TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report – To Saturday 20 June 2015
Issued 21 June 2015
TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 20 June 2015
Issued 21 June 2015
Page 2 of 11
TABLE OF CONTENTS
1 ACTIONS & OPERATIONS – 7th
June to 20th
June 2015................................................................3
1.1 Power Restoration..............................................................................................................3
1.2 Water Restoration...............................................................................................................3
1.3 Sewer System......................................................................................................................3
1.4 Procurement .......................................................................................................................3
1.5 Operations Financing ..........................................................................................................3
2 PROGRESS ..................................................................................................................................3
3 MISCELLANEOUS........................................................................................................................4
3.1 Restoration Progress: .........................................................................................................4
3.2 Liaison with other agencies.................................................................................................5
3.2.1 IOM..............................................................................................................................5
3.2.2 Pohnpei Utility Corporation.........................................................................................5
3.2.3 National Government..................................................................................................5
3.3 Weather Advisory From National Weather Service Tiyan Guam .........................................5
3.4 Work Program.....................................................................................................................5
Annex 1 – Feeder Restoration & Solar System Condition Summaries ................................8
ANNEX 2 – Customer Meter Restoration Progress .............................................................9
ANNEX 3 – Restoration Summary Graphs ......................................................................... 10
TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 20 June 2015
Issued 21 June 2015
Page 3 of 11
1 ACTIONS & OPERATIONS – 7th
June to 20th
June 2015
1.1 Power Restoration
Primary line recovery efforts in the period have been directed in Wichap and Epinup over the period.
A further 3,250 feet (2.9% of total line length) of line has been reconstructed and energized during
the period. Total line operational to date is 98,700 feet or 89.4% of total line length.
Pole construction from Wichap repeater to the end of Epinup was completed on the 19th June and
restringing of the Epinup single phase line will be completed by the end of w/c 22 June.
Support to tree trimming at the Governor’s office was also provided during the period – this work
will be completed by 29th
June.
The peak load remains around 2.1 MW or 95% of peak prior to the typhoon with night-time load
around 1.3 MW. CPUC generation load profile from 30th
March to 31st
May is shown in Annex 3.
At 20th
June all three phase customers and 85.8% (1,491 number) of single phase customers have
been reconnected. Details are shown in Annex 2.
1.2 Water Restoration
Well restoration is complete across Weno.
1.3 Sewer System
Daily pumping operations continued on all lift stations;
1.4 Procurement
Essential materials have now started to arrive in Weno from the first purchase orders placed. CPUC is
still awaiting confirmation of USAID funding balance from IOM/USAID – further procurement is on
hold until that point.
1.5 Operations Financing
Operations continues to be financed from revenues – a detailed update on CPUC financial position
will be included in the June monthly report.
2 PROGRESS
Progress to date versus initial target is indicated in the Annexes 1 to 3 below.
Restoration progress summary charts are shown in Annex 2 & 3.
TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 20 June 2015
Issued 21 June 2015
Page 4 of 11
3 MISCELLANEOUS
3.1 Restoration Progress:
Summary of progress made in restoration is tabled below:
Feet
As % of
Network
Feet
As % of
Network
Feet
As % of
Network
Feet
As % of
Network
Total System Length: 110,305 110,305 110,305 110,305
Total Restored - 3 Phase 83,706 75.9% 86,192 78.1% 95,411 86.5% 98,666 89.4%
Total Ok but Off 6,675 6.1% 6,053 5.5% 3,248 2.9% 0 0.0%
Total Damaged 19,924 18.1% 18,060 16.4% 11,646 10.6% 11,639 10.6%
Restored Lengths
PP to WTP 3,565 3,565 3,565 3,565
COM to LS8A 933 933 933 933
PP to Tunnuk 13,285 13,285 13,285 13,285
Aiprort to WWTP 1,037 1,037 1,037 1,037
PP to Municipal 6,005 6,005 6,005 6,005
Back Road past Shigeto 1,882 1,882 1,882 1,882
V6K ot L5 1,490 1,490 1,490 1,490
Old Mormon corner to well 20 681 681 681 681
Municipal to Dump site corner 5,999 5,999 5,999 5,999
Dummp site to SDA 6,080 6,080 6,080 6,080
Blue Lagoon Spur 266 266 266 266
Blue Lagoon junct to LS 19 1,243 1,243 1,243 1,243
Tunnuk to LS 7 464 464 464 464
Tunnuk towards Pou Bay 723 723 723 723
Tunnuk to Peniesene - Single phase only 5,400 5,400 5,400 5,400
Upper Nantaku 1,075 1,075 1,075 1,075
F3 Weno Port Spur 550 550 550 550
LS8 to Well 15 460 460 460 460
Nepukos Jnct to 83-07 500 500 500 500
Nepukos Jnct to TH-09 320 320 320 320
mechitiw to ADB 4 1500 1500 1500 1500
Wichen Spur to ADB 10 1000 1000 1000 1000
F4 J Robert to Wichen Spur 1000 1000 1000 1000
Peniesene to Xavier Junction Sapuk 7300 7300 7300 7300
Xavier Jnctn to Kansou Bakery 590 590 590 590
ADB4 to F1: 30 1492 1492 1492 1492
F3: LS18 to LS19 2977 2977 2977 2977
Kurassa to Tonachau Mast 2857 2857 2857 2857
LS8 to Tunnuk Back Road Switch 520 520 520 520
Back road to Pink Apartment Tank 1342 1342 1342 1342
Pou Bay to Tunnuk Back Road 4309 4309 4309 4309
Well 15 to Hill to Mechitiw road 825 825 825 825
Link to Education past Governor office 725 725 725 725
Sapuk Kansou Bakery past KORDI 4811 4811 4811 4811
Nantaku Behind Governor's office 500 500 500 500
Xavier Jnctn to Xavier School 2486 2486 2486
N Sapuk Extension 580 580
Xavier Back Jnct to B Killion (east) 2588 2588
Sapuk Seaside West spur 3842 3842
Nepukos Back road left side 2209 2209
Blue Lagoon Corner to Wichap Repeater 3255
Total Restored 83,706 86,192 95,411 98,666
30-May23-May 06-Jun 19-Jun
TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 20 June 2015
Issued 21 June 2015
Page 5 of 11
To date full supply has been restored to 89.4% of the network – the three phase line from Blue
Lagoon corner in Neauo to Wichap Repeater has been rebuilt..
3.2 Liaison with other agencies
3.2.1 IOM
IOM will be acting as the contact agency for CPUC procurement of emergency materials under the
USAID funding program. The disbursement methodology is still being worked out between USAID
and OIM
3.2.2 Pohnpei Utility Corporation
PUC are supporting CPUC with 2 no. 4 man crews. A request has been made to retain one crew for
the first two weeks in July by which time it is anticipated that full system coverage will have been
restored.
3.2.3 National Government
CPUC CFO is liaising with FSM National Finance to disburse funds for the ongoing procurement.
Purchase contracts have been forwarded along with an anticipated disbursement plan.
3.3 Weather Advisory From National Weather Service Tiyan Guam
The latest weather advisory updates from NOAA can be obtained from the link below:
http://www.prh.noaa.gov/guam/MicroHazards.php
There is currently no tropical storm activity in the region.
A six day weather summary for Weno can be found at the link below:
http://www.tide-forecast.com/locations/Moen-Island-Chuuk-
FederatedStatesofMicronesia/forecasts/latest/six_dayp
3.4 Work Program
A work program from 22nd
June to 11th
July is under preparation and will be issued on 22nd
June. This
will be posted on CPUC website: http://www.cpuc.fm/typhoon-maysak-recovery/work-programs/
Note – CPUC Sewer and Water Systems are fully restored to pre-typhoon conditions. Relevant maps
of these systems have now been deleted from the report.
TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 20 June 2015
Issued 21 June 2015
Page 6 of 11
Primary Cable Status as of 5:00 pm 20 June 2o15
Yellow – Primary 3 Phase restored – 89.4% of system
length;
Green Primary in place but off;
Red – Primary down;
Pink - Line rebuildingongoing in Epinup;
CPUCService crewsare workingre-establish supply in
primaryrestoredareas– significant damageto serviceshas
occurred;
CPUC Power System Recovery Progress – 5:00 pm 20 June 2015
TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 6 June 2015
Issued 8 June 2015
Page 7 of 11
Initial Damage Assessment – (minor revision from 4th
April)
Feet As %
Total System Length 110,305
Total Restored 28,197 25.6%
Total Ok but Off 33,019 29.9%
Total Damaged 49,089 44.5%
Restored Lengths
PP to WTP 3,565
COM to LS8A 933
PP to Tunnuk 13,285
Aiprort to WWTP 1,037
PP to Municipal 6,005
Back Road past Shigeto 1,882
V6K ot L5 1,490
Total Restored 28,197
Unrestored Areas Primary Line Status
OK Down ok Straighten Replace
Tunnuk to Sapuk 18,874 11,936 88 6 41
Peniesene along Wichen river 0 1,963 0 0 8
Municipal to Epinup 11,713 14,263 118 6 20
Nepukos Backroad 0 6,648 0 0 44
Behind Governor office 0 1,070 4 6
F1 Pou Bay CSHS to Mechitiw 550 4,272 11 6 8
F2 Pou Bay CSHS to Tunnuk 1,882 5,010 19 10 7
Nantaku Hill to WTP 0 1,070 6 0 0
Kurassa to Telecome Mast 0 2,857 0 0 10
Total Unrestored 33,019 49,089 246 28 144
Pole Status
TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 6 June 2015
Issued 8 June 2015
Page 8 of 11
Annex 1 – Feeder Restoration & Solar System Condition Summaries
Target Actual
Feeder 1
Power Plant to Hospital 30 March 2015 30 March 2015
Hospital to Nantaku WTP 03 April 2015 11 April 2015
Feeder 2
Power Plant to Governors Office 31 March 2015 31 March 2015
Governors office to CSHS 01 April 2015 31 March 2015
CSHS to Mechitiw backroad (Pou Bay West) 18 April 2015 18 April 2015
CHSH to Tunnuk backrooad (Pou Bay East) 06 May 2015 06 May 2015
CSHS to Pink Apt Tank 05 May 2015 05 May 2015
Feeder 3
Power Plant to Downtown gas Station 31 March 2015 31 March 2015
Downtown Gas Station to Municipal Office 03 April 2015 03 April 2015
Municipal Office to Mizpah 07 April 2015 06 April 2015
Nepukos Backroad - Yamaha to Nepukos jnctn 04 April 2015 04 April 2015
Nepukos Jnctn to Mizpah 07 July 2015 Partial - TH-09; and 83-07 15 April
Mizpah to dump site road jnctn 07 April 2015 06 April 2015
Dump site road jnctn to Blue Lagoon - back road 07 April 2015 07 April 2015
Dump site road jnctn to Blue Lagoon corner - main road 02 May 2015 01 May 2015
Blue Lagoon corner to Quarry 20 June 2015 20 June 2015
Quarry to Wichap 20 June 2015 20 June 2015
Wichap to Epinup 28 June 2015
Feeder 4
Power plant to Airport 30 March 2015 30 March 2015
Airport to WWTP 30 March 2015 30 March 2015
Airport to Kurassa 01 April 2015 31 March 2015
Kurassa to telecom Tower 03 April 2015 02 May 2015
Kurassa to Mechitiw corner 03 April 2015 01 April 2015
Mechitiw corner to Tunnuk (Pou Bay Causeway) 06 April 2015 01 April 2015
Tunnuk to Penia 15 April 2015 15 April 2015
Penia to Peniesene 27 April 2015 24 April 2015
Peniesene spur 02 May 2015 19 April 105 Partial to Well ADB-10
Peniesene to Xavier Jnctn 02 May 2015 24 April 2015
Xavier Jnctn to Sapuk 23 May 2015 22 May 2105
Xavier jnctn to Xavier HS 30 May 2015 30 May 2015
Xavier sea side to Sapuk 02 June 2015 04 June 2015 Patched line/extension from KSORC Side;
SOLAR PV SYSTEMS
Grid Connected:
Weno - Chuuk State High School - 200 kWp 8% panel damage - system repair schedule for early July 2015
Weno - Chuuk International Airport - 65 kWp System fully restored - 2 April 2015
Stand Alone (schools and Dispensaries):
Moch - Mortlocks Region Operational
Satowan - Mortlocks Region Operational
Lechinioch - Mortlocks Region Operational
Oneop - Mortlocks Region Inoperational - Equipment failure pre-typhoon
Onoun - Northwest Operational
Fanapanges - Faichuk Region Operational
Central Wonip - Faichuk Region Operational
Munian - Faichuk Region Operational
Udot -- Faichuk Region Operational
Uman - Southern Namoneas Operational
Fefan (Sapore and West Fefan) - Southern Namoneas Operational
Restore Date
Feeder Section Comments
TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 6 June 2015
Issued 8 June 2015
Page 9 of 11
ANNEX 2 – Customer Meter Restoration Progress
SINGLE PHASE METER RESTORATION PROGRESS - 19 June 2015
Weno Villages With Primary Power Restored
Village Connections Restored Balance Restore %
IRAS 283 262 21 92.6%
MECHITIW 259 232 27 89.6%
MWAN 203 175 28 86.2%
NANTAKU 13 13 0 100.0%
NEAUO 107 95 12 88.8%
NEPUKOS 498 466 32 93.6%
PENIA 32 31 1 96.9%
PENIESENE 67 54 13 80.6%
SAPUK 101 73 28 72.3%
TUNNUK 102 90 12 88.2%
WICHAP 58 0 58 0.0%
Total 1,723 1,491 232 86.5%
Weno Villages Without Primary Power Restored
Village Connections Restored Balance Restore %
EPINUP 15 0 15 0.0%
Total 15 0 15 0.0%
System Total 1,738 1,491 247 85.8%
Three phase meter restoration is now fully complete
TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 6 June 2015
Issued 8 June 2015
Page 10 of 11
ANNEX 3 – Restoration Summary Graphs
The graphs below show restoration progress towards achieving 100% system restoration
0
20,000
40,000
60,000
80,000
100,000
120,000
29-Mar
31-Mar
02-Apr
04-Apr
06-Apr
08-Apr
10-Apr
12-Apr
14-Apr
16-Apr
18-Apr
20-Apr
22-Apr
24-Apr
26-Apr
28-Apr
30-Apr
02-May
04-…
06-…
08-…
10-May
12-May
14-May
16-May
18-May
20-May
22-May
24-May
26-May
28-May
30-May
01-Jun
03-Jun
05-Jun
07-Jun
09-Jun
11-Jun
13-Jun
15-Jun
17-Jun
19-Jun
PrimaryLineLengthRestoredInFeet
CPUC - Primary Line Restoration Progress
Total Primary Line Length
Primary Line Restored
0
200
400
600
800
1000
1200
1400
1600
1800
2000
30-Mar
01-Apr
03-Apr
05-Apr
07-Apr
09-Apr
11-Apr
13-Apr
15-Apr
17-Apr
19-Apr
21-Apr
23-Apr
25-Apr
27-Apr
29-Apr
01-May
03-May
05-May
07-May
09-May
11-May
13-May
15-May
17-May
19-May
21-May
23-May
25-May
27-May
29-May
31-May
02-Jun
04-Jun
06-Jun
08-Jun
10-Jun
12-Jun
14-Jun
16-Jun
18-Jun
No.ofConnectionsRestored
CPUC - Single Phase Power Connection Restoration Progress
Total Connections
Restored Connections
TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 6 June 2015
Issued 8 June 2015
Page 11 of 11

More Related Content

Viewers also liked

Zooplacnton agua dulce
Zooplacnton  agua dulceZooplacnton  agua dulce
Zooplacnton agua dulceKaren Baque
 
Vodafone case study
Vodafone case studyVodafone case study
Vodafone case studyvishnu1204
 
Interpretes mas reconocidos
Interpretes mas reconocidosInterpretes mas reconocidos
Interpretes mas reconocidosanamaria2409
 

Viewers also liked (6)

3D printing
3D printing3D printing
3D printing
 
Resume_Ronak Dhalawat
Resume_Ronak DhalawatResume_Ronak Dhalawat
Resume_Ronak Dhalawat
 
Zooplacnton agua dulce
Zooplacnton  agua dulceZooplacnton  agua dulce
Zooplacnton agua dulce
 
Vodafone case study
Vodafone case studyVodafone case study
Vodafone case study
 
Unido
UnidoUnido
Unido
 
Interpretes mas reconocidos
Interpretes mas reconocidosInterpretes mas reconocidos
Interpretes mas reconocidos
 

Similar to CPUC - Typhoon Maysak - Restoration Report To 20 June 2015

Report of the committee appointed to investigate the Electricity Supply Inter...
Report of the committee appointed to investigate the Electricity Supply Inter...Report of the committee appointed to investigate the Electricity Supply Inter...
Report of the committee appointed to investigate the Electricity Supply Inter...Private Consultants
 
Msedcl aar 2018-19
Msedcl aar 2018-19Msedcl aar 2018-19
Msedcl aar 2018-19ZahidManiyar
 
Monthly report of maintenance by Swamina International Ltd.
Monthly report of maintenance by Swamina International Ltd.Monthly report of maintenance by Swamina International Ltd.
Monthly report of maintenance by Swamina International Ltd.TusarKole
 
Pakistan electric power crisis and its possible solutions
Pakistan electric power crisis and its possible solutionsPakistan electric power crisis and its possible solutions
Pakistan electric power crisis and its possible solutionsAmad Ali
 
Monthly report may 2013 final1
Monthly report may 2013   final1Monthly report may 2013   final1
Monthly report may 2013 final1vuurenian
 
Project report-TATA Power
Project report-TATA PowerProject report-TATA Power
Project report-TATA PowerSHIVAM DWIVEDI
 
Ministry electric power_myanmar_2_27_13
Ministry electric power_myanmar_2_27_13Ministry electric power_myanmar_2_27_13
Ministry electric power_myanmar_2_27_13Seokho Shin
 
Clean Energy Council (CEC) Annual Conference 2015 Compiled Presentations
Clean Energy Council (CEC) Annual Conference 2015 Compiled Presentations Clean Energy Council (CEC) Annual Conference 2015 Compiled Presentations
Clean Energy Council (CEC) Annual Conference 2015 Compiled Presentations Turlough Guerin GAICD FGIA
 
PM Performamnec report- Jan'23.pptx
PM Performamnec report- Jan'23.pptxPM Performamnec report- Jan'23.pptx
PM Performamnec report- Jan'23.pptxsantosh509014
 
Ipp process in indonesia 1995 by cockcroft and fuller
Ipp process in indonesia 1995 by cockcroft and fullerIpp process in indonesia 1995 by cockcroft and fuller
Ipp process in indonesia 1995 by cockcroft and fullerPeter Cockcroft
 
Gasoducto Sur Peruano en Calgary
Gasoducto Sur Peruano en CalgaryGasoducto Sur Peruano en Calgary
Gasoducto Sur Peruano en CalgaryErnesto Linares
 
Presentation september - fina lv2
Presentation   september - fina lv2Presentation   september - fina lv2
Presentation september - fina lv2FirstQuantum
 
Flinders Island Isolated Power System (IPS) Connect 2016 F GAFARO IRENA
Flinders Island Isolated Power System (IPS) Connect 2016 F GAFARO IRENAFlinders Island Isolated Power System (IPS) Connect 2016 F GAFARO IRENA
Flinders Island Isolated Power System (IPS) Connect 2016 F GAFARO IRENAjames hamilton
 
Corporate Presentation September 2015
Corporate Presentation September 2015Corporate Presentation September 2015
Corporate Presentation September 2015FirstQuantum
 
TRANSIENT STABILITY ANALYSIS
TRANSIENT STABILITY ANALYSISTRANSIENT STABILITY ANALYSIS
TRANSIENT STABILITY ANALYSISJeff taly
 

Similar to CPUC - Typhoon Maysak - Restoration Report To 20 June 2015 (20)

Report of the committee appointed to investigate the Electricity Supply Inter...
Report of the committee appointed to investigate the Electricity Supply Inter...Report of the committee appointed to investigate the Electricity Supply Inter...
Report of the committee appointed to investigate the Electricity Supply Inter...
 
Msedcl aar 2018-19
Msedcl aar 2018-19Msedcl aar 2018-19
Msedcl aar 2018-19
 
Monthly report of maintenance by Swamina International Ltd.
Monthly report of maintenance by Swamina International Ltd.Monthly report of maintenance by Swamina International Ltd.
Monthly report of maintenance by Swamina International Ltd.
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
Pakistan electric power crisis and its possible solutions
Pakistan electric power crisis and its possible solutionsPakistan electric power crisis and its possible solutions
Pakistan electric power crisis and its possible solutions
 
Monthly report may 2013 final1
Monthly report may 2013   final1Monthly report may 2013   final1
Monthly report may 2013 final1
 
Project report-TATA Power
Project report-TATA PowerProject report-TATA Power
Project report-TATA Power
 
Chakresh meecl report
Chakresh meecl reportChakresh meecl report
Chakresh meecl report
 
Eskom load shedding
Eskom load sheddingEskom load shedding
Eskom load shedding
 
Ministry electric power_myanmar_2_27_13
Ministry electric power_myanmar_2_27_13Ministry electric power_myanmar_2_27_13
Ministry electric power_myanmar_2_27_13
 
Clean Energy Council (CEC) Annual Conference 2015 Compiled Presentations
Clean Energy Council (CEC) Annual Conference 2015 Compiled Presentations Clean Energy Council (CEC) Annual Conference 2015 Compiled Presentations
Clean Energy Council (CEC) Annual Conference 2015 Compiled Presentations
 
PM Performamnec report- Jan'23.pptx
PM Performamnec report- Jan'23.pptxPM Performamnec report- Jan'23.pptx
PM Performamnec report- Jan'23.pptx
 
Ipp process in indonesia 1995 by cockcroft and fuller
Ipp process in indonesia 1995 by cockcroft and fullerIpp process in indonesia 1995 by cockcroft and fuller
Ipp process in indonesia 1995 by cockcroft and fuller
 
Gasoducto Sur Peruano en Calgary
Gasoducto Sur Peruano en CalgaryGasoducto Sur Peruano en Calgary
Gasoducto Sur Peruano en Calgary
 
Presentation september - fina lv2
Presentation   september - fina lv2Presentation   september - fina lv2
Presentation september - fina lv2
 
Flinders Island Isolated Power System (IPS) Connect 2016 F GAFARO IRENA
Flinders Island Isolated Power System (IPS) Connect 2016 F GAFARO IRENAFlinders Island Isolated Power System (IPS) Connect 2016 F GAFARO IRENA
Flinders Island Isolated Power System (IPS) Connect 2016 F GAFARO IRENA
 
Corporate Presentation September 2015
Corporate Presentation September 2015Corporate Presentation September 2015
Corporate Presentation September 2015
 
TRANSIENT STABILITY ANALYSIS
TRANSIENT STABILITY ANALYSISTRANSIENT STABILITY ANALYSIS
TRANSIENT STABILITY ANALYSIS
 
Dashboard
DashboardDashboard
Dashboard
 
Final report
Final reportFinal report
Final report
 

CPUC - Typhoon Maysak - Restoration Report To 20 June 2015

  • 1. Page 1 of 11 TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report – To Saturday 20 June 2015 Issued 21 June 2015
  • 2. TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 20 June 2015 Issued 21 June 2015 Page 2 of 11 TABLE OF CONTENTS 1 ACTIONS & OPERATIONS – 7th June to 20th June 2015................................................................3 1.1 Power Restoration..............................................................................................................3 1.2 Water Restoration...............................................................................................................3 1.3 Sewer System......................................................................................................................3 1.4 Procurement .......................................................................................................................3 1.5 Operations Financing ..........................................................................................................3 2 PROGRESS ..................................................................................................................................3 3 MISCELLANEOUS........................................................................................................................4 3.1 Restoration Progress: .........................................................................................................4 3.2 Liaison with other agencies.................................................................................................5 3.2.1 IOM..............................................................................................................................5 3.2.2 Pohnpei Utility Corporation.........................................................................................5 3.2.3 National Government..................................................................................................5 3.3 Weather Advisory From National Weather Service Tiyan Guam .........................................5 3.4 Work Program.....................................................................................................................5 Annex 1 – Feeder Restoration & Solar System Condition Summaries ................................8 ANNEX 2 – Customer Meter Restoration Progress .............................................................9 ANNEX 3 – Restoration Summary Graphs ......................................................................... 10
  • 3. TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 20 June 2015 Issued 21 June 2015 Page 3 of 11 1 ACTIONS & OPERATIONS – 7th June to 20th June 2015 1.1 Power Restoration Primary line recovery efforts in the period have been directed in Wichap and Epinup over the period. A further 3,250 feet (2.9% of total line length) of line has been reconstructed and energized during the period. Total line operational to date is 98,700 feet or 89.4% of total line length. Pole construction from Wichap repeater to the end of Epinup was completed on the 19th June and restringing of the Epinup single phase line will be completed by the end of w/c 22 June. Support to tree trimming at the Governor’s office was also provided during the period – this work will be completed by 29th June. The peak load remains around 2.1 MW or 95% of peak prior to the typhoon with night-time load around 1.3 MW. CPUC generation load profile from 30th March to 31st May is shown in Annex 3. At 20th June all three phase customers and 85.8% (1,491 number) of single phase customers have been reconnected. Details are shown in Annex 2. 1.2 Water Restoration Well restoration is complete across Weno. 1.3 Sewer System Daily pumping operations continued on all lift stations; 1.4 Procurement Essential materials have now started to arrive in Weno from the first purchase orders placed. CPUC is still awaiting confirmation of USAID funding balance from IOM/USAID – further procurement is on hold until that point. 1.5 Operations Financing Operations continues to be financed from revenues – a detailed update on CPUC financial position will be included in the June monthly report. 2 PROGRESS Progress to date versus initial target is indicated in the Annexes 1 to 3 below. Restoration progress summary charts are shown in Annex 2 & 3.
  • 4. TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 20 June 2015 Issued 21 June 2015 Page 4 of 11 3 MISCELLANEOUS 3.1 Restoration Progress: Summary of progress made in restoration is tabled below: Feet As % of Network Feet As % of Network Feet As % of Network Feet As % of Network Total System Length: 110,305 110,305 110,305 110,305 Total Restored - 3 Phase 83,706 75.9% 86,192 78.1% 95,411 86.5% 98,666 89.4% Total Ok but Off 6,675 6.1% 6,053 5.5% 3,248 2.9% 0 0.0% Total Damaged 19,924 18.1% 18,060 16.4% 11,646 10.6% 11,639 10.6% Restored Lengths PP to WTP 3,565 3,565 3,565 3,565 COM to LS8A 933 933 933 933 PP to Tunnuk 13,285 13,285 13,285 13,285 Aiprort to WWTP 1,037 1,037 1,037 1,037 PP to Municipal 6,005 6,005 6,005 6,005 Back Road past Shigeto 1,882 1,882 1,882 1,882 V6K ot L5 1,490 1,490 1,490 1,490 Old Mormon corner to well 20 681 681 681 681 Municipal to Dump site corner 5,999 5,999 5,999 5,999 Dummp site to SDA 6,080 6,080 6,080 6,080 Blue Lagoon Spur 266 266 266 266 Blue Lagoon junct to LS 19 1,243 1,243 1,243 1,243 Tunnuk to LS 7 464 464 464 464 Tunnuk towards Pou Bay 723 723 723 723 Tunnuk to Peniesene - Single phase only 5,400 5,400 5,400 5,400 Upper Nantaku 1,075 1,075 1,075 1,075 F3 Weno Port Spur 550 550 550 550 LS8 to Well 15 460 460 460 460 Nepukos Jnct to 83-07 500 500 500 500 Nepukos Jnct to TH-09 320 320 320 320 mechitiw to ADB 4 1500 1500 1500 1500 Wichen Spur to ADB 10 1000 1000 1000 1000 F4 J Robert to Wichen Spur 1000 1000 1000 1000 Peniesene to Xavier Junction Sapuk 7300 7300 7300 7300 Xavier Jnctn to Kansou Bakery 590 590 590 590 ADB4 to F1: 30 1492 1492 1492 1492 F3: LS18 to LS19 2977 2977 2977 2977 Kurassa to Tonachau Mast 2857 2857 2857 2857 LS8 to Tunnuk Back Road Switch 520 520 520 520 Back road to Pink Apartment Tank 1342 1342 1342 1342 Pou Bay to Tunnuk Back Road 4309 4309 4309 4309 Well 15 to Hill to Mechitiw road 825 825 825 825 Link to Education past Governor office 725 725 725 725 Sapuk Kansou Bakery past KORDI 4811 4811 4811 4811 Nantaku Behind Governor's office 500 500 500 500 Xavier Jnctn to Xavier School 2486 2486 2486 N Sapuk Extension 580 580 Xavier Back Jnct to B Killion (east) 2588 2588 Sapuk Seaside West spur 3842 3842 Nepukos Back road left side 2209 2209 Blue Lagoon Corner to Wichap Repeater 3255 Total Restored 83,706 86,192 95,411 98,666 30-May23-May 06-Jun 19-Jun
  • 5. TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 20 June 2015 Issued 21 June 2015 Page 5 of 11 To date full supply has been restored to 89.4% of the network – the three phase line from Blue Lagoon corner in Neauo to Wichap Repeater has been rebuilt.. 3.2 Liaison with other agencies 3.2.1 IOM IOM will be acting as the contact agency for CPUC procurement of emergency materials under the USAID funding program. The disbursement methodology is still being worked out between USAID and OIM 3.2.2 Pohnpei Utility Corporation PUC are supporting CPUC with 2 no. 4 man crews. A request has been made to retain one crew for the first two weeks in July by which time it is anticipated that full system coverage will have been restored. 3.2.3 National Government CPUC CFO is liaising with FSM National Finance to disburse funds for the ongoing procurement. Purchase contracts have been forwarded along with an anticipated disbursement plan. 3.3 Weather Advisory From National Weather Service Tiyan Guam The latest weather advisory updates from NOAA can be obtained from the link below: http://www.prh.noaa.gov/guam/MicroHazards.php There is currently no tropical storm activity in the region. A six day weather summary for Weno can be found at the link below: http://www.tide-forecast.com/locations/Moen-Island-Chuuk- FederatedStatesofMicronesia/forecasts/latest/six_dayp 3.4 Work Program A work program from 22nd June to 11th July is under preparation and will be issued on 22nd June. This will be posted on CPUC website: http://www.cpuc.fm/typhoon-maysak-recovery/work-programs/ Note – CPUC Sewer and Water Systems are fully restored to pre-typhoon conditions. Relevant maps of these systems have now been deleted from the report.
  • 6. TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 20 June 2015 Issued 21 June 2015 Page 6 of 11 Primary Cable Status as of 5:00 pm 20 June 2o15 Yellow – Primary 3 Phase restored – 89.4% of system length; Green Primary in place but off; Red – Primary down; Pink - Line rebuildingongoing in Epinup; CPUCService crewsare workingre-establish supply in primaryrestoredareas– significant damageto serviceshas occurred; CPUC Power System Recovery Progress – 5:00 pm 20 June 2015
  • 7. TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 6 June 2015 Issued 8 June 2015 Page 7 of 11 Initial Damage Assessment – (minor revision from 4th April) Feet As % Total System Length 110,305 Total Restored 28,197 25.6% Total Ok but Off 33,019 29.9% Total Damaged 49,089 44.5% Restored Lengths PP to WTP 3,565 COM to LS8A 933 PP to Tunnuk 13,285 Aiprort to WWTP 1,037 PP to Municipal 6,005 Back Road past Shigeto 1,882 V6K ot L5 1,490 Total Restored 28,197 Unrestored Areas Primary Line Status OK Down ok Straighten Replace Tunnuk to Sapuk 18,874 11,936 88 6 41 Peniesene along Wichen river 0 1,963 0 0 8 Municipal to Epinup 11,713 14,263 118 6 20 Nepukos Backroad 0 6,648 0 0 44 Behind Governor office 0 1,070 4 6 F1 Pou Bay CSHS to Mechitiw 550 4,272 11 6 8 F2 Pou Bay CSHS to Tunnuk 1,882 5,010 19 10 7 Nantaku Hill to WTP 0 1,070 6 0 0 Kurassa to Telecome Mast 0 2,857 0 0 10 Total Unrestored 33,019 49,089 246 28 144 Pole Status
  • 8. TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 6 June 2015 Issued 8 June 2015 Page 8 of 11 Annex 1 – Feeder Restoration & Solar System Condition Summaries Target Actual Feeder 1 Power Plant to Hospital 30 March 2015 30 March 2015 Hospital to Nantaku WTP 03 April 2015 11 April 2015 Feeder 2 Power Plant to Governors Office 31 March 2015 31 March 2015 Governors office to CSHS 01 April 2015 31 March 2015 CSHS to Mechitiw backroad (Pou Bay West) 18 April 2015 18 April 2015 CHSH to Tunnuk backrooad (Pou Bay East) 06 May 2015 06 May 2015 CSHS to Pink Apt Tank 05 May 2015 05 May 2015 Feeder 3 Power Plant to Downtown gas Station 31 March 2015 31 March 2015 Downtown Gas Station to Municipal Office 03 April 2015 03 April 2015 Municipal Office to Mizpah 07 April 2015 06 April 2015 Nepukos Backroad - Yamaha to Nepukos jnctn 04 April 2015 04 April 2015 Nepukos Jnctn to Mizpah 07 July 2015 Partial - TH-09; and 83-07 15 April Mizpah to dump site road jnctn 07 April 2015 06 April 2015 Dump site road jnctn to Blue Lagoon - back road 07 April 2015 07 April 2015 Dump site road jnctn to Blue Lagoon corner - main road 02 May 2015 01 May 2015 Blue Lagoon corner to Quarry 20 June 2015 20 June 2015 Quarry to Wichap 20 June 2015 20 June 2015 Wichap to Epinup 28 June 2015 Feeder 4 Power plant to Airport 30 March 2015 30 March 2015 Airport to WWTP 30 March 2015 30 March 2015 Airport to Kurassa 01 April 2015 31 March 2015 Kurassa to telecom Tower 03 April 2015 02 May 2015 Kurassa to Mechitiw corner 03 April 2015 01 April 2015 Mechitiw corner to Tunnuk (Pou Bay Causeway) 06 April 2015 01 April 2015 Tunnuk to Penia 15 April 2015 15 April 2015 Penia to Peniesene 27 April 2015 24 April 2015 Peniesene spur 02 May 2015 19 April 105 Partial to Well ADB-10 Peniesene to Xavier Jnctn 02 May 2015 24 April 2015 Xavier Jnctn to Sapuk 23 May 2015 22 May 2105 Xavier jnctn to Xavier HS 30 May 2015 30 May 2015 Xavier sea side to Sapuk 02 June 2015 04 June 2015 Patched line/extension from KSORC Side; SOLAR PV SYSTEMS Grid Connected: Weno - Chuuk State High School - 200 kWp 8% panel damage - system repair schedule for early July 2015 Weno - Chuuk International Airport - 65 kWp System fully restored - 2 April 2015 Stand Alone (schools and Dispensaries): Moch - Mortlocks Region Operational Satowan - Mortlocks Region Operational Lechinioch - Mortlocks Region Operational Oneop - Mortlocks Region Inoperational - Equipment failure pre-typhoon Onoun - Northwest Operational Fanapanges - Faichuk Region Operational Central Wonip - Faichuk Region Operational Munian - Faichuk Region Operational Udot -- Faichuk Region Operational Uman - Southern Namoneas Operational Fefan (Sapore and West Fefan) - Southern Namoneas Operational Restore Date Feeder Section Comments
  • 9. TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 6 June 2015 Issued 8 June 2015 Page 9 of 11 ANNEX 2 – Customer Meter Restoration Progress SINGLE PHASE METER RESTORATION PROGRESS - 19 June 2015 Weno Villages With Primary Power Restored Village Connections Restored Balance Restore % IRAS 283 262 21 92.6% MECHITIW 259 232 27 89.6% MWAN 203 175 28 86.2% NANTAKU 13 13 0 100.0% NEAUO 107 95 12 88.8% NEPUKOS 498 466 32 93.6% PENIA 32 31 1 96.9% PENIESENE 67 54 13 80.6% SAPUK 101 73 28 72.3% TUNNUK 102 90 12 88.2% WICHAP 58 0 58 0.0% Total 1,723 1,491 232 86.5% Weno Villages Without Primary Power Restored Village Connections Restored Balance Restore % EPINUP 15 0 15 0.0% Total 15 0 15 0.0% System Total 1,738 1,491 247 85.8% Three phase meter restoration is now fully complete
  • 10. TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 6 June 2015 Issued 8 June 2015 Page 10 of 11 ANNEX 3 – Restoration Summary Graphs The graphs below show restoration progress towards achieving 100% system restoration 0 20,000 40,000 60,000 80,000 100,000 120,000 29-Mar 31-Mar 02-Apr 04-Apr 06-Apr 08-Apr 10-Apr 12-Apr 14-Apr 16-Apr 18-Apr 20-Apr 22-Apr 24-Apr 26-Apr 28-Apr 30-Apr 02-May 04-… 06-… 08-… 10-May 12-May 14-May 16-May 18-May 20-May 22-May 24-May 26-May 28-May 30-May 01-Jun 03-Jun 05-Jun 07-Jun 09-Jun 11-Jun 13-Jun 15-Jun 17-Jun 19-Jun PrimaryLineLengthRestoredInFeet CPUC - Primary Line Restoration Progress Total Primary Line Length Primary Line Restored 0 200 400 600 800 1000 1200 1400 1600 1800 2000 30-Mar 01-Apr 03-Apr 05-Apr 07-Apr 09-Apr 11-Apr 13-Apr 15-Apr 17-Apr 19-Apr 21-Apr 23-Apr 25-Apr 27-Apr 29-Apr 01-May 03-May 05-May 07-May 09-May 11-May 13-May 15-May 17-May 19-May 21-May 23-May 25-May 27-May 29-May 31-May 02-Jun 04-Jun 06-Jun 08-Jun 10-Jun 12-Jun 14-Jun 16-Jun 18-Jun No.ofConnectionsRestored CPUC - Single Phase Power Connection Restoration Progress Total Connections Restored Connections
  • 11. TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 6 June 2015 Issued 8 June 2015 Page 11 of 11