2. Outline
•Introduction(Background)
•Current Administration (Transformation)
–Strategies and Actions
–Results and achievements
–Work Photographs
–Video
•Conclusion
Ministerial Briefing, September 2014 2
3. FERMA is committed to a consistent preventive road maintenance culture through intensive surveillance, monitoring and repairs.
Ministerial Briefing, September 2014 3
11. Current Administration
Otherstrategiesexploredforsustainableroadmaintenanceprogrammeinclude:
i.Comprehensivepavementmanagementsystem(PMS)
DeployingFallingWeightDeflectometer(FWD),RoadRoughness, andDynamicConePenetrometerequipmentfordatagatheringtoinformdecisionmakingandcosteffectiveroadmanagement.
ii.AreaManagementContracts
Contractingoutmaintenanceworksonaspecifiedkmofroadtocompetentandequippedcontractorsforafixedtermperiod.
iii.Alternativefunding.
IVTC,RoWbillboards(aswillbeapprovedbyrelevantauthorities), andMOToptionsetc.
Ministerial Briefing, September 2014 11
12. SUMMARY OF CURRENT ROAD MAINTENANCE TRANSFORMATION PROGRAMME:
•Proactive Recovery of Federal roads in bad conditions.
•Acquisition of all in one state of the art BergkampMobile pothole patchers –38 Nos.
•Operational use of 2No 80TPH Asphalt plant –Kuje& Lagos.
•Regular use of over 40No. Mini Asphalt plants.
•Production of Cold Asphalt for all year round maintenance work.
•Blending of Emulsion for regular use at sites.
•Inauguration of the Public Works Programme/SURE P.
•Road Surveillance Unit for proactive maintenance.
•General reorientation and workforce motivation.
•Selective Emergency Intervention Works nationwide.
•Selective Pavement Strengthening (overlay) programme.
•Progressive repairs and replacement of damaged/vandalized hydraulic structures, bridge handrails and road signs. 12
13. S/N
DESCRIPTION
BEFORE
DURING
AFTER
NORTH CENTRAL ZONE
1
SPECIALREPAIRS & PAVEMENT STRENGTHENINGOF SECTIONSOF MOKWA - TEGINA ROAD
2
GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG AKWANGA -KEFFI ROAD IN NASARAWA STATE
3
GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG KATSINA –ALA – TAKUM –KONA BAISSA ROADPHOTOGRAPHS OF SOME EXECUTED ROAD MAINTENANCE PROJECTS
13
14. S/N
DESCRIPTION
BEFORE
DURING
AFTER
NORTH EAST ZONE
1
GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG MAYOBELWA –JADA – GANYE ROAD
2
GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG GOMBE -BILLIRI –FILLIYA ROAD IN GOMBE STATE
3
GENERAL MAINTENANCE REPAIRS & PAVEMENT STRENGTHENING OF SECTIONS ALONG GOMBE - POTISKUM ROAD, SECTION II(KM.80+000 -KM.124+000) IN YOBE STATE 14
PHOTOGRAPHS OF SOME EXECUTED ROAD MAINTENANCE PROJECTS
15. S/N
DESCRIPTION
BEFORE
DURING
AFTER
NORTH WEST ZONE
1
KANO -ZARIA ROAD (KM.0+000 -KM.86+000) SECTION I KANO STATE
2
EMERGENCY REPAIRS OF WASHOUT AT KM.22+000 ALONG BAGUDO -TUGA - KAOJE ROAD IN KEBBI STATE
3
SECTIONS OF KADUNA - BIRNIN GWARI ROAD IN KADUNA STATE
15
PHOTOGRAPHS OF SOME EXECUTED ROAD MAINTENANCE PROJECTS
16. S/N
DESCRIPTION
BEFORE
DURING
AFTER
SOUTH EAST ZONE
1
GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG 9TH MILE – AWKA (OLD ROAD) IN ANAMBRA STATE
2
GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG UMUAHIA – BENDE ROAD
3
GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG YAHE –ABAKALIKI – NKALAGU –ENUGU ROAD 16
PHOTOGRAPHS OF SOME EXECUTED ROAD MAINTENANCE PROJECTS
17. S/N
DESCRIPTION
BEFORE
DURING
AFTER
SOUTH SOUTHZONE
1
GENERAL REPAIRS AND PAVEMENT STRENGTHENING (OVERLAY) OF SECTIONS ALONG OGOJA –OBUDU ROAD
2
GENERAL REPAIRS AND PAVEMENT STRENGTHENING (OVERLAY) OF SECTIONS ALONG AHOADA –ABUA -DEGEMA ROAD
3
GENERAL REPAIRS AND PAVEMENT STRENGHTENING (OVERLAY) OF SECTIONS ALONG AMUKPE-ABRAKA-UMUTU- AGBOR-UROMI ROAD
17
PHOTOGRAPHS OF SOME EXECUTED ROAD MAINTENANCE PROJECTS
18. S/N
DESCRIPTION
BEFORE
DURING
AFTER
SOUTH WEST ZONE
1
GENERAL REPAIRS OF SECTIONS ALONG ITAWURE -ESA OKE JUNCTION OSUN STATE BORDER ROAD IN EKITI STATE
2
OLD ABEOKUTA ROAD IN LAGOS STATE
3
REPAIRS OF IJORA COURSE WAY, LAGOS STATE (FAILED SECTIONS)
18
PHOTOGRAPHS OF SOME EXECUTED ROAD MAINTENANCE PROJECTS
19. NORTH CENTRAL ZONE1. POTHOLE PATCHING ALONG MAKURDI –GBOKO –YANDEV ROAD (CH.0+000 –CH.82+000) IN BENUE STATE
19
20. NORTH CENTRAL ZONE2. GENERAL REPAIRS OF SECTIONS ALONG KABBA –ISANLU –EGBE ROAD (INCLUDING ABU BRIDGE) IN KOGI STATE
20
21. NORTH EAST ZONE1. SPECIAL MAINTENANCE REPAIRS ALONG NGURORE -MAYOBELWA ROAD CH. 18+000 –CH. 44+000 IN ADAMAWA STATE. 21
22. NORTH EAST ZONE 2. EMERGENCY REPAIRS OF GOMBE –NUMAN ROAD (KM. 136 + 400 –KM. 145 + 200) IN GOMBE STATE.
22
23. NORTH WEST ZONE1. SPECIAL GENERAL MAINTENANCE OF SECTIONS OF KAFFIN MAIYAKI –TUDUN WADA – SAMINAKA ROAD IN KANO STATE
23
24. NORTH WEST ZONE 2. EMERGENCY REPAIRS OF EMBANKMENT WASHOUT AT KM.16+200-KM.19+500 AND KM.35+100 ALONG RIJAU-RIBAH-WASAGU ROAD IN KEBBI STATE
24
25. SOUTH EAST ZONE1. GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG OWERRI –OKIGWE ROAD IN IMO STATE
25
26. SOUTH EAST ZONE 2. REPAIRS OF FAILED SECTIONS ALONG OWUTU –AMASIRI –OKPOSI –UBURU ROAD IN EBONYI STATE
26
27. SOUTH SOUTH ZONE
1. EXPANSION OF MBIAMA – YENAGOA ROAD, BAYELSA STATE.
27
28. SOUTH SOUTH ZONE 2. GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG EWU –UROMI –AGBOR ROAD IN EDO STATE
28
29. SOUTH WEST ZONE 1. MAINTENANCE REPAIRS OF FAILED SECTIONS ALONG ILESHA –IJEBU JESA ROAD IN OSUN STATE
29
30. SOUTH WEST ZONE SPECIAL REPAIRS OF CRITICAL SECTIONS ALONG ADO-IKERE-ONDO STATE BORDER ROAD (CH 14+000 -CH 25 + 000) IN EKITI STATE
30
31. (1) Reinstatement of Collapsed 7-Cell Box Culvert at
CH.11+850 & CH.12+850 along Katsina – Kano highway &
provision of 2 bridges & approach roads.
(2) Reinstatement of Embankment washout & collapsed 3-
cell culvert at KM.34+200 along Gombe – Bauchi road,
Gombe state – In progress.
(3) Washout at culvert locations at CH.0+450 along Kaduna
Western Bypass Road – In progress.
(4) Reinstatement of submerged box culvert and
approaches at Ch. 29+500 along Asaba – Ebu – Ilushi
Road, Delta state – In progress.
Photographs in subsequent slides.
31
FERMA EMERGENCY INTERVENTION WORKS ON
ROAD WASHOUTS & BRIDGES
41. REINSTATEMENT OF WASHOUT AND COLLAPSED OF TRIPLE CELL CULVERT AT KM 10+500 (4THINTERCHANGE) ENUGU –PORT HARCOURT DUAL CARRIAGEWAY
41
42. Table Showing Conditions of Federal Roads in 2011 & 2013
Condition
2011(%KM)
2013(%KM)
Good
52%(17,742KM)
Over 75%(25,600KM)
Bad
48%(16,378KM)
25%(8,520KM)
42
43. MOVEMENT OF GAS TURBINE FROM ONNE PORT
TO KADUNA POWER PLANT
43
TAKE OFF POINT FOR THE TURBINE MOVEMENT FROM ONNE PORT, PH TO KADUNA
44. MOVEMENT OF GAS TURBINE FROM ONNE PORT
TO KADUNA POWER PLANT
ARRIVAL OF THE FINAL TRIP AT KADUNA 44
45. FEDERAL ROAD COMMITTEE ON SURVEILLANCE AND ACTION
AGAINST ROAD ABUSE (FERCSARA)
45
In response to an urgent need to address the abuses
and bad behavior exhibited on the road network the
Agency has recently inaugurated a Federal Roads
Committee on Surveillance and Action Against Road
Abuse(FERCSARA). The membership comprises of ;
FERMA Headquaters and Zonal officers,
Federal Ministry of Works(Highways) officers,
Nigerian Army Engineers,
Nigerian Police Force (NPF),
Federal Roads Safety Corps (FRSC),
National Union of Road Transport Workers (NUTRW),
National Security and Civil Defense Corps, and
Local Government works officials
46. FEDERAL ROAD COMMITTEE ON SURVEILLANCE AND ACTION
AGAINST ROAD ABUSE (FERCSARA)
46
The Committee is responsible for;
identifying major abuses and proffering solutions
monitoring occurrences of road abuse and carry out
corrective measures
liaising with law enforcement agencies to ensure the
reinstatement and replacement of damaged carriageway
and road furniture
collaborating with appropriate law enforcement agencies
for the enforcement of relevant extant rules and regulations
on willful damage to government properties in the road
infrastructure sub sector.
liaising with relevant stakeholders to stop further abuses
and ensure sustenance of good road usage by motorists.
cause arrest to be made where necessary.
discourage major haulage companies from deliberate
overloading and indiscriminate parking.
47. FEDERAL ROAD COMMITTEE ON SURVEILLANCE AND ACTION
AGAINST ROAD ABUSE (FERCSARA)
47 REMOVAL OF SHOULDER ENCHROACHMENT IN PROGRESS
55. MOBILE POTHOLE PATCHER IN OPERATION AT THIRD MAINLAND BRIDGE, LAGOSMOBILE POTHOLE PATCHERS AT WORK
MOBILE POTHOLE PATCHER IN OPERATION ALONG ABUJA –KADUNA DUAL CARRIAGEWAY
55
56. MOBILE POTHOLE PATCHERS AT WORK
MOBILE POTHOLE PATCHER IN OPERATION ALONG ABUJA –KEFFI DUAL CARRIAGEWAY
56
57. 80TPH ASPHALT PLANT INSTALLED AT ABUJA, LAGOS, OSOGBO WHILE 4 OTHERS ARE AT VARIOUS STAGES OF INSTALLATIONS 40 MINI ASPHALT PLANT DEPLOYED TO VARIOUS FIELD OFFICES NATIONWIDE
57
58. COLD ASPHALT PRODUCTION Product of FERMA R&D for proactive intervention works6 MONTH OLD COLDASPHALTBAGGED COLD ASPHALTPRIMING & OVERLAY WITH COLD ASPHALTPRIMING & OVERLAY WITH COLD ASPHALTAGGREGATE BLENDING FOR COLD ASPHALT PRODUCTIONCOLD ASPHALT PRODUCTION IN PROGRESS
58
59. OBSERVATION & SERVICE CAMP Built by FERMA to provide emergency services to road users, utilised by the FERMA, Police,& FRSCRECENTLY COMPLETED OBERVATION & SERVICE CAMP ALONG AKURE –ADO EKITI ROAD (KM.7+400) ITAOGBOLU, ONDO STATERECENTLY COMPLETED OBERVATION CAMP AT ODUKPANI, CROSS RIVER STATE
59
60. www.ferma.gov.ng
SOME PICTURES OF OBSERVATION & SERVICE CAMPS CONSTRUCTION
OBSERVATION CAMP AT ELELE, RIVERS STATE OBSERVATION & SERVICE CAMP AT AGO ARE, OYO STATE
OBSERVATION CAMP AT AKWANGA ,NASARAWA STATE OBSERVATION CAMP AT IGBO UKWU, ANAMBRA STATE
60
61. www.ferma.gov.ng
SOME PICTURES OF TRAILER PARKS & FIELD OFFICES CONSTRUCTION
FENCING OF STATE FIELD OFFICE, AWKA, ANAMBRA STATE FENCING OF TRAILER PARK AT AKINYELE, OYO STATE
STATE FIELD OFFICE CONSTRUCTION AT LAFIA COMPLETED STATE FIELD OFFICE AT ZAMFARA
61
63. www.ferma.gov.ng
SOLAR POWERED LIGHTING AT KEFFI
INTERCHANGE, NASARAWA
SOME HIGHWAY/BRIDGE LIGHTING PROJECTS
PROCURED ALTEC L37 M STREETLIGHTS
PLAT FORM IN USE AT JOS
63
64. www.ferma.gov.ng
LIGHTING ON NIGER BRIDGE,
ONITSHA/ASABA
HIGHWAY LIGHTING ALONG KADUNA
WESTERN BYPASS
SOME HIGHWAY/BRIDGE LIGHTING PROJECTS
64
67. OBJECTIVES: PROGRAMME CONCEPT•Prolong the life span of selected roads of high economic impact •Ensure that roads are made safe and motorable all year round•Job creation/Poverty alleviation•Enhance sustainable maintenance culture•Engender community/public ownership and involvement in road works•Improve trust and goodwill between government and the people•Reduce overall huge cost of corrective maintenance contracts
67
69. PROVISION AND INSTALLATION OF HIGH-RESISTANT POLYMER NEW JERSEY CRASH-BARRIERS TO REPLACE VANDALIZED/DAMAGED HANDRAILS AT TAFA BRIDGE ALONG KADUNA-ABUJA DUAL CARRIAGEWAY
69
72. POTHOLE PATCHING USING FP5 BERGKAMP FLAMELESS PATCHER & PAINTING OF PARAPET WALLSAND BRIDGE RAILINGS ON 3RD MAINLAND BRIDGE BY THE SURE P -FERMA PUBLIC WORKS TEAM
72
73. ROAD MARKING ALONG ABUJA – KADUNA DUAL CARRIAGEWAY UNDER
FERMA SURE-P
73
74. SOME OF THE KITS AND BASIC HANDTOOLS FOR PUBLIC WORKS
74
75. 75
SOME ECONOMIC ROUTES MONITORED/MAINTAINED BY FERMAS/NCONSIDERED ROUTESLENGTH (KM)STATES COVERED1Abuja-Kaduna-Dual307.0FCT -Kaduna2Kaduna-Kano -Dual336.0Kaduna-Kano3Benin-Asaba-Dual266.0Edo-Delta4Enugu-9th Mile-Otukpa93.0Enugu-Benue5Shagamu-Ore -Dual98.0Lagos-Ogun-Ondo6Owerri-Onitsha -Dual88.0Imo-Anambra7Jos-Bauchi112.0Plateau-Bauchi8Benin-Bypass-Warri-Dual138.0Edo-Delta9Partsof Benin-Auchi-Okene176.0Edo-Kogi10Parts of Lokoja-Okene100.0FCT-Kogi11Abuja-Keffi-Akwanga -(Abuja-Keffi -Dual)107.0FCT-Nasarawa12Ikot Ekpene-Odukpani-Calabar90.0AkwaIbom-Cross River
76. 76
SOME ECONOMIC ROUTES MONITORED/MAINTAINED BY FERMAS/NCONSIDERED ROUTESLENGTH (KM) STATES COVERED13Ibadan-Ilorin Dual130.0Oyo-Kwara14Primary Roads In Yenegoa35.0Bayelsa15Sokoto-Gusau210.0Zamfara-Sokoto16KatsinaAla-ZakiBiam-Wukari95.0Benue-Taraba17Ajaokuta -Itobe -Ayangba56.0Kogi18Ayangba -Ankpa -Ofu (Benue State Border)94.0Kogi19ApapaOworonshoki-Old Toll Gate32.0Lagos203rd Mailand Bridge11.0Lagos21Lagos-Badagry Seme Border Rroad180.0Lagos22Panyam -Shendam85.0Plateau23Abua-Ahoada-Omoke-Egbema129.0Rivers
78. 78
SELECTEDCOST SAVING PROJECTSS/NPROJECT DESCRIPTIONPROPOSED COST (N) EXECUTED COST (N) SAVINGS (N) 1Emergency Works Kano -Katsina Bridge800M556M244M2Emergency Works Mbiama-Yenegoaroad& BridgeOver 3Billion (S/C) 2.7Billion (D/C) 3.3Billion3Emergency Repairs and pavement strenghteningof sections along OnnePort - Kaduna route project for movement of Gas Turbines to Kaduna Power Plant (Enugu Bound) 4Billion1.7Billion2.3BillionCURRENTEFFORTS & KEY PERFORMANCE EVALUATION 1Length of Road with good ridingquality17,742km (2011)27,320km (2013)77%
79. 79
FERMA FUNDING SUMMARY FOR THE LAST 5 YEARS(2009 –2014) YEARAPPROPRIATION (N)RELEASES (N)SHORT FALL (N) 200943,969,689,656.4243,852,651,223.72-117,038,432.70201062,616,065,053.0051,611,527,557.80-11,004,537,495.20201129,655,265,155.0032,818,510,794.003,163,245,639.00201243,838,424,547.0043,838,404,544.04-20,002.96201339,139,930,827.0027,699,336,797.68-11,440,594,029.32