Group 5’s Project Plan
(12/9/2015)
Ka Chun Chan
Michael Lim Meng
Bingyue Xu
Aaron Huang
Anthony Mottla
Project Summary:
Our project is to implement a way for people to order their items manually while they are inside
the store through a tablet. They will be able to do this either by manually ordering from a table or
if they want to place an order to go at the front desk. This idea is for customers to have the ability
for themselves to order without having to go to the front register. The organization which this
project will be used for is at, Buccini’s Mr.Subs at 64 Billings Rd, Quincy Ma. Our main contact
person will be our group member, Michael Lim Meng who currently works there. The group
members who will be working on this project will be, Ka chun Chan (KC), Michael Lim Meng,
Bingyue Xu, Aaron Huang, and Anthony Mottla whom are part of group 5.
1
Problem Statement:
The Buccini’s Mr.Subs has been using “Food Tech Inc.” as its cashier and delivery system
for many years. At the beginning of the last fall, The Food Tech Inc. announced that the whole
cashier and delivery system will end mainstream support on December 31, 2015 and end
extended support on December 31, 2016. That means Food Tech Inc. will not fix any
vulnerabilities for the system and it would impact all of Buccini’s Mr.Subs’s business.
There has been a weak business continuity plan for the machines or system if they are
having issues and the dealer of Food Tech Inc. said that they will cancel the same day
maintenance support in December 31, 2015. That means Buccini’s Mr.Subs would need to wait a
day or more if the server down. Most importantly, Buccini’s Mr.Subs will need to pay additional
money for the extended support, but they are not including vulnerabilities fixes. Since the cashier
and delivery system are important for Buccini’s Mr.Subs, management had to begin seeking
viable alternatives to replace and upgrade the current cashier and delivery system.
Mission Statement, Goals, and Objectives
Project Mission
To enhance the ordering system through the replacement of the current outdated
system with the new, easily adaptable and more efficient hardware and software solutions, which
would:
Implement a way for people to order their items more efficiency.
Apply the tablets PC (For example, iPad) on each table for customers to place orders by
themselves.
Project Goals
· Grasp an opportunity to advance the ordering system and provide effective support to all
the employees and customers.
· Enhance the existing ordering hardware with the new tablets to improve overall efficiency.
2
a. Within a time frame of five months and
b. Within a budget of $31,500
1) Salary cost for the implementation team, $11,500
2) $20,000 for purchasing the tablets and other accessories
· Become a successful restaurant using a tablet ordering system.
Project Objectives
· Complete the planning and requirements gathering stage within the first month from the
project start date.
· Meet deadlines for the deliverables throughout the project’s life cycle.
· Closely monitor the project’s performance and effectively apply any change to the
ordering system.
· Within two months of the project, make sure all the employees master the steps of the new
ordering system skillfully.
· Successfully convert the old ordering system to the new solution.
· Analyze the customer satisfaction and compare the requirements of the users to rate the
success of the project. In detail, examine:
a. Interface
b. User-friendly system
c. Customer satisfaction
· Maintain both ordering systems until December 31, 2016 and after this date use only the
new ordering system.
Project Strategy
SWOT Analysis
In order to better understand the gains and risks of this project, analysis of environmental
factors specific to the business must be conducted. Factors internal to the business will be
considered strengths and weaknesses, and factors outside the business will be called
opportunities and threats; this is called SWOT analysis. SWOT analysis is important to
understand the resources and capabilities this project will have.
Strengths
· Good location for consumer testing.
· Small constrained environment.
o Both the physical location and the environment needed to develop the program.
Weakness
· No current database for the program.
3
o A new database has to be developed for the program, that means resources have to be
set aside for the database.
Opportunities
· Increased company appeal.
o Making the business look more appealing through adapting new technology.
· Increased business and revenue.
· Marketing a new software to other businesses.
o Selling or leasing the software to other businesses in order to gain a new source of revenue.
Threats
· There is the potential threat that neighboring restaurants will adopt and implement this
idea before this project is finished.
o To address this, we have to run them out of business, or finish the project on time.
· The software being developed may become outdated.
o Address this by hiring another person onto the team to ensure the software is
continuously maintained and possibly improved upon.
· Tablet hardware may become outdated.
o To address this, the software will have to work in all sorts of environment, from
phones to computers.
· There may be bugs with the software.
o Address by creating a stable version of the software to be used. Any patches or
improvements done will have to be tested in an environment outside the restaurant before
implementation.
Risk Analysis
Risk Impact Probability Consequences Decision
1 Possible bugs
and glitches
M H -Unable to use or
start the program.
-Application may
have to be
reworked or
restarted if bugs are
persistent.
Ensure there is a
stable working
version of the
program. Any
patches or
improvements will
be added in testing
environment.
2 Delay in meeting
deliverables
M L -Project completion
becomes delayed.
Increase work
hours, allow for
overtime if the
budget allows it.
4
Possibly hire
another member to
the team.
3 Outdated
Hardware
L L -Application has to
be updated to
support the new
hardware.
Create the
application to be
flexible so that it
can adopted onto
other technology.
4 IT Team Quits M L -The project
becomes stalled.
-We have to find
new IT team to
handle the software
development.
Find an immediate
replacement
member for the
team.
5 Undeveloped
Database
H L -The database does
not connect to the
application.
-Transfer resources
to further develop
the database.
6 Over-budget H L -Not enough of the
budget to complete
the other tasks.
-Reevaluate budget
plans and see where
cuts can be made.
Internal Analysis
The importance of doing an internal analysis of the project is to better understand the
situation and environment the project will be developed in. Knowing the strengths and
weaknesses of the business and the project itself will allow the team to know its advantages and
disadvantages.
The location of the business Buccini’s gives the IT team a way to test its beta applications
before its launch. Because Buccini’s has an environment in which customers can sit down and
order, it is possible to section off certain parts of the restaurant to allow the testing of the newly
developed application. By sectioning off parts of the restaurant for testing, the team can gather
real world data on the application. They can also gather reports from customers themselves
which will help them improve the application.
Because the project is on a smaller scale, this allows the overall project to have more
focused goals. The project is developed to work with machines that use iOS so the development
environment can be any environment.
5
The database currently for Buccini’s maintains inventory and checks sales. The database
will have to be modified so that orders placed on the application will show up on the database, or
at least allow the application to have information from the database.
External Analysis
Aside from the strengths and weaknesses this project has, opportunities and threats may
arise as the project goes on. Because of this, it is important to also analyze the environment
outside the business, such as market competition and possible opportunities.
Because there are not a lot of restaurants that have adopted this model of service, by
developing the application, Buccini’s will become more appealing in aesthetics and its technical
side.
If Buccini’s wishes to sell or license their application to other businesses, it will open up
a new source of revenue for Buccini’s. To do this, the application has to be flexible in adopting
new databases, and also accessible.
Because application development is never perfect, the application being developed for
this project will come across some bugs. To iron out the bugs that may appear, QA testers will
have to be hired to check the application. Also, the application will have to be tested on a small
number of customers to get their feedback as well.
Project Deliverables
The project deliverables are tangible or intangible objects to be delivered to the customer
throughout the duration of the project. These deliverables include:
● A project charter to identify and outline the scope and requirements of the project.
● A work plan document to outline the specific work breakdown structure, schedule, and
budget of the project.
● Modifications to the current database so inventory, ordering, and sales all work
seamlessly with the new software.
● Initial version of ordering software for tablets capable of running iOS.
● Training program and procedures for employees to learn new software after the first
month.
● Reports and analysis on employees’ feedback to be considered for the next phase of the
software.
● Updated version of ordering software capable of running on other devices in addition to
tablets, such as computers and smartphones. To be implemented on tablets in designated
testing section.
● Reports and analysis from both employees’ and customers’ feedback for the final version
of the software.
● Completed project: A customer friendly, fully operational ordering system implemented
on all tablets in the restaurant by December 1, 2015. It must allow customers to place
orders while keeping track of inventory, orders, and sales on the back end.
6
● Final evaluation document detailing the improved ordering system and customer
satisfaction.
Project’s Schedule
Group 5’s WBS
0 Group 5 Project
1 Evaluate and Recommend
1.1 Evaluate Current Hardware
1.2 Evaluate Current Software
1.2.1 Evaluate User Interface
1.2.2 Evaluate Database Management
1.3 Milestone
2 Develop Project Charter
2.1 Define Scope
2.2 Define Requirements
2.3 Identify High-Level Roles
2.4 Develop High-Level Budget
2.5 Identify High-Level Control Strategies
2.6 Review Meetings
2.7 Revise Project Charter
2.8 Milestone
3 Planning
3.1 Develop Work Plan
3.1.1 Develop WBS
3.1.2 Develop Project Schedule
3.1.3 Develop Budget
3.2 Develop Project Control
3.2.1 Develop Communication
3.3 Finalize Project Plan
7
3.4 Milestone
4 Design
4.1 System/Interface Design
4.1.1 Design Content
4.1.1.1 Design Layout
4.1.1.1.1 Create Home Menu
4.1.1.1.2 Create Tabs for Categories
4.1.1.1.3 Assign Items to Category Tabs
4.1.1.1.4 Assign Prices to items
4.1.1.1.5 Assign Pictures to items
4.1.1.1.6 Add Descriptions to items
4.1.1.1.7 Add ingredients to items
4.1.1.2 Implement Company’s Logo to layout
4.1.1.3 Design Database
4.1.1.3.1 List Items and Prices
4.1.1.3.2 Establish relationship with database and applications
4.1.1.4 Design User Interface
4.1.1.4.1 Design application thumbnail
4.2 Milestone
5 Installation
5.1 Install Hardware
5.1.1 Install Docking System for Ordering System
5.1.2 Install Cabling
5.2 Install Software
5.2.1 Internet Establishment
5.2.2 Update Software
5.2.3 Security System
5.2.4 Payment Methods
5.3 Milestone
6 Testing
6.1 Test Phase
6.1.1 Test the System/Interface
6.1.1.1 Test Usability of System
6.1.1.2 Test Usability of interface
6.1.1.3 Test for bugs and glitches
6.1.1.4 Test for Quality
6.1.1.5 Test for Responsiveness
6.1.2 Gather User’s feedback
6.1.2.1 If Negative Feedback
6.1.2.1.1 Determine Level of importance
6.1.2.1.1.1 Low Priority
6.1.2.1.1.1.1 Fix if deadline/budget allows
6.1.2.1.1.2 High Priority
6.1.2.1.1.2.1 Fix immediately
8
6.1.2.2 If Positive Feedback
6.1.2.2.1 Optimize current application
6.2 Milestone
7 Training
7.1 Develop Training Manual
7.1.1 Provide Appropriate Training
7.1.1.1 Online Training
7.1.1.2 Instore Training
7.1.2 Train Managers
7.1.3 Train Employees
7.1.3.1 Full Time
7.1.3.2 Part Time
7.2 Milestone
8 Control
8.1 Project Case Meetings
8.2 Risk Management
8.3 Update Project
8.4 Milestone
9 Close Project
9.1 Conduct and evaluate project’s success
9.2 Milestone
Activity Description Estimated Duration
(Days)
Predecessor
A Conceptualize and
Initialize
3 None
B Develop Project
Charter
27 A
C Planning 17.5 A
D Design 8 A
E Installation 2 B,C,D
F Testing 20 E
G Training 13 E
H Control 25 E
9
I Close 1 F,G,H
Arrow on the Node Network Diagram (AON)
Possible Paths Paths Total
Path 1 A+B+E+F+I
3+27+2+20+1
53
Path 2 A+B+E+G+I
3+27+2+13+1
41
Path 3 (The Critical Path) A+B+E+H+I
3+27+2+25+1
58
Path 4 A+C+E+F+I
3+17.5+2+20+1
48.5
10
Path 5 A+C+E+G+I
3+17.5+2+13+1
31.5
Path 6 A+C+E+H+I
3+17.5+2+25+1
48.5
Path 7 A+D+E+F+I
3+8+2+20+1
34
Path 8 A+D+E+G+I
3+8+2+13+1
22
Path 9 A+D+E+H+I
3+8+2+25+1
39
Gantt Chart
11
12
Control and Evaluation
To ensure that the efforts of the implementation team are not wasted and that the envisioned
performance is achieved, four main stages methodology was devised to establish, monitor and
control the issues that might happen during the implementation of the system. Those stages are:
· Budgeted Cost of Work Scheduled (BCWS)
· Control procedures for
13
o Cost
o Quality
o Risk
BCWS
The physical work scheduled, plus the authorized budget to accomplish the scheduled
work.
a. Within a time frame of five months and salary cost around $11,500 for the
implementation team
b. Within a budget of $20,000 for purchasing the tablets and other accessories
Cost Control
A series of steps that the implementation team uses to maintain proper control over its cost.
· Budget. Change control over the project estimated money that spend on each part while
implementing.
· Decision. Knowledge of effectively and reasonably designs the cost control plans used for
choosing different kinds of tablets and software.
· Organization. Knowledge of organizing the team according to the results of the decision.
· Implement. Knowledge of implementing the project to all the sections.
Quality Control
Focus on assuring a well-designed system that would work stable in the restaurant. The
effectiveness of the system need to be ensured.
· Network. Change control over the network status with implementation.
· Responsibility. Change control over the physical deterioration for the tablets and other
accessories.
· Targets. Aims that will be carried out through to the end. For example, both the hardware
and software must meet the needs for the restaurant.
· Supervision. Rationalize all the work.
Risk Control
The process to deal with problems once the project delay in meeting the deliverables,
over-budget, or poorly performing.
· Stability. Knowledge of controlling some possible bugs and glitches, we want to make sure
that there is a stable working version of the program.
· Completion. Change control over different deadlines for different parts of the project.
· Loyalty. Knowledge of methods that used for the team cohesion.
Organization
14
Buccini’s Mr. Sub is a privately owned restaurant with a small staff of 15 employees.
Because the staff of Buccini’s is split into different groups based on their function, the
organization structure of the project team will mainly be functional, with some cross-
functionality. Dividing the project team into smaller groups who will focus on their specific
tasks will allow the Buccini’s business to complete the project in a timely fashion. The IT
team will mainly be focusing on the development and testing of the application, while the
restaurant staff will be assisting with the testing of the application; while also focusing on
training employees on using the application.
Work Distribution Table
15

More Related Content

What's hot

Presentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajanPresentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajanPMI_IREP_TP
 
Jurnal an example of using key performance indicators for software development
Jurnal   an example of using key performance indicators for software developmentJurnal   an example of using key performance indicators for software development
Jurnal an example of using key performance indicators for software developmentUniversitas Putera Batam
 
Presentation by meghna jadhav
Presentation by meghna jadhavPresentation by meghna jadhav
Presentation by meghna jadhavPMI_IREP_TP
 
aw_survivalguide_r2opt
aw_survivalguide_r2optaw_survivalguide_r2opt
aw_survivalguide_r2optReza Abed
 
Major Accomplishments, Career Summary & Recommendations.
Major Accomplishments, Career Summary & Recommendations.Major Accomplishments, Career Summary & Recommendations.
Major Accomplishments, Career Summary & Recommendations.Lou Piombino
 
Knaul.Tim.Resume 150429
Knaul.Tim.Resume 150429 Knaul.Tim.Resume 150429
Knaul.Tim.Resume 150429 Tim Knaul
 
Ch22-Software Engineering 9
Ch22-Software Engineering 9Ch22-Software Engineering 9
Ch22-Software Engineering 9Ian Sommerville
 
Presentation by saurabh chandra
Presentation by saurabh chandraPresentation by saurabh chandra
Presentation by saurabh chandraPMI_IREP_TP
 
Ian Sommerville, Software Engineering, 9th Edition Ch 23
Ian Sommerville,  Software Engineering, 9th Edition Ch 23Ian Sommerville,  Software Engineering, 9th Edition Ch 23
Ian Sommerville, Software Engineering, 9th Edition Ch 23Mohammed Romi
 
Resume_Brijesh_Pavith
Resume_Brijesh_PavithResume_Brijesh_Pavith
Resume_Brijesh_Pavithbeeemused
 
Critical Success Factors for ERP
Critical Success Factors for ERPCritical Success Factors for ERP
Critical Success Factors for ERPGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Communication Map Plan for Business
Communication Map Plan for Business Communication Map Plan for Business
Communication Map Plan for Business Ravi Nakulan
 
Establishing the performance measurement baseline (v4)
Establishing the performance measurement baseline (v4) Establishing the performance measurement baseline (v4)
Establishing the performance measurement baseline (v4) Glen Alleman
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineGlen Alleman
 
Managing an agile mobile app development project with asana
Managing an agile mobile app development project with asanaManaging an agile mobile app development project with asana
Managing an agile mobile app development project with asanaAnthony Monticchio
 

What's hot (20)

Quality Management Practice in IT Projects
Quality Management Practice in IT ProjectsQuality Management Practice in IT Projects
Quality Management Practice in IT Projects
 
Presentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajanPresentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajan
 
Jurnal an example of using key performance indicators for software development
Jurnal   an example of using key performance indicators for software developmentJurnal   an example of using key performance indicators for software development
Jurnal an example of using key performance indicators for software development
 
Presentation by meghna jadhav
Presentation by meghna jadhavPresentation by meghna jadhav
Presentation by meghna jadhav
 
Profile Seema Wadhwa
Profile Seema WadhwaProfile Seema Wadhwa
Profile Seema Wadhwa
 
aw_survivalguide_r2opt
aw_survivalguide_r2optaw_survivalguide_r2opt
aw_survivalguide_r2opt
 
Major Accomplishments, Career Summary & Recommendations.
Major Accomplishments, Career Summary & Recommendations.Major Accomplishments, Career Summary & Recommendations.
Major Accomplishments, Career Summary & Recommendations.
 
Knaul.Tim.Resume 150429
Knaul.Tim.Resume 150429 Knaul.Tim.Resume 150429
Knaul.Tim.Resume 150429
 
Ch22-Software Engineering 9
Ch22-Software Engineering 9Ch22-Software Engineering 9
Ch22-Software Engineering 9
 
Presentation by saurabh chandra
Presentation by saurabh chandraPresentation by saurabh chandra
Presentation by saurabh chandra
 
Ian Sommerville, Software Engineering, 9th Edition Ch 23
Ian Sommerville,  Software Engineering, 9th Edition Ch 23Ian Sommerville,  Software Engineering, 9th Edition Ch 23
Ian Sommerville, Software Engineering, 9th Edition Ch 23
 
Ch23 project planning
Ch23 project planningCh23 project planning
Ch23 project planning
 
Resume_Brijesh_Pavith
Resume_Brijesh_PavithResume_Brijesh_Pavith
Resume_Brijesh_Pavith
 
Critical Success Factors for ERP
Critical Success Factors for ERPCritical Success Factors for ERP
Critical Success Factors for ERP
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Communication Map Plan for Business
Communication Map Plan for Business Communication Map Plan for Business
Communication Map Plan for Business
 
Establishing the performance measurement baseline (v4)
Establishing the performance measurement baseline (v4) Establishing the performance measurement baseline (v4)
Establishing the performance measurement baseline (v4)
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement Baseline
 
Managing an agile mobile app development project with asana
Managing an agile mobile app development project with asanaManaging an agile mobile app development project with asana
Managing an agile mobile app development project with asana
 
Control systems
Control systemsControl systems
Control systems
 

Viewers also liked

Group7_EE284_ProjectReport
Group7_EE284_ProjectReportGroup7_EE284_ProjectReport
Group7_EE284_ProjectReportJagbir Kalirai
 
Translation The Noble Quran in the Bangla / Bengali Language
Translation The Noble Quran in the Bangla / Bengali LanguageTranslation The Noble Quran in the Bangla / Bengali Language
Translation The Noble Quran in the Bangla / Bengali LanguageThe Choice
 
Диагностика одаренности как средство успешного обучения младших школьников
Диагностика одаренности как средство успешного обучения младших школьниковДиагностика одаренности как средство успешного обучения младших школьников
Диагностика одаренности как средство успешного обучения младших школьниковfrostblood87
 
"Designing, implementing and monitoring evidence-based policies effectively
"Designing, implementing and monitoring evidence-based policies effectively "Designing, implementing and monitoring evidence-based policies effectively
"Designing, implementing and monitoring evidence-based policies effectively ExternalEvents
 
качество как объект управления
качество как объект управлениякачество как объект управления
качество как объект управленияfrostblood87
 
"Empowering Women as Key drivers of Food System Change Lindiwe Majele Sibanda...
"Empowering Women as Key drivers of Food System Change Lindiwe Majele Sibanda..."Empowering Women as Key drivers of Food System Change Lindiwe Majele Sibanda...
"Empowering Women as Key drivers of Food System Change Lindiwe Majele Sibanda...ExternalEvents
 
2012 Quayron Aliens
2012 Quayron Aliens2012 Quayron Aliens
2012 Quayron AliensFulhamPrep
 
«педагогикалық ізденіс– педагогический поиск»
«педагогикалық ізденіс– педагогический поиск»«педагогикалық ізденіс– педагогический поиск»
«педагогикалық ізденіс– педагогический поиск»KBerik
 
Frankfurt Zoological Society's Annual Report 2012 / Prospects for 2013
Frankfurt Zoological Society's Annual Report 2012 / Prospects for 2013Frankfurt Zoological Society's Annual Report 2012 / Prospects for 2013
Frankfurt Zoological Society's Annual Report 2012 / Prospects for 2013FrankfurtZoological
 
Group 2 presentation 2014 uhc final
Group 2 presentation 2014 uhc finalGroup 2 presentation 2014 uhc final
Group 2 presentation 2014 uhc finalBen Collin
 

Viewers also liked (12)

Group7_EE284_ProjectReport
Group7_EE284_ProjectReportGroup7_EE284_ProjectReport
Group7_EE284_ProjectReport
 
Capstone Final
Capstone FinalCapstone Final
Capstone Final
 
Translation The Noble Quran in the Bangla / Bengali Language
Translation The Noble Quran in the Bangla / Bengali LanguageTranslation The Noble Quran in the Bangla / Bengali Language
Translation The Noble Quran in the Bangla / Bengali Language
 
IGCSE
IGCSEIGCSE
IGCSE
 
Диагностика одаренности как средство успешного обучения младших школьников
Диагностика одаренности как средство успешного обучения младших школьниковДиагностика одаренности как средство успешного обучения младших школьников
Диагностика одаренности как средство успешного обучения младших школьников
 
"Designing, implementing and monitoring evidence-based policies effectively
"Designing, implementing and monitoring evidence-based policies effectively "Designing, implementing and monitoring evidence-based policies effectively
"Designing, implementing and monitoring evidence-based policies effectively
 
качество как объект управления
качество как объект управлениякачество как объект управления
качество как объект управления
 
"Empowering Women as Key drivers of Food System Change Lindiwe Majele Sibanda...
"Empowering Women as Key drivers of Food System Change Lindiwe Majele Sibanda..."Empowering Women as Key drivers of Food System Change Lindiwe Majele Sibanda...
"Empowering Women as Key drivers of Food System Change Lindiwe Majele Sibanda...
 
2012 Quayron Aliens
2012 Quayron Aliens2012 Quayron Aliens
2012 Quayron Aliens
 
«педагогикалық ізденіс– педагогический поиск»
«педагогикалық ізденіс– педагогический поиск»«педагогикалық ізденіс– педагогический поиск»
«педагогикалық ізденіс– педагогический поиск»
 
Frankfurt Zoological Society's Annual Report 2012 / Prospects for 2013
Frankfurt Zoological Society's Annual Report 2012 / Prospects for 2013Frankfurt Zoological Society's Annual Report 2012 / Prospects for 2013
Frankfurt Zoological Society's Annual Report 2012 / Prospects for 2013
 
Group 2 presentation 2014 uhc final
Group 2 presentation 2014 uhc finalGroup 2 presentation 2014 uhc final
Group 2 presentation 2014 uhc final
 

Similar to Group 5's Tablet Ordering Project

Feature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PMFeature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PMProduct School
 
Kinsley FosterJuly 27, 2019PM 430Software .docx
Kinsley FosterJuly 27, 2019PM 430Software .docxKinsley FosterJuly 27, 2019PM 430Software .docx
Kinsley FosterJuly 27, 2019PM 430Software .docxcroysierkathey
 
IT 625 Final Project Case Study Medical Informatics Backgroun.docx
IT 625 Final Project Case Study Medical Informatics Backgroun.docxIT 625 Final Project Case Study Medical Informatics Backgroun.docx
IT 625 Final Project Case Study Medical Informatics Backgroun.docxpriestmanmable
 
BOB EVANS FARMS INC. PROJECT MANAGEMENT PLAN .docx
BOB EVANS FARMS INC. PROJECT MANAGEMENT PLAN                   .docxBOB EVANS FARMS INC. PROJECT MANAGEMENT PLAN                   .docx
BOB EVANS FARMS INC. PROJECT MANAGEMENT PLAN .docxAASTHA76
 
Odoo Implementation Methodology
Odoo Implementation MethodologyOdoo Implementation Methodology
Odoo Implementation MethodologyQuang Ngoc
 
Odoo implementation
Odoo implementationOdoo implementation
Odoo implementationOdoo Thaidev
 
online food delivery system projects.docx
online food delivery system projects.docxonline food delivery system projects.docx
online food delivery system projects.docxAKHILPATEL92
 
Medical IS Vendor Medical IS Vendor Medical IS Vendor Medical .docx
Medical IS Vendor Medical IS Vendor Medical IS Vendor Medical .docxMedical IS Vendor Medical IS Vendor Medical IS Vendor Medical .docx
Medical IS Vendor Medical IS Vendor Medical IS Vendor Medical .docxbuffydtesurina
 
Ian_M_Resume_062015
Ian_M_Resume_062015Ian_M_Resume_062015
Ian_M_Resume_062015Ian Coughlin
 
Course project scenario the course project scenario in this c
Course project scenario the course project scenario in this cCourse project scenario the course project scenario in this c
Course project scenario the course project scenario in this cAISHA232980
 
Running head UNIT III PROJECT1 UNIT III PROJECT2.docx
Running head UNIT III PROJECT1 UNIT III PROJECT2.docxRunning head UNIT III PROJECT1 UNIT III PROJECT2.docx
Running head UNIT III PROJECT1 UNIT III PROJECT2.docxtodd521
 
6 Steps to Confirm Successful Workday Deployment
6 Steps to Confirm Successful Workday Deployment6 Steps to Confirm Successful Workday Deployment
6 Steps to Confirm Successful Workday DeploymentZaranTech LLC
 
about start up for you 12
about start up for you 12about start up for you 12
about start up for you 12aliaalistartup
 
How to implement an enterprise system
How to implement an enterprise systemHow to implement an enterprise system
How to implement an enterprise systemMiki Lumnitz
 
1. Companies could use the System Development Life Cycle (SDLC) to.docx
1. Companies could use the System Development Life Cycle (SDLC) to.docx1. Companies could use the System Development Life Cycle (SDLC) to.docx
1. Companies could use the System Development Life Cycle (SDLC) to.docxjackiewalcutt
 
Scope Statement1Scope Statement10Scope StatementCP.docx
Scope Statement1Scope Statement10Scope StatementCP.docxScope Statement1Scope Statement10Scope StatementCP.docx
Scope Statement1Scope Statement10Scope StatementCP.docxbagotjesusa
 
Project Report on Employee Management System.docx
Project Report on Employee Management System.docxProject Report on Employee Management System.docx
Project Report on Employee Management System.docxDhineshkumarPrakasam
 
SMARTPHONE PRODUCTION SYSTEM
SMARTPHONE PRODUCTION SYSTEMSMARTPHONE PRODUCTION SYSTEM
SMARTPHONE PRODUCTION SYSTEMSisubalan Selvan
 
JamesCarr461FinalProject
JamesCarr461FinalProjectJamesCarr461FinalProject
JamesCarr461FinalProjectJames Carr
 

Similar to Group 5's Tablet Ordering Project (20)

Feature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PMFeature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PM
 
Kinsley FosterJuly 27, 2019PM 430Software .docx
Kinsley FosterJuly 27, 2019PM 430Software .docxKinsley FosterJuly 27, 2019PM 430Software .docx
Kinsley FosterJuly 27, 2019PM 430Software .docx
 
IT 625 Final Project Case Study Medical Informatics Backgroun.docx
IT 625 Final Project Case Study Medical Informatics Backgroun.docxIT 625 Final Project Case Study Medical Informatics Backgroun.docx
IT 625 Final Project Case Study Medical Informatics Backgroun.docx
 
BOB EVANS FARMS INC. PROJECT MANAGEMENT PLAN .docx
BOB EVANS FARMS INC. PROJECT MANAGEMENT PLAN                   .docxBOB EVANS FARMS INC. PROJECT MANAGEMENT PLAN                   .docx
BOB EVANS FARMS INC. PROJECT MANAGEMENT PLAN .docx
 
Odoo Implementation Methodology
Odoo Implementation MethodologyOdoo Implementation Methodology
Odoo Implementation Methodology
 
Odoo implementation
Odoo implementationOdoo implementation
Odoo implementation
 
online food delivery system projects.docx
online food delivery system projects.docxonline food delivery system projects.docx
online food delivery system projects.docx
 
Assignment .pdf
Assignment .pdfAssignment .pdf
Assignment .pdf
 
Medical IS Vendor Medical IS Vendor Medical IS Vendor Medical .docx
Medical IS Vendor Medical IS Vendor Medical IS Vendor Medical .docxMedical IS Vendor Medical IS Vendor Medical IS Vendor Medical .docx
Medical IS Vendor Medical IS Vendor Medical IS Vendor Medical .docx
 
Ian_M_Resume_062015
Ian_M_Resume_062015Ian_M_Resume_062015
Ian_M_Resume_062015
 
Course project scenario the course project scenario in this c
Course project scenario the course project scenario in this cCourse project scenario the course project scenario in this c
Course project scenario the course project scenario in this c
 
Running head UNIT III PROJECT1 UNIT III PROJECT2.docx
Running head UNIT III PROJECT1 UNIT III PROJECT2.docxRunning head UNIT III PROJECT1 UNIT III PROJECT2.docx
Running head UNIT III PROJECT1 UNIT III PROJECT2.docx
 
6 Steps to Confirm Successful Workday Deployment
6 Steps to Confirm Successful Workday Deployment6 Steps to Confirm Successful Workday Deployment
6 Steps to Confirm Successful Workday Deployment
 
about start up for you 12
about start up for you 12about start up for you 12
about start up for you 12
 
How to implement an enterprise system
How to implement an enterprise systemHow to implement an enterprise system
How to implement an enterprise system
 
1. Companies could use the System Development Life Cycle (SDLC) to.docx
1. Companies could use the System Development Life Cycle (SDLC) to.docx1. Companies could use the System Development Life Cycle (SDLC) to.docx
1. Companies could use the System Development Life Cycle (SDLC) to.docx
 
Scope Statement1Scope Statement10Scope StatementCP.docx
Scope Statement1Scope Statement10Scope StatementCP.docxScope Statement1Scope Statement10Scope StatementCP.docx
Scope Statement1Scope Statement10Scope StatementCP.docx
 
Project Report on Employee Management System.docx
Project Report on Employee Management System.docxProject Report on Employee Management System.docx
Project Report on Employee Management System.docx
 
SMARTPHONE PRODUCTION SYSTEM
SMARTPHONE PRODUCTION SYSTEMSMARTPHONE PRODUCTION SYSTEM
SMARTPHONE PRODUCTION SYSTEM
 
JamesCarr461FinalProject
JamesCarr461FinalProjectJamesCarr461FinalProject
JamesCarr461FinalProject
 

Group 5's Tablet Ordering Project

  • 1. Group 5’s Project Plan (12/9/2015) Ka Chun Chan Michael Lim Meng Bingyue Xu Aaron Huang Anthony Mottla Project Summary: Our project is to implement a way for people to order their items manually while they are inside the store through a tablet. They will be able to do this either by manually ordering from a table or if they want to place an order to go at the front desk. This idea is for customers to have the ability for themselves to order without having to go to the front register. The organization which this project will be used for is at, Buccini’s Mr.Subs at 64 Billings Rd, Quincy Ma. Our main contact person will be our group member, Michael Lim Meng who currently works there. The group members who will be working on this project will be, Ka chun Chan (KC), Michael Lim Meng, Bingyue Xu, Aaron Huang, and Anthony Mottla whom are part of group 5.
  • 2. 1 Problem Statement: The Buccini’s Mr.Subs has been using “Food Tech Inc.” as its cashier and delivery system for many years. At the beginning of the last fall, The Food Tech Inc. announced that the whole cashier and delivery system will end mainstream support on December 31, 2015 and end extended support on December 31, 2016. That means Food Tech Inc. will not fix any vulnerabilities for the system and it would impact all of Buccini’s Mr.Subs’s business. There has been a weak business continuity plan for the machines or system if they are having issues and the dealer of Food Tech Inc. said that they will cancel the same day maintenance support in December 31, 2015. That means Buccini’s Mr.Subs would need to wait a day or more if the server down. Most importantly, Buccini’s Mr.Subs will need to pay additional money for the extended support, but they are not including vulnerabilities fixes. Since the cashier and delivery system are important for Buccini’s Mr.Subs, management had to begin seeking viable alternatives to replace and upgrade the current cashier and delivery system. Mission Statement, Goals, and Objectives Project Mission To enhance the ordering system through the replacement of the current outdated system with the new, easily adaptable and more efficient hardware and software solutions, which would: Implement a way for people to order their items more efficiency. Apply the tablets PC (For example, iPad) on each table for customers to place orders by themselves. Project Goals · Grasp an opportunity to advance the ordering system and provide effective support to all the employees and customers. · Enhance the existing ordering hardware with the new tablets to improve overall efficiency.
  • 3. 2 a. Within a time frame of five months and b. Within a budget of $31,500 1) Salary cost for the implementation team, $11,500 2) $20,000 for purchasing the tablets and other accessories · Become a successful restaurant using a tablet ordering system. Project Objectives · Complete the planning and requirements gathering stage within the first month from the project start date. · Meet deadlines for the deliverables throughout the project’s life cycle. · Closely monitor the project’s performance and effectively apply any change to the ordering system. · Within two months of the project, make sure all the employees master the steps of the new ordering system skillfully. · Successfully convert the old ordering system to the new solution. · Analyze the customer satisfaction and compare the requirements of the users to rate the success of the project. In detail, examine: a. Interface b. User-friendly system c. Customer satisfaction · Maintain both ordering systems until December 31, 2016 and after this date use only the new ordering system. Project Strategy SWOT Analysis In order to better understand the gains and risks of this project, analysis of environmental factors specific to the business must be conducted. Factors internal to the business will be considered strengths and weaknesses, and factors outside the business will be called opportunities and threats; this is called SWOT analysis. SWOT analysis is important to understand the resources and capabilities this project will have. Strengths · Good location for consumer testing. · Small constrained environment. o Both the physical location and the environment needed to develop the program. Weakness · No current database for the program.
  • 4. 3 o A new database has to be developed for the program, that means resources have to be set aside for the database. Opportunities · Increased company appeal. o Making the business look more appealing through adapting new technology. · Increased business and revenue. · Marketing a new software to other businesses. o Selling or leasing the software to other businesses in order to gain a new source of revenue. Threats · There is the potential threat that neighboring restaurants will adopt and implement this idea before this project is finished. o To address this, we have to run them out of business, or finish the project on time. · The software being developed may become outdated. o Address this by hiring another person onto the team to ensure the software is continuously maintained and possibly improved upon. · Tablet hardware may become outdated. o To address this, the software will have to work in all sorts of environment, from phones to computers. · There may be bugs with the software. o Address by creating a stable version of the software to be used. Any patches or improvements done will have to be tested in an environment outside the restaurant before implementation. Risk Analysis Risk Impact Probability Consequences Decision 1 Possible bugs and glitches M H -Unable to use or start the program. -Application may have to be reworked or restarted if bugs are persistent. Ensure there is a stable working version of the program. Any patches or improvements will be added in testing environment. 2 Delay in meeting deliverables M L -Project completion becomes delayed. Increase work hours, allow for overtime if the budget allows it.
  • 5. 4 Possibly hire another member to the team. 3 Outdated Hardware L L -Application has to be updated to support the new hardware. Create the application to be flexible so that it can adopted onto other technology. 4 IT Team Quits M L -The project becomes stalled. -We have to find new IT team to handle the software development. Find an immediate replacement member for the team. 5 Undeveloped Database H L -The database does not connect to the application. -Transfer resources to further develop the database. 6 Over-budget H L -Not enough of the budget to complete the other tasks. -Reevaluate budget plans and see where cuts can be made. Internal Analysis The importance of doing an internal analysis of the project is to better understand the situation and environment the project will be developed in. Knowing the strengths and weaknesses of the business and the project itself will allow the team to know its advantages and disadvantages. The location of the business Buccini’s gives the IT team a way to test its beta applications before its launch. Because Buccini’s has an environment in which customers can sit down and order, it is possible to section off certain parts of the restaurant to allow the testing of the newly developed application. By sectioning off parts of the restaurant for testing, the team can gather real world data on the application. They can also gather reports from customers themselves which will help them improve the application. Because the project is on a smaller scale, this allows the overall project to have more focused goals. The project is developed to work with machines that use iOS so the development environment can be any environment.
  • 6. 5 The database currently for Buccini’s maintains inventory and checks sales. The database will have to be modified so that orders placed on the application will show up on the database, or at least allow the application to have information from the database. External Analysis Aside from the strengths and weaknesses this project has, opportunities and threats may arise as the project goes on. Because of this, it is important to also analyze the environment outside the business, such as market competition and possible opportunities. Because there are not a lot of restaurants that have adopted this model of service, by developing the application, Buccini’s will become more appealing in aesthetics and its technical side. If Buccini’s wishes to sell or license their application to other businesses, it will open up a new source of revenue for Buccini’s. To do this, the application has to be flexible in adopting new databases, and also accessible. Because application development is never perfect, the application being developed for this project will come across some bugs. To iron out the bugs that may appear, QA testers will have to be hired to check the application. Also, the application will have to be tested on a small number of customers to get their feedback as well. Project Deliverables The project deliverables are tangible or intangible objects to be delivered to the customer throughout the duration of the project. These deliverables include: ● A project charter to identify and outline the scope and requirements of the project. ● A work plan document to outline the specific work breakdown structure, schedule, and budget of the project. ● Modifications to the current database so inventory, ordering, and sales all work seamlessly with the new software. ● Initial version of ordering software for tablets capable of running iOS. ● Training program and procedures for employees to learn new software after the first month. ● Reports and analysis on employees’ feedback to be considered for the next phase of the software. ● Updated version of ordering software capable of running on other devices in addition to tablets, such as computers and smartphones. To be implemented on tablets in designated testing section. ● Reports and analysis from both employees’ and customers’ feedback for the final version of the software. ● Completed project: A customer friendly, fully operational ordering system implemented on all tablets in the restaurant by December 1, 2015. It must allow customers to place orders while keeping track of inventory, orders, and sales on the back end.
  • 7. 6 ● Final evaluation document detailing the improved ordering system and customer satisfaction. Project’s Schedule Group 5’s WBS 0 Group 5 Project 1 Evaluate and Recommend 1.1 Evaluate Current Hardware 1.2 Evaluate Current Software 1.2.1 Evaluate User Interface 1.2.2 Evaluate Database Management 1.3 Milestone 2 Develop Project Charter 2.1 Define Scope 2.2 Define Requirements 2.3 Identify High-Level Roles 2.4 Develop High-Level Budget 2.5 Identify High-Level Control Strategies 2.6 Review Meetings 2.7 Revise Project Charter 2.8 Milestone 3 Planning 3.1 Develop Work Plan 3.1.1 Develop WBS 3.1.2 Develop Project Schedule 3.1.3 Develop Budget 3.2 Develop Project Control 3.2.1 Develop Communication 3.3 Finalize Project Plan
  • 8. 7 3.4 Milestone 4 Design 4.1 System/Interface Design 4.1.1 Design Content 4.1.1.1 Design Layout 4.1.1.1.1 Create Home Menu 4.1.1.1.2 Create Tabs for Categories 4.1.1.1.3 Assign Items to Category Tabs 4.1.1.1.4 Assign Prices to items 4.1.1.1.5 Assign Pictures to items 4.1.1.1.6 Add Descriptions to items 4.1.1.1.7 Add ingredients to items 4.1.1.2 Implement Company’s Logo to layout 4.1.1.3 Design Database 4.1.1.3.1 List Items and Prices 4.1.1.3.2 Establish relationship with database and applications 4.1.1.4 Design User Interface 4.1.1.4.1 Design application thumbnail 4.2 Milestone 5 Installation 5.1 Install Hardware 5.1.1 Install Docking System for Ordering System 5.1.2 Install Cabling 5.2 Install Software 5.2.1 Internet Establishment 5.2.2 Update Software 5.2.3 Security System 5.2.4 Payment Methods 5.3 Milestone 6 Testing 6.1 Test Phase 6.1.1 Test the System/Interface 6.1.1.1 Test Usability of System 6.1.1.2 Test Usability of interface 6.1.1.3 Test for bugs and glitches 6.1.1.4 Test for Quality 6.1.1.5 Test for Responsiveness 6.1.2 Gather User’s feedback 6.1.2.1 If Negative Feedback 6.1.2.1.1 Determine Level of importance 6.1.2.1.1.1 Low Priority 6.1.2.1.1.1.1 Fix if deadline/budget allows 6.1.2.1.1.2 High Priority 6.1.2.1.1.2.1 Fix immediately
  • 9. 8 6.1.2.2 If Positive Feedback 6.1.2.2.1 Optimize current application 6.2 Milestone 7 Training 7.1 Develop Training Manual 7.1.1 Provide Appropriate Training 7.1.1.1 Online Training 7.1.1.2 Instore Training 7.1.2 Train Managers 7.1.3 Train Employees 7.1.3.1 Full Time 7.1.3.2 Part Time 7.2 Milestone 8 Control 8.1 Project Case Meetings 8.2 Risk Management 8.3 Update Project 8.4 Milestone 9 Close Project 9.1 Conduct and evaluate project’s success 9.2 Milestone Activity Description Estimated Duration (Days) Predecessor A Conceptualize and Initialize 3 None B Develop Project Charter 27 A C Planning 17.5 A D Design 8 A E Installation 2 B,C,D F Testing 20 E G Training 13 E H Control 25 E
  • 10. 9 I Close 1 F,G,H Arrow on the Node Network Diagram (AON) Possible Paths Paths Total Path 1 A+B+E+F+I 3+27+2+20+1 53 Path 2 A+B+E+G+I 3+27+2+13+1 41 Path 3 (The Critical Path) A+B+E+H+I 3+27+2+25+1 58 Path 4 A+C+E+F+I 3+17.5+2+20+1 48.5
  • 11. 10 Path 5 A+C+E+G+I 3+17.5+2+13+1 31.5 Path 6 A+C+E+H+I 3+17.5+2+25+1 48.5 Path 7 A+D+E+F+I 3+8+2+20+1 34 Path 8 A+D+E+G+I 3+8+2+13+1 22 Path 9 A+D+E+H+I 3+8+2+25+1 39 Gantt Chart
  • 12. 11
  • 13. 12 Control and Evaluation To ensure that the efforts of the implementation team are not wasted and that the envisioned performance is achieved, four main stages methodology was devised to establish, monitor and control the issues that might happen during the implementation of the system. Those stages are: · Budgeted Cost of Work Scheduled (BCWS) · Control procedures for
  • 14. 13 o Cost o Quality o Risk BCWS The physical work scheduled, plus the authorized budget to accomplish the scheduled work. a. Within a time frame of five months and salary cost around $11,500 for the implementation team b. Within a budget of $20,000 for purchasing the tablets and other accessories Cost Control A series of steps that the implementation team uses to maintain proper control over its cost. · Budget. Change control over the project estimated money that spend on each part while implementing. · Decision. Knowledge of effectively and reasonably designs the cost control plans used for choosing different kinds of tablets and software. · Organization. Knowledge of organizing the team according to the results of the decision. · Implement. Knowledge of implementing the project to all the sections. Quality Control Focus on assuring a well-designed system that would work stable in the restaurant. The effectiveness of the system need to be ensured. · Network. Change control over the network status with implementation. · Responsibility. Change control over the physical deterioration for the tablets and other accessories. · Targets. Aims that will be carried out through to the end. For example, both the hardware and software must meet the needs for the restaurant. · Supervision. Rationalize all the work. Risk Control The process to deal with problems once the project delay in meeting the deliverables, over-budget, or poorly performing. · Stability. Knowledge of controlling some possible bugs and glitches, we want to make sure that there is a stable working version of the program. · Completion. Change control over different deadlines for different parts of the project. · Loyalty. Knowledge of methods that used for the team cohesion. Organization
  • 15. 14 Buccini’s Mr. Sub is a privately owned restaurant with a small staff of 15 employees. Because the staff of Buccini’s is split into different groups based on their function, the organization structure of the project team will mainly be functional, with some cross- functionality. Dividing the project team into smaller groups who will focus on their specific tasks will allow the Buccini’s business to complete the project in a timely fashion. The IT team will mainly be focusing on the development and testing of the application, while the restaurant staff will be assisting with the testing of the application; while also focusing on training employees on using the application. Work Distribution Table
  • 16. 15