aim for quality in constructionAim for quality in construction
Aim for quality in construction
 
5.2 brick and stone MASONRY.pptx
5.2 brick and stone MASONRY.pptx5.2 brick and stone MASONRY.pptx
5.2 brick and stone MASONRY.pptx
 

Spring Box_compressed

  • 2. Using the following presentation assumes that individuals have a basic knowledge of construction. The user should be able to adjust measurements and quantities depending on their specific site requirements. The exact measurements will depend on the site specific design criteria, but at a minimum, the spring box should have three PVC pipes exiting the box (one for the main line, one for future expansion, and one overflow) and an access door. Cement should be mixed to local specifications depending on the type of materials available. Disclaimer
  • 3. Materials •1 tube (6m) PVC pipe •The size of pipe will be a function of the flow from the spring • Three or Four PVC elbows of size equal to tube •2 lbs of tie wire • 100kg of 3/8” reinforcing rods (rebar) • Twenty (20) x 50kg bags cement • 2 cubic meter sand • 2 cubic meters gravel •5 cubic meters large stone (15+ cm diameter) •1 lb of 2-1/2” nail •1 lb of 4” nails •Three (3) wood boards 10” x 3/4” x 12’ •Six (6) wood boards 2” x 4” x 6’ •One (1) wood post 3” x 3” x 6’ •One (1) 2” bronze lock for access door
  • 4. • Once the spring has been identified, determine a convenient location to build the spring box wall. In this case where the banks of the pool narrowed into a stream. • clear away as much of the rocks and foliage as possible, both within the spring pool and the surrounding banks. Getting Started
  • 5. • It is important to have several areas flattened for work • A flat area, approximately 2.5m, in diameter will be needed for mixing concrete •Space should be cleared to store sand and gravel • The area where the spring comes to the surface should be dug out, flattened, and all large stones (greater than 10cm diameter) should be removed Getting Started
  • 6. Site Preparation Flatten an area for mixing of concrete Remove all stones and level the area Where the spring surfaces Sand storage area Gravel Storage Area
  • 7. • Once the spring has been cleared of debris, begin to fill it with rocks, starting from the spring source Spring Source Spring cleared of all debris and made level, ready to place stones Getting Started
  • 8. Preparing the Spring Spring Surfaces, water flows in this direction
  • 9. Preparing the Spring Spring Surfaces, water flows in this direction Fill this area with stone An area should be left clear in this location approximately 1m x 1m x 0.7m depth. This space will be used to construct a box where water will collect before exiting the box.
  • 10. Continue to fill the spring with large stone (15cm-50cm diameter) until the area is filled and matches the contours of the surrounding land Preparing the Spring
  • 11. • Dig two trenches on either side of the spring to be filled with cement. The “wings” will serve to capture groundwater into the spring box The “Wings” Trench or “Wing”
  • 12. Trenches dug to either side of the spring Try to maintain a 40cm to 50cm width for the trench. It is okay if the trench becomes wider. Sometimes it is necessary to widen the trench to remove large stones.
  • 13. “Wing” or trench “Wing” or trench Next slide shown looking into trench
  • 14. If possible, continue digging away from the spring until water is no longer seeping in from the end of the trench here Water should not being seeping in from this wall Spring source
  • 15. Layout 1m As Needed AsNeeded This area should be flat and free of any large stones Spring Surfaces, water flows in this direction PVC pipe exiting the spring box with elbow turned upwards at this end
  • 17. Spring Box Wall Locations Concrete Trench •Build a mold that will fit inside the trench and across the front wall of the spring box •The form should provide a wall thickness of at least 10cm •A rebar frame should be built that will fit inside the form •It will be placed in the center of the mold, allowing 5cm clear cover between the form walls on all sides Front Wall
  • 18. Attach the rods using small pieces of metal wire, ensuring that once tied, there are no sharp tails left. For rods that are parallel to each other, a simple wrap round and twist with a pair of pliers, will be sufficient How to Tie Rebar
  • 19. For rods that are perpendicular to each other use an “iron workers knot “ illustrated in the pictures opposite. How to Tie Rebar
  • 20. • Construct a wooden form for the spring box wall. It should be large enough to span the three sides of the spring box. The form for the front wall should have holes cut in the center at the bottom of the form to allow PVC Pipe (minimum 3 tubes) to fit through • Construct the rebar frame to fit inside the form • Leave holes in the bottom of the frame for PVC Pipe (minimum 3 tubes)
  • 21. Rebar Wall Frame (Plan) 1m AsNeeded AsNeeded •The rebar frame should be built to fit inside the wooden form, matching the contour of the trenches •5cm clear cover should be maintained between rebar and wooden mold for concrete
  • 22. Rebar Wall Frame (Elevation) Space left open for PVC tubing Maintain 10cm spacing, number of bars will vary Maintain10cmspacing,numberof barswillvary
  • 23. Rebar Wall Frame Trench Trench Area dug out, stones removed, then refilled with stone (15-50cm diameter) Hole in place for tubing
  • 24. • Place the form walls across the stream • Insert the rebar frame within the form walls, ensuring that the holes through which the tubes will fit, are aligned
  • 25. • Insert the at least three tubes through the holes. • The tubing will have a 90° elbow attached to the end contained within the spring box.
  • 26. • One tube will be used as an overflow. Be sure this pipe sits with the top of the elbow (where water will enter) at least 10cm above the other tubes. You may need to place sand or pebbles under them to ensure this is the case. • Block gaps left between the tubes and the hole cut into the mould walls. In this case, empty cement bags were used.
  • 27. • Ensure that the mould walls are supported so they do not collapse under the weight of the cement • Remaining wood boards can be used and stones are make good supports
  • 28. • Pour dry cement into the bottom of the form to absorb standing water • Now, add wet cement until the mould is full • The mix should be 3 parts gravel to 1 part sand to one part cement by volume
  • 29.
  • 30. Preparing the Spring Spring Surfaces, water flows in this direction This area filled with stone Place rocks in order to create a box 1m x 1m x 0.7m depth. Water will collect in this area before exiting the spring capture box.
  • 31. • Continue to add rocks to create a box • The dimensions should be approximately L 1m x W 1m x D 70cm
  • 32. • Build the roof over the pool to the same level as the surrounding rocks • Be sure to score the wood in the area of the access door • You must be able to break out the wood in this area with a hammer • See following slides for more information
  • 33. • Place a box with the dimensions of 30cm x 30cm x 30cm over the roof of the tank, above the tubing, to provide space to insert the access door • The wood in the area under the form should be precut along the edges of the access door • The roof will be covered with concrete except in this area. • The precut sections of wood can be knocked out with a hammer after concrete has sufficiently cured • The door will lift off from this spot, and you must be able to enter the spring box from this spot.
  • 34. Rebar Roof Frame Access Door Form in Place Trench Trench Trench Trench Rebar Roof frame in Place
  • 35. Rebar Roof Frame (Front View) Access Door Form in Place Trench Trench
  • 36. Rebar Roof Frame (Plan) Maintain 10cm spacing, number of bars will vary Maintain10cmspacing,numberof barswillvary
  • 37. Rebar Roof Frame (Elevation) Maintain 10cm to 20cm spacing, number of bars will vary Maintain20cm spacing,numberof barswillvary
  • 38. • Reinforce the roof with rebar • Tie bars together with wire to form a grid. • The grid will extend out over the surrounding rocks, but need not cover the whole area
  • 39. • Attach iron rods over the roof of the tank, forming a semi circle surrounding the trap door. • This semi-circle will form a wall to prevent contaminated run-off entering through the trapdoor. • Flatten any rods from the metal frame that are protruding from the wall mould
  • 40. • Fill any gaps between the wooden roof supports and the rock bed. • Cover the roof support and rock bed with water, to allow the cement greater adhesiveness
  • 41. • Cover the entire roof of the tank and rock bed with cement. • Use wooden planks to surround the tank to ensure a neat finish. • Some concrete should be added around the perimeter of the future access door to create a ridge • The access door will fit over this raised section
  • 42. • Attach rebar horizontally across the rods shaped as a semi-circle. • Cut wood and attach them to the semi circle to form a mold • Leave a gap of 10cm between forms to fill with concrete
  • 43. • Once the cement has dried, the moulds can be taken off the tank. • The front of the tank will need a layer of grout to leave a finished surface. • A mix of 2 parts sand to 1 part cement will be used.
  • 44. The Access Door • A form should be placed over the box where water collects before exiting the spring capture box • The access door will allow for periodic cleaning and maintenance of the spring capture box. • The following slides show how to construct a lid for the box.
  • 45. •Rebar should be equally spaced at 10cm apart •The wood form should have inside dimensions of 35cm x 35cm x 10cm •Maintain 5cm clear cover between form and rebar
  • 46. • To make the access door to the spring box first create a 30cm x 30cm form. • Add rebar as shown, maintaining 5cm clear cover around the perimeter • Pour concrete to top of form (10cm) • A handle, made of rebar, may be added at the center by tying a rectangular section of rebar to the center square of bar created