METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017
Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA
1
PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA
METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA
TAHUN 2017
Oleh : PT. ANSI MEGA INSTRUMENINDO - JAKARTA
METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017
Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA
2
PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA
DAFTAR ISI
1. PENDAHULUAN ............................................................................................................................................3
1.1. LATAR BELAKANG.........................................................................................................................................3
1.2. TUJUAN DAN USAHA MENGIKUTI LELANG PEKERJAAN “PERBAIKAN SISTEM METERING DI SPPP -
TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA”. .....................................................................4
2. DETAIL PEKERJAAN.......................................................................................................................................4
2.1 PEKERJAAN PESIAPAN :................................................................................................................................4
2.1.1. Persiapan & Pembersihan Lapangan Kerja................................................................................................4
2.1.2. Mobilisasi Peralatan dan Tenaga Kerja......................................................................................................4
2.1.3. Penyediaan APD & Peralatan Keselamatan Kerja ....................................................................................4
2.1.4. Pengamanan Material & Lokasi Kerja.......................................................................................................4
2.2 PENGADAAN & INSTALASI MATERIAL UTAMA.............................................................................................4
2.3. PENGADAAN & INTALASI MATERIAL PENUNJANG.......................................................................................5
2.4. Fabrikasi Material Fitting dan Pipa...............................................................................................................5
2.5. INSTALASI DAN KONFIGURASI SISTEM METERING.......................................................................................6
2.6. PENGUJIAN , KALIBRASI & COMMISSIONING...............................................................................................6
2.7. TRAINING.......................................................................................................................................................7
2.7.1. In House Training .......................................................................................................................................7
2.8. PEKERJAAN PERAPIHAN DAN DOKUMENTASI..............................................................................................7
3. WAKTU PELAKSANAAN PEKERJAAN. ...........................................................................................................7
4. Lokasi Perbaikan Sistem Metering di SPPP Tempino , PT Pertamina Gas Central Sumatera Area. ............7
5. KENDALA DAN RESIKO DALAM PERBAIKAN SISTEM MEERING DI SPPP TEMPINO PT PERTAMINA GAS
CENTRAL SUMATERA AREA.....................................................................................................................9
6. KEGIATAN DALAM PERBAIKAN SISTEM METERING DI SPPP TEMPINO.......................................................9
7. PELAKSANAAN PEKERJAAN DALAM PERBAIKAN SISTEM METERING DI SPPP TEMPINO............................9
8. RENCANA BIAYA DAN RENCANA ANGGARAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO. .........10
9. STRUKTUR DIAGRAM ORGANISASI PROYEK PERBAIKAN SISTIM METERING SPPP TEMPINO. .................10
TRUKTUR DIAGRAM ORGANISASI PROYEK PERBAIKAN SISTEM METERING SPPP TEMPINO...................11
10. RENCANA MANAJEMEN PROYEK PENGADAAN DAN PERBAIKAN SISTEM METER DI SPPP TEMPINO.......11
10.1 MANAJEMEN PERBAIKAN SISTEM METERING DI SPPP TEMPINO ............................................................11
10.2 KEGIATAN MEETING..................................................................................................................................12
10.3 TANGGUNG JAWAB DALAM PROYEK ........................................................................................................12
10.4. MODIFIKASI DAN PERUBAHAN DETAIL PEKERJAAN.................................................................................12
10.5. PELAKSANAAN PROSEDUR PEKERJAAN LAPANGAN ....................................................................................
METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017
Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA
3
PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA
10.6. SISTIM KOMUNIKASI DALAM PROYEK (KANTOR DAN PROYEK LAPANGAN)..........................................13
10.7 DOKUMEN MANAJEMEN KONTROL..........................................................................................................13
10.8 MANAJEMEN RESIKO DAN KESALAHAN KERJA........................................................................................13
10.9. MODIFIKASI DAN PERUBAHAN DETAIL PEKERJAAN.................................................................................13
10.10. PELAKSANAAN PROSEDUR PEKERJAAN LAPANGAN .............................................................................13
11. KELENGKAPAN DOKUMEN LENGKAP PERBAIKAN SISTEM METERING DI SPPP TEMPINO......................13
12. PEKERJAAN PEMERIKSAAN TEKNIS ..........................................................................................................13
13. PEKERJAAN PERSIAPAN SERAH TERIMA PEKERJAAN...............................................................................14
14. PEKERJAAN PELATIHAN DAN TRAINING OPERATOR SPPP TEMPINO......................................................14
15. DATA LAMPIRAN PEKERJAAN...................................................................................................................14
1. PENDAHULUAN
1.1. LATAR BELAKANG
METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017
Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA
4
PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA
PT. Pertamina Gas Stasiun Pusat Pemompaan Produksi (SPPP) Tempino, akan meningkatkan
kemampuan penyaluran minyak bumi dari Tempino ke Sungai Gerong (RU III Plaju), melalui PD Meter
sebagai alat ukur arus minyak dengan ukuran dan distribusi sebagai berikut :
1.1.1. PD Meter pada stream Nomor 1 : ukuran 3
1.1.2. PD Meter pada stream Nomor 2 : ukuran 3”
1.1.3. PD Meter pada stream Nomor 3 : ukuran 2”
PD Meter di SPPP Tempino tersebut sudah mulai masuk usia tua , sehingga PT Pertamina Gas perlu
melakukan perbaikan sistem dan atau penggantian PD Meter di SPPP Tempino, hal ini dimaksudkan
agar supaya hasil penyaluran minyak bumi melalui alat ukur PD Meter lebih akurat.
Untuk kegiatan ini PT Pertamina Gas akan mengganti PD Meter Nomor 3 , dari ukuran 2” dirubah
kapasitas jalu alur minyak bumi menjadi ukuran 3”, sehingga semua stream meter di SPPP Tempino
adalah menjadi 3” untuk ketiga stream di SPPP Tempino.diharapkan dengan adanya perbaikan dan
atau penggantian PD meter dengan kapasitas laju arus 3” , maka kapasitas maximal bisa menjadi rata-
rata 450 BOPH dari yang sebelumnya 400 BOPH.
Dengan perbaikan sistem metering di SPPP Tempino kualitas sample minyak bisa 99,99% sesuai
dengan standard API MPMS 8.2 , tentunya hal ini bisa sangat membantu qualitas penyaluran minyak
bumi , dan dengan adanya perbaikan sistem metering dipastikan tidak ada lagi kendala operasional
dan data real time bisa terpantau dengan benar.
1.2. TUJUAN DAN USAHA MENGIKUTI LELANG PEKERJAAN “PERBAIKAN SISTEM METERING DI SPPP
TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA”.
PT ANSI MEGA INSTRUMENINDO , ikut berpartisipasi dalam pekerjaan perbaikan sistem metering PD
Meter dan kelengkapan nya di SPPP Tempino, yang akan dipasangkan pada stream nomor 3 ukuran
2”menjadi ukuran 3”, tentu hal ini akan memperbaiki alat ukur arus minyak dengan kehandalannya
serta dapat dipantau setiap waktu.
1.2.1. Tujuan Lelang Pekerjaan Perbaikan Sistem Metering di SPPP Tempino adalah sbb :
Tujuan lelang Pekerjaan Perbaikan Sistem Metering Di SPPP Tempino PT Pertamina Gas Central
Sumatera Area , adalah sesuai paket lelang pekerjaan Dokumen Penawaran Request For
Quotation Number / Date : 6600041085/08.06.2017.
Collective Number : S17PB0041A
1.2.2. Lokasi Pekerjaan :
Lokasi Pekerjaan Perbaikan Sistem Metering di SPPP Tempino, Distrik Jambi, PT Pertamina Gas
Central Sumatera Area.
1.2.3. Uraian Singkat dan Rincian Pekerjaan :
Pekerjaan Perbaikan Sistem Metering di SPPP Tempino PT Pertamina Gas Central Sumatera
Area, meliput pekerjaan sebagai dalam daftar berikut .
2. DETAIL PEKERJAAN.
2.1 PEKERJAAN PESIAPAN :
2.1.1. Persiapan & Pembersihan Lapangan Kerja
2.1.2. Mobilisasi Peralatan dan Tenaga Kerja
2.1.3. Penyediaan APD & Peralatan Keselamatan Kerja
2.1.4. Pengamanan Material & Lokasi Kerja
2.2 PENGADAAN & INSTALASI MATERIAL UTAMA
2.2.1. Positive Displacement Meter
2.2.1.1. PD Meter FMC Smith Type E3-56, Max Flow Rate :420 USGPM.
METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017
Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA
5
PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA
2.2.1.2. Max Working Pressure : 740 psi, Flange:#00 ANSIB-16.5 Resied Face.
2.2.1.3. Trim : Std , Temp Compresation : ATG
2.2.2. In Line 3” ANSI 300 Basket strainer, attched air release kit , MAWP 720 Psi
2.2.3. Pekerjaan Instalasi PD Meter 3” E3 -56 & Basket Strainer 3”
2.2.2 Flow Computer
2.2.2.1. Flow Computer Eqv. FMC 2, Untuk 3 stream PD Meter dan prover meter
2.2.2.2. Wonderware Flow Comp and HMI CPU, Monitor 32 Inchi, Standing Panel dan printer.
2.2.2.3. Pembongkaran Computer Exsisting
2.2.2.4. Pemasangan Flow Computer FMC 2
2.3. PENGADAAN & INTALASI MATERIAL PENUNJANG.
2.3.1. Penyediaan Material Penunjang
2.3.1.1. Differential Pressure Indicating Transmitter, eq Rosemount, Accuracy up to 0.05% ,
Comm.Protocol : 4-20 mA Hart, Range : (0~300) Psi.
2.3.1.2. Acc: Instrument manifold, mounting bracket, and others fitting to strainer tap.
2.3.1.3 Automatic Sample Controller, eq clifmock true cut C series, Include Probe & Adabtor, Fluid :
Crude Oil, Viscosity : (5~ 300) cst, Actuation Method : Electrical, Sample Grab Size : 1,5 cc ±
5%, Material SS 316, Operating Temp : 32 – 275F,Sample Outlet Connection : 1 - ¼”.
2.3.1.4. Manual Calibrator comlete w. Adjuster eq AM-5 FCM Smith Meter,
2.3.1.5. Cluster Gear 5 : 1eq FMC Smith.
2.3.1.6. Gear 8.4 : 1 eq FMC Smith
2.3.1.7. Junction Box IP 65 SS
2.3.1.8. Electric Actuator for 4-Way Valve eq ROTORK
2.3.1.9. UPS 3000VA eq. APC
2.3.2. Pemasangan Material Penunjang
2.3.2.1. Penyetelan dan pemasangan DPT.
2.3.2.2. Penyetelan dan pemasngan Automatic Sampler Controller.
2.3.2.3. Penyetelan dan pemasangan Manual Calibrator, Gear Cluster, dan Gear Plate
2.3.2.4. Penyetelan dan pemasangan actuator for 4-way.
2.3.3. Penyediaan Material Fitting dan Pipa
2.3.3.1 Pipa Baja karbon 3” sch 40 API 5L Gr B
2.3.3.2. Pipa Baja karbon 4” sch 40 API 5L Gr B
2.3.3.3 Pipa Baja karbon 6” sch 40 API 5L Gr B
2.3.3.4 Reducer 4” x 3” ANSI sch 60
2.3.3.5. Equal tee 3” ANSI sch 40
2.3.3.6. WN Flange 3” ANSI #300
2.3.3.7. Blid Flange 3” ANSI #300
2.3.3.8. Gate Valve 3” ANSI #300
2.3.3.9. DBB/twin seal valve w/press relief system, 3” eq General Valve model 200
2.3.3.10. Check Valve 3” ANSI #300
2.3.3.11. Butterfly Valve 3”ANSI #300
2.3.3.12. Cable Power 4 x 4 mm NYFGBY
2.3.3.13. Cable Instrument 3 x 2,5 mm XLPE
2.3.3.14. Material pondasi meter (pelat 10 mm)
2.4. Fabrikasi Material Fitting dan Pipa
2.4.1. Ecer, Potong & Bevel Pipa
METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017
Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA
6
PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA
2.4.2. Pekerjaan Stel Las Pipa & Fitting
2.4.2.1. Pipa Baja karbon 3” sch 40 API 5L Gr B
2.4.2.2. Pipa Baja karbon 4” sch 40 API 5L Gr B
2.4.2.3. Pipa Baja karbon 6” sch 40 API 5L Gr B
2.4.2.4. Reducer 4” x 3” ANSI sch 60
2.4.2.5. Equal tee 3” ANSI sch 40
2.4.2.6. WN Flange 3” ANSI #300
2.4.3. Pemasangan Fitting.
2.4.3.1. Blid Flange 3” ANSI #300
2.4.3.2. Gate Valve 3” ANSI #300
2.4.3.3. Check Valve 3” ANSI #300
2.4.3.4. DBB/twin seal valve w/press relief system, 3” eq General Valve model 200
2.4.3.5. Butterfly Valve 3”ANSI #300.
2.4.4. Pekerjaan Hot-Tapping.
2.4.4.1. Pengelasan fitting 2”
2.4.4.2. Hot Tapping acces fitting 2”
2.4.4.3. Rental Hot Tapping Machine
2.4.4.4. Ambulan dan Tenaga Medis
2.4.4.5.Inspeksi NDT
2.5. INSTALASI DAN KONFIGURASI SISTEM METERING
2.5.1. Instalasi & Konfigurasi Flow Comp & Sistem Metering
2.5.1.1. Pemasangan kabel dan integrasi seluruh peralatan ke sistem flowco
2.5.1.2. Pekerjaan Galian dan penanaman kabel data dan kabel power incl. Cable tray.
2.5.1.3. Pekerjaan Integrasi Metering system (PD Meter, Prover Meter, Field Instrument)
2.5.1.4. Pekerjaan koneksi Densitometer dan water in crude analyzer ke Flow Computer.
2.5.1.5. Pekerjaan koneksi actuator 4-way valve ke Flow Computer
2.5.1.6. Pekerjaan Penyediaan Koneksitas ke Sistem Meter keL SM/SCADA
2.6. PENGUJIAN , KALIBRASI & COMMISSIONING
2.6.1. Pengujian dan Pengetesan
2.6.1.1. Metering SKID
2.6.1.2. NDT (Radiography)
2.6.1.3. Hydrotest / Pneumatic Test
2.6.1.4. Desitometer dan Water In Crude analyzer
2.6.1.5.Pengetesan Lapangan
2.6.1.6.Kalibrasi
2.6.1.7.Automatic Sampler
2.6.1.8.Pengetesan
2.6.2. Pekerjaan Kalibrasi dan Sertifikasi
2.6.2.1. 3 unit differential pressure indicating transmitter
2.6.2.2. Flow Computer
2.6.2.3. 3 unit PD Meter
2.6.2.4. Pressure Indicating Transmitter
2.6.2.5. Temperature Indicating Transmitter
2.6.3. Commissioning
METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017
Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA
7
PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA
2.7. TRAINING
2.7.1. In House Training
2.8. PEKERJAAN PERAPIHAN DAN DOKUMENTASI
2.8.1. Dokumen Pelaporan
2.8.2. Laporan Mingguan
2.8.3. Laporan Akhir
2.8.4. Pembersihan , Perapihan & Demobilisasi.
3. WAKTU PELAKSANAAN PEKERJAAN.
3.1. Pelaksanaan Pekerjaan adalah 180 (seratus delapan puluh ) hari kalender sejak diterbitkan surat
penujukan.
3.2. Penyerahan pekerjaan (termasuk pelaksanaan pengujian/tes, Commissioning dan Training Operator
dan Teknisi)
3.3. Pengendalian waktu pelaksanaan , memakai metode bar chart.
3.4. Pengendalian Mutu Pelaksanaan :
Untuk menjamin mutu pelaksanaan pekerjaan , dalam pelaksanaan kerja akan mengacu pada
spesifikasi teknis yang ada dalam dokumen tender , berita acara rapat tinjauan lapangan ,
dikendalikan quality control plan.
Persiapan pelaksanaan melakukan koordinasi dengan HSE , Engineering dan Keamanan dan petugas
lapangan, untuk menjamin keamanan keselamatan kerja serta lingkungan hidup.
3.5 Rencana Kerja Perbaikan Sistem Metering di SPPP Tempino, PT Pertamina Gas CSA
Note : Rencana Kerja 180 (seratus delapan puluh) hari kalender
4. Lokasi Perbaikan Sistem Metering di SPPP Tempino , PT Pertamina Gas Central Sumatera Area.
“LOKASI PEKERJAAN PERBAIKAN SISTEM METERING SPPP TEMPINO , DISTRIK JAMBI , PT. PERTAMINA GAS
CENTRAL SUMATRA AREA”
METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017
Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA
8
PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA
Foto No. 1 : Provinsi Sumatera Selatan.
PETA PROVINSI JAMBI
Foto No 2 : Provinsi Jambi
LOKASI PERBAIKAN SISTEM
METERING DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL
SUMATERA AREA
LOKASI PERBAIKAN SISTEM
METERING DI SPPP
TEMPINO,DISTRIK JAMBI
PT PERTAMINA GAS CENTRAL
SUMATERA AREA
METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017
Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA
9
PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA
5. KENDALA DAN RESIKO DALAM PERBAIKAN SISTEM MEERING DI SPPP TEMPINO PT PERTAMINA GAS
CENTRAL SUMATERA AREA.
Dalam hal pelaksanaan perbaikan sistem metering di SPPP Tempino, akan menghadapi beberapa
kendala yang akhirnya akan memberikan dampak kepada keberhasilan perbaikan sistem metering.
Keberhasilan suatu perbaikan sistem metering di SPPP Tempino adalah , tepat waktu, dan salah satu cara
untuk untuk menjamin keberhasilan adalah mengelola kendala yang terjadi di lapangan.
Kendala adalah salah satu resiko pengadaan dan perbaikan sistem metering , resiko adalah kombinasi
kesempatan dalam pekerjaan yang akan mempengaruhi langsung pada jadwal pekerjaan pemasangan ,
sebagaian dari kosekuensi dari resiko pemasangan sistem metering , yang tak kalah penting nya adalah
memperkecil resiko pemasanga untuk bisa antisipasi pada sumber bahaya (HAZARD / HASOP) dan rujukan
terhadap keselamatan kerja serta , keselamatan instalasinya.
Selanjutnya perlu secara khusus menganalisa resiko yang akan terkait dengan pencapaian , waktu , biaya ,
dan kualitas pekerjaan pemasangan flow meter yang menjadi prioritas utama agar bisa berjalan dengan
effisien.
Ada beberapa kendala dan resiko yang perlu dilakukan antisipasi adalah sebagai berikut :
a) Perizinan dengan beberapa pihak yang terkait dengan
• HSE ( JSA – Permit To Work ,Data Matrix )
• Keamanan / Security ( Indentitas Pekerja – Foto Pekerja )
• Administrasi Panitia Pengadaan
• Surat menyurat dan dokumen teknis ataupun administratip.
b) Sistem Metering PD Meter
• Antisipasi terhadap keselamatan kerja yang sedang memasang PD Meter Sistem
• Resiko kegagalan dalam penyambungan pipa , baik dalam segi teknis , pelaksanaan dan operasional.
c) Kemungkinan resiko dalam transportasi darat dan menyeberang laut
• Salah satu resiko adalah gelombang pasang yang tinggi diatas 5 m dan kapal sudah terlanjut berlayar
dari pelabuhan Merak menuju Bakahuni , resikonya adalah kapal terbalik dan peralatan serta
equipment ikut tenggelam ke dasar laut .
• Kemungkinan bisa terjadi akibat gelombang peti kayu yang berisi peralatan PD Meter rusak karena
kapal ter-ombang ambing di laut Gresik Bawean.
• Alat Angkutan darat terbalik di jalan raya yang membuat peralatan PD Meter menjadi rusak.
d) Diperlukan asuransi pengapalan (Asuransi Cargo) terhadap pengangkutan barang untuk jaminan
keamanan barang yang akan dikirim ke Pulau Sunmatera tidak beresiko tinggi.
6. KEGIATAN DALAM PERBAIKAN SISTEM METERING DI SPPP TEMPINO.
Kegiatan pengadaan dan pemasangan PD Meter di SPPP Tempino,akan dimanfaatkan untuk analisa
akurasi pemakaian crude oil dengan , aman , teliti , terkoreksi , terencana dan terprogram dengan sasaran
akhir effisiensi untuk pemakaian kegiatan produksi di SPPP Tempino, termasuk kegiatan tera ulang PD Meter
Stream 3 di SPPP Tempino memakai flow meter. Dan perhitungan perbandingan meter factor (MF) PD Meter
3 melalui flow comp, sehingga acuan pada SE No 8631/18.06/DJM.T/2008 perihal Penggunaan Sistem Alat
Ukur Kegiatan Usaha Migas , bisa terpenuhi.
Akan melaksanakan perbaikan sistem metering PD Meter Nomor 3 dari semula 2 “ menjadi 3 “ agar
kehandalan sistem alat ukur bisa akurat sesuai dengan standar rujukan dari Ditjen Migas.
7. PELAKSANAAN PEKERJAAN DALAM PERBAIKAN SISTEM METERING DI SPPP TEMPINO.
Lingkup Pekerjaan sesuai dengan Request For Quotation Number : 6600041085/08.06.2017 , Collective
Number : S17PB0041A ,adalah sebagai berikut :
METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017
Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA
10
PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA
a) Lampiran Dokumen Teknik .
• Asli Spesifikasi Teknik Barang dan Jasa
• Copy Surat Dukungan dari Pabrikan
• Asli Piping Instrument Diagram Drawing
• Asli Brosur Teknis dari Material
• Asli Bukti Pengalaman Kerja
• Copy Kontrak
• Asli daftar Peralatan
• Asli Metodologi Kerja
• Asli Rencana Kerja dan Jadwal kegiatan
• Asli Struktur Organisasi
• Asli Daftar Personil Pekerja
• Asli CV dan Serifikat Kompetensi Tenaga Kerja
• Dokumen K3
b) Pelaksanaan Kegiatan .
Pelaksanaan kegiatan perbaikan sistem metering di SPPP Tempino , termasuk penyerahan barang ,
dokumen , training operator dengan total keseluruhannya 180 (seratus delapan puluh) hari Kerja
Kalender, sejak diterbitkan surat penunjukan perintah kerja.
8. RENCANA BIAYA DAN RENCANA ANGGARAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO.
a) Rencana Anggaran Biaya
• Project Costing
• Vendor Purchasing Order
• Bank / Insvestment
• Jaminan Bank
b) Rencana Anggaran Pengadaan dan Perbaikan Sistem Metering
• Accaunt Payble untuk Kebutuhan Operasional
• Pembayaran Upah dan Gaji
• Petty Cash
• Material Cadangan
• Pekerjaan Pengelasan dan Kelengkapannya
• Sewa Angkutan / dan Biaya Penerbangan / Akomodasi .
9. STRUKTUR DIAGRAM ORGANISASI PROYEK PERBAIKAN SISTIM METERING SPPP TEMPINO.
Struktur Diagram organisasi dari PT ANSI MEGA INSTRUMENINDO ini yang akan melaksanakan kegiatan
pemasangan PD Meter untuk SPPP Tempino. Dengan struktur organisasi diagram ini akan mencerminkan
batasan tugas dan tanggung jawab , masing masing dalam rangka tugas yang dipertanggung jawabkan untuk
pelaksanaan kegiatan pemasangan PD Meter untuk SPPP Tempino.
METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017
Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA
11
PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA
TRUKTUR DIAGRAM ORGANISASI PROYEK PERBAIKAN SISTEM METERING SPPP TEMPINO
10. RENCANA MANAJEMEN PROYEK PENGADAAN DAN PERBAIKAN SISTEM METER DI SPPP TEMPINO
10.1 MANAJEMEN PERBAIKAN SISTEM METERING DI SPPP TEMPINO
10.1.1 Penjadwalan kegiatan pekerjaan perbaikan sistem metering di SPPP Tempino.
10.1.2 Mengimplementasikan rencana pengadaan dan pemasangan , membuat perencanaan tugas untuk
distribusi pekerjaan di lapangan.
METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017
Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA
12
PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA
10.1.3 Mengontrol , mengendalikan dan mengambil tindakan untuk melakukan pekerjaan dan serta
berinisiatif terhadap pengadaan dan pemasangan PD Meter yang dipertanggung jawabkan, dari
mulai start pekerjaan , sampai finish ( Project Hand Over ).
10.1.4 Menentukan Ketergantungan antara pekerjaan dan resiko pekerjaan dari:
10.1.4.1 Finish-to-Strat.
10.1.4.2 Start-to-Finish.
10.1.4.3 Finish-to-Finish
10.1.4.4 Mengintegrasikan sumber daya sesuai dengan posisi dan jadwal yang sudah dibuat dalam hal
sumber daya, tenaga kerja , fasilitas kerja , material , budget dan anggaran keuangan.
10.1.5 Diagram Organisasi Pengadaan dan Pemasangan PD Meter untuk SPPP Tempino.
10.1.5.1 Project Manager (Sdr. Aris Yuliarta)
10.1.5.2 Planner & Document Control (Sdr. Akrim Hanafi)
10.1.5.3 QA/QC ( Sdr. Dimas )
10.1.5.4 Instrumentation & Electrical (Sdr. Said R)
10.1.5.5 Measurement & Mechanical (Sdr.Andi Yuli Handoko)
10.1.5.6 Electric Engineer (Sdr. Guntur M)
10.1.5.7 Instrument Engineer (Sdr. M. Luthfi)
10.1.5.8 Flow Com Engineer (Sdr. Tri Hendrawan)
10.1.5.9 Gas Pressure Technician (Sdr. Budiono)
10.1.5.10 HSE Representative
10.2 KEGIATAN MEETING
10.2.1. Meeting Total Manajemen Proyek.
10.2.2. Meeting Perencana, Engineering , Pemilik Proyek
10.2.3. Rapat Koordinasi Semua Team Lapangan
10.2.4. Rapat Teknik , Instrument, Electrical , Mechanical
10.2.5. Rapat Pelaksanaan Lapangan
10.2.6. Rapat Manajemen Kontruksi
10.2.7. Rapat Engineering Perencana.
10.3. TANGGUNG JAWAB DALAM PROYEK
10.3.1. Kerjasama Operasi dalam Proyek
10.3.2. Project Manager, Site Operation
10.3.4. Planner & Document Control dan Aktivitas kegiatan
10.3.5. Project Change dan Perubahan / Modifikasi Pekerjaan
10.3.6. Penanggulangan jalur Kritis dalam Pekerjaan
10.4. MODIFIKASI DAN PERUBAHAN DETAIL PEKERJAAN
10.4.1. Pembuatan Sub Assy Drawing & Analisa Perbaikan
10.4.2. Persetujuan Sub Assy Drawing & Approval Modification Pekerjaan
10.4.3. Persetujuan Tagihan Biaya Perubahan Detail Pekerjaan
10.5. PELAKSANAAN PROSEDUR PEKERJAAN LAPANGAN
10.5.1. Metode Pelaksanaan Pekerjaan Lapangan, HSE dan Perizinan
10.5.2. Metode Pekerjaan Mekanikal, Pekerjaan Pipa , Flange , Pengelasan
METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017
Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA
13
PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA
10.5.3. Metode Pekerjaan Elektrikal, Panyambungan , penambahan kabel power. Switching.
10.5.4. Pekerjaan Wiring , Cabling , Panel, HMI , Cable Tray, Instrumentasi
10.6. SISTIM KOMUNIKASI DALAM PROYEK (KANTOR DAN PROYEK LAPANGAN)
10.6.1. Status Laporan Proyek Harian
10.6.2. Status Laporan Proyek Bulanan
10.6.3. Komunikasi Proyek (Kantor Proyek & Lapangan)
10.7 DOKUMEN MANAJEMEN KONTROL
10.7.1. Laporan Progress dan Data untuk Meeting
10.7.2. Dokumen dan Sertifikat Material Asli
10.7.3. Dokumen kontrak dan Detail Kontrak
10.7.4. Dokumen Asset Manajemen
10.8 MANAJEMEN RESIKO DAN KESALAHAN KERJA
10.8.1. Pengurusan keterlambatan perizinan
10.8.2. Pengurusan Keterlambatan persetujuan dokumen teknis
10.8.3. Analisa Potensi Hazard / Hasop (Risk Scorsing)
10.9. MODIFIKASI DAN PERUBAHAN DETAIL PEKERJAAN
10.9.1. Pembuatan Sub Assy Drawing & Analisa Perbaikan
10.9.2. Persetujuan Sub Assy Drawing & Approval Modification Pekerjaan
10.9.3. Persetujuan Tagihan Biaya Perubahan Detail Pekerjaan
10.10. PELAKSANAAN PROSEDUR PEKERJAAN LAPANGAN
10.10.1. Metode Pelaksanaan Pekerjaan Lapangan, HSE dan Perizinan
10.10.2. Metode Pekerjaan Mekanikal, Pekerjaan Pipa , Flange , Pengelasan
10.10.3. Metode Pekerjaan Elektrikal, Panyambungan , penambahan kabel power. Switching.
10.10.4. Pekerjaan Wiring , Cabling , Panel, HMI , Cable Tray, Instrumentasi
11.KELENGKAPAN DOKUMEN LENGKAP PERBAIKAN SISTEM METERING DI SPPP TEMPINO.
11.1.1 Lampiran Data Schedule Gant Chart.
11.1.2. Data Cost Report (Cash Flow, Cost Overun, Task Cost Overview, Earnet Value Report, Recource
Cost Overview)
11.1.2 In Progress Report (Critical Task, Late Task, Milestone Report, Slipping Task)
11.1.3 Dashboard (Cost Overview, Project Overview, Work Overview, Upcoming Task)
11.2 Laporan Kesalahan Pemasangan Instalasi Pipa dan Dudukan Flange.
11.3 Laporan Data Chage Order Pekerjaan / Tambahan Pekerjaan.
11.4 Lampiran Tambahan Pekerjaan.
11.4.1 Laporan Permintaan penambahan Pengecatan.
11.4.2 Laporan Perubahan dan Tambahan Material.
11.5 Prosedure Modifikasi dan Perubahan Pekerjaan
11.5.1 Persetujuan Permintaan Perubahan Desin Pekerjaan
11.5.2 Persetujuan Penambahan Biaya atas Perubahan Pekerjaan
12. PEKERJAAN PEMERIKSAAN TEKNIS
12.1.1 Mengacu pada Desin Engineering dan Dokumen Kontrak dan Berita Acara Anwijzing
METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017
Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA
14
PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA
yang terbaru.
12.1.2 Cakupan kerja dan Metode Pelaksanaan Kerja
12.1.3 QA / QC
12.1.4 HSE dan Lingkungan Hidup
12.1.5 Sertifikat Dokumen Asli
12.1.6 Kelengkapan Dokumen Asli
12.1.7 Dokumen Teknis Inspeksi HSE
12.1.8 Dokumen Teknis Inspeksi Peralatan
13. PEKERJAAN PERSIAPAN SERAH TERIMA PEKERJAAN
13.1. Berita Acara Serah Terima Laporan Hasil Serah Terima Pekerjaan (LHSTP)
13.2 Laporan dan Lampiran Foto Bergambar Kegiatan Pemasangan PD Meter
13.3 Laporan Pembersihan Lokasi Kerja dan Pengangkutan Peralatan Kerja
14. PEKERJAAN PELATIHAN DAN TRAINING OPERATOR SPPP TEMPINO
14.1 Pembuatan Materi Training dan Pelatihan
14.2 Koordinasi dengan HSE / Engineering SPPP Tempino
14.3 Pelaksanaan Training In Class Room / Site Plant Operation
14.4 Closing Training & Serah Terima Peserta Training kepada SPPP Tempino.
15.DATA LAMPIRAN PEKERJAAN
15.1 Rencana Kerja Perbaikan Sistem Metering di SPPP Tempino
15.3 Dokumen HAZOP / HAZID
METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017
Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA
15
PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA
METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING
DI SPPP TEMPINO
PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017
Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA
16
PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA

More Related Content

What's hot

9.1.1.3 Analisa tindak lanjut mutu klinis.docx
9.1.1.3 Analisa tindak lanjut mutu klinis.docx9.1.1.3 Analisa tindak lanjut mutu klinis.docx
9.1.1.3 Analisa tindak lanjut mutu klinis.docxSaepulMustopaKamal
 
Belajar kontrol
Belajar kontrolBelajar kontrol
Belajar kontrolketutjuan
 
Pedoman Pemantauan dan Evaluasi Penyelenggaraan Pengembangan Sistem Penyediaa...
Pedoman Pemantauan dan Evaluasi Penyelenggaraan Pengembangan Sistem Penyediaa...Pedoman Pemantauan dan Evaluasi Penyelenggaraan Pengembangan Sistem Penyediaa...
Pedoman Pemantauan dan Evaluasi Penyelenggaraan Pengembangan Sistem Penyediaa...infosanitasi
 
Pengoperasian ketel uap.ppt
Pengoperasian ketel uap.pptPengoperasian ketel uap.ppt
Pengoperasian ketel uap.pptirwankurniawan45
 
Prosedur pelaporan (laporan harian, mingguan, bulanan) kon-19
Prosedur pelaporan (laporan harian, mingguan, bulanan) kon-19Prosedur pelaporan (laporan harian, mingguan, bulanan) kon-19
Prosedur pelaporan (laporan harian, mingguan, bulanan) kon-19Claudius Herry
 
Tutorial kasir excel
Tutorial kasir excelTutorial kasir excel
Tutorial kasir excelTommyAdrian
 
jadwal penugasan tenaga ahli
jadwal penugasan tenaga ahlijadwal penugasan tenaga ahli
jadwal penugasan tenaga ahlialam161
 
Pertemuan 1 simulasi dan komunikasi digital kd 3.3
Pertemuan 1   simulasi dan komunikasi digital kd 3.3Pertemuan 1   simulasi dan komunikasi digital kd 3.3
Pertemuan 1 simulasi dan komunikasi digital kd 3.3julipermanik
 
RENCANA PELAKSANAAN PELATIHAN 2.pdf
RENCANA PELAKSANAAN PELATIHAN 2.pdfRENCANA PELAKSANAAN PELATIHAN 2.pdf
RENCANA PELAKSANAAN PELATIHAN 2.pdfHarisPurnawan1
 
Bab ii pgn sicanang
Bab ii pgn sicanangBab ii pgn sicanang
Bab ii pgn sicanangEka Regar
 
Pedoman Penyusunan Perencanaan Teknis Pengembangan Sistem Penyediaan Air Minum
Pedoman Penyusunan Perencanaan Teknis Pengembangan Sistem Penyediaan Air MinumPedoman Penyusunan Perencanaan Teknis Pengembangan Sistem Penyediaan Air Minum
Pedoman Penyusunan Perencanaan Teknis Pengembangan Sistem Penyediaan Air Minuminfosanitasi
 
Pedoman Penyusunan Studi Kelayakan Pengembangan Sistem Penyediaan Air Minum
Pedoman Penyusunan Studi Kelayakan Pengembangan Sistem Penyediaan Air MinumPedoman Penyusunan Studi Kelayakan Pengembangan Sistem Penyediaan Air Minum
Pedoman Penyusunan Studi Kelayakan Pengembangan Sistem Penyediaan Air Minuminfosanitasi
 
PMK no. 7 Tahun 2019_Tentang Kesehatan Lingkungan Rumah Sakit
PMK no. 7 Tahun 2019_Tentang Kesehatan Lingkungan Rumah SakitPMK no. 7 Tahun 2019_Tentang Kesehatan Lingkungan Rumah Sakit
PMK no. 7 Tahun 2019_Tentang Kesehatan Lingkungan Rumah SakitUFDK
 
K3 UAP & BT_K3 K.pptx
K3 UAP & BT_K3 K.pptxK3 UAP & BT_K3 K.pptx
K3 UAP & BT_K3 K.pptxalam8313
 
PAPARAN ASPAK KLINIK.pptx
PAPARAN ASPAK KLINIK.pptxPAPARAN ASPAK KLINIK.pptx
PAPARAN ASPAK KLINIK.pptxmedikasejahtera
 

What's hot (20)

Resume Kompressor MKE_.pptx
Resume Kompressor MKE_.pptxResume Kompressor MKE_.pptx
Resume Kompressor MKE_.pptx
 
9.1.1.3 Analisa tindak lanjut mutu klinis.docx
9.1.1.3 Analisa tindak lanjut mutu klinis.docx9.1.1.3 Analisa tindak lanjut mutu klinis.docx
9.1.1.3 Analisa tindak lanjut mutu klinis.docx
 
Sosialisasi bahan dan limbah b3
Sosialisasi bahan dan limbah b3Sosialisasi bahan dan limbah b3
Sosialisasi bahan dan limbah b3
 
Belajar kontrol
Belajar kontrolBelajar kontrol
Belajar kontrol
 
Pedoman Pemantauan dan Evaluasi Penyelenggaraan Pengembangan Sistem Penyediaa...
Pedoman Pemantauan dan Evaluasi Penyelenggaraan Pengembangan Sistem Penyediaa...Pedoman Pemantauan dan Evaluasi Penyelenggaraan Pengembangan Sistem Penyediaa...
Pedoman Pemantauan dan Evaluasi Penyelenggaraan Pengembangan Sistem Penyediaa...
 
Ds industri hilir migas 1, 2
Ds industri hilir migas 1, 2Ds industri hilir migas 1, 2
Ds industri hilir migas 1, 2
 
Pengoperasian ketel uap.ppt
Pengoperasian ketel uap.pptPengoperasian ketel uap.ppt
Pengoperasian ketel uap.ppt
 
Turbin gas
Turbin gas Turbin gas
Turbin gas
 
Prosedur pelaporan (laporan harian, mingguan, bulanan) kon-19
Prosedur pelaporan (laporan harian, mingguan, bulanan) kon-19Prosedur pelaporan (laporan harian, mingguan, bulanan) kon-19
Prosedur pelaporan (laporan harian, mingguan, bulanan) kon-19
 
Tutorial kasir excel
Tutorial kasir excelTutorial kasir excel
Tutorial kasir excel
 
jadwal penugasan tenaga ahli
jadwal penugasan tenaga ahlijadwal penugasan tenaga ahli
jadwal penugasan tenaga ahli
 
Pertemuan 1 simulasi dan komunikasi digital kd 3.3
Pertemuan 1   simulasi dan komunikasi digital kd 3.3Pertemuan 1   simulasi dan komunikasi digital kd 3.3
Pertemuan 1 simulasi dan komunikasi digital kd 3.3
 
RENCANA PELAKSANAAN PELATIHAN 2.pdf
RENCANA PELAKSANAAN PELATIHAN 2.pdfRENCANA PELAKSANAAN PELATIHAN 2.pdf
RENCANA PELAKSANAAN PELATIHAN 2.pdf
 
Bab ii pgn sicanang
Bab ii pgn sicanangBab ii pgn sicanang
Bab ii pgn sicanang
 
Pedoman Penyusunan Perencanaan Teknis Pengembangan Sistem Penyediaan Air Minum
Pedoman Penyusunan Perencanaan Teknis Pengembangan Sistem Penyediaan Air MinumPedoman Penyusunan Perencanaan Teknis Pengembangan Sistem Penyediaan Air Minum
Pedoman Penyusunan Perencanaan Teknis Pengembangan Sistem Penyediaan Air Minum
 
Pedoman Penyusunan Studi Kelayakan Pengembangan Sistem Penyediaan Air Minum
Pedoman Penyusunan Studi Kelayakan Pengembangan Sistem Penyediaan Air MinumPedoman Penyusunan Studi Kelayakan Pengembangan Sistem Penyediaan Air Minum
Pedoman Penyusunan Studi Kelayakan Pengembangan Sistem Penyediaan Air Minum
 
Dukungan material
Dukungan materialDukungan material
Dukungan material
 
PMK no. 7 Tahun 2019_Tentang Kesehatan Lingkungan Rumah Sakit
PMK no. 7 Tahun 2019_Tentang Kesehatan Lingkungan Rumah SakitPMK no. 7 Tahun 2019_Tentang Kesehatan Lingkungan Rumah Sakit
PMK no. 7 Tahun 2019_Tentang Kesehatan Lingkungan Rumah Sakit
 
K3 UAP & BT_K3 K.pptx
K3 UAP & BT_K3 K.pptxK3 UAP & BT_K3 K.pptx
K3 UAP & BT_K3 K.pptx
 
PAPARAN ASPAK KLINIK.pptx
PAPARAN ASPAK KLINIK.pptxPAPARAN ASPAK KLINIK.pptx
PAPARAN ASPAK KLINIK.pptx
 

Similar to Metodologi Kerja SPPP Tempino

Dermaga 1-4-7 ka-andal_bab_3
Dermaga   1-4-7 ka-andal_bab_3Dermaga   1-4-7 ka-andal_bab_3
Dermaga 1-4-7 ka-andal_bab_3Messy Cool
 
2.Tim RAYTEK ( PT.SAS ) - Makalah Step 1-8 - 2023 (Rev-2) QCC YUTAKA.pptx
2.Tim RAYTEK ( PT.SAS ) - Makalah  Step 1-8 - 2023 (Rev-2) QCC YUTAKA.pptx2.Tim RAYTEK ( PT.SAS ) - Makalah  Step 1-8 - 2023 (Rev-2) QCC YUTAKA.pptx
2.Tim RAYTEK ( PT.SAS ) - Makalah Step 1-8 - 2023 (Rev-2) QCC YUTAKA.pptxDanuSetyo3
 
Penentuan jadwal-penggantian-optimal-komponen-scraper-plate-pada-mesin-giling...
Penentuan jadwal-penggantian-optimal-komponen-scraper-plate-pada-mesin-giling...Penentuan jadwal-penggantian-optimal-komponen-scraper-plate-pada-mesin-giling...
Penentuan jadwal-penggantian-optimal-komponen-scraper-plate-pada-mesin-giling...Andy Sulistio
 
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minum
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air MinumPedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minum
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minuminfosanitasi
 
1 pengantar sop
1 pengantar sop1 pengantar sop
1 pengantar sopbedhoo
 
Presentasi pertek emisi PT BRM .pptx
Presentasi pertek emisi PT BRM .pptxPresentasi pertek emisi PT BRM .pptx
Presentasi pertek emisi PT BRM .pptxMohammadIsaMario1
 
Pemeliharaan servis sistem_bahan_bakar_diesel2
Pemeliharaan servis sistem_bahan_bakar_diesel2Pemeliharaan servis sistem_bahan_bakar_diesel2
Pemeliharaan servis sistem_bahan_bakar_diesel2dwi_dop19
 
Teknologi 2012 9_1_3_taribuka (1)
Teknologi 2012 9_1_3_taribuka (1)Teknologi 2012 9_1_3_taribuka (1)
Teknologi 2012 9_1_3_taribuka (1)Handoko Subekti
 
Pedoman Pengelolaan Sistem Penyediaan Air Minum
Pedoman Pengelolaan Sistem Penyediaan Air MinumPedoman Pengelolaan Sistem Penyediaan Air Minum
Pedoman Pengelolaan Sistem Penyediaan Air Minuminfosanitasi
 
Download contoh-presentasi-yang-baik-lpik-itb
Download contoh-presentasi-yang-baik-lpik-itbDownload contoh-presentasi-yang-baik-lpik-itb
Download contoh-presentasi-yang-baik-lpik-itbillend
 
Roche alimin p227-232
Roche alimin p227-232Roche alimin p227-232
Roche alimin p227-232Darman Syah
 
259900734-EFI-pdf.pdf
259900734-EFI-pdf.pdf259900734-EFI-pdf.pdf
259900734-EFI-pdf.pdfMoebasir
 
Silabus teknik sepeda motor
Silabus teknik sepeda motorSilabus teknik sepeda motor
Silabus teknik sepeda motorherman hidayat
 
Pedoman Pemeliharaan dan Rehabilitasi Sistem Penyediaan Air Minum
Pedoman Pemeliharaan dan Rehabilitasi Sistem Penyediaan Air MinumPedoman Pemeliharaan dan Rehabilitasi Sistem Penyediaan Air Minum
Pedoman Pemeliharaan dan Rehabilitasi Sistem Penyediaan Air Minuminfosanitasi
 

Similar to Metodologi Kerja SPPP Tempino (20)

Ipi293800
Ipi293800Ipi293800
Ipi293800
 
Dermaga 1-4-7 ka-andal_bab_3
Dermaga   1-4-7 ka-andal_bab_3Dermaga   1-4-7 ka-andal_bab_3
Dermaga 1-4-7 ka-andal_bab_3
 
turbin gas
turbin gasturbin gas
turbin gas
 
final presentasi ptp3.pptx
final presentasi ptp3.pptxfinal presentasi ptp3.pptx
final presentasi ptp3.pptx
 
2.Tim RAYTEK ( PT.SAS ) - Makalah Step 1-8 - 2023 (Rev-2) QCC YUTAKA.pptx
2.Tim RAYTEK ( PT.SAS ) - Makalah  Step 1-8 - 2023 (Rev-2) QCC YUTAKA.pptx2.Tim RAYTEK ( PT.SAS ) - Makalah  Step 1-8 - 2023 (Rev-2) QCC YUTAKA.pptx
2.Tim RAYTEK ( PT.SAS ) - Makalah Step 1-8 - 2023 (Rev-2) QCC YUTAKA.pptx
 
Penentuan jadwal-penggantian-optimal-komponen-scraper-plate-pada-mesin-giling...
Penentuan jadwal-penggantian-optimal-komponen-scraper-plate-pada-mesin-giling...Penentuan jadwal-penggantian-optimal-komponen-scraper-plate-pada-mesin-giling...
Penentuan jadwal-penggantian-optimal-komponen-scraper-plate-pada-mesin-giling...
 
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minum
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air MinumPedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minum
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minum
 
1 pengantar sop
1 pengantar sop1 pengantar sop
1 pengantar sop
 
Presentasi pertek emisi PT BRM .pptx
Presentasi pertek emisi PT BRM .pptxPresentasi pertek emisi PT BRM .pptx
Presentasi pertek emisi PT BRM .pptx
 
Bab 1
Bab 1Bab 1
Bab 1
 
Pemeliharaan servis sistem_bahan_bakar_diesel2
Pemeliharaan servis sistem_bahan_bakar_diesel2Pemeliharaan servis sistem_bahan_bakar_diesel2
Pemeliharaan servis sistem_bahan_bakar_diesel2
 
Introduction
IntroductionIntroduction
Introduction
 
Teknologi 2012 9_1_3_taribuka (1)
Teknologi 2012 9_1_3_taribuka (1)Teknologi 2012 9_1_3_taribuka (1)
Teknologi 2012 9_1_3_taribuka (1)
 
Pedoman Pengelolaan Sistem Penyediaan Air Minum
Pedoman Pengelolaan Sistem Penyediaan Air MinumPedoman Pengelolaan Sistem Penyediaan Air Minum
Pedoman Pengelolaan Sistem Penyediaan Air Minum
 
Modul epanet
Modul epanetModul epanet
Modul epanet
 
Download contoh-presentasi-yang-baik-lpik-itb
Download contoh-presentasi-yang-baik-lpik-itbDownload contoh-presentasi-yang-baik-lpik-itb
Download contoh-presentasi-yang-baik-lpik-itb
 
Roche alimin p227-232
Roche alimin p227-232Roche alimin p227-232
Roche alimin p227-232
 
259900734-EFI-pdf.pdf
259900734-EFI-pdf.pdf259900734-EFI-pdf.pdf
259900734-EFI-pdf.pdf
 
Silabus teknik sepeda motor
Silabus teknik sepeda motorSilabus teknik sepeda motor
Silabus teknik sepeda motor
 
Pedoman Pemeliharaan dan Rehabilitasi Sistem Penyediaan Air Minum
Pedoman Pemeliharaan dan Rehabilitasi Sistem Penyediaan Air MinumPedoman Pemeliharaan dan Rehabilitasi Sistem Penyediaan Air Minum
Pedoman Pemeliharaan dan Rehabilitasi Sistem Penyediaan Air Minum
 

Recently uploaded

Manual Desain Perkerasan jalan 2017 FINAL.pptx
Manual Desain Perkerasan jalan 2017 FINAL.pptxManual Desain Perkerasan jalan 2017 FINAL.pptx
Manual Desain Perkerasan jalan 2017 FINAL.pptxRemigius1984
 
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptx
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptxMateri Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptx
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptxarifyudianto3
 
2024.02.26 - Pra-Rakor Tol IKN 3A-2 - R2 V2.pptx
2024.02.26 - Pra-Rakor Tol IKN 3A-2 - R2 V2.pptx2024.02.26 - Pra-Rakor Tol IKN 3A-2 - R2 V2.pptx
2024.02.26 - Pra-Rakor Tol IKN 3A-2 - R2 V2.pptxEnginerMine
 
MAteri:Penggunaan fungsi pada pemrograman c++
MAteri:Penggunaan fungsi pada pemrograman c++MAteri:Penggunaan fungsi pada pemrograman c++
MAteri:Penggunaan fungsi pada pemrograman c++FujiAdam
 
10.-Programable-Logic-Controller (1).ppt
10.-Programable-Logic-Controller (1).ppt10.-Programable-Logic-Controller (1).ppt
10.-Programable-Logic-Controller (1).ppttaniaalda710
 
Manajer Lapangan Pelaksanaan Pekerjaan Gedung - Endy Aitya.pptx
Manajer Lapangan Pelaksanaan Pekerjaan Gedung - Endy Aitya.pptxManajer Lapangan Pelaksanaan Pekerjaan Gedung - Endy Aitya.pptx
Manajer Lapangan Pelaksanaan Pekerjaan Gedung - Endy Aitya.pptxarifyudianto3
 
Presentasi gedung jenjang 6 - Isman Kurniawan.ppt
Presentasi gedung jenjang 6 - Isman Kurniawan.pptPresentasi gedung jenjang 6 - Isman Kurniawan.ppt
Presentasi gedung jenjang 6 - Isman Kurniawan.pptarifyudianto3
 
BAB_3_Teorema superposisi_thevenin_norton (1).ppt
BAB_3_Teorema superposisi_thevenin_norton (1).pptBAB_3_Teorema superposisi_thevenin_norton (1).ppt
BAB_3_Teorema superposisi_thevenin_norton (1).pptDellaEkaPutri2
 
TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdf
TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdfTEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdf
TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdfYogiCahyoPurnomo
 
sample for Flow Chart Permintaan Spare Part
sample for Flow Chart Permintaan Spare Partsample for Flow Chart Permintaan Spare Part
sample for Flow Chart Permintaan Spare Parthusien3
 
Strategi Pengembangan Agribisnis di Indonesia
Strategi Pengembangan Agribisnis di IndonesiaStrategi Pengembangan Agribisnis di Indonesia
Strategi Pengembangan Agribisnis di IndonesiaRenaYunita2
 
SOAL UJIAN SKKhhhhhhjjjjjjjjjjjjjjjj.pptx
SOAL UJIAN SKKhhhhhhjjjjjjjjjjjjjjjj.pptxSOAL UJIAN SKKhhhhhhjjjjjjjjjjjjjjjj.pptx
SOAL UJIAN SKKhhhhhhjjjjjjjjjjjjjjjj.pptxFahrizalTriPrasetyo
 
Laporan Tinjauan Manajemen HSE/Laporan HSE Triwulanpptx
Laporan Tinjauan Manajemen HSE/Laporan HSE TriwulanpptxLaporan Tinjauan Manajemen HSE/Laporan HSE Triwulanpptx
Laporan Tinjauan Manajemen HSE/Laporan HSE Triwulanpptxilanarespatinovitari1
 

Recently uploaded (14)

Manual Desain Perkerasan jalan 2017 FINAL.pptx
Manual Desain Perkerasan jalan 2017 FINAL.pptxManual Desain Perkerasan jalan 2017 FINAL.pptx
Manual Desain Perkerasan jalan 2017 FINAL.pptx
 
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptx
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptxMateri Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptx
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptx
 
2024.02.26 - Pra-Rakor Tol IKN 3A-2 - R2 V2.pptx
2024.02.26 - Pra-Rakor Tol IKN 3A-2 - R2 V2.pptx2024.02.26 - Pra-Rakor Tol IKN 3A-2 - R2 V2.pptx
2024.02.26 - Pra-Rakor Tol IKN 3A-2 - R2 V2.pptx
 
MAteri:Penggunaan fungsi pada pemrograman c++
MAteri:Penggunaan fungsi pada pemrograman c++MAteri:Penggunaan fungsi pada pemrograman c++
MAteri:Penggunaan fungsi pada pemrograman c++
 
10.-Programable-Logic-Controller (1).ppt
10.-Programable-Logic-Controller (1).ppt10.-Programable-Logic-Controller (1).ppt
10.-Programable-Logic-Controller (1).ppt
 
Manajer Lapangan Pelaksanaan Pekerjaan Gedung - Endy Aitya.pptx
Manajer Lapangan Pelaksanaan Pekerjaan Gedung - Endy Aitya.pptxManajer Lapangan Pelaksanaan Pekerjaan Gedung - Endy Aitya.pptx
Manajer Lapangan Pelaksanaan Pekerjaan Gedung - Endy Aitya.pptx
 
Abortion Pills In Doha // QATAR (+966572737505 ) Get Cytotec
Abortion Pills In Doha // QATAR (+966572737505 ) Get CytotecAbortion Pills In Doha // QATAR (+966572737505 ) Get Cytotec
Abortion Pills In Doha // QATAR (+966572737505 ) Get Cytotec
 
Presentasi gedung jenjang 6 - Isman Kurniawan.ppt
Presentasi gedung jenjang 6 - Isman Kurniawan.pptPresentasi gedung jenjang 6 - Isman Kurniawan.ppt
Presentasi gedung jenjang 6 - Isman Kurniawan.ppt
 
BAB_3_Teorema superposisi_thevenin_norton (1).ppt
BAB_3_Teorema superposisi_thevenin_norton (1).pptBAB_3_Teorema superposisi_thevenin_norton (1).ppt
BAB_3_Teorema superposisi_thevenin_norton (1).ppt
 
TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdf
TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdfTEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdf
TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdf
 
sample for Flow Chart Permintaan Spare Part
sample for Flow Chart Permintaan Spare Partsample for Flow Chart Permintaan Spare Part
sample for Flow Chart Permintaan Spare Part
 
Strategi Pengembangan Agribisnis di Indonesia
Strategi Pengembangan Agribisnis di IndonesiaStrategi Pengembangan Agribisnis di Indonesia
Strategi Pengembangan Agribisnis di Indonesia
 
SOAL UJIAN SKKhhhhhhjjjjjjjjjjjjjjjj.pptx
SOAL UJIAN SKKhhhhhhjjjjjjjjjjjjjjjj.pptxSOAL UJIAN SKKhhhhhhjjjjjjjjjjjjjjjj.pptx
SOAL UJIAN SKKhhhhhhjjjjjjjjjjjjjjjj.pptx
 
Laporan Tinjauan Manajemen HSE/Laporan HSE Triwulanpptx
Laporan Tinjauan Manajemen HSE/Laporan HSE TriwulanpptxLaporan Tinjauan Manajemen HSE/Laporan HSE Triwulanpptx
Laporan Tinjauan Manajemen HSE/Laporan HSE Triwulanpptx
 

Metodologi Kerja SPPP Tempino

  • 1. METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017 Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA 1 PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA TAHUN 2017 Oleh : PT. ANSI MEGA INSTRUMENINDO - JAKARTA
  • 2. METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017 Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA 2 PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA DAFTAR ISI 1. PENDAHULUAN ............................................................................................................................................3 1.1. LATAR BELAKANG.........................................................................................................................................3 1.2. TUJUAN DAN USAHA MENGIKUTI LELANG PEKERJAAN “PERBAIKAN SISTEM METERING DI SPPP - TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA”. .....................................................................4 2. DETAIL PEKERJAAN.......................................................................................................................................4 2.1 PEKERJAAN PESIAPAN :................................................................................................................................4 2.1.1. Persiapan & Pembersihan Lapangan Kerja................................................................................................4 2.1.2. Mobilisasi Peralatan dan Tenaga Kerja......................................................................................................4 2.1.3. Penyediaan APD & Peralatan Keselamatan Kerja ....................................................................................4 2.1.4. Pengamanan Material & Lokasi Kerja.......................................................................................................4 2.2 PENGADAAN & INSTALASI MATERIAL UTAMA.............................................................................................4 2.3. PENGADAAN & INTALASI MATERIAL PENUNJANG.......................................................................................5 2.4. Fabrikasi Material Fitting dan Pipa...............................................................................................................5 2.5. INSTALASI DAN KONFIGURASI SISTEM METERING.......................................................................................6 2.6. PENGUJIAN , KALIBRASI & COMMISSIONING...............................................................................................6 2.7. TRAINING.......................................................................................................................................................7 2.7.1. In House Training .......................................................................................................................................7 2.8. PEKERJAAN PERAPIHAN DAN DOKUMENTASI..............................................................................................7 3. WAKTU PELAKSANAAN PEKERJAAN. ...........................................................................................................7 4. Lokasi Perbaikan Sistem Metering di SPPP Tempino , PT Pertamina Gas Central Sumatera Area. ............7 5. KENDALA DAN RESIKO DALAM PERBAIKAN SISTEM MEERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA.....................................................................................................................9 6. KEGIATAN DALAM PERBAIKAN SISTEM METERING DI SPPP TEMPINO.......................................................9 7. PELAKSANAAN PEKERJAAN DALAM PERBAIKAN SISTEM METERING DI SPPP TEMPINO............................9 8. RENCANA BIAYA DAN RENCANA ANGGARAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO. .........10 9. STRUKTUR DIAGRAM ORGANISASI PROYEK PERBAIKAN SISTIM METERING SPPP TEMPINO. .................10 TRUKTUR DIAGRAM ORGANISASI PROYEK PERBAIKAN SISTEM METERING SPPP TEMPINO...................11 10. RENCANA MANAJEMEN PROYEK PENGADAAN DAN PERBAIKAN SISTEM METER DI SPPP TEMPINO.......11 10.1 MANAJEMEN PERBAIKAN SISTEM METERING DI SPPP TEMPINO ............................................................11 10.2 KEGIATAN MEETING..................................................................................................................................12 10.3 TANGGUNG JAWAB DALAM PROYEK ........................................................................................................12 10.4. MODIFIKASI DAN PERUBAHAN DETAIL PEKERJAAN.................................................................................12 10.5. PELAKSANAAN PROSEDUR PEKERJAAN LAPANGAN ....................................................................................
  • 3. METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017 Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA 3 PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA 10.6. SISTIM KOMUNIKASI DALAM PROYEK (KANTOR DAN PROYEK LAPANGAN)..........................................13 10.7 DOKUMEN MANAJEMEN KONTROL..........................................................................................................13 10.8 MANAJEMEN RESIKO DAN KESALAHAN KERJA........................................................................................13 10.9. MODIFIKASI DAN PERUBAHAN DETAIL PEKERJAAN.................................................................................13 10.10. PELAKSANAAN PROSEDUR PEKERJAAN LAPANGAN .............................................................................13 11. KELENGKAPAN DOKUMEN LENGKAP PERBAIKAN SISTEM METERING DI SPPP TEMPINO......................13 12. PEKERJAAN PEMERIKSAAN TEKNIS ..........................................................................................................13 13. PEKERJAAN PERSIAPAN SERAH TERIMA PEKERJAAN...............................................................................14 14. PEKERJAAN PELATIHAN DAN TRAINING OPERATOR SPPP TEMPINO......................................................14 15. DATA LAMPIRAN PEKERJAAN...................................................................................................................14 1. PENDAHULUAN 1.1. LATAR BELAKANG
  • 4. METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017 Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA 4 PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA PT. Pertamina Gas Stasiun Pusat Pemompaan Produksi (SPPP) Tempino, akan meningkatkan kemampuan penyaluran minyak bumi dari Tempino ke Sungai Gerong (RU III Plaju), melalui PD Meter sebagai alat ukur arus minyak dengan ukuran dan distribusi sebagai berikut : 1.1.1. PD Meter pada stream Nomor 1 : ukuran 3 1.1.2. PD Meter pada stream Nomor 2 : ukuran 3” 1.1.3. PD Meter pada stream Nomor 3 : ukuran 2” PD Meter di SPPP Tempino tersebut sudah mulai masuk usia tua , sehingga PT Pertamina Gas perlu melakukan perbaikan sistem dan atau penggantian PD Meter di SPPP Tempino, hal ini dimaksudkan agar supaya hasil penyaluran minyak bumi melalui alat ukur PD Meter lebih akurat. Untuk kegiatan ini PT Pertamina Gas akan mengganti PD Meter Nomor 3 , dari ukuran 2” dirubah kapasitas jalu alur minyak bumi menjadi ukuran 3”, sehingga semua stream meter di SPPP Tempino adalah menjadi 3” untuk ketiga stream di SPPP Tempino.diharapkan dengan adanya perbaikan dan atau penggantian PD meter dengan kapasitas laju arus 3” , maka kapasitas maximal bisa menjadi rata- rata 450 BOPH dari yang sebelumnya 400 BOPH. Dengan perbaikan sistem metering di SPPP Tempino kualitas sample minyak bisa 99,99% sesuai dengan standard API MPMS 8.2 , tentunya hal ini bisa sangat membantu qualitas penyaluran minyak bumi , dan dengan adanya perbaikan sistem metering dipastikan tidak ada lagi kendala operasional dan data real time bisa terpantau dengan benar. 1.2. TUJUAN DAN USAHA MENGIKUTI LELANG PEKERJAAN “PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA”. PT ANSI MEGA INSTRUMENINDO , ikut berpartisipasi dalam pekerjaan perbaikan sistem metering PD Meter dan kelengkapan nya di SPPP Tempino, yang akan dipasangkan pada stream nomor 3 ukuran 2”menjadi ukuran 3”, tentu hal ini akan memperbaiki alat ukur arus minyak dengan kehandalannya serta dapat dipantau setiap waktu. 1.2.1. Tujuan Lelang Pekerjaan Perbaikan Sistem Metering di SPPP Tempino adalah sbb : Tujuan lelang Pekerjaan Perbaikan Sistem Metering Di SPPP Tempino PT Pertamina Gas Central Sumatera Area , adalah sesuai paket lelang pekerjaan Dokumen Penawaran Request For Quotation Number / Date : 6600041085/08.06.2017. Collective Number : S17PB0041A 1.2.2. Lokasi Pekerjaan : Lokasi Pekerjaan Perbaikan Sistem Metering di SPPP Tempino, Distrik Jambi, PT Pertamina Gas Central Sumatera Area. 1.2.3. Uraian Singkat dan Rincian Pekerjaan : Pekerjaan Perbaikan Sistem Metering di SPPP Tempino PT Pertamina Gas Central Sumatera Area, meliput pekerjaan sebagai dalam daftar berikut . 2. DETAIL PEKERJAAN. 2.1 PEKERJAAN PESIAPAN : 2.1.1. Persiapan & Pembersihan Lapangan Kerja 2.1.2. Mobilisasi Peralatan dan Tenaga Kerja 2.1.3. Penyediaan APD & Peralatan Keselamatan Kerja 2.1.4. Pengamanan Material & Lokasi Kerja 2.2 PENGADAAN & INSTALASI MATERIAL UTAMA 2.2.1. Positive Displacement Meter 2.2.1.1. PD Meter FMC Smith Type E3-56, Max Flow Rate :420 USGPM.
  • 5. METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017 Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA 5 PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA 2.2.1.2. Max Working Pressure : 740 psi, Flange:#00 ANSIB-16.5 Resied Face. 2.2.1.3. Trim : Std , Temp Compresation : ATG 2.2.2. In Line 3” ANSI 300 Basket strainer, attched air release kit , MAWP 720 Psi 2.2.3. Pekerjaan Instalasi PD Meter 3” E3 -56 & Basket Strainer 3” 2.2.2 Flow Computer 2.2.2.1. Flow Computer Eqv. FMC 2, Untuk 3 stream PD Meter dan prover meter 2.2.2.2. Wonderware Flow Comp and HMI CPU, Monitor 32 Inchi, Standing Panel dan printer. 2.2.2.3. Pembongkaran Computer Exsisting 2.2.2.4. Pemasangan Flow Computer FMC 2 2.3. PENGADAAN & INTALASI MATERIAL PENUNJANG. 2.3.1. Penyediaan Material Penunjang 2.3.1.1. Differential Pressure Indicating Transmitter, eq Rosemount, Accuracy up to 0.05% , Comm.Protocol : 4-20 mA Hart, Range : (0~300) Psi. 2.3.1.2. Acc: Instrument manifold, mounting bracket, and others fitting to strainer tap. 2.3.1.3 Automatic Sample Controller, eq clifmock true cut C series, Include Probe & Adabtor, Fluid : Crude Oil, Viscosity : (5~ 300) cst, Actuation Method : Electrical, Sample Grab Size : 1,5 cc ± 5%, Material SS 316, Operating Temp : 32 – 275F,Sample Outlet Connection : 1 - ¼”. 2.3.1.4. Manual Calibrator comlete w. Adjuster eq AM-5 FCM Smith Meter, 2.3.1.5. Cluster Gear 5 : 1eq FMC Smith. 2.3.1.6. Gear 8.4 : 1 eq FMC Smith 2.3.1.7. Junction Box IP 65 SS 2.3.1.8. Electric Actuator for 4-Way Valve eq ROTORK 2.3.1.9. UPS 3000VA eq. APC 2.3.2. Pemasangan Material Penunjang 2.3.2.1. Penyetelan dan pemasangan DPT. 2.3.2.2. Penyetelan dan pemasngan Automatic Sampler Controller. 2.3.2.3. Penyetelan dan pemasangan Manual Calibrator, Gear Cluster, dan Gear Plate 2.3.2.4. Penyetelan dan pemasangan actuator for 4-way. 2.3.3. Penyediaan Material Fitting dan Pipa 2.3.3.1 Pipa Baja karbon 3” sch 40 API 5L Gr B 2.3.3.2. Pipa Baja karbon 4” sch 40 API 5L Gr B 2.3.3.3 Pipa Baja karbon 6” sch 40 API 5L Gr B 2.3.3.4 Reducer 4” x 3” ANSI sch 60 2.3.3.5. Equal tee 3” ANSI sch 40 2.3.3.6. WN Flange 3” ANSI #300 2.3.3.7. Blid Flange 3” ANSI #300 2.3.3.8. Gate Valve 3” ANSI #300 2.3.3.9. DBB/twin seal valve w/press relief system, 3” eq General Valve model 200 2.3.3.10. Check Valve 3” ANSI #300 2.3.3.11. Butterfly Valve 3”ANSI #300 2.3.3.12. Cable Power 4 x 4 mm NYFGBY 2.3.3.13. Cable Instrument 3 x 2,5 mm XLPE 2.3.3.14. Material pondasi meter (pelat 10 mm) 2.4. Fabrikasi Material Fitting dan Pipa 2.4.1. Ecer, Potong & Bevel Pipa
  • 6. METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017 Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA 6 PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA 2.4.2. Pekerjaan Stel Las Pipa & Fitting 2.4.2.1. Pipa Baja karbon 3” sch 40 API 5L Gr B 2.4.2.2. Pipa Baja karbon 4” sch 40 API 5L Gr B 2.4.2.3. Pipa Baja karbon 6” sch 40 API 5L Gr B 2.4.2.4. Reducer 4” x 3” ANSI sch 60 2.4.2.5. Equal tee 3” ANSI sch 40 2.4.2.6. WN Flange 3” ANSI #300 2.4.3. Pemasangan Fitting. 2.4.3.1. Blid Flange 3” ANSI #300 2.4.3.2. Gate Valve 3” ANSI #300 2.4.3.3. Check Valve 3” ANSI #300 2.4.3.4. DBB/twin seal valve w/press relief system, 3” eq General Valve model 200 2.4.3.5. Butterfly Valve 3”ANSI #300. 2.4.4. Pekerjaan Hot-Tapping. 2.4.4.1. Pengelasan fitting 2” 2.4.4.2. Hot Tapping acces fitting 2” 2.4.4.3. Rental Hot Tapping Machine 2.4.4.4. Ambulan dan Tenaga Medis 2.4.4.5.Inspeksi NDT 2.5. INSTALASI DAN KONFIGURASI SISTEM METERING 2.5.1. Instalasi & Konfigurasi Flow Comp & Sistem Metering 2.5.1.1. Pemasangan kabel dan integrasi seluruh peralatan ke sistem flowco 2.5.1.2. Pekerjaan Galian dan penanaman kabel data dan kabel power incl. Cable tray. 2.5.1.3. Pekerjaan Integrasi Metering system (PD Meter, Prover Meter, Field Instrument) 2.5.1.4. Pekerjaan koneksi Densitometer dan water in crude analyzer ke Flow Computer. 2.5.1.5. Pekerjaan koneksi actuator 4-way valve ke Flow Computer 2.5.1.6. Pekerjaan Penyediaan Koneksitas ke Sistem Meter keL SM/SCADA 2.6. PENGUJIAN , KALIBRASI & COMMISSIONING 2.6.1. Pengujian dan Pengetesan 2.6.1.1. Metering SKID 2.6.1.2. NDT (Radiography) 2.6.1.3. Hydrotest / Pneumatic Test 2.6.1.4. Desitometer dan Water In Crude analyzer 2.6.1.5.Pengetesan Lapangan 2.6.1.6.Kalibrasi 2.6.1.7.Automatic Sampler 2.6.1.8.Pengetesan 2.6.2. Pekerjaan Kalibrasi dan Sertifikasi 2.6.2.1. 3 unit differential pressure indicating transmitter 2.6.2.2. Flow Computer 2.6.2.3. 3 unit PD Meter 2.6.2.4. Pressure Indicating Transmitter 2.6.2.5. Temperature Indicating Transmitter 2.6.3. Commissioning
  • 7. METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017 Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA 7 PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA 2.7. TRAINING 2.7.1. In House Training 2.8. PEKERJAAN PERAPIHAN DAN DOKUMENTASI 2.8.1. Dokumen Pelaporan 2.8.2. Laporan Mingguan 2.8.3. Laporan Akhir 2.8.4. Pembersihan , Perapihan & Demobilisasi. 3. WAKTU PELAKSANAAN PEKERJAAN. 3.1. Pelaksanaan Pekerjaan adalah 180 (seratus delapan puluh ) hari kalender sejak diterbitkan surat penujukan. 3.2. Penyerahan pekerjaan (termasuk pelaksanaan pengujian/tes, Commissioning dan Training Operator dan Teknisi) 3.3. Pengendalian waktu pelaksanaan , memakai metode bar chart. 3.4. Pengendalian Mutu Pelaksanaan : Untuk menjamin mutu pelaksanaan pekerjaan , dalam pelaksanaan kerja akan mengacu pada spesifikasi teknis yang ada dalam dokumen tender , berita acara rapat tinjauan lapangan , dikendalikan quality control plan. Persiapan pelaksanaan melakukan koordinasi dengan HSE , Engineering dan Keamanan dan petugas lapangan, untuk menjamin keamanan keselamatan kerja serta lingkungan hidup. 3.5 Rencana Kerja Perbaikan Sistem Metering di SPPP Tempino, PT Pertamina Gas CSA Note : Rencana Kerja 180 (seratus delapan puluh) hari kalender 4. Lokasi Perbaikan Sistem Metering di SPPP Tempino , PT Pertamina Gas Central Sumatera Area. “LOKASI PEKERJAAN PERBAIKAN SISTEM METERING SPPP TEMPINO , DISTRIK JAMBI , PT. PERTAMINA GAS CENTRAL SUMATRA AREA”
  • 8. METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017 Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA 8 PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA Foto No. 1 : Provinsi Sumatera Selatan. PETA PROVINSI JAMBI Foto No 2 : Provinsi Jambi LOKASI PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA LOKASI PERBAIKAN SISTEM METERING DI SPPP TEMPINO,DISTRIK JAMBI PT PERTAMINA GAS CENTRAL SUMATERA AREA
  • 9. METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017 Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA 9 PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA 5. KENDALA DAN RESIKO DALAM PERBAIKAN SISTEM MEERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA. Dalam hal pelaksanaan perbaikan sistem metering di SPPP Tempino, akan menghadapi beberapa kendala yang akhirnya akan memberikan dampak kepada keberhasilan perbaikan sistem metering. Keberhasilan suatu perbaikan sistem metering di SPPP Tempino adalah , tepat waktu, dan salah satu cara untuk untuk menjamin keberhasilan adalah mengelola kendala yang terjadi di lapangan. Kendala adalah salah satu resiko pengadaan dan perbaikan sistem metering , resiko adalah kombinasi kesempatan dalam pekerjaan yang akan mempengaruhi langsung pada jadwal pekerjaan pemasangan , sebagaian dari kosekuensi dari resiko pemasangan sistem metering , yang tak kalah penting nya adalah memperkecil resiko pemasanga untuk bisa antisipasi pada sumber bahaya (HAZARD / HASOP) dan rujukan terhadap keselamatan kerja serta , keselamatan instalasinya. Selanjutnya perlu secara khusus menganalisa resiko yang akan terkait dengan pencapaian , waktu , biaya , dan kualitas pekerjaan pemasangan flow meter yang menjadi prioritas utama agar bisa berjalan dengan effisien. Ada beberapa kendala dan resiko yang perlu dilakukan antisipasi adalah sebagai berikut : a) Perizinan dengan beberapa pihak yang terkait dengan • HSE ( JSA – Permit To Work ,Data Matrix ) • Keamanan / Security ( Indentitas Pekerja – Foto Pekerja ) • Administrasi Panitia Pengadaan • Surat menyurat dan dokumen teknis ataupun administratip. b) Sistem Metering PD Meter • Antisipasi terhadap keselamatan kerja yang sedang memasang PD Meter Sistem • Resiko kegagalan dalam penyambungan pipa , baik dalam segi teknis , pelaksanaan dan operasional. c) Kemungkinan resiko dalam transportasi darat dan menyeberang laut • Salah satu resiko adalah gelombang pasang yang tinggi diatas 5 m dan kapal sudah terlanjut berlayar dari pelabuhan Merak menuju Bakahuni , resikonya adalah kapal terbalik dan peralatan serta equipment ikut tenggelam ke dasar laut . • Kemungkinan bisa terjadi akibat gelombang peti kayu yang berisi peralatan PD Meter rusak karena kapal ter-ombang ambing di laut Gresik Bawean. • Alat Angkutan darat terbalik di jalan raya yang membuat peralatan PD Meter menjadi rusak. d) Diperlukan asuransi pengapalan (Asuransi Cargo) terhadap pengangkutan barang untuk jaminan keamanan barang yang akan dikirim ke Pulau Sunmatera tidak beresiko tinggi. 6. KEGIATAN DALAM PERBAIKAN SISTEM METERING DI SPPP TEMPINO. Kegiatan pengadaan dan pemasangan PD Meter di SPPP Tempino,akan dimanfaatkan untuk analisa akurasi pemakaian crude oil dengan , aman , teliti , terkoreksi , terencana dan terprogram dengan sasaran akhir effisiensi untuk pemakaian kegiatan produksi di SPPP Tempino, termasuk kegiatan tera ulang PD Meter Stream 3 di SPPP Tempino memakai flow meter. Dan perhitungan perbandingan meter factor (MF) PD Meter 3 melalui flow comp, sehingga acuan pada SE No 8631/18.06/DJM.T/2008 perihal Penggunaan Sistem Alat Ukur Kegiatan Usaha Migas , bisa terpenuhi. Akan melaksanakan perbaikan sistem metering PD Meter Nomor 3 dari semula 2 “ menjadi 3 “ agar kehandalan sistem alat ukur bisa akurat sesuai dengan standar rujukan dari Ditjen Migas. 7. PELAKSANAAN PEKERJAAN DALAM PERBAIKAN SISTEM METERING DI SPPP TEMPINO. Lingkup Pekerjaan sesuai dengan Request For Quotation Number : 6600041085/08.06.2017 , Collective Number : S17PB0041A ,adalah sebagai berikut :
  • 10. METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017 Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA 10 PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA a) Lampiran Dokumen Teknik . • Asli Spesifikasi Teknik Barang dan Jasa • Copy Surat Dukungan dari Pabrikan • Asli Piping Instrument Diagram Drawing • Asli Brosur Teknis dari Material • Asli Bukti Pengalaman Kerja • Copy Kontrak • Asli daftar Peralatan • Asli Metodologi Kerja • Asli Rencana Kerja dan Jadwal kegiatan • Asli Struktur Organisasi • Asli Daftar Personil Pekerja • Asli CV dan Serifikat Kompetensi Tenaga Kerja • Dokumen K3 b) Pelaksanaan Kegiatan . Pelaksanaan kegiatan perbaikan sistem metering di SPPP Tempino , termasuk penyerahan barang , dokumen , training operator dengan total keseluruhannya 180 (seratus delapan puluh) hari Kerja Kalender, sejak diterbitkan surat penunjukan perintah kerja. 8. RENCANA BIAYA DAN RENCANA ANGGARAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO. a) Rencana Anggaran Biaya • Project Costing • Vendor Purchasing Order • Bank / Insvestment • Jaminan Bank b) Rencana Anggaran Pengadaan dan Perbaikan Sistem Metering • Accaunt Payble untuk Kebutuhan Operasional • Pembayaran Upah dan Gaji • Petty Cash • Material Cadangan • Pekerjaan Pengelasan dan Kelengkapannya • Sewa Angkutan / dan Biaya Penerbangan / Akomodasi . 9. STRUKTUR DIAGRAM ORGANISASI PROYEK PERBAIKAN SISTIM METERING SPPP TEMPINO. Struktur Diagram organisasi dari PT ANSI MEGA INSTRUMENINDO ini yang akan melaksanakan kegiatan pemasangan PD Meter untuk SPPP Tempino. Dengan struktur organisasi diagram ini akan mencerminkan batasan tugas dan tanggung jawab , masing masing dalam rangka tugas yang dipertanggung jawabkan untuk pelaksanaan kegiatan pemasangan PD Meter untuk SPPP Tempino.
  • 11. METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017 Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA 11 PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA TRUKTUR DIAGRAM ORGANISASI PROYEK PERBAIKAN SISTEM METERING SPPP TEMPINO 10. RENCANA MANAJEMEN PROYEK PENGADAAN DAN PERBAIKAN SISTEM METER DI SPPP TEMPINO 10.1 MANAJEMEN PERBAIKAN SISTEM METERING DI SPPP TEMPINO 10.1.1 Penjadwalan kegiatan pekerjaan perbaikan sistem metering di SPPP Tempino. 10.1.2 Mengimplementasikan rencana pengadaan dan pemasangan , membuat perencanaan tugas untuk distribusi pekerjaan di lapangan.
  • 12. METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017 Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA 12 PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA 10.1.3 Mengontrol , mengendalikan dan mengambil tindakan untuk melakukan pekerjaan dan serta berinisiatif terhadap pengadaan dan pemasangan PD Meter yang dipertanggung jawabkan, dari mulai start pekerjaan , sampai finish ( Project Hand Over ). 10.1.4 Menentukan Ketergantungan antara pekerjaan dan resiko pekerjaan dari: 10.1.4.1 Finish-to-Strat. 10.1.4.2 Start-to-Finish. 10.1.4.3 Finish-to-Finish 10.1.4.4 Mengintegrasikan sumber daya sesuai dengan posisi dan jadwal yang sudah dibuat dalam hal sumber daya, tenaga kerja , fasilitas kerja , material , budget dan anggaran keuangan. 10.1.5 Diagram Organisasi Pengadaan dan Pemasangan PD Meter untuk SPPP Tempino. 10.1.5.1 Project Manager (Sdr. Aris Yuliarta) 10.1.5.2 Planner & Document Control (Sdr. Akrim Hanafi) 10.1.5.3 QA/QC ( Sdr. Dimas ) 10.1.5.4 Instrumentation & Electrical (Sdr. Said R) 10.1.5.5 Measurement & Mechanical (Sdr.Andi Yuli Handoko) 10.1.5.6 Electric Engineer (Sdr. Guntur M) 10.1.5.7 Instrument Engineer (Sdr. M. Luthfi) 10.1.5.8 Flow Com Engineer (Sdr. Tri Hendrawan) 10.1.5.9 Gas Pressure Technician (Sdr. Budiono) 10.1.5.10 HSE Representative 10.2 KEGIATAN MEETING 10.2.1. Meeting Total Manajemen Proyek. 10.2.2. Meeting Perencana, Engineering , Pemilik Proyek 10.2.3. Rapat Koordinasi Semua Team Lapangan 10.2.4. Rapat Teknik , Instrument, Electrical , Mechanical 10.2.5. Rapat Pelaksanaan Lapangan 10.2.6. Rapat Manajemen Kontruksi 10.2.7. Rapat Engineering Perencana. 10.3. TANGGUNG JAWAB DALAM PROYEK 10.3.1. Kerjasama Operasi dalam Proyek 10.3.2. Project Manager, Site Operation 10.3.4. Planner & Document Control dan Aktivitas kegiatan 10.3.5. Project Change dan Perubahan / Modifikasi Pekerjaan 10.3.6. Penanggulangan jalur Kritis dalam Pekerjaan 10.4. MODIFIKASI DAN PERUBAHAN DETAIL PEKERJAAN 10.4.1. Pembuatan Sub Assy Drawing & Analisa Perbaikan 10.4.2. Persetujuan Sub Assy Drawing & Approval Modification Pekerjaan 10.4.3. Persetujuan Tagihan Biaya Perubahan Detail Pekerjaan 10.5. PELAKSANAAN PROSEDUR PEKERJAAN LAPANGAN 10.5.1. Metode Pelaksanaan Pekerjaan Lapangan, HSE dan Perizinan 10.5.2. Metode Pekerjaan Mekanikal, Pekerjaan Pipa , Flange , Pengelasan
  • 13. METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017 Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA 13 PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA 10.5.3. Metode Pekerjaan Elektrikal, Panyambungan , penambahan kabel power. Switching. 10.5.4. Pekerjaan Wiring , Cabling , Panel, HMI , Cable Tray, Instrumentasi 10.6. SISTIM KOMUNIKASI DALAM PROYEK (KANTOR DAN PROYEK LAPANGAN) 10.6.1. Status Laporan Proyek Harian 10.6.2. Status Laporan Proyek Bulanan 10.6.3. Komunikasi Proyek (Kantor Proyek & Lapangan) 10.7 DOKUMEN MANAJEMEN KONTROL 10.7.1. Laporan Progress dan Data untuk Meeting 10.7.2. Dokumen dan Sertifikat Material Asli 10.7.3. Dokumen kontrak dan Detail Kontrak 10.7.4. Dokumen Asset Manajemen 10.8 MANAJEMEN RESIKO DAN KESALAHAN KERJA 10.8.1. Pengurusan keterlambatan perizinan 10.8.2. Pengurusan Keterlambatan persetujuan dokumen teknis 10.8.3. Analisa Potensi Hazard / Hasop (Risk Scorsing) 10.9. MODIFIKASI DAN PERUBAHAN DETAIL PEKERJAAN 10.9.1. Pembuatan Sub Assy Drawing & Analisa Perbaikan 10.9.2. Persetujuan Sub Assy Drawing & Approval Modification Pekerjaan 10.9.3. Persetujuan Tagihan Biaya Perubahan Detail Pekerjaan 10.10. PELAKSANAAN PROSEDUR PEKERJAAN LAPANGAN 10.10.1. Metode Pelaksanaan Pekerjaan Lapangan, HSE dan Perizinan 10.10.2. Metode Pekerjaan Mekanikal, Pekerjaan Pipa , Flange , Pengelasan 10.10.3. Metode Pekerjaan Elektrikal, Panyambungan , penambahan kabel power. Switching. 10.10.4. Pekerjaan Wiring , Cabling , Panel, HMI , Cable Tray, Instrumentasi 11.KELENGKAPAN DOKUMEN LENGKAP PERBAIKAN SISTEM METERING DI SPPP TEMPINO. 11.1.1 Lampiran Data Schedule Gant Chart. 11.1.2. Data Cost Report (Cash Flow, Cost Overun, Task Cost Overview, Earnet Value Report, Recource Cost Overview) 11.1.2 In Progress Report (Critical Task, Late Task, Milestone Report, Slipping Task) 11.1.3 Dashboard (Cost Overview, Project Overview, Work Overview, Upcoming Task) 11.2 Laporan Kesalahan Pemasangan Instalasi Pipa dan Dudukan Flange. 11.3 Laporan Data Chage Order Pekerjaan / Tambahan Pekerjaan. 11.4 Lampiran Tambahan Pekerjaan. 11.4.1 Laporan Permintaan penambahan Pengecatan. 11.4.2 Laporan Perubahan dan Tambahan Material. 11.5 Prosedure Modifikasi dan Perubahan Pekerjaan 11.5.1 Persetujuan Permintaan Perubahan Desin Pekerjaan 11.5.2 Persetujuan Penambahan Biaya atas Perubahan Pekerjaan 12. PEKERJAAN PEMERIKSAAN TEKNIS 12.1.1 Mengacu pada Desin Engineering dan Dokumen Kontrak dan Berita Acara Anwijzing
  • 14. METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017 Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA 14 PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA yang terbaru. 12.1.2 Cakupan kerja dan Metode Pelaksanaan Kerja 12.1.3 QA / QC 12.1.4 HSE dan Lingkungan Hidup 12.1.5 Sertifikat Dokumen Asli 12.1.6 Kelengkapan Dokumen Asli 12.1.7 Dokumen Teknis Inspeksi HSE 12.1.8 Dokumen Teknis Inspeksi Peralatan 13. PEKERJAAN PERSIAPAN SERAH TERIMA PEKERJAAN 13.1. Berita Acara Serah Terima Laporan Hasil Serah Terima Pekerjaan (LHSTP) 13.2 Laporan dan Lampiran Foto Bergambar Kegiatan Pemasangan PD Meter 13.3 Laporan Pembersihan Lokasi Kerja dan Pengangkutan Peralatan Kerja 14. PEKERJAAN PELATIHAN DAN TRAINING OPERATOR SPPP TEMPINO 14.1 Pembuatan Materi Training dan Pelatihan 14.2 Koordinasi dengan HSE / Engineering SPPP Tempino 14.3 Pelaksanaan Training In Class Room / Site Plant Operation 14.4 Closing Training & Serah Terima Peserta Training kepada SPPP Tempino. 15.DATA LAMPIRAN PEKERJAAN 15.1 Rencana Kerja Perbaikan Sistem Metering di SPPP Tempino 15.3 Dokumen HAZOP / HAZID
  • 15. METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017 Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA 15 PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA
  • 16. METODOLOGI PEKERJAAN PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA – TAHUN 2017 Oleh : PT ANSI MEGA INSTRUMENINDO - JAKARTA 16 PERBAIKAN SISTEM METERING DI SPPP TEMPINO PT PERTAMINA GAS CENTRAL SUMATERA AREA