Microsoft Project - cash center
1. ID ID Task Name Duration Start Finish
1 1 CASH CENTER BUILDING 737 days Mon 4/1/13 Tue 4/7/15
2 2 Contract/approved Cash Center Building WBS 580 days Mon 4/1/13 Sat 11/1/14
3 3 Re checking of boundary of lot prior to start of
construction. Found not matching with Client approved lot
plan, Rectification done
55 days Tue 5/7/13 Sun 6/30/13
4 4 Resolve the conflict of CCB foundation to the retaining
wall of Operation Building
136 days Sun 4/14/13 Tue 8/27/13
5 5 ADDITIONAL TIME GIVEN BY ARB 55 days Sat 11/1/14 Thu 12/25/14
6 6 MAIN BUILDING CONSTRUCTION COMPLETION DATE 519 days Mon 4/1/13 Mon 9/1/14
7 7 STUCTURAL WORKS 556 days Mon 4/1/13 Wed 10/8/14
8 8 B.L. MAIN BUILDING SUB-STRUCTURE
ACTIVITIES
210 days Mon 4/1/13 Sun 10/27/13
9 9 ACTUAL MAIN BUILDING -SUB-STRUCTURE
ACTIVITIES
246 days Mon 4/1/13 Sat 8/30/14
10 10 B.L. GROUND FLOOR ACTIVITIES 36 days Tue 11/26/13 Tue 12/31/13
11 11 ACTUAL MAIN BUILDING GF ACTIVITIES 46 days Tue 10/29/13 Wed 9/10/14
12 12 B.L.FIRST FLOOR ACTIVITIES 36 days Tue 12/31/13 Tue 2/4/14
13 13 ACTUAL FF BUILDING GF ACTIVITIES 51 days Tue 12/3/13 Mon 9/22/14
14 14 B.L.PENTHOUSE FLOOR ACTIVITIES 27 days Tue 2/4/14 Sun 3/2/14
15 15 ACTUAL PH BUILDING GF ACTIVITIES 38 days Fri 1/24/14 Wed 10/8/14
16 16 ARCHITECTURAL WORK 456 days Tue 1/7/14 Tue 4/7/15
17 17 APPROVAL OF ARCHITECTURAL FINISHING
WORK
456 days Tue 1/7/14 Tue 4/7/15
18 18 ELECTROMECHANICAL WORKS 285 days Sat 1/4/14 Wed 10/15/14
19 19 B.L ELECTRICAL WORKS LOW CURRENT
SYSTEM
196 days Tue 1/7/14 Mon 7/21/14
20 20 ACTUAL LOW CURRENT SYSTEM INCLUDING
THE CHANGES (UP TO RELEASED OF
APPROVED DRAWING ONLY FROM CLIENT)
285 days Sat 1/4/14 Wed 10/15/14
21 21 APPROVAL FROM CLIENT ( NO FINAL) 0 days Wed 10/15/14 Wed 10/15/14
4/1 4/7
CASH CENTER BUILDING
737 days
4/1 11/1
Contract/approved Cash Center Building WBS
580 days
5/7 6/30
g of boundary of lot prior to start of construction. Found not matching with Client approved lot plan, Rectification done
55 days
4/14 8/27
Resolve the conflict of CCB foundation to the retaining wall of Operation Building
136 days
11/1 12/25
ADDITIONAL TIME GIVEN BY ARB
55 days
4/1 9/1
MAIN BUILDING CONSTRUCTION COMPLETION DATE
519 days
4/1 10/8
STUCTURAL WORKS
556 days
4/1 10/27
B.L. MAIN BUILDING SUB-STRUCTURE ACTIVITIES
210 days
4/1 8/30
10 MONTHS DELAY DUE TO THE CONFLICT WITH OPERATION RETAINING WALL EXCAVATION OF BASEMENT
246 days
ACTUAL MAIN BUILDING -SUB-STRUCTURE ACTIVITIES
11/26 12/31
B.L. GROUND FLOOR ACTIVITIES
36 days
10/29 9/10
ACTUAL MAIN BUILDING GF ACTIVITIES
46 days
12/31 2/4
B.L.FIRST FLOOR ACTIVITIES
36 days
12/3 9/22
ACTUAL FF BUILDING GF ACTIVITIES
51 days
2/4 3/2
B.L.PENTHOUSE FLOOR ACTIVITIES
27 days
1/24 10/8
ACTUAL PH BUILDING GF ACTIVITIES
38 days
1/7 4/7
APPROVAL OF ARCHITECTURAL FINISHING WORK
456 days
1/4 10/15
ELECTROMECHANICAL WORKS
285 days
1/7 B.L ELECTRICAL WORKS LOW CURRENT SYSTEM
196 days
B.L ELECTRICAL WORKS
1/4 10/15
ACTUAL LOW CURRENT SYSTEM INCLUDING THE CHANGES (UP TO RELEASED OF APPROVED DRAWING ONLY FROM CLIENT)
285 days
10/15
APPROVAL FROM CLIENT ( NO FINAL)
FINAL APPROVAL URGENTLY NEEDED FROM CLIENT . SECURITY DRAWING APPROVED FROM ARB SECURITY DEPARTMENT
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
2013 2014 2015 2016
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
CASH CENTER BUILDING DELAY ANALYSIS
Page 1
Project: cash center
Date: Sat 8/27/16