Process Planning and Control
by: Charles Justin Davies
ISE 677
Professor: Dr. Thom Hodgson
North Carolina State University
2Davies
Tables of Contents
Abstract……………………………………………………………………………3
Introduction………………………………………………………………………..4
Phase 1……………………………………………………………………………4
Phase 2…………………………………………………………………………..11
Phase 3…………………………………………………………………………..14
The Next Step….Where the Research Goes Now………………………….19
Conclusion……………………………………………………………………….20
3Davies
Abstract
In any manufacturing environment, production planning and control is essential in order for
companies to remain competitive. There is a strong emphasis on this factor of operations in
manufacturing. Such an emphasis is needed in the General Electric Energy Division Product
Definition Engineering Department. Visual flow network techniques were utilized to test a
sample of data which revealed measurable results. These results suggested repeated instances of
rework loops, work stalls due to scope change, and errors from standard practices. An
opportunity for improvement was highlighted based upon these findings. The researcher
understood that improvements are based upon a medium of measurement which sets a baseline
of current state. Efforts were engaged to develop the current state for numerous activities within
the PDE organization. Simple averages were employed for this reflection. The data was first
extracted from Activity Management Tools generated by individual drafters who performed the
work. The results of the data did not fit intuition of the respective management and employees
involved. Thus, the AMT was decommissioned as a tool to capture the current state. Data
analysis was applied to a database that houses durations of activities based upon the time sheet
recording database. The data of drafting activities for any given duration from this approach was
considerably skewed. Measures of central tendency and spread were applied. These results
proved insufficient for activity planning. All of the data researched possessed skewed
distributions with considerable spreads. Due to this spread, graphical representations of the data
suggested variations that would make accurate planning impossible. A normalization method
was applied to capture a measurement mechanism based upon confidence intervals. Such a
method proved valuable in acquiring a baseline for measurement and a gage for planning and
loading of drafting work.
4Davies
Introduction
Today’s business environment requires that companies become more competitive by
reducing costs. This concept has traditionally been applied to the manufacturing environment
where cycle times, lead times, WIP status etc. define the financial measuring stick of the
organization. Nonetheless, there is extreme value in applying these approaches to the other
industries.
There has been a need to quantitatively measure the operational health of the Product
Definition Engineering Division of the General Electric Energy Division. Although there is no
production per say on a manufacturing line, this organization provides design services for the gas
turbine energy division. Currently, the department has little visibility to the loading within the
various groups along with any metrics from which to be measured such as productivity. As a
contractor for GE, QuEST Global Services approached this need as an opportunity to partner
with GE to make them more productive and efficient.
The purpose of this paper is to methodically demonstrate the problem solving approach
that was implemented to meet the end goal – defined metrics for drafting activities. This paper
will also demonstrate methods used to convince management that the approaches developed
were optimal based on the current research performed and the resources available. It is important
to understand that 90% of the problem solving is communicating to upper management and all
employees involved. The method of communication and the approach of the communication are
key factors.
Phase 1
Determining the current state of the drafting system was the first step in defining
appropriate direction. As a starting point, communication with the drafters was carried out in
depth to understand the day-to-day issues that were experienced. There were a lot of comments,
attitudes, opinions etc. It was realized early on that in order to effectively solve the process
issues much attitude and personality must be filtered. Common states of the drafting process
were classified and defined according to the following along with their respective definitions:
1. Original Assignment Work (Orig.Assign.Wk) – This state occurs only at the beginning of
the project when the drafter first receives his/her inputs and direction from the engineer.
5Davies
2. Mishap Rework (Mis.Rwk) – This is defined as rework performed by the drafter based
upon mistakes that the drafter made while performing their assigned task; this is a
definite highlight for improvement from the drafting side of the business.
3. Preference Rework (Pr.Rwk) – This is defined as rework performed by the drafter based
upon personal preference of the drawing checker and/or the engineer; this rework has
nothing to do with the communication of the drawing and its integrity.
4. Scope Change Work (Sc.Ch.Wk) – This is defined as work performed by the drafter on
their respective drawing or model based upon the engineer changing the scope as
originally defined in the work instructions.
5. Checking (CK) – This is the state at which QuEST customer GE performs checking on
the drafting/modeling of the work and either approves or send back for corrections,
preference rework, mishap rework, scope change work etc.
6. Finish (Finish) – This is the final state of the drafting process in which the respective
drafting/modeling is completed and approved by all responsible parties.
To start the analysis, a sample size of jobs was studied through their lifecycle based upon the
state in which they resided on a time scale factor. A network flow diagram was generated to
visualize the current state.
The letters located on the
paths traveling from state
to state indicate route at
which a job coded by that
letter traveled. Although
this tool is not very useful
for measurement and
analysis, it does visualize
the waste in the system.
The ST1 and ST2 located on the right side and above the blue lines indicate stages. Thus every
time a job crosses this blue line, it indicates a waste. Intuitively speaking, the less stages a job
travels, the less wastes involved and more than likely the less cycle time. This particular
network was used to generate a graph that depicts the number of state X to state Y that jobs take
to reach completion. The state moves include the following: Original Assignment Work to
Network Flow Diagram
Figure 1
*Note
6Davies
Check; Original Assignment Work to Scope Change Work; Scope Change Work to Scope
Change Work; Check to Scope Change Work; and Check to Preference Rework. A total of 35
state moves were observed in this study. The following percentage distributions according to the
figure 2 were realized:
 Orig.Assign.Wk to Ck – 20%
 Orig.Assign.Wk to Sc.Ch.Wk. –
20%
 Sc.Ch.Wk to Sc.Ch.Wk – 8.6%
 CK to Sc.Ch.Wk – 20%
 CK to Pr.Rwk – 31.4%
These results suggest
considerable waste in the
system. It is noted that the
intended path of every job in
the perfect scenario follows the sequence Orig.Assign.Wk – CK – Finish. Only 20% of the
moves in the Orig.Assign.Wk to CK category fit this model.
The measurement approach was presented to the GE management after the study
resulting in positive feedback. One of the drawbacks of the approach was the exact definition of
preference rework vs. drafter mishap rework. This definition is relative based upon the
viewpoint from the engineer directing the work or the drafter performing the work. Preference
rework to a drafter may be defined as mishap rework to the engineer. It is important to note here
that in order to quantitatively measure a process, subjectivity and interpretation must be
minimized. In response, the approach adopted was to combine the preference and mishap
rework into a general rework category.
After taking the feedback from the first test, the approach was to determine a graphical
way to link the output of a diagram to measurable ratios and percentages. In essence, this
approach took the same data in the same time series with the same results but displayed them for
clarity of representation.
Figure 2
*Note
7Davies
Contrary to the previous approach, this display lays out the stages horizontally instead of
vertically. Also the colored cells indicated a one in the respective cell with conditional
formatting. The formatting indicates the type of moves made. The coloring convention is
created as such: red is a stagnant move, orange is a slowed move, and green is a dynamic or
rather a finish move. Such convention indicates levels of queuing. Another change from the
previous method is the representation of the moves. In this improved method the following
coding applies:
 Checking Move (C) – All of these moves will be indicated in red since there is always
waiting time involved in the checking queue. In metric form this will be defined by an
Idle Queue (IQ) measurement.
 Finish Move (F) – This move indicates the completion of a job and will always be shown
in green.
 Scope Change (SC) – This move can be an idle or a dynamic move. Those moves
consisting of scope change indicated in orange suggest that the drafter working on that
particular job is in the process of being worked. Those moves consisting of scope change
indicated in red suggest that the drafter working on that job is working on another job due
to priority. Thus this job is in the state of scope change in idle queue.
Figure 3
Binary Network Flow Diagram
*Note
8Davies
 Rework Move (RW) – This move can also be an idle or a dynamic move just like scope
change, thus it can be represented in orange or red respectively.
The gray columns under C and RW indicate potential improvement opportunities from the
drafter perspective. Operational soundness can be generally indicated by a minimized number of
moves in these regions. It must be understood that jobs could move in this region from factors
outside control of drafting. Case by case investigation would determine such since preferential
and mishap factors are no longer displayed as in the original approach method.
On the lower left hand corner of Figure 3 above, a metrics table is compiled of critical to
quality (CTQ) metrics for the particular instant in time that the study was performed. A brief
description of each of these metrics is listed as follows below. Note that there are a few metrics
that were explained as moves previously. This explanation involves ratios related to the moves:
 Idle Queue Move Ratio (IQ) – This metric relates the number of idle moves made to this
point in time to the total move made. On the graph, all idle moves are indicated in red.
Mathematically it is (idle moves/total moves). In the example above the IQ = 78%.
 Rework Move Ratio (RW) – This metric relates the number of rework moves to the total
moves made. Mathematically this metric is derived from the operation (rework
moves/idle moves). In the example above the RW = 14%.
 Scope Change Ratio (SC) – This metric is resultant of relating the number of scope
change moves to the total moves. Mathematically this metric is derived from the
operation (scope change moves/total moves). In the example above the SC = 35%.
 Finish to Check Ratio (FCR) – This metric is the ratio of the number of finish moves
compared to the number of checking moves. Mathematically this metric is derived from
the operation (finish moves/checking moves). In the example above the FCR = 4%.
 First Pass Yield (FPY) – This metric is the ratio of the number of jobs that went to
checking the first time and moved to finish the same time. In the example above the FPY
= 0%.
The data results provided in this test suggest serious operational problems. The goal for IQ, RW,
and SC is 0% and that of FCR and FPY is 100%. The study went further to gather these metrics
for a series of three weeks and plotted the progression to validate any trends and capture the
average performance level.
9Davies
Figure 4c
Figure 4bFigure 4b
Figure 4a
*Note
*Note
*Note
10Davies
At this point in the analysis, it is important to understand the management side of
depicting these figures. Upon presenting this data to management, there was increased concern
that none of the analysis focused on cycle times in conducting drafting activities. Original
response and discussion of such lead to the realization that cycle times in this business is
increasingly varied due to the stochastic nature of the process. However, management thought it
most beneficial that the analysis focus on cycle times. The analysis presented to this point
provided a good understanding of the waste involved in the process.
Figure 4e
Figure 4d
*Note
*Note
11Davies
Phase 2
Prior to performing the data analysis, the GE PDE group was using a process log to
record cycle times of activities. Due to the complexity of the tool, not much research was
conducted on the integrity of data that the tool generated. The tool consisted of multiple
automation features compiled on an excel spreadsheet. Usage of the tool appeared to give too
much subjectivity to interpretation due to a lack of constraint on the human aspect of its usage.
However, management insisted that the research would analyze the data generated from this tool
in search of the current state of performance. It must be pointed out that the search for the
optimal solution is a journey and sometime not an easy one. The researcher tried to convince
management that the data generated from this tool would not yield true direction since human
behavior of fudging the data input was not adequately constrained. However, the approach was
to go through the rigger of analyzing the data and let the results speak for itself.
The data from the process logs was compiled manually by selecting a random sample of
388 logs and generating a table of data with times associated with categories such as drafter work
time, scope change time, checking time etc. This data was then analyzed using Minitab as seen
in the below graphs:
Figure 5aFigure 5a Figure 5b*Note *Note
12Davies
These graphs reference data on a sub
group within the PDE organization. The
group name as seen displayed as
“Variable: Fra&CasCheck” is the
Frames and Casings Group. This group
was picked since its available data set
was larger than the other groups for the
purposes of the study. The graphs do not
follow a normal distribution given that
the P-values are less than .05. This
factor suggests that using simple
averages as performance estimates were
not sufficient for estimation purposes
since the distribution cannot be characterized as normal. In response, there was extensive study
performing Mood’s Median and Homogeneity of Variance Test to analyze factors relating to the
medians. These analyses still showed incredible spread that would make grouping insufficient.
This factor would make it difficult to tracks trends in the data in the absence of a large data set.
The study was also broken down to group MLIs within the Frames and Casings group to
determine if there is any normality at
a more granular level as seen in
Figure 6. The evidence in the P-
Value showed no change from the
previous level of granularity.
However, the study was furthered to
determine the validity of the data.
Management perception of
this data and its validity added to the
challenges of weeding through the
analysis to obtain the current state. Prior to this analysis, management viewed the process logs
as an accurate assessment of the performance of the system. One of the challenges was changing
that perception. The history of the process logs gave indications of human error. There were
Figure 5c
Figure 6
Frames and Casings Drafter Work Time
(0805,0706,0705 from Sample Group)
*Note
*Note
13Davies
daily reports provided to management of the status of every drafter’s job based on their
respective process logs. In the fields of the process logs, drafters indicated their best estimate of
respective durations. Once a step such as “checking” with an estimated duration was crossed in
time, the real duration was not being captured. In essence, this tool was designed to be a
planning and a data capture tool all at once. Understanding the dynamics of this gave the
researcher the indication that human behavior is to stay out of the spot light, thus there is a
tendency to “fudge” the number to stay off a report. The researcher brought this factor to
management as a potential disclaimer of the data residing in the process logs. Management was
not receptive of this idea as a possible reason for error in the data. The first response of
management was that the real problem was with drafter behavior. The researcher attempted to
steer management away from this perception. While behavior is a factor, it must not be coerced
in process design, it must be constrained. As industrial engineers it is essential to understand
human behavior as it relates to system performance and data representation. The approach taken
from this was to continue the analysis on the process log data and let simple intuition of
relationships be compared to the data.
Some simple regression analysis was performed to determine if intuitive relationships
between variables was realized. The first relationship tested was the drafter work time imputed
in the log versus the applied hours in the database connected to the drafter time record system.
Intuition would suggest that as the drafter work time increases so does the total hours applied.
Figure 7a shows this relationship. The plot shows that there is no relationship between the two
variables under study as evidenced by the R-Sq = 7.8%. This fact suggests that there is potential
Figure 7a Figure 7b *Note*Note
14Davies
for human error in the data input on the logs and/or likewise on the drafter time record in the
database. Such evidence indicated to the research effort that using the process log data would be
inaccurate for activity duration measurement and planning. However, the research team
continued the analysis to verify the errors in the process log data. Figure 7b portrays the
relationship between time for engineering input to scope change time. Again intuitively, change
in scope is a direct correlation of the time it take for engineering to revise inputs. However, the
data portrayed shows R-Sq = 23.7%. Again, the results portray that the data within the process
logs were insufficient.
Phase 3
Given the results from the process logs, the research had to change direction of which the
search was to determine an accurate estimate of the current state of the system for selected
activities within the PDE organization. At this point in the analysis, research was conducted on
the database that houses all the activities on the schedule and captures the charges in hours to
those respective activities or in GE language manufacturing line item (MLI). Data was extracted
from this database for selected MLIs over a four year period (February 1, 2007 – February 1,
2011). The two variables analyzed in the study were duration in days and actual hours charged.
These two variables would help determine on-time delivery and productivity. Each MLI studied
has a respective drafting item and an engineering item respectively. Drafting items are
designated by numbers while engineering items are designated with their same connected
drafting item with an “E” tagged to the end. It is important to note that the values stream for any
complete drafting job starts with an engineering item and ends with a drafting item. In dumping
this data, both the engineering and drafting item was captured simultaneously. This data was
then sorted accordingly to fit the engineering in front of the drafting item in order to capture the
exact duration of the drafting item. The results as known previously still showed immense
spread in the data as seen in Figure 8 for MLI# 0961. This returns the research to the fact that
the data is so spread that simple averages would do little for measurement purposes – it would
make trend analysis very difficult.
15Davies
Based on the findings discovered to this point in the
analysis, it became clear that a single number to represent
the current state was insufficient however a starting point
was needed. Based on review with management consensus
was to start with an 80% application. This method sorts all
of the durations and/or actual hours of a particular MLI in
ascending order. As an example refer to Figure 8 to the
right. The hrs_actual column has the respective times for
MLI 0961 listed in ascending order. As noted in the figure,
there are 16 data points for this MLI. Eighty percent of 16 is
12.8 or rounded up to 13 since .8 is greater than or equal to
.5. Counting down in ascending order, the 13th
data point
falls on 36 hours. Thus the assumption with the approach
from an operational point of view is that there is 80% confidence that MLI 0961 will be
completed in less than or equal to 36 hours. This particular method provides for more accurate
planning. The very nature of the PDE organization is that erroneous finish times are set by
management with no understanding of historical data surrounding certain activities. Thus there
is no adequate level of confidence in the planning function. The confidence in this metric was
validated when the 80% numbers for select MLI’s was compared to the original scheduling
model of durations within GE’s database for those MLI’s. The research was encouraged to know
that the 80% rule matched the system loading most of the time.
An addition to the 80% rule was needed to help normalize the data for measurement
purposes. Research was conducted as to how to achieve this in keeping with estimation accuracy
due to the spread of the data points. The researcher discovered an existing estimation method of
which is used highly in the construction industry – PERT (program evaluation and review
technique) (Omar, July 2009). Within this technique, estimated time (TE) can be calculated by
the following formula:
TE = (w + 4m + b) / 6 where w = worst estimate, m = mode or the most likely estimate, and b =
best estimate.
Figure 8
MLI 0961 Analysis
*Note
16Davies
Note that the application of the worst and best estimate applied was based on the 95%
confidence. In the example of the data given in Figure 8 the WA (weighted average) or TE (time
estimate) of the hrs_actual for MLI 0961 is as follows:
TE = (63+4(2) +0) / 6 TE = 11.8 ~ 12 hour.
At this point in the modeling
development of MLIs for drafting
time estimates, the study has
generated two numbers that help to
depict the current state of the
system. In the example of MLI
0961, the 80% confidence number
= 36 hours and the WA = 12
hours. The normalization is
achieved by using these two data
points and relating them to the
actual occurrences. Refer to the
graphical representation of this relationship in Figure 9. This graph provides examples of
random data points representing MLI 0961 jobs that occur in time T1, T2, T3…..Tx. At these
different times other MLIs are being worked at which the combined productivities of MLIs at
any Tx are averaged to produce a productivity number. Data Point B occurring at T2 was
completed in 10hrs yet the Weighted Average number is 12. Thus the productivity of 120% is
realized by dividing 12 from 10. The Data Point C occurring at T3 is 90% since 36/40=90%.
The method developed was tested on a drafter for one week to measure results and
determine accuracy of approach. Data was downloaded for this drafter on their current load for
the week beginning August 22. It is important to not at this juncture in the analysis that the
employee studied was generally classified as a top tier drafter in terms of efficiency of work
performed. The factor of skills matched to performance measured is a more thorough factor
beyond the scope of the current study. Also, it was determined to continue the analysis with a
focus on hours applied instead of duration for simplicity. Refer to Figures 10a and 10b for the
loading projected and the measurement of the performance at the end of the test week:
Figure 9 *Note
17Davies
According the 80% Max metric Employee C is loaded 17.3 hours/day for MLI 0909. This
loading is indicated by orange suggesting a risk in this item closing on its current due date of
August 25. The orange shading also projects the loading out to a suggested revised LFD based
upon loading of 8 hrs/day. This indicates that the date should be moved to September 1. At the
end of the test, this MLI was finally
completed on September 1. Such a
reality provided potential evidence
that the approach was valid. Also at
the end of the test week, the
performance of the WIP and
completed jobs under drafter C was
measured. The results are shown in
Figure 11. Note in this figure that
there are several activities – 1602 and
1623 – that are duplicated. These are
instances in which the same activity is
performed on similar gas turbine
units. In these cases, the approach was to test a heuristic by combining the actual hours of both
Figure 10b
Figure 11
Figure 10a
Employee C Loading Projection
*Note
*Note
*Note
18Davies
activities into one and increasing the metric for the activity by 20%. This was chosen since a
duplication of activities for similar machines usually involves a “Save As” operation, thus
requiring less time for the second similar activity. It must be understood that this is a random
heuristic test to start as a baseline. Given this assumption the measured productivity for
Employee C for the test week averaged to 91%. At the macro level, this seems fair and
reasonable. However, importance was placed on the items that exceeded the 80% metrics values
such as MLIs 096101 and 1602. This highlights opportunities for improvement. The test and
subsequent results were presented to management for feedback and discussion. Positive reaction
was prevalent however; management proposed that the approach be applied to a team of drafters
within the PDE organization and compare
one team such as CTQ to another sub team.
Such a test required substantial data mining
and analysis along with rigorous excel
functions. However, this test would give
management a better understanding and view
of individual team performance as well as
loading. A test was implemented on the
research group for a week to ascertain the
response of the approach to the perceived loading and performance. This method was also
applied to a second group simultaneously to understand competing group and how they
measured accordingly. The two groups were teams CTQ and GEIQ respectfully. Team CTQ
was the control group and team GEIQ was the comparison group. At the end of the test week the
results were realized according to Figure 12. An important comparison in these graphs is the
earned hours per head. It was agreed that the 80% metric be the earned hours applied to a given
Figure 12
Weekly Comparison of Team’s
Performance
*Note
19Davies
job once completed. CTQ being the research group possessed earned hours/head = 11.4 while
GEIQ was earned hours/head = 25 respectively. Another indicative measurement was cost
performance index (CPI) where CTQ’s was 44% while GEIQ’s was 92%. These metrics suggest
that the overall performance of GEIQ is better that CTQ. It is important to note that these are the
results of performance of the closed activities for the week under study. Management was very
receptive to this approach as it had been the first time that a more granular measurement has
been applied to stochastically driven processes in the PDE organization. The top manager was
so impressed with the approach that he asked for the research to be expanded and applied his
whole team of over 300 drafters so as to report to senior executive level management.
It was determined by the researcher that a more realistic view of one team’s performance
versus another was to be obtained by a running average for a series of weeks. This was obtained
as evidenced in Figure 13. These results show that more normalization was needed in the
measurement method. For instance, the average
productivity for CTQ is so high due to one activity that
was completed in 1 hour while the WA was 7. This
fact skews the layout of the results. However, a base
method of approach was reached upon which
modifications will be applied. Based upon the theme of
this study, the intent of the research was achieved – to
mathematically model a quantitative method to
measure the operational health of the PDE
organization.
The Next Step….Where the Research Goes Now?
Despite the fact that the basic intent of the research was achieved, there are much needed
modifications and facets that were identified to more accurately mathematically model the
system. This section will focus on the approaches needed to make the study achieve an optimal
approach to planning and measuring PDE processes.
A better method of planning was identified while performing the test on Employee C. By
performing simple algorithms in the data, confidence intervals could be created. Say for instance
there is the following naming convention:
Figure 13
*Note
20Davies
Drafter Name – Drafter X
Job Name – X1,X2…..
Due Date – DX1(for X1), DX2(for X2)……
There is an array of jobs loaded on Drafter X. If this array of X1 and X2 are running in parallel,
there would also be DX1 and DX2 respectfully. If for instance that DX1 is before DX2, then
allow 8 hours per day up to DX1. Then begin from the DX1+1 the same method for X2. Thus if
for example there were 2 days for DX1 and 5 days for DX2, then the hours applied for job X1
would be 16 hours and for job X2 24 hrs respectfully. The 5 is subtracted from the 2 since the
drafter is working on job X1 before job X2. The 16hrs and 24hrs for the respective job’s MLIs
are added to the hours already applied to their respective jobs. This new number of total
estimated hours falls within a percentile range once compared to the array study from the MLIs
once arranged in ascending order. Much like the 80% confidence, this would generate a level of
confidence that the job would be completed by the current due date. Theoretically, this method
would assist in level loading the work load for planning purposes.
Another opportunity was identified for optimal application
of the methods developed in the research. Refer to Figure 14 as
used prior on page 15 of this research. Note in this figure that five
of the data points 2 – 7 took 2hrs to complete. Management
suggested that the history of these data points should be researched
to determine factors that caused this MLI to take 2hrs instead of the
other hours in the array. Furthermore, there could be another layer
of normalization applied to the hours that fall within a heuristic set
number of sigma’s range to determine common denominators
among job groups. If this in-depth research were conducted, the planning function in the study
would generate more granular output of loading among drafters.
Conclusion
The findings from this research have yielded considerable gains in understanding the
drafting process at the GE Gas Turbines Product Definition Engineering Division. The research
Figure 14
MLI 0961 Analysis
*Note
21Davies
was subdivided into a series of phases representing methodical stages in a heuristic approach to
find the optimal solution. Each phase within the search was the result of an elimination of the
previous phase. The intent of the research was met – to create a mathematical model of the
drafting process that is accepted by management for planning and measurement purposes. Even
though there are improvements to the approach needed, it is understood that there will always be
a search for the “optimal”.
The results of this study are fairly significant. Recall from the first section, that the study
was performed by an employee for QuEST – a contractor for GE. By the end of the third phase
of this research, GE management noted that the method produced from this study was more
accurate than the method used and developed by GE employees. The end intent of this is to
highlight the waste so QuEST can mathematically prove to GE the savings that can be yielded
once improvements are made to the process. As an industrial engineer, the researcher
understands that the value of this work is in the money that can be saved based upon the methods
generated from the analysis. Now that GE has agreed to an approach of measurement, the
researcher feels certain that there is over a 1 million/year that can be saved from using this
method as a planning and measurement tool. The top GE PDE manager, Craig Humanchuk,
made the following statement regarding the results from this study: “It was an analysis that has
never been done in the past and will be a game changer for how GE PDE will run its business in
the future. It will give us a better way to monitor when our process gets off track.”
22Davies
References and Notes
Omar, Anwar (July 1, 2009) Uncertainty in Project Scheduling – Its Use in PERT/CPM
Conventional Techniques, Cost Engineering Vol. 51/No. 7 July 2009, retrieved from:
http://ehis.ebscohost.com.prox.lib.ncsu.edu/ehost/pdfviewer/pdfviewer?sid=7a85b964-
558c-49be-bf24-7f2dc8593788%40sessionmgr113&vid=2&hid=120
*Note: Data and Graphical representations were generated with approval from related companies
using related company’s software packages such as Minitab, PowerPoint, and Excel for the
completion of this project.

More Related Content

What's hot

Six Sigma : Process Capability
Six Sigma : Process CapabilitySix Sigma : Process Capability
Six Sigma : Process CapabilityLalit Padekar
 
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...IJERA Editor
 
Process capability
Process capabilityProcess capability
Process capabilitypadam nagar
 
IRJET- Optimization of Plastic Injection Molding
IRJET- Optimization of Plastic Injection MoldingIRJET- Optimization of Plastic Injection Molding
IRJET- Optimization of Plastic Injection MoldingIRJET Journal
 
Us gsa (1992) value engineering program guide for design and construction -...
Us gsa (1992)   value engineering program guide for design and construction -...Us gsa (1992)   value engineering program guide for design and construction -...
Us gsa (1992) value engineering program guide for design and construction -...Wan Yusoff Wan Mahmood
 
Six sigma part1: Process capability
Six sigma part1: Process capabilitySix sigma part1: Process capability
Six sigma part1: Process capabilityNavneet Dwivedi
 
Estimation of process capability 1st yr mpharmacy
Estimation of process capability 1st yr mpharmacyEstimation of process capability 1st yr mpharmacy
Estimation of process capability 1st yr mpharmacypriyankapatil7896
 
6. process capability analysis (variable data)
6. process capability analysis (variable data)6. process capability analysis (variable data)
6. process capability analysis (variable data)Hakeem-Ur- Rehman
 
Process capability analysis
Process capability analysisProcess capability analysis
Process capability analysisSurya Teja
 
IRJET- Review on Scheduling using Dependency Structure Matrix
IRJET-  	  Review on Scheduling using Dependency Structure MatrixIRJET-  	  Review on Scheduling using Dependency Structure Matrix
IRJET- Review on Scheduling using Dependency Structure MatrixIRJET Journal
 
SPC - Statistical process control
SPC  - Statistical process controlSPC  - Statistical process control
SPC - Statistical process controlSenthil kumar
 
Cpk guide 0211_tech1
Cpk guide 0211_tech1Cpk guide 0211_tech1
Cpk guide 0211_tech1Piyush Bose
 
A new technique for evaluating the balanced scorecard
A new technique for evaluating the balanced scorecardA new technique for evaluating the balanced scorecard
A new technique for evaluating the balanced scorecardPhuong Dx
 
Analyze phase lean six sigma tollgate template
Analyze phase   lean six sigma tollgate templateAnalyze phase   lean six sigma tollgate template
Analyze phase lean six sigma tollgate templateSteven Bonacorsi
 

What's hot (20)

Six Sigma : Process Capability
Six Sigma : Process CapabilitySix Sigma : Process Capability
Six Sigma : Process Capability
 
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
 
Process capability
Process capabilityProcess capability
Process capability
 
IRJET- Optimization of Plastic Injection Molding
IRJET- Optimization of Plastic Injection MoldingIRJET- Optimization of Plastic Injection Molding
IRJET- Optimization of Plastic Injection Molding
 
Us gsa (1992) value engineering program guide for design and construction -...
Us gsa (1992)   value engineering program guide for design and construction -...Us gsa (1992)   value engineering program guide for design and construction -...
Us gsa (1992) value engineering program guide for design and construction -...
 
Six sigma part1: Process capability
Six sigma part1: Process capabilitySix sigma part1: Process capability
Six sigma part1: Process capability
 
Estimation of process capability 1st yr mpharmacy
Estimation of process capability 1st yr mpharmacyEstimation of process capability 1st yr mpharmacy
Estimation of process capability 1st yr mpharmacy
 
PROCESS CAPABILITY
PROCESS CAPABILITYPROCESS CAPABILITY
PROCESS CAPABILITY
 
6. process capability analysis (variable data)
6. process capability analysis (variable data)6. process capability analysis (variable data)
6. process capability analysis (variable data)
 
PROCESS CAPABILITY
PROCESS CAPABILITYPROCESS CAPABILITY
PROCESS CAPABILITY
 
Process capability analysis
Process capability analysisProcess capability analysis
Process capability analysis
 
IRJET- Review on Scheduling using Dependency Structure Matrix
IRJET-  	  Review on Scheduling using Dependency Structure MatrixIRJET-  	  Review on Scheduling using Dependency Structure Matrix
IRJET- Review on Scheduling using Dependency Structure Matrix
 
Six sigma
Six sigmaSix sigma
Six sigma
 
SPC - Statistical process control
SPC  - Statistical process controlSPC  - Statistical process control
SPC - Statistical process control
 
IJIRS_Improvement of Quality Sigma Level of Copper Terminal at Vertical Machi...
IJIRS_Improvement of Quality Sigma Level of Copper Terminal at Vertical Machi...IJIRS_Improvement of Quality Sigma Level of Copper Terminal at Vertical Machi...
IJIRS_Improvement of Quality Sigma Level of Copper Terminal at Vertical Machi...
 
Presentation1
Presentation1Presentation1
Presentation1
 
Cpk guide 0211_tech1
Cpk guide 0211_tech1Cpk guide 0211_tech1
Cpk guide 0211_tech1
 
A new technique for evaluating the balanced scorecard
A new technique for evaluating the balanced scorecardA new technique for evaluating the balanced scorecard
A new technique for evaluating the balanced scorecard
 
BA371deliv3
BA371deliv3BA371deliv3
BA371deliv3
 
Analyze phase lean six sigma tollgate template
Analyze phase   lean six sigma tollgate templateAnalyze phase   lean six sigma tollgate template
Analyze phase lean six sigma tollgate template
 

Viewers also liked

Task 10 research article
Task 10 research articleTask 10 research article
Task 10 research articlebeckybbb
 
Gerencia de proyectos
Gerencia de proyectosGerencia de proyectos
Gerencia de proyectosamordios123
 
Silencers dampeners stabilizers report
Silencers dampeners stabilizers reportSilencers dampeners stabilizers report
Silencers dampeners stabilizers reportMayur Pangrekar
 
Научная Ёлка Wow!How? в РАН. Кросс-промо.
Научная Ёлка Wow!How? в РАН. Кросс-промо.Научная Ёлка Wow!How? в РАН. Кросс-промо.
Научная Ёлка Wow!How? в РАН. Кросс-промо.Evgeny Bezverkhiy
 
Gotas de-bencao1/2
Gotas de-bencao1/2Gotas de-bencao1/2
Gotas de-bencao1/2danilo sant
 
Questionnaire 13 oct
Questionnaire 13 octQuestionnaire 13 oct
Questionnaire 13 octbeccaweight16
 
Zineyzie de la zine
Zineyzie de la zineZineyzie de la zine
Zineyzie de la zinebeckybbb
 
Finalfifdndiasnfiandfsianfs
FinalfifdndiasnfiandfsianfsFinalfifdndiasnfiandfsianfs
Finalfifdndiasnfiandfsianfsbeckybbb
 
Q cover analysisisisi
Q cover analysisisisiQ cover analysisisisi
Q cover analysisisisibeckybbb
 
ζώα του αγροκτήματος!!!
ζώα του αγροκτήματος!!!ζώα του αγροκτήματος!!!
ζώα του αγροκτήματος!!!marianna angelopoulou
 

Viewers also liked (15)

παιχνίδι κανόνες
παιχνίδι κανόνεςπαιχνίδι κανόνες
παιχνίδι κανόνες
 
Task 10 research article
Task 10 research articleTask 10 research article
Task 10 research article
 
Bhartiyam ppt
Bhartiyam pptBhartiyam ppt
Bhartiyam ppt
 
Gerencia de proyectos
Gerencia de proyectosGerencia de proyectos
Gerencia de proyectos
 
Silencers dampeners stabilizers report
Silencers dampeners stabilizers reportSilencers dampeners stabilizers report
Silencers dampeners stabilizers report
 
Task 10
Task 10Task 10
Task 10
 
Научная Ёлка Wow!How? в РАН. Кросс-промо.
Научная Ёлка Wow!How? в РАН. Кросс-промо.Научная Ёлка Wow!How? в РАН. Кросс-промо.
Научная Ёлка Wow!How? в РАН. Кросс-промо.
 
Gotas de-bencao1/2
Gotas de-bencao1/2Gotas de-bencao1/2
Gotas de-bencao1/2
 
Questionnaire 13 oct
Questionnaire 13 octQuestionnaire 13 oct
Questionnaire 13 oct
 
Zineyzie de la zine
Zineyzie de la zineZineyzie de la zine
Zineyzie de la zine
 
Thermal Wire and Cable 2015
Thermal Wire and Cable 2015Thermal Wire and Cable 2015
Thermal Wire and Cable 2015
 
Finalfifdndiasnfiandfsianfs
FinalfifdndiasnfiandfsianfsFinalfifdndiasnfiandfsianfs
Finalfifdndiasnfiandfsianfs
 
Fullfillment warehouse
Fullfillment warehouseFullfillment warehouse
Fullfillment warehouse
 
Q cover analysisisisi
Q cover analysisisisiQ cover analysisisisi
Q cover analysisisisi
 
ζώα του αγροκτήματος!!!
ζώα του αγροκτήματος!!!ζώα του αγροκτήματος!!!
ζώα του αγροκτήματος!!!
 

Similar to Data Evaluation and Modeling for Product Definition Engineering - ISE 677

2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.pptAlfredoArturoGranado
 
Methodology Patterns (Agile Cambridge 2014)
Methodology Patterns (Agile Cambridge 2014)Methodology Patterns (Agile Cambridge 2014)
Methodology Patterns (Agile Cambridge 2014)Giovanni Asproni
 
Budgeting in SCRUM by Divante
Budgeting in SCRUM by DivanteBudgeting in SCRUM by Divante
Budgeting in SCRUM by DivanteDivante
 
Six Sigma BB Project Update
Six Sigma BB Project UpdateSix Sigma BB Project Update
Six Sigma BB Project Updatecybermetheus
 
Pm0015 quantitative methods in project management
Pm0015   quantitative methods in project managementPm0015   quantitative methods in project management
Pm0015 quantitative methods in project managementsmumbahelp
 
Glenn Vanderburg — Real software engineering
Glenn Vanderburg — Real software engineeringGlenn Vanderburg — Real software engineering
Glenn Vanderburg — Real software engineeringatr2006
 
Final Report - Optimizing Work Distribution for NP Orders
Final Report - Optimizing Work Distribution for NP OrdersFinal Report - Optimizing Work Distribution for NP Orders
Final Report - Optimizing Work Distribution for NP OrdersBrian Kaiser, PE
 
Improving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dunganImproving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dunganignitetribes
 
Real software engineering
Real software engineeringReal software engineering
Real software engineeringatr2006
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615EqraBaig
 
Innovation framework
Innovation frameworkInnovation framework
Innovation frameworkJames Basker
 
project-closure-software-engineering.ppt
project-closure-software-engineering.pptproject-closure-software-engineering.ppt
project-closure-software-engineering.pptJigneshKadia
 
Increasing the probability of program success
Increasing the probability of program successIncreasing the probability of program success
Increasing the probability of program successGlen Alleman
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingHariasha
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Acumen
 

Similar to Data Evaluation and Modeling for Product Definition Engineering - ISE 677 (20)

2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt
 
CSC-1986.original
CSC-1986.originalCSC-1986.original
CSC-1986.original
 
Methodology Patterns (Agile Cambridge 2014)
Methodology Patterns (Agile Cambridge 2014)Methodology Patterns (Agile Cambridge 2014)
Methodology Patterns (Agile Cambridge 2014)
 
Budgeting in SCRUM by Divante
Budgeting in SCRUM by DivanteBudgeting in SCRUM by Divante
Budgeting in SCRUM by Divante
 
Six Sigma BB Project Update
Six Sigma BB Project UpdateSix Sigma BB Project Update
Six Sigma BB Project Update
 
Pm0015 quantitative methods in project management
Pm0015   quantitative methods in project managementPm0015   quantitative methods in project management
Pm0015 quantitative methods in project management
 
Glenn Vanderburg — Real software engineering
Glenn Vanderburg — Real software engineeringGlenn Vanderburg — Real software engineering
Glenn Vanderburg — Real software engineering
 
Final Report - Optimizing Work Distribution for NP Orders
Final Report - Optimizing Work Distribution for NP OrdersFinal Report - Optimizing Work Distribution for NP Orders
Final Report - Optimizing Work Distribution for NP Orders
 
Improving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dunganImproving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dungan
 
Real software engineering
Real software engineeringReal software engineering
Real software engineering
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615
 
Innovation framework
Innovation frameworkInnovation framework
Innovation framework
 
project-closure-software-engineering.ppt
project-closure-software-engineering.pptproject-closure-software-engineering.ppt
project-closure-software-engineering.ppt
 
Increasing the probability of program success
Increasing the probability of program successIncreasing the probability of program success
Increasing the probability of program success
 
Slides chapters 24-25
Slides chapters 24-25Slides chapters 24-25
Slides chapters 24-25
 
PROCESS IMPOVEMENT PLAN
PROCESS IMPOVEMENT PLAN                                           PROCESS IMPOVEMENT PLAN
PROCESS IMPOVEMENT PLAN
 
Use of network scheduling technique
Use of network scheduling technique Use of network scheduling technique
Use of network scheduling technique
 
SE chapters 24-25
SE chapters 24-25SE chapters 24-25
SE chapters 24-25
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursing
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 

Data Evaluation and Modeling for Product Definition Engineering - ISE 677

  • 1. 1Davies Data Analysis and Modeling for PDE Process Planning and Control by: Charles Justin Davies ISE 677 Professor: Dr. Thom Hodgson North Carolina State University
  • 2. 2Davies Tables of Contents Abstract……………………………………………………………………………3 Introduction………………………………………………………………………..4 Phase 1……………………………………………………………………………4 Phase 2…………………………………………………………………………..11 Phase 3…………………………………………………………………………..14 The Next Step….Where the Research Goes Now………………………….19 Conclusion……………………………………………………………………….20
  • 3. 3Davies Abstract In any manufacturing environment, production planning and control is essential in order for companies to remain competitive. There is a strong emphasis on this factor of operations in manufacturing. Such an emphasis is needed in the General Electric Energy Division Product Definition Engineering Department. Visual flow network techniques were utilized to test a sample of data which revealed measurable results. These results suggested repeated instances of rework loops, work stalls due to scope change, and errors from standard practices. An opportunity for improvement was highlighted based upon these findings. The researcher understood that improvements are based upon a medium of measurement which sets a baseline of current state. Efforts were engaged to develop the current state for numerous activities within the PDE organization. Simple averages were employed for this reflection. The data was first extracted from Activity Management Tools generated by individual drafters who performed the work. The results of the data did not fit intuition of the respective management and employees involved. Thus, the AMT was decommissioned as a tool to capture the current state. Data analysis was applied to a database that houses durations of activities based upon the time sheet recording database. The data of drafting activities for any given duration from this approach was considerably skewed. Measures of central tendency and spread were applied. These results proved insufficient for activity planning. All of the data researched possessed skewed distributions with considerable spreads. Due to this spread, graphical representations of the data suggested variations that would make accurate planning impossible. A normalization method was applied to capture a measurement mechanism based upon confidence intervals. Such a method proved valuable in acquiring a baseline for measurement and a gage for planning and loading of drafting work.
  • 4. 4Davies Introduction Today’s business environment requires that companies become more competitive by reducing costs. This concept has traditionally been applied to the manufacturing environment where cycle times, lead times, WIP status etc. define the financial measuring stick of the organization. Nonetheless, there is extreme value in applying these approaches to the other industries. There has been a need to quantitatively measure the operational health of the Product Definition Engineering Division of the General Electric Energy Division. Although there is no production per say on a manufacturing line, this organization provides design services for the gas turbine energy division. Currently, the department has little visibility to the loading within the various groups along with any metrics from which to be measured such as productivity. As a contractor for GE, QuEST Global Services approached this need as an opportunity to partner with GE to make them more productive and efficient. The purpose of this paper is to methodically demonstrate the problem solving approach that was implemented to meet the end goal – defined metrics for drafting activities. This paper will also demonstrate methods used to convince management that the approaches developed were optimal based on the current research performed and the resources available. It is important to understand that 90% of the problem solving is communicating to upper management and all employees involved. The method of communication and the approach of the communication are key factors. Phase 1 Determining the current state of the drafting system was the first step in defining appropriate direction. As a starting point, communication with the drafters was carried out in depth to understand the day-to-day issues that were experienced. There were a lot of comments, attitudes, opinions etc. It was realized early on that in order to effectively solve the process issues much attitude and personality must be filtered. Common states of the drafting process were classified and defined according to the following along with their respective definitions: 1. Original Assignment Work (Orig.Assign.Wk) – This state occurs only at the beginning of the project when the drafter first receives his/her inputs and direction from the engineer.
  • 5. 5Davies 2. Mishap Rework (Mis.Rwk) – This is defined as rework performed by the drafter based upon mistakes that the drafter made while performing their assigned task; this is a definite highlight for improvement from the drafting side of the business. 3. Preference Rework (Pr.Rwk) – This is defined as rework performed by the drafter based upon personal preference of the drawing checker and/or the engineer; this rework has nothing to do with the communication of the drawing and its integrity. 4. Scope Change Work (Sc.Ch.Wk) – This is defined as work performed by the drafter on their respective drawing or model based upon the engineer changing the scope as originally defined in the work instructions. 5. Checking (CK) – This is the state at which QuEST customer GE performs checking on the drafting/modeling of the work and either approves or send back for corrections, preference rework, mishap rework, scope change work etc. 6. Finish (Finish) – This is the final state of the drafting process in which the respective drafting/modeling is completed and approved by all responsible parties. To start the analysis, a sample size of jobs was studied through their lifecycle based upon the state in which they resided on a time scale factor. A network flow diagram was generated to visualize the current state. The letters located on the paths traveling from state to state indicate route at which a job coded by that letter traveled. Although this tool is not very useful for measurement and analysis, it does visualize the waste in the system. The ST1 and ST2 located on the right side and above the blue lines indicate stages. Thus every time a job crosses this blue line, it indicates a waste. Intuitively speaking, the less stages a job travels, the less wastes involved and more than likely the less cycle time. This particular network was used to generate a graph that depicts the number of state X to state Y that jobs take to reach completion. The state moves include the following: Original Assignment Work to Network Flow Diagram Figure 1 *Note
  • 6. 6Davies Check; Original Assignment Work to Scope Change Work; Scope Change Work to Scope Change Work; Check to Scope Change Work; and Check to Preference Rework. A total of 35 state moves were observed in this study. The following percentage distributions according to the figure 2 were realized:  Orig.Assign.Wk to Ck – 20%  Orig.Assign.Wk to Sc.Ch.Wk. – 20%  Sc.Ch.Wk to Sc.Ch.Wk – 8.6%  CK to Sc.Ch.Wk – 20%  CK to Pr.Rwk – 31.4% These results suggest considerable waste in the system. It is noted that the intended path of every job in the perfect scenario follows the sequence Orig.Assign.Wk – CK – Finish. Only 20% of the moves in the Orig.Assign.Wk to CK category fit this model. The measurement approach was presented to the GE management after the study resulting in positive feedback. One of the drawbacks of the approach was the exact definition of preference rework vs. drafter mishap rework. This definition is relative based upon the viewpoint from the engineer directing the work or the drafter performing the work. Preference rework to a drafter may be defined as mishap rework to the engineer. It is important to note here that in order to quantitatively measure a process, subjectivity and interpretation must be minimized. In response, the approach adopted was to combine the preference and mishap rework into a general rework category. After taking the feedback from the first test, the approach was to determine a graphical way to link the output of a diagram to measurable ratios and percentages. In essence, this approach took the same data in the same time series with the same results but displayed them for clarity of representation. Figure 2 *Note
  • 7. 7Davies Contrary to the previous approach, this display lays out the stages horizontally instead of vertically. Also the colored cells indicated a one in the respective cell with conditional formatting. The formatting indicates the type of moves made. The coloring convention is created as such: red is a stagnant move, orange is a slowed move, and green is a dynamic or rather a finish move. Such convention indicates levels of queuing. Another change from the previous method is the representation of the moves. In this improved method the following coding applies:  Checking Move (C) – All of these moves will be indicated in red since there is always waiting time involved in the checking queue. In metric form this will be defined by an Idle Queue (IQ) measurement.  Finish Move (F) – This move indicates the completion of a job and will always be shown in green.  Scope Change (SC) – This move can be an idle or a dynamic move. Those moves consisting of scope change indicated in orange suggest that the drafter working on that particular job is in the process of being worked. Those moves consisting of scope change indicated in red suggest that the drafter working on that job is working on another job due to priority. Thus this job is in the state of scope change in idle queue. Figure 3 Binary Network Flow Diagram *Note
  • 8. 8Davies  Rework Move (RW) – This move can also be an idle or a dynamic move just like scope change, thus it can be represented in orange or red respectively. The gray columns under C and RW indicate potential improvement opportunities from the drafter perspective. Operational soundness can be generally indicated by a minimized number of moves in these regions. It must be understood that jobs could move in this region from factors outside control of drafting. Case by case investigation would determine such since preferential and mishap factors are no longer displayed as in the original approach method. On the lower left hand corner of Figure 3 above, a metrics table is compiled of critical to quality (CTQ) metrics for the particular instant in time that the study was performed. A brief description of each of these metrics is listed as follows below. Note that there are a few metrics that were explained as moves previously. This explanation involves ratios related to the moves:  Idle Queue Move Ratio (IQ) – This metric relates the number of idle moves made to this point in time to the total move made. On the graph, all idle moves are indicated in red. Mathematically it is (idle moves/total moves). In the example above the IQ = 78%.  Rework Move Ratio (RW) – This metric relates the number of rework moves to the total moves made. Mathematically this metric is derived from the operation (rework moves/idle moves). In the example above the RW = 14%.  Scope Change Ratio (SC) – This metric is resultant of relating the number of scope change moves to the total moves. Mathematically this metric is derived from the operation (scope change moves/total moves). In the example above the SC = 35%.  Finish to Check Ratio (FCR) – This metric is the ratio of the number of finish moves compared to the number of checking moves. Mathematically this metric is derived from the operation (finish moves/checking moves). In the example above the FCR = 4%.  First Pass Yield (FPY) – This metric is the ratio of the number of jobs that went to checking the first time and moved to finish the same time. In the example above the FPY = 0%. The data results provided in this test suggest serious operational problems. The goal for IQ, RW, and SC is 0% and that of FCR and FPY is 100%. The study went further to gather these metrics for a series of three weeks and plotted the progression to validate any trends and capture the average performance level.
  • 9. 9Davies Figure 4c Figure 4bFigure 4b Figure 4a *Note *Note *Note
  • 10. 10Davies At this point in the analysis, it is important to understand the management side of depicting these figures. Upon presenting this data to management, there was increased concern that none of the analysis focused on cycle times in conducting drafting activities. Original response and discussion of such lead to the realization that cycle times in this business is increasingly varied due to the stochastic nature of the process. However, management thought it most beneficial that the analysis focus on cycle times. The analysis presented to this point provided a good understanding of the waste involved in the process. Figure 4e Figure 4d *Note *Note
  • 11. 11Davies Phase 2 Prior to performing the data analysis, the GE PDE group was using a process log to record cycle times of activities. Due to the complexity of the tool, not much research was conducted on the integrity of data that the tool generated. The tool consisted of multiple automation features compiled on an excel spreadsheet. Usage of the tool appeared to give too much subjectivity to interpretation due to a lack of constraint on the human aspect of its usage. However, management insisted that the research would analyze the data generated from this tool in search of the current state of performance. It must be pointed out that the search for the optimal solution is a journey and sometime not an easy one. The researcher tried to convince management that the data generated from this tool would not yield true direction since human behavior of fudging the data input was not adequately constrained. However, the approach was to go through the rigger of analyzing the data and let the results speak for itself. The data from the process logs was compiled manually by selecting a random sample of 388 logs and generating a table of data with times associated with categories such as drafter work time, scope change time, checking time etc. This data was then analyzed using Minitab as seen in the below graphs: Figure 5aFigure 5a Figure 5b*Note *Note
  • 12. 12Davies These graphs reference data on a sub group within the PDE organization. The group name as seen displayed as “Variable: Fra&CasCheck” is the Frames and Casings Group. This group was picked since its available data set was larger than the other groups for the purposes of the study. The graphs do not follow a normal distribution given that the P-values are less than .05. This factor suggests that using simple averages as performance estimates were not sufficient for estimation purposes since the distribution cannot be characterized as normal. In response, there was extensive study performing Mood’s Median and Homogeneity of Variance Test to analyze factors relating to the medians. These analyses still showed incredible spread that would make grouping insufficient. This factor would make it difficult to tracks trends in the data in the absence of a large data set. The study was also broken down to group MLIs within the Frames and Casings group to determine if there is any normality at a more granular level as seen in Figure 6. The evidence in the P- Value showed no change from the previous level of granularity. However, the study was furthered to determine the validity of the data. Management perception of this data and its validity added to the challenges of weeding through the analysis to obtain the current state. Prior to this analysis, management viewed the process logs as an accurate assessment of the performance of the system. One of the challenges was changing that perception. The history of the process logs gave indications of human error. There were Figure 5c Figure 6 Frames and Casings Drafter Work Time (0805,0706,0705 from Sample Group) *Note *Note
  • 13. 13Davies daily reports provided to management of the status of every drafter’s job based on their respective process logs. In the fields of the process logs, drafters indicated their best estimate of respective durations. Once a step such as “checking” with an estimated duration was crossed in time, the real duration was not being captured. In essence, this tool was designed to be a planning and a data capture tool all at once. Understanding the dynamics of this gave the researcher the indication that human behavior is to stay out of the spot light, thus there is a tendency to “fudge” the number to stay off a report. The researcher brought this factor to management as a potential disclaimer of the data residing in the process logs. Management was not receptive of this idea as a possible reason for error in the data. The first response of management was that the real problem was with drafter behavior. The researcher attempted to steer management away from this perception. While behavior is a factor, it must not be coerced in process design, it must be constrained. As industrial engineers it is essential to understand human behavior as it relates to system performance and data representation. The approach taken from this was to continue the analysis on the process log data and let simple intuition of relationships be compared to the data. Some simple regression analysis was performed to determine if intuitive relationships between variables was realized. The first relationship tested was the drafter work time imputed in the log versus the applied hours in the database connected to the drafter time record system. Intuition would suggest that as the drafter work time increases so does the total hours applied. Figure 7a shows this relationship. The plot shows that there is no relationship between the two variables under study as evidenced by the R-Sq = 7.8%. This fact suggests that there is potential Figure 7a Figure 7b *Note*Note
  • 14. 14Davies for human error in the data input on the logs and/or likewise on the drafter time record in the database. Such evidence indicated to the research effort that using the process log data would be inaccurate for activity duration measurement and planning. However, the research team continued the analysis to verify the errors in the process log data. Figure 7b portrays the relationship between time for engineering input to scope change time. Again intuitively, change in scope is a direct correlation of the time it take for engineering to revise inputs. However, the data portrayed shows R-Sq = 23.7%. Again, the results portray that the data within the process logs were insufficient. Phase 3 Given the results from the process logs, the research had to change direction of which the search was to determine an accurate estimate of the current state of the system for selected activities within the PDE organization. At this point in the analysis, research was conducted on the database that houses all the activities on the schedule and captures the charges in hours to those respective activities or in GE language manufacturing line item (MLI). Data was extracted from this database for selected MLIs over a four year period (February 1, 2007 – February 1, 2011). The two variables analyzed in the study were duration in days and actual hours charged. These two variables would help determine on-time delivery and productivity. Each MLI studied has a respective drafting item and an engineering item respectively. Drafting items are designated by numbers while engineering items are designated with their same connected drafting item with an “E” tagged to the end. It is important to note that the values stream for any complete drafting job starts with an engineering item and ends with a drafting item. In dumping this data, both the engineering and drafting item was captured simultaneously. This data was then sorted accordingly to fit the engineering in front of the drafting item in order to capture the exact duration of the drafting item. The results as known previously still showed immense spread in the data as seen in Figure 8 for MLI# 0961. This returns the research to the fact that the data is so spread that simple averages would do little for measurement purposes – it would make trend analysis very difficult.
  • 15. 15Davies Based on the findings discovered to this point in the analysis, it became clear that a single number to represent the current state was insufficient however a starting point was needed. Based on review with management consensus was to start with an 80% application. This method sorts all of the durations and/or actual hours of a particular MLI in ascending order. As an example refer to Figure 8 to the right. The hrs_actual column has the respective times for MLI 0961 listed in ascending order. As noted in the figure, there are 16 data points for this MLI. Eighty percent of 16 is 12.8 or rounded up to 13 since .8 is greater than or equal to .5. Counting down in ascending order, the 13th data point falls on 36 hours. Thus the assumption with the approach from an operational point of view is that there is 80% confidence that MLI 0961 will be completed in less than or equal to 36 hours. This particular method provides for more accurate planning. The very nature of the PDE organization is that erroneous finish times are set by management with no understanding of historical data surrounding certain activities. Thus there is no adequate level of confidence in the planning function. The confidence in this metric was validated when the 80% numbers for select MLI’s was compared to the original scheduling model of durations within GE’s database for those MLI’s. The research was encouraged to know that the 80% rule matched the system loading most of the time. An addition to the 80% rule was needed to help normalize the data for measurement purposes. Research was conducted as to how to achieve this in keeping with estimation accuracy due to the spread of the data points. The researcher discovered an existing estimation method of which is used highly in the construction industry – PERT (program evaluation and review technique) (Omar, July 2009). Within this technique, estimated time (TE) can be calculated by the following formula: TE = (w + 4m + b) / 6 where w = worst estimate, m = mode or the most likely estimate, and b = best estimate. Figure 8 MLI 0961 Analysis *Note
  • 16. 16Davies Note that the application of the worst and best estimate applied was based on the 95% confidence. In the example of the data given in Figure 8 the WA (weighted average) or TE (time estimate) of the hrs_actual for MLI 0961 is as follows: TE = (63+4(2) +0) / 6 TE = 11.8 ~ 12 hour. At this point in the modeling development of MLIs for drafting time estimates, the study has generated two numbers that help to depict the current state of the system. In the example of MLI 0961, the 80% confidence number = 36 hours and the WA = 12 hours. The normalization is achieved by using these two data points and relating them to the actual occurrences. Refer to the graphical representation of this relationship in Figure 9. This graph provides examples of random data points representing MLI 0961 jobs that occur in time T1, T2, T3…..Tx. At these different times other MLIs are being worked at which the combined productivities of MLIs at any Tx are averaged to produce a productivity number. Data Point B occurring at T2 was completed in 10hrs yet the Weighted Average number is 12. Thus the productivity of 120% is realized by dividing 12 from 10. The Data Point C occurring at T3 is 90% since 36/40=90%. The method developed was tested on a drafter for one week to measure results and determine accuracy of approach. Data was downloaded for this drafter on their current load for the week beginning August 22. It is important to not at this juncture in the analysis that the employee studied was generally classified as a top tier drafter in terms of efficiency of work performed. The factor of skills matched to performance measured is a more thorough factor beyond the scope of the current study. Also, it was determined to continue the analysis with a focus on hours applied instead of duration for simplicity. Refer to Figures 10a and 10b for the loading projected and the measurement of the performance at the end of the test week: Figure 9 *Note
  • 17. 17Davies According the 80% Max metric Employee C is loaded 17.3 hours/day for MLI 0909. This loading is indicated by orange suggesting a risk in this item closing on its current due date of August 25. The orange shading also projects the loading out to a suggested revised LFD based upon loading of 8 hrs/day. This indicates that the date should be moved to September 1. At the end of the test, this MLI was finally completed on September 1. Such a reality provided potential evidence that the approach was valid. Also at the end of the test week, the performance of the WIP and completed jobs under drafter C was measured. The results are shown in Figure 11. Note in this figure that there are several activities – 1602 and 1623 – that are duplicated. These are instances in which the same activity is performed on similar gas turbine units. In these cases, the approach was to test a heuristic by combining the actual hours of both Figure 10b Figure 11 Figure 10a Employee C Loading Projection *Note *Note *Note
  • 18. 18Davies activities into one and increasing the metric for the activity by 20%. This was chosen since a duplication of activities for similar machines usually involves a “Save As” operation, thus requiring less time for the second similar activity. It must be understood that this is a random heuristic test to start as a baseline. Given this assumption the measured productivity for Employee C for the test week averaged to 91%. At the macro level, this seems fair and reasonable. However, importance was placed on the items that exceeded the 80% metrics values such as MLIs 096101 and 1602. This highlights opportunities for improvement. The test and subsequent results were presented to management for feedback and discussion. Positive reaction was prevalent however; management proposed that the approach be applied to a team of drafters within the PDE organization and compare one team such as CTQ to another sub team. Such a test required substantial data mining and analysis along with rigorous excel functions. However, this test would give management a better understanding and view of individual team performance as well as loading. A test was implemented on the research group for a week to ascertain the response of the approach to the perceived loading and performance. This method was also applied to a second group simultaneously to understand competing group and how they measured accordingly. The two groups were teams CTQ and GEIQ respectfully. Team CTQ was the control group and team GEIQ was the comparison group. At the end of the test week the results were realized according to Figure 12. An important comparison in these graphs is the earned hours per head. It was agreed that the 80% metric be the earned hours applied to a given Figure 12 Weekly Comparison of Team’s Performance *Note
  • 19. 19Davies job once completed. CTQ being the research group possessed earned hours/head = 11.4 while GEIQ was earned hours/head = 25 respectively. Another indicative measurement was cost performance index (CPI) where CTQ’s was 44% while GEIQ’s was 92%. These metrics suggest that the overall performance of GEIQ is better that CTQ. It is important to note that these are the results of performance of the closed activities for the week under study. Management was very receptive to this approach as it had been the first time that a more granular measurement has been applied to stochastically driven processes in the PDE organization. The top manager was so impressed with the approach that he asked for the research to be expanded and applied his whole team of over 300 drafters so as to report to senior executive level management. It was determined by the researcher that a more realistic view of one team’s performance versus another was to be obtained by a running average for a series of weeks. This was obtained as evidenced in Figure 13. These results show that more normalization was needed in the measurement method. For instance, the average productivity for CTQ is so high due to one activity that was completed in 1 hour while the WA was 7. This fact skews the layout of the results. However, a base method of approach was reached upon which modifications will be applied. Based upon the theme of this study, the intent of the research was achieved – to mathematically model a quantitative method to measure the operational health of the PDE organization. The Next Step….Where the Research Goes Now? Despite the fact that the basic intent of the research was achieved, there are much needed modifications and facets that were identified to more accurately mathematically model the system. This section will focus on the approaches needed to make the study achieve an optimal approach to planning and measuring PDE processes. A better method of planning was identified while performing the test on Employee C. By performing simple algorithms in the data, confidence intervals could be created. Say for instance there is the following naming convention: Figure 13 *Note
  • 20. 20Davies Drafter Name – Drafter X Job Name – X1,X2….. Due Date – DX1(for X1), DX2(for X2)…… There is an array of jobs loaded on Drafter X. If this array of X1 and X2 are running in parallel, there would also be DX1 and DX2 respectfully. If for instance that DX1 is before DX2, then allow 8 hours per day up to DX1. Then begin from the DX1+1 the same method for X2. Thus if for example there were 2 days for DX1 and 5 days for DX2, then the hours applied for job X1 would be 16 hours and for job X2 24 hrs respectfully. The 5 is subtracted from the 2 since the drafter is working on job X1 before job X2. The 16hrs and 24hrs for the respective job’s MLIs are added to the hours already applied to their respective jobs. This new number of total estimated hours falls within a percentile range once compared to the array study from the MLIs once arranged in ascending order. Much like the 80% confidence, this would generate a level of confidence that the job would be completed by the current due date. Theoretically, this method would assist in level loading the work load for planning purposes. Another opportunity was identified for optimal application of the methods developed in the research. Refer to Figure 14 as used prior on page 15 of this research. Note in this figure that five of the data points 2 – 7 took 2hrs to complete. Management suggested that the history of these data points should be researched to determine factors that caused this MLI to take 2hrs instead of the other hours in the array. Furthermore, there could be another layer of normalization applied to the hours that fall within a heuristic set number of sigma’s range to determine common denominators among job groups. If this in-depth research were conducted, the planning function in the study would generate more granular output of loading among drafters. Conclusion The findings from this research have yielded considerable gains in understanding the drafting process at the GE Gas Turbines Product Definition Engineering Division. The research Figure 14 MLI 0961 Analysis *Note
  • 21. 21Davies was subdivided into a series of phases representing methodical stages in a heuristic approach to find the optimal solution. Each phase within the search was the result of an elimination of the previous phase. The intent of the research was met – to create a mathematical model of the drafting process that is accepted by management for planning and measurement purposes. Even though there are improvements to the approach needed, it is understood that there will always be a search for the “optimal”. The results of this study are fairly significant. Recall from the first section, that the study was performed by an employee for QuEST – a contractor for GE. By the end of the third phase of this research, GE management noted that the method produced from this study was more accurate than the method used and developed by GE employees. The end intent of this is to highlight the waste so QuEST can mathematically prove to GE the savings that can be yielded once improvements are made to the process. As an industrial engineer, the researcher understands that the value of this work is in the money that can be saved based upon the methods generated from the analysis. Now that GE has agreed to an approach of measurement, the researcher feels certain that there is over a 1 million/year that can be saved from using this method as a planning and measurement tool. The top GE PDE manager, Craig Humanchuk, made the following statement regarding the results from this study: “It was an analysis that has never been done in the past and will be a game changer for how GE PDE will run its business in the future. It will give us a better way to monitor when our process gets off track.”
  • 22. 22Davies References and Notes Omar, Anwar (July 1, 2009) Uncertainty in Project Scheduling – Its Use in PERT/CPM Conventional Techniques, Cost Engineering Vol. 51/No. 7 July 2009, retrieved from: http://ehis.ebscohost.com.prox.lib.ncsu.edu/ehost/pdfviewer/pdfviewer?sid=7a85b964- 558c-49be-bf24-7f2dc8593788%40sessionmgr113&vid=2&hid=120 *Note: Data and Graphical representations were generated with approval from related companies using related company’s software packages such as Minitab, PowerPoint, and Excel for the completion of this project.