SlideShare a Scribd company logo
1 of 19
UNIVERSITY OF MINES AND TECHNOLOGY
FACULTY OF MINERAL RESOURCES TECHNOLOGY
MINING ENGINEERING DEPARTMENT
SEMINAR PRESENTATION
TOPIC
ASSESSMENT OF THE DEVELOPMENT AND
STOPING EFFICIENCIES OF A MINING BLOCK -
A CASE STUDY
BY: SUPERVISOR:
OBENG-SIKA JOSEPH MR. EMMANUEL M. BUABA
1
MODE OF PRESENTATION
PROBLEM DEFINITION
OBJECTIVES
METHODS USED
DATA ANALYSIS
CONCLUSIONS
RECOMMENDATIONS
2
STATEMENT OF PROBLEM
 Underground mine development involves the
excavation of series of openings to gain access to
the orebody for eventual stope production.
 For enhanced stope productivity, development
operations is co-ordinated with production stages.
 AGA Obuasi Mine has been a vibrant
underground mine and a major backbone of the
Ghanaian economy for several decades.
3
STATEMENT OF PROBLEM CONT’D
 The mine has experienced a decline in its
production tonnages for the past few years
primarily due to the fall in the rate of advance of
secondary development openings.
 This project seeks to assess the efficiencies of
the secondary development and stoping
operations of the Brown Sub Vertical Shaft
(BSVS) Mine of AGA.
4
OBJECTIVES
To determine the development efficiency
(Ed) of the block.
To determine the stoping efficiency (ES) of
the block.
To identify the relationship between the
development and stoping efficiencies of
the block.
5
METHODS USED
Literature review on the subject area
Field visits and interaction with personnel at
the stopes in Block 8 Lower of BSVS Mine.
Analysis of collected data
6
DATA ANALYSIS
Fig. 1 Development Cycle in Underground Mines 7
DATA ANALYSIS CONT’D
Fig. 2 Sublevel Stoping Cycle 8
DATA ANALYSIS CONT’D
0
50
100
150
200
250
300
Advancement(m)
FORECAST ACHIEVED AVERAGE ACHIEVED AVERAGE FORECAST
Fig. 3 Development Advance for 2013 9
DATA ANALYSIS CONT’D
0
5,000
10,000
15,000
20,000
25,000
ProductionTonnages(t)
FORECAST ACHIEVED AVERAGE FORECAST AVERAGE ACHIEVED
Fig. 4 Production Tonnages for 2013 10
DATA ANALYSIS CONT’D
𝐸 𝑑 =
𝐴𝑚𝑜𝑢𝑛𝑡 𝑜𝑓 𝑠𝑒𝑐𝑜𝑛𝑑𝑎𝑟𝑦 𝑑𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 𝑚3
1000 𝑡𝑜𝑛𝑛𝑒𝑠 𝑜𝑓 𝑜𝑟𝑒 𝑚𝑖𝑛𝑒𝑑
=
𝐿𝐷 ×42 +(𝑉𝐷 ×2.42)
1000 𝑡𝑜𝑛𝑛𝑒𝑠 𝑜𝑓 𝑜𝑟𝑒 𝑚𝑖𝑛𝑒𝑑
𝐸𝑆 =
𝑇𝑜𝑛𝑛𝑒𝑠 𝑜𝑓 𝑜𝑟𝑒 𝑚𝑖𝑛𝑒𝑑
𝑁𝑜. 𝑜𝑓 𝑒𝑚𝑝𝑙𝑜𝑦𝑒𝑒𝑠 ×𝑆ℎ𝑖𝑓𝑡𝑠 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑
11
DATA ANALYSIS CONT’D
MONTH
ACHIEVED DEVELOPMENT (m) ACHIEVED
TONNAGES (t)
DEVELOPMENT
EFFICIENCY
(m3
/t)LATERAL VERTICAL
January 141.6 33 18,812 130.54
February 175.4 40 15,737 192.98
March 178.8 40 14,974 206.44
April 203.7 40 18,715 186.47
May 181.7 40 16,315 192.31
June 214.1 40 15,333 238.44
July 214.6 20 12,182 291.32
August 225.3 19 16,451 225.78
September 223.0 34 15,251 246.80
October 239.1 33 16,097 249.47
November 265.5 15 13,472 321.73
December 213.0 49 17,778 207.57
Table 1 Monthly Development Efficiencies for 2013
12
DATA ANALYSIS CONT’D
MONTH No. of Days ACHIEVED Es (t/employee-
shift)
January 31 18,812 37.93
February 28 15,737 35.13
March 31 14,974 30.19
April 30 18,715 38.99
May 31 16,315 32.89
June 30 15,333 31.94
July 31 12,182 24.56
August 31 16,451 33.17
September 30 15,251 31.77
October 31 16,097 32.45
November 30 13,472 28.07
December 31 17,778 35.84
Table 2 Monthly Stoping Efficiencies for 2013
13
DATA ANALYSIS CONT’D
50
100
150
200
250
300
350
DevelopmentEfficiency(m³/t)
Development Efficiency
Average Development
Efficiency
Fig 5 Development Efficiency Trend for 2013 14
DATA ANALYSIS CONT’D
10
20
30
40
50
60
StopingEfficiency(t/employee-shift)
Stoping Efficiency Average Stoping Efficiency
Maximum Stoping Efficiency Minimum Stoping Efficiency
Fig. 6 Monthly Stoping Efficiencies Against Standardised Values
15
DATA ANALYSIS CONT’D
16
y = -10.387x + 564.35
R² = 0.6824
50
100
150
200
250
300
350
24 26 28 30 32 34 36 38 40
DevelopmentEfficiency(m³/t)
Stoping Efficiency (t/employee-shift)
Fig 7 Relationship Between Development and Stoping Efficiencies
CONCLUSION
 The average monthly Ed was 224.23 m3/t,
implying for every 10 m advance, a tonne of ore
is obtained.
 The ES ranged between 24.56 t/employee-shift
to 38.99 t/employee-shift.
 Ed is inversely proportional to ES.
17
RECOMMENDATIONS
Jumbos should be employed over the use
of jackhammers.
Development and stope preparations
should be done in advance as the current
stope is mined to allow for concurrent
stoping.
Standard ES and Ed values should be
generated against which field values are
assessed.
18
THANK YOU
19

More Related Content

What's hot

89176662 04-teknik-pemboran
89176662 04-teknik-pemboran89176662 04-teknik-pemboran
89176662 04-teknik-pemboranrramdan383
 
Underground mining system
Underground mining systemUnderground mining system
Underground mining systemSrimontorumpa
 
Perencanaan sistem penyaliran tambang
Perencanaan sistem penyaliran tambangPerencanaan sistem penyaliran tambang
Perencanaan sistem penyaliran tambangIpung Noor
 
Lectures on metal mining
Lectures on metal miningLectures on metal mining
Lectures on metal miningRanjeet Kumar
 
Underground Coal Mining Study
Underground Coal Mining StudyUnderground Coal Mining Study
Underground Coal Mining StudyOnur Tuncay
 
Investasi tambang
Investasi tambangInvestasi tambang
Investasi tambangSyarif .
 
Mine scheduling process
Mine scheduling processMine scheduling process
Mine scheduling processVR M
 
support system in metal mine
support system in metal minesupport system in metal mine
support system in metal minejyotiranavasiya
 
Metode penyaliran tambang
Metode penyaliran tambangMetode penyaliran tambang
Metode penyaliran tambangNoveriady
 
KAJIAN HUBUNGAN ANTARA KEKUATAN TANAH DENGAN DENSITAS PADA TANAH LATOSOL DAN ...
KAJIAN HUBUNGAN ANTARA KEKUATAN TANAH DENGAN DENSITAS PADA TANAH LATOSOL DAN ...KAJIAN HUBUNGAN ANTARA KEKUATAN TANAH DENGAN DENSITAS PADA TANAH LATOSOL DAN ...
KAJIAN HUBUNGAN ANTARA KEKUATAN TANAH DENGAN DENSITAS PADA TANAH LATOSOL DAN ...Repository Ipb
 
Mine air sampling
Mine air samplingMine air sampling
Mine air samplingOmKaitade
 
Pasir besi - bahan galian industri
Pasir besi - bahan galian industriPasir besi - bahan galian industri
Pasir besi - bahan galian industriBonita Susimah
 
Ekonomi Mineral by Yuli Kusumawati
Ekonomi Mineral by Yuli KusumawatiEkonomi Mineral by Yuli Kusumawati
Ekonomi Mineral by Yuli Kusumawatiyulika usman
 
Kope winder or friction winder ppt
Kope winder or friction winder pptKope winder or friction winder ppt
Kope winder or friction winder pptAMIT SAHU
 
Kuliah eksplorasi & genesa geologi batubara indonesia
Kuliah eksplorasi & genesa geologi batubara indonesiaKuliah eksplorasi & genesa geologi batubara indonesia
Kuliah eksplorasi & genesa geologi batubara indonesiaoilandgas24
 

What's hot (20)

Block caving method
Block caving methodBlock caving method
Block caving method
 
89176662 04-teknik-pemboran
89176662 04-teknik-pemboran89176662 04-teknik-pemboran
89176662 04-teknik-pemboran
 
Pillar design
Pillar designPillar design
Pillar design
 
Underground mining system
Underground mining systemUnderground mining system
Underground mining system
 
Design of openings
Design of openingsDesign of openings
Design of openings
 
Perencanaan sistem penyaliran tambang
Perencanaan sistem penyaliran tambangPerencanaan sistem penyaliran tambang
Perencanaan sistem penyaliran tambang
 
Lectures on metal mining
Lectures on metal miningLectures on metal mining
Lectures on metal mining
 
Underground Coal Mining Study
Underground Coal Mining StudyUnderground Coal Mining Study
Underground Coal Mining Study
 
Board & Pillar
Board & PillarBoard & Pillar
Board & Pillar
 
Investasi tambang
Investasi tambangInvestasi tambang
Investasi tambang
 
Mine scheduling process
Mine scheduling processMine scheduling process
Mine scheduling process
 
support system in metal mine
support system in metal minesupport system in metal mine
support system in metal mine
 
Metode penyaliran tambang
Metode penyaliran tambangMetode penyaliran tambang
Metode penyaliran tambang
 
KAJIAN HUBUNGAN ANTARA KEKUATAN TANAH DENGAN DENSITAS PADA TANAH LATOSOL DAN ...
KAJIAN HUBUNGAN ANTARA KEKUATAN TANAH DENGAN DENSITAS PADA TANAH LATOSOL DAN ...KAJIAN HUBUNGAN ANTARA KEKUATAN TANAH DENGAN DENSITAS PADA TANAH LATOSOL DAN ...
KAJIAN HUBUNGAN ANTARA KEKUATAN TANAH DENGAN DENSITAS PADA TANAH LATOSOL DAN ...
 
Mine air sampling
Mine air samplingMine air sampling
Mine air sampling
 
Pasir besi - bahan galian industri
Pasir besi - bahan galian industriPasir besi - bahan galian industri
Pasir besi - bahan galian industri
 
Ekonomi Mineral by Yuli Kusumawati
Ekonomi Mineral by Yuli KusumawatiEkonomi Mineral by Yuli Kusumawati
Ekonomi Mineral by Yuli Kusumawati
 
Kope winder or friction winder ppt
Kope winder or friction winder pptKope winder or friction winder ppt
Kope winder or friction winder ppt
 
Alluvial mine
Alluvial mineAlluvial mine
Alluvial mine
 
Kuliah eksplorasi & genesa geologi batubara indonesia
Kuliah eksplorasi & genesa geologi batubara indonesiaKuliah eksplorasi & genesa geologi batubara indonesia
Kuliah eksplorasi & genesa geologi batubara indonesia
 

Viewers also liked (10)

Underground mine
Underground mineUnderground mine
Underground mine
 
Metoda Penambangan
Metoda PenambanganMetoda Penambangan
Metoda Penambangan
 
PERUMIN 31: Modern Practices for the Design and Planning Underground Mines
PERUMIN 31: Modern Practices for the Design and Planning Underground MinesPERUMIN 31: Modern Practices for the Design and Planning Underground Mines
PERUMIN 31: Modern Practices for the Design and Planning Underground Mines
 
Perforación de rocas
Perforación de rocasPerforación de rocas
Perforación de rocas
 
Métodos de perforación
Métodos de perforaciónMétodos de perforación
Métodos de perforación
 
Perforación en mineria
Perforación en mineria Perforación en mineria
Perforación en mineria
 
Underground mining methods
Underground mining methodsUnderground mining methods
Underground mining methods
 
Mining ppt 2014
Mining ppt 2014Mining ppt 2014
Mining ppt 2014
 
Topic 5: Mining Methods-Part I-Surface mining
Topic 5: Mining Methods-Part I-Surface mining Topic 5: Mining Methods-Part I-Surface mining
Topic 5: Mining Methods-Part I-Surface mining
 
Lecture 4: Underground Mining
Lecture 4: Underground MiningLecture 4: Underground Mining
Lecture 4: Underground Mining
 

UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

  • 1. UNIVERSITY OF MINES AND TECHNOLOGY FACULTY OF MINERAL RESOURCES TECHNOLOGY MINING ENGINEERING DEPARTMENT SEMINAR PRESENTATION TOPIC ASSESSMENT OF THE DEVELOPMENT AND STOPING EFFICIENCIES OF A MINING BLOCK - A CASE STUDY BY: SUPERVISOR: OBENG-SIKA JOSEPH MR. EMMANUEL M. BUABA 1
  • 2. MODE OF PRESENTATION PROBLEM DEFINITION OBJECTIVES METHODS USED DATA ANALYSIS CONCLUSIONS RECOMMENDATIONS 2
  • 3. STATEMENT OF PROBLEM  Underground mine development involves the excavation of series of openings to gain access to the orebody for eventual stope production.  For enhanced stope productivity, development operations is co-ordinated with production stages.  AGA Obuasi Mine has been a vibrant underground mine and a major backbone of the Ghanaian economy for several decades. 3
  • 4. STATEMENT OF PROBLEM CONT’D  The mine has experienced a decline in its production tonnages for the past few years primarily due to the fall in the rate of advance of secondary development openings.  This project seeks to assess the efficiencies of the secondary development and stoping operations of the Brown Sub Vertical Shaft (BSVS) Mine of AGA. 4
  • 5. OBJECTIVES To determine the development efficiency (Ed) of the block. To determine the stoping efficiency (ES) of the block. To identify the relationship between the development and stoping efficiencies of the block. 5
  • 6. METHODS USED Literature review on the subject area Field visits and interaction with personnel at the stopes in Block 8 Lower of BSVS Mine. Analysis of collected data 6
  • 7. DATA ANALYSIS Fig. 1 Development Cycle in Underground Mines 7
  • 8. DATA ANALYSIS CONT’D Fig. 2 Sublevel Stoping Cycle 8
  • 9. DATA ANALYSIS CONT’D 0 50 100 150 200 250 300 Advancement(m) FORECAST ACHIEVED AVERAGE ACHIEVED AVERAGE FORECAST Fig. 3 Development Advance for 2013 9
  • 10. DATA ANALYSIS CONT’D 0 5,000 10,000 15,000 20,000 25,000 ProductionTonnages(t) FORECAST ACHIEVED AVERAGE FORECAST AVERAGE ACHIEVED Fig. 4 Production Tonnages for 2013 10
  • 11. DATA ANALYSIS CONT’D 𝐸 𝑑 = 𝐴𝑚𝑜𝑢𝑛𝑡 𝑜𝑓 𝑠𝑒𝑐𝑜𝑛𝑑𝑎𝑟𝑦 𝑑𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 𝑚3 1000 𝑡𝑜𝑛𝑛𝑒𝑠 𝑜𝑓 𝑜𝑟𝑒 𝑚𝑖𝑛𝑒𝑑 = 𝐿𝐷 ×42 +(𝑉𝐷 ×2.42) 1000 𝑡𝑜𝑛𝑛𝑒𝑠 𝑜𝑓 𝑜𝑟𝑒 𝑚𝑖𝑛𝑒𝑑 𝐸𝑆 = 𝑇𝑜𝑛𝑛𝑒𝑠 𝑜𝑓 𝑜𝑟𝑒 𝑚𝑖𝑛𝑒𝑑 𝑁𝑜. 𝑜𝑓 𝑒𝑚𝑝𝑙𝑜𝑦𝑒𝑒𝑠 ×𝑆ℎ𝑖𝑓𝑡𝑠 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 11
  • 12. DATA ANALYSIS CONT’D MONTH ACHIEVED DEVELOPMENT (m) ACHIEVED TONNAGES (t) DEVELOPMENT EFFICIENCY (m3 /t)LATERAL VERTICAL January 141.6 33 18,812 130.54 February 175.4 40 15,737 192.98 March 178.8 40 14,974 206.44 April 203.7 40 18,715 186.47 May 181.7 40 16,315 192.31 June 214.1 40 15,333 238.44 July 214.6 20 12,182 291.32 August 225.3 19 16,451 225.78 September 223.0 34 15,251 246.80 October 239.1 33 16,097 249.47 November 265.5 15 13,472 321.73 December 213.0 49 17,778 207.57 Table 1 Monthly Development Efficiencies for 2013 12
  • 13. DATA ANALYSIS CONT’D MONTH No. of Days ACHIEVED Es (t/employee- shift) January 31 18,812 37.93 February 28 15,737 35.13 March 31 14,974 30.19 April 30 18,715 38.99 May 31 16,315 32.89 June 30 15,333 31.94 July 31 12,182 24.56 August 31 16,451 33.17 September 30 15,251 31.77 October 31 16,097 32.45 November 30 13,472 28.07 December 31 17,778 35.84 Table 2 Monthly Stoping Efficiencies for 2013 13
  • 14. DATA ANALYSIS CONT’D 50 100 150 200 250 300 350 DevelopmentEfficiency(m³/t) Development Efficiency Average Development Efficiency Fig 5 Development Efficiency Trend for 2013 14
  • 15. DATA ANALYSIS CONT’D 10 20 30 40 50 60 StopingEfficiency(t/employee-shift) Stoping Efficiency Average Stoping Efficiency Maximum Stoping Efficiency Minimum Stoping Efficiency Fig. 6 Monthly Stoping Efficiencies Against Standardised Values 15
  • 16. DATA ANALYSIS CONT’D 16 y = -10.387x + 564.35 R² = 0.6824 50 100 150 200 250 300 350 24 26 28 30 32 34 36 38 40 DevelopmentEfficiency(m³/t) Stoping Efficiency (t/employee-shift) Fig 7 Relationship Between Development and Stoping Efficiencies
  • 17. CONCLUSION  The average monthly Ed was 224.23 m3/t, implying for every 10 m advance, a tonne of ore is obtained.  The ES ranged between 24.56 t/employee-shift to 38.99 t/employee-shift.  Ed is inversely proportional to ES. 17
  • 18. RECOMMENDATIONS Jumbos should be employed over the use of jackhammers. Development and stope preparations should be done in advance as the current stope is mined to allow for concurrent stoping. Standard ES and Ed values should be generated against which field values are assessed. 18