Productivity measurement of agile teams –
overcoming the issues with non-functional
requirements.
Harold van Heeringen
METRI B.V.
Schiphol-Rijk, the Netherlands
harold.van.heeringen@metrigroup.com
Theo Prins
Sizing, Estimating & Control
Sogeti Nederland B.V.
Vianen, Nederland
theo.prins@sogeti.com
Edwin van Gorp
Sizing, Estimating & Control
Sogeti Nederland B.V.
Vianen, Nederland
edwin.van.gorp@sogeti.com
Abstract—Nowadays, as the software industry is slowly
becoming more mature, software measurement and performance
measurement are becoming increasingly important.
Organizations need to know their productivity and
competitiveness in software development projects for various
reasons. In many software development contracts, targets are set
for the suppliers to reach. These targets are based on software
metrics like productivity, speed of delivery and software quality.
In order to check if the targets are reached, it is necessary to
measure the functional size of the software product that is
delivered and also the functional size of the software development
project that is carried out, as there is usually a difference between
these two sizes. To be able to use functional size in contracts, it
must be measured in an objective, repeatable, verifiable and
therefore defensible way. That being the case, the industry’s best
practice is to use an ISO/IEC standard for functional size
measurement, e.g. Nesma, COSMIC or IFPUG function points.
However, these methods only measure the functional user
requirements from the total software requirements to be
delivered. In activities like project estimation and productivity
measurement, the influence of the non-functional requirements is
expressed in the Project Delivery Rate (PDR) which is expressed
in effort hours per function point. If more than the average
amount of non-functional requirements need to be realized in a
project (or more severe non-functional requirements), the PDR
used should also be higher. In the industry it is customary to set
productivity targets based on an average (or calibrated) influence
of non-functional requirements and this works quite fine in
traditional software projects. In software development projects
that are executed in an agile way, this is not always the case. When
working agile, there are forces that influence the traditional way
of performance measurement significantly, resulting in a number
of serious issues. In this paper these issues are explained and a
method to overcome these issues is proposed.
Keywords— agile development; story points, outsourcing,
performance measurement, functional requirements, Nesma,
ISBSG, non-functional requirements, Agile normalized size.
I. INTRODUCTION
These days, more and more software development projects
are carried out in agile oriented approaches like Scrum or
DSDM. Projects following an agile software development
method deliver software in an iterative way. The iterations are
usually called sprints. The main idea behind agile software
development is that short feedback loops enable the customer
(users) to experience the product sooner, which allows the
requirements and solutions to evolve during the execution of the
project. As Scrum is the most dominant agile software
development method nowadays, this paper is primarily focused
on this method and the concepts and terminology of Scrum are
used in the text.
1. The development of a specific set of requirements in a
specific period of time. Although executed in an iterative way,
the project has a ‘goal’, and at one point it is decided that the
project is finished. The product owner controls the project,
making sure that the necessary functionality is delivered within
time and budget.
In traditional approaches, this type of development would be
called a ‘New development project’ or a ‘release’;
2. The continued development (evolving) of an
application. In this situation there is no definite duration or a
specific set of user requirements. A year is divided into X sprints
of Y weeks and the team is continuously working on the product
backlog items the product owner deems the most important until,
it is decided that the product does not need further maintenance
(which may be in the far future).
In traditional approaches, this type of development would be
called ‘Maintenance’.
Productivity measurement of the contract type listed as
number 1, is not significantly different in agile projects than in
traditional projects. In both approaches, the difficulty lies in
measuring all functional changes properly in order to measure
the actual project size.
The focus of this paper is on the contract type described
under number 2. A team is working for an indefinite period of
time, which is divided into sprints of 2, 3 or 4 weeks length each,
on a product backlog. The product backlog is prioritized in such
a way that the product backlog items (PBI’s) with the highest
importance are planned to be delivered first. The PBI’s are also
rated in story points, which are assigned in a team effort.
II. PRODUCTIVITY MEASUREMENT IN TRADITIONAL
SOFTWARE PROJECTS
Productivity measurement in traditional software
development projects is quite straightforward [1]. The customer
and the supplier have to agree on a few items beforehand, the
most important being:
 Which (variant of which) size measurement method to
use;
 Which performance metrics to use;
 Which activities are in scope and which activities are
out of scope for the performance measurement;
 Which are the benchmarks or targets to use per metric;
 Who is measuring, who is reviewing, how to deal with
differences of opinion.
To give an example, let’s look at a performance
measurement contract that a government agency and a supplier
used to measure the performance in a specific Java development
project with an indicative size of around 400 Nesma [2] function
points (FP). The items above were addressed in the following
way:
 Size measurement: Estimated Nesma [3] ;
 Performance metrics:
o Productivity: PDR (h/FP);
o Functional Quality: Defects/FP Acceptance
Test + 1st month production;
o Delivery Speed: FP per calendar month.
 Activities in scope: Technical design, Coding,
Programmer test, System test, Support acceptance test,
Project management, Quality assurance;
 Activities out of scope: Functional design, delivery
management, acceptance test, implementation;
 Benchmarks targets: A relevant subset from the ISBSG
repository New Developments & Enhancements [4]
(e.g. Java projects, Government, size between 300 and
500 FP)
o PDR: ISBSG subset median PDR;
o Defects/FP: ISBSG subset percentile 25%;
o Speed of deliver: ISBSG subset median PDR.
 The supplier measures the functional size, the customer
reviews the size measurement. The metrics can be
audited by the customer periodically. Independent third
parties may be used to solve differences of opinion.
Because of the specific set of requirements and the fact that
the goal of the project is clear (to realize that specific set of
requirements), the performance measurement is pretty
straightforward. As it is a Java development project for a
government agency, it is easy to select a proper subset from the
ISBSG repository to set the targets and benchmarks for this
project. If there are specific non-functional requirements that are
expected to have a significant influence on the performance, the
benchmarks and targets may need to be re-evaluated and agreed
upon.
After the project has finished, the project size is determined,
the performance metrics are calculated and it becomes clear if
the performance targets are met or not..
III. WHY ARE AGILE PROJECTS DIFFERENT?
Most people in the software industry know the four main
principles of the agile manifesto [5]:
 Individuals and interactions over processes and tools;
 Working software over comprehensive documentation;
 Customer collaboration over contract negotiation;
 Responding to change over following a plan.
Although the items on the right of the word ‘over’ are still
important, the items on the left are considered more important.
In practice, an agile project can be described in the following
general way:
A very important role is played by the product owner, who
is a representative of the customer/user organization. This
product owner needs to be knowledgeable about the
functionality of the product and the business value it offers to
the users. Also, the product owner needs to have a mandate from
the customer organization to make decisions and he needs to be
committed to fulfill his role. This means that he is able to devote
the time needed to carry out his role, this means that he is able
to meet with the team when necessary, make decisions when
necessary and prioritize the backlog items by business value.
There is a product backlog available which lists the product
backlog items identified by the product owner. These backlog
items are either functional or non-functional by nature. The
effort needed to realize the product backlog items are estimated
by the team members using story points. Although many people
in the agile community think the story point measure is a size
measure, it is in fact an effort measure. It is a relative measure
which gives an estimate of how many hours the team thinks they
need to spend on a particular product backlog item, compared to
a specific baseline backlog item to which a random number of
story points was assigned. There is no standard approach for
assigning story points. Most teams identify the smallest product
backlog item in the product backlog and assign 1, 2 or 3 story
points to it. All other backlog items are then compared to this
baseline backlog item and the number of story points assigned
to them reflect the effort the team needs to realize them,
compared to the baseline item. This method is absolutely
subjective and probably not very repeatable or verifiable.
Although story points are quite useful for sprint planning, as
to decide which product backlog items can be realized in a
specific sprint, metrics based on story points are completely
useless for performance measurement. As there is no standard
for assigning story points (it is not a measurement activity), it is
quite easy to manipulate the amount of story points realized in a
sprint in order to comply to the targets set. And since there is no
reference point, it is easy to manipulate the targets as well.
But still, organizations wish, and sometimes need, to
measure the performance of their suppliers, also in agile
executed projects. In many cases the usual performance metrics
are agreed upon, but instead of using a project or a release as a
basis for measurement, the performance measurement
instrument is applied to sprints. This means that for every sprint,
the functional size delivered should be measured, the effort
hours in scope need to be retrieved, the defects found and
resolved must be identified and the performance metrics should
be calculated. Some issues, when not properly addressed,
already arise here:
 Agile teams don’t usually register defects. Especially
not when they are easy to resolve;
 Agile teams are multidisciplinary by nature. Sometimes
it is hard for the team members to register their effort on
specific tasks. This is important however, as some tasks
may be out of scope for performance measurement;
 Agile teams sometimes don’t change the functional
documentation in the same sprint where the
functionality is realized in. This makes it difficult to
measure the functional size of that sprint;
 According to the theory, at the end of each sprint,
working software is delivered that could be
implemented in a production environment. In practice,
this is not always the case and product backlog items are
declared “not ready” at the end of the sprint. As only
functionality that is ready is measured, this means a low
size delivered in that sprint and possibly a relatively
high size delivered in the next sprint.
The product owner decides which product backlog items are
the most important. Here, the main issue comes to light. The
product owner may decide that mainly non-functional backlog
items need to be realized in a specific sprint. As functional size
measurement methods only measure the functional user
requirements, a size measurement of such a sprint would result
in a few (or even zero) function points. In these cases, the usual
performance metrics result in bad values and targets are not met
for that sprint.
So, there is a number of issues when trying to implement the
traditional performance measurement instrument on sprint level
in agile contracts. Summarized these issues are:
 The functional size of the delivered product can be hard
to measure, either because of under specification, or
because the documentation provided does not reflect the
status of the product after the sprint;
 The effort hours are not booked consciously on the right
tasks in the effort registration system, making it hard to
define the number of hours spent on the activities in
scope of the performance measurement;
 During the sprint, system tests and acceptance tests are
carried out, but defects found and defects resolved are
not logged appropriately, making it hard to use the
quality metrics.
 The functional size delivered in a sprint may be very low
(or zero), seriously affecting the performance metrics.
Reasons for this could be (not limitative):
o The product backlog items turned out to be
too big to deliver in a sprint and were not ready;
o Illness of team members or other unplanned
events that may have disturbed productivity;
o Non-functional backlog items to realize in the
sprint (e.g. improving performance, security, code
quality, et cetera).Finally, complete content and
organizational editing before formatting. Please take note
of the following items when proofreading spelling and
grammar:
These issues result in very uneven performance metrics over
time. An example of how this could look like is given below for
the PDR. Let’s say the following data is measured for 8 sprints
(table 1).
Sprint 1 2 3 4 5 6 7 8
Effort 345 389 367 412 365 375 390 401
Size (FP) 15 5 16 3 25 0 36 32
Table 1
This would result in the following PDR per sprint (table 2).
Sprint 1 2 3 4 5 6 7 8
PDR
(h/FP)
23,0 77,8 22,9 137,3 14,6 n/a 10,8 12,5
Table 2
In sprint 6 zero function points were realized, so it is
impossible to determine the PDR in h/FP. Let’s assume the
target PDR for the specific project is set to be 25,0 hours per
function point, the performance graph would look like in figure
1.
Fig. 1. PDR actual vs. target
The productivity realized shows a very uneven view. In the
next paragraph a method is proposed that should give better
insight into the suppliers capabilities and performance.
An option to overcome the issues mentioned would be to
only use the effort hours spent on functional backlog items for
the performance measurement. In practice, it is very hard to
identify these effort hours. Furthermore, this approach makes it
easy to manipulate the performance measurement simply by
booking more hours on non-functional backlog items (assuming
that there is no control on the effort hours booked). Instead of
normalizing the effort hours to match the functional size, the
method proposed in this paper is to normalize the functional size
to match the total effort.
IV. PROPOSED METHOD
The performance measurement method that is proposed in
this paper is to normalize the functional size in order to
determine the functional size that the team could have realized
if they would not have been instructed to realize any non-
functional backlog items.
This method enables organizations to use the standard
methods and techniques for performance measurement and
benchmarking , while almost no extra data or effort is necessary.
The method is not totally objective, but possibilities of
manipulation (consciously or unconsciously) are very limited.
In order to carry out this normalization activity, one extra
activity needs to be performed. The Scrum team assigns story
points to the backlog items, so the number of story points that is
realized in a specific sprint is known. Of each of the sprint
backlog items, the team should decide if the nature of the item
is (mainly) functional or non-functional. The ratio between the
functional and the non-functional story points is used to
normalize the functional size.
Examples of functional backlog items could be: Add a field
to the database table ‘User’ named ‘twitter username’, add a
field to the ‘manage user’ screen in which the administrator can
enter the ‘twitter username’ and Add a twitter icon to the screen
if the user has a ‘twitter username, linking to user’s twitter page.
Examples of non-functional backlog items could be:
Improve the performance of the batch job in order to have it run
in under 2 hours, Improve the code quality of the application to
be to compliant to SQALE rating A [6] or Upgrade the
development environment to the next version, because the
supplier stops supporting the current version any time soon’
The proposed method contains the following steps:
1. Measure the functional size of the functional sprint
backlog items that were ready at the end of the sprint
using one of the mentioned ISO/IEC standards for
functional sizing;
2. Determine for all sprint backlog items that were ready
at the end of the sprint, if these were functional or non-
functional by nature. In case of a hybrid nature, try to
assess the ratio functional/non-functional;
3. Determine the number of story points that were
assigned to the functional backlog items that were
ready at the end of the sprint;
4. Determine the total number of story points that were
assigned to all backlog items that were ready at the end
of the sprint;
5. Calculate the Agile Normalized Size (ANS) using this
formula:
ANS = (functional size / functional story points) *
total story points
Example: In a sprint, five backlog items were realized (see
table 3). Three of them are functional by nature, the other two
non-functional. The functional size of the functional backlog
items is measured using Nesma function point analysis.
Sprint X Nature Nesma FP Story points
BLI 1 Functional 4 4
BLI 2 Non-functional 0 6
BLI 3 Non-functional 0 2
BLI 4 Functional 5 3
BLI 5 Functional 4 3
Total 13 18
Table 3
The ANS in this example is: (13 / 10) * 18 = 23,4 FP. The
ANS represents the equivalent of the functional size that could
have been realized if only functional backlog items would have
been included in the sprint.
0,0
20,0
40,0
60,0
80,0
100,0
120,0
140,0
160,0
3 4 5 6 7 8 9 10
PDR (h/FP) Target PDR (h/FP)
In table 4, it is displayed that the ANS gives a more accurate
view of the size in sprints in which a lot of non-functional
backlog items were realized. This is especially obvious in sprint
4:
Table 4
Advantages of this method
The main advantage of this method is that the influence of
the non-functional backlog items is reduced, while still an
ISO/IEC standard method is used in order to determine the
functional size. This productivity can then be compared with
data that is measured using the same (type of) ISO/IEC standard
method.
Disadvantages of this method
The method is dependent on the story points assigned to the
functional and non-functional backlog items. Assigning story
points, as indicated before, is a highly subjective activity.
However, as it is a necessary activity carried out before the
actual start of the sprint and because of the fact that the product
owner is usually present to oversee this activity, chances of the
team manipulating the assigning of the story points are
considered to be small. Also, for the determination of the nature
of the backlog items, there is no standard approach, but usually
it should be easy to understand if backlog items are functional or
non-functional by nature. One other disadvantage of the method
is that it is impossible to measure the ANS if only non-functional
backlog items are realized in a specific sprint. In section V The
Progressive Approach, this issue is solved.
Effort hours in scope of performance measurement
It is always important to carefully consider the effort hours
that should be taken in scope of the performance measurement.
Usually, the benchmark used determines the effort hours that are
in scope, as you wish to compare apples with apples. If, for
instance, the benchmark used is based on a project lifecycle
excluding functional design and overhead hours, the effort hours
spent on these activities should be placed out of scope for the
performance measurement.
Due to the fact that in the proposed method the size is
normalized, all activities that are carried out to realize any
backlog item, functional or non-functional, have to be in scope
for performance measurement. This would mean activities like
(not limitative):
 Design (functional and/or technical);
 Coding and programmer test;
 System test;
 Scrum master;
 Project support (for the Scrum master);
 Create/adjust documentation;
 Resolving defects;
 Research (proof of concepts et cetera);
 Meetings / sessions.
Effort hours spent on activities that are not directly related to
realizing backlog items are out of scope for performance
measurement, e.g.:
 Delivery management;
 Quality Management;
 Project support (for the delivery management).
After the effort hours in scope have been determined, the
productivity per normalized FP can be calculated, see the
example in table 5:
Table 5
In the figure 2 it is clear that the hours/nFP metric provides
a more stable view than the hours/FP metric. The fact that
development of new functionality is not the most important goal
is normalized into a situation where it is.
Sprint
Func.
size
Functional
story
points
Non-
functional
story points
Total
story
points ANS
1 20 32 12 44 27,5
2 25 y28 16 44 39,3
3 18 24 20 44 33
4 29 35 4 39 32,3
5 4 6 36 42 28
6 15 16 24 40 37,5
Sprint
Func.
size (FP)
Agile
normalized
size (nFP)
Effort
spent
Hours/
FP
Hours
/nFP
1 20 27,5 500 25 18,2
2 25 39,3 480 19,2 12,2
3 18 33 530 29,4 16,1
4 29 32,3 468 16,1 14,5
5 4 28 534 133,5 19,1
6 15 37,5 522 34,8 13,9
Fig. 2. Hours/FP vs. Hours per nFP
V. THE PROGRESSIVE APPROACH
One of the aforementioned disadvantages of the proposed
method is that it’s not possible to determine the normalized size
for sprints in which no functional backlog items were realized.
This can be obviated by using the progressive approach.
The progressive approach divides the sum of the functional
sizes of all completed sprints by the sum of the functional story
points of these sprints. The result hereof is then multiplied with
the sum of all story points of all completed sprints. This
approach makes it possible to take sprints into account in which
no functional backlog items were realized. In table 6, the
example used earlier has been elaborated to explain the
progressive approach:
Sprint
Functionalsize(FP)
Functionalstorypoints
Non-functionalstorypoints
Totalstorypoints
Agilenormalizedsize(nFP)
Hours/nFP
Hoursspent(cumulative)
ANS(progressive)
Hours(cum)/nFP(progressive)
1 20 32 12 44 27,5 18,2 500 27,5 18,2
2 25 28 16 44 39,3 12,2 980 66 14,8
3 18 24 20 44 33 16,1 1.510 99 15,3
4 29 35 4 39 32,3 14,5 1.978 132,2 15
5 4 6 36 42 28 19,1 2.512 163,6 15,4
6 15 16 24 40 37,5 13,9 3.034 199,2 15,2
7 0 0 41 41 n/a n/a 3.546 231,4 15,3
8 18 24 20 44 33 15,4 4.054 264,3 15,3
Table 6
The productivity expressed in hours/nFP and the
productivity in hours (cum)/ nFP(progressive) can be
benchmarked against the traditional internal and external
hours/FP benchmarks, like for instance the ‘New Developments
and Enhancements repository of the International Software
Benchmarking Standards Group [4].
In the figure 3, the figures from the example are shown. The
benchmark PDR in this example is set on 20 hours/FP.
Fig. 3. The progressive apprach results
The main benefits of the proposed method are clearly
visible in sprints 5 (in which mainly non-functional backlog
items were realized) and 7 (in which only non-functional
backlog items were realized).
Starting points
In order to use the proposed method in the proper way, a
number of starting points have to be taken into account.
Effort administration
 The effort hours need to be booked in the effort
administration in such a way that it is possible to
clearly identify the effort hours in scope and out of
scope of the performance measurement;
 All effort hours spent on the project must be booked,
also overtime;
 Hours spent on other projects should not be booked on
the project that is being measured;
 The team members need to understand the importance
of an accurate and correct time administration.
Documentation
 After each sprint the functional documentation should
be made up-to-date and it must be clear:
o Which functionality was added in the sprint;
o Which functionality was changed in the sprint
and in which way;
o Which functionality was deleted in the sprint.
Size Measurement
 The effort hours need to be booked in the effort
administration in such a way that it is possible to
clearly identify the effort hours in scope and out of
scope of the performance measurement
Product backlog and sprint backlog
 The product backlog consists of functional and non-
functional backlog items. For each item it is known
which type it concerns;
 All items have been assigned story points to in a
realistic way;
 The product owner decides which product backlog
items will be placed on the sprint backlog of the
sprints;
 After each sprint it is decided which backlog items are
ready (meet the definition of done1
) and which items
are not (or not completely);
Data collection
 After each sprint, a data collection form (DCF) must be
filled in by the Scrum master. In this DCF at least the
following information must be filled in:
o the effort hours per activity;
o the backlog items declared ready and their
associated type;
o the story points assigned to these backlog
items.
Performance Measurement
 The productivity is determined using the method
described above;
 The functional size, the data and the results of the
productivity measurement is stored in a central
location;
 Standard reports are created in which the productivity
measurement is shown and compared to predefined
internal and external benchmarks. Also trends in
productivity within the projects are reported.
VI. CONCLUSIONS
More and more organizations adopt agile software
development methodologies to deliver new functionality in a
faster way to their customer. In the meantime, in the slowly
maturing software industry, the need for productivity
measurement is becoming more and more important, especially
in outsourcing contracts. As long as the most important
objective of agile projects remains delivering new or changed
functionality, the traditional productivity measurement
instruments can still be used in an effective way. In projects, or
contracts, that are mainly about evolving a certain application,
without a specific end date or a specific scope, the productivity
is sometimes hard to measure in ISO/IEC standards for
functional size measurements. The influence of non-functional
requirements can really impact the productivity and the product
owner (customer) is the only one who can control this. Some
attempts have been made in the recent past to normalize the
effort hours in order to capture only effort hours that were spent
on functional user requirements. However, in practice it seems
impossible to do so. Instead, this paper proposes to normalize
the functional size in such a way that the functional size is
calculated that could have been realized in a sprint if the product
owner only put functional backlog items on the sprint backlog.
Whether this method really is going to solve all the issues in
productivity measurement of agile projects still has to be
proven.
REFERENCES
[1] Bundshuh, M. and Dekkers, C, The IT Measurement Compendium,
Estimating and benchmarking success with functional size measurement,
page 313, Spinger, ISBN: 978-3-540-68187-8
[2] NESMA: ISO/IEC 24570:2005 Software engineering - NESMA function
size measurement method version 2.1 - Definitions and counting
guidelines for the application of Function Point Analysis, ISBN: 978-90-
76258-19-5
[3] Early Function Point Counting, http://nesma.org/themes/sizing/function-
point-analysis/early-function-point-counting/
[4] International Software Benchmarking Standards Group (ISBSG) New
Developments & enhancements R13, released February 22015,
www.isbsg.org
[5] Beck, Kent et al. (2001). "Manifesto for Agile Software Development".
Agile Alliance. Retrieved 14 June 2010
[6] Letouzey, J-L, The SQALE Method for Evaluating Technical Debt,
proceedings of the 3rd
international workshop on managing technical debt
(ICSE 2012), Zurich (Switzerland) june 9-12 2012.
1
The Definition of done is determined before the start of an
agile project. Only if all characteristics of that definition have
been met, the item is considered ‘ready’.

More Related Content

What's hot

Agile Project Management for IT Projects
Agile Project Management for IT ProjectsAgile Project Management for IT Projects
Agile Project Management for IT Projectsrachna_nainani
 
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...John Carter
 
Agile Planning Powerpoint Presentation Slides
Agile Planning Powerpoint Presentation SlidesAgile Planning Powerpoint Presentation Slides
Agile Planning Powerpoint Presentation SlidesSlideTeam
 
Presentation by saurabh chandra
Presentation by saurabh chandraPresentation by saurabh chandra
Presentation by saurabh chandraPMI_IREP_TP
 
The art of agile project initiation
The art of agile project initiationThe art of agile project initiation
The art of agile project initiationKshitij Agrawal
 
Estimation of agile functionality in software development
Estimation of agile functionality in software developmentEstimation of agile functionality in software development
Estimation of agile functionality in software developmentBashir Nasr Azadani
 
Contracting for Agile Software Development
Contracting for Agile Software DevelopmentContracting for Agile Software Development
Contracting for Agile Software Developmentcspag67
 
Lean Agile Metrics And KPIs
Lean Agile Metrics And KPIsLean Agile Metrics And KPIs
Lean Agile Metrics And KPIsYuval Yeret
 
CMMI-DEV 1.3 Tool (checklist)
CMMI-DEV 1.3 Tool (checklist)CMMI-DEV 1.3 Tool (checklist)
CMMI-DEV 1.3 Tool (checklist)Robert Levy
 
Project managemen, the agile way
Project managemen, the agile wayProject managemen, the agile way
Project managemen, the agile wayVlad Stanescu
 
Best Practices When Moving To Agile Project Management
Best Practices When Moving To Agile Project ManagementBest Practices When Moving To Agile Project Management
Best Practices When Moving To Agile Project ManagementRobert McGeachy
 
Agile Project Management
Agile Project ManagementAgile Project Management
Agile Project ManagementAbdullah Khan
 
Agility under Control - SCRUM vs COBIT
Agility under Control - SCRUM vs COBITAgility under Control - SCRUM vs COBIT
Agility under Control - SCRUM vs COBITPrzemek Wysota
 
Lean as Agile methodology – A Study
Lean as Agile methodology – A StudyLean as Agile methodology – A Study
Lean as Agile methodology – A StudyEswar Publications
 
Project charter v2
Project charter v2Project charter v2
Project charter v2Stefan Csosz
 
Presentation by shubham vyas
Presentation by shubham vyasPresentation by shubham vyas
Presentation by shubham vyasPMI_IREP_TP
 
Quality by Design Course Preview
Quality by Design Course PreviewQuality by Design Course Preview
Quality by Design Course PreviewInvensis Learning
 
ISTQB Agile Extension
ISTQB Agile ExtensionISTQB Agile Extension
ISTQB Agile ExtensionDavis Thomas
 

What's hot (20)

Agile Project Management for IT Projects
Agile Project Management for IT ProjectsAgile Project Management for IT Projects
Agile Project Management for IT Projects
 
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
 
Agile Planning Powerpoint Presentation Slides
Agile Planning Powerpoint Presentation SlidesAgile Planning Powerpoint Presentation Slides
Agile Planning Powerpoint Presentation Slides
 
Presentation by saurabh chandra
Presentation by saurabh chandraPresentation by saurabh chandra
Presentation by saurabh chandra
 
The art of agile project initiation
The art of agile project initiationThe art of agile project initiation
The art of agile project initiation
 
Estimation of agile functionality in software development
Estimation of agile functionality in software developmentEstimation of agile functionality in software development
Estimation of agile functionality in software development
 
Contracting for Agile Software Development
Contracting for Agile Software DevelopmentContracting for Agile Software Development
Contracting for Agile Software Development
 
ETPM5
ETPM5ETPM5
ETPM5
 
Lean Agile Metrics And KPIs
Lean Agile Metrics And KPIsLean Agile Metrics And KPIs
Lean Agile Metrics And KPIs
 
CMMI-DEV 1.3 Tool (checklist)
CMMI-DEV 1.3 Tool (checklist)CMMI-DEV 1.3 Tool (checklist)
CMMI-DEV 1.3 Tool (checklist)
 
Project managemen, the agile way
Project managemen, the agile wayProject managemen, the agile way
Project managemen, the agile way
 
Best Practices When Moving To Agile Project Management
Best Practices When Moving To Agile Project ManagementBest Practices When Moving To Agile Project Management
Best Practices When Moving To Agile Project Management
 
Agile Project Management
Agile Project ManagementAgile Project Management
Agile Project Management
 
Agility under Control - SCRUM vs COBIT
Agility under Control - SCRUM vs COBITAgility under Control - SCRUM vs COBIT
Agility under Control - SCRUM vs COBIT
 
Lean as Agile methodology – A Study
Lean as Agile methodology – A StudyLean as Agile methodology – A Study
Lean as Agile methodology – A Study
 
Project charter v2
Project charter v2Project charter v2
Project charter v2
 
D11 Define Review
D11 Define ReviewD11 Define Review
D11 Define Review
 
Presentation by shubham vyas
Presentation by shubham vyasPresentation by shubham vyas
Presentation by shubham vyas
 
Quality by Design Course Preview
Quality by Design Course PreviewQuality by Design Course Preview
Quality by Design Course Preview
 
ISTQB Agile Extension
ISTQB Agile ExtensionISTQB Agile Extension
ISTQB Agile Extension
 

Viewers also liked

Paper 9: Innovation Assessment and Improvement (D. Xu)
Paper 9: Innovation Assessment and Improvement (D. Xu)Paper 9: Innovation Assessment and Improvement (D. Xu)
Paper 9: Innovation Assessment and Improvement (D. Xu)Kent Business School
 
Learning from Burndown Charts
Learning from Burndown ChartsLearning from Burndown Charts
Learning from Burndown ChartsZach Nies
 
Balancing the agile equation
Balancing the agile equationBalancing the agile equation
Balancing the agile equationGeorge Anghelache
 
Agile Development Practices - Productivity
Agile Development Practices - ProductivityAgile Development Practices - Productivity
Agile Development Practices - ProductivityAlex Moore
 
PRODUCTIVITY OF AGILE TEAMS: AN EMPIRICAL EVALUATION OF FACTORS AND MONITORIN...
PRODUCTIVITY OF AGILE TEAMS: AN EMPIRICAL EVALUATION OF FACTORS AND MONITORIN...PRODUCTIVITY OF AGILE TEAMS: AN EMPIRICAL EVALUATION OF FACTORS AND MONITORIN...
PRODUCTIVITY OF AGILE TEAMS: AN EMPIRICAL EVALUATION OF FACTORS AND MONITORIN...Claudia Melo
 

Viewers also liked (6)

Paper 9: Innovation Assessment and Improvement (D. Xu)
Paper 9: Innovation Assessment and Improvement (D. Xu)Paper 9: Innovation Assessment and Improvement (D. Xu)
Paper 9: Innovation Assessment and Improvement (D. Xu)
 
Learning from Burndown Charts
Learning from Burndown ChartsLearning from Burndown Charts
Learning from Burndown Charts
 
Balancing the agile equation
Balancing the agile equationBalancing the agile equation
Balancing the agile equation
 
Agile Development Practices - Productivity
Agile Development Practices - ProductivityAgile Development Practices - Productivity
Agile Development Practices - Productivity
 
Agile Metrics
Agile MetricsAgile Metrics
Agile Metrics
 
PRODUCTIVITY OF AGILE TEAMS: AN EMPIRICAL EVALUATION OF FACTORS AND MONITORIN...
PRODUCTIVITY OF AGILE TEAMS: AN EMPIRICAL EVALUATION OF FACTORS AND MONITORIN...PRODUCTIVITY OF AGILE TEAMS: AN EMPIRICAL EVALUATION OF FACTORS AND MONITORIN...
PRODUCTIVITY OF AGILE TEAMS: AN EMPIRICAL EVALUATION OF FACTORS AND MONITORIN...
 

Similar to Productivity measurement of agile teams (IWSM 2015)

Presentation by lavika upadhyay
Presentation by lavika upadhyayPresentation by lavika upadhyay
Presentation by lavika upadhyayPMI_IREP_TP
 
Enterprise IT Projects: Agile Release Planning Strategies
Enterprise IT Projects: Agile Release Planning StrategiesEnterprise IT Projects: Agile Release Planning Strategies
Enterprise IT Projects: Agile Release Planning StrategiesKaali Dass PMP, PhD.
 
The Business value of agile development
The Business value of agile developmentThe Business value of agile development
The Business value of agile developmentPhavadol Srisarnsakul
 
Importance of software quality metrics
Importance of software quality metricsImportance of software quality metrics
Importance of software quality metricsPiyush Sohaney
 
AGILE PROJECT MANAGEMENT NOTES.docx
AGILE PROJECT MANAGEMENT NOTES.docxAGILE PROJECT MANAGEMENT NOTES.docx
AGILE PROJECT MANAGEMENT NOTES.docxVardha Mago
 
Designing A Brand Market Analysis
Designing A Brand Market AnalysisDesigning A Brand Market Analysis
Designing A Brand Market AnalysisOlga Bautista
 
Are Function Points Still Relevant?
Are Function Points Still Relevant?Are Function Points Still Relevant?
Are Function Points Still Relevant?DCG Software Value
 
Are Function Points Still Relevant?
Are Function Points Still Relevant?Are Function Points Still Relevant?
Are Function Points Still Relevant?Premios Group
 
6 Steps to Confirm Successful Workday Deployment
6 Steps to Confirm Successful Workday Deployment6 Steps to Confirm Successful Workday Deployment
6 Steps to Confirm Successful Workday DeploymentZaranTech LLC
 
How to Do Backlog Prioritization Easily and Efficiently _ StoriesOnBoard.pdf
How to Do Backlog Prioritization Easily and Efficiently _ StoriesOnBoard.pdfHow to Do Backlog Prioritization Easily and Efficiently _ StoriesOnBoard.pdf
How to Do Backlog Prioritization Easily and Efficiently _ StoriesOnBoard.pdfStoriesOnBoard
 
How to Reach Peak Performance With the Product Management Organizational Heal...
How to Reach Peak Performance With the Product Management Organizational Heal...How to Reach Peak Performance With the Product Management Organizational Heal...
How to Reach Peak Performance With the Product Management Organizational Heal...Aggregage
 
Implementation Of Incremental Development Process
Implementation Of Incremental Development ProcessImplementation Of Incremental Development Process
Implementation Of Incremental Development ProcessSherry Bailey
 
Managing Business Analysis for Agile Development
Managing Business Analysis for Agile DevelopmentManaging Business Analysis for Agile Development
Managing Business Analysis for Agile DevelopmentIJMER
 
Gopinathramachandran 131008015755-phpapp02
Gopinathramachandran 131008015755-phpapp02Gopinathramachandran 131008015755-phpapp02
Gopinathramachandran 131008015755-phpapp02PMI_IREP_TP
 
Gopinath ramachandran
Gopinath ramachandranGopinath ramachandran
Gopinath ramachandranPMI2011
 

Similar to Productivity measurement of agile teams (IWSM 2015) (20)

Presentation by lavika upadhyay
Presentation by lavika upadhyayPresentation by lavika upadhyay
Presentation by lavika upadhyay
 
Art of Agile For ShairPoint
Art of Agile For ShairPointArt of Agile For ShairPoint
Art of Agile For ShairPoint
 
Enterprise IT Projects: Agile Release Planning Strategies
Enterprise IT Projects: Agile Release Planning StrategiesEnterprise IT Projects: Agile Release Planning Strategies
Enterprise IT Projects: Agile Release Planning Strategies
 
Agile Software Development
Agile Software DevelopmentAgile Software Development
Agile Software Development
 
The Business value of agile development
The Business value of agile developmentThe Business value of agile development
The Business value of agile development
 
Cost estimation
Cost estimationCost estimation
Cost estimation
 
Importance of software quality metrics
Importance of software quality metricsImportance of software quality metrics
Importance of software quality metrics
 
AGILE PROJECT MANAGEMENT NOTES.docx
AGILE PROJECT MANAGEMENT NOTES.docxAGILE PROJECT MANAGEMENT NOTES.docx
AGILE PROJECT MANAGEMENT NOTES.docx
 
Designing A Brand Market Analysis
Designing A Brand Market AnalysisDesigning A Brand Market Analysis
Designing A Brand Market Analysis
 
Are Function Points Still Relevant?
Are Function Points Still Relevant?Are Function Points Still Relevant?
Are Function Points Still Relevant?
 
Are Function Points Still Relevant?
Are Function Points Still Relevant?Are Function Points Still Relevant?
Are Function Points Still Relevant?
 
6 Steps to Confirm Successful Workday Deployment
6 Steps to Confirm Successful Workday Deployment6 Steps to Confirm Successful Workday Deployment
6 Steps to Confirm Successful Workday Deployment
 
How to Do Backlog Prioritization Easily and Efficiently _ StoriesOnBoard.pdf
How to Do Backlog Prioritization Easily and Efficiently _ StoriesOnBoard.pdfHow to Do Backlog Prioritization Easily and Efficiently _ StoriesOnBoard.pdf
How to Do Backlog Prioritization Easily and Efficiently _ StoriesOnBoard.pdf
 
Gears agile
Gears agileGears agile
Gears agile
 
MOM on BA
MOM on BAMOM on BA
MOM on BA
 
How to Reach Peak Performance With the Product Management Organizational Heal...
How to Reach Peak Performance With the Product Management Organizational Heal...How to Reach Peak Performance With the Product Management Organizational Heal...
How to Reach Peak Performance With the Product Management Organizational Heal...
 
Implementation Of Incremental Development Process
Implementation Of Incremental Development ProcessImplementation Of Incremental Development Process
Implementation Of Incremental Development Process
 
Managing Business Analysis for Agile Development
Managing Business Analysis for Agile DevelopmentManaging Business Analysis for Agile Development
Managing Business Analysis for Agile Development
 
Gopinathramachandran 131008015755-phpapp02
Gopinathramachandran 131008015755-phpapp02Gopinathramachandran 131008015755-phpapp02
Gopinathramachandran 131008015755-phpapp02
 
Gopinath ramachandran
Gopinath ramachandranGopinath ramachandran
Gopinath ramachandran
 

More from Harold van Heeringen

Methodisch begroten van projecten hanzehogeschool groningen december2014
Methodisch begroten van projecten   hanzehogeschool groningen december2014Methodisch begroten van projecten   hanzehogeschool groningen december2014
Methodisch begroten van projecten hanzehogeschool groningen december2014Harold van Heeringen
 
The importance of benchmarking software projects - Van Heeringen and Ogilvie
The importance of benchmarking software projects - Van Heeringen and OgilvieThe importance of benchmarking software projects - Van Heeringen and Ogilvie
The importance of benchmarking software projects - Van Heeringen and OgilvieHarold van Heeringen
 
Van Heeringen and van Gorp - Measure the functional size of a mobile app usi...
Van Heeringen and van Gorp  - Measure the functional size of a mobile app usi...Van Heeringen and van Gorp  - Measure the functional size of a mobile app usi...
Van Heeringen and van Gorp - Measure the functional size of a mobile app usi...Harold van Heeringen
 
Measuring the functional size of mobile apps with COSMIC FP
Measuring the functional size of mobile apps with COSMIC FPMeasuring the functional size of mobile apps with COSMIC FP
Measuring the functional size of mobile apps with COSMIC FPHarold van Heeringen
 
Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Harold van Heeringen
 
ISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization success
ISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization successISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization success
ISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization successHarold van Heeringen
 
Gastcollege Hanzehogeschool Groningen 10 januari 2014
Gastcollege Hanzehogeschool Groningen 10 januari 2014Gastcollege Hanzehogeschool Groningen 10 januari 2014
Gastcollege Hanzehogeschool Groningen 10 januari 2014Harold van Heeringen
 
The value of benchmarking software projects
The value of benchmarking software projectsThe value of benchmarking software projects
The value of benchmarking software projectsHarold van Heeringen
 
Using the ISBSG data to improve your organization success - van Heeringen (Me...
Using the ISBSG data to improve your organization success - van Heeringen (Me...Using the ISBSG data to improve your organization success - van Heeringen (Me...
Using the ISBSG data to improve your organization success - van Heeringen (Me...Harold van Heeringen
 
Asl bi sl metrics themasessie 2013 devops sogeti
Asl bi sl metrics themasessie 2013   devops sogetiAsl bi sl metrics themasessie 2013   devops sogeti
Asl bi sl metrics themasessie 2013 devops sogetiHarold van Heeringen
 
Begroten van software projecten - Hogeschool Rotterdam gastcollege 05-11-2013
Begroten van software projecten - Hogeschool Rotterdam gastcollege 05-11-2013Begroten van software projecten - Hogeschool Rotterdam gastcollege 05-11-2013
Begroten van software projecten - Hogeschool Rotterdam gastcollege 05-11-2013Harold van Heeringen
 
Van heeringen estimate faster, cheaper, better
Van heeringen   estimate faster, cheaper, betterVan heeringen   estimate faster, cheaper, better
Van heeringen estimate faster, cheaper, betterHarold van Heeringen
 
van Heeringen - estimate faster,cheaper and better!
van Heeringen - estimate faster,cheaper and better!van Heeringen - estimate faster,cheaper and better!
van Heeringen - estimate faster,cheaper and better!Harold van Heeringen
 
The value of benchmarking IT projects - H.S. van Heeringen
The value of benchmarking IT projects - H.S. van HeeringenThe value of benchmarking IT projects - H.S. van Heeringen
The value of benchmarking IT projects - H.S. van HeeringenHarold van Heeringen
 
Begroten van agile projecten, technical meeting Sogeti 2013-09
Begroten van agile projecten, technical meeting Sogeti 2013-09Begroten van agile projecten, technical meeting Sogeti 2013-09
Begroten van agile projecten, technical meeting Sogeti 2013-09Harold van Heeringen
 
Sogeti seminar Supplier Performance Measurement
Sogeti seminar Supplier Performance MeasurementSogeti seminar Supplier Performance Measurement
Sogeti seminar Supplier Performance MeasurementHarold van Heeringen
 
Software Estimating and Performance Measurement
Software Estimating and Performance MeasurementSoftware Estimating and Performance Measurement
Software Estimating and Performance MeasurementHarold van Heeringen
 
Project Control using functional size - which method to use?
Project Control using functional size - which method to use?Project Control using functional size - which method to use?
Project Control using functional size - which method to use?Harold van Heeringen
 
Metrics based software supplier selection - Best practice used in the largest...
Metrics based software supplier selection - Best practice used in the largest...Metrics based software supplier selection - Best practice used in the largest...
Metrics based software supplier selection - Best practice used in the largest...Harold van Heeringen
 
ISPA/SCEA conference Brussels 2012
ISPA/SCEA conference Brussels 2012ISPA/SCEA conference Brussels 2012
ISPA/SCEA conference Brussels 2012Harold van Heeringen
 

More from Harold van Heeringen (20)

Methodisch begroten van projecten hanzehogeschool groningen december2014
Methodisch begroten van projecten   hanzehogeschool groningen december2014Methodisch begroten van projecten   hanzehogeschool groningen december2014
Methodisch begroten van projecten hanzehogeschool groningen december2014
 
The importance of benchmarking software projects - Van Heeringen and Ogilvie
The importance of benchmarking software projects - Van Heeringen and OgilvieThe importance of benchmarking software projects - Van Heeringen and Ogilvie
The importance of benchmarking software projects - Van Heeringen and Ogilvie
 
Van Heeringen and van Gorp - Measure the functional size of a mobile app usi...
Van Heeringen and van Gorp  - Measure the functional size of a mobile app usi...Van Heeringen and van Gorp  - Measure the functional size of a mobile app usi...
Van Heeringen and van Gorp - Measure the functional size of a mobile app usi...
 
Measuring the functional size of mobile apps with COSMIC FP
Measuring the functional size of mobile apps with COSMIC FPMeasuring the functional size of mobile apps with COSMIC FP
Measuring the functional size of mobile apps with COSMIC FP
 
Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...
 
ISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization success
ISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization successISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization success
ISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization success
 
Gastcollege Hanzehogeschool Groningen 10 januari 2014
Gastcollege Hanzehogeschool Groningen 10 januari 2014Gastcollege Hanzehogeschool Groningen 10 januari 2014
Gastcollege Hanzehogeschool Groningen 10 januari 2014
 
The value of benchmarking software projects
The value of benchmarking software projectsThe value of benchmarking software projects
The value of benchmarking software projects
 
Using the ISBSG data to improve your organization success - van Heeringen (Me...
Using the ISBSG data to improve your organization success - van Heeringen (Me...Using the ISBSG data to improve your organization success - van Heeringen (Me...
Using the ISBSG data to improve your organization success - van Heeringen (Me...
 
Asl bi sl metrics themasessie 2013 devops sogeti
Asl bi sl metrics themasessie 2013   devops sogetiAsl bi sl metrics themasessie 2013   devops sogeti
Asl bi sl metrics themasessie 2013 devops sogeti
 
Begroten van software projecten - Hogeschool Rotterdam gastcollege 05-11-2013
Begroten van software projecten - Hogeschool Rotterdam gastcollege 05-11-2013Begroten van software projecten - Hogeschool Rotterdam gastcollege 05-11-2013
Begroten van software projecten - Hogeschool Rotterdam gastcollege 05-11-2013
 
Van heeringen estimate faster, cheaper, better
Van heeringen   estimate faster, cheaper, betterVan heeringen   estimate faster, cheaper, better
Van heeringen estimate faster, cheaper, better
 
van Heeringen - estimate faster,cheaper and better!
van Heeringen - estimate faster,cheaper and better!van Heeringen - estimate faster,cheaper and better!
van Heeringen - estimate faster,cheaper and better!
 
The value of benchmarking IT projects - H.S. van Heeringen
The value of benchmarking IT projects - H.S. van HeeringenThe value of benchmarking IT projects - H.S. van Heeringen
The value of benchmarking IT projects - H.S. van Heeringen
 
Begroten van agile projecten, technical meeting Sogeti 2013-09
Begroten van agile projecten, technical meeting Sogeti 2013-09Begroten van agile projecten, technical meeting Sogeti 2013-09
Begroten van agile projecten, technical meeting Sogeti 2013-09
 
Sogeti seminar Supplier Performance Measurement
Sogeti seminar Supplier Performance MeasurementSogeti seminar Supplier Performance Measurement
Sogeti seminar Supplier Performance Measurement
 
Software Estimating and Performance Measurement
Software Estimating and Performance MeasurementSoftware Estimating and Performance Measurement
Software Estimating and Performance Measurement
 
Project Control using functional size - which method to use?
Project Control using functional size - which method to use?Project Control using functional size - which method to use?
Project Control using functional size - which method to use?
 
Metrics based software supplier selection - Best practice used in the largest...
Metrics based software supplier selection - Best practice used in the largest...Metrics based software supplier selection - Best practice used in the largest...
Metrics based software supplier selection - Best practice used in the largest...
 
ISPA/SCEA conference Brussels 2012
ISPA/SCEA conference Brussels 2012ISPA/SCEA conference Brussels 2012
ISPA/SCEA conference Brussels 2012
 

Recently uploaded

The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 

Recently uploaded (20)

The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 

Productivity measurement of agile teams (IWSM 2015)

  • 1. Productivity measurement of agile teams – overcoming the issues with non-functional requirements. Harold van Heeringen METRI B.V. Schiphol-Rijk, the Netherlands harold.van.heeringen@metrigroup.com Theo Prins Sizing, Estimating & Control Sogeti Nederland B.V. Vianen, Nederland theo.prins@sogeti.com Edwin van Gorp Sizing, Estimating & Control Sogeti Nederland B.V. Vianen, Nederland edwin.van.gorp@sogeti.com Abstract—Nowadays, as the software industry is slowly becoming more mature, software measurement and performance measurement are becoming increasingly important. Organizations need to know their productivity and competitiveness in software development projects for various reasons. In many software development contracts, targets are set for the suppliers to reach. These targets are based on software metrics like productivity, speed of delivery and software quality. In order to check if the targets are reached, it is necessary to measure the functional size of the software product that is delivered and also the functional size of the software development project that is carried out, as there is usually a difference between these two sizes. To be able to use functional size in contracts, it must be measured in an objective, repeatable, verifiable and therefore defensible way. That being the case, the industry’s best practice is to use an ISO/IEC standard for functional size measurement, e.g. Nesma, COSMIC or IFPUG function points. However, these methods only measure the functional user requirements from the total software requirements to be delivered. In activities like project estimation and productivity measurement, the influence of the non-functional requirements is expressed in the Project Delivery Rate (PDR) which is expressed in effort hours per function point. If more than the average amount of non-functional requirements need to be realized in a project (or more severe non-functional requirements), the PDR used should also be higher. In the industry it is customary to set productivity targets based on an average (or calibrated) influence of non-functional requirements and this works quite fine in traditional software projects. In software development projects that are executed in an agile way, this is not always the case. When working agile, there are forces that influence the traditional way of performance measurement significantly, resulting in a number of serious issues. In this paper these issues are explained and a method to overcome these issues is proposed. Keywords— agile development; story points, outsourcing, performance measurement, functional requirements, Nesma, ISBSG, non-functional requirements, Agile normalized size. I. INTRODUCTION These days, more and more software development projects are carried out in agile oriented approaches like Scrum or DSDM. Projects following an agile software development method deliver software in an iterative way. The iterations are usually called sprints. The main idea behind agile software development is that short feedback loops enable the customer (users) to experience the product sooner, which allows the requirements and solutions to evolve during the execution of the project. As Scrum is the most dominant agile software development method nowadays, this paper is primarily focused on this method and the concepts and terminology of Scrum are used in the text. 1. The development of a specific set of requirements in a specific period of time. Although executed in an iterative way, the project has a ‘goal’, and at one point it is decided that the project is finished. The product owner controls the project, making sure that the necessary functionality is delivered within time and budget. In traditional approaches, this type of development would be called a ‘New development project’ or a ‘release’; 2. The continued development (evolving) of an application. In this situation there is no definite duration or a specific set of user requirements. A year is divided into X sprints of Y weeks and the team is continuously working on the product backlog items the product owner deems the most important until, it is decided that the product does not need further maintenance (which may be in the far future). In traditional approaches, this type of development would be called ‘Maintenance’.
  • 2. Productivity measurement of the contract type listed as number 1, is not significantly different in agile projects than in traditional projects. In both approaches, the difficulty lies in measuring all functional changes properly in order to measure the actual project size. The focus of this paper is on the contract type described under number 2. A team is working for an indefinite period of time, which is divided into sprints of 2, 3 or 4 weeks length each, on a product backlog. The product backlog is prioritized in such a way that the product backlog items (PBI’s) with the highest importance are planned to be delivered first. The PBI’s are also rated in story points, which are assigned in a team effort. II. PRODUCTIVITY MEASUREMENT IN TRADITIONAL SOFTWARE PROJECTS Productivity measurement in traditional software development projects is quite straightforward [1]. The customer and the supplier have to agree on a few items beforehand, the most important being:  Which (variant of which) size measurement method to use;  Which performance metrics to use;  Which activities are in scope and which activities are out of scope for the performance measurement;  Which are the benchmarks or targets to use per metric;  Who is measuring, who is reviewing, how to deal with differences of opinion. To give an example, let’s look at a performance measurement contract that a government agency and a supplier used to measure the performance in a specific Java development project with an indicative size of around 400 Nesma [2] function points (FP). The items above were addressed in the following way:  Size measurement: Estimated Nesma [3] ;  Performance metrics: o Productivity: PDR (h/FP); o Functional Quality: Defects/FP Acceptance Test + 1st month production; o Delivery Speed: FP per calendar month.  Activities in scope: Technical design, Coding, Programmer test, System test, Support acceptance test, Project management, Quality assurance;  Activities out of scope: Functional design, delivery management, acceptance test, implementation;  Benchmarks targets: A relevant subset from the ISBSG repository New Developments & Enhancements [4] (e.g. Java projects, Government, size between 300 and 500 FP) o PDR: ISBSG subset median PDR; o Defects/FP: ISBSG subset percentile 25%; o Speed of deliver: ISBSG subset median PDR.  The supplier measures the functional size, the customer reviews the size measurement. The metrics can be audited by the customer periodically. Independent third parties may be used to solve differences of opinion. Because of the specific set of requirements and the fact that the goal of the project is clear (to realize that specific set of requirements), the performance measurement is pretty straightforward. As it is a Java development project for a government agency, it is easy to select a proper subset from the ISBSG repository to set the targets and benchmarks for this project. If there are specific non-functional requirements that are expected to have a significant influence on the performance, the benchmarks and targets may need to be re-evaluated and agreed upon. After the project has finished, the project size is determined, the performance metrics are calculated and it becomes clear if the performance targets are met or not.. III. WHY ARE AGILE PROJECTS DIFFERENT? Most people in the software industry know the four main principles of the agile manifesto [5]:  Individuals and interactions over processes and tools;  Working software over comprehensive documentation;  Customer collaboration over contract negotiation;  Responding to change over following a plan. Although the items on the right of the word ‘over’ are still important, the items on the left are considered more important. In practice, an agile project can be described in the following general way: A very important role is played by the product owner, who is a representative of the customer/user organization. This product owner needs to be knowledgeable about the functionality of the product and the business value it offers to the users. Also, the product owner needs to have a mandate from the customer organization to make decisions and he needs to be committed to fulfill his role. This means that he is able to devote the time needed to carry out his role, this means that he is able to meet with the team when necessary, make decisions when necessary and prioritize the backlog items by business value. There is a product backlog available which lists the product backlog items identified by the product owner. These backlog items are either functional or non-functional by nature. The effort needed to realize the product backlog items are estimated by the team members using story points. Although many people in the agile community think the story point measure is a size measure, it is in fact an effort measure. It is a relative measure which gives an estimate of how many hours the team thinks they need to spend on a particular product backlog item, compared to
  • 3. a specific baseline backlog item to which a random number of story points was assigned. There is no standard approach for assigning story points. Most teams identify the smallest product backlog item in the product backlog and assign 1, 2 or 3 story points to it. All other backlog items are then compared to this baseline backlog item and the number of story points assigned to them reflect the effort the team needs to realize them, compared to the baseline item. This method is absolutely subjective and probably not very repeatable or verifiable. Although story points are quite useful for sprint planning, as to decide which product backlog items can be realized in a specific sprint, metrics based on story points are completely useless for performance measurement. As there is no standard for assigning story points (it is not a measurement activity), it is quite easy to manipulate the amount of story points realized in a sprint in order to comply to the targets set. And since there is no reference point, it is easy to manipulate the targets as well. But still, organizations wish, and sometimes need, to measure the performance of their suppliers, also in agile executed projects. In many cases the usual performance metrics are agreed upon, but instead of using a project or a release as a basis for measurement, the performance measurement instrument is applied to sprints. This means that for every sprint, the functional size delivered should be measured, the effort hours in scope need to be retrieved, the defects found and resolved must be identified and the performance metrics should be calculated. Some issues, when not properly addressed, already arise here:  Agile teams don’t usually register defects. Especially not when they are easy to resolve;  Agile teams are multidisciplinary by nature. Sometimes it is hard for the team members to register their effort on specific tasks. This is important however, as some tasks may be out of scope for performance measurement;  Agile teams sometimes don’t change the functional documentation in the same sprint where the functionality is realized in. This makes it difficult to measure the functional size of that sprint;  According to the theory, at the end of each sprint, working software is delivered that could be implemented in a production environment. In practice, this is not always the case and product backlog items are declared “not ready” at the end of the sprint. As only functionality that is ready is measured, this means a low size delivered in that sprint and possibly a relatively high size delivered in the next sprint. The product owner decides which product backlog items are the most important. Here, the main issue comes to light. The product owner may decide that mainly non-functional backlog items need to be realized in a specific sprint. As functional size measurement methods only measure the functional user requirements, a size measurement of such a sprint would result in a few (or even zero) function points. In these cases, the usual performance metrics result in bad values and targets are not met for that sprint. So, there is a number of issues when trying to implement the traditional performance measurement instrument on sprint level in agile contracts. Summarized these issues are:  The functional size of the delivered product can be hard to measure, either because of under specification, or because the documentation provided does not reflect the status of the product after the sprint;  The effort hours are not booked consciously on the right tasks in the effort registration system, making it hard to define the number of hours spent on the activities in scope of the performance measurement;  During the sprint, system tests and acceptance tests are carried out, but defects found and defects resolved are not logged appropriately, making it hard to use the quality metrics.  The functional size delivered in a sprint may be very low (or zero), seriously affecting the performance metrics. Reasons for this could be (not limitative): o The product backlog items turned out to be too big to deliver in a sprint and were not ready; o Illness of team members or other unplanned events that may have disturbed productivity; o Non-functional backlog items to realize in the sprint (e.g. improving performance, security, code quality, et cetera).Finally, complete content and organizational editing before formatting. Please take note of the following items when proofreading spelling and grammar: These issues result in very uneven performance metrics over time. An example of how this could look like is given below for the PDR. Let’s say the following data is measured for 8 sprints (table 1). Sprint 1 2 3 4 5 6 7 8 Effort 345 389 367 412 365 375 390 401 Size (FP) 15 5 16 3 25 0 36 32 Table 1 This would result in the following PDR per sprint (table 2). Sprint 1 2 3 4 5 6 7 8 PDR (h/FP) 23,0 77,8 22,9 137,3 14,6 n/a 10,8 12,5 Table 2 In sprint 6 zero function points were realized, so it is impossible to determine the PDR in h/FP. Let’s assume the target PDR for the specific project is set to be 25,0 hours per function point, the performance graph would look like in figure 1.
  • 4. Fig. 1. PDR actual vs. target The productivity realized shows a very uneven view. In the next paragraph a method is proposed that should give better insight into the suppliers capabilities and performance. An option to overcome the issues mentioned would be to only use the effort hours spent on functional backlog items for the performance measurement. In practice, it is very hard to identify these effort hours. Furthermore, this approach makes it easy to manipulate the performance measurement simply by booking more hours on non-functional backlog items (assuming that there is no control on the effort hours booked). Instead of normalizing the effort hours to match the functional size, the method proposed in this paper is to normalize the functional size to match the total effort. IV. PROPOSED METHOD The performance measurement method that is proposed in this paper is to normalize the functional size in order to determine the functional size that the team could have realized if they would not have been instructed to realize any non- functional backlog items. This method enables organizations to use the standard methods and techniques for performance measurement and benchmarking , while almost no extra data or effort is necessary. The method is not totally objective, but possibilities of manipulation (consciously or unconsciously) are very limited. In order to carry out this normalization activity, one extra activity needs to be performed. The Scrum team assigns story points to the backlog items, so the number of story points that is realized in a specific sprint is known. Of each of the sprint backlog items, the team should decide if the nature of the item is (mainly) functional or non-functional. The ratio between the functional and the non-functional story points is used to normalize the functional size. Examples of functional backlog items could be: Add a field to the database table ‘User’ named ‘twitter username’, add a field to the ‘manage user’ screen in which the administrator can enter the ‘twitter username’ and Add a twitter icon to the screen if the user has a ‘twitter username, linking to user’s twitter page. Examples of non-functional backlog items could be: Improve the performance of the batch job in order to have it run in under 2 hours, Improve the code quality of the application to be to compliant to SQALE rating A [6] or Upgrade the development environment to the next version, because the supplier stops supporting the current version any time soon’ The proposed method contains the following steps: 1. Measure the functional size of the functional sprint backlog items that were ready at the end of the sprint using one of the mentioned ISO/IEC standards for functional sizing; 2. Determine for all sprint backlog items that were ready at the end of the sprint, if these were functional or non- functional by nature. In case of a hybrid nature, try to assess the ratio functional/non-functional; 3. Determine the number of story points that were assigned to the functional backlog items that were ready at the end of the sprint; 4. Determine the total number of story points that were assigned to all backlog items that were ready at the end of the sprint; 5. Calculate the Agile Normalized Size (ANS) using this formula: ANS = (functional size / functional story points) * total story points Example: In a sprint, five backlog items were realized (see table 3). Three of them are functional by nature, the other two non-functional. The functional size of the functional backlog items is measured using Nesma function point analysis. Sprint X Nature Nesma FP Story points BLI 1 Functional 4 4 BLI 2 Non-functional 0 6 BLI 3 Non-functional 0 2 BLI 4 Functional 5 3 BLI 5 Functional 4 3 Total 13 18 Table 3 The ANS in this example is: (13 / 10) * 18 = 23,4 FP. The ANS represents the equivalent of the functional size that could have been realized if only functional backlog items would have been included in the sprint. 0,0 20,0 40,0 60,0 80,0 100,0 120,0 140,0 160,0 3 4 5 6 7 8 9 10 PDR (h/FP) Target PDR (h/FP)
  • 5. In table 4, it is displayed that the ANS gives a more accurate view of the size in sprints in which a lot of non-functional backlog items were realized. This is especially obvious in sprint 4: Table 4 Advantages of this method The main advantage of this method is that the influence of the non-functional backlog items is reduced, while still an ISO/IEC standard method is used in order to determine the functional size. This productivity can then be compared with data that is measured using the same (type of) ISO/IEC standard method. Disadvantages of this method The method is dependent on the story points assigned to the functional and non-functional backlog items. Assigning story points, as indicated before, is a highly subjective activity. However, as it is a necessary activity carried out before the actual start of the sprint and because of the fact that the product owner is usually present to oversee this activity, chances of the team manipulating the assigning of the story points are considered to be small. Also, for the determination of the nature of the backlog items, there is no standard approach, but usually it should be easy to understand if backlog items are functional or non-functional by nature. One other disadvantage of the method is that it is impossible to measure the ANS if only non-functional backlog items are realized in a specific sprint. In section V The Progressive Approach, this issue is solved. Effort hours in scope of performance measurement It is always important to carefully consider the effort hours that should be taken in scope of the performance measurement. Usually, the benchmark used determines the effort hours that are in scope, as you wish to compare apples with apples. If, for instance, the benchmark used is based on a project lifecycle excluding functional design and overhead hours, the effort hours spent on these activities should be placed out of scope for the performance measurement. Due to the fact that in the proposed method the size is normalized, all activities that are carried out to realize any backlog item, functional or non-functional, have to be in scope for performance measurement. This would mean activities like (not limitative):  Design (functional and/or technical);  Coding and programmer test;  System test;  Scrum master;  Project support (for the Scrum master);  Create/adjust documentation;  Resolving defects;  Research (proof of concepts et cetera);  Meetings / sessions. Effort hours spent on activities that are not directly related to realizing backlog items are out of scope for performance measurement, e.g.:  Delivery management;  Quality Management;  Project support (for the delivery management). After the effort hours in scope have been determined, the productivity per normalized FP can be calculated, see the example in table 5: Table 5 In the figure 2 it is clear that the hours/nFP metric provides a more stable view than the hours/FP metric. The fact that development of new functionality is not the most important goal is normalized into a situation where it is. Sprint Func. size Functional story points Non- functional story points Total story points ANS 1 20 32 12 44 27,5 2 25 y28 16 44 39,3 3 18 24 20 44 33 4 29 35 4 39 32,3 5 4 6 36 42 28 6 15 16 24 40 37,5 Sprint Func. size (FP) Agile normalized size (nFP) Effort spent Hours/ FP Hours /nFP 1 20 27,5 500 25 18,2 2 25 39,3 480 19,2 12,2 3 18 33 530 29,4 16,1 4 29 32,3 468 16,1 14,5 5 4 28 534 133,5 19,1 6 15 37,5 522 34,8 13,9
  • 6. Fig. 2. Hours/FP vs. Hours per nFP V. THE PROGRESSIVE APPROACH One of the aforementioned disadvantages of the proposed method is that it’s not possible to determine the normalized size for sprints in which no functional backlog items were realized. This can be obviated by using the progressive approach. The progressive approach divides the sum of the functional sizes of all completed sprints by the sum of the functional story points of these sprints. The result hereof is then multiplied with the sum of all story points of all completed sprints. This approach makes it possible to take sprints into account in which no functional backlog items were realized. In table 6, the example used earlier has been elaborated to explain the progressive approach: Sprint Functionalsize(FP) Functionalstorypoints Non-functionalstorypoints Totalstorypoints Agilenormalizedsize(nFP) Hours/nFP Hoursspent(cumulative) ANS(progressive) Hours(cum)/nFP(progressive) 1 20 32 12 44 27,5 18,2 500 27,5 18,2 2 25 28 16 44 39,3 12,2 980 66 14,8 3 18 24 20 44 33 16,1 1.510 99 15,3 4 29 35 4 39 32,3 14,5 1.978 132,2 15 5 4 6 36 42 28 19,1 2.512 163,6 15,4 6 15 16 24 40 37,5 13,9 3.034 199,2 15,2 7 0 0 41 41 n/a n/a 3.546 231,4 15,3 8 18 24 20 44 33 15,4 4.054 264,3 15,3 Table 6 The productivity expressed in hours/nFP and the productivity in hours (cum)/ nFP(progressive) can be benchmarked against the traditional internal and external hours/FP benchmarks, like for instance the ‘New Developments and Enhancements repository of the International Software Benchmarking Standards Group [4]. In the figure 3, the figures from the example are shown. The benchmark PDR in this example is set on 20 hours/FP. Fig. 3. The progressive apprach results The main benefits of the proposed method are clearly visible in sprints 5 (in which mainly non-functional backlog items were realized) and 7 (in which only non-functional backlog items were realized). Starting points In order to use the proposed method in the proper way, a number of starting points have to be taken into account. Effort administration  The effort hours need to be booked in the effort administration in such a way that it is possible to clearly identify the effort hours in scope and out of scope of the performance measurement;  All effort hours spent on the project must be booked, also overtime;  Hours spent on other projects should not be booked on the project that is being measured;  The team members need to understand the importance of an accurate and correct time administration. Documentation  After each sprint the functional documentation should be made up-to-date and it must be clear: o Which functionality was added in the sprint;
  • 7. o Which functionality was changed in the sprint and in which way; o Which functionality was deleted in the sprint. Size Measurement  The effort hours need to be booked in the effort administration in such a way that it is possible to clearly identify the effort hours in scope and out of scope of the performance measurement Product backlog and sprint backlog  The product backlog consists of functional and non- functional backlog items. For each item it is known which type it concerns;  All items have been assigned story points to in a realistic way;  The product owner decides which product backlog items will be placed on the sprint backlog of the sprints;  After each sprint it is decided which backlog items are ready (meet the definition of done1 ) and which items are not (or not completely); Data collection  After each sprint, a data collection form (DCF) must be filled in by the Scrum master. In this DCF at least the following information must be filled in: o the effort hours per activity; o the backlog items declared ready and their associated type; o the story points assigned to these backlog items. Performance Measurement  The productivity is determined using the method described above;  The functional size, the data and the results of the productivity measurement is stored in a central location;  Standard reports are created in which the productivity measurement is shown and compared to predefined internal and external benchmarks. Also trends in productivity within the projects are reported. VI. CONCLUSIONS More and more organizations adopt agile software development methodologies to deliver new functionality in a faster way to their customer. In the meantime, in the slowly maturing software industry, the need for productivity measurement is becoming more and more important, especially in outsourcing contracts. As long as the most important objective of agile projects remains delivering new or changed functionality, the traditional productivity measurement instruments can still be used in an effective way. In projects, or contracts, that are mainly about evolving a certain application, without a specific end date or a specific scope, the productivity is sometimes hard to measure in ISO/IEC standards for functional size measurements. The influence of non-functional requirements can really impact the productivity and the product owner (customer) is the only one who can control this. Some attempts have been made in the recent past to normalize the effort hours in order to capture only effort hours that were spent on functional user requirements. However, in practice it seems impossible to do so. Instead, this paper proposes to normalize the functional size in such a way that the functional size is calculated that could have been realized in a sprint if the product owner only put functional backlog items on the sprint backlog. Whether this method really is going to solve all the issues in productivity measurement of agile projects still has to be proven. REFERENCES [1] Bundshuh, M. and Dekkers, C, The IT Measurement Compendium, Estimating and benchmarking success with functional size measurement, page 313, Spinger, ISBN: 978-3-540-68187-8 [2] NESMA: ISO/IEC 24570:2005 Software engineering - NESMA function size measurement method version 2.1 - Definitions and counting guidelines for the application of Function Point Analysis, ISBN: 978-90- 76258-19-5 [3] Early Function Point Counting, http://nesma.org/themes/sizing/function- point-analysis/early-function-point-counting/ [4] International Software Benchmarking Standards Group (ISBSG) New Developments & enhancements R13, released February 22015, www.isbsg.org [5] Beck, Kent et al. (2001). "Manifesto for Agile Software Development". Agile Alliance. Retrieved 14 June 2010 [6] Letouzey, J-L, The SQALE Method for Evaluating Technical Debt, proceedings of the 3rd international workshop on managing technical debt (ICSE 2012), Zurich (Switzerland) june 9-12 2012. 1 The Definition of done is determined before the start of an agile project. Only if all characteristics of that definition have been met, the item is considered ‘ready’.