CPUC - Typhoon Maysak - Restoration Report To 20 June 2015
1. Page 1 of 11
TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report – To Saturday 20 June 2015
Issued 21 June 2015
2. TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 20 June 2015
Issued 21 June 2015
Page 2 of 11
TABLE OF CONTENTS
1 ACTIONS & OPERATIONS – 7th
June to 20th
June 2015................................................................3
1.1 Power Restoration..............................................................................................................3
1.2 Water Restoration...............................................................................................................3
1.3 Sewer System......................................................................................................................3
1.4 Procurement .......................................................................................................................3
1.5 Operations Financing ..........................................................................................................3
2 PROGRESS ..................................................................................................................................3
3 MISCELLANEOUS........................................................................................................................4
3.1 Restoration Progress: .........................................................................................................4
3.2 Liaison with other agencies.................................................................................................5
3.2.1 IOM..............................................................................................................................5
3.2.2 Pohnpei Utility Corporation.........................................................................................5
3.2.3 National Government..................................................................................................5
3.3 Weather Advisory From National Weather Service Tiyan Guam .........................................5
3.4 Work Program.....................................................................................................................5
Annex 1 – Feeder Restoration & Solar System Condition Summaries ................................8
ANNEX 2 – Customer Meter Restoration Progress .............................................................9
ANNEX 3 – Restoration Summary Graphs ......................................................................... 10
3. TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 20 June 2015
Issued 21 June 2015
Page 3 of 11
1 ACTIONS & OPERATIONS – 7th
June to 20th
June 2015
1.1 Power Restoration
Primary line recovery efforts in the period have been directed in Wichap and Epinup over the period.
A further 3,250 feet (2.9% of total line length) of line has been reconstructed and energized during
the period. Total line operational to date is 98,700 feet or 89.4% of total line length.
Pole construction from Wichap repeater to the end of Epinup was completed on the 19th June and
restringing of the Epinup single phase line will be completed by the end of w/c 22 June.
Support to tree trimming at the Governor’s office was also provided during the period – this work
will be completed by 29th
June.
The peak load remains around 2.1 MW or 95% of peak prior to the typhoon with night-time load
around 1.3 MW. CPUC generation load profile from 30th
March to 31st
May is shown in Annex 3.
At 20th
June all three phase customers and 85.8% (1,491 number) of single phase customers have
been reconnected. Details are shown in Annex 2.
1.2 Water Restoration
Well restoration is complete across Weno.
1.3 Sewer System
Daily pumping operations continued on all lift stations;
1.4 Procurement
Essential materials have now started to arrive in Weno from the first purchase orders placed. CPUC is
still awaiting confirmation of USAID funding balance from IOM/USAID – further procurement is on
hold until that point.
1.5 Operations Financing
Operations continues to be financed from revenues – a detailed update on CPUC financial position
will be included in the June monthly report.
2 PROGRESS
Progress to date versus initial target is indicated in the Annexes 1 to 3 below.
Restoration progress summary charts are shown in Annex 2 & 3.
4. TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 20 June 2015
Issued 21 June 2015
Page 4 of 11
3 MISCELLANEOUS
3.1 Restoration Progress:
Summary of progress made in restoration is tabled below:
Feet
As % of
Network
Feet
As % of
Network
Feet
As % of
Network
Feet
As % of
Network
Total System Length: 110,305 110,305 110,305 110,305
Total Restored - 3 Phase 83,706 75.9% 86,192 78.1% 95,411 86.5% 98,666 89.4%
Total Ok but Off 6,675 6.1% 6,053 5.5% 3,248 2.9% 0 0.0%
Total Damaged 19,924 18.1% 18,060 16.4% 11,646 10.6% 11,639 10.6%
Restored Lengths
PP to WTP 3,565 3,565 3,565 3,565
COM to LS8A 933 933 933 933
PP to Tunnuk 13,285 13,285 13,285 13,285
Aiprort to WWTP 1,037 1,037 1,037 1,037
PP to Municipal 6,005 6,005 6,005 6,005
Back Road past Shigeto 1,882 1,882 1,882 1,882
V6K ot L5 1,490 1,490 1,490 1,490
Old Mormon corner to well 20 681 681 681 681
Municipal to Dump site corner 5,999 5,999 5,999 5,999
Dummp site to SDA 6,080 6,080 6,080 6,080
Blue Lagoon Spur 266 266 266 266
Blue Lagoon junct to LS 19 1,243 1,243 1,243 1,243
Tunnuk to LS 7 464 464 464 464
Tunnuk towards Pou Bay 723 723 723 723
Tunnuk to Peniesene - Single phase only 5,400 5,400 5,400 5,400
Upper Nantaku 1,075 1,075 1,075 1,075
F3 Weno Port Spur 550 550 550 550
LS8 to Well 15 460 460 460 460
Nepukos Jnct to 83-07 500 500 500 500
Nepukos Jnct to TH-09 320 320 320 320
mechitiw to ADB 4 1500 1500 1500 1500
Wichen Spur to ADB 10 1000 1000 1000 1000
F4 J Robert to Wichen Spur 1000 1000 1000 1000
Peniesene to Xavier Junction Sapuk 7300 7300 7300 7300
Xavier Jnctn to Kansou Bakery 590 590 590 590
ADB4 to F1: 30 1492 1492 1492 1492
F3: LS18 to LS19 2977 2977 2977 2977
Kurassa to Tonachau Mast 2857 2857 2857 2857
LS8 to Tunnuk Back Road Switch 520 520 520 520
Back road to Pink Apartment Tank 1342 1342 1342 1342
Pou Bay to Tunnuk Back Road 4309 4309 4309 4309
Well 15 to Hill to Mechitiw road 825 825 825 825
Link to Education past Governor office 725 725 725 725
Sapuk Kansou Bakery past KORDI 4811 4811 4811 4811
Nantaku Behind Governor's office 500 500 500 500
Xavier Jnctn to Xavier School 2486 2486 2486
N Sapuk Extension 580 580
Xavier Back Jnct to B Killion (east) 2588 2588
Sapuk Seaside West spur 3842 3842
Nepukos Back road left side 2209 2209
Blue Lagoon Corner to Wichap Repeater 3255
Total Restored 83,706 86,192 95,411 98,666
30-May23-May 06-Jun 19-Jun
5. TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 20 June 2015
Issued 21 June 2015
Page 5 of 11
To date full supply has been restored to 89.4% of the network – the three phase line from Blue
Lagoon corner in Neauo to Wichap Repeater has been rebuilt..
3.2 Liaison with other agencies
3.2.1 IOM
IOM will be acting as the contact agency for CPUC procurement of emergency materials under the
USAID funding program. The disbursement methodology is still being worked out between USAID
and OIM
3.2.2 Pohnpei Utility Corporation
PUC are supporting CPUC with 2 no. 4 man crews. A request has been made to retain one crew for
the first two weeks in July by which time it is anticipated that full system coverage will have been
restored.
3.2.3 National Government
CPUC CFO is liaising with FSM National Finance to disburse funds for the ongoing procurement.
Purchase contracts have been forwarded along with an anticipated disbursement plan.
3.3 Weather Advisory From National Weather Service Tiyan Guam
The latest weather advisory updates from NOAA can be obtained from the link below:
http://www.prh.noaa.gov/guam/MicroHazards.php
There is currently no tropical storm activity in the region.
A six day weather summary for Weno can be found at the link below:
http://www.tide-forecast.com/locations/Moen-Island-Chuuk-
FederatedStatesofMicronesia/forecasts/latest/six_dayp
3.4 Work Program
A work program from 22nd
June to 11th
July is under preparation and will be issued on 22nd
June. This
will be posted on CPUC website: http://www.cpuc.fm/typhoon-maysak-recovery/work-programs/
Note – CPUC Sewer and Water Systems are fully restored to pre-typhoon conditions. Relevant maps
of these systems have now been deleted from the report.
6. TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 20 June 2015
Issued 21 June 2015
Page 6 of 11
Primary Cable Status as of 5:00 pm 20 June 2o15
Yellow – Primary 3 Phase restored – 89.4% of system
length;
Green Primary in place but off;
Red – Primary down;
Pink - Line rebuildingongoing in Epinup;
CPUCService crewsare workingre-establish supply in
primaryrestoredareas– significant damageto serviceshas
occurred;
CPUC Power System Recovery Progress – 5:00 pm 20 June 2015
7. TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 6 June 2015
Issued 8 June 2015
Page 7 of 11
Initial Damage Assessment – (minor revision from 4th
April)
Feet As %
Total System Length 110,305
Total Restored 28,197 25.6%
Total Ok but Off 33,019 29.9%
Total Damaged 49,089 44.5%
Restored Lengths
PP to WTP 3,565
COM to LS8A 933
PP to Tunnuk 13,285
Aiprort to WWTP 1,037
PP to Municipal 6,005
Back Road past Shigeto 1,882
V6K ot L5 1,490
Total Restored 28,197
Unrestored Areas Primary Line Status
OK Down ok Straighten Replace
Tunnuk to Sapuk 18,874 11,936 88 6 41
Peniesene along Wichen river 0 1,963 0 0 8
Municipal to Epinup 11,713 14,263 118 6 20
Nepukos Backroad 0 6,648 0 0 44
Behind Governor office 0 1,070 4 6
F1 Pou Bay CSHS to Mechitiw 550 4,272 11 6 8
F2 Pou Bay CSHS to Tunnuk 1,882 5,010 19 10 7
Nantaku Hill to WTP 0 1,070 6 0 0
Kurassa to Telecome Mast 0 2,857 0 0 10
Total Unrestored 33,019 49,089 246 28 144
Pole Status
8. TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 6 June 2015
Issued 8 June 2015
Page 8 of 11
Annex 1 – Feeder Restoration & Solar System Condition Summaries
Target Actual
Feeder 1
Power Plant to Hospital 30 March 2015 30 March 2015
Hospital to Nantaku WTP 03 April 2015 11 April 2015
Feeder 2
Power Plant to Governors Office 31 March 2015 31 March 2015
Governors office to CSHS 01 April 2015 31 March 2015
CSHS to Mechitiw backroad (Pou Bay West) 18 April 2015 18 April 2015
CHSH to Tunnuk backrooad (Pou Bay East) 06 May 2015 06 May 2015
CSHS to Pink Apt Tank 05 May 2015 05 May 2015
Feeder 3
Power Plant to Downtown gas Station 31 March 2015 31 March 2015
Downtown Gas Station to Municipal Office 03 April 2015 03 April 2015
Municipal Office to Mizpah 07 April 2015 06 April 2015
Nepukos Backroad - Yamaha to Nepukos jnctn 04 April 2015 04 April 2015
Nepukos Jnctn to Mizpah 07 July 2015 Partial - TH-09; and 83-07 15 April
Mizpah to dump site road jnctn 07 April 2015 06 April 2015
Dump site road jnctn to Blue Lagoon - back road 07 April 2015 07 April 2015
Dump site road jnctn to Blue Lagoon corner - main road 02 May 2015 01 May 2015
Blue Lagoon corner to Quarry 20 June 2015 20 June 2015
Quarry to Wichap 20 June 2015 20 June 2015
Wichap to Epinup 28 June 2015
Feeder 4
Power plant to Airport 30 March 2015 30 March 2015
Airport to WWTP 30 March 2015 30 March 2015
Airport to Kurassa 01 April 2015 31 March 2015
Kurassa to telecom Tower 03 April 2015 02 May 2015
Kurassa to Mechitiw corner 03 April 2015 01 April 2015
Mechitiw corner to Tunnuk (Pou Bay Causeway) 06 April 2015 01 April 2015
Tunnuk to Penia 15 April 2015 15 April 2015
Penia to Peniesene 27 April 2015 24 April 2015
Peniesene spur 02 May 2015 19 April 105 Partial to Well ADB-10
Peniesene to Xavier Jnctn 02 May 2015 24 April 2015
Xavier Jnctn to Sapuk 23 May 2015 22 May 2105
Xavier jnctn to Xavier HS 30 May 2015 30 May 2015
Xavier sea side to Sapuk 02 June 2015 04 June 2015 Patched line/extension from KSORC Side;
SOLAR PV SYSTEMS
Grid Connected:
Weno - Chuuk State High School - 200 kWp 8% panel damage - system repair schedule for early July 2015
Weno - Chuuk International Airport - 65 kWp System fully restored - 2 April 2015
Stand Alone (schools and Dispensaries):
Moch - Mortlocks Region Operational
Satowan - Mortlocks Region Operational
Lechinioch - Mortlocks Region Operational
Oneop - Mortlocks Region Inoperational - Equipment failure pre-typhoon
Onoun - Northwest Operational
Fanapanges - Faichuk Region Operational
Central Wonip - Faichuk Region Operational
Munian - Faichuk Region Operational
Udot -- Faichuk Region Operational
Uman - Southern Namoneas Operational
Fefan (Sapore and West Fefan) - Southern Namoneas Operational
Restore Date
Feeder Section Comments
9. TYPHOON MAYSAK - 29 MARCH 2015
Restoration Report to Saturday 6 June 2015
Issued 8 June 2015
Page 9 of 11
ANNEX 2 – Customer Meter Restoration Progress
SINGLE PHASE METER RESTORATION PROGRESS - 19 June 2015
Weno Villages With Primary Power Restored
Village Connections Restored Balance Restore %
IRAS 283 262 21 92.6%
MECHITIW 259 232 27 89.6%
MWAN 203 175 28 86.2%
NANTAKU 13 13 0 100.0%
NEAUO 107 95 12 88.8%
NEPUKOS 498 466 32 93.6%
PENIA 32 31 1 96.9%
PENIESENE 67 54 13 80.6%
SAPUK 101 73 28 72.3%
TUNNUK 102 90 12 88.2%
WICHAP 58 0 58 0.0%
Total 1,723 1,491 232 86.5%
Weno Villages Without Primary Power Restored
Village Connections Restored Balance Restore %
EPINUP 15 0 15 0.0%
Total 15 0 15 0.0%
System Total 1,738 1,491 247 85.8%
Three phase meter restoration is now fully complete