Microsoft Project Gantt Chat

This is a Gantt Chart for a project completed by myself on Microsoft Project, It is an example Gantt Chart schedule including resources and a highlighted critical path.

  • Be the first to comment

Microsoft Project Gantt Chat

  1. 1. Nov 5 Task Name Warehouse WBS Duration Start Finish 17,Resource Names Apr '13 T 1 Pilkington Tenant Improvement Schedule 193 days 1.1 LEASE RELATED ACTIVITIES 15 days 1.1.1 Sign Letter of Intent to Start Design 0 days 1.1.2 Lease Review 3 wks 1.1.3 Sign Lease Agrement 0 days 1.2 DESIGN DEVELOPMENT 71 days 1.2.1 Preliminary Design Development (SD) 4 wks 1.2.2 Provide Racking Plan (Pilkington) 0 days 1.2.3 Approve Space Plan (Moves 1,2,3) 1 day 1.2.4 Approve Space Plan (Moves 4,5) 1 day 1.2.5 Approve Preliminary Warehouse Space Plan (Dock Locations) 0 days 1.2.6 Design Development (Moves 1,2,3) 2 wks 1.2.7 Design Development (Moves 4,5) 2 wks 1.2.8 Engineered Racking Drawings (Pilkington) 10 days 1.2.9 Office Allowance Budget Approval 0 days 1.2.10 Finalize Interior Finishes 1 day 1.2.11 Bid and Award MEP Design Build Subcontracts 2 days 1.2.12 MEP Design Documents 1 day 1.2.13 Approval of Final Design Documents (Pilkington) 0 days 1.2.14 Bid/Award General Trades/Finishes Packages 0 days 1.2.15 Reconcile Office/Warehouse Alowance Budget 0 days 1.2.16 Submit Permit Drawings (Moves 1,2,3) 4 wks 1.2.17 Submit Permit Drawings (Moves 4,5) 4 wks 1.3 PERMITS 61 days 1.3.1 State of Ohio Building Permit (Moves 1,2,3) 4 wks 1.3.2 State of Ohio Building Permit (Moves 4,5) 4 wks 1.3.3 Racking Plan Review 10 days 1.4 CONSTRUCTION (MOVES 1,2,3) (Phase A) 49 days 1.4.1 Warehouse Power/Lighting 2 days 1.4.1.1 Trench for Underground plumbing 1 day Apr 24 Apr 24 May 14 Apr 24 May 14 May 14 May 15 May 14 Jun 26 Jun 26 Jun 11 Jun 12 Jun 12 May 15 Jun 26 Jun 27 Jul 1 Jun 28 Jun 26 Jun 26 Aug 21 Jun 27 Jun 27 May 29 Jul 25 Jul 25 May 29 Aug 22 Aug 22 Aug 23 Jan 17 May 14 May 14 May 14 May 14 Aug 21 Jun 11 May 14 Jun 26 Jun 26 Jun 11 Jun 25 Jun 25 May 28 Jun 26 Jun 27 Jul 2 Jun 28 Jun 26 Jun 26 Aug 21 Jul 24 Jul 24 Aug 21 Aug 21 Aug 21 Jun 11 Oct 29 Aug 23 Aug 23 Apr 24, '13 W T F Mike Deskin S MDesign,Owner MDesign,Owner MDesign,Owner MDesign MDesign Owner Owner Owner MDesign MDesign MDesign Owner MDesign,Owner MDesign,Owner MDesign Owner MDesign Owner Owner MDesign,Owner Owner Owner MDesign,Owner Cement Crew,Plumbers Perpared for client: Jeff Suchy S M T May 1, '13 W T F S S M T May 8, '13 W T F S S M T May 15, '13 W T F S S M T May 22, '13 W T F S 5/14 MDesign,Owner 5/14 5/14 O O
  2. 2. Nov 5 Task Name Warehouse WBS Duration Start Finish 17,Resource Names Apr '13 T 1.4.1.2 Temporary Lighting 1.4.2 Tenant Racking 1.4.2.1 Install Racks 1.4.3 Rough Framing/Carpentry 1.4.3.1 Install Steel Studs 1.4.3.2 Install Door Frames 1.4.3.3 Install Blocking 1.4.3.4 Install Drywall 1.4.4 Office MEP Rough-in 1.4.4.1 Rough in Electric 1.4.4.2 Run under slab Pipes for Plumbing 1.4.4.3 Run pipes under slab bathroom 1.4.4.4 Run HVAC 1.4.4.5 MEP Rough Inspection 1.4.5 Dock Pit Pour Back 1.4.5.1 FRIPS dock pit 1.4.5.2 Let Cure 1.4.5.3 Install Dock Equipment 1.4.5.4 Complete remaining millwork 1.4.6 Tenant Cabling 1.4.6.1 Install Telephone, Internet 1.4.6.2 Final runs electric 1.4.7 Drywall/Finishes/Ceiling 1.4.7.1 Install Ceiling tile grid 1.4.7.2 Install Ceiling Tiles 1.4.7.3 Mud/Sand Drywall 1.4.7.4 Install Carpet 1.4.7.5 Drop cloth Carpet 1.4.7.6 Paint 2 coats 1.4.7.7 Install tile 1 day 2 days 4 days 25 days 10 days 4 days 6 days 5 days 21 days 2 days 2 days 2 days 5 days 0 days 17 days 2 days 10 days 2 days 3 days 1 day 1 day 1 day 18 days 2 days 3 days 2 days 2 days 1 day 2 days 2 days Aug 22 Sep 4 Sep 27 Aug 26 Aug 26 Sep 17 Sep 9 Sep 23 Aug 26 Sep 9 Aug 26 Aug 28 Sep 17 Sep 23 Aug 30 Aug 30 Sep 3 Sep 17 Sep 19 Sep 24 Sep 24 Sep 24 Sep 24 Oct 7 Sep 24 Sep 30 Oct 2 Oct 4 Oct 9 Oct 11 Aug 22 Sep 5 Oct 2 Sep 27 Sep 6 Sep 20 Sep 16 Sep 27 Sep 23 Sep 10 Aug 27 Aug 29 Sep 23 Sep 23 Sep 23 Sep 2 Sep 16 Sep 18 Sep 23 Sep 24 Sep 24 Sep 24 Oct 17 Oct 8 Sep 26 Oct 1 Oct 3 Oct 4 Oct 10 Oct 14 Apr 24, '13 W T F Mike Deskin S Electrician Labors 1 Rough Carpenters Rough Carpenters Rough Carpenters Finish Carpenters Electrician Plumbers Plumbers HVAC Inspectors Cement Crew Cement Crew Labors 1 Finish Carpenters Electrician Electrician Labors 2 Labors 2 Rough Carpenters Carpet Layers Painters Painters Tile Layers Perpared for client: Jeff Suchy S M T May 1, '13 W T F S S M T May 8, '13 W T F S S M T May 15, '13 W T F S S M T May 22, '13 W T F S
  3. 3. Nov 5 Task Name Warehouse WBS Duration Start Finish 17,Resource Names Apr '13 T 1.4.7.8 Bathroom recepticles 1.4.8 MEP Finishes 1.4.8.1 Bathroom Fixtures 1.4.8.2 MEP Final Inspections 1.4.8.3 finish all life saftey 1.4.9 Final Inspections/Life Saftey 1.4.9.1 Final Structual Inspections 1.4.9.2 Testing of Life Saftey 1.4.9.3 Certificate of Occupancy 1.4.9.4 Substanial Completion 1.4.9.5 Punch List 1.4.9.6 Tenant Relocation (Move 1) 1.4.9.7 Tenant Relocation (Move 2) 1.4.9.8 Tenant Relocation (Move 3) 1.4.9.9 Phase A Complete 1.5 CONSTRUCTION (MOVES 4,5)(Phase B) 1.5.1 Warehouse Power/Lighting 1.5.1.1 Trench out for plumbing 1.5.1.2 Run under slab plumbing 1.5.1.3 Temporary Lighting 1.5.2 Tenant Racking 1.5.2.1 Install Racks 1.5.2.2 All Final Inspections 1.5.3 Rough Framing/Carpentry 1.5.3.1 Install Steel Studs 1.5.3.2 Install Door Frames 1.5.3.3 Install Blocking 1.5.3.4 Install Drywall 1.5.4 Office MEP Rough-in 1.5.4.1 Rough in electric 3 days 14 days 2 days 0 days 1 day 24 days 0 days 0 days 0 days 1 day 3 days 1 day 1 day 1 day 1 day 85 days 6 days 3 days 2 days 1 day 3 days 3 days 0 days 14 days 10 days 2 days 2 days 3 days 15 days 1 day Oct 15 Sep 24 Oct 11 Sep 24 Sep 25 Sep 25 Oct 8 Sep 25 Oct 23 Oct 18 Oct 21 Oct 24 Oct 25 Oct 28 Oct 29 Jul 3 Jul 3 Jul 4 Jul 9 Jul 3 Aug 6 Aug 6 Aug 8 Jul 11 Jul 11 Jul 25 Jul 29 Jul 12 Jul 11 Jul 25 Oct 17 Oct 14 Oct 14 Sep 24 Sep 25 Oct 29 Oct 8 Sep 25 Oct 23 Oct 18 Oct 23 Oct 24 Oct 25 Oct 28 Oct 29 Oct 29 Jul 10 Jul 8 Jul 10 Jul 3 Aug 8 Aug 8 Aug 8 Jul 30 Jul 24 Jul 26 Jul 30 Jul 16 Jul 31 Jul 25 Apr 24, '13 W T F Mike Deskin S Labors 1 Labors 1 Inspectors Labors 1 Inspectors Inspectors Owner Owner Labors 1,Labors 2,MDesign Owner Owner Owner MDesign Cement Crew,Plumbers Plumbers Electrician Labors 1 Inspectors Rough Carpenters Rough Carpenters Rough Carpenters Rough Carpenters Electrician Perpared for client: Jeff Suchy S M T May 1, '13 W T F S S M T May 8, '13 W T F S S M T May 15, '13 W T F S S M T May 22, '13 W T F S
  4. 4. Nov 5 Task Name Warehouse WBS Duration Start Finish 17,Resource Names Apr '13 T 1.5.4.2 Install bathroom Pipes for Plumbing 1.5.4.3 Run HVAC 1.5.4.4 MEP Rough Inspection 1.5.5 Tenant Cabling 1.5.5.1 Install Telephone, Internet 1.5.5.2 Final electrical runs 1.5.6 Drywall/Finishes/Ceiling 1.5.6.1 Install Ceiling Rack 1.5.6.2 Install carpet and VCT 1.5.6.3 Install Ceiling Tiles 1.5.6.4 Mud/Sand Drywall 1.5.6.5 Paint 2 coats 1.5.7 MEP Finishes 1.5.7.1 Bathroom Fixtures 1.5.7.2 MEP Final Inspections 1.5.7.3 Substanial Completion 1.5.7.4 Punch List 1.5.7.5 Tenant Relocation (Move 4) 1.5.7.6 Phase B Complete 1.5.7.7 Project Complete 1.5.7.8 Tenant Relocation (Move 5) 1.5.7.9 Tenant Relocation (Move 5) ALTERNATE 1 day 1 day 0 days 3 days 2 days 1 day 21 days 2 days 4 days 3 days 2 days 4 days 61 days 2 days 0 days 1 day 2 days 1 day 0 days 0 days 1 day 1 day Jul 11 Jul 31 Jul 31 Aug 1 Aug 1 Aug 5 Jul 17 Jul 31 Jul 17 Aug 6 Jul 23 Aug 9 Aug 5 Aug 15 Aug 5 Aug 9 Aug 19 Aug 21 Aug 22 Oct 29 Aug 21 Aug 22 Jul 11 Jul 31 Jul 31 Aug 5 Aug 2 Aug 5 Aug 14 Aug 1 Jul 22 Aug 8 Jul 24 Aug 14 Oct 29 Aug 16 Aug 5 Aug 9 Aug 20 Aug 21 Aug 22 Oct 29 Aug 21 Aug 22 Apr 24, '13 W T F Mike Deskin S Plumbers HVAC Inspectors Electrician Electrician Labors 2 Carpet Layers,Tile Layers Labors 1 Rough Carpenters Painters Labors 2 Inspectors MDesign,Owner MDesign Owner MDesign,Owner MDesign,Owner Owner Owner Perpared for client: Jeff Suchy S M T May 1, '13 W T F S S M T May 8, '13 W T F S S M T May 15, '13 W T F S S M T May 22, '13 W T F S
  5. 5. Nov 5 Warehouse WBS '13 S S M T May 29, '13 W T F S S M T Jun 5, '13 W T F S S M T Jun 12, '13 W T F S S M T Jun 19, '13 W T F S S M T Mike Deskin Jun 26, '13 W T F S S M T Jul 3, '13 W T F S MDesign Owner Owner 6/11 MDesign MDesign MDesign 6/26 MDesign,Owner MDesign,Owner MDesign 6/26 6/26 MDesign,Owner Perpared for client: Jeff Suchy S M T Jul 10, '13 W T F S S M T Jul 17, '13 W T F S S M T W
  6. 6. Nov 5 Warehouse WBS '13 S S M T May 29, '13 W T F S S M T Jun 5, '13 W T F S S M T Jun 12, '13 W T F S S M T Jun 19, '13 W T F S S M T Mike Deskin Jun 26, '13 W T F S S M T Jul 3, '13 W T F S S M T Jul 10, '13 W T F S S M T Jul 17, '13 W T F S S M T W H F Perpared for client: Jeff Suchy
  7. 7. Nov 5 Warehouse WBS '13 S S M T May 29, '13 W T F S S M T Jun 5, '13 W T F S S M T Jun 12, '13 W T F S S M T Jun 19, '13 W T F S S M T Mike Deskin Jun 26, '13 W T F S S M T Jul 3, '13 W T F S S M T Jul 10, '13 W T F S S M T Jul 17, '13 W T F S Cement Crew,Plumbers Plumbers Electrician Rough Carpenters Perpared for client: Jeff Suchy S M T W
  8. 8. Nov 5 Warehouse WBS '13 S S M T May 29, '13 W T F S S M T Jun 5, '13 W T F S S M T Jun 12, '13 W T F S S M T Jun 19, '13 W T F S S M T Mike Deskin Jun 26, '13 W T F S S M T Jul 3, '13 W T F S S M T Jul 10, '13 W T F S S Plumbers M T Jul 17, '13 W T F S S M T W Carpet La Perpared for client: Jeff Suchy
  9. 9. Nov 5 Jul 24, '13 W T F Warehouse WBS S S M T Jul 31, '13 W T F S S M T Aug 7, '13 W T F S S M T Aug 14, '13 W T F S S M T Aug 21, '13 W T F S Mike Deskin S M T Aug 28, '13 W T F 8/21 Owner MDesign,Owner Owner Owner Cement Crew,Plumbers Perpared for client: Jeff Suchy S S M T Sep 4, '13 W T F S S M T Sep 11, '13 W T F S S M T Sep 18, '13 W T F S S
  10. 10. Nov 5 Jul 24, '13 W T F Warehouse WBS S S M T Jul 31, '13 W T F S S M T Aug 7, '13 W T F S S M T Aug 14, '13 W T F S S M T Aug 21, '13 W T F S S Electrician Mike Deskin M T Aug 28, '13 W T F S S M T Sep 4, '13 W T F S S M T Sep 11, '13 W T F S S M T Sep 18, '13 W T F S S Rough Carpenters Rough Ca Rough Carpenters Electrician Plumbers Plumbers Cement Crew Cement Crew Labors 1 Perpared for client: Jeff Suchy
  11. 11. Nov 5 Warehouse WBS Jul 24, '13 W T F S S M T Jul 31, '13 W T F S S M T Aug 7, '13 W T F S S M T Aug 14, '13 W T F S S M T Aug 21, '13 W T F S Mike Deskin S Labors 1 8/8 Rough Carpenters Rough Carpenters Rough Carpenters Electrician Perpared for client: Jeff Suchy M T Aug 28, '13 W T F S S M T Sep 4, '13 W T F S S M T Sep 11, '13 W T F S S M T Sep 18, '13 W T F S S
  12. 12. Nov 5 Jul 24, '13 W T F Warehouse WBS S S M T Jul 31, '13 W T F S S M T Aug 7, '13 W T F S S M T Aug 14, '13 W T F S S M T Aug 21, '13 W T F S Mike Deskin S HVAC 7/31 Electrician Electrician Labors 2 Carpet Layers,Tile Layers Labors 1 Rough Carpenters Painters Labors 2 8/5 MDesign,Owner MDesign Owner 8/22 Owner Owner Perpared for client: Jeff Suchy M T Aug 28, '13 W T F S S M T Sep 4, '13 W T F S S M T Sep 11, '13 W T F S S M T Sep 18, '13 W T F S S
  13. 13. Nov 5 S M Warehouse WBS T Sep 25, '13 W T F S S M T Oct 2, '13 W T F S S M T Oct 9, '13 W T F S S M T Oct 16, '13 W T F S S M T Oct 23, '13 W T F Perpared for client: Jeff Suchy Mike Deskin S S M T Oct 30, '13 W T F S S M T Nov 6, '13 W T F S S M T Nov 13, '13 W T F S S M T Nov 20, '1 W T
  14. 14. Nov 5 S M Warehouse WBS T Sep 25, '13 W T F S S M T Oct 2, '13 W T F S S M T Oct 9, '13 W T F S S M T Oct 16, '13 W T F S S M T Oct 23, '13 W T F Labors 1 Rough Carpenters ers Finish Carpenters HVAC 9/23 s1 Finish Carpenters Electrician Electrician Labors 2 Labors 2 Rough Carpenters Carpet Layers Painters Painters Tile Layers Perpared for client: Jeff Suchy Mike Deskin S S M T Oct 30, '13 W T F S S M T Nov 6, '13 W T F S S M T Nov 13, '13 W T F S S M T Nov 20, '1 W T
  15. 15. Nov 5 S M Warehouse WBS T Sep 25, '13 W T F S S M T Oct 2, '13 W T F S S M T Oct 9, '13 W T F S S M T Oct 16, '13 W T F S S Labors 1 M T Mike Deskin Oct 23, '13 W T F S S M T Oct 30, '13 W T F Labors 1 9/24 Labors 1 10/8 9/25 10/23 Owner Labors 1,Labors 2,MDesign Owner Owner Owner MDesign Perpared for client: Jeff Suchy S S M T Nov 6, '13 W T F S S M T Nov 13, '13 W T F S S M T Nov 20, '1 W T
  16. 16. Nov 5 S M Warehouse WBS T Sep 25, '13 W T F S S M T Oct 2, '13 W T F S S M T Oct 9, '13 W T F S S M T Oct 16, '13 W T F S S M T Oct 23, '13 W T F Mike Deskin S S M T Oct 30, '13 W T F 10/29 Perpared for client: Jeff Suchy S S M T Nov 6, '13 W T F S S M T Nov 13, '13 W T F S S M T Nov 20, '1 W T
  17. 17. Nov 5 Nov 20, '13 T F Warehouse WBS S S M T Nov 27, '13 W T F S S M T Dec 4, '13 W T F S S M T Dec 11, '13 W T F S S M T Dec 18, '13 W T F S S Mike Deskin M Perpared for client: Jeff Suchy T Dec 25, '13 W T F S S M T Jan 1, '13 W T F S S M T Jan 8, '13 W T F S S M T Jan 15, '13 W T F S S M
  18. 18. Nov 5 Nov 20, '13 T F Warehouse WBS S S M T Nov 27, '13 W T F S S M T Dec 4, '13 W T F S S M T Dec 11, '13 W T F S S M T Dec 18, '13 W T F S S Mike Deskin M Perpared for client: Jeff Suchy T Dec 25, '13 W T F S S M T Jan 1, '13 W T F S S M T Jan 8, '13 W T F S S M T Jan 15, '13 W T F S S M
  19. 19. Nov 5 Nov 20, '13 T F Warehouse WBS S S M T Nov 27, '13 W T F S S M T Dec 4, '13 W T F S S M T Dec 11, '13 W T F S S M T Dec 18, '13 W T F S S Mike Deskin M Perpared for client: Jeff Suchy T Dec 25, '13 W T F S S M T Jan 1, '13 W T F S S M T Jan 8, '13 W T F S S M T Jan 15, '13 W T F S S M
  20. 20. Nov 5 Nov 20, '13 T F Warehouse WBS S S M T Nov 27, '13 W T F S S M T Dec 4, '13 W T F S S M T Dec 11, '13 W T F S S M T Dec 18, '13 W T F S S Mike Deskin M Perpared for client: Jeff Suchy T Dec 25, '13 W T F S S M T Jan 1, '13 W T F S S M T Jan 8, '13 W T F S S M T Jan 15, '13 W T F S S M

×